Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES

OE:1076764070

ObjectID: 100-FW-5302-SL-A18 System: 53 - FIXED FIREWATER SYSTEM Package: 53A02 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0023 TestMedium: Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM 100-FW-5301-A18 to FIRE WATER Description: RING WELLHEAD AREA Sub System: 53A - FIREWATER DISTRIBUTION Area: Flushing Medium: Completed by Verified by Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924).

BDEWC QA/QC

BDEWC Commission

1/423

OE:1076764070

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1076786854

ObjectID: 100-FW-5302-SL-A18 System: 53 - FIXED FIREWATER SYSTEM Package: 53A02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM 100-FW-5301-A18 to FIRE WATER Description: RING WELLHEAD AREA Sub System: 53A - FIREWATER DISTRIBUTION Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

2/423

OE:1076786854

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1345210023

ObjectID: 100-FW-5302-SL-A18 System: 53 - FIXED FIREWATER SYSTEM Package: 53A02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM 100-FW-5301-A18 to FIRE WATER Description: RING WELLHEAD AREA Sub System: 53A - FIREWATER DISTRIBUTION Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

3/423

OE:1345210023

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:208686117

ObjectID: 150-DN-6547-SL-A18 System: 65 - OPEN DRAIN Package: 65C02 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0016 TestMedium: Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM NON-HAZARDOUS OPEN DRAIN Description: HEADER to OHD CAISSON (T-6510) Sub System: 65C - NON-HAZARDOUS OPEN DRAINS HEADER Area: Flushing Medium: Completed by Verified by Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924).

BDEWC QA/QC

BDEWC Commission

4/423

OE:208686117

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:208676645

ObjectID: 150-DN-6547-SL-A18 System: 65 - OPEN DRAIN Package: 65C02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM NON-HAZARDOUS OPEN DRAIN Description: HEADER to OHD CAISSON (T-6510) Sub System: 65C - NON-HAZARDOUS OPEN DRAINS HEADER Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

5/423

OE:208676645

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:477108004

ObjectID: 150-DN-6547-SL-A18 System: 65 - OPEN DRAIN Package: 65C02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM NON-HAZARDOUS OPEN DRAIN Description: HEADER to OHD CAISSON (T-6510) Sub System: 65C - NON-HAZARDOUS OPEN DRAINS HEADER Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

6/423

OE:477108004

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:913119723

ObjectID: 150-PG-0101-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01B03 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM CHOKE VALVE HCV-0111 to 150-PGDescription: 0151-GIY Sub System: 01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINE Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924).

BDEWC QA/QC

BDEWC Commission

7/423

OE:913119723

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:913142507

ObjectID: 150-PG-0101-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01B03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM CHOKE VALVE HCV-0111 to 150-PGDescription: 0151-GIY Sub System: 01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINE Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

8/423

OE:913142507

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:644694762

ObjectID: 150-PG-0101-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01B03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM CHOKE VALVE HCV-0111 to 150-PGDescription: 0151-GIY Sub System: 01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINE Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

9/423

OE:644694762

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:927799787

ObjectID: 150-PG-0102-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01C03 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM CHOKE VALVE HCV-0121 to 150-PGDescription: 0152-GIY Sub System: 01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINE Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924).

BDEWC QA/QC

BDEWC Commission

10/42

OE:927799787

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:927822571

ObjectID: 150-PG-0102-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01C03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM CHOKE VALVE HCV-0121 to 150-PGDescription: 0152-GIY Sub System: 01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINE Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

11/42

OE:927822571

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:659374826

ObjectID: 150-PG-0102-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01C03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM CHOKE VALVE HCV-0121 to 150-PGDescription: 0152-GIY Sub System: 01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINE Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

12/42

OE:659374826

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:807213547

ObjectID: 150-PG-0103-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01D03 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM CHOKE VALVE HCV-0131 to 150-PGDescription: 0153-GIY Sub System: 01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINE Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924).

BDEWC QA/QC

BDEWC Commission

13/42

OE:807213547

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:807236331

ObjectID: 150-PG-0103-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01D03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM CHOKE VALVE HCV-0131 to 150-PGDescription: 0153-GIY Sub System: 01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINE Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

14/42

OE:807236331

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:538788586

ObjectID: 150-PG-0103-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01D03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM CHOKE VALVE HCV-0131 to 150-PGDescription: 0153-GIY Sub System: 01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINE Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

15/42

OE:538788586

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:838670827

ObjectID: 150-PG-0104-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01E03 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM CHOKE VALVE HCV-0141 to 150-PGDescription: 0154-GIY Sub System: 01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINE Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924).

BDEWC QA/QC

BDEWC Commission

16/42

OE:838670827

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:838693611

ObjectID: 150-PG-0104-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01E03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM CHOKE VALVE HCV-0141 to 150-PGDescription: 0154-GIY Sub System: 01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINE Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

17/42

OE:838693611

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:570245866

ObjectID: 150-PG-0104-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01E03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM CHOKE VALVE HCV-0141 to 150-PGDescription: 0154-GIY Sub System: 01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINE Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

18/42

OE:570245866

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:853350891

ObjectID: 150-PG-0105-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01F03 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM CHOKE VALVE HCV-0151 to 150-PGDescription: 0155-GIY Sub System: 01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINE Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924).

BDEWC QA/QC

BDEWC Commission

19/42

OE:853350891

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:853373675

ObjectID: 150-PG-0105-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01F03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM CHOKE VALVE HCV-0151 to 150-PGDescription: 0155-GIY Sub System: 01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINE Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

20/42

OE:853373675

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:584925930

ObjectID: 150-PG-0105-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01F03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM CHOKE VALVE HCV-0151 to 150-PGDescription: 0155-GIY Sub System: 01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINE Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

21/42

OE:584925930

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:866982379

ObjectID: 150-PG-0106-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01G03 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM CHOKE VALVE HCV-0161 to 150-PGDescription: 0156-GIY Sub System: 01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINE Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924).

BDEWC QA/QC

BDEWC Commission

22/42

OE:866982379

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:867005163

ObjectID: 150-PG-0106-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01G03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM CHOKE VALVE HCV-0161 to 150-PGDescription: 0156-GIY Sub System: 01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINE Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

23/42

OE:867005163

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:598557418

ObjectID: 150-PG-0106-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01G03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM CHOKE VALVE HCV-0161 to 150-PGDescription: 0156-GIY Sub System: 01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINE Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

24/42

OE:598557418

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1031608811

ObjectID: 150-PG-0107-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01H03 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM CHOKE VALVE HCV-0171 to 150-PGDescription: 0157-GIY Sub System: 01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINE Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924).

BDEWC QA/QC

BDEWC Commission

25/42

OE:1031608811

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1031631595

ObjectID: 150-PG-0107-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01H03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM CHOKE VALVE HCV-0171 to 150-PGDescription: 0157-GIY Sub System: 01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINE Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

26/42

OE:1031631595

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:763183850

ObjectID: 150-PG-0107-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01H03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM CHOKE VALVE HCV-0171 to 150-PGDescription: 0157-GIY Sub System: 01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINE Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

27/42

OE:763183850

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1046288875

ObjectID: 150-PG-0108-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01I03 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM CHOKE VALVE HCV-0181 to 150-PGDescription: 0158-GIY Sub System: 01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINE Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924).

BDEWC QA/QC

BDEWC Commission

28/42

OE:1046288875

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1046311659

ObjectID: 150-PG-0108-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01I03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM CHOKE VALVE HCV-0181 to 150-PGDescription: 0158-GIY Sub System: 01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINE Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

29/42

OE:1046311659

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:777863914

ObjectID: 150-PG-0108-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01I03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM CHOKE VALVE HCV-0181 to 150-PGDescription: 0158-GIY Sub System: 01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINE Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

30/42

OE:777863914

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1060968939

ObjectID: 150-PG-0109-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01J03 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM CHOKE VALVE HCV-0191 to 150-PGDescription: 0159-GIY Sub System: 01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINE Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28924).

BDEWC QA/QC

BDEWC Commission

31/42

OE:1060968939

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1060991723

ObjectID: 150-PG-0109-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01J03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM CHOKE VALVE HCV-0191 to 150-PGDescription: 0159-GIY Sub System: 01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINE Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

32/42

OE:1060991723

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:792543978

ObjectID: 150-PG-0109-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01J03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM CHOKE VALVE HCV-0191 to 150-PGDescription: 0159-GIY Sub System: 01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINE Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:07, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

33/42

OE:792543978

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:877463787

ObjectID: 150-PG-0110-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01K03 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM CHOKE VALVE HCV-0201 to 150-PGDescription: 0160-GIY Sub System: 01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINE Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

34/42

OE:877463787

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:877487083

ObjectID: 150-PG-0110-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01K03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM CHOKE VALVE HCV-0201 to 150-PGDescription: 0160-GIY Sub System: 01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINE Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

35/42

OE:877487083

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:609047530

ObjectID: 150-PG-0110-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01K03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM CHOKE VALVE HCV-0201 to 150-PGDescription: 0160-GIY Sub System: 01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINE Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

36/42

OE:609047530

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:913115371

ObjectID: 150-PG-0111-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01L03 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM CHOKE VALVE HCV-0211 to 150-PGDescription: 0145-GIY Sub System: 01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINE Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

37/42

OE:913115371

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:913138667

ObjectID: 150-PG-0111-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01L03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM CHOKE VALVE HCV-0211 to 150-PGDescription: 0145-GIY Sub System: 01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINE Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

38/42

OE:913138667

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:644699114

ObjectID: 150-PG-0111-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01L03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM CHOKE VALVE HCV-0211 to 150-PGDescription: 0145-GIY Sub System: 01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINE Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

39/42

OE:644699114

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:927795435

ObjectID: 150-PG-0112-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01M03 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM CHOKE VALVE HCV-0221 to 150-PGDescription: 0146-GIY Sub System: Area: Flushing Medium: 01M - WELLHEAD WH-0220 (SLOT 12) & FLOWLINE

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

40/42

OE:927795435

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:927818731

ObjectID: 150-PG-0112-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01M03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM CHOKE VALVE HCV-0221 to 150-PGDescription: 0146-GIY Sub System: Area: 01M - WELLHEAD WH-0220 (SLOT 12) & FLOWLINE

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

41/42

OE:927818731

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:659379178

ObjectID: 150-PG-0112-SL-G1Y System: 01 - WELLHEADS & FLOWLINES Package: 01M03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM CHOKE VALVE HCV-0221 to 150-PGDescription: 0146-GIY Sub System: Area: 01M - WELLHEAD WH-0220 (SLOT 12) & FLOWLINE

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

42/42

OE:659379178

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1031108017

ObjectID: 100-PW-4203-SL-B1Y System: 42 - PRODUCED WATER TREATMENT Package: 42A03 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0012 TestMedium: Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM PRODUCED WATER SYSTEM (ADescription: 4200) to OHD CAISSON (T-6510) Sub System: 42A - A-4200 PRODUCED WATER Area: Flushing Medium: Completed by Verified by Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

43/42

OE:1031108017

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1031085745

ObjectID: 100-PW-4203-SL-B1Y System: 42 - PRODUCED WATER TREATMENT Package: 42A03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM PRODUCED WATER SYSTEM (ADescription: 4200) to OHD CAISSON (T-6510) Sub System: 42A - A-4200 PRODUCED WATER Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

44/42

OE:1031085745

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:762654384

ObjectID: 100-PW-4203-SL-B1Y System: 42 - PRODUCED WATER TREATMENT Package: 42A03 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM PRODUCED WATER SYSTEM (ADescription: 4200) to OHD CAISSON (T-6510) Sub System: 42A - A-4200 PRODUCED WATER Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

45/42

OE:762654384

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1896898980

ObjectID: 150-DH-6503-SL-A18 System: 65 - OPEN DRAIN Package: 65B02 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0016 TestMedium: Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM HAZ'DOUS OPEN DRAIN HEADER Description: (MAIN DECK) to OHD CAISSON (T-6510) Sub System: 65B - HAZARDOUS OPEN DRAINS HEADER Area: Flushing Medium: Completed by Verified by Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

46/42

OE:1896898980

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1896876708

ObjectID: 150-DH-6503-SL-A18 System: 65 - OPEN DRAIN Package: 65B02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM HAZ'DOUS OPEN DRAIN HEADER Description: (MAIN DECK) to OHD CAISSON (T-6510) Sub System: 65B - HAZARDOUS OPEN DRAINS HEADER Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

47/42

OE:1896876708

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1628453541

ObjectID: 150-DH-6503-SL-A18 System: 65 - OPEN DRAIN Package: 65B02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM HAZ'DOUS OPEN DRAIN HEADER Description: (MAIN DECK) to OHD CAISSON (T-6510) Sub System: 65B - HAZARDOUS OPEN DRAINS HEADER Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

48/42

OE:1628453541

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1268396634

ObjectID: 200-PL-3306-SL-C8Y System: 33 - CONDENSATE IMPORT/EXPORT Package: 33A02 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0013 TestMedium: Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM COND. PIG RECEIVER (L-3310) to Description: PLEM VIA SUBSEA PIPELINE Sub System: 33A - CONDENSATE EXPORT Area: Flushing Medium: Completed by Verified by Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

49/42

OE:-1268396634

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1268406618

ObjectID: 200-PL-3306-SL-C8Y System: 33 - CONDENSATE IMPORT/EXPORT Package: 33A02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM COND. PIG RECEIVER (L-3310) to Description: PLEM VIA SUBSEA PIPELINE Sub System: 33A - CONDENSATE EXPORT Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

50/42

OE:-1268406618

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1536846169

ObjectID: 200-PL-3306-SL-C8Y System: 33 - CONDENSATE IMPORT/EXPORT Package: 33A02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM COND. PIG RECEIVER (L-3310) to Description: PLEM VIA SUBSEA PIPELINE Sub System: 33A - CONDENSATE EXPORT Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

51/42

OE:-1536846169

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:2091123198

ObjectID: 500-PG-2921-SL-C8Y System: 29 - GAS IMPORT/EXPORT Package: 29A02 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0014 TestMedium: Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM GAS PIG LAUNCHER (L-2920) to Description: MEPA / GORA PIPELINE BOUNDARY Sub System: 29A - GAS EXPORT Area: Flushing Medium: Completed by Verified by Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

52/42

OE:2091123198

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:2091150078

ObjectID: 500-PG-2921-SL-C8Y System: 29 - GAS IMPORT/EXPORT Package: 29A02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM GAS PIG LAUNCHER (L-2920) to Description: MEPA / GORA PIPELINE BOUNDARY Sub System: 29A - GAS EXPORT Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

53/42

OE:2091150078

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1822710527

ObjectID: 500-PG-2921-SL-C8Y System: 29 - GAS IMPORT/EXPORT Package: 29A02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM GAS PIG LAUNCHER (L-2920) to Description: MEPA / GORA PIPELINE BOUNDARY Sub System: 29A - GAS EXPORT Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

54/42

OE:1822710527

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:609277634

ObjectID: 50-B-6201-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D14 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM WELLHEAD WH-0110 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

55/42

OE:609277634

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:609271234

ObjectID: 50-B-6201-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D14 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM WELLHEAD WH-0110 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

56/42

OE:609271234

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:877694403

ObjectID: 50-B-6201-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D14 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM WELLHEAD WH-0110 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

57/42

OE:877694403

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:628152002

ObjectID: 50-B-6202-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D15 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM WELLHEAD WH-0120 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

58/42

OE:628152002

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:628145602

ObjectID: 50-B-6202-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D15 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM WELLHEAD WH-0120 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

59/42

OE:628145602

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:896568771

ObjectID: 50-B-6202-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D15 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM WELLHEAD WH-0120 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

60/42

OE:896568771

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:572577474

ObjectID: 50-B-6203-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D16 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM WELLHEAD WH-0130 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

61/42

OE:572577474

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:572571074

ObjectID: 50-B-6203-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D16 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM WELLHEAD WH-0130 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

62/42

OE:572571074

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:840994243

ObjectID: 50-B-6203-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D16 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM WELLHEAD WH-0130 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

63/42

OE:840994243

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:599840450

ObjectID: 50-B-6204-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D17 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM WELLHEAD WH-0140 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

64/42

OE:599840450

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:599834050

ObjectID: 50-B-6204-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D17 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM WELLHEAD WH-0140 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

65/42

OE:599834050

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:868257219

ObjectID: 50-B-6204-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D17 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM WELLHEAD WH-0140 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

66/42

OE:868257219

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:551605954

ObjectID: 50-B-6205-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D18 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM WELLHEAD WH-0150 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

67/42

OE:551605954

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:551599554

ObjectID: 50-B-6205-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D18 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM WELLHEAD WH-0150 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

68/42

OE:551599554

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:820022723

ObjectID: 50-B-6205-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D18 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM WELLHEAD WH-0150 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

69/42

OE:820022723

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:628148162

ObjectID: 50-B-6212-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D01 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0003 TestMedium: Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM CASING BLOWDOWN HEADER to 50Description: B-6213-B1Y Sub System: 62D - CASING BLOWDOWN Area: Flushing Medium: Completed by Verified by Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

70/42

OE:628148162

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:628141250

ObjectID: 50-B-6212-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D01 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM CASING BLOWDOWN HEADER to 50Description: B-6213-B1Y Sub System: 62D - CASING BLOWDOWN Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

71/42

OE:628141250

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:896572611

ObjectID: 50-B-6212-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D01 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM CASING BLOWDOWN HEADER to 50Description: B-6213-B1Y Sub System: 62D - CASING BLOWDOWN Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

72/42

OE:896572611

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:563140290

ObjectID: 50-B-6206-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D19 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM WELLHEAD WH-0160 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

73/42

OE:563140290

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:563133890

ObjectID: 50-B-6206-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D19 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM WELLHEAD WH-0160 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

74/42

OE:563133890

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:831557059

ObjectID: 50-B-6206-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D19 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM WELLHEAD WH-0160 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

75/42

OE:831557059

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:792778434

ObjectID: 50-B-6207-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D20 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM WELLHEAD WH-0170 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

76/42

OE:792778434

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:792772034

ObjectID: 50-B-6207-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D20 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM WELLHEAD WH-0170 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

77/42

OE:792772034

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1061195203

ObjectID: 50-B-6207-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D20 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM WELLHEAD WH-0170 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

78/42

OE:1061195203

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:744543938

ObjectID: 50-B-6208-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D21 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM WELLHEAD WH-0180 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

79/42

OE:744543938

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:744537538

ObjectID: 50-B-6208-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D21 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM WELLHEAD WH-0180 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

80/42

OE:744537538

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1012960707

ObjectID: 50-B-6208-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D21 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM WELLHEAD WH-0180 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

81/42

OE:1012960707

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:755029698

ObjectID: 50-B-6209-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D22 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM WELLHEAD WH-0190 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

82/42

OE:755029698

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:755023298

ObjectID: 50-B-6209-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D22 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM WELLHEAD WH-0190 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

83/42

OE:755023298

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1023446467

ObjectID: 50-B-6209-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D22 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM WELLHEAD WH-0190 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

84/42

OE:1023446467

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:644925378

ObjectID: 50-B-6210-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D23 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM WELLHEAD WH-0200 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

85/42

OE:644925378

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:644918466

ObjectID: 50-B-6210-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D23 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM WELLHEAD WH-0200 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

86/42

OE:644918466

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:913349827

ObjectID: 50-B-6210-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D23 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM WELLHEAD WH-0200 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

87/42

OE:913349827

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:572582338

ObjectID: 50-B-6263-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D24 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM WELLHEAD WH-0210 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

88/42

OE:572582338

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:572555970

ObjectID: 50-B-6263-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D24 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM WELLHEAD WH-0210 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

89/42

OE:572555970

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:841003715

ObjectID: 50-B-6263-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D24 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM WELLHEAD WH-0210 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

90/42

OE:841003715

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:599845314

ObjectID: 50-B-6264-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D25 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0001 TestMedium: -1 Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM WELLHEAD WH-0220 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area: Flushing Medium:

Completed by

Verified by

Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

91/42

OE:599845314

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:599818946

ObjectID: 50-B-6264-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D25 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM WELLHEAD WH-0220 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

92/42

OE:599818946

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:868266691

ObjectID: 50-B-6264-SL-G1Y System: 62 - HP FLARE SYSTEM Package: 62D25 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM WELLHEAD WH-0220 CASING to 50-B Description: -6211-G1Y Sub System: 62D - CASING BLOWDOWN Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

93/42

OE:868266691

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-76968732

ObjectID: 50-DC-6541-SL-B1Y System: 65 - OPEN DRAIN Package: 65A02 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0021 TestMedium: Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM OHD CAISSON (T-6510) to OHD Description: CAISSON PUMP (P-6520)(OFFSHORE) Sub System: 65A - T-6510 OPEN DRAINS CAISSON & PUMP Area: Flushing Medium: Completed by Verified by Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

94/42

OE:-76968732

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:996773118

ObjectID: 50-DC-6541-SL-B1Y System: 65 - OPEN DRAIN Package: 65A02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM OHD CAISSON (T-6510) to OHD Description: CAISSON PUMP (P-6520)(OFFSHORE) Sub System: 65A - T-6510 OPEN DRAINS CAISSON & PUMP Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

95/42

OE:996773118

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:996216050

ObjectID: 50-DC-6541-SL-B1Y System: 65 - OPEN DRAIN Package: 65A02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM OHD CAISSON (T-6510) to OHD Description: CAISSON PUMP (P-6520)(OFFSHORE) Sub System: 65A - T-6510 OPEN DRAINS CAISSON & PUMP Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

96/42

OE:996216050

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1745386267

ObjectID: 50-DH-6508-SL-A18 System: 65 - OPEN DRAIN Package: 65B02 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0021 TestMedium: Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM OHD CAISON PUMP (P-6520) to 150Description: DH-6503-A18 Sub System: 65B - HAZARDOUS OPEN DRAINS HEADER Area: Flushing Medium: Completed by Verified by Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

97/42

OE:-1745386267

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1475839231

ObjectID: 50-DH-6508-SL-A18 System: 65 - OPEN DRAIN Package: 65B02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM OHD CAISON PUMP (P-6520) to 150Description: DH-6503-A18 Sub System: 65B - HAZARDOUS OPEN DRAINS HEADER Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

98/42

OE:1475839231

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1476330739

ObjectID: 50-DH-6508-SL-A18 System: 65 - OPEN DRAIN Package: 65B02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM OHD CAISON PUMP (P-6520) to 150Description: DH-6503-A18 Sub System: 65B - HAZARDOUS OPEN DRAINS HEADER Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

99/42

OE:1476330739

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1475839205

ObjectID: 50-DH-6528-SL-A18 System: 65 - OPEN DRAIN Package: 65B02 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0018 TestMedium: Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM FLARE K.O. DRUM COAMED AREA to Description: 150-DH-6503-A18 Sub System: 65B - HAZARDOUS OPEN DRAINS HEADER Area: Flushing Medium: Completed by Verified by Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

100/4

OE:1475839205

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1745386241

ObjectID: 50-DH-6528-SL-A18 System: 65 - OPEN DRAIN Package: 65B02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM FLARE K.O. DRUM COAMED AREA to Description: 150-DH-6503-A18 Sub System: 65B - HAZARDOUS OPEN DRAINS HEADER Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

101/4

OE:-1745386241

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1744894733

ObjectID: 50-DH-6528-SL-A18 System: 65 - OPEN DRAIN Package: 65B02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM FLARE K.O. DRUM COAMED AREA to Description: 150-DH-6503-A18 Sub System: 65B - HAZARDOUS OPEN DRAINS HEADER Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

102/4

OE:-1744894733

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-8879906

ObjectID: 50-FW-5310-SL-A18 System: 53 - FIXED FIREWATER SYSTEM Package: 53A02 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0023 TestMedium: Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM 100-FW-5302-A18 to OVERBOARD Description: DUMP Sub System: 53A - FIREWATER DISTRIBUTION Area: Flushing Medium: Completed by Verified by Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

103/4

OE:-8879906

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1064861892

ObjectID: 50-FW-5310-SL-A18 System: 53 - FIXED FIREWATER SYSTEM Package: 53A02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM 100-FW-5302-A18 to OVERBOARD Description: DUMP Sub System: 53A - FIREWATER DISTRIBUTION Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

104/4

OE:1064861892

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1064304840

ObjectID: 50-FW-5310-SL-A18 System: 53 - FIXED FIREWATER SYSTEM Package: 53A02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM 100-FW-5302-A18 to OVERBOARD Description: DUMP Sub System: 53A - FIREWATER DISTRIBUTION Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

105/4

OE:1064304840

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:2004507870

ObjectID: 50-FW-5309-SL-A18 System: 53 - FIXED FIREWATER SYSTEM Package: 53A02 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0023 TestMedium: Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM 100-FW-5302-A18 to OVERBOARD Description: DUMP Sub System: 53A - FIREWATER DISTRIBUTION Area: Flushing Medium: Completed by Verified by Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

106/4

OE:2004507870

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1216717628

ObjectID: 50-FW-5309-SL-A18 System: 53 - FIXED FIREWATER SYSTEM Package: 53A02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM 100-FW-5302-A18 to OVERBOARD Description: DUMP Sub System: 53A - FIREWATER DISTRIBUTION Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

107/4

OE:-1216717628

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1217209144

ObjectID: 50-FW-5309-SL-A18 System: 53 - FIXED FIREWATER SYSTEM Package: 53A02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM 100-FW-5302-A18 to OVERBOARD Description: DUMP Sub System: 53A - FIREWATER DISTRIBUTION Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

108/4

OE:-1217209144

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1211973564

ObjectID: 50-VA-9802-SL-A18 System: 51 - SERVICE WATER SYSTEM Package: 51B02 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0022 TestMedium: Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM AIR RELEASE VALVE P-5110 to VENT Description: TO SAFE LOCATION (OFFSHORE) Sub System: 51B - SERVICE WATER DISTRIBUTION Area: Flushing Medium: Completed by Verified by Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

109/4

OE:-1211973564

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:2009251934

ObjectID: 50-VA-9802-SL-A18 System: 51 - SERVICE WATER SYSTEM Package: 51B02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM AIR RELEASE VALVE P-5110 to VENT Description: TO SAFE LOCATION (OFFSHORE) Sub System: 51B - SERVICE WATER DISTRIBUTION Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

110/4

OE:2009251934

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:2009743442

ObjectID: 50-VA-9802-SL-A18 System: 51 - SERVICE WATER SYSTEM Package: 51B02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM AIR RELEASE VALVE P-5110 to VENT Description: TO SAFE LOCATION (OFFSHORE) Sub System: 51B - SERVICE WATER DISTRIBUTION Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

111/4

OE:2009743442

Inspection Test Report P04A Flushing and Testing Certificate MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:2000686169

ObjectID: 50-WS-5104-SL-A18 System: 51 - SERVICE WATER SYSTEM Package: 51B02 PIDNo: 06001-MEPA-EG-PR-DWG-PNID-0022 TestMedium: Operational Medium: Description of Item to be completed and Checked Limits of Test in accordance with the scope listed on attached Test Index P-01A and marked up P&ID's. System prepared for flushing in accordance with the approved procedure. Flushing completed in accordance with the approved procedure System prepared for testing in accordance with the approved procedure. System tested in accordance with the approved procedure. (Refer Note 1). Test Results and Readings Test Pressure at start Ambient Temperature at start Start Date and Time Test Pressure at end Ambient Temperature at end End Date and Time Test Duration Tested by Contractor Test Witnessed by (Note2)

LINES FROM SERVICE WATER SUPPLY CAISSON Description: (T-5510) to SERVICE WATER NETWORK Sub System: 51B - SERVICE WATER DISTRIBUTION Area: Flushing Medium: Completed by Verified by Date

BarG Degree C Date and Time BarG Degree C Date and Time Hours Name and Signature Name and Signature

Notes 1. 2. 3.

