ZONE:HASSAN Details of LIST-I works under APW 13-14
Cost. of Dept. Supply Materials and others Cumulative Expenditure as on 31.03.13 Indicate whether the works are Expenditure % Expenditure 1. physically completed or incurred during over allocated 2. financially closed or the year budget 13-14 3. both physically and financially closed Remarks
Rs. In Lakhs
Sl. No.
Work code
District
Cost of DWA
CR Patna (Yachanahalli): Establishing 2x100MVA, 220/66kV Station with 220kV LILO line from Hootagalli- Hassan CA1004 Shimoga 220kV DC line (one Ckt. LILO). Brahmavara: Up-grading 2x5MVA, 33/11kV MUSS to 2x10MVA, 110/11kV CC1001 Sub-Station withtap line from Hassan Manipal - Nittur line, 2nd circuit from Manipal & TB at Manipal. Nandikur: Establishing 1x10MVA, 110/11kV & 1x20MVA, 110/33kV Sub-Station with 110kV DC line on 220/110kV CC1002 MC towers from 220kV Khemar Hassan Station to proposed 110/33/11kV Nandikur S/S and providing 2nos of 110kV TB at 220kV Khemar S/S . Navunda: Establishing 1x10MVA, 110/11kV & 1x20MVA, 110/3311kV Sub-Station with tap from Hiriyadka - Kundapura line.
3064.00
3238.52
38
3276.52
S/S-M/s BHEL 220kV line: Sagar steels 66kV Line: Transglobal M/s TB: Shreem Capacitors
2861.00
116.00
0.01
0.01
1258.02
800.27
151.56
951.83
M/s DCIL
811.86
86.00
3384.57
2462.15
162.99
2625.14
M/s DCIL
2464.73
111.00
0.99
0.89
Commissioned on
CC1008
Hassan
2100.85
1425.72
128.82
1248.93
172.00
8.60
1) Jelly spreading 2) Repl of battery 3)Arresting the gas leakage of 33kV bank breaker 4) Repairing of the limb of the line breaker 5) Storm water drainage 6) painting of control room 7)Providing bolt 7 nuts to security fencing 8) Providing collapsable gate to control room.
Shiralkoppa: Establishing 2x100MVA, CD1008 220/110kV Station with 220kV Hassan LILO SVP - Ranebennur line. Essur: Establishing 1x10MVA, CD1010 110/11kV Sub-Station with tap Hassan line from Shiralakoppa Shikaripura line.
5628.21
3620.82
1330.95
4696.91
255.00
16.94
6.64
Commissioned on 30.01.2009. Physically completed & No bills pending except LD amount of Rs. 255 lakhs.
629
461
206
666.96
427.53
5.00
- Commissioned on 19.02.2009
Mallapura: Establishing 1x8MVA, 66/11kV CD1011 Sub-Station with LILO line from Hassan Shimoga- Honnali line. Chandragutti: Establishing 1x10MVA, CD1020 110/11kV Sub-Station with Hassan 110kV tap line from Jog - Sirsi LILO line. Singatagere: Establishing 1x10MVA, 110/11kV Sub-Station with CE1005 Hassan 110kV SC line on DC towers from Yagati & TB at Yagati. Hirenallur: Establishing 1x10MVA, 110/11kV Sub-Station with tap CE1006 line from Birur - Anjanapura Hassan line.
330
369
229
597.70
550.84
47.00
31.54
67.11
750
517
190
706.84
605.77
61.50
41.56
67.58
582
587
151
738.23
645.07
9.50
- Physically completed
611
398
138
535.74
383.10
40.02
0.72
Commissioned on 31.03.2009 Physically completed. QV to be submitted. 1.80 Requisit documents is not furnished by the agency to TA&QC for conducting inspection. Stn. With line Commissioned on 19.07.08.
Kadavina Kote: Establishing 2x100MVA, 220/66kV Station with 220kV CA1027 Hassan line from Shimoga - Mysore line with associated 66kV lines KIADB Hassan: Establishing 2x12.5MVA, Hassan 66/11kV Sub-Station with associated line. Hosur: Establishing 1x10MVA, 110/11KV Sub-Station with CD1032 Hassan tapping from 110kV Kittadahalli -Shikaripura SC line CA1038 Total of Sub-stations Talaguppa: CD1013 Providing 3rd 315MVA, Hassan 400/220kV Transformer Mandli: Replacing 1x10MVA, 110/11kV CD1031 Hassan by 1x20MVA, 110/11kV transformer Muthinakoppa: Providing additional 1x10MVA, CE1010 Hassan 110/11kV transformer Machenahalli: Replacing 1x10MVA, by 1x20MVA, transformer Nittur: Replacing 1x10MVA, by 1x20MVA, CC1014 Transformer CE1020 110/11kV Hassan 110/11kV
7252
6137
157
6136.68
60.00
49.04
557
519
25
544.40
M/s Anil Electricals & Sanitary Goods stores M/s Bharth Electrical Contractors & Manufacturers Pvt Ltd.,
440.04
104.00
83.93
80.70
Commissioned on 13.02.2013.
