Day 1 AM: Tasks to do

28/10/13 Complete d?

10:00 - walk around & visit location where possible digital photography could be done morning photography where light is needed (page 1) 11:00 - Audition models to prepare for the upcoming photographs Red, Wolf, Jack & Grandma. This will allow me to purchase the costumes needed

12:00 - Measurements taken of the 4 models

Day 1 PM: Tasks to do 13:00 - Make my way into town with measurements/ models to purchase costumes needed. Costumes needed specified on equipment document.

Complet ed?

16:00 Fitting of the costumes (if costumes do not fit I will be pushed back a day)

17:00 Finished for the day

Day 2 AM: Tasks to do

29/10/13 Complete d?

10:00 Morning test shots with the models for Red & Jack.

10:30 First shoot with Red & Jack (page 1 of graphic novel)

12:00 Viewing of the photos produced to check Ive produced what I need

Day 2 PM: Tasks to do

Complet ed?

13:00 - Second shoot with Red & Jack (page 1 of graphic novel)

14:00 Viewing of photos produced to check Ive produced what I need 18:00 Walk around & visit locations where possible digital photography could be done night photography where shadows are needed (pages 2 & 3)

19:00 - Finished for the day Day 3 AM: Tasks to do 30/10/13 Complete d?

AM IF IMAGES HAVE NOT BEEN PRODUCED FOR PAGE 1 THIS MORNING WILL BE USED

10:00 Location scouting for Grandmas House (pages 4 & 5)

Day 3 PM: Tasks to do

Complet ed?

15:00 Test shots for Grandmas house scene (page 4 & 5)

18:00 Test shots for pages two & three with Red & Wolf

19:00 First shoot with Red & Wolf (pages two & three)

21:00 Check Ive produced what I need Day 4 AM: Tasks to do 31/10/13 Complete d?

Day 4 PM: Tasks to do

Complet ed?

16:00 First photo shoot with Red, Grandma, Jack, Wolf (page 4 & 5)

19:00 Checking of photographs

21:00 done for the day

Day 5 AM: Tasks to do

01/11/13 Complete d?

Day 5 PM: Tasks to do

Complet ed?

19:30 - second shoot with Red & Wolf (pages two & three)

21:00 checking of photographs

Day 6 AM: Tasks to do

02/11/13 Complete d?

Day 6 PM: Tasks to do

Complet

ed?

16:00 Second photo shoot with Red, Grandma, Jack, Wolf (page 4 & 5)

18:00 checking of photographs

Day 7 AM: Tasks to do

03/11/13 Complete d?

General checking of photographs & anything else needed before production of m actual product THIS WILL BE USED FOR PHOTOGRAPHS I HAVE NOT PRODUCED/HAVE NOT COME OUT TO A HIGH STANDARD

Please note: Timing in general can move around, especially once you are depending on other people. Timing may vary depending on when models are available, weather conditions & location availability.