All test and Calibration charts to be Signed, Verified and Identified with the Test Number. Where Test is not witnessed state NA. All activity required Commissioning & Client Witness points

BDEWC Construction Name: Sign: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28924).

BDEWC QA/QC

BDEWC Commission

112/4

OE:2000686169

Inspection Test Report P02A Piping Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1220539325

ObjectID: 50-WS-5104-SL-A18 System: 51 - SERVICE WATER SYSTEM Package: 51B02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 TestPack:

LINES FROM SERVICE WATER SUPPLY CAISSON Description: (T-5510) to SERVICE WATER NETWORK Sub System: 51B - SERVICE WATER DISTRIBUTION Area:

Description System complies with P and ID's and isometric drawings. All field weld inspection and NDE, Traceability and History records complete and accepted. All NDT/Stress relieving requirements performed in accordance with requirements and documented. Correct bolts and gaskets are installed at all mechanical joints. All vents and drains are installed, including vents and drains for testing and are of correct pressure rating. Piping of correct material, schedule and type. *W* Rating of all forged steel fittings is correct. *W* Check Valve Materials - (Use spec ref. in piping material specification, tags and nameplates. Branch reinforcements are correct. Compound on screwed connections in accordance with specifications. All pressure connections as per specification. Correct direction of flow through filters and strainers traps, check valves, globe valves and control valves. *W* All instrument connections installed and any delicate instruments are isolated / removed from test. *W* All Relief valves, Bursting disks, and specified control valves have been removed. *W* Check Orifice valve tap orientation correct, taps and plugs have been seal welded and unused. Tapped holes are plugged and welded. *W* Check Orifice flanges have required upstream and downstream clearances, which bores have been ground and orifice plates have been removed. *W* All thermowells are installed. All pipe supports installed according to drawings and specifications. Gags on spring supports and expansion joints are in position. Check that system is adequately supported such that no spring in pipework causes stress on pumps or vessel nozzles. All chain wheels and extended spindles installed.

NA

OK

PL

Output /Remarks

Notes and Remarks *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

113/4

OE:-1220539325

Inspection Test Report P10A Line Walk Verification MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1219982257

ObjectID: 50-WS-5104-SL-A18 System: 51 - SERVICE WATER SYSTEM Package: 51B02 Service: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

LINES FROM SERVICE WATER SUPPLY CAISSON Description: (T-5510) to SERVICE WATER NETWORK Sub System: 51B - SERVICE WATER DISTRIBUTION Area:

Description Line walk sub-system and verify it reflects the latest revision of the P & ID's, and all pipework, valves, auxiliaries, etc are undamaged. All pipe supports installed in accordance with the drawings and Project spec's and all lines adequately supported. Lines flushed in accordance with Project requirements. *W* Lines dried in accordance with Project requirements *W* All Hydrotesting completed. *W* Lines Chemically cleaned / Pickled according to Project / Vendor requirements, where specified. *W* Lines Hot Oil Flushed according to Project / Vendor requirements (if specified). *W* Line preserved according to project requirements. Check manual valves are correctly lubricated, assessable and operational Line reinstated according to requirements and latest revision of the P&ID's, and all spectacle blinds in position shown on P&IDs All temporary commissioning and start up strainers installed *W* Coupling alignment completed in accordance with ITR M06A on all pipe spools connected to rotating equipment. (mandatory) The ITRs have been completed for all in-line items that require dismantling of flanges to carry out ITR, e.g. M-09A inspection of inline filters. (mandatory) All certification documentation, including test charts and test equipment calibration certificates signed and approved. Flange management complete and tag fitted to every joint (if specified in project requirements) Required DOSH & 3rd Party witnessed

NA

OK

PL

Output /Remarks

Notes and Remarks: *W* Commissioning & Client Witness points

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

114/4

OE:-1219982257

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-306091743

ObjectID: 7710-JL05-9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: JUNCTION BOX 7710-JL05-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

115/4

OE:-306091743

Inspection Test Report E05A Distribution Board, Junction Box & Control Station MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-37645536

ObjectID: 7710-JL05-9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 Manufacturer: SingleLineDwg: Item 01 02 03 04 05 06 07 08 09 10 11 12 Model/Type:

Description: JUNCTION BOX 7710-JL05-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: SerialNo: NA OK PL Output /Remarks

Description Installation as per AFC Drawings and cable schedule Visually inspect equipment for external damage. Confirm equipment is tagged correctly Check equipment fixings and mountings are secure. Check interior for damage, cleanliness and transport packing has been removed. Check earthing conforms to project specifications. Check correct circuit identification labels. Check component ratings are as per drawings Confirm all components are operational and lockable where necessary On completion of all cable glanding confirm spare entries are correctly plugged. Check gaskets and seals are not damaged. Replace all covers and check all bolts are correct none missing.

Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

116/4

OE:-37645536

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-306091761

ObjectID: 7710-JL06-9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: JUNCTION BOX 7710-JL06-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

117/4

OE:-306091761

Inspection Test Report E05A Distribution Board, Junction Box & Control Station MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-37645554

ObjectID: 7710-JL06-9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 Manufacturer: SingleLineDwg: Item 01 02 03 04 05 06 07 08 09 10 11 12 Model/Type:

Description: JUNCTION BOX 7710-JL06-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: SerialNo: NA OK PL Output /Remarks

Description Installation as per AFC Drawings and cable schedule Visually inspect equipment for external damage. Confirm equipment is tagged correctly Check equipment fixings and mountings are secure. Check interior for damage, cleanliness and transport packing has been removed. Check earthing conforms to project specifications. Check correct circuit identification labels. Check component ratings are as per drawings Confirm all components are operational and lockable where necessary On completion of all cable glanding confirm spare entries are correctly plugged. Check gaskets and seals are not damaged. Replace all covers and check all bolts are correct none missing.

Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

118/4

OE:-37645554

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-306091819

ObjectID: 7710-JL07-9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: JUNCTION BOX 7710-JL07-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

119/4

OE:-306091819

Inspection Test Report E05A Distribution Board, Junction Box & Control Station MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-37645612

ObjectID: 7710-JL07-9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 Manufacturer: SingleLineDwg: Item 01 02 03 04 05 06 07 08 09 10 11 12 Model/Type:

Description: JUNCTION BOX 7710-JL07-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: SerialNo: NA OK PL Output /Remarks

Description Installation as per AFC Drawings and cable schedule Visually inspect equipment for external damage. Confirm equipment is tagged correctly Check equipment fixings and mountings are secure. Check interior for damage, cleanliness and transport packing has been removed. Check earthing conforms to project specifications. Check correct circuit identification labels. Check component ratings are as per drawings Confirm all components are operational and lockable where necessary On completion of all cable glanding confirm spare entries are correctly plugged. Check gaskets and seals are not damaged. Replace all covers and check all bolts are correct none missing.

Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

120/4

OE:-37645612

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-306091855

ObjectID: 7710-JL08-9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: JUNCTION BOX 7710-JL08-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

121/4

OE:-306091855

Inspection Test Report E05A Distribution Board, Junction Box & Control Station MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-37645648

ObjectID: 7710-JL08-9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 Manufacturer: SingleLineDwg: Item 01 02 03 04 05 06 07 08 09 10 11 12 Model/Type:

Description: JUNCTION BOX 7710-JL08-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: SerialNo: NA OK PL Output /Remarks

Description Installation as per AFC Drawings and cable schedule Visually inspect equipment for external damage. Confirm equipment is tagged correctly Check equipment fixings and mountings are secure. Check interior for damage, cleanliness and transport packing has been removed. Check earthing conforms to project specifications. Check correct circuit identification labels. Check component ratings are as per drawings Confirm all components are operational and lockable where necessary On completion of all cable glanding confirm spare entries are correctly plugged. Check gaskets and seals are not damaged. Replace all covers and check all bolts are correct none missing.

Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

122/4

OE:-37645648

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-367956047

ObjectID: 7710-LE05-9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: LIGHTING FIXTURE 7710-LE05-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

123/4

OE:-367956047

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-367956065

ObjectID: 7710-LE06-9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: LIGHTING FIXTURE 7710-LE06-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

124/4

OE:-367956065

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-367956411

ObjectID: 7710-LE07-9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: LIGHTING FIXTURE 7710-LE07-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:08, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

125/4

OE:-367956411

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-367956447

ObjectID: 7710-LE08-9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: LIGHTING FIXTURE 7710-LE08-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

126/4

OE:-367956447

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-373690140

ObjectID: 7710-LE-09/9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 CableType: P2 ToTag: JUNCTION BOX 7710-JL05-9R Item 01 02 03 04 05 06 07 08 09 10
Notes:

Cable From JUNCTION BOX 7710-JL04-9R To Description: JUNCTION BOX 7710-JL05-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: FromTag: JUNCTION BOX 7710-JL04-9R VoltageRating: 240V Size: 2Cx4mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

127/4

OE:-373690140

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-122049692

ObjectID: 7710-LE-10/9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 CableType: P2 ToTag: LIGHTING FIXTURE 7710-LE05-9R Item 01 02 03 04 05 06 07 08 09 10
Notes:

Cable From JUNCTION BOX 7710-JL05-9R To Description: LIGHTING FIXTURE 7710-LE05-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: FromTag: JUNCTION BOX 7710-JL05-9R VoltageRating: 240V Size: 2Cx4mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

128/4

OE:-122049692

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-122045852

ObjectID: 7710-LE-11/9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 CableType: P2 ToTag: JUNCTION BOX 7710-JL06-9R Item 01 02 03 04 05 06 07 08 09 10
Notes:

Cable From JUNCTION BOX 7710-JL05-9R To Description: JUNCTION BOX 7710-JL06-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: FromTag: JUNCTION BOX 7710-JL05-9R VoltageRating: 240V Size: 2Cx4mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

129/4

OE:-122045852

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-122047644

ObjectID: 7710-LE-12/9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 CableType: P2 ToTag: LIGHTING FIXTURE 7710-LE06-9R Item 01 02 03 04 05 06 07 08 09 10
Notes:

Cable From JUNCTION BOX 7710-JL06-9R To Description: LIGHTING FIXTURE 7710-LE06-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: FromTag: JUNCTION BOX 7710-JL06-9R VoltageRating: 240V Size: 2Cx4mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

130/4

OE:-122047644

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-122058268

ObjectID: 7710-LE-13/9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 CableType: P2 ToTag: JUNCTION BOX 7710-JL07-9R Item 01 02 03 04 05 06 07 08 09 10
Notes:

Cable From JUNCTION BOX 7710-JL06-9R To Description: JUNCTION BOX 7710-JL07-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: FromTag: JUNCTION BOX 7710-JL06-9R VoltageRating: 240V Size: 2Cx4mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

131/4

OE:-122058268

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-122059036

ObjectID: 7710-LE-14/9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 CableType: P2 ToTag: LIGHTING FIXTURE 7710-LE07-9R Item 01 02 03 04 05 06 07 08 09 10
Notes:

Cable From JUNCTION BOX 7710-JL07-9R To Description: LIGHTING FIXTURE 7710-LE07-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: FromTag: JUNCTION BOX 7710-JL07-9R VoltageRating: 240V Size: 2Cx4mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

132/4

OE:-122059036

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-122052636

ObjectID: 7710-LE-15/9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 CableType: P2 ToTag: JUNCTION BOX 7710-JL08-9R Item 01 02 03 04 05 06 07 08 09 10
Notes:

Cable From JUNCTION BOX 7710-JL07-9R To Description: JUNCTION BOX 7710-JL08-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: FromTag: JUNCTION BOX 7710-JL07-9R VoltageRating: 240V Size: 2Cx4mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

133/4

OE:-122052636

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-122055580

ObjectID: 7710-LE-16/9R System: 77 - POWER GENERATION DISTRIBUTION LV Package: 77D07 CableType: P2 ToTag: LIGHTING FIXTURE 7710-LE08-9R Item 01 02 03 04 05 06 07 08 09 10
Notes:

Cable From JUNCTION BOX 7710-JL08-9R To Description: LIGHTING FIXTURE 7710-LE08-9R Sub System: 77D - LV EMERGENCY DISTRIBUTION Area: FromTag: JUNCTION BOX 7710-JL08-9R VoltageRating: 240V Size: 2Cx4mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

134/4

OE:-122055580

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1349334717

ObjectID: GOPB-ANT-9206 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92E01 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: PARABOLIC ANTENNA Sub System: 92E - GOPB TELECOM Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

135/4

OE:-1349334717

Inspection Test Report T01A Telecoms Field Device Installation Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-275101665

ObjectID: GOPB-ANT-9206 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92E01 Manufacturer: Type: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 Serial No:

Description: PARABOLIC ANTENNA Sub System: 92E - GOPB TELECOM Area: Service: NA OK PL Output /Remarks

Description Installed according to latest revision of Layout drawing. Item complies with Data sheet. Equipment suitable for area classification. Identification correct. Supports installed correctly. Fixings correct. Access suitable. Paintwork correct. Spare gland entries plugged correctly. Terminal box flanges undamaged. Gaskets & seals undamaged. Gaskets & seals fitted correctly. Check earthing conforms to earthing philosophy. Suitable grease applied to flanges (Ex-d enclosures).

Notes and Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

136/4

OE:-275101665

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1370961597

ObjectID: GOPB-ANT-9207 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92E01 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: PARABOLIC ANTENNA Sub System: 92E - GOPB TELECOM Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

137/4

OE:-1370961597

Inspection Test Report T01A Telecoms Field Device Installation Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-297777121

ObjectID: GOPB-ANT-9207 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92E01 Manufacturer: Type: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 Serial No:

Description: PARABOLIC ANTENNA Sub System: 92E - GOPB TELECOM Area: Service: NA OK PL Output /Remarks

Description Installed according to latest revision of Layout drawing. Item complies with Data sheet. Equipment suitable for area classification. Identification correct. Supports installed correctly. Fixings correct. Access suitable. Paintwork correct. Spare gland entries plugged correctly. Terminal box flanges undamaged. Gaskets & seals undamaged. Gaskets & seals fitted correctly. Check earthing conforms to earthing philosophy. Suitable grease applied to flanges (Ex-d enclosures).

Notes and Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

138/4

OE:-297777121

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:942423269

ObjectID: GORA-PG-2950 System: 29 - GAS IMPORT/EXPORT Package: 29C01 Manufacturer: Service: Item 01 02 03 04 05 06 Model/Type:

Description: PRESSURE GAUGE Sub System: Area: SerialNo: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

139/4

OE:942423269

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:2016165108

ObjectID: GORA-PG-2953 System: 29 - GAS IMPORT/EXPORT Package: 29C01 Manufacturer: Service: Item 01 02 03 04 05 06 Model/Type:

Description: PRESSURE GAUGE Sub System: Area: SerialNo: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

140/4

OE:2016165108

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-131318541

ObjectID: GORA-PG-2954 System: 29 - GAS IMPORT/EXPORT Package: 29C01 Manufacturer: Service: Item 01 02 03 04 05 06 Model/Type:

Description: PRESSURE GAUGE Sub System: Area: SerialNo: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

141/4

OE:-131318541

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:955366657

ObjectID: GORA-PG-3390 System: 33 - CONDENSATE IMPORT/EXPORT Package: 33C01 Manufacturer: Service: Item 01 02 03 04 05 06 Model/Type:

Description: PRESSURE GAUGE Sub System: Area: SerialNo: NA OK PL Output /Remarks 33C - MEPA CONDENSATE RECEIVING FACILITIES AT GORA

Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

142/4

OE:955366657

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:2029108496

ObjectID: GORA-PG-3393 System: 33 - CONDENSATE IMPORT/EXPORT Package: 33C01 Manufacturer: Service: Item 01 02 03 04 05 06 Model/Type:

Description: PRESSURE GAUGE Sub System: Area: SerialNo: NA OK PL Output /Remarks 33C - MEPA CONDENSATE RECEIVING FACILITIES AT GORA

Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

143/4

OE:2029108496

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-118375145

ObjectID: GORA-PG-3394 System: 33 - CONDENSATE IMPORT/EXPORT Package: 33C01 Manufacturer: Service: Item 01 02 03 04 05 06 Model/Type:

Description: PRESSURE GAUGE Sub System: Area: SerialNo: NA OK PL Output /Remarks 33C - MEPA CONDENSATE RECEIVING FACILITIES AT GORA

Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

144/4

OE:-118375145

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:452355156

ObjectID: GORA-PIA-2952 System: 29 - GAS IMPORT/EXPORT Package: 29C01 Manufacturer: Service: Item 01 02 03 04 05 06 Model/Type:

Description: PRESSURE TRANSMITTER Sub System: Area: SerialNo: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

145/4

OE:452355156

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-621386675

ObjectID: GORA-PIA-2952 System: 29 - GAS IMPORT/EXPORT Package: 29C01 C&E No: Service: Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: PRESSURE TRANSMITTER Sub System: Area: LoopNo: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

146/4

OE:-621386675

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:440689748

ObjectID: GORA-PIA-2955 System: 29 - GAS IMPORT/EXPORT Package: 29C01 Manufacturer: Service: Item 01 02 03 04 05 06 Model/Type:

Description: PRESSURE DIFFERENTIAL TRANSMITTER Sub System: Area: SerialNo: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

147/4

OE:440689748

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-633052083

ObjectID: GORA-PIA-2955 System: 29 - GAS IMPORT/EXPORT Package: 29C01 C&E No: Service: Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: PRESSURE DIFFERENTIAL TRANSMITTER Sub System: Area: LoopNo: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

148/4

OE:-633052083

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:366367540

ObjectID: GORA-PIA-3392 System: 33 - CONDENSATE IMPORT/EXPORT Package: 33C01 Manufacturer: Service: Item 01 02 03 04 05 06 Model/Type:

Description: PRESSURE TRANSMITTER Sub System: Area: SerialNo: NA OK PL Output /Remarks 33C - MEPA CONDENSATE RECEIVING FACILITIES AT GORA

Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

149/4

OE:366367540

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-707374291

ObjectID: GORA-PIA-3392 System: 33 - CONDENSATE IMPORT/EXPORT Package: 33C01 C&E No: Service: Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: PRESSURE TRANSMITTER Sub System: Area: LoopNo: NA OK PL Output /Remarks 33C - MEPA CONDENSATE RECEIVING FACILITIES AT GORA

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

150/4

OE:-707374291

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:449841236

ObjectID: GORA-PZA-2951 System: 29 - GAS IMPORT/EXPORT Package: 29C01 Manufacturer: Service: Item 01 02 03 04 05 06 Model/Type:

Description: PRESSURE TRANSMITTER Sub System: Area: SerialNo: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

151/4

OE:449841236

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-623900595

ObjectID: GORA-PZA-2951 System: 29 - GAS IMPORT/EXPORT Package: 29C01 C&E No: Service: Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: PRESSURE TRANSMITTER Sub System: Area: LoopNo: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

152/4

OE:-623900595

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:368066356

ObjectID: GORA-PZA-3391 System: 33 - CONDENSATE IMPORT/EXPORT Package: 33C01 Manufacturer: Service: Item 01 02 03 04 05 06 Model/Type:

Description: PRESSURE TRANSMITTER Sub System: Area: SerialNo: NA OK PL Output /Remarks 33C - MEPA CONDENSATE RECEIVING FACILITIES AT GORA

Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

153/4

OE:368066356

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-705675475

ObjectID: GORA-PZA-3391 System: 33 - CONDENSATE IMPORT/EXPORT Package: 33C01 C&E No: Service: Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: PRESSURE TRANSMITTER Sub System: Area: LoopNo: NA OK PL Output /Remarks 33C - MEPA CONDENSATE RECEIVING FACILITIES AT GORA

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

154/4

OE:-705675475

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-157891497

ObjectID: GORA-SDV-2950 System: 29 - GAS IMPORT/EXPORT Package: 29C01 Manufacturer: Service: Item 01 02 03 04 05 06 Model/Type:

Description: SHUTDOWN VALVE Sub System: Area: SerialNo: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

155/4

OE:-157891497

Inspection Test Report I03A Valve and Ancillaries MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-157891492

ObjectID: GORA-SDV-2950 System: 29 - GAS IMPORT/EXPORT Package: 29C01 Item 01

Description: SHUTDOWN VALVE Sub System: Area: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

Description All equipment free from damage and installed correctly All equipment to be checked for correctness against current revision of data sheet for: 02 Manufacturer, Type, Model No. and Serial No. 02.01 VALVE 02.02 - Serial No : ______________________ 02.03 - Model / type : ______________________ 02.04 - Size 02.05 - Rating 02.06 - Flange type 02.07 - Service 02.08 - Material certification correct 02.09 - Body material 02.10 - Trim material correct 02.11 - Leakage class 02.12 ACTUATOR 02.13 - Serial No : ______________________ 02.14 - Model / type : ______________________ 02.15 - Input range 02.16 - Failure action 02.17 - Hand wheel operation correct 02.18 POSITIONER 02.19 - Serial No : ______________________ 02.20 - Model / type : ______________________ 02.21 - Signal range 02.22 - Output range 02.23 I/P CONVERTER 02.24 - Serial No : ______________________ 02.25 - Model / type : ______________________ 02.26 - Signal range 02.27 - Output range 02.28 FILTER/REGULATOR 02.29 - Serial No : ______________________ 02.30 - Model / type : ______________________ 02.31 - Range 02.32 MISCELLANEOUS ACCESSORIES 02.33 - Correct to Data Sheet Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

