Method Statement for Osaka J apan Since 1919

Electrical work Related to Doc. Ref. : MS – NSPS - EL – 03


replacement of MCC in New Date : 31.12.2008
GTC71 / 2005
Salwa pumping station : .Rev

1.0 Replacement of MCC

The present status of existing MCC is Transformer 1 & 2 ( NA5 & NA11 ) & bus coupler (NA6)
were in on condition and bus coupler (NA10) is in switched off condition.

Sr.No Activity Day / Time

1 Installation of new 11 KV switchgear and pre commissioning to be completed

Lay the LV cable to new DB in 11 KV switch gear room from existing MCC and
2
energize the Battery charger for switchgear protection.

Lay the new LV cable from new MCC to pump numbers 3, 4,6,7,8 & 9 and terminate
3
the power cable in the MCC side... Refer drawing number

Lay and terminate 11 KV cable between 11 KV switchgear and transformer number –


4
3 and terminate the cable at both the end.

Reroute the 2 numbers of 11KV cable ( Ring ) from Existing 11 KV switchgear to


5 new switchgear and commission the new switchgear by ENA approved contractor by
taking PTW..

Arrange for the inspection of MCC panel by Kahramaa customer department and
6
install the new KWH meter.

Commission the transformer – 3 after checking the protection interlock and energize
7
the MCC pertaining to TX- 3

Shift the VFD connection for pump number 4 from existing MCC ( NA12) to new
8
MCC (Q48) by taking PTW

Shift the VFD connection for pump number 8 from existing MCC ( NA17) to new
9
MCC (Q49) by taking PTW

Shift the VFD connection for pump number 9 from existing MCC ( NA18) to new
10
MCC (Q50) by taking PTW

Switch on the bus coupler between Transformer 2 & 3 (QB2) and energize the bus
11
bar of Transformer – 2 and ensure that QM2 in switched off condition

-1-
Method Statement for Osaka J apan Since 1919
Electrical work Related to Doc. Ref. : MS – NSPS - EL – 03
replacement of MCC in New Date : 31.12.2008
GTC71 / 2005
Salwa pumping station : .Rev

1.0 Replacement of MCC - Contd.

Sr.No Activity Day / Time

Shift the VFD connection for pump number 7 from existing MCC ( NA13) to new
12
MCC (Q24) by taking PTW

Lay and terminate 11 KV cable between 11 KV switchgear and transformer number –


13 2 and terminate the cable at both the end, by ENA department approved
Contractor by taking PTW.

14 Commission the transformer – 2 after checking the protection interlock. .

Switch off existing transformer number – 2 after obtaining approval from ENA
15 department. Arrange to remove the KWH meter by the Meter Section of customer
department by submitting all relevant documents.

Arrange for the inspection of part of MCC panel (Transformer – 2) by Kahramaa


16
customer department and install the new KWH meter.

Switch off bus coupler (QB2) and energize the bus bar pertaining to TX- 2.by
17
switching on QM2

Ensure that Bus coupler ( NA10 ) should be in switched off condition and remove the
18
part of existing MCC ( NA11, NA12, NA13, NA17 & NA18 ) by obtaining PTW.

Install last part of new MCC (Q1 to Q4 ) and complete the installation pertaining to
19
transformer – 1 section

Shift the VFD connection for pump number 6 from existing MCC ( NA4) to new MCC
20
(Q23) by taking PTW

Shift the VFD connection for pump number 7 from existing MCC ( NA13) to new
21
MCC (Q24) by taking PTW

22 Switch on the bus coupler (BC1) of new MCC

-2-
Method Statement for Osaka J apan Since 1919
Electrical work Related to Doc. Ref. : MS – NSPS - EL – 03
replacement of MCC in New Date : 31.12.2008
GTC71 / 2005
Salwa pumping station : .Rev

1.0 Replacement of MCC - Contd.

Sr.No Activity Day / Time

Shift the VFD connection for pump number 1 from existing MCC ( NA16) to new
23
MCC (Q19) by taking PTW

Shift the VFD connection for pump number 2 from existing MCC ( NA1) to new MCC
24
(Q20) by taking PTW

Shift the VFD connection for pump number 5 from existing MCC ( NA3) to new MCC
25
(Q21) by taking PTW

Shift all auxiliary loads from existing MCC to new MCC – Refer method statement
26
MS – NSPS – EL – 04.

Lay and terminate 11 KV cable between 11 KV switchgear and transformer number –


27 1 and terminate the cable at both the end, by ENA department approved
Contractor by taking PTW.

28 Commission the transformer – 1 after checking the protection interlock. .

Switch off existing transformer number – 1 after obtaining approval from ENA
29 department. Arrange to remove the KWH meter by the Meter Section of customer
department by submitting all relevant documents.

Arrange for the inspection of part of MCC panel (Transformer – 1) by Kahramaa


30
customer department and install the new KWH meter.

Switch off bus coupler (QB1) and energize the bus bar pertaining to TX- 1.by
31
switching on QM1

Reroute the balance 11KV cables from Existing 11 KV switchgear to new


32
switchgear by ENA approved contractor by taking PTW from ENA department.

Arrange to remove balance part of existing MCC, transformers and existing 11 KV


33
switchgear to hand over to Kahramaa’s store