Академический Документы
Профессиональный Документы
Культура Документы
The goal of the project was to gather integrity data on these pipelines and to evaluate these data to determine the integrity condition of the pipelines and facilities. The pipelines, constructed to API 5L X52 with bitumen wrapping, were designed in the early 1970s. The pipelines were initially installed with 20 inch diameter pipe, but since 1986 some sections have been replaced with 16 inch diameter pipe, due to leakage or other circumstances.
Topographic survey
This measured all topographical items, including landmarks, buildings, streams, rivers, rail tracks, roads, visible crossings of third-party infrastructure, etc., in a 50 m corridor on both sides of the pipeline. The data collected were entered onto alignment sheets and delivered as a database, conforming to the geographical information system (GIS) database structure prescribed by the client, for direct implementation into the GIS.
Terrestrial survey
All structures and landmarks, in corridor of 100 m on both sides of the pipeline, were surveyed to gather reliable data on terrestrial conditions and to mark the pipeline route with a grid of survey reference markers for possible rehabilitation project execution on the pipelines.
LRUT/GWUT
The most suitable positions for LRUT/GWUT were determined, together with the client; these were at locations were the pipeline route changes from above-ground to below-ground. With these
technical
Figure 2: EMAT schematic. Diameter (inches) 20 24 16 16 16 16 14 16 16 16 16 20 20 20 20 20 16 Wall thickness (mm) 8.34 11.9 9.36 9.2 8.39 7.75 12.2 7.75 7.95 7.92 7.92 14.38 9.24 9.8 7.92 7.83 9.35 OK Coating degradation, dent in pipeline, welding anomalies Bad support with corrosion indication Coating degradation and damage, welding anomalies Bad support with corrosion indication Coating degradation and damage Crossing is sagging, welding anomalies Coating degradation and damage, four anomalies detected Coating degradation and damage, two welding anomalies Coating degradation and damage, welding anomalies Bad support with corrosion indication Coating degradation and damage Coating degradation and damage Coating degradation and damage, two remnant welding anomalies, Bow crossing of ditch Coating degradation and damage Coating degradation and damage Coating degradation and damage Coating degradation and damage, four anomalies detected (Class 2, 3), four welding anomalies Coating degradation and damage, four anomalies detected (Class 2, 3), nine welding anomalies
Chainage 144 5054 11628 18081 24417 31418 31681 32315 32794 36144 47534 53144 54231 55726 62100 85213 100026
No. IP3A IP22 IP34 IP36C IP37 IP58 IP60 IP61A IP61B IP73 IP77A IP85 IP88 IP92 IP95C IP120 IP139
Table 1: LRUT and GWUT investigations for the Route 1 pipeline. spot checks, at the most corrosion-sensitive area of the pipelines, it was possible to evaluate the general integrity of the pipeline. The advanced LRUT/GWUT system (Figure 1) is designed for rapid screening of long lengths of pipe to detect corrosion and other forms of axial and circumferential metal degradation. It can be used on a wide variety of pipes including those that are insulated. The tests can be done with the pipeline operational (inservice), so disruption and any expensive down-time are minimised. Hundreds of metres of pipe can be inspected in a single shift and 100 per cent thickness of the pipe wall is inspected during a test. The LRUT/GWUT system uses low-frequency ultrasonic guidedwaves that travel along the full wall thickness of the pipe as a circular type wave front around the pipe circumference. The pulse-echo application means that changes in wall thickness (such as corrosion) along the pipe length will generate signals that return to the transducers. These returning echoes are presented on a simple amplitude versus distance A-scan signal, which the operator can use to discriminate between genuine pipe features (such as welds) and problem areas (such as corrosion wall loss) via the operational software.
technical
Diameter (inches) 8 14 16 16 16 16 16 16 16 16 Wall thickness (mm) 7.89 8.63 7.25 7.16 6.9 10.5 10.8 12.33 7.6 8.63 OK Coating degradation and damage Three leak repairs and coating with severe degradation OK Coating degradation and damage Defects in welding OK Welding defects
No. MS2 MS4 MS6 MS7A MS7B MS14 MS23 MS24 MS47 MS54
Table 2: LRUT and GWUT investigations for the Route 2 pipeline. Chainage 6,375 m 7,648 m 32,489 m 32,792 m 33,664 m 55,569 m 62,725 m 63,425 m 75,231 m 91,747 m Depth (m) 150 130 150 190 60 95 130 150 200 160 Diameter (inches) 20 20 20 20 20 20 20 16 20 20 Spiral Seamless Seamless Bad Poor Good Pipe type Seamless Seamless Seamless Seamless Poor Bad Condition Radius (m) 1.5 1.5 0.6 0.7 Segments 4.6 0.8 0.9 6 6.5 Angle () 159 147 90 110 116 138 112 120 90 140
Table 3: Pipe bends (elbows) and diameter for the Route 1 pipeline. Chainage 3,160 m 3,407 m 3,439 m 8,976 m 9,319 m 18,655 m 22,207 m Depth (m) 120 cm 150 cm 130 cm 130 cm 100 cm 120 cm 120 cm Diameter (inches) 16 16 16 16 16 16 16 Spiral Spiral Corrosion Corrosion Seamless Pipe type Spiral Condition Radius (m) 2.6 3.0 1.5 3.0 7.0 6.4 5.0 Angle () 124 127 148 127 114 140 134
Table 4: Pipe bends (elbows) and diameter for the Route 2 pipeline.