156/4

OE:-157891492

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:915850318

ObjectID: GORA-SDV-2950 System: 29 - GAS IMPORT/EXPORT Package: 29C01 C&E No: Service: Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: SHUTDOWN VALVE Sub System: Area: LoopNo: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

157/4

OE:915850318

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-153959337

ObjectID: GORA-SDV-2951 System: 29 - GAS IMPORT/EXPORT Package: 29C01 Manufacturer: Service: Item 01 02 03 04 05 06 Model/Type:

Description: SHUTDOWN VALVE Sub System: Area: SerialNo: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

158/4

OE:-153959337

Inspection Test Report I03A Valve and Ancillaries MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-153959332

ObjectID: GORA-SDV-2951 System: 29 - GAS IMPORT/EXPORT Package: 29C01 Item 01

Description: SHUTDOWN VALVE Sub System: Area: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

Description All equipment free from damage and installed correctly All equipment to be checked for correctness against current revision of data sheet for: 02 Manufacturer, Type, Model No. and Serial No. 02.01 VALVE 02.02 - Serial No : ______________________ 02.03 - Model / type : ______________________ 02.04 - Size 02.05 - Rating 02.06 - Flange type 02.07 - Service 02.08 - Material certification correct 02.09 - Body material 02.10 - Trim material correct 02.11 - Leakage class 02.12 ACTUATOR 02.13 - Serial No : ______________________ 02.14 - Model / type : ______________________ 02.15 - Input range 02.16 - Failure action 02.17 - Hand wheel operation correct 02.18 POSITIONER 02.19 - Serial No : ______________________ 02.20 - Model / type : ______________________ 02.21 - Signal range 02.22 - Output range 02.23 I/P CONVERTER 02.24 - Serial No : ______________________ 02.25 - Model / type : ______________________ 02.26 - Signal range 02.27 - Output range 02.28 FILTER/REGULATOR 02.29 - Serial No : ______________________ 02.30 - Model / type : ______________________ 02.31 - Range 02.32 MISCELLANEOUS ACCESSORIES 02.33 - Correct to Data Sheet Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

159/4

OE:-153959332

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:919782478

ObjectID: GORA-SDV-2951 System: 29 - GAS IMPORT/EXPORT Package: 29C01 C&E No: Service: Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: SHUTDOWN VALVE Sub System: Area: LoopNo: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

160/4

OE:919782478

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-105450697

ObjectID: GORA-SDV-3390 System: 33 - CONDENSATE IMPORT/EXPORT Package: 33C01 Manufacturer: Service: Item 01 02 03 04 05 06 Model/Type:

Description: SHUTDOWN VALVE Sub System: Area: SerialNo: NA OK PL Output /Remarks 33C - MEPA CONDENSATE RECEIVING FACILITIES AT GORA

Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

161/4

OE:-105450697

Inspection Test Report I03A Valve and Ancillaries MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-105450692

ObjectID: GORA-SDV-3390 System: 33 - CONDENSATE IMPORT/EXPORT Package: 33C01 Item 01

Description: SHUTDOWN VALVE Sub System: Area: NA OK PL Output /Remarks 33C - MEPA CONDENSATE RECEIVING FACILITIES AT GORA

Description All equipment free from damage and installed correctly All equipment to be checked for correctness against current revision of data sheet for: 02 Manufacturer, Type, Model No. and Serial No. 02.01 VALVE 02.02 - Serial No : ______________________ 02.03 - Model / type : ______________________ 02.04 - Size 02.05 - Rating 02.06 - Flange type 02.07 - Service 02.08 - Material certification correct 02.09 - Body material 02.10 - Trim material correct 02.11 - Leakage class 02.12 ACTUATOR 02.13 - Serial No : ______________________ 02.14 - Model / type : ______________________ 02.15 - Input range 02.16 - Failure action 02.17 - Hand wheel operation correct 02.18 POSITIONER 02.19 - Serial No : ______________________ 02.20 - Model / type : ______________________ 02.21 - Signal range 02.22 - Output range 02.23 I/P CONVERTER 02.24 - Serial No : ______________________ 02.25 - Model / type : ______________________ 02.26 - Signal range 02.27 - Output range 02.28 FILTER/REGULATOR 02.29 - Serial No : ______________________ 02.30 - Model / type : ______________________ 02.31 - Range 02.32 MISCELLANEOUS ACCESSORIES 02.33 - Correct to Data Sheet Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

162/4

OE:-105450692

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:968291118

ObjectID: GORA-SDV-3390 System: 33 - CONDENSATE IMPORT/EXPORT Package: 33C01 C&E No: Service: Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: SHUTDOWN VALVE Sub System: Area: LoopNo: NA OK PL Output /Remarks 33C - MEPA CONDENSATE RECEIVING FACILITIES AT GORA

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

163/4

OE:968291118

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1051489945

ObjectID: GORA-XI-2952 System: 29 - GAS IMPORT/EXPORT Package: 29C01 C&E No: Service: Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: PIG SIGNALLER - LOCAL INDICATION -L2950 Sub System: Area: LoopNo: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

164/4

OE:1051489945

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1047656317

ObjectID: GORA-XI-3392 System: 33 - CONDENSATE IMPORT/EXPORT Package: 33C01 C&E No: Service: Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: PIG SIGNALLER - LOCAL INDICATION -L3390 Sub System: Area: LoopNo: NA OK PL Output /Remarks 33C - MEPA CONDENSATE RECEIVING FACILITIES AT GORA

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

165/4

OE:1047656317

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:2060608599

ObjectID: GORA-XIA-2951 System: 29 - GAS IMPORT/EXPORT Package: 29C01 Manufacturer: Service: Item 01 02 03 04 05 06 Model/Type:

Description: PIG SIGNALLER - REMOTE INDICATION - L2950 Sub System: Area: SerialNo: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

166/4

OE:2060608599

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1160616882

ObjectID: GORA-XIA-2951 System: 29 - GAS IMPORT/EXPORT Package: 29C01 C&E No: Service: Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: PIG SIGNALLER - REMOTE INDICATION - L2950 Sub System: Area: LoopNo: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

167/4

OE:-1160616882

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1978815287

ObjectID: GORA-XIA-3391 System: 33 - CONDENSATE IMPORT/EXPORT Package: 33C01 Manufacturer: Service: Item 01 02 03 04 05 06 Model/Type:

Description: PIG SIGNALLER - REMOTE INDICATION - L3390 Sub System: Area: SerialNo: NA OK PL Output /Remarks 33C - MEPA CONDENSATE RECEIVING FACILITIES AT GORA

Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

168/4

OE:1978815287

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1242410194

ObjectID: GORA-XIA-3391 System: 33 - CONDENSATE IMPORT/EXPORT Package: 33C01 C&E No: Service: Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: PIG SIGNALLER - REMOTE INDICATION - L3390 Sub System: Area: LoopNo: NA OK PL Output /Remarks 33C - MEPA CONDENSATE RECEIVING FACILITIES AT GORA

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

169/4

OE:-1242410194

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-660729992

ObjectID: HY-0111 System: 01 - WELLHEADS & FLOWLINES Package: 01B03 CableType: I2 ToTag: MEPA-HY-0111 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-009 To MEPA-HY-0111 Sub System: 01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINE Area: FromTag: MEPA-IJB-009 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

170/4

OE:-660729992

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-660959368

ObjectID: HY-0121 System: 01 - WELLHEADS & FLOWLINES Package: 01C03 CableType: I2 ToTag: MEPA-HY-0121 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-009 To MEPA-HY-0121 Sub System: 01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINE Area: FromTag: MEPA-IJB-009 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

171/4

OE:-660959368

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-662188168

ObjectID: HY-0131 System: 01 - WELLHEADS & FLOWLINES Package: 01D03 CableType: I2 ToTag: MEPA-HY-0131 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-009 To MEPA-HY-0131 Sub System: 01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINE Area: FromTag: MEPA-IJB-009 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

172/4

OE:-662188168

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-662679688

ObjectID: HY-0141 System: 01 - WELLHEADS & FLOWLINES Package: 01E03 CableType: I2 ToTag: MEPA-HY-0141 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-009 To MEPA-HY-0141 Sub System: 01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINE Area: FromTag: MEPA-IJB-009 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

173/4

OE:-662679688

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-661860488

ObjectID: HY-0151 System: 01 - WELLHEADS & FLOWLINES Package: 01F03 CableType: I2 ToTag: MEPA-HY-0151 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-009 To MEPA-HY-0151 Sub System: 01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINE Area: FromTag: MEPA-IJB-009 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

174/4

OE:-661860488

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-662106248

ObjectID: HY-0161 System: 01 - WELLHEADS & FLOWLINES Package: 01G03 CableType: I2 ToTag: MEPA-HY-0161 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-009 To MEPA-HY-0161 Sub System: 01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINE Area: FromTag: MEPA-IJB-009 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

175/4

OE:-662106248

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-659402888

ObjectID: HY-0171 System: 01 - WELLHEADS & FLOWLINES Package: 01H03 CableType: I2 ToTag: MEPA-HY-0171 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-009 To MEPA-HY-0171 Sub System: 01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINE Area: FromTag: MEPA-IJB-009 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

176/4

OE:-659402888

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-658583688

ObjectID: HY-0181 System: 01 - WELLHEADS & FLOWLINES Package: 01I03 CableType: I2 ToTag: MEPA-HY-0181 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-009 To MEPA-HY-0181 Sub System: 01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINE Area: FromTag: MEPA-IJB-009 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

177/4

OE:-658583688

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-658813064

ObjectID: HY-0191 System: 01 - WELLHEADS & FLOWLINES Package: 01J03 CableType: I2 ToTag: MEPA-HY-0191 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-009 To MEPA-HY-0191 Sub System: 01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINE Area: FromTag: MEPA-IJB-009 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

178/4

OE:-658813064

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-661221540

ObjectID: HY-0201 System: 01 - WELLHEADS & FLOWLINES Package: 01K03 CableType: I2 ToTag: MEPA-HY-0201 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-009 To MEPA-HY-0201 Sub System: 01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINE Area: FromTag: MEPA-IJB-009 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

179/4

OE:-661221540

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-660730020

ObjectID: HY-0211 System: 01 - WELLHEADS & FLOWLINES Package: 01L03 CableType: I2 ToTag: MEPA-HY-0211 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-009 To MEPA-HY-0211 Sub System: 01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINE Area: FromTag: MEPA-IJB-009 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

180/4

OE:-660730020

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-660959396

ObjectID: HY-0221 System: 01 - WELLHEADS & FLOWLINES Package: 01M03 CableType: I2 ToTag: MEPA-HY-0221 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-009 To MEPA-HY-0221 Sub System: Area: FromTag: MEPA-IJB-009 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks 01M - WELLHEAD WH-0220 (SLOT 12) & FLOWLINE

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

181/4

OE:-660959396

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1579289606

ObjectID: LT-6510 System: 65 - OPEN DRAIN Package: 65A02 CableType: I2 ToTag: MEPA-LT-6510 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-015 To MEPA-LT-6510 Sub System: 65A - T-6510 OPEN DRAINS CAISSON & PUMP Area: FromTag: MEPA-IJB-015 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

182/4

OE:1579289606

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1351177929

ObjectID: MEPA-ANT-9201 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92A02 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: PARABOLIC ANTENNA Sub System: 92A - DMR SYSTEM Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

183/4

OE:-1351177929

Inspection Test Report T01A Telecoms Field Device Installation Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-276944789

ObjectID: MEPA-ANT-9201 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92A02 Manufacturer: Type: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 Serial No:

Description: PARABOLIC ANTENNA Sub System: 92A - DMR SYSTEM Area: Service: NA OK PL Output /Remarks

Description Installed according to latest revision of Layout drawing. Item complies with Data sheet. Equipment suitable for area classification. Identification correct. Supports installed correctly. Fixings correct. Access suitable. Paintwork correct. Spare gland entries plugged correctly. Terminal box flanges undamaged. Gaskets & seals undamaged. Gaskets & seals fitted correctly. Check earthing conforms to earthing philosophy. Suitable grease applied to flanges (Ex-d enclosures).

Notes and Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

184/4

OE:-276944789

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1353537225

ObjectID: MEPA-ANT-9202 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92A02 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: PARABOLIC ANTENNA Sub System: 92A - DMR SYSTEM Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

185/4

OE:-1353537225

Inspection Test Report T01A Telecoms Field Device Installation Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-279304085

ObjectID: MEPA-ANT-9202 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92A02 Manufacturer: Type: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 Serial No:

Description: PARABOLIC ANTENNA Sub System: 92A - DMR SYSTEM Area: Service: NA OK PL Output /Remarks

Description Installed according to latest revision of Layout drawing. Item complies with Data sheet. Equipment suitable for area classification. Identification correct. Supports installed correctly. Fixings correct. Access suitable. Paintwork correct. Spare gland entries plugged correctly. Terminal box flanges undamaged. Gaskets & seals undamaged. Gaskets & seals fitted correctly. Check earthing conforms to earthing philosophy. Suitable grease applied to flanges (Ex-d enclosures).

Notes and Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

186/4

OE:-279304085

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1346852553

ObjectID: MEPA-ANT-9203 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92C02 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: PARABOLIC ANTENNA Sub System: 92C - UHF/VHF SYSTEM Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

187/4

OE:-1346852553

Inspection Test Report T01A Telecoms Field Device Installation Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-273667989

ObjectID: MEPA-ANT-9203 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92C02 Manufacturer: Type: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 Serial No:

Description: PARABOLIC ANTENNA Sub System: 92C - UHF/VHF SYSTEM Area: Service: NA OK PL Output /Remarks

Description Installed according to latest revision of Layout drawing. Item complies with Data sheet. Equipment suitable for area classification. Identification correct. Supports installed correctly. Fixings correct. Access suitable. Paintwork correct. Spare gland entries plugged correctly. Terminal box flanges undamaged. Gaskets & seals undamaged. Gaskets & seals fitted correctly. Check earthing conforms to earthing philosophy. Suitable grease applied to flanges (Ex-d enclosures).

Notes and Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

188/4

OE:-273667989

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1350260425

ObjectID: MEPA-ANT-9204 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92C02 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: PARABOLIC ANTENNA Sub System: 92C - UHF/VHF SYSTEM Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

189/4

OE:-1350260425

Inspection Test Report T01A Telecoms Field Device Installation Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-276027285

ObjectID: MEPA-ANT-9204 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92C02 Manufacturer: Type: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 Serial No:

Description: PARABOLIC ANTENNA Sub System: 92C - UHF/VHF SYSTEM Area: Service: NA OK PL Output /Remarks

Description Installed according to latest revision of Layout drawing. Item complies with Data sheet. Equipment suitable for area classification. Identification correct. Supports installed correctly. Fixings correct. Access suitable. Paintwork correct. Spare gland entries plugged correctly. Terminal box flanges undamaged. Gaskets & seals undamaged. Gaskets & seals fitted correctly. Check earthing conforms to earthing philosophy. Suitable grease applied to flanges (Ex-d enclosures).

Notes and Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

190/4

OE:-276027285

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1344231113

ObjectID: MEPA-ANT-9205 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92C02 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: PARABOLIC ANTENNA Sub System: 92C - UHF/VHF SYSTEM Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

191/4

OE:-1344231113

Inspection Test Report T01A Telecoms Field Device Installation Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-269997973

ObjectID: MEPA-ANT-9205 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92C02 Manufacturer: Type: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 Serial No:

Description: PARABOLIC ANTENNA Sub System: 92C - UHF/VHF SYSTEM Area: Service: NA OK PL Output /Remarks

Description Installed according to latest revision of Layout drawing. Item complies with Data sheet. Equipment suitable for area classification. Identification correct. Supports installed correctly. Fixings correct. Access suitable. Paintwork correct. Spare gland entries plugged correctly. Terminal box flanges undamaged. Gaskets & seals undamaged. Gaskets & seals fitted correctly. Check earthing conforms to earthing philosophy. Suitable grease applied to flanges (Ex-d enclosures).

Notes and Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

192/4

OE:-269997973

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1345410761

ObjectID: MEPA-ANT-9206 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92C02 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: UHF DATA RADIO 5.8GHZ Sub System: 92C - UHF/VHF SYSTEM Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

193/4

OE:-1345410761

Inspection Test Report T01A Telecoms Field Device Installation Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-272226197

ObjectID: MEPA-ANT-9206 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92C02 Manufacturer: Type: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 Serial No:

Description: UHF DATA RADIO 5.8GHZ Sub System: 92C - UHF/VHF SYSTEM Area: Service: NA OK PL Output /Remarks

Description Installed according to latest revision of Layout drawing. Item complies with Data sheet. Equipment suitable for area classification. Identification correct. Supports installed correctly. Fixings correct. Access suitable. Paintwork correct. Spare gland entries plugged correctly. Terminal box flanges undamaged. Gaskets & seals undamaged. Gaskets & seals fitted correctly. Check earthing conforms to earthing philosophy. Suitable grease applied to flanges (Ex-d enclosures).

Notes and Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

194/4

OE:-272226197

Inspection Test Report M20A Area Completion MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:335707679

ObjectID: MEPA-BL-7100 System: 71 - STRUCTURAL Package: 71E01 Item 01 02

Description: BOAT LANDING Sub System: 71E - BOAT LANDING Area: Output /Remarks

Description NA OK PL General All equipment located and correctly tagged in accordance with latest AFC drawings. All equipment free from damage installed and correctly secured in accordance with latest 03 AFC drawings. 04 All equipment performs its specified function. Wall and ceiling linings: Insulation and vapour barrier placed and undamaged, lining 05 colour correct, ceiling and wall panels correctly trimmed and free from damage. Pre-fabricated firewalls/louvers installed to specification with sealed joints, plumb and 06 lined, without damage. Floor coating: Floor screed placed according to specification, carpet or tiles of correct 07 colour, embedding of carpet or tiles is firm without any gaps or damage. 08 Floors lay to drain evenly to outlets, with no puddling or flat spots. 09 Water bunds turned up around walls in wet areas. 10 Suspended floors correct and un-damaged. All doors and windows free from damage and installed correctly in accordance with latest 11 AFC drawings. Furniture: All furniture of correct colour and placed in accordance with drawings, all 12 drawers/locker doors open/shut, all locks function. All spare keys taped securely adjacent to respective locks. 13 Information signs installed. 14 Area is clean and free of all debris. 15 Electrical Cable Racks, ladder, transit and cover Confirm all cable trays and racks are installed in accordance with routing and detail 16 drawings 17 Confirm all supports and fixings are correct and complete 18 Confirm all cable racks are identified 19 Confirm all cables are clipped with permanent fixings 20 Confirm all earth bonding is complete 21 Confirm all dissimilar metal insulators are installed. 22 Confirm all transit frames are installed correctly 23 Confirm all transits are packed in accordance with the transit schedule 24 Confirm all transits are complete and blocked. 25 Confirm cable dressing is complete 26 Confirm all cable ladder are fully covered (if applicable) 27 Walls and Ceilings 28 Pins installed, where applicable, in accordance with latest AFC specifications. Insulating material and thickness in accordance with the latest AFC specification. Vapour 29 barriers installed where required. 30 Mesh of correct type has been installed according to the latest AFC specification. All piping and ducting penetrations in accordance with the requirements of the latest AFC 31 penetration dossier for fire rating. All cable penetrations confirm to the requirements of the penetration dossier for fire 32 rating. Galvanised steel lining fixed to protect wall and deck-head insulation as specified by 33 latest AFC shop drawings and Vendor details. 34 HVAC Ductwork 35 Limits of insulation with the latest AFC D & ID drawings and specifications. 36 Insulation, thickness and material in accordance with the latest AFC specifications. 37 Jacketing, type, application and condition conforms to requirements. 38 Data plates and tag numbers are visible. 39 Insulation materials do not obstruct operation of access man-ways. BDEWC Construction BDEWC QA/QC BDEWC Commissioning Check that where required 'snap on' boxes are fitted in accordance with the latest AFC 40 Name: specification. 41 Identification labels and arrows installed. Signature: 42 System and temporary dust blinds are visible. 43 Piping Systems Date: 44 Limits of insulation in accordance with the latest AFC P&ID, drawings and specifications. Printed Montaha, Nasrun. 16-Mar-2013 09:09, system (ID=28922). 45 by: No attachment points on the piping are covered by insulation material. Access to all instruments, including in-line instruments unobstructed by insulation 46 materials. 47 Snap on boxes fitted at all required locations in accordance with the specifications. OE:335707679

195/4

Insulating material and thickness in accordance with the latest AFC specification. Vapour barriers installed where required. 30 Mesh of correct type has been installed according to the latest AFC specification. All piping and ductingReport penetrations in accordance with the requirements of the latest AFC Inspection Test 31 penetration dossier for fire rating. M20AAll cable Area Completion penetrations confirm to the requirements of the penetration dossier for fire 32 rating. MERAPUH-A (MEPA) PRODUCTION TOPSIDE Galvanised steel lining fixed to protect wall and deck-head insulation as specified by FACILITIES 33 latest AFC shop drawings and Vendor details. 34 HVAC Ductwork 35 ObjectID: Limits of MEPA-BL-7100 insulation with the latest AFC D & ID drawings and specifications. Description: BOAT LANDING 36 Insulation, thickness and material in accordance with the latest AFC specifications. System: 71 - STRUCTURAL Sub System: 71E - BOAT LANDING 37 Jacketing, type, application and condition conforms to requirements. 71E01 Area: 38 Package: Data plates and tag numbers are visible. 29 Insulation materials do not obstruct operation of access man-ways. Check that where required 'snap on' boxes are fitted in accordance with the latest AFC 40 specification. 41 Identification labels and arrows installed. 42 System and temporary dust blinds are visible. 43 Piping Systems 44 Limits of insulation in accordance with the latest AFC P&ID, drawings and specifications. 45 No attachment points on the piping system are covered by insulation material. Access to all instruments, including in-line instruments unobstructed by insulation 46 materials. 47 Snap on boxes fitted at all required locations in accordance with the specifications. 48 Insulation, thickness and material in accordance with the latest AFC specifications. 49 Jacketing thickness and material in accordance with the latest AFC specifications. Fixing materials, including screws and banding, are of the correct type and installed in 50 accordance with the latest AFC specification. Cable and piping penetrations completed and sealed in accordance with the latest AFC 51 specifications. 52 Mastic and water seals correctly installed 53 Equipment 54 Insulation, thickness and material in accordance with latest AFC specifications. 55 Jacketing, type, application and condition conforms to latest AFC specifications. 56 All equipment nozzles and instruments are clear of the insulation material and jacketing. 57 All data plates and tag numbers are visible. 58 Insulation materials do not obstruct operation of access man-ways. Check that where required 'snap on' boxes are fitted in accordance with the latest AFC 59 specification. 60 Escape Routes and Platform Signs 61 Escape route in accordance with Loss Control layout drawings. 62 Escape routes not obstructed. 63 Escape routes painted to specification and non-skid surface complete. 64 Direction of escape correct and clearly marked. 65 Escape route / safety signs, location correct as per Loss Control layout drawings. 66 Escape route / safety signs securely fixed in position. 67 Escape route / safety signs not obstructed and legible. 68 Hose reels 69 Hose reel correctly installed to manufacturers instructions. 70 Cabinet doors secure. 71 Operation instructions fitted and legible. 72 Stop valves checked for ease of operation and shut-off. 73 Main valves checked for ease of operation and shut-off. 74 Hose reel runs out correctly. 75 Hose free from damage and kinks. 76 Hose nozzle operation and shut-off checked. 77 Hose reel rewind satisfactorily. 78 Painting , Coatings and Fireproofing Correct paint system applied according to specification and in accordance with supplier 79 requirements 80 All specified adhesion tests completed and accepted 81 All remedial work completed and accepted 82 Finish paint colour conforms to specification 83 All paintwork clean and undamaged BDEWC Construction BDEWC QA/QC BDEWC Commissioning 84 Fireproofing materials applied according to specification Name: 85 Fireproofing material finish conforms to agreed sample (where applicable) 86 All Fireproofing clean and undamaged Signature: Date:
Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

