Вы находитесь на странице: 1из 2

PROJECT:

KAIA DEVELOPMENT PROJECT - PHASE 1


Activity ID

Activity Name

OD

PACKAGE 422 (3
(3-Week Look Ahead)-WEEK 151 (DD 02/Dec/2013)

07-Jan-14

115.00

32.00

06-Oct-13 A

07-Jan-14

115.00

32.00

06-Oct-13 A

07-Jan-14

98.80

32.00

28-Oct-13 A

07-Jan-14

Remaining Backfilling around the Central Switch Hall

8.00
44.00

8.00
19.00

02-Dec-13
29-Oct-13 A

10-Dec-13
23-Dec-13

Removal of Scaffolding at the corridor areas (Closer To SEC Tunnels)

12.00
18.00

0.00
1.80

18-Nov-13 A
03-Nov-13 A

28-Nov-13 A
03-Dec-13

100%

High Level MEP Works (Cable Trays, Ducting and Piping) (3)

18.00
18.00

1.80
7.00

03-Nov-13 A
29-Oct-13 A

03-Dec-13
09-Dec-13

90%

High Level MEP and Painting Works (Supports and Cable Trays are in progress) (1)

18.00
18.00

7.00
7.00

29-Oct-13 A
29-Oct-13 A

09-Dec-13
09-Dec-13

61.11%

High Level MEP Works (Cable Trays, Ducting and Piping)

18.00
12.00

7.00
12.00

29-Oct-13 A
10-Dec-13

09-Dec-13
23-Dec-13

61.11%

Ground Level: Slab Form work(2)

12.00
98.80

12.00
32.00

10-Dec-13
28-Oct-13 A

23-Dec-13
07-Jan-14

0%

Basement Floor
Part 01
Part 03
422P-140290

Part 04
422P-140310

Part 06
422P-140230

Ground Floor

45.46

19.00

17-Nov-13 A

23-Dec-13

18.00
2.00
18.00

17.00
2.00
18.00

17-Nov-13 A
22-Dec-13
17-Nov-13 A

21-Dec-13
23-Dec-13
22-Dec-13

5.56%
0%

Roof Slab: Beams and Slab Reinforcement (3)

18.00
18.00

18.00
18.00

17-Nov-13 A
02-Dec-13

22-Dec-13
22-Dec-13

0%

Remaining Vertical Elements (3)


Roof Slab: Scaffolding & Formwork (2)

12.00
6.00
18.00

12.00
6.00
18.00

02-Dec-13
16-Dec-13
02-Dec-13

15-Dec-13
22-Dec-13
22-Dec-13

0%
0%

Remaining Vertical Elements (3)


Roof Slab: Scaffolding & Formwork (2)

12.00
6.00
98.80

12.00
6.00
32.00

02-Dec-13
16-Dec-13
28-Oct-13 A

15-Dec-13
22-Dec-13
07-Jan-14

0%
0%

Vertical Elements (Middle Portion)


Roof Slab: Scaffolding & Formwork (2)
Roof Slab: Reinforcement (2)

18.00
6.00
18.00
55.00

8.00
6.00
18.00
28.00

28-Oct-13 A
11-Dec-13
18-Dec-13
23-Oct-13 A

10-Dec-13
17-Dec-13
07-Jan-14
02-Jan-14

33%
0%
0%

18.00

18.00

24-Nov-13 A

22-Dec-13

18.00

12.00

24-Nov-13 A

15-Dec-13

Highlevel Cable Traying, Trunking, Ducting and piping (before & along with Blockwall work

18.00
18.00

12.00
18.00

24-Nov-13 A
02-Dec-13

15-Dec-13
22-Dec-13

0%

Blockwall Works

18.00
28.00

18.00
28.00

02-Dec-13
24-Nov-13 A

22-Dec-13
02-Jan-14

0%

Part 02
422P-140770

Part 03
422P-140780
422P-140360

Part 04
422P-140790
422P-140390

Part 05
422P-140720
422P-140740
422P-140750

Office Building
Ground Floor (Including
(Includ
Roof Slab)
MEP
422-CN-C120-31-3032

Finishes
422P-140430-1

First Floor

28.00

28.00

24-Nov-13 A

02-Jan-14

Highlevel Cable Traying, Trunking, Ducting and piping (before & along with Blockwall work
Highlevel MEP and Finishes (After Blockwall Works)

18.00
18.00
12.00

12.00
18.00
10.00

24-Nov-13 A
14-Dec-13
24-Nov-13 A

15-Dec-13
02-Jan-14
12-Dec-13

0%
0%

Block wall Works (Closer to Central Switch Hall) (After 1.2m height)

12.00
18.00

10.00
9.00

24-Nov-13 A
23-Oct-13 A

12-Dec-13
11-Dec-13

5%

Scaffolding and formwork for roof slab

18.00
25.00

9.00
19.00

23-Oct-13 A
18-Nov-13 A

11-Dec-13
23-Dec-13

50%

Raft at the Connection of Left and Right Wing to Areas 1 and 2 resp. and mid tunnel

18.00
17.00

8.00
17.00

18-Nov-13 A
24-Nov-13 A

10-Dec-13
21-Dec-13

55.56%

2.00
8.00
6.00
8.00
19.00

2.00
6.00
6.00
8.00
19.00

02-Dec-13
24-Nov-13 A
05-Dec-13
12-Dec-13
24-Nov-13 A

03-Dec-13
08-Dec-13
11-Dec-13
21-Dec-13
23-Dec-13

0%
25%
0%
0%

MEP
422-CN-C120-31-3042
A18200

Finishes
422P-1123223

Third Floor
422P-140420

Generator Building
422P-140810

Ground Floor - Area 01


A15840
A123434
A15860
A17300

Concreting For Vertical Elements till GF level


Reinforcement & Concrete For RC Plinths (Transformer Area)
Reinforcement & Concrete For 300mm Ground Bearing Slab
Reinforcement & Concrete For Vertical Elements till GF level

Ground Floor - Area 02


Remaining Work
Actual Work
Critical Remaining...