technical
Pipeline depth (cm) Pipe condition Pipe diameter (inches) 20 Bad 20 20 20 20 Bad Poor Poor 20 Bad Poor Poor API 5L X52 Poor Poor Poor Poor API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 Spiral 62,725 m 63,425 m 75,231 m 85,213 m 91,747 m 100,026 m 130 150 200 AG 160 AG Spiral Spiral API 5L X52 API 5L X52 API 5L X52 Bad Bad Seamless Seamless API 5L X52 Poor Poor Poor Bad Bad Poor Poor Good Poor Bad 20 22 20 20 14 14 14 20 20 20 Spiral Spiral 53,144 m 54,231 m 55,569 m 55,726 m AG AG 95 Seamless Spiral Spiral 20 20 20 20 20 20 20 20 20 20 20 20 20 16 Wall thickness min (mm) 7.8 9.5 9.2 12.9 8.18 8.5 8.7 8.7 8.0 3.6 9.4 7.7 7.5 12.2 7.2 7.2 7.5 9.6 7.9 7.0 6.9 13.0 8.6 7.9 7.8 7.0 9.3 9.4 8.3 6.5 9 9.5 Wall thickness max (mm) 8.1 12.5 9.2 13.6 13.8 9.6 8.7 8.7 8.9 7.9 9.8 7.8 7.9 12.9 8.8 8.8 9.8 10.9 8.2 7.2 7.5 15.1 9.2 11.9 9.1 7.9 9.3 10.8 9.3 8.2 9.4 9.5
Pipe type
API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52
24,417 m 2628 km 29,621 m 30,127 m 31,418 m 31,604 m 32,315 m 32,465 m 32,489 m 32,792 m 33,664 m 36,144 m
Spiral Spiral Seamless Seamless Spiral Seamless Spiral Spiral Seamless Seamless
Table 5: Wall thickness measurement for the Route 1 pipeline. Two types of guided wave longitudinal and torsional are used to broaden the range of possible frequencies and to adjust for different situations, for example the presence of liquids. Symmetrical and flexural waves allow defect detection and interpretation of the results. An important point to note is that LRUT/GWUT techniques do not provide a direct measurement of pipe wall thickness, but are sensitive to a combination of the depth and circumferential extent of any metal loss. LRUT/GWUT is not able to distinguish the difference between internal or external material loss. As a redundancy for the LRUT/GWUT we executed nine EMAT measurements on positions where the spiral-welded pipe was giving bad readings via the LRUT/GWUT technology. In this case, the electromagnetic acoustic transducer (EMAT) technology was a hand-held tool which could be moved around the pipe (it was not a collar, like guided wave). The EMAT must be placed on the pipe and it shoots forwards by approximately 1.5 m (Figure 2). The transducer can be moved circumferentially around the pipe and with this movement a 360 coverage with a measuring length of 1.5 m can be achieved.
Excavations
Fifty locations were selected to excavate the pipeline for the bend identification and wall thickness measurements. The diameter changes should have been excavated as well, but because of the method used for pipeline replacement in the past, these were not detectable.