OE:335707679

39

196/4

OE:335707679

71 Operation instructions fitted and legible. 72 Stop valves checked for ease of operation and shut-off. 73 Main valves checked for ease of operation and shut-off. Inspection Test Report 74 Hose reel runs out correctly. M20A Area Completion 75 Hose free from damage and kinks. MERAPUH-A PRODUCTION TOPSIDE 76 Hose nozzle (MEPA) operation and shut-off checked. 77 Hose reel rewind satisfactorily. FACILITIES 78 Painting , Coatings and Fireproofing Correct paint system applied according to specification and in accordance with supplier 79 requirements ObjectID: MEPA-BL-7100 Description: BOAT LANDING 80 All specified adhesion tests completed and accepted System: 71 - STRUCTURAL Sub System: 71E - BOAT LANDING 81 All remedial work completed and accepted 71E01 Area: 82 Package: Finish paint colour conforms to specification 83 84 85 86 All paintwork clean and undamaged Fireproofing materials applied according to specification Fireproofing material finish conforms to agreed sample (where applicable) All Fireproofing clean and undamaged

OE:335707679

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

197/4

OE:335707679

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1673674738

ObjectID: MEPA-GB-5110 System: 51 - SERVICE WATER SYSTEM Package: 51A01 C&E No: Service: Service Water Pump P-5110 RUN/STOP STATUS Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: Sub System: 51A - T-5110 SERVICE WATER CAISSON/PUMP Area: LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

198/4

OE:-1673674738

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:497631589

ObjectID: MEPA-GD-8026 System: 80 - FIRE & GAS DETECTION Package: 80E02 C&E No: Service: Gas Detector at Cellar Deck Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: IR - POINT TYPE GAS DETECTOR - Cellar Deck Sub System: 80E - FIRE ZONE 4 Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

199/4

OE:497631589

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1571373406

ObjectID: MEPA-GD-8027 System: 80 - FIRE & GAS DETECTION Package: 80E02 C&E No: Service: Gas Detector at Cellar Deck Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: IR - POINT TYPE GAS DETECTOR - Cellar Deck Sub System: 80E - FIRE ZONE 4 Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

200/4

OE:1571373406

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:985257494

ObjectID: MEPA-GSC-3210 System: 32 - CONDENSATE METERING Package: 32A01 C&E No: Service: MEPA-XV-3210 - Allocation Condensate Meter Duty Run Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

LIMIT SWITCH CLOSE - MEPA-XV-3210 - Allocation Description: Condensate Meter Duty Run Sub System: Area: LoopNo: 32A - A-3200 CONDENSATE ALLOCATION METERING

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

201/4

OE:985257494

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:989713942

ObjectID: MEPA-GSC-3211 System: 32 - CONDENSATE METERING Package: 32A01 C&E No: Service: MEPA-XV-3211 - Allocation Condensate Meter Duty Run Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

LIMIT SWITCH CLOSE - MEPAXV-3211 - Allocation Description: Condensate Meter Duty Run Sub System: Area: LoopNo: 32A - A-3200 CONDENSATE ALLOCATION METERING

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

202/4

OE:989713942

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:985257782

ObjectID: MEPA-GSC-3220 System: 32 - CONDENSATE METERING Package: 32A01 C&E No: Service: MEPA-XV-3220-Allocation Condensate Meter Standby Run Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

LIMIT SWITCH CLOSE - MEPA-XV-3220-Allocation Description: Condensate Meter Standby Run Sub System: Area: LoopNo: 32A - A-3200 CONDENSATE ALLOCATION METERING

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

203/4

OE:985257782

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:989714230

ObjectID: MEPA-GSC-3221 System: 32 - CONDENSATE METERING Package: 32A01 C&E No: Service: MEPA-XV-3221-Allocation Condensate Meter Standby Run Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

LIMIT SWITCH CLOSE - MEPA-XV-3221-Allocation Description: Condensate Meter Standby Run Sub System: Area: LoopNo: 32A - A-3200 CONDENSATE ALLOCATION METERING

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

204/4

OE:989714230

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:28956182

ObjectID: MEPA-GSO-3210 System: 32 - CONDENSATE METERING Package: 32A01 C&E No: Service: MEPA-XV-3210 - Allocation Condensate Meter Duty Run Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

LIMIT SWITCH OPEN - MEPA-XV-3210 - Allocation Description: Condensate Meter Duty Run Sub System: Area: LoopNo: 32A - A-3200 CONDENSATE ALLOCATION METERING

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

205/4

OE:28956182

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:33412630

ObjectID: MEPA-GSO-3211 System: 32 - CONDENSATE METERING Package: 32A01 C&E No: Service: MEPA-XV-3211 - Allocation Condensate Meter Duty Run Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

LIMIT SWITCH OPEN - MEPA-XV-3211 - Allocation Description: Condensate Meter Duty Run Sub System: Area: LoopNo: 32A - A-3200 CONDENSATE ALLOCATION METERING

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

206/4

OE:33412630

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:28956470

ObjectID: MEPA-GSO-3220 System: 32 - CONDENSATE METERING Package: 32A01 C&E No: Service: MEPA-XV-3220-Allocation Condensate Meter Standby Run Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

LIMIT SWITCH OPEN - MEPA-XV-3220-Allocation Description: Condensate Meter Standby Run Sub System: Area: LoopNo: 32A - A-3200 CONDENSATE ALLOCATION METERING

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

207/4

OE:28956470

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:33412918

ObjectID: MEPA-GSO-3221 System: 32 - CONDENSATE METERING Package: 32A01 C&E No: Service: MEPA-XV-3222-Allocation Condensate Meter Standby Run Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

LIMIT SWITCH OPEN - MEPA-XV-3222-Allocation Description: Condensate Meter Standby Run Sub System: Area: LoopNo: 32A - A-3200 CONDENSATE ALLOCATION METERING

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC Commissioning

208/4

OE:33412918

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-874538855

ObjectID: MEPA-HCV-0111 System: 01 - WELLHEADS & FLOWLINES Package: 01B03 Item 01

CHOKE VALVE - Gas Wellhead MEPA-WH-0110 Description: Gas Flowline Sub System: 01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINE Area: NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

209/4

OE:-874538855

Inspection Test Report I03A Valve and Ancillaries MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1948280700

ObjectID: MEPA-HCV-0111 System: 01 - WELLHEADS & FLOWLINES Package: 01B03 Item 01

CHOKE VALVE - Gas Wellhead MEPA-WH-0110 Description: Gas Flowline Sub System: 01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINE Area: NA OK PL Output /Remarks

Description All equipment free from damage and installed correctly All equipment to be checked for correctness against current revision of data sheet for: 02 Manufacturer, Type, Model No. and Serial No. 02.01 VALVE 02.02 - Serial No : ______________________ 02.03 - Model / type : ______________________ 02.04 - Size 02.05 - Rating 02.06 - Flange type 02.07 - Service 02.08 - Material certification correct 02.09 - Body material 02.10 - Trim material correct 02.11 - Leakage class 02.12 ACTUATOR 02.13 - Serial No : ______________________ 02.14 - Model / type : ______________________ 02.15 - Input range 02.16 - Failure action 02.17 - Hand wheel operation correct 02.18 POSITIONER 02.19 - Serial No : ______________________ 02.20 - Model / type : ______________________ 02.21 - Signal range 02.22 - Output range 02.23 I/P CONVERTER 02.24 - Serial No : ______________________ 02.25 - Model / type : ______________________ 02.26 - Signal range 02.27 - Output range 02.28 FILTER/REGULATOR 02.29 - Serial No : ______________________ 02.30 - Model / type : ______________________ 02.31 - Range 02.32 MISCELLANEOUS ACCESSORIES 02.33 - Correct to Data Sheet Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

210/4

OE:-1948280700

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-874538567

ObjectID: MEPA-HCV-0121 System: 01 - WELLHEADS & FLOWLINES Package: 01C03 Item 01

CHOKE VALVE - Gas Wellhead MEPA-WH-0120 Description: Gas Flowline Sub System: 01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINE Area: NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

211/4

OE:-874538567

Inspection Test Report I03A Valve and Ancillaries MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1948280412

ObjectID: MEPA-HCV-0121 System: 01 - WELLHEADS & FLOWLINES Package: 01C03 Item 01

CHOKE VALVE - Gas Wellhead MEPA-WH-0120 Description: Gas Flowline Sub System: 01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINE Area: NA OK PL Output /Remarks

Description All equipment free from damage and installed correctly All equipment to be checked for correctness against current revision of data sheet for: 02 Manufacturer, Type, Model No. and Serial No. 02.01 VALVE 02.02 - Serial No : ______________________ 02.03 - Model / type : ______________________ 02.04 - Size 02.05 - Rating 02.06 - Flange type 02.07 - Service 02.08 - Material certification correct 02.09 - Body material 02.10 - Trim material correct 02.11 - Leakage class 02.12 ACTUATOR 02.13 - Serial No : ______________________ 02.14 - Model / type : ______________________ 02.15 - Input range 02.16 - Failure action 02.17 - Hand wheel operation correct 02.18 POSITIONER 02.19 - Serial No : ______________________ 02.20 - Model / type : ______________________ 02.21 - Signal range 02.22 - Output range 02.23 I/P CONVERTER 02.24 - Serial No : ______________________ 02.25 - Model / type : ______________________ 02.26 - Signal range 02.27 - Output range 02.28 FILTER/REGULATOR 02.29 - Serial No : ______________________ 02.30 - Model / type : ______________________ 02.31 - Range 02.32 MISCELLANEOUS ACCESSORIES 02.33 - Correct to Data Sheet Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

212/4

OE:-1948280412

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-874537239

ObjectID: MEPA-HCV-0131 System: 01 - WELLHEADS & FLOWLINES Package: 01D03 Item 01

CHOKE VALVE - Gas Wellhead MEPA-WH-0130 Description: Gas Flowline Sub System: 01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINE Area: NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

213/4

OE:-874537239

Inspection Test Report I03A Valve and Ancillaries MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1948279052

ObjectID: MEPA-HCV-0131 System: 01 - WELLHEADS & FLOWLINES Package: 01D03 Item 01

CHOKE VALVE - Gas Wellhead MEPA-WH-0130 Description: Gas Flowline Sub System: 01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINE Area: NA OK PL Output /Remarks

Description All equipment free from damage and installed correctly All equipment to be checked for correctness against current revision of data sheet for: 02 Manufacturer, Type, Model No. and Serial No. 02.01 VALVE 02.02 - Serial No : ______________________ 02.03 - Model / type : ______________________ 02.04 - Size 02.05 - Rating 02.06 - Flange type 02.07 - Service 02.08 - Material certification correct 02.09 - Body material 02.10 - Trim material correct 02.11 - Leakage class 02.12 ACTUATOR 02.13 - Serial No : ______________________ 02.14 - Model / type : ______________________ 02.15 - Input range 02.16 - Failure action 02.17 - Hand wheel operation correct 02.18 POSITIONER 02.19 - Serial No : ______________________ 02.20 - Model / type : ______________________ 02.21 - Signal range 02.22 - Output range 02.23 I/P CONVERTER 02.24 - Serial No : ______________________ 02.25 - Model / type : ______________________ 02.26 - Signal range 02.27 - Output range 02.28 FILTER/REGULATOR 02.29 - Serial No : ______________________ 02.30 - Model / type : ______________________ 02.31 - Range 02.32 MISCELLANEOUS ACCESSORIES 02.33 - Correct to Data Sheet Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

214/4

OE:-1948279052

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-874537207

ObjectID: MEPA-HCV-0141 System: 01 - WELLHEADS & FLOWLINES Package: 01E03 Item 01

Description: Gas Wellhead MEPA-WH-0140 Gas Flowline Sub System: 01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINE Area: NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

215/4

OE:-874537207

Inspection Test Report I03A Valve and Ancillaries MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1948279020

ObjectID: MEPA-HCV-0141 System: 01 - WELLHEADS & FLOWLINES Package: 01E03 Item 01

Description: Gas Wellhead MEPA-WH-0140 Gas Flowline Sub System: 01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINE Area: NA OK PL Output /Remarks

Description All equipment free from damage and installed correctly All equipment to be checked for correctness against current revision of data sheet for: 02 Manufacturer, Type, Model No. and Serial No. 02.01 VALVE 02.02 - Serial No : ______________________ 02.03 - Model / type : ______________________ 02.04 - Size 02.05 - Rating 02.06 - Flange type 02.07 - Service 02.08 - Material certification correct 02.09 - Body material 02.10 - Trim material correct 02.11 - Leakage class 02.12 ACTUATOR 02.13 - Serial No : ______________________ 02.14 - Model / type : ______________________ 02.15 - Input range 02.16 - Failure action 02.17 - Hand wheel operation correct 02.18 POSITIONER 02.19 - Serial No : ______________________ 02.20 - Model / type : ______________________ 02.21 - Signal range 02.22 - Output range 02.23 I/P CONVERTER 02.24 - Serial No : ______________________ 02.25 - Model / type : ______________________ 02.26 - Signal range 02.27 - Output range 02.28 FILTER/REGULATOR 02.29 - Serial No : ______________________ 02.30 - Model / type : ______________________ 02.31 - Range 02.32 MISCELLANEOUS ACCESSORIES 02.33 - Correct to Data Sheet Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

216/4

OE:-1948279020

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-874537943

ObjectID: MEPA-HCV-0151 System: 01 - WELLHEADS & FLOWLINES Package: 01F03 Item 01

Description: Gas Wellhead MEPA-WH-0150 Gas Flowline Sub System: 01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINE Area: NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

217/4

OE:-874537943

Inspection Test Report I03A Valve and Ancillaries MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1948279756

ObjectID: MEPA-HCV-0151 System: 01 - WELLHEADS & FLOWLINES Package: 01F03 Item 01

Description: Gas Wellhead MEPA-WH-0150 Gas Flowline Sub System: 01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINE Area: NA OK PL Output /Remarks

Description All equipment free from damage and installed correctly All equipment to be checked for correctness against current revision of data sheet for: 02 Manufacturer, Type, Model No. and Serial No. 02.01 VALVE 02.02 - Serial No : ______________________ 02.03 - Model / type : ______________________ 02.04 - Size 02.05 - Rating 02.06 - Flange type 02.07 - Service 02.08 - Material certification correct 02.09 - Body material 02.10 - Trim material correct 02.11 - Leakage class 02.12 ACTUATOR 02.13 - Serial No : ______________________ 02.14 - Model / type : ______________________ 02.15 - Input range 02.16 - Failure action 02.17 - Hand wheel operation correct 02.18 POSITIONER 02.19 - Serial No : ______________________ 02.20 - Model / type : ______________________ 02.21 - Signal range 02.22 - Output range 02.23 I/P CONVERTER 02.24 - Serial No : ______________________ 02.25 - Model / type : ______________________ 02.26 - Signal range 02.27 - Output range 02.28 FILTER/REGULATOR 02.29 - Serial No : ______________________ 02.30 - Model / type : ______________________ 02.31 - Range 02.32 MISCELLANEOUS ACCESSORIES 02.33 - Correct to Data Sheet Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

218/4

OE:-1948279756

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-874537639

ObjectID: MEPA-HCV-0161 System: 01 - WELLHEADS & FLOWLINES Package: 01G03 Item 01

Description: Gas Wellhead MEPA-WH-0160 Gas Flowline Sub System: 01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINE Area: NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

219/4

OE:-874537639

Inspection Test Report I03A Valve and Ancillaries MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1948279484

ObjectID: MEPA-HCV-0161 System: 01 - WELLHEADS & FLOWLINES Package: 01G03 Item 01

Description: Gas Wellhead MEPA-WH-0160 Gas Flowline Sub System: 01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINE Area: NA OK PL Output /Remarks

Description All equipment free from damage and installed correctly All equipment to be checked for correctness against current revision of data sheet for: 02 Manufacturer, Type, Model No. and Serial No. 02.01 VALVE 02.02 - Serial No : ______________________ 02.03 - Model / type : ______________________ 02.04 - Size 02.05 - Rating 02.06 - Flange type 02.07 - Service 02.08 - Material certification correct 02.09 - Body material 02.10 - Trim material correct 02.11 - Leakage class 02.12 ACTUATOR 02.13 - Serial No : ______________________ 02.14 - Model / type : ______________________ 02.15 - Input range 02.16 - Failure action 02.17 - Hand wheel operation correct 02.18 POSITIONER 02.19 - Serial No : ______________________ 02.20 - Model / type : ______________________ 02.21 - Signal range 02.22 - Output range 02.23 I/P CONVERTER 02.24 - Serial No : ______________________ 02.25 - Model / type : ______________________ 02.26 - Signal range 02.27 - Output range 02.28 FILTER/REGULATOR 02.29 - Serial No : ______________________ 02.30 - Model / type : ______________________ 02.31 - Range 02.32 MISCELLANEOUS ACCESSORIES 02.33 - Correct to Data Sheet Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

220/4

OE:-1948279484

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-874540151

ObjectID: MEPA-HCV-0171 System: 01 - WELLHEADS & FLOWLINES Package: 01H03 Item 01

CHOKE VALVE - Gas Wellhead MEPA-WH-0170 Description: Gas Flowline Sub System: 01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINE Area: NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

221/4

OE:-874540151

Inspection Test Report I03A Valve and Ancillaries MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1948281964

ObjectID: MEPA-HCV-0171 System: 01 - WELLHEADS & FLOWLINES Package: 01H03 Item 01

CHOKE VALVE - Gas Wellhead MEPA-WH-0170 Description: Gas Flowline Sub System: 01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINE Area: NA OK PL Output /Remarks

Description All equipment free from damage and installed correctly All equipment to be checked for correctness against current revision of data sheet for: 02 Manufacturer, Type, Model No. and Serial No. 02.01 VALVE 02.02 - Serial No : ______________________ 02.03 - Model / type : ______________________ 02.04 - Size 02.05 - Rating 02.06 - Flange type 02.07 - Service 02.08 - Material certification correct 02.09 - Body material 02.10 - Trim material correct 02.11 - Leakage class 02.12 ACTUATOR 02.13 - Serial No : ______________________ 02.14 - Model / type : ______________________ 02.15 - Input range 02.16 - Failure action 02.17 - Hand wheel operation correct 02.18 POSITIONER 02.19 - Serial No : ______________________ 02.20 - Model / type : ______________________ 02.21 - Signal range 02.22 - Output range 02.23 I/P CONVERTER 02.24 - Serial No : ______________________ 02.25 - Model / type : ______________________ 02.26 - Signal range 02.27 - Output range 02.28 FILTER/REGULATOR 02.29 - Serial No : ______________________ 02.30 - Model / type : ______________________ 02.31 - Range 02.32 MISCELLANEOUS ACCESSORIES 02.33 - Correct to Data Sheet Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

222/4

OE:-1948281964

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-874540887

ObjectID: MEPA-HCV-0181 System: 01 - WELLHEADS & FLOWLINES Package: 01I03 Item 01

CHOKE VALVE - Gas Wellhead MEPA-WH-0180 Description: Gas Flowline Sub System: 01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINE Area: NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

223/4

OE:-874540887

Inspection Test Report I03A Valve and Ancillaries MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1948282700

ObjectID: MEPA-HCV-0181 System: 01 - WELLHEADS & FLOWLINES Package: 01I03 Item 01

CHOKE VALVE - Gas Wellhead MEPA-WH-0180 Description: Gas Flowline Sub System: 01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINE Area: NA OK PL Output /Remarks

Description All equipment free from damage and installed correctly All equipment to be checked for correctness against current revision of data sheet for: 02 Manufacturer, Type, Model No. and Serial No. 02.01 VALVE 02.02 - Serial No : ______________________ 02.03 - Model / type : ______________________ 02.04 - Size 02.05 - Rating 02.06 - Flange type 02.07 - Service 02.08 - Material certification correct 02.09 - Body material 02.10 - Trim material correct 02.11 - Leakage class 02.12 ACTUATOR 02.13 - Serial No : ______________________ 02.14 - Model / type : ______________________ 02.15 - Input range 02.16 - Failure action 02.17 - Hand wheel operation correct 02.18 POSITIONER 02.19 - Serial No : ______________________ 02.20 - Model / type : ______________________ 02.21 - Signal range 02.22 - Output range 02.23 I/P CONVERTER 02.24 - Serial No : ______________________ 02.25 - Model / type : ______________________ 02.26 - Signal range 02.27 - Output range 02.28 FILTER/REGULATOR 02.29 - Serial No : ______________________ 02.30 - Model / type : ______________________ 02.31 - Range 02.32 MISCELLANEOUS ACCESSORIES 02.33 - Correct to Data Sheet Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

224/4

OE:-1948282700

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-874540599

ObjectID: MEPA-HCV-0191 System: 01 - WELLHEADS & FLOWLINES Package: 01J03 Item 01

CHOKE VALVE - Gas Wellhead MEPA-WH-0190 Description: Gas Flowline Sub System: 01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINE Area: NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:09, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

225/4

OE:-874540599

Inspection Test Report I03A Valve and Ancillaries MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1948282412

ObjectID: MEPA-HCV-0191 System: 01 - WELLHEADS & FLOWLINES Package: 01J03 Item 01

CHOKE VALVE - Gas Wellhead MEPA-WH-0190 Description: Gas Flowline Sub System: 01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINE Area: NA OK PL Output /Remarks

Description All equipment free from damage and installed correctly All equipment to be checked for correctness against current revision of data sheet for: 02 Manufacturer, Type, Model No. and Serial No. 02.01 VALVE 02.02 - Serial No : ______________________ 02.03 - Model / type : ______________________ 02.04 - Size 02.05 - Rating 02.06 - Flange type 02.07 - Service 02.08 - Material certification correct 02.09 - Body material 02.10 - Trim material correct 02.11 - Leakage class 02.12 ACTUATOR 02.13 - Serial No : ______________________ 02.14 - Model / type : ______________________ 02.15 - Input range 02.16 - Failure action 02.17 - Hand wheel operation correct 02.18 POSITIONER 02.19 - Serial No : ______________________ 02.20 - Model / type : ______________________ 02.21 - Signal range 02.22 - Output range 02.23 I/P CONVERTER 02.24 - Serial No : ______________________ 02.25 - Model / type : ______________________ 02.26 - Signal range 02.27 - Output range 02.28 FILTER/REGULATOR 02.29 - Serial No : ______________________ 02.30 - Model / type : ______________________ 02.31 - Range 02.32 MISCELLANEOUS ACCESSORIES 02.33 - Correct to Data Sheet Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

226/4

OE:-1948282412

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-889218375

ObjectID: MEPA-HCV-0201 System: 01 - WELLHEADS & FLOWLINES Package: 01K03 Item 01

CHOKE VALVE - Gas Wellhead MEPA-WH-0200 Description: Gas Flowline Sub System: 01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINE Area: NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

227/4

OE:-889218375

Inspection Test Report I03A Valve and Ancillaries MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1962960220

ObjectID: MEPA-HCV-0201 System: 01 - WELLHEADS & FLOWLINES Package: 01K03 Item 01

CHOKE VALVE - Gas Wellhead MEPA-WH-0200 Description: Gas Flowline Sub System: 01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINE Area: NA OK PL Output /Remarks

Description All equipment free from damage and installed correctly All equipment to be checked for correctness against current revision of data sheet for: 02 Manufacturer, Type, Model No. and Serial No. 02.01 VALVE 02.02 - Serial No : ______________________ 02.03 - Model / type : ______________________ 02.04 - Size 02.05 - Rating 02.06 - Flange type 02.07 - Service 02.08 - Material certification correct 02.09 - Body material 02.10 - Trim material correct 02.11 - Leakage class 02.12 ACTUATOR 02.13 - Serial No : ______________________ 02.14 - Model / type : ______________________ 02.15 - Input range 02.16 - Failure action 02.17 - Hand wheel operation correct 02.18 POSITIONER 02.19 - Serial No : ______________________ 02.20 - Model / type : ______________________ 02.21 - Signal range 02.22 - Output range 02.23 I/P CONVERTER 02.24 - Serial No : ______________________ 02.25 - Model / type : ______________________ 02.26 - Signal range 02.27 - Output range 02.28 FILTER/REGULATOR 02.29 - Serial No : ______________________ 02.30 - Model / type : ______________________ 02.31 - Range 02.32 MISCELLANEOUS ACCESSORIES 02.33 - Correct to Data Sheet Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

228/4

OE:-1962960220

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-889218919

ObjectID: MEPA-HCV-0211 System: 01 - WELLHEADS & FLOWLINES Package: 01L03 Item 01

