Академический Документы
Профессиональный Документы
Культура Документы
V = Velocity in m/s R = Hydraulic Radius, m S = Slope in m/1000m Assume, n = 0.013 Assume circular sewer
Design Average Water Supply (in Year 2023) = 45,000.(240) = 10.8 million liters/day Assuming 80 percent water becomes wastewater, Design Average Wastewater Generation = 10.8.(0.8) = 8.64 million liters per day Assuming a Peaking Factor of 3, Design Peak Wastewater Generation = 3.(8.64) = 25.92 million liters per day Design Peak Wastewater Generation = For a pipe flowing full:
At q = 0.3 m3/s, the pipe is flowing 0.8 full When, Assuming, n = 0.013, Solving, . Therefore,
; Therefore, vDesign = Velocity at design peak flow = (1.076).(1.1) = 1.184 m/s (which is within the recommended range of 0.8 m/s to 3 m/s)
At present peak flow, ; corresponding Therefore, vpresent = velocity at present peak flow = (0.65).(1.076) = 0.699 m/s (which is greater than the recommended minimum value of 0.6 m/s)
Hence use 700 mm circular concrete pipe at a slope 0f 2 m per 1000 m for accommodating the above flow. 2. Consider the sewer system shown in the figure below. A main sewer (MS5) with manholes, M5.4 (starting manhole) to M 5.1 discharges into manhole M5 of the trunk sewer. Branch sewers discharge into manhole M5.1 M5.4 of the main sewer (MS5) as shown in the figure. Invert levels of the branch sewers discharging into manhole M5.4 M5.1 are 97.223, 98.775, 98.311, and 96.334 m respectively. Invert level of the trunk sewer leaving manhole M5 is 93.700 m. Based on this information explain how values in the last three columns of the design table for main sewer (MS5) have been calculated. All branch sewers have 400 mm diameter. The ground level in the area under question is between 101 and 102 m.
Table 1.
1 2
Solution: Elevation of the centerline of branch sewer at manhole M5.4 = 97.223 + 0.2 = 97.423 Elevation of centerline of the upper end of the main sewer from M5.4 to M5.3 = 97.423 0.4 = 97.023 Invert level of the upper end of the main sewer for M5.4 to M5.3
= 97.023 0.25 = 96.773 Fall from M5.4 to M5.3 = 88.(0.002) = 0.176 Invert level of the lower end of the main sewer for M5.4 to M5.3 = 96.773 0.176 = 96.597 Invert level of the upper end of the main sewer for M5.3 to M5.2 = 96.597 0.2 = 96.397 Considering the above invert level, minimum invert level of the branch sewer at M5.3 should be 96.397 + 0.35 + 0.4 0.2 = 96.957, while the actual invert level is 98.775. Hence okay. Fall from M5.3 to M5.2 = 77.(0.002) = 0.154 Invert level of the lower end of the main sewer for M5.3 to M5.2 = 96.397 0.154 = 96.243 Invert level of the upper end of the main sewer for M5.2 to M5.1 = 96.243 0.03 = 96.213 Considering the above invert level, minimum invert level of the branch sewer at M5.2 should be 96.213 + 0.35 + 0.4 0.2 = 96.763, while the actual invert level is 98.311. Hence okay. Fall from M5.2 to M5.1 = 101.(0.002) = 0.202 Invert level of the lower end of the main sewer for M5.2 to M5.1 = 96.213 0.202 = 96.011 Invert level of the upper end of the main sewer for M5.1 to M5 = 96.011 0.1 = 95.911 Considering the above invert level, minimum invert level of the branch sewer at M5.1 should be 95.911 + 0.4 + 0.4 0.2 = 96.511, while the actual invert level is 96.334. Hence not okay. Hence, actual invert level of the upper end of the main sewer for M5.1 to M5 = 96.334 + 0.2 0.4 0.4 = 95.734 Fall from M5.1 to M5 = 122.(0.002) = 0.244 Invert level of the lower end of the main sewer for M5.1 to M5 = 95.734 0.244 = 95.490