SUBMITTAL FORM

BATHEAY REFERRAL HOSPITAL PROJECT


TO: Attention: KOICA Representative KIM SANG JUN RO HI YOUL Subject: Deputy Representative TOPEC CM Document Type We would like to submit you the Weekly Progress Report (WR44) for November 2013. Please find attached report. For Thank you for your good cooperation, Action Status KOICA's Comment: Received by Date: Reviewed by Position: Approved by Schedule Calculation Sample Report Proposed Review Approved 1 = No. Objection 2 = No. Objection with Comment 4 = Objection 5 = Return to Contractor (Resubmit) Drawing Quality Document Catalogue Method Statement Information Record Submission Date: Submission No.: 10-Nov-2013 HSBA-121

Weekly Progress Report (WR44)

FOR KOICA USE

Project Manager/ HWASHIN

TAI GONE, WON

Position:

WEEKLY PROGRESS REPORT (WR44)


BATHEAY REFERRAL HOSPITAL PROJECT DESCRIPTION THIS WEEK (2013.11.03-11.09)
1. Site Survey Work 2. Balcony Beam & Slab Concrete

NEXT WEEK (2013.11.10-11.16)


1. Site Survey Work 2. 2nd Floor Beam & Slab Part A Rebar Work 3. Air-con Room Beam & Slab Rebar Work 4. 2nd Floor Beam & Slab Part A Concrete 5. Air-con Room Beam & Slab Concrete 6. Laying Brick Work for Ground Floor & 1st Floor 7. Install Water Pipe System for Ground Floor & 1st Floor 8. Install Embedded Electrical Pipe for Slab & Wall 9. Curing Water for 2nd Floor Slab

REMARK

TEMPORARY WORK CONCRETE WORK & MASONRY WORK

3. 2nd Floor Beam & Slab Part B Concrete 4. 2nd Floor Beam & Slab Part A Formwork 5. Air-con Room Beam & Slab Formwork 6. Laying Brick Work for Ground Floor & 1st Floor 7. Install Water Pipe System for Ground Floor & 1st Floor 8. Install Embedded Electrical Pipe for Slab & Wall 9. Curing Water for 2nd Floor Slab Part B

SAFETY STATUS PERCENTAGE (DONE/PLAN) SPECIAL ITEMS

None ( 43.80% / 49.15% )

1. MR. RO HI YOUL Visit Site for 2nd Floor Beam, Slab Part B & Balcony Inspection: 14:00 06-Nov

MONTHLY SCHEDULE (NOVEMBER)


Date: 31-Oct-2013 DESCRIPTION
Site cleaning Line marking Form support External Scaffolding Earth work Level extension work Ground floor con'c First floor con'c ARCHITECTURAL WORKS Under roof con'c 2nd floor slab con'c Roof column con'c Steel frame work Masonry work Tiling work Carpentry work Waterproof work Roofing work Metal work Plaster work Door & window work Glazing work Painting work MECHANICAL WORKS ELECTRICAL WORKS 34.50 37.30 40.10 42.90 45.70 49.15 52.60 PERCENTAGE (Plan/Done) 31.20 32.70 35.80 38.20 40.90 43.80 56.05 59.50 62.10 64.70 67.30 69.90 72.50 Finished Finished Finished Finished Finished

OCTOBER

NOVEMBER

DECEMBER

9/29-10/5 10/6-10/12 10/13-10/19 10/20-10/26 10/27-11/2 11/3-11/9 11/10-11/16 11/17-11/23 11/24-11/30 12/1-12/7 12/8-12/14 12/15-12/21 12/22-12/28 12/29-1/4

REMARK