CHOKE VALVE - Gas Wellhead MEPA-WH-0210 Description: Gas Flowline Sub System: 01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINE Area: NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

229/4

OE:-889218919

Inspection Test Report I03A Valve and Ancillaries MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1962960764

ObjectID: MEPA-HCV-0211 System: 01 - WELLHEADS & FLOWLINES Package: 01L03 Item 01

CHOKE VALVE - Gas Wellhead MEPA-WH-0210 Description: Gas Flowline Sub System: 01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINE Area: NA OK PL Output /Remarks

Description All equipment free from damage and installed correctly All equipment to be checked for correctness against current revision of data sheet for: 02 Manufacturer, Type, Model No. and Serial No. 02.01 VALVE 02.02 - Serial No : ______________________ 02.03 - Model / type : ______________________ 02.04 - Size 02.05 - Rating 02.06 - Flange type 02.07 - Service 02.08 - Material certification correct 02.09 - Body material 02.10 - Trim material correct 02.11 - Leakage class 02.12 ACTUATOR 02.13 - Serial No : ______________________ 02.14 - Model / type : ______________________ 02.15 - Input range 02.16 - Failure action 02.17 - Hand wheel operation correct 02.18 POSITIONER 02.19 - Serial No : ______________________ 02.20 - Model / type : ______________________ 02.21 - Signal range 02.22 - Output range 02.23 I/P CONVERTER 02.24 - Serial No : ______________________ 02.25 - Model / type : ______________________ 02.26 - Signal range 02.27 - Output range 02.28 FILTER/REGULATOR 02.29 - Serial No : ______________________ 02.30 - Model / type : ______________________ 02.31 - Range 02.32 MISCELLANEOUS ACCESSORIES 02.33 - Correct to Data Sheet Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

230/4

OE:-1962960764

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-889218631

ObjectID: MEPA-HCV-0221 System: 01 - WELLHEADS & FLOWLINES Package: 01M03 Item 01

CHOKE VALVE - Gas Wellhead MEPA-WH-0220 Description: Gas Flowline Sub System: Area: NA OK PL Output /Remarks 01M - WELLHEAD WH-0220 (SLOT 12) & FLOWLINE

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

231/4

OE:-889218631

Inspection Test Report I03A Valve and Ancillaries MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1962960476

ObjectID: MEPA-HCV-0221 System: 01 - WELLHEADS & FLOWLINES Package: 01M03 Item 01

CHOKE VALVE - Gas Wellhead MEPA-WH-0220 Description: Gas Flowline Sub System: Area: NA OK PL Output /Remarks 01M - WELLHEAD WH-0220 (SLOT 12) & FLOWLINE

Description All equipment free from damage and installed correctly All equipment to be checked for correctness against current revision of data sheet for: 02 Manufacturer, Type, Model No. and Serial No. 02.01 VALVE 02.02 - Serial No : ______________________ 02.03 - Model / type : ______________________ 02.04 - Size 02.05 - Rating 02.06 - Flange type 02.07 - Service 02.08 - Material certification correct 02.09 - Body material 02.10 - Trim material correct 02.11 - Leakage class 02.12 ACTUATOR 02.13 - Serial No : ______________________ 02.14 - Model / type : ______________________ 02.15 - Input range 02.16 - Failure action 02.17 - Hand wheel operation correct 02.18 POSITIONER 02.19 - Serial No : ______________________ 02.20 - Model / type : ______________________ 02.21 - Signal range 02.22 - Output range 02.23 I/P CONVERTER 02.24 - Serial No : ______________________ 02.25 - Model / type : ______________________ 02.26 - Signal range 02.27 - Output range 02.28 FILTER/REGULATOR 02.29 - Serial No : ______________________ 02.30 - Model / type : ______________________ 02.31 - Range 02.32 MISCELLANEOUS ACCESSORIES 02.33 - Correct to Data Sheet Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

232/4

OE:-1962960476

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:478137062

ObjectID: MEPA-HY-0111 System: 01 - WELLHEADS & FLOWLINES Package: 01B03 C&E No: Service: For MEPA-HCV-0111 - Gas Wellhead MEPA-WH-0110 Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

I/P POSITIONER - For MEPA-HCV-0111 - Gas Description: Wellhead MEPA-WH-0110 Sub System: 01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINE Area: LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

233/4

OE:478137062

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:125821927

ObjectID: MEPA-HY-0111 System: 01 - WELLHEADS & FLOWLINES Package: 01B03 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

I/P POSITIONER - For MEPA-HCV-0111 - Gas Description: Wellhead MEPA-WH-0110 Sub System: 01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINE Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

234/4

OE:125821927

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:477842150

ObjectID: MEPA-HY-0121 System: 01 - WELLHEADS & FLOWLINES Package: 01C03 C&E No: Service: For MEPA-HCV-0121 - Gas Wellhead MEPA-WH-0120 Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

I/P POSITIONER - For MEPA-HCV-0121 - Gas Description: Wellhead MEPA-WH-0120 Sub System: 01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINE Area: LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

235/4

OE:477842150

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:125527015

ObjectID: MEPA-HY-0121 System: 01 - WELLHEADS & FLOWLINES Package: 01C03 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

I/P POSITIONER - For MEPA-HCV-0121 - Gas Description: Wellhead MEPA-WH-0120 Sub System: 01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINE Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

236/4

OE:125527015

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:476449510

ObjectID: MEPA-HY-0131 System: 01 - WELLHEADS & FLOWLINES Package: 01D03 C&E No: Service: For MEPA-HCV-0131 - Gas Wellhead MEPA-WH-0130 Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

I/P POSITIONER - For MEPA-HCV-0131 - Gas Description: Wellhead MEPA-WH-0130 Sub System: 01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINE Area: LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

237/4

OE:476449510

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:124134375

ObjectID: MEPA-HY-0131 System: 01 - WELLHEADS & FLOWLINES Package: 01D03 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

I/P POSITIONER - For MEPA-HCV-0131 - Gas Description: Wellhead MEPA-WH-0130 Sub System: 01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINE Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

238/4

OE:124134375

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:476154598

ObjectID: MEPA-HY-0141 System: 01 - WELLHEADS & FLOWLINES Package: 01E03 C&E No: Service: For MEPA-HCV-0141 - Gas Wellhead MEPA-WH-0140 Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

I/P POSITIONER - For MEPA-HCV-0141 - Gas Description: Wellhead MEPA-WH-0140 Sub System: 01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINE Area: LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

239/4

OE:476154598

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:123839463

ObjectID: MEPA-HY-0141 System: 01 - WELLHEADS & FLOWLINES Package: 01E03 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

I/P POSITIONER - For MEPA-HCV-0141 - Gas Description: Wellhead MEPA-WH-0140 Sub System: 01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINE Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

240/4

OE:123839463

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:476908262

ObjectID: MEPA-HY-0151 System: 01 - WELLHEADS & FLOWLINES Package: 01F03 C&E No: Service: For MEPA-HCV-0151 - Gas Wellhead MEPA-WH-0150 Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

I/P POSITIONER - For MEPA-HCV-0151 - Gas Description: Wellhead MEPA-WH-0150 Sub System: 01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINE Area: LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

241/4

OE:476908262

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:124593127

ObjectID: MEPA-HY-0151 System: 01 - WELLHEADS & FLOWLINES Package: 01F03 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

I/P POSITIONER - For MEPA-HCV-0151 - Gas Description: Wellhead MEPA-WH-0150 Sub System: 01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINE Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

242/4

OE:124593127

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:476629734

ObjectID: MEPA-HY-0161 System: 01 - WELLHEADS & FLOWLINES Package: 01G03 C&E No: Service: For MEPA-HCV-0161 - Gas Wellhead MEPA-WH-0160 Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

I/P POSITIONER - For MEPA-HCV-0161 - Gas Description: Wellhead MEPA-WH-0160 Sub System: 01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINE Area: LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

243/4

OE:476629734

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:124314599

ObjectID: MEPA-HY-0161 System: 01 - WELLHEADS & FLOWLINES Package: 01G03 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

I/P POSITIONER - For MEPA-HCV-0161 - Gas Description: Wellhead MEPA-WH-0160 Sub System: 01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINE Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

244/4

OE:124314599

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:475237094

ObjectID: MEPA-HY-0171 System: 01 - WELLHEADS & FLOWLINES Package: 01H03 C&E No: Service: For MEPA-HCV-0171 - Gas Wellhead MEPA-WH-0170 Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

I/P POSITIONER - For MEPA-HCV-0171 - Gas Description: Wellhead MEPA-WH-0170 Sub System: 01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINE Area: LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

245/4

OE:475237094

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:122921959

ObjectID: MEPA-HY-0171 System: 01 - WELLHEADS & FLOWLINES Package: 01H03 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

I/P POSITIONER - For MEPA-HCV-0171 - Gas Description: Wellhead MEPA-WH-0170 Sub System: 01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINE Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

246/4

OE:122921959

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:475990758

ObjectID: MEPA-HY-0181 System: 01 - WELLHEADS & FLOWLINES Package: 01I03 C&E No: Service: For MEPA-HCV-0181 - Gas Wellhead MEPA-WH-0180 Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

I/P POSITIONER - For MEPA-HCV-0181 - Gas Description: Wellhead MEPA-WH-0180 Sub System: 01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINE Area: LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

247/4

OE:475990758

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:123675623

ObjectID: MEPA-HY-0181 System: 01 - WELLHEADS & FLOWLINES Package: 01I03 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

I/P POSITIONER - For MEPA-HCV-0181 - Gas Description: Wellhead MEPA-WH-0180 Sub System: 01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINE Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

248/4

OE:123675623

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:475695846

ObjectID: MEPA-HY-0191 System: 01 - WELLHEADS & FLOWLINES Package: 01J03 C&E No: Service: For MEPA-HCV-0191 - Gas Wellhead MEPA-WH-0190 Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

I/P POSITIONER - For MEPA-HCV-0191 - Gas Description: Wellhead MEPA-WH-0190 Sub System: 01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINE Area: LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

249/4

OE:475695846

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:123380711

ObjectID: MEPA-HY-0191 System: 01 - WELLHEADS & FLOWLINES Package: 01J03 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

I/P POSITIONER - For MEPA-HCV-0191 - Gas Description: Wellhead MEPA-WH-0190 Sub System: 01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINE Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

250/4

OE:123380711

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:477579970

ObjectID: MEPA-HY-0201 System: 01 - WELLHEADS & FLOWLINES Package: 01K03 C&E No: Service: For MEPA-HCV-0201 - Gas Wellhead MEPA-WH-0200 Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

I/P POSITIONER - For MEPA-HCV-0201 - Gas Description: Wellhead MEPA-WH-0200 Sub System: 01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINE Area: LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

251/4

OE:477579970

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:125264835

ObjectID: MEPA-HY-0201 System: 01 - WELLHEADS & FLOWLINES Package: 01K03 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

I/P POSITIONER - For MEPA-HCV-0201 - Gas Description: Wellhead MEPA-WH-0200 Sub System: 01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINE Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

252/4

OE:125264835

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:478137026

ObjectID: MEPA-HY-0211 System: 01 - WELLHEADS & FLOWLINES Package: 01L03 C&E No: Service: For MEPA-HCV-0211 - Gas Wellhead MEPA-WH-0210 Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

I/P POSITIONER - For MEPA-HCV-0211 - Gas Description: Wellhead MEPA-WH-0210 Sub System: 01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINE Area: LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

253/4

OE:478137026

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:125821891

ObjectID: MEPA-HY-0211 System: 01 - WELLHEADS & FLOWLINES Package: 01L03 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

I/P POSITIONER - For MEPA-HCV-0211 - Gas Description: Wellhead MEPA-WH-0210 Sub System: 01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINE Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

254/4

OE:125821891

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:477842114

ObjectID: MEPA-HY-0221 System: 01 - WELLHEADS & FLOWLINES Package: 01M03 C&E No: Service: For MEPA-HCV-0221 - Gas Wellhead MEPA-WH-0220 Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

I/P POSITIONER - For MEPA-HCV-0221 - Gas Description: Wellhead MEPA-WH-0220 Sub System: Area: LoopNo: 01M - WELLHEAD WH-0220 (SLOT 12) & FLOWLINE

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

255/4

OE:477842114

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:125526979

ObjectID: MEPA-HY-0221 System: 01 - WELLHEADS & FLOWLINES Package: 01M03 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

I/P POSITIONER - For MEPA-HCV-0221 - Gas Description: Wellhead MEPA-WH-0220 Sub System: Area: SerialNo: NA OK PL Output /Remarks 01M - WELLHEAD WH-0220 (SLOT 12) & FLOWLINE

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

256/4

OE:125526979

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1849458024

ObjectID: MEPA-LT-6510 System: 65 - OPEN DRAIN Package: 65A02 Manufacturer: Service: OHD Caisson, A-6510 Level Item 01 02 03 04 05 06 Model/Type:

Description: LEVEL TRANSMITTER - OHD Caisson, A-6510 Level Sub System: 65A - T-6510 OPEN DRAINS CAISSON & PUMP Area: SerialNo: NA OK PL Output /Remarks

Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

257/4

OE:-1849458024

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1698444904

ObjectID: MEPA-LT-6510 System: 65 - OPEN DRAIN Package: 65A02 C&E No: Service: OHD Caisson, A-6510 Level Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: LEVEL TRANSMITTER - OHD Caisson, A-6510 Level Sub System: 65A - T-6510 OPEN DRAINS CAISSON & PUMP Area: LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

258/4

OE:-1698444904

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-2117869415

ObjectID: MEPA-LT-6510 System: 65 - OPEN DRAIN Package: 65A02 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: LEVEL TRANSMITTER - OHD Caisson, A-6510 Level Sub System: 65A - T-6510 OPEN DRAINS CAISSON & PUMP Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

259/4

OE:-2117869415

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1849439848

ObjectID: MEPA-LT-6510 System: 65 - OPEN DRAIN Package: 65A02 Manufacturer: Service: OHD Caisson, A-6510 Level Item 01 02 03 04 05 06 07 08 09 Model/Type:

Description: LEVEL TRANSMITTER - OHD Caisson, A-6510 Level Sub System: 65A - T-6510 OPEN DRAINS CAISSON & PUMP Area: SerialNo: NA OK PL Output /Remarks

Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

260/4

OE:-1849439848

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1849435240

ObjectID: MEPA-LT-6510 System: 65 - OPEN DRAIN Package: 65A02 Item 01

Description: LEVEL TRANSMITTER - OHD Caisson, A-6510 Level Sub System: 65A - T-6510 OPEN DRAINS CAISSON & PUMP Area: NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

261/4

OE:-1849435240

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-950454217

ObjectID: MEPA-LZT-4222 System: 42 - PRODUCED WATER TREATMENT Package: 42A01 C&E No: Service: Degassing Vessel, V-4220 Level Trip Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

LEVEL TRANSMITTER - Degassing Vessel, V-4220 Description: Level Trip Sub System: 42A - A-4200 PRODUCED WATER Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

262/4

OE:-950454217

Inspection Test Report M05A Submersible Pump MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-991462951

ObjectID: MEPA-P-5110 System: 51 - SERVICE WATER SYSTEM Package: 51A01 Manufacturer: FLOWSERVE Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14
Notes:

Description: SERVICE WATER PUMP Sub System: 51A - T-5110 SERVICE WATER CAISSON/PUMP Area: Sub-Cellar Deck SerialNo: 110600613 Type: Motor Tag NA OK PL Output /Remarks

Description Nameplate details are in accordance with data sheet. Check equipment is installed to manufacturer's instructions. Motor/pump assembly correct. *W* Confirm suction strainer/mesh fitted. *W* Check and record number of riser spools. Check riser spool faces are undamaged and square. Check riser spool gaskets are to spec. and all fitted. Check riser spool stud bolts are to spec. and all fitted. Check spider restraints are correct to drawing. Check delivery head flange to caisson is secure. Check headroom for spool removal is sufficient. Check Hypochlorite dosing pipework is complete (if fitted) Check motor cable is secure and undamaged. Confirm external lubrication system installed correctly and filled (if fitted)

*W* Commissioning & Client Witness points ______________________________________________________________________________________________________________________ Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

263/4

OE:-991462951

Function Test Report M04B Pumps MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1156020702

ObjectID: MEPA-P-5110 System: 51 - SERVICE WATER SYSTEM Package: 51A01 Manufacturer: FLOWSERVE Item 01 02 03 04 05 06 07 08 09 10 11 12 13
Notes:

Description: SERVICE WATER PUMP Sub System: 51A - T-5110 SERVICE WATER CAISSON/PUMP Area: Sub-Cellar Deck Model: SerialNo: 110600613 NA OK PL Output /Remarks

Description Construction check list completed and no subsequent damage occurred. Preservation removed. Lube/Seal oil systems flushing complete. Lube/Seal oil systems filled with the correct grade of lubricant to full level. *W* Check Lube/Seal oil systems for leaks. Check pump discharge is protected against over pressurisation. Coupling spacer is fitted. All guards are fitted and secure. Air release valve fitted correctly Pump discharge is protected against over pressure. Hypochlorite dosing lines complete, (if fitted) Cooling system complete. Ensure motor direction is correct and clearly marked, and matches direction of rotation of pump *W*

*W* Commissioning & Client Witness points ______________________________________________________________________________________________________________________ Remarks:

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

264/4

OE:1156020702

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-761019664

ObjectID: MEPA-PG-6215 System: 62 - HP FLARE SYSTEM Package: 62D14 Manufacturer: BADOTHERM Model/Type: BDT 21/A Service: Gas Wellhead MEPA-WH-0110 Casing Blowdown Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0110 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck SerialNo:

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

265/4

OE:-761019664

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-761016080

ObjectID: MEPA-PG-6215 System: 62 - HP FLARE SYSTEM Package: 62D14 Item 01

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0110 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

266/4

OE:-761016080

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-760804880

ObjectID: MEPA-PG-6225 System: 62 - HP FLARE SYSTEM Package: 62D15 Manufacturer: Model/Type: Service: Gas Wellhead MEPA-WH-0120 Casing Blowdown Item 01 02 03 04 05 06 Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0120 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: SerialNo:

NA

OK

PL

Output /Remarks

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

267/4

OE:-760804880

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-760790288

ObjectID: MEPA-PG-6225 System: 62 - HP FLARE SYSTEM Package: 62D15 Manufacturer: Model/Type: Service: Gas Wellhead MEPA-WH-0120 Casing Blowdown Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0120 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: SerialNo:

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

268/4

OE:-760790288

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-760786704

ObjectID: MEPA-PG-6225 System: 62 - HP FLARE SYSTEM Package: 62D15 Item 01

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0120 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

269/4

OE:-760786704

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-759561488

ObjectID: MEPA-PG-6235 System: 62 - HP FLARE SYSTEM Package: 62D16 Manufacturer: BADOTHERM Model/Type: ASI 316 Service: Gas Wellhead MEPA-WH-0130 Casing Blowdown Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0130 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck SerialNo:

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

270/4

OE:-759561488

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-759557904

ObjectID: MEPA-PG-6235 System: 62 - HP FLARE SYSTEM Package: 62D16 Item 01

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0130 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

271/4

OE:-759557904

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-759332112

ObjectID: MEPA-PG-6245 System: 62 - HP FLARE SYSTEM Package: 62D17 Manufacturer: BADOTHERM Model/Type: ASI 316 Service: Gas Wellhead MEPA-WH-0140 Casing Blowdown Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0140 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck SerialNo:

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

272/4

OE:-759332112

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-759328528

ObjectID: MEPA-PG-6245 System: 62 - HP FLARE SYSTEM Package: 62D17 Item 01

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0140 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

273/4

OE:-759328528

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-760151312

ObjectID: MEPA-PG-6255 System: 62 - HP FLARE SYSTEM Package: 62D18 Manufacturer: BADOTHERM Model/Type: BDT21/A Service: Gas Wellhead MEPA-WH-0150 Casing Blowdown Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0150 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck SerialNo:

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

274/4

OE:-760151312

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-760147728

ObjectID: MEPA-PG-6255 System: 62 - HP FLARE SYSTEM Package: 62D18 Item 01

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0150 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

275/4

OE:-760147728

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-759905552

ObjectID: MEPA-PG-6265 System: 62 - HP FLARE SYSTEM Package: 62D19 Manufacturer: BADOTHERM Model/Type: ASI 316 Service: Gas Wellhead MEPA-WH-0160 Casing Blowdown Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0160 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck SerialNo:

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

276/4

OE:-759905552

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-759901968

ObjectID: MEPA-PG-6265 System: 62 - HP FLARE SYSTEM Package: 62D19 Item 01

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0160 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

277/4

OE:-759901968

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-762346768

ObjectID: MEPA-PG-6275 System: 62 - HP FLARE SYSTEM Package: 62D20 Manufacturer: BADOTHERM Model/Type: BDT21/A Service: Gas Wellhead MEPA-WH-0170 Casing Blowdown Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0170 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck SerialNo:

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

278/4

OE:-762346768

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-762343184

ObjectID: MEPA-PG-6275 System: 62 - HP FLARE SYSTEM Package: 62D20 Item 01

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0170 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

279/4

OE:-762343184

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-762936592

ObjectID: MEPA-PG-6295 System: 62 - HP FLARE SYSTEM Package: 62D22 Manufacturer: BADOTHERM Model/Type: BDT21/A Service: Gas Wellhead MEPA-WH-0190 Casing Blowdown Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0190 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck SerialNo:

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

280/4

OE:-762936592

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-762933008

ObjectID: MEPA-PG-6295 System: 62 - HP FLARE SYSTEM Package: 62D22 Item 01

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0190 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

281/4

OE:-762933008

Inspection Test Report I05A Instrument Calibration Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-760542950

ObjectID: MEPA-PG-6305 System: 62 - HP FLARE SYSTEM Package: 62D23 Manufacturer: Model/Type: Service: Gas Wellhead MEPA-WH-0200 Casing Blowdown Item 01 02 03 04 05 06 Description Calibrate Instrument as per Data Sheet (refer to table1) Position transmitter/switches (open/closed) operating correctly. Solenoid Valve operating correctly I/P & Positioner operating correctly Miscellaneous equipment operating correctly Valve Stroke Time in accordance with data sheet

Description: PRESSURE GAUGE Sub System: 62D - CASING BLOWDOWN Area: SerialNo:

NA

OK

PL

Output /Remarks

Table 1

_____________________________________________________________________________________________________________________

Record Valve Stroke Time:

Remarks:

_____________________________________________________________________________________________________________________ Test Equipment : Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

282/4

OE:-760542950

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-760528358

ObjectID: MEPA-PG-6305 System: 62 - HP FLARE SYSTEM Package: 62D23 Manufacturer: Model/Type: Service: Gas Wellhead MEPA-WH-0200 Casing Blowdown Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

Description: PRESSURE GAUGE Sub System: 62D - CASING BLOWDOWN Area: SerialNo:

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

283/4

OE:-760528358

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-760524774

ObjectID: MEPA-PG-6305 System: 62 - HP FLARE SYSTEM Package: 62D23 Item 01

Description: PRESSURE GAUGE Sub System: 62D - CASING BLOWDOWN Area: NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

284/4

OE:-760524774

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-763165968

ObjectID: MEPA-PG-6285 System: 62 - HP FLARE SYSTEM Package: 62D21 Manufacturer: BADOTHERM Model/Type: BDT 21/A Service: Gas Wellhead MEPA-WH-0180 Casing Blowdown Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0180 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck SerialNo:

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

285/4

OE:-763165968

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-763162384

ObjectID: MEPA-PG-6285 System: 62 - HP FLARE SYSTEM Package: 62D21 Item 01

PRESSURE GAUGE - Gas Wellhead MEPA-WHDescription: 0180 Casing Blowdown Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

286/4

OE:-763162384

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-761019878

ObjectID: MEPA-PG-6315 System: 62 - HP FLARE SYSTEM Package: 62D24 Manufacturer: BADOTHERM Model/Type: BDT21/A Service: Gas Wellhead MEPA-WH-0210 Casing Blowdown Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

Description: PRESSURE GAUGE Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck SerialNo:

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

287/4

OE:-761019878

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-761016294

ObjectID: MEPA-PG-6315 System: 62 - HP FLARE SYSTEM Package: 62D24 Item 01

Description: PRESSURE GAUGE Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

288/4

OE:-761016294

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-760790502

ObjectID: MEPA-PG-6325 System: 62 - HP FLARE SYSTEM Package: 62D25 Manufacturer: BADOTHERM Model/Type: BDT21/A Service: Gas Wellhead MEPA-WH-0220 Casing Blowdown Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