technical
Pipeline depth (cm) AG 90 AG 80 120 150 AG 130 AG 130 100 120 120 120 AG Spiral Spiral Spiral Spiral Spiral Seamless Spiral Spiral 8,976 m 9,319 m 18,655 m 22,207 m 22,227 m 26,757 m Pipe condition Fair Bad Corrosion Corrosion Pipe diameter (inches) 814 16 16 16 16 16 Corrosion Corrosion Corrosion 16 16 16 16 16 16 Corrosion Corrosion Corrosion Corrosion 16 16 16 16 Wall thickness min (mm) 7.7 8.2 6.9 7.0 10.0 6.3 7.2 10.9 11.3 11.5 6.3 9.9 10.0 9.3 7.5 7.6 Wall thickness max (mm) 8.0 8.9 7.3 7.3 10.8 6.8 10.8 11.8 12.8 13.5 6.8 10.6 10.0 10.1 7.6 8.8
Grade API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52 API 5L X52
Table 6: Wall thickness measurement for the Route 2 pipeline. Design pressure classes Pipe diameter (inches) 16 20 ANSI 400 400 ISO (bar) 64 64 Wall thickness (mm) 12.5 14.2 Alternative wall thickness (mm) (client approval needed) 8.8 10
Grade
L360 NB L360 NB
Table 7: Clients technical specification for wall thickness. According to the information received from the client, the bypasses should have been constructed in parallel positions to the old pipeline, and connected with elbows to the original line. It was later discovered that this was not the way these bypasses had been constructed. After a second detection survey, in which these connections were still undetectable, the client mobilised its field inspectors and the construction company who carried out the bypass construction to indicate the positions in the field. During this identification survey we were informed about the changed construction method for the bypass connections: over a length of 50100 m the new pipeline was positioned in the original route of the old pipeline and connected without the elbows as indicated during the project scope. Due to some landowner issues and high water conditions, there were some locations which could not be accessed, and at which excavations were therefore cancelled by the clients project management and ILF. At the other excavations, the pipeline diameter and wall thickness were measured and a general inspection of the coating was performed. angle, wall thickness, position, depth, and coating condition were selected. Table 3 shows the data from these investigations. According to EN 1594, field bends for pipelines greater than 16 inches in diameter shall have at least 40 times the diameter: this is a radius of 16 m for 16 inches, and 20.3 m for 20 inch pipes. Factory bends can have smaller radii. In general bends, made of segments (mitred, or cut elbows) are not permitted according to EN 14161. While only performing visual inspection on the investigated bends, it was not possible to identify if the bends were mitred or factory bends.
Wall thickness
According to EN 1594 the minimum required wall thickness is calculated with following equation:
Bends (elbows)
In agreement with the client, the locations of short-radius bends and elbows which were excavated during the pipeline-detection survey to investigate the bend type, radius, change of direction
where: DP = design pressure (bar) DOD = outside diameter (mm) fo = utilisation factor according to EN 1594 Rt0.5 = yield strength according to API 5L (N/mm) This equation does not consider any supplemental wall thickness, such as might be used for corrosion. Also, the equation
technical
of 360 N/mm, this leads to a minimum wall thickness of 3 mm for the 16 inch pipeline, and one of 3.9 mm for the 20 inch pipeline. For the Route 2 pipeline with an original operating pressure of 42 bar, a wall thickness of 3.6 mm is the absolute minimum required. To these values a safety design factor of 2 mm and a corrosion allowance of 3 mm is to be added, giving the following results: Route 1: wall thickness >8 mm for the 16 inch and 8.9 mm for the 20 inch pipelines Route 2: wall thickness >8.6 mm for the 16 inch pipeline. According to the clients technical specification, based on the local standard for wall thickness calculations, the specifications in Table 7 are given, included the prescribed 2 mm safety design factor and the 3 mm corrosion allowance. All wall thicknesses below the minimum prescribed values are marked in red in Tables 5 and 6.
Material
The information received from the client stated that there is only API 5L X52 and L360 linepipe material used for these pipelines. According to API 5L, the API 5L X52 and the L360 linepipe materials are equal. The minimum yield strength (Rt0.5) is 360N/ mm and the chemical composition for X52 gives maximum contents (mass fraction) of 0.26 per cent carbon, 1.4 per cent of manganese, and 0.03 per cent of phosphorous and sulphur for welded pipes (in non-sour service).
Figure 3: Examples of poor welding. is only a rule of thumb and is valid for straight pipe (not for bends). For the Route 1 pipeline with its original operating pressure of 36 bar, an fo of 0.72 (which is the reciprocal safety factor), and Rt0.5 Chainage value 3411 6318 5054 5054 11628 11628 11628 31604 32315 53144 85213 85213 No. MS14 MS23 IP22 IP22 IP34 w1 IP34 w2 IP34 w3 IP60 IP61 IP85 IP120 w1 IP120 w2
Measured 1 (joint) on 14 inch 1 (joint) on 16 inch 1 (joint) on 24 inch 1 (ws) on 20 inch 1 (joint) on 16 inch 1 (joint) on 16 inch 1 (joint) on 16 inch 1 (joint) on 14 inch 1 (joint) on 16 inch 1 (joint) on 20 inch 1 (joint) on 20 inch 1 (joint) on 20 inch
10
technical
penetration and/or incomplete fusion, and nine of the 12 investigated joints were therefore rejected. Figure 3 ab and Table 8 give further details.