554
501
37
537.78
377.68
160.00
12.18
26,700.88 1550
21,036.14 1460
2,945.14 23981.28
1460.35 M/s BHEL
21,650.14 1186.54
1,227.02 4.16
245.51 4.16
271.71
55.79
121.00
176.79
149.38
10.00
2.34
168.00
110.25
3.55
113.80
109.75
0.32
- Physically completed.
202.96
37.20
141.93
179.13
140.29
5.50
1.41
25.64
110/11kV 110/11kV
Hassan
157.81
7.80
128.95
136.75
107.28
30.00
1) Erection of nitrogen fire extinguisher 2) Erection and commissioning of NCT 3)Allignment of 11kV cables
165.67
16.78
146.94
163.72
Tr Commissioned on
128.53
35.00
22.10
CE1025
Muthinakoppa: Replacing 1x10MVA, 110/11kV by Hassan 1x20MVA, 110/33kV transformer Total of Augmentations
1) Nitrogen fire extinguisher is to be provided, erected & commd 2) Trafo guard system for protection of the power transformer is to be commissioned. _
154.17
3.25
128.46
131.71
113.76
0.65
0.63
96.92
2,670.32
1,691.42
670.83
2362.25
1,935.53
85.63
30.64
35.78
Termination of the line to the gantry is pending for the want of completion of 3Nos of terminal bays at Konaje which was awarded to M/s Pushpa Electricals & work is under progress.
Kavoor - Puttur line to Konaje: Construction of 110kV SC link line on DC towers tapping the CB1011 exisiting 110kV SC Kavoor - Hassan Puttur line to 110kV Konaje Station (0.414KM) NPCL - KEMAR : Construction of 220kV DC on CC1006 partly DC & MC towers from Hassan UPCL-Khemar Sub-Station with TBs at Khemar Varahi - Shimoga: Construction of 220kV DC line CD1014 from Varahi to Shimoga & Hassan dismantling of 110kV SC line with T.B. Bhadra Hydel Station to Chickmagalur: Construction of 66kV DC line with Coyote ACSR in the CE1001 existing corridor between Hassan Bhadra Hydel Station to Chickmagalur Sub-Station via Lingadahalli. Comprehensive Scheme for Jog Evacuation: 1) Jog to Sagar : Construction of 110kV MC line (in existing corridor) with TBs at JOG. CD1012 2) Sagar to MRS : Coverting Hassan 110kV SC line to DC line 3) Sagar : Providing 110kV TBs. Total of Lines Shanthigrama: CA1029 Construction of 400kV & 220kV Hassan TBs. JOG: Providing protection devices for CD1019 Hassan 110kV JST1 LILO line Total of 'TB's and Others Total for Hassan Zone
26
54
10
64.57
M/s DCIL
40.55
18.00
Commissioned on 25.03.2009.
1434
1287
928.00
122.00
7.78
6.38
5496
554
269
822.55
378.90
51.20
40.86
729
897
64
961.56
M/s DCIL
889.00
30.00
8080
6618
367
6299.00
585.50
291.35
49.76
15,764.13 2000
9,411.23 2000
713.85 10125.08 0
DCW work 2000.00 executed by M/s PGCIL M/s Tejaswini Electricals
8,535.45 1789.00
806.70 -
339.99
42.15 _
Commissioned on 25.08.2012. Physically & fiancially closed. Commissioned on 02.03.13. Physically completed. QV to be approved. (Financially to be closed)
81 2,081 47,217
52 2,052 34,190
24
75.31
7.84 7.84
28.96
As on 31.08.2013
Rs. In Lakhs
Remarks
Time extension proposal yet to be approvedto release the LD amount. The time extension proposal placed before CPC.
Price variation bill is submitted for audit verification.Bill will be released after audit verification.
Since balance works are not completed, final quantity variation is yet to be prepared .
Bills to be submitted.
QV pending
QV bills pending
QV bills approval pending. 1) Supply, Civil & erection bills yet to be received. 2)10% price variation bills yet to be received. 3) PV for supply of power transformer is yet to be received.
1) Supply, Civil & erection bills yet to be received. 2) Retension bill & price variation bills of Tr yet to be received. 3) QV yet to be received. a) B.R.No: 228/12.06.2013- Rs. 27,500/b) B.R.No: 373/ 30.07.2013-Rs. 500.00
Qty Var submitted to CEE/T&P/B'lore, to be approved. 2) PV bill submitted for audit verifacation, to be sanctioned.