Description: PRESSURE GAUGE Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck SerialNo:

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

289/4

OE:-760790502

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-760786918

ObjectID: MEPA-PG-6325 System: 62 - HP FLARE SYSTEM Package: 62D25 Item 01

Description: PRESSURE GAUGE Sub System: 62D - CASING BLOWDOWN Area: Cellar Deck NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

290/4

OE:-760786918

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-2104628081

ObjectID: MEPA-PM-5110 System: 51 - SERVICE WATER SYSTEM Package: 51A01 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: Motor - Service Water Pump Motor Sub System: 51A - T-5110 SERVICE WATER CAISSON/PUMP Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

291/4

OE:-2104628081

Inspection Test Report E08A Electric Motor MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1836196210

ObjectID: MEPA-PM-5110 System: 51 - SERVICE WATER SYSTEM Package: 51A01 Manufacturer: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type:

Description: Motor - Service Water Pump Motor Sub System: 51A - T-5110 SERVICE WATER CAISSON/PUMP Area: SerialNo: NA OK PL Output /Remarks

14

15

Description Installation as per AFC Drawing and data sheet Installation conforms to hazardous area classification Confirm all equipment is tagged in accordance with specification Motor and control station are earthed according to drawings Confirm motor shaft rotates freely Check all cable connections/glands are tight and cables are identified Verify terminal box gasket and seals are present and have been installed correctly For motors >= 5.5 kW check anti-condensate heater, confirm element voltage rating is correct, i.e.240V Check unused cable entries have been plugged correctly Confirm equipment mountings are secure and grouting is complete Confirm all guards and covers are installed Check bolts are of correct type and that no bolts are missing Check paintwork is complete Disconnect motor cables test and record insulation resistance value Motor voltage Test voltage <=1Kv 500V Values: L1-E:__________ohm L2-E:__________ohm L3-E:__________ohm For motors >= 1kV See Vendor Recommendations Disconnect heater cable test and record insulation resistance value Heater voltage Test voltage <=240V 500V Values: Element to earth:__________ ohm Reconnect motor power and heater cables as per connection diagram Where applicable visually inspect and confirm no damage to local devices: i.e. Temperature indicators/detectors and Vibration switches

16 17

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

292/4

OE:-1836196210

Function Test Report E08B Electric Motor MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1718755698

ObjectID: MEPA-PM-5110 System: 51 - SERVICE WATER SYSTEM Package: 51A01 Manufacturer: Item 01 02

Description: Motor - Service Water Pump Motor Sub System: 51A - T-5110 SERVICE WATER CAISSON/PUMP Area:

Description Erect safety barriers and warning signs in and around test areas Confirm motor feeder cubicle is isolated and locked out Check cable is at zero potential, disconnect motor cables, test and record motor insulation resistance value Motor voltage <=1kV Record values: L1-E: ______(ohm) Test voltage 500V L2-E: ______(ohm) L3-E: ______(ohm)

NA

OK

PL

Output /Remarks

03

04

For motors > 1kV See Vendor Recommendations Measure resistance between phases L1-L2: ______(ohm) L1-L3: ______(ohm)

L2-L3: ______(ohm)

Disconnect heater cable, test and record insulation resistance value 05 Heater voltage Test voltage <=240V 500V Element to earth: ___________(ohm) Reconnect power and heater cables as per connection diagram, for HV motors ensure torque settings are as per vendor requirements Confirm anti condensate heater is functioning Confirm motor is uncoupled from driven device and reinstate motor guard If applicable test RTD's and vibration switches Remove isolation from motor feeder Confirm functionality of local controls and emergency stop "Bump" motor and confirm correct direction of rotation, if a direction change is required this is to be affected where practical within the motor terminal box Uncoupled Motor Run Noise checks, shall be checked at a height if 1mtr above ground level and at both 3 mtrs and 6 mtrs from the drive, in accordance with relevant standards and codes or practice. Perform no load run and record line amps (refer to Table 1) L1: ______ A L2: ______ A L3: ______ A 15 16 17 Mechanicals to reinstate motor and driven device coupling (M06B item 14) In conjunction with mechanical and process run motor "on load" and record line amps (refer to Table 2) L1: ______ A L2: ______ A L3: ______ A For motorised valves confirm operation of limit switches and indicators

06 07 08 09 10 11 12

13

Notes: 1. All switching and testing of equipment is to be carried out in accordance with the BDEWC / Client electrical safety rules and operating procedures 2. All relevant ITRs and FTRs to be complete prior to commissioning 3. All test durations and acceptable values to be as per vendor recommendations 4. All directly connected motors to be commissioned in conjunction with vendor

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

293/4

OE:-1718755698

Function Test Report E08B Electric Motor MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1718755698

ObjectID: MEPA-PM-5110 System: 51 - SERVICE WATER SYSTEM Package: 51A01


Table 1 - Uncoupled Motor Run

Description: Motor - Service Water Pump Motor Sub System: 51A - T-5110 SERVICE WATER CAISSON/PUMP Area:

Table 2 - Coupled Motor Run

______________________________________________________________________________________________________________________ Remarks:

______________________________________________________________________________________________________________________ Test Equipment:

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

294/4

OE:-1718755698

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1994257559

ObjectID: MEPA-PSL-0111 System: 01 - WELLHEADS & FLOWLINES Package: 01B02 C&E No: Service: SCSSV-0111 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SCSSV-0111 Open/Closed Description: Status Sub System: 01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

295/4

OE:1994257559

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1996092567

ObjectID: MEPA-PSL-0112 System: 01 - WELLHEADS & FLOWLINES Package: 01B02 C&E No: Service: SSV-0112 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SSV-0112 Open/Closed Description: Status Sub System: 01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

296/4

OE:1996092567

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1981019287

ObjectID: MEPA-PSL-0113 System: 01 - WELLHEADS & FLOWLINES Package: 01B02 C&E No: Service: WV-0113 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - WV-0113 Open/Closed Description: Status Sub System: 01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

297/4

OE:1981019287

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1994257847

ObjectID: MEPA-PSL-0121 System: 01 - WELLHEADS & FLOWLINES Package: 01C02 C&E No: Service: SCSSV-0121 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SCSSV-0121 Open/Closed Description: Status Sub System: 01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

298/4

OE:1994257847

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1996092855

ObjectID: MEPA-PSL-0122 System: 01 - WELLHEADS & FLOWLINES Package: 01C02 C&E No: Service: SSV-0122 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SSV-0122 Open/Closed Description: Status Sub System: 01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

299/4

OE:1996092855

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1981019575

ObjectID: MEPA-PSL-0123 System: 01 - WELLHEADS & FLOWLINES Package: 01C02 C&E No: Service: WV-0123 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - WV-0123 Open/Closed Description: Status Sub System: 01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

300/4

OE:1981019575

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1994257127

ObjectID: MEPA-PSL-0131 System: 01 - WELLHEADS & FLOWLINES Package: 01D02 C&E No: Service: SCSSV-0131 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SCSSV-0131 Open/Closed Description: Status Sub System: 01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

301/4

OE:1994257127

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1996092135

ObjectID: MEPA-PSL-0132 System: 01 - WELLHEADS & FLOWLINES Package: 01D02 C&E No: Service: SSV-0132 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SSV-0132 Open/Closed Description: Status Sub System: 01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

302/4

OE:1996092135

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1981018855

ObjectID: MEPA-PSL-0133 System: 01 - WELLHEADS & FLOWLINES Package: 01D02 C&E No: Service: WV-0133 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - WV-0133 Open/Closed Description: Status Sub System: 01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

303/4

OE:1981018855

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1994257159

ObjectID: MEPA-PSL-0141 System: 01 - WELLHEADS & FLOWLINES Package: 01E02 C&E No: Service: SCSSV-0141 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SCSSV-0141 Open/Closed Description: Status Sub System: 01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

304/4

OE:1994257159

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1996092167

ObjectID: MEPA-PSL-0142 System: 01 - WELLHEADS & FLOWLINES Package: 01E02 C&E No: Service: SSV-0142 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SSV-0142 Open/Closed Description: Status Sub System: 01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

305/4

OE:1996092167

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1981018887

ObjectID: MEPA-PSL-0143 System: 01 - WELLHEADS & FLOWLINES Package: 01E02 C&E No: Service: WV-0143 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - WV-0143 Open/Closed Description: Status Sub System: 01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

306/4

OE:1981018887

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1994256423

ObjectID: MEPA-PSL-0151 System: 01 - WELLHEADS & FLOWLINES Package: 01F02 C&E No: Service: SCSSV-0151 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SCSSV-0151 Open/Closed Description: Status Sub System: 01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

307/4

OE:1994256423

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1996091431

ObjectID: MEPA-PSL-0152 System: 01 - WELLHEADS & FLOWLINES Package: 01F02 C&E No: Service: SSV-0152 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SSV-0152 Open/Closed Description: Status Sub System: 01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

308/4

OE:1996091431

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1981018151

ObjectID: MEPA-PSL-0153 System: 01 - WELLHEADS & FLOWLINES Package: 01F02 C&E No: Service: WV-0153 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - WV-0153 Open/Closed Description: Status Sub System: 01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

309/4

OE:1981018151

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1994256727

ObjectID: MEPA-PSL-0161 System: 01 - WELLHEADS & FLOWLINES Package: 01G02 C&E No: Service: SCSSV-0161 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SCSSV-0161 Open/Closed Description: Status Sub System: 01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

310/4

OE:1994256727

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1996091735

ObjectID: MEPA-PSL-0162 System: 01 - WELLHEADS & FLOWLINES Package: 01G02 C&E No: Service: SSV-0162 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SSV-0162 Open/Closed Description: Status Sub System: 01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

311/4

OE:1996091735

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1981018455

ObjectID: MEPA-PSL-0163 System: 01 - WELLHEADS & FLOWLINES Package: 01G02 C&E No: Service: WV-0163 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - WV-0163 Open/Closed Description: Status Sub System: 01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

312/4

OE:1981018455

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1994260359

ObjectID: MEPA-PSL-0171 System: 01 - WELLHEADS & FLOWLINES Package: 01H02 C&E No: Service: SCSSV-0171 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SCSSV-0171 Open/Closed Description: Status Sub System: 01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

313/4

OE:1994260359

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1996095367

ObjectID: MEPA-PSL-0172 System: 01 - WELLHEADS & FLOWLINES Package: 01H02 C&E No: Service: SSV-0172 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SSV-0172 Open/Closed Description: Status Sub System: 01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

314/4

OE:1996095367

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1981022087

ObjectID: MEPA-PSL-0173 System: 01 - WELLHEADS & FLOWLINES Package: 01H02 C&E No: Service: WV-0173 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - WV-0173 Open/Closed Description: Status Sub System: 01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

315/4

OE:1981022087

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1994259623

ObjectID: MEPA-PSL-0181 System: 01 - WELLHEADS & FLOWLINES Package: 01I02 C&E No: Service: SCSSV-0181 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SCSSV-0181 Open/Closed Description: Status Sub System: 01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

316/4

OE:1994259623

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1996094631

ObjectID: MEPA-PSL-0182 System: 01 - WELLHEADS & FLOWLINES Package: 01I02 C&E No: Service: SSV-0182 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SSV-0182 Open/Closed Description: Status Sub System: 01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

317/4

OE:1996094631

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1981021351

ObjectID: MEPA-PSL-0183 System: 01 - WELLHEADS & FLOWLINES Package: 01I02 C&E No: Service: WV-0183 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - WV-0183 Open/Closed Description: Status Sub System: 01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:10, (ID=28922).

BDEWC Commissioning

318/4

OE:1981021351

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1994259911

ObjectID: MEPA-PSL-0191 System: 01 - WELLHEADS & FLOWLINES Package: 01J02 C&E No: Service: SCSSV-0191 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SCSSV-0191 Open/Closed Description: Status Sub System: 01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

319/4

OE:1994259911

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1996094919

ObjectID: MEPA-PSL-0192 System: 01 - WELLHEADS & FLOWLINES Package: 01J02 C&E No: Service: SSV-0192 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SSV-0192 Open/Closed Description: Status Sub System: 01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

320/4

OE:1996094919

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1981021639

ObjectID: MEPA-PSL-0193 System: 01 - WELLHEADS & FLOWLINES Package: 01J02 C&E No: Service: WV-0193 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - WV-0193 Open/Closed Description: Status Sub System: 01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

321/4

OE:1981021639

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:2013132471

ObjectID: MEPA-PSL-0201 System: 01 - WELLHEADS & FLOWLINES Package: 01K02 C&E No: Service: SCSSV-0201 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SCSSV-0201 Open/Closed Description: Status Sub System: 01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

322/4

OE:2013132471

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:2010773175

ObjectID: MEPA-PSL-0202 System: 01 - WELLHEADS & FLOWLINES Package: 01K02 C&E No: Service: SSV-0202 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SSV-0202 Open/Closed Description: Status Sub System: 01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

323/4

OE:2010773175

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1999894199

ObjectID: MEPA-PSL-0203 System: 01 - WELLHEADS & FLOWLINES Package: 01K02 C&E No: Service: WV-0203 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - WV-0203 Open/Closed Description: Status Sub System: 01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

324/4

OE:1999894199

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:2013131927

ObjectID: MEPA-PSL-0211 System: 01 - WELLHEADS & FLOWLINES Package: 01L02 C&E No: Service: SCSSV-0211 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SCSSV-0211 Open/Closed Description: Status Sub System: 01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

325/4

OE:2013131927

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:2010772631

ObjectID: MEPA-PSL-0212 System: 01 - WELLHEADS & FLOWLINES Package: 01L02 C&E No: Service: SSV-0212 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SSV-0212 Open/Closed Description: Status Sub System: 01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

326/4

OE:2010772631

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1999893655

ObjectID: MEPA-PSL-0213 System: 01 - WELLHEADS & FLOWLINES Package: 01L02 C&E No: Service: WV-0213 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - WV-0213 Open/Closed Description: Status Sub System: 01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINE Area: Cellar Deck LoopNo: NA OK PL Output /Remarks

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

327/4

OE:1999893655

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:2013132215

ObjectID: MEPA-PSL-0221 System: 01 - WELLHEADS & FLOWLINES Package: 01M02 C&E No: Service: SCSSV-0221 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SCSSV-0221 Open/Closed Description: Status Sub System: 01M - WELLHEAD WH-0220 (SLOT 12) & FLOWLINE LoopNo: NA OK PL Output /Remarks

Area: Cellar Deck

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

328/4

OE:2013132215

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:2010772919

ObjectID: MEPA-PSL-0222 System: 01 - WELLHEADS & FLOWLINES Package: 01M02 C&E No: Service: SSV-0222 status Open/Close Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - SSV-0222 status Open/Close Description: Status Sub System: 01M - WELLHEAD WH-0220 (SLOT 12) & FLOWLINE LoopNo: NA OK PL Output /Remarks

Area: Cellar Deck

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

329/4

OE:2010772919

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1999893943

ObjectID: MEPA-PSL-0223 System: 01 - WELLHEADS & FLOWLINES Package: 01M02 C&E No: Service: WV-0223 Open/Closed Status Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

PRESSURE SWITCH - WV-0223 Open/Closed Description: Status Sub System: 01M - WELLHEAD WH-0220 (SLOT 12) & FLOWLINE LoopNo: NA OK PL Output /Remarks

Area: Cellar Deck

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

330/4

OE:1999893943

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1499449624

ObjectID: MEPA-PT-0114 System: 01 - WELLHEADS & FLOWLINES Package: 01B03 C&E No: LoopDwg: Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0111) Item 01 02 03 04 05 06 07 08 09 10

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0111) Sub System: 01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINE Area: CELLAR DECK LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

331/4

OE:1499449624

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1113579545

ObjectID: MEPA-PT-0114 System: 01 - WELLHEADS & FLOWLINES Package: 01B03 Manufacturer: YOKOGAWA Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type: EJX530A

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0111) Sub System: 01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINE Area: CELLAR DECK SerialNo: 91H913547 NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

332/4

OE:1113579545

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1382009112

ObjectID: MEPA-PT-0114 System: 01 - WELLHEADS & FLOWLINES Package: 01B03 Manufacturer: YOKOGAWA Model/Type: EJX530A Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0111) Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0111) Sub System: 01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINE Area: CELLAR DECK SerialNo: 91H913547

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

333/4

OE:1382009112

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1382013720

ObjectID: MEPA-PT-0114 System: 01 - WELLHEADS & FLOWLINES Package: 01B03 Item 01

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0111) Sub System: 01B - WELLHEAD WH-0110 (SLOT 1) & FLOWLINE Area: CELLAR DECK NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

334/4

OE:1382013720

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1499154712

ObjectID: MEPA-PT-0124 System: 01 - WELLHEADS & FLOWLINES Package: 01C03 C&E No: LoopDwg: Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0121) Item 01 02 03 04 05 06 07 08 09 10

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0121) Sub System: 01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINE Area: CELLAR DECK LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

335/4

OE:1499154712

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1113284633

ObjectID: MEPA-PT-0124 System: 01 - WELLHEADS & FLOWLINES Package: 01C03 Manufacturer: FOXBORO Item 01 02 03 04 05 06 07 08 09 10 11 12 13

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0121) Sub System: 01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINE Area: CELLAR DECK Model/Type: IGP10-T52E5D-L1T SerialNo: 11294827 NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

336/4

OE:1113284633

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1381714200

ObjectID: MEPA-PT-0124 System: 01 - WELLHEADS & FLOWLINES Package: 01C03

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0121) Sub System: 01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINE Area: CELLAR DECK SerialNo: 11294827

Manufacturer: FOXBORO Model/Type: IGP10-T52E5D-L1T Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0121) Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

337/4

OE:1381714200

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1381718808

ObjectID: MEPA-PT-0124 System: 01 - WELLHEADS & FLOWLINES Package: 01C03 Item 01

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0121) Sub System: 01C - WELLHEAD WH-0120 (SLOT 2) & FLOWLINE Area: CELLAR DECK NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

338/4

OE:1381718808

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1497762072

ObjectID: MEPA-PT-0134 System: 01 - WELLHEADS & FLOWLINES Package: 01D03 C&E No: LoopDwg: Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0131) Item 01 02 03 04 05 06 07 08 09 10

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0131) Sub System: 01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINE Area: CELLAR DECK LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

339/4

OE:1497762072

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1111891993

ObjectID: MEPA-PT-0134 System: 01 - WELLHEADS & FLOWLINES Package: 01D03 Manufacturer: YOKOGAWA Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type: EJX530A

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0131) Sub System: 01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINE Area: CELLAR DECK SerialNo: 91H913549 NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

340/4

OE:1111891993

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1380321560

ObjectID: MEPA-PT-0134 System: 01 - WELLHEADS & FLOWLINES Package: 01D03 Manufacturer: YOKOGAWA Model/Type: EJX530A Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0131) Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0131) Sub System: 01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINE Area: CELLAR DECK SerialNo: 91H913549

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

341/4

OE:1380321560

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1380326168

ObjectID: MEPA-PT-0134 System: 01 - WELLHEADS & FLOWLINES Package: 01D03 Item 01

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0131) Sub System: 01D - WELLHEAD WH-0130 (SLOT 3) & FLOWLINE Area: CELLAR DECK NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

342/4

OE:1380326168

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1497467160

ObjectID: MEPA-PT-0144 System: 01 - WELLHEADS & FLOWLINES Package: 01E03 C&E No: LoopDwg: Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0141) Item 01 02 03 04 05 06 07 08 09 10

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0141) Sub System: 01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINE Area: LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

343/4

OE:1497467160

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1111597081

ObjectID: MEPA-PT-0144 System: 01 - WELLHEADS & FLOWLINES Package: 01E03 Manufacturer: YOKOGAWA Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type: EJA 530 A

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0141) Sub System: 01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINE Area: SerialNo: 91L 911840-139 NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

344/4

OE:1111597081

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1380026648

ObjectID: MEPA-PT-0144 System: 01 - WELLHEADS & FLOWLINES Package: 01E03 Manufacturer: YOKOGAWA Model/Type: EJA 530 A Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0141) Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0141) Sub System: 01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINE Area: SerialNo: 91L 911840-139

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

345/4

OE:1380026648

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1380031256

ObjectID: MEPA-PT-0144 System: 01 - WELLHEADS & FLOWLINES Package: 01E03 Item 01

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0141) Sub System: 01E - WELLHEAD WH-0140 (SLOT 5) & FLOWLINE Area: NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

346/4

OE:1380031256

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1498220824

ObjectID: MEPA-PT-0154 System: 01 - WELLHEADS & FLOWLINES Package: 01F03 C&E No: LoopDwg: Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0151) Item 01 02 03 04 05 06 07 08 09 10

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0151) Sub System: 01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINE Area: Cellar Deck LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

347/4

OE:1498220824

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1112350745

ObjectID: MEPA-PT-0154 System: 01 - WELLHEADS & FLOWLINES Package: 01F03 Manufacturer: YKOGAWA Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type: EJA 530 A

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0151) Sub System: 01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINE Area: Cellar Deck SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

348/4

OE:1112350745

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1380780312

ObjectID: MEPA-PT-0154 System: 01 - WELLHEADS & FLOWLINES Package: 01F03 Manufacturer: YKOGAWA Model/Type: EJA 530 A Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0151) Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0151) Sub System: 01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINE Area: Cellar Deck SerialNo:

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

349/4

OE:1380780312

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1380784920

ObjectID: MEPA-PT-0154 System: 01 - WELLHEADS & FLOWLINES Package: 01F03 Item 01

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0151) Sub System: 01F - WELLHEAD WH-0150 (SLOT 6) & FLOWLINE Area: Cellar Deck NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

350/4

OE:1380784920

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1497942296

ObjectID: MEPA-PT-0164 System: 01 - WELLHEADS & FLOWLINES Package: 01G03 C&E No: LoopDwg: Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0161) Item 01 02 03 04 05 06 07 08 09 10

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0161) Sub System: 01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINE Area: Cellar Deck LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

351/4

OE:1497942296

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1112072217

ObjectID: MEPA-PT-0164 System: 01 - WELLHEADS & FLOWLINES Package: 01G03 Manufacturer: YOKOGAWA Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type: EJA 530 A

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0161) Sub System: 01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINE Area: Cellar Deck SerialNo: 91L911 841-139 NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

352/4

OE:1112072217

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1380501784

ObjectID: MEPA-PT-0164 System: 01 - WELLHEADS & FLOWLINES Package: 01G03 Manufacturer: YOKOGAWA Model/Type: EJA 530 A Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0161) Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0161) Sub System: 01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINE Area: Cellar Deck SerialNo: 91L911 841-139

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

353/4

OE:1380501784

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1380506392

ObjectID: MEPA-PT-0164 System: 01 - WELLHEADS & FLOWLINES Package: 01G03 Item 01

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0161) Sub System: 01G - WELLHEAD WH-0160 (SLOT 4) & FLOWLINE Area: Cellar Deck NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

354/4

OE:1380506392

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1500743960

ObjectID: MEPA-PT-0174 System: 01 - WELLHEADS & FLOWLINES Package: 01H03 C&E No: LoopDwg: Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0171) Item 01 02 03 04 05 06 07 08 09 10

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0171) Sub System: 01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINE Area: LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

355/4

OE:1500743960

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1114873881

ObjectID: MEPA-PT-0174 System: 01 - WELLHEADS & FLOWLINES Package: 01H03 Manufacturer: YOKOGAWA Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type: EJA 530A

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0171) Sub System: 01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINE Area: SerialNo: 91L911838 138 NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

356/4

OE:1114873881

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1383303448

ObjectID: MEPA-PT-0174 System: 01 - WELLHEADS & FLOWLINES Package: 01H03 Manufacturer: YOKOGAWA Model/Type: EJA 530A Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0171) Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0171) Sub System: 01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINE Area: SerialNo: 91L911838 138

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

357/4

OE:1383303448

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1383308056

ObjectID: MEPA-PT-0174 System: 01 - WELLHEADS & FLOWLINES Package: 01H03 Item 01

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0171) Sub System: 01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINE Area: NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

358/4

OE:1383308056

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1501497624

ObjectID: MEPA-PT-0184 System: 01 - WELLHEADS & FLOWLINES Package: 01I03 C&E No: LoopDwg: Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0181) Item 01 02 03 04 05 06 07 08 09 10

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0181) Sub System: 01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINE Area: LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