Visual inspection
For all above-ground installations, excavations, and UT investigation sites, a visual inspection was carried out which included identification of the pipe type (spiral or longitudinally welded), the identification of bends, and the measurement of diameter and wall thickness. Also the general state of the coating was evaluated and recorded. For above-ground installations such as flanges and valves, the general state, presence of all bolts and nuts, and the corrosion condition, were recorded. The presence of handwheels for the valves were also checked. Along the pipeline route there are many roads crossings, some of which have ventilation pipes which indicate an installed casing. On the locations where there were no ventilation pipes observed, especially on the national roads and highways, it was assumed that, according to the old standard that was in place during the construction of the original pipeline, the ventilation pipes were corroded, had disappeared or been stolen for scrap metal collection. Data on all road crossings was obtained, regardless of road type minor, secondary, national, or highway. Some casings made of old oil barrels under a minor road were detected, as well as some concrete pipes as a kind of casing under a secondary road. It was assumed that many of these crossings had not been constructed in conformity with the old standard, and certainly they were not in accordance with new standards and practices. At some water crossings the pipe could be seen lying directly in the watercourse. According to European norms, the rule for thumb for water crossings is to cross at least 0.8 m below the deepest point of the water course.
Leakages
During the pipeline detection survey leakages were detected which were immediately reported to the client. The client had recorded all leakages on the pipelines in the previous two years: the total number of reported/recorded leakages in 2008 was 28. The repair methods were neither in accordance to the quality control and safety standards of the client nor to internationally accepted standards (Fig.4 a-c). Most repairs were observed as being executed by simple steel screwed-on clamps, without
11
technical
Figure 5: Concrete blocks used at a river crossing. even removing and reinstalling the coating. Some severe damage caused by excavation works for leakage repair was also observed on the pipeline.
Buoyancy protection
In areas where the soil contains a lot of water (moor or marsh), and also for larger river crossings, buoyancy protection for the pipeline is required and is mandatory. According to the European standard EN 1594, the pipe should be ballasted or anchored, if necessary, in areas where the pipe tends to float or because of the high groundwater table. It was seen that some kind of buoyancy protection for the pipelines had been used in a few locations, although this was neither according to European standards nor sufficient. At a few locations the bare pipe was seen lying directly in the water, covered by some concrete blocks (Figure 5).
Figure 6: Concrete block laying on the pipe. This meant that there should be rehabilitated 101 km of new 16 inch pipeline would be installed. The rehabilitation sequence/steps and detailed explanation are discussed later.
12
technical
Figure 8: Pipe bent due to ground movement. influences (such as landslides). This was environmentally unjustifiable and public safety, as well as the safety of the clients personnel, was in jeopardy. Corporate reputation was also at stake; when a serious incident occurs, it is realistic to assume that the pipelines present integrity status will be examined and published by the public media. As mentioned already, there had been 28 leakages detected and reported in the last two years.
Crossings
All pipeline crossings should be made by directional drilling, horizontal directional drilling, or prefabricated siphons; if this is not possible, existing crossings should be rehabilitated to be of a safe and reliable construction (Figure 8).
13
technical
14
technical
Procedures are to be set up concerning what is to be inspected, what is be to reported, how the reports are to be made, and to whom the reports are to be given. A schedule for ILI to observe the feature degradation and to plan maintenance.
Maintenance programme
In the course of time, several maintenance strategies were developed with their own advantages and disadvantages. The three major existing categories of maintenance are: Corrective maintenance (CM) Preventive maintenance (PM) Risk-based maintenance (RBM).
Close interval potential survey measurements Cleaning/drying liquids in the pipeline (semi-routine) by pigging or drain systems. An extension of preventive maintenance is condition-based maintenance, which has to be developed for each individual pipeline system on the basis of the experience during the first years of operation, followed by continuous improvement based on actual experience (the Deming circle).
Risk-based maintenance
In risk-based maintenance, the system and its components are evaluated in terms of their probability of failure and the risks involved (Figure 10). The results are visualised in a risk matrix. With the focus on the relevant system components for the operation, the integrity of the whole system is improved. Highly qualified staff are required to undertake this analysis. In central Europe, it is recommended that condition-based maintenance is regularly undertaken to achieve a high reliability of the individual components and thus for the whole system.
Corrective maintenance
The CM strategy is independent of time or condition of the system, and the work consists only of repairing defective equipment. Thus, the unscheduled and unpredictable work leads to relatively low costs. High expenditures could arise, however, when the whole system has to be shut down because of the repairs.
Preventive maintenance
PM contains all the work/interventions performed periodically on critical units according to specified instructions, or vendor maintenance manuals, recommendations, and procedures. Examples of PM are: Greasing the valves Function testing line valves Emission testing valve seals and compressor/pump seals Intelligent pig runs DCVG coating investigation
15