359/4

OE:1501497624

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1115627545

ObjectID: MEPA-PT-0184 System: 01 - WELLHEADS & FLOWLINES Package: 01I03 Manufacturer: YOKOGAWA Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type: EJA 530 A

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0181) Sub System: 01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINE Area: SerialNo: NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

360/4

OE:1115627545

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1384057112

ObjectID: MEPA-PT-0184 System: 01 - WELLHEADS & FLOWLINES Package: 01I03 Manufacturer: YOKOGAWA Model/Type: EJA 530 A Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0181) Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0181) Sub System: 01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINE Area: SerialNo:

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

361/4

OE:1384057112

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1384061720

ObjectID: MEPA-PT-0184 System: 01 - WELLHEADS & FLOWLINES Package: 01I03 Item 01

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0181) Sub System: 01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINE Area: NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

362/4

OE:1384061720

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1501202712

ObjectID: MEPA-PT-0194 System: 01 - WELLHEADS & FLOWLINES Package: 01J03 C&E No: LoopDwg: Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0191) Item 01 02 03 04 05 06 07 08 09 10

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0191) Sub System: 01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINE Area: LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

363/4

OE:1501202712

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1115332633

ObjectID: MEPA-PT-0194 System: 01 - WELLHEADS & FLOWLINES Package: 01J03 Manufacturer: YOKOGAWA Item 01 02 03 04 05 06 07 08 09 10 11 12 13 Model/Type: EJA 530A

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0191) Sub System: 01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINE Area: SerialNo: 91L911839-138 NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

364/4

OE:1115332633

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1383762200

ObjectID: MEPA-PT-0194 System: 01 - WELLHEADS & FLOWLINES Package: 01J03 Manufacturer: YOKOGAWA Model/Type: EJA 530A Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0191) Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0191) Sub System: 01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINE Area: SerialNo: 91L911839-138

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

365/4

OE:1383762200

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1383766808

ObjectID: MEPA-PT-0194 System: 01 - WELLHEADS & FLOWLINES Package: 01J03 Item 01

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0191) Sub System: 01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINE Area: NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

366/4

OE:1383766808

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1498892604

ObjectID: MEPA-PT-0204 System: 01 - WELLHEADS & FLOWLINES Package: 01K03 C&E No: LoopDwg: Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0201) Item 01 02 03 04 05 06 07 08 09 10

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0201) Sub System: 01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINE Area: CELLAR DECK LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC Commissioning

367/4

OE:1498892604

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1113022525

ObjectID: MEPA-PT-0204 System: 01 - WELLHEADS & FLOWLINES Package: 01K03 Manufacturer: FOXBORO Item 01 02 03 04 05 06 07 08 09 10 11 12 13

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0201) Sub System: 01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINE Area: CELLAR DECK Model/Type: IGP10-T52E5D-L1T SerialNo: 11294828 NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:11, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

368/4

OE:1113022525

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1381452092

ObjectID: MEPA-PT-0204 System: 01 - WELLHEADS & FLOWLINES Package: 01K03

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0201) Sub System: 01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINE Area: CELLAR DECK SerialNo: 11294828

Manufacturer: FOXBORO Model/Type: IGP10-T52E5D-L1T Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0201) Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

369/4

OE:1381452092

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1381456700

ObjectID: MEPA-PT-0204 System: 01 - WELLHEADS & FLOWLINES Package: 01K03 Item 01

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0201) Sub System: 01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINE Area: CELLAR DECK NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

370/4

OE:1381456700

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1499449660

ObjectID: MEPA-PT-0214 System: 01 - WELLHEADS & FLOWLINES Package: 01L03 C&E No: LoopDwg: Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0211) Item 01 02 03 04 05 06 07 08 09 10

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0211) Sub System: 01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINE Area: CELLAR DECK LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

371/4

OE:1499449660

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1113579581

ObjectID: MEPA-PT-0214 System: 01 - WELLHEADS & FLOWLINES Package: 01L03 Manufacturer: FOXBORO Item 01 02 03 04 05 06 07 08 09 10 11 12 13

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0211) Sub System: 01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINE Area: CELLAR DECK Model/Type: IGP10-T52E5D-L1T SerialNo: 11294829 NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

372/4

OE:1113579581

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1382009148

ObjectID: MEPA-PT-0214 System: 01 - WELLHEADS & FLOWLINES Package: 01L03

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0211) Sub System: 01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINE Area: CELLAR DECK SerialNo: 11294829

Manufacturer: FOXBORO Model/Type: IGP10-T52E5D-L1T Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0211) Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

373/4

OE:1382009148

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1382013756

ObjectID: MEPA-PT-0214 System: 01 - WELLHEADS & FLOWLINES Package: 01L03 Item 01

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0211) Sub System: 01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINE Area: CELLAR DECK NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

374/4

OE:1382013756

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1499154748

ObjectID: MEPA-PT-0224 System: 01 - WELLHEADS & FLOWLINES Package: 01M03 C&E No: LoopDwg: Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0221) Item 01 02 03 04 05 06 07 08 09 10

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0221) Sub System: 01M - WELLHEAD WH-0220 (SLOT 12) & FLOWLINE LoopNo:

Area: CELLAR DECK

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

375/4

OE:1499154748

Inspection Test Report E17A Certified Equipment MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1113284669

ObjectID: MEPA-PT-0224 System: 01 - WELLHEADS & FLOWLINES Package: 01M03 Manufacturer: FOXBORO Item 01 02 03 04 05 06 07 08 09 10 11 12 13

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0221) Sub System: 01M - WELLHEAD WH-0220 (SLOT 12) & FLOWLINE

Area: CELLAR DECK Model/Type: IGP10-T52E5D-L1T SerialNo: 11294830 NA OK PL Output /Remarks

Description Equipment is installed as per AFC Drawings and conforms to hazardous area classification Check equipment is as per data sheet Check glands have IP sealing washer fitted and are installed in accordance with vendor specification Enclosure has Certifying Authority label attached. Enclosure has manufacturer's data identification label attached. Apparatus is clean and corrosion free. Apparatus is not damaged and has no unauthorised modifications. Ensure no build up of dirt or corrosion on flame paths. Confirm terminal blocks have been supplied by the manufacturer and are fitted correctly. Clean all blind holes of dirt and grease prior to assembly. Check earthing conforms to design requirement Ensure all electrical connections are tight Equipment Certification No:_____________________________

Notes: 1. All checks to be in accordance with IEC60079-0 ______________________________________________________________________________________________________________________ Remarks:

___________________________________________________________________________________________________________________________________ Test equipment:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

376/4

OE:1113284669

Inspection Test Report I01A Inst Inspection MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1381714236

ObjectID: MEPA-PT-0224 System: 01 - WELLHEADS & FLOWLINES Package: 01M03

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0221) Sub System: 01M - WELLHEAD WH-0220 (SLOT 12) & FLOWLINE SerialNo: 11294830

Area: CELLAR DECK

Manufacturer: FOXBORO Model/Type: IGP10-T52E5D-L1T Service: At Chem. Inj. Ring Upstream of Choke vlv (HCV-0221) Item 01 02 03 04 05 06 07 08 09 Description Instrument is checked correct against current revision of data sheet. Data plate details correct All materials are correct. Instrument is not damaged. Process connections correct. Electrical connections correct. Pneumatic connections correct. Hydraulic connections correct. Equipment Certification No.:____________________________

NA

OK

PL

Output /Remarks

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

377/4

OE:1381714236

Inspection Test Report I02A Inst Installation MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1381718844

ObjectID: MEPA-PT-0224 System: 01 - WELLHEADS & FLOWLINES Package: 01M03 Item 01

PRESSURE TRANSMITTER - At Chem. Inj. Ring Description: Upstream of Choke vlv (HCV-0221) Sub System: 01M - WELLHEAD WH-0220 (SLOT 12) & FLOWLINE

Area: CELLAR DECK NA OK PL Output /Remarks

02

03

Description Data 01.01 - Confirm the instrument is connected and installed correctly to relevant layout, termination, loop and hook-up drawings. Inspection The following checks are to be performed. 02.01 - Instrument correctly mounted, orientation correct, elevation correct and free from vibration. 02.02 - Instrument is accessible for maintenance and clear of obstructions. 02.03 - Vent lines are directed into a safe area. 02.04 - Impulse, Hydraulic, Pneumatic Signal and Supply lines correctly installed and correctly supported. 02.05 - In-Line equipment installed and supported correctly. 02.06 - Spare entries plugged correctly. 02.07 - Instrument earthed in accordance with project specification. 02.08 - Aspirator tubes and Test gas tubes are installed and supported correctly. 02.09 - EOL resistor fitted and correctly rated where applicable. 02.10 - Check all Tag No's. 02.11 - Labelling correct. Instrument Line Pressure and Leak Test *W* 03.01 - Prior to any testing taking place, confirm test equipment is within calibration period. 03.02 - Using project and manufacture's specification for test pressure, test medium and test duration, perform pressure tests and verify acceptable leak rates on the following lines where applicable: Impulse Lines Hydraulic Lines Pneumatic Lines Air Supply Lines 03.03 - Confirm the following lines have been blown clear: Pneumatic Lines Test Gas Lines 03.04 - Confirm all hydraulic lines have been flushed and cleaned to project specifications. 03.05 - Confirm all impulse lines have been drained and cleaned

Notes: *W* Commissioning & Client Witness points ____________________________________________________________________________________________________________________________________ Remarks:

____________________________________________________________________________________________________________________________________ Test Equipment Code Description

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

378/4

OE:1381718844

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:371673588

ObjectID: MEPA-QT-0401 System: 04 - MANIFOLDS Package: 04A01 C&E No: Service: Production Header Manifold To Production Cooler Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: PRODUCTION Header Manifold (sand detector) Sub System: 04A - PRODUCTION HEADER Area: Mezzanine Deck LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

379/4

OE:371673588

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1775810064

ObjectID: MEPA-QT-0402 System: 04 - MANIFOLDS Package: 04B01 C&E No: Service: Test Header Manifold To Test Separator Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: SAND DETECTOR - Test Header Manifold Sub System: 04B - TEST HEADER Area: Mezzanine Deck LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

380/4

OE:-1775810064

Function Test Report E05B Distribution Board, Junction Box & Control Station MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-167979851

ObjectID: MEPA-RCU-PM-5110 System: 51 - SERVICE WATER SYSTEM Package: 51A01 Manufacturer: Item 01 02 03 04 SingleLineDwg:

Description: Field Control Unit - Service Water Pump Sub System: 51A - T-5110 SERVICE WATER CAISSON/PUMP Area:

05

06

07 Notes. 1.

Description Check ratings of MCB's and main isolator are as per AFC Drawing Check busbars are at zero potential and main isolator and all MCB's are open For local control stations confirm switching in conjunction with motor run test Using a 1000V Megger perform IR Test on Distribution Board L1 - E _________Mohm L2 - E _________Mohm L3 - E _________Mohm L1 - L2_________Mohm L1 - L3_________Mohm L2 - L3_________Mohm L1 - N _________Mohm L2 - N _________Mohm L3 - N _________Mohm Energise Distribution Board confirm and record voltage: L1 - L2 L1 - L3 L2 - L3 L1 - N L2 - N L3 - N For lighting and small power distribution boards check balance of phases is as per single line diagram Record full load current readings: Red : Amps Yellow : Amps Blue : Amps Lock out equipment

NA

OK

PL

Output /Remarks

All switching and testing of equipment is to be carried out in accordance with the BDEWC / Client electrical safety rules and operating procedures All relevant ITRs and FTRs to be complete prior to commissioning ______________________________________________________________________________________________________________________ Remarks:

______________________________________________________________________________________________________________________ Test equipment:

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

381/4

OE:-167979851

Function Test Report E22B Motor Starter Contactor MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-964814696

ObjectID: MEPA-SB-7700-L5B System: 51 - SERVICE WATER SYSTEM Package: 51A01 Manufacturer: Item 01 02 03 SingleLineDwg:

Description: Switchboard Cubicle - Service Water Pump Sub System: 51A - T-5110 SERVICE WATER CAISSON/PUMP Area:

Description Confirm switchboard busbars are at zero potential and all switchboard feeders are isolated and locked out Place equipment in test position Confirm control voltage is available and energise controls Perform injection test on overload relays: *W* Motor: _______ KW ______ Amps Set range: _______ Amps Test Current: _______ (2xlr Amps) Acceptable Curve: _______ secs Actual: _______ secs Starter Unit Function Checked: _______ Prove auxiliary circuits and function of following: *W* 05.01 - Trips and alarms 05.02 - Indication lights and Ammeter 05.03 - Manual and automatic closing 05.04 - Operation of local and field controls, stop start station 05.05 - Anti condensate heater Check voltage and phase rotation is correct Equipment is ready for service Motor to be run and tested in accordance with FTR EO8B

NA

OK

PL

Output /Remarks

04

05

06 07 08
Notes 1. 2. 3.

All switching and testing of equipment is to be carried out in accordance with the BDEWC / Client electrical safety rules and operating procedures All relevant ITRs and FTRs to be complete prior to energisation procedure Some of the tests listed below may have been performed at the FAT and not scheduled to be re tested at the SAT, in which case a copy of the FAT tests shall be attached to this check sheet

*W* Commissioning & Client Witness points ______________________________________________________________________________________________________________________ Remarks:

______________________________________________________________________________________________________________________ Test Equipment:

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

382/4

OE:-964814696

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:391859120

ObjectID: MEPA-SV-6801 System: 68 - CHEMICAL INJECTION Package: 68A02 C&E No: Service: Corrossion inhibitor -Flowline Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: SOLENOID VALVE - A6800 Chemical Injection Skid Sub System: 68A - A-6800 CHEMICAL INJECTION SKID PACKAGE (CORROSION INHIBITOR - FLOWLINE) LoopNo: NA OK PL Output /Remarks

Area: Mezzanine Deck

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

383/4

OE:391859120

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1755624524

ObjectID: MEPA-SV-6802 System: 68 - CHEMICAL INJECTION Package: 68A02 C&E No: Service: Corrossion inhibitor -Flowline Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: SOLENOID VALVE - A6800 Chemical Injection Skid Sub System: 68A - A-6800 CHEMICAL INJECTION SKID PACKAGE (CORROSION INHIBITOR - FLOWLINE) LoopNo: NA OK PL Output /Remarks

Area: Mezzanine Deck

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

384/4

OE:-1755624524

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-681882711

ObjectID: MEPA-SV-6803 System: 68 - CHEMICAL INJECTION Package: 68A02 C&E No: Service: Corrossion inhibitor -Flowline Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: SOLENOID VALVE - A6800 Chemical Injection Skid Sub System: 68A - A-6800 CHEMICAL INJECTION SKID PACKAGE (CORROSION INHIBITOR - FLOWLINE) LoopNo: NA OK PL Output /Remarks

Area: Mezzanine Deck

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

385/4

OE:-681882711

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1465600942

ObjectID: MEPA-SV-6804 System: 68 - CHEMICAL INJECTION Package: 68A02 C&E No: Service: Corrossion inhibitor -Flowline Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: SOLENOID VALVE - A6800 Chemical Injection Skid Sub System: 68A - A-6800 CHEMICAL INJECTION SKID PACKAGE (CORROSION INHIBITOR - FLOWLINE) LoopNo: NA OK PL Output /Remarks

Area: Mezzanine Deck

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

386/4

OE:1465600942

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-681882718

ObjectID: MEPA-SV-6805 System: 68 - CHEMICAL INJECTION Package: 68A02 C&E No: Service: Corrossion inhibitor -Flowline Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: SOLENOID VALVE - A6800 Chemical Injection Skid Sub System: 68A - A-6800 CHEMICAL INJECTION SKID PACKAGE (CORROSION INHIBITOR - FLOWLINE) LoopNo: NA OK PL Output /Remarks

Area: Mezzanine Deck

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

387/4

OE:-681882718

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:391859111

ObjectID: MEPA-SV-6806 System: 68 - CHEMICAL INJECTION Package: 68A02 C&E No: Service: Corrossion inhibitor -Flowline Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: SOLENOID VALVE - A6800 Chemical Injection Skid Sub System: 68A - A-6800 CHEMICAL INJECTION SKID PACKAGE (CORROSION INHIBITOR - FLOWLINE) LoopNo: NA OK PL Output /Remarks

Area: Mezzanine Deck

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

388/4

OE:391859111

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1465600924

ObjectID: MEPA-SV-6807 System: 68 - CHEMICAL INJECTION Package: 68A02 C&E No: Service: Corrossion inhibitor -Flowline Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: SOLENOID VALVE - A6800 Chemical Injection Skid Sub System: 68A - A-6800 CHEMICAL INJECTION SKID PACKAGE (CORROSION INHIBITOR - FLOWLINE) LoopNo: NA OK PL Output /Remarks

Area: Mezzanine Deck

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

389/4

OE:1465600924

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1465600917

ObjectID: MEPA-SV-6809 System: 68 - CHEMICAL INJECTION Package: 68A02 C&E No: Service: Corrossion inhibitor -Flowline Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: SOLENOID VALVE - A6800 Chemical Injection Skid Sub System: 68A - A-6800 CHEMICAL INJECTION SKID PACKAGE (CORROSION INHIBITOR - FLOWLINE) LoopNo: NA OK PL Output /Remarks

Area: Mezzanine Deck

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

390/4

OE:1465600917

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1756116040

ObjectID: MEPA-SV-6810 System: 68 - CHEMICAL INJECTION Package: 68A02 C&E No: Service: Corrossion inhibitor -Flowline Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: SOLENOID VALVE - A6800 Chemical Injection Skid Sub System: 68A - A-6800 CHEMICAL INJECTION SKID PACKAGE (CORROSION INHIBITOR - FLOWLINE) LoopNo: NA OK PL Output /Remarks

Area: Mezzanine Deck

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

391/4

OE:-1756116040

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:391367600

ObjectID: MEPA-SV-6811 System: 68 - CHEMICAL INJECTION Package: 68A02 C&E No: Service: Corrossion inhibitor -Flowline Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: SOLENOID VALVE - A6800 Chemical Injection Skid Sub System: 68A - A-6800 CHEMICAL INJECTION SKID PACKAGE (CORROSION INHIBITOR - FLOWLINE) LoopNo: NA OK PL Output /Remarks

Area: Mezzanine Deck

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

392/4

OE:391367600

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1756116044

ObjectID: MEPA-SV-6812 System: 68 - CHEMICAL INJECTION Package: 68A02 C&E No: Service: Corrossion inhibitor -Flowline Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: SOLENOID VALVE - A6800 Chemical Injection Skid Sub System: 68A - A-6800 CHEMICAL INJECTION SKID PACKAGE (CORROSION INHIBITOR - FLOWLINE) LoopNo: NA OK PL Output /Remarks

Area: Mezzanine Deck

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

393/4

OE:-1756116044

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-681882736

ObjectID: MEPA-SV-6808 System: 68 - CHEMICAL INJECTION Package: 68A02 C&E No: Service: Corrossion inhibitor -Flowline Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: SOLENOID VALVE - A6800 Chemical Injection Skid Sub System: 68A - A-6800 CHEMICAL INJECTION SKID PACKAGE (CORROSION INHIBITOR - FLOWLINE) LoopNo: NA OK PL Output /Remarks

Area: Mezzanine Deck

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

394/4

OE:-681882736

Inspection Test Report M01A Tank MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:2003270091

ObjectID: MEPA-T-5110 System: 51 - SERVICE WATER SYSTEM Package: 51A01 SerialNo: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Notes:

Description: SERVICE WATER SUPPLY CAISSON Sub System: 51A - T-5110 SERVICE WATER CAISSON/PUMP Area: Sub-Cellar Deck

Description Nameplate details are correct in accordance with the data sheet. Tank has been installed to the manufacturer's instructions. Tank is installed level and as per P & IDs. Sliding feet (if any) are free to move, and are fitted with locknuts. Tank is secure. All structural bolting is tight and to spec. Fittings, connections, sacrificial anodes, bird screens, etc, complete as per vendor drawings. All hot oil flushing and chemical cleaning of adjoining pipework has been completed All pipes and equipment which interface with the tank have been installed, their flanges have been torqued/tensioned. All flange management tags are still intact on all vessel flanges (if specified) All checks sheets for associated equipment such as pumps that require internal access to the tank have been completed. e.g. inspection of pump inlet strainers. All hot work in the vicinity of the tank walls and roof is complete, e.g. ensure that pipe supports shall not be welded onto adjacent wall which may be common with tank wall. If specified on project drawings, confirm that vacuum breaker is installed and its certification is valid Vent and drain valves are fitted Internals and vessel trims are fitted as per drawing. *W* Tank is clean internally. *W* Check coating is undamaged. *W* Manway is accessible. Manway lifting arrangements are adequate. Access ladders and platforms are correctly installed. Access to valves, gauges and fittings is adequate. All gaskets are correct to specification. All gaskets are fitted, with the exception of the manway gasket/s. Confirm that the manway gasket/s (which must not yet be fitted) are correctly preserved and stored in the warehouse. Confirm earth bonding completed. Check nozzle loading is not excessive. Adequate clearance exists for removal of internals. Ensure that preservation is correct. Where preservation materials are installed, equipment is marked "PRESERVATION INSIDE". If overflow is fitted, ensure that it is unobstructed and routed to location shown on P&ID. Upon successful completion of all steps above, close manway door with shipping gasket only and finger tighten all bolts. New gasket must NOT be used. Seal/cover flange to prevent entry of water/dirt. *W*

NA

OK

PL

Output /Remarks

*W* Commissioning & Client Witness points ______________________________________________________________________________________________________________________ Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

395/4

OE:2003270091

Function Test Report M01B TANK MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:2003270080

ObjectID: MEPA-T-5110 System: 51 - SERVICE WATER SYSTEM Package: 51A01 SerialNo: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

Description: SERVICE WATER SUPPLY CAISSON Sub System: 51A - T-5110 SERVICE WATER CAISSON/PUMP Area: Sub-Cellar Deck

Description Construction check list completed and no subsequent damage has occurred. All pipes and equipment which interface with the vessel have been installed. All flange bolts have been torqued/tensioned/tightened. All flange management tags are still intact on all vessel flanges (if specified) All fittings, connections, sacrificial anodes, bird screens, spec blinds, etc, still present and in good order. All hot oil flushing and chemical cleaning of adjoining pipework, (if any), has been completed. All checks sheets for associated equipment such as pumps that require internal access to the tank have been completed. e.g. inspection of pump inlet strainers. All hot work in the vicinity of the tank walls and roof is complete, e.g. ensure that pipe supports shall not be welded onto adjacent wall which may be common with tank wall. Vessel externally clean and free from obstruction. Vessel internally clean and no internal degradation has occurred since the 'A' checks were carried out *W* Vent and drain valves fitted and exercised. Remove all non soluble preservation, and ensure that soluble preservation coatings are applied, (if specified in project Preservation Procedure). If specified on project drawings, confirm that vacuum breaker is installed and its certification is valid Confirm earth bonding completed. After items 2 to 13 have been completed, close manway(s)/hatch(s) with correct gaskets and bolting. *W* Torque manway flanges and confirm that torquing/tightening certification is complete *W*

NA

OK

PL

Output /Remarks

Notes & Remarks: *W* Commissioning & Client Witness points

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

396/4

OE:2003270080

Inspection Test Report M01A Tank MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1943499339

ObjectID: MEPA-T-6510 System: 65 - OPEN DRAIN Package: 65A02 SerialNo: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30


Notes:

Description: OHD CAISSON Sub System: 65A - T-6510 OPEN DRAINS CAISSON & PUMP Area: Sub-Cellar Deck

Description Nameplate details are correct in accordance with the data sheet. Tank has been installed to the manufacturer's instructions. Tank is installed level and as per P & IDs. Sliding feet (if any) are free to move, and are fitted with locknuts. Tank is secure. All structural bolting is tight and to spec. Fittings, connections, sacrificial anodes, bird screens, etc, complete as per vendor drawings. All hot oil flushing and chemical cleaning of adjoining pipework has been completed All pipes and equipment which interface with the tank have been installed, their flanges have been torqued/tensioned. All flange management tags are still intact on all vessel flanges (if specified) All checks sheets for associated equipment such as pumps that require internal access to the tank have been completed. e.g. inspection of pump inlet strainers. All hot work in the vicinity of the tank walls and roof is complete, e.g. ensure that pipe supports shall not be welded onto adjacent wall which may be common with tank wall. If specified on project drawings, confirm that vacuum breaker is installed and its certification is valid Vent and drain valves are fitted Internals and vessel trims are fitted as per drawing. *W* Tank is clean internally. *W* Check coating is undamaged. *W* Manway is accessible. Manway lifting arrangements are adequate. Access ladders and platforms are correctly installed. Access to valves, gauges and fittings is adequate. All gaskets are correct to specification. All gaskets are fitted, with the exception of the manway gasket/s. Confirm that the manway gasket/s (which must not yet be fitted) are correctly preserved and stored in the warehouse. Confirm earth bonding completed. Check nozzle loading is not excessive. Adequate clearance exists for removal of internals. Ensure that preservation is correct. Where preservation materials are installed, equipment is marked "PRESERVATION INSIDE". If overflow is fitted, ensure that it is unobstructed and routed to location shown on P&ID. Upon successful completion of all steps above, close manway door with shipping gasket only and finger tighten all bolts. New gasket must NOT be used. Seal/cover flange to prevent entry of water/dirt. *W*

NA

OK

PL

Output /Remarks

*W* Commissioning & Client Witness points ______________________________________________________________________________________________________________________ Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

397/4

OE:1943499339

Function Test Report M01B TANK MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1943499328

ObjectID: MEPA-T-6510 System: 65 - OPEN DRAIN Package: 65A02 SerialNo: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16

Description: OHD CAISSON Sub System: 65A - T-6510 OPEN DRAINS CAISSON & PUMP Area: Sub-Cellar Deck

Description Construction check list completed and no subsequent damage has occurred. All pipes and equipment which interface with the vessel have been installed. All flange bolts have been torqued/tensioned/tightened. All flange management tags are still intact on all vessel flanges (if specified) All fittings, connections, sacrificial anodes, bird screens, spec blinds, etc, still present and in good order. All hot oil flushing and chemical cleaning of adjoining pipework, (if any), has been completed. All checks sheets for associated equipment such as pumps that require internal access to the tank have been completed. e.g. inspection of pump inlet strainers. All hot work in the vicinity of the tank walls and roof is complete, e.g. ensure that pipe supports shall not be welded onto adjacent wall which may be common with tank wall. Vessel externally clean and free from obstruction. Vessel internally clean and no internal degradation has occurred since the 'A' checks were carried out *W* Vent and drain valves fitted and exercised. Remove all non soluble preservation, and ensure that soluble preservation coatings are applied, (if specified in project Preservation Procedure). If specified on project drawings, confirm that vacuum breaker is installed and its certification is valid Confirm earth bonding completed. After items 2 to 13 have been completed, close manway(s)/hatch(s) with correct gaskets and bolting. *W* Torque manway flanges and confirm that torquing/tightening certification is complete *W*

NA

OK

PL

Output /Remarks

Notes & Remarks: *W* Commissioning & Client Witness points

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

398/4

OE:1943499328

Inspection Test Report M21A Main Structural Completion MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:200104837

ObjectID: MEPA-TEL-TOWER System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92D01 Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17

Description: TELECOM TOWER Sub System: 92D - MISCELLANEOUS EQUIPMENT Area: Main Deck NA OK PL Output /Remarks

Description Main structural members installed in accordance with drawings, and all temporary aids / brackets removed. Bulkheads installed in accordance with drawings, and all temporary aids / brackets removed. Deck structures installed in accordance with drawings, and all temporary aids / brackets removed. Roof structures are installed in accordance with drawings, and all temporary aids / brackets removed. All platforms and walkways are installed in accordance with drawings, and all temporary aids/brackets removed. All gulley gratings to drains installed. All penetrations installed, with sleeves/kick plates of specified size complete with drain holes as required. All grating installed and no gaps exist that allow the penetration of a ball bearing of diameter > 15 mm. All foundations installed and do not create traps for water, ample drainage is available for the area. Foundations and handrails installed in accordance with specifications, ladder entrances have safety bar complete with protected landing end and portable hand railings are secured. All structural supports installed in accordance with drawings and all temporary aids / brackets removed. Confirm that all maintenance / scaffolding lugs are installed in accordance with layout drawings with the correct orientation. Main and Interface dimensions checked. Temporary steel work to be removed at a later date, clearly marked and identified on relevant drawings. All welding and NDT work completed and cleared. All piping & ducting penetrations through bulkheads & decks fitted with gas tight sleeves/seals All items covered by this record undamaged and clean.

Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

399/4

OE:200104837

Inspection Test Report T01A Telecoms Field Device Installation Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-235039639

ObjectID: MEPA-TUO-9201 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92B02 Manufacturer: Type: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 Serial No:

Description: IP TELEPHONE Sub System: 92B - CCTV/LAN SYSTEM Area: Service: NA OK PL Output /Remarks

Description Installed according to latest revision of Layout drawing. Item complies with Data sheet. Equipment suitable for area classification. Identification correct. Supports installed correctly. Fixings correct. Access suitable. Paintwork correct. Spare gland entries plugged correctly. Terminal box flanges undamaged. Gaskets & seals undamaged. Gaskets & seals fitted correctly. Check earthing conforms to earthing philosophy. Suitable grease applied to flanges (Ex-d enclosures).

Notes and Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

400/4

OE:-235039639

Inspection Test Report T01A Telecoms Field Device Installation Check MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-237398935

ObjectID: MEPA-TUO-9202 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92B02 Manufacturer: Type: Item 01 02 03 04 05 06 07 08 09 10 11 12 13 14 Serial No:

Description: IP TELEPHONE Sub System: 92B - CCTV/LAN SYSTEM Area: E&I ROOM Service: NA OK PL Output /Remarks

Description Installed according to latest revision of Layout drawing. Item complies with Data sheet. Equipment suitable for area classification. Identification correct. Supports installed correctly. Fixings correct. Access suitable. Paintwork correct. Spare gland entries plugged correctly. Terminal box flanges undamaged. Gaskets & seals undamaged. Gaskets & seals fitted correctly. Check earthing conforms to earthing philosophy. Suitable grease applied to flanges (Ex-d enclosures).

Notes and Remarks:

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

401/4

OE:-237398935

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1751269186

ObjectID: MEPA-UA-5110 System: 51 - SERVICE WATER SYSTEM Package: 51A01 C&E No: Service: Service Water Pump P-5110 FAULT ALARM Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: Sub System: 51A - T-5110 SERVICE WATER CAISSON/PUMP Area: LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

402/4

OE:-1751269186

Function Test Report I01B Loop Test MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1751266802

ObjectID: MEPA-UZ-5110 System: 51 - SERVICE WATER SYSTEM Package: 51A01 C&E No: Service: Trip Service Water Pump MEPA-P5110 Fan Motor Item 01 02 03 04 05 06 07 08 09 10 LoopDwg:

Description: Sub System: 51A - T-5110 SERVICE WATER CAISSON/PUMP Area: LoopNo:

Description All relevant inspection & calibration checklists complete All relevant installation checklists complete Confirm valve stroke time(s) is as per data sheet Confirm valve action correct Alarm, trip settings & ranges set in accordance with the Trip and Alarm schedule. Function test of loop and all components in accordance with loop & data sheet(s) Face Plates displayed correctly Graphic points displayed correctly Cause & Effect Yellow Lined Relevant as-built mark-ups complete

NA

OK

PL

Output /Remarks

Remarks : Valve Action = Alarm Point = Trip Point = Stroke Time = Range(s) = dir/rev inc/dec inc/dec secs

_____________________________________________________________________________________________________________________ Test Equipment : Code Description Calibration Date

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

403/4

OE:-1751266802

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:2036215469

ObjectID: PL-8900-4 System: 89 - NAVAIDS Package: 89A03 CableType: P5 ToTag: TELECOM MAST AIRCRAFT WARNING LIGHT Item 01 02 03 04 05 06 07 08 09 10
Notes:

Cable From MEPA-NCCP-8900 NAV-AIDS CENTRAL Description: CONTROL PANEL To TELECOM MAST AIRCRAFT WA Sub System: 89A - MEPA NAVAIDS Area: FromTag: MEPA-NCCP-8900 NAV-AIDS CENTRAL CONTROL PANEL VoltageRating: 240V NA OK PL Output /Remarks Size: 2Cx4mm2

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

404/4

OE:2036215469

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1062693670

ObjectID: PN-PM5110 System: 51 - SERVICE WATER SYSTEM Package: 51A01 CableType: P2 ToTag: MEPA-PM-5110 SERVICE WATER PUMP Item 01 02 03 04 05 06 07 08 09 10
Notes:

Cable From 415V SWITCHBOARD/MCC MEPA-SBDescription: 7700 To MEPA-PM-5110 SERVICE WATER PUMP Sub System: 51A - T-5110 SERVICE WATER CAISSON/PUMP Area: FromTag: 415V SWITCHBOARD/MCC MEPASB-7700 VoltageRating: 415V NA OK PL Output /Remarks Size: 3Cx4mm2

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

405/4

OE:-1062693670

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1651356538

ObjectID: PT-0174 System: 01 - WELLHEADS & FLOWLINES Package: 01H03 CableType: I2 ToTag: MEPA-PT-0174 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-010 To MEPA-PT-0174 Sub System: 01H - WELLHEAD WH-0170 (SLOT 7) & FLOWLINE Area: FromTag: MEPA-IJB-010 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

406/4

OE:-1651356538

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1650537338

ObjectID: PT-0184 System: 01 - WELLHEADS & FLOWLINES Package: 01I03 CableType: I2 ToTag: MEPA-PT-0184 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-010 To MEPA-PT-0184 Sub System: 01I - WELLHEAD WH-0180 (SLOT 9) & FLOWLINE Area: FromTag: MEPA-IJB-010 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

407/4

OE:-1650537338

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1650766714

ObjectID: PT-0194 System: 01 - WELLHEADS & FLOWLINES Package: 01J03 CableType: I2 ToTag: MEPA-PT-0194 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-010 To MEPA-PT-0194 Sub System: 01J - WELLHEAD WH-0190 (SLOT 8) & FLOWLINE Area: FromTag: MEPA-IJB-010 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

408/4

OE:-1650766714

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1648980830

ObjectID: PT-0204 System: 01 - WELLHEADS & FLOWLINES Package: 01K03 CableType: I2 ToTag: MEPA-PT-0204 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-010 To MEPA-PT-0204 Sub System: 01K - WELLHEAD WH-0200 (SLOT 10) & FLOWLINE Area: FromTag: MEPA-IJB-010 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

409/4

OE:-1648980830

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1648489310

ObjectID: PT-0214 System: 01 - WELLHEADS & FLOWLINES Package: 01L03 CableType: I2 ToTag: MEPA-PT-0214 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-010 To MEPA-PT-0214 Sub System: 01L - WELLHEAD WH-0210 (SLOT 11) & FLOWLINE Area: FromTag: MEPA-IJB-010 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

410/4

OE:-1648489310

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1648718686

ObjectID: PT-0224 System: 01 - WELLHEADS & FLOWLINES Package: 01M03 CableType: I2 ToTag: MEPA-PT-0224 Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Inst. Cable From MEPA-IJB-010 To MEPA-PT-0224 Sub System: Area: FromTag: MEPA-IJB-010 VoltageRating: Size: 1PRx1.5mm2 NA OK PL Output /Remarks 01M - WELLHEAD WH-0220 (SLOT 12) & FLOWLINE

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

411/4

OE:-1648718686

Function Test Report P05B Witnessed Joint MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:898532292

ObjectID: RTP-GORA-1 System: 29 - GAS IMPORT/EXPORT Package: 29C01 PIDNo: Item 01 02 03 04 05 06 07 08 09 10 11 12 Flange description/ID::

Description: GORA Reinstatement Test Pack - 29 Sub System: Area: Joint desciption :: NA OK PL Output /Remarks 29C - MEPA GAS RECEIVING FACILITIES AT GORA

13

14 15

Description Prior to reinstatement, the following checks will be made: Flange faces examined and seen to be clean and damage free. Gaskets examined and seen to be clean, damage free and the correct type and size. Nuts and stud bolts examined and seen to be undamaged and correct size and type. Flange faces parallel. Joint pulled up evenly on opposing stud bolts. All nuts pulled up to required tightness. No visible damage to gasket when joint completed. Minimum of one thread proud of all nuts. No excessive length of stud bolt protruding through each nut. Torquing/ tension certificate complete and flange management tag fitted (if specified in project requirements) Post reinstatement, the following checks will be made: Circle one item from list below: - N2 Helium leak test / Service test / Nil / Soapy bubble leak test / - check with hand held gas detector after introduction of gas / - other (provide details)..... Post reinstatement test described in line 10 completed satisfactorily Attach supporting documentation for post reisnstement test to this sheet

Remarks:

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

412/4

OE:898532292

Function Test Report P04B N2 LEAK TEST MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:898544068

TestPack No: RTP-GORA-1 System: 29 - GAS IMPORT/EXPORT Package: 29C01 PIDNo: Test temperature: Design Pressure (MAWP): Chart Reference: TestDuration: Operational Flow Medium: Design temperature: Recorder Serial No.:

Description: GORA Reinstatement Test Pack - 29 Sub System: Area: TestPressure: Gauge Serial No.: TestMedium: 29C - MEPA GAS RECEIVING FACILITIES AT GORA

LineNo
100-PG-2928-C8Y-2 100-PG-2928-C8Y-4 400-PG-2945-C8Y-1 400-PG-2945-C8Y-2 500-PG-2925-C8Y-5 500-PG-2925-C8Y-6 500-PG-2925-C8Y-7 50-PG-2927-C1Y-1 50-PG-2927-C1Y-2 50-PG-2943-C1Y-1 50-PG-2954-C1Y-1

Description
GORA - PIG RECEIVER R-2950 LINE FROM HV-29408 TO HV-29409 GORA - PIG RECEIVER R-2950 LINE FROM 100-PG-2928-C8Y-2 TO HV-29411 GORA - PIG RECEIVER R-2950 LINE FROM SBT-2903 TO HV-29403 GORA - PIG RECEIVER R-2950 LINE FROM 400-PG-2945-C8Y-1 TO HV-29402 GORA - PIG RECEIVER R-2950 LINE FROM SDV-2950 TO T05.EL.17000 GORA - PIG RECEIVER R-2950 LINE FROM TO T05.EL.17000 GORA - PIG RECEIVER R-2950 LINE FROM T05.EL.17000 TO HV-29404 GORA - PIG RECEIVER R-2950 LINE FROM HV-29413 TO HV-29415 GORA - PIG RECEIVER R-2950 LINE FROM 50-PG-2927-C1Y-1 TO HV-29416 GORA - PIG RECEIVER R-2950 LINE FROM 400-PG-2945-C8Y TO HV-29400 GORA - PIG RECEIVER R-2950 LINE FROM TP-314A TO SDV-2951

P&ID
06001-GORA-EG-PR-DWG-PNID-0004 06001-GORA-EG-PR-DWG-PNID-0004 06001-GORA-EG-PR-DWG-PNID-0004 06001-GORA-EG-PR-DWG-PNID-0004 06001-GORA-EG-PR-DWG-PNID-0004 06001-GORA-EG-PR-DWG-PNID-0004 06001-GORA-EG-PR-DWG-PNID-0004 06001-GORA-EG-PR-DWG-PNID-0004 06001-GORA-EG-PR-DWG-PNID-0004 06001-GORA-EG-PR-DWG-PNID-0004 06001-GORA-EG-PR-DWG-PNID-0004

Comment

Item 01 02

Description Leak test completed and certificate attached to this sheet All witness joints entered into Witness Joint Register and copy attached to this sheet.
Service Test Reinstatement Leak Test (N2He) (Delete as appropriate) 1. Line valves confirmed half open for test (to test stem packing) . 2. Isolation valve integrity test to be conducted.

NA

OK

PL

Output /Remarks

Remarks: Type of Test:

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28946).

BDEWC Commissioning

413/4

OE:898544068

Function Test Report P05B Witnessed Joint MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1248951360

ObjectID: RTP-GORA-2 System: 33 - CONDENSATE IMPORT/EXPORT Package: 33C01 PIDNo: Item 01 02 03 04 05 06 07 08 09 10 11 12 Flange description/ID::

Description: GORA Reinstatement Test Pack - 33 Sub System: Area: Joint desciption :: NA OK PL Output /Remarks 33C - MEPA CONDENSATE RECEIVING FACILITIES AT GORA

13

14 15

Description Prior to reinstatement, the following checks will be made: Flange faces examined and seen to be clean and damage free. Gaskets examined and seen to be clean, damage free and the correct type and size. Nuts and stud bolts examined and seen to be undamaged and correct size and type. Flange faces parallel. Joint pulled up evenly on opposing stud bolts. All nuts pulled up to required tightness. No visible damage to gasket when joint completed. Minimum of one thread proud of all nuts. No excessive length of stud bolt protruding through each nut. Torquing/ tension certificate complete and flange management tag fitted (if specified in project requirements) Post reinstatement, the following checks will be made: Circle one item from list below: - N2 Helium leak test / Service test / Nil / Soapy bubble leak test / - check with hand held gas detector after introduction of gas / - other (provide details)..... Post reinstatement test described in line 10 completed satisfactorily Attach supporting documentation for post reisnstement test to this sheet

Remarks:

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC Commissioning

414/4

OE:-1248951360

Function Test Report P04B N2 LEAK TEST MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1248939584

TestPack No: RTP-GORA-2 System: 33 - CONDENSATE IMPORT/EXPORT Package: 33C01 PIDNo: Test temperature: Design Pressure (MAWP): Chart Reference: TestDuration: Operational Flow Medium: Design temperature: Recorder Serial No.:

Description: GORA Reinstatement Test Pack - 33 Sub System: Area: TestPressure: Gauge Serial No.: TestMedium: 33C - MEPA CONDENSATE RECEIVING FACILITIES AT GORA

LineNo
100-PL-3323-C1Y-1 100-PL-3323-C1Y-2 150-PL-3308-C8Y-1 150-PL-3308-C8Y-2 150-PL-3308-C8Y-3 200-PL-3315-C8Y-1 200-PL-3315-C8Y-2 200-PL-3315-C8Y-3 200-PL-3315-C8Y-4 200-PL-3315-C8Y-5 200-PL-3315-C8Y-6 200-PL-3315-C8Y-7 50-PL-3322-C8Y-1 50-PL-3322-C8Y-2 50-PL-3322-C8Y-3 50-PL-3322-C8Y-4

Description
GORA - PIG RECEIVER R-3390 LINE FROM HV-33311 TO HV-33313 GORA - PIG RECEIVER R-3390 LINE FROM HV-33311 TO HV-33313 GORA - PIG RECEIVER R-3390 LINE FROM SBT-3302 TO HV-33300 GORA - PIG RECEIVER R-3390 LINE FROM 150-PL-3308-C8Y-1 TO HV-33301 GORA - PIG RECEIVER R-3390 LINE FROM 150-PL-3308-C8Y-2 TO SOC-3304 GORA - PIG RECEIVER R-3390 LINE FROM SDV-3390 TO HV-33302 GORA - PIG RECEIVER R-3390 LINE FROM SDV-3390 TO HV-33302 GORA - PIG RECEIVER R-3390 LINE FROM SDV-3390 TO HV-33302 GORA - PIG RECEIVER R-3390 LINE FROM SDV-3390 TO HV-33302 GORA - PIG RECEIVER R-3390 LINE FROM SDV-3390 TO HV-33302 GORA - PIG RECEIVER R-3390 LINE FROM SDV-3390 TO HV-33302 GORA - PIG RECEIVER R-3390 LINE FROM HV-33302 TO HV-33304 GORA - PIG RECEIVER R-3390 LINE FROM HV-33306 TO HV-33307 GORA - PIG RECEIVER R-3390 LINE FROM HV-33306 TO HV-33307 GORA - PIG RECEIVER R-3390 LINE FROM HV-33306 TO HV-33307 GORA - PIG RECEIVER R-3390 LINE FROM HV-33306 TO HV-33307

P&ID
06001-GORA-EG-PR-DWG-PNID-0010 06001-GORA-EG-PR-DWG-PNID-0010 06001-GORA-EG-PR-DWG-PNID-0010 06001-GORA-EG-PR-DWG-PNID-0010 06001-GORA-EG-PR-DWG-PNID-0010 06001-GORA-EG-PR-DWG-PNID-0010 06001-GORA-EG-PR-DWG-PNID-0010 06001-GORA-EG-PR-DWG-PNID-0010 06001-GORA-EG-PR-DWG-PNID-0010 06001-GORA-EG-PR-DWG-PNID-0010 06001-GORA-EG-PR-DWG-PNID-0010 06001-GORA-EG-PR-DWG-PNID-0010 06001-GORA-EG-PR-DWG-PNID-0010 06001-GORA-EG-PR-DWG-PNID-0010 06001-GORA-EG-PR-DWG-PNID-0010 06001-GORA-EG-PR-DWG-PNID-0010

Comment

Item 01 02

Description Leak test completed and certificate attached to this sheet All witness joints entered into Witness Joint Register and copy attached to this sheet.
Service Test Reinstatement Leak Test (N2He) (Delete as appropriate) 1. Line valves confirmed half open for test (to test stem packing) . 2. Isolation valve integrity test to be conducted.

NA

OK

PL

Output /Remarks

Remarks: Type of Test:

BDEWC QA/QC Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28946).

BDEWC Commissioning

415/4

OE:-1248939584

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:690104358

ObjectID: YAFC-0001 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92A02 CableType: ToTag: x Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Telecom Cables Sub System: 92A - DMR SYSTEM Area: FromTag: VoltageRating: Size: NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

416/4

OE:690104358

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1457379294

ObjectID: YAFC-0002 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92A02 CableType: ToTag: x Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Telecom Cables Sub System: 92A - DMR SYSTEM Area: FromTag: VoltageRating: Size: NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

417/4

OE:-1457379294

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:690104369

ObjectID: YAFC-0006 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92E01 CableType: ToTag: x Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Telecom Cables Sub System: 92E - GOPB TELECOM Area: FromTag: VoltageRating: Size: NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

418/4

OE:690104369

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1763846154

ObjectID: YAFC-0007 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92E01 CableType: ToTag: x Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Telecom Cables Sub System: 92E - GOPB TELECOM Area: FromTag: VoltageRating: Size: NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

419/4

OE:1763846154

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:1761748666

ObjectID: YDEE-0007 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92C02 CableType: ToTag: x Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Telecom Cables Sub System: 92C - UHF/VHF SYSTEM Area: FromTag: VoltageRating: Size: NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

420/4

OE:1761748666

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-1445829582

ObjectID: YUHF-0002 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92C02 CableType: ToTag: x Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Telecom Cables Sub System: 92C - UHF/VHF SYSTEM Area: FromTag: VoltageRating: Size: NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

421/4

OE:-1445829582

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:-372087761

ObjectID: YUHF-0003 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92C02 CableType: ToTag: x Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Telecom Cables Sub System: 92C - UHF/VHF SYSTEM Area: FromTag: VoltageRating: Size: NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

422/4

OE:-372087761

Inspection Test Report E02A Cable < 1000 Volts MERAPUH-A (MEPA) PRODUCTION TOPSIDE FACILITIES
OE:701659830

ObjectID: YVHF-0001 System: 92 - TELECOMMUNICATIONS SYSTEM Package: 92C02 CableType: ToTag: x Item 01 02 03 04 05 06 07 08 09 10
Notes:

Description: Telecom Cables Sub System: 92C - UHF/VHF SYSTEM Area: FromTag: VoltageRating: Size: NA OK PL Output /Remarks

Description Installation as per AFC Drawings and data sheets Cable properly glanded and terminated Cable glands suited to hazardous are classification Cable correctly numbered, tagged at both ends and at specified intervals Cable racks adequately supported, bonded and visibly earthed Cable neatly laid and strapped to rack Destination of cable and phasing confirmed by continuity test Perform insulation resistance test, indicate number of cores and identification method, colour or numbered cores Test voltage <=1000V Record values Discharge all cores to ground Replace all equipment covers, check bolts washers etc. are reinstated correctly

Cable bending radii to be as per vendor recommendations ______________________________________________________________________________________________________________________

Remarks:

______________________________________________________________________________________________________________________ Test Equipment :

BDEWC Construction Name: Signature: Date:


Printed by: Montaha, Nasrun. 16-Mar-2013 09:12, (ID=28922).

BDEWC QA/QC

BDEWC Commissioning

423/4

OE:701659830