Data Date : 02-Dec-13


Project Start : 11-Jan-11
Project Completion : 9-Jan-14

Nov 23
M T W Thr Fri Sat S

Three Week Look Ahead Schedule


Page 1 of 2

Nov 30
M T W Thr Fri Sat S

2013
Dec 07
M T W Thr Fri Sat S

Dec 14
M T W Thr Fri Sat S

Dec 21
Dec 28
M T W Thr Fri Sat S M T

0%

Roof Slab: Reinforcement (3)


Slab Concrete

Part 01
422P-140760
422P-128164

Activity %
Complete

06-Oct-13 A

Central Switch Hall

422P-140510

Finish

32.00

Construction

422P-140800

Start

115.00

Load Center " B "( Zone Manager- Eng Hani Mahgoub)

A19790

RD

Date
02-Dec-13

Revision
Three Week Lookahead Schedule

Checked

Approved

PROJECT:
KAIA DEVELOPMENT PROJECT - PHASE 1
Activity ID

Activity Name

422-CN-C120-31-3052
422-CN-C120-31-3092
A17310
A15880

08-Dec-13
11-Dec-13
21-Dec-13
23-Dec-13
08-Dec-13

25%
0%
0%
0%

Reinforcement For RC Plinths (Transformer Area)

8.00
8.00

6.00
6.00

24-Nov-13 A
24-Nov-13 A

08-Dec-13
08-Dec-13

0%

Reinforcement For RC Plinths (Transformer Area)

8.00
53.36

6.00
25.20

24-Nov-13 A
10-Nov-13 A

08-Dec-13
31-Dec-13

0%

53.36

25.20

10-Nov-13 A

31-Dec-13

9.00

9.00

24-Nov-13 A

11-Dec-13

2.00
9.00
9.00
53.36

2.00
9.00
9.00
25.20

02-Dec-13
24-Nov-13 A
24-Nov-13 A
10-Nov-13 A

03-Dec-13
11-Dec-13
11-Dec-13
31-Dec-13

0%

14.00
53.36
14.00

5.60
25.20
2.80

14-Nov-13 A
10-Nov-13 A
10-Nov-13 A

08-Dec-13
31-Dec-13
04-Dec-13

60%

14.00
14.00
14.00
71.00

7.00
11.20
14.00
4.80

24-Nov-13 A
20-Nov-13 A
15-Dec-13
06-Oct-13 A

09-Dec-13
15-Dec-13
31-Dec-13
07-Dec-13

50%
20%
0%

18.00
12.00
68.92

2.00
4.80
15.00

06-Oct-13 A
28-Oct-13 A
23-Nov-13 A

03-Dec-13
07-Dec-13
18-Dec-13

75%
60%

68.92

15.00

23-Nov-13 A

18-Dec-13

6.00

6.00

02-Dec-13

08-Dec-13

0%

9.00
9.00
18.00

8.00
9.00
18.00

23-Nov-13 A
09-Dec-13
02-Dec-13

10-Dec-13
18-Dec-13
22-Dec-13

25%
0%

18.00

18.00

02-Dec-13

22-Dec-13

12.00
6.00
18.00

12.00
6.00
18.00

02-Dec-13
16-Dec-13
02-Dec-13

15-Dec-13
22-Dec-13
22-Dec-13

18.00

18.00

02-Dec-13

22-Dec-13

18.00
28.00

18.00
6.00

02-Dec-13
28-Oct-13 A

22-Dec-13
08-Dec-13

0%

9.00
9.00

1.00
6.00

28-Oct-13 A
21-Nov-13 A

02-Dec-13
08-Dec-13

85%
70%

Basement 02
422P-128425-11
Raft Concrete (on the Basement Service Gallery and B2 of DCP)
Area 05
422-CN-C120-31-3082 Walls and Columns (Near the 2nd area of the Basement Service Gallery) (2)

Mezzanine level
Slab/Beam Reinforcement
Slab Scaffolding/Form Work Area 01
Slab Scaffolding/Form Work Area 02
Slab/Beam Reinforcement Area 01
Slab/Beam Reinforcement Area 02

Basement Service Gallery


Gal
422P-140470
422P-140500

Highlevel Conduits & Piping


Area 3 : Vertical Elements

Workshop & Storage


Structural Works
A19510

Column Neck Construction (Area-01)

N17260
A17280

Footings - reinforcement, Formwork & Concrete (Area-01)


Backfilling to the bottom of the Bearing Slab level (Area-01)

Potable Water Pumping


Pumpin Station
Structural Works
N17390
A19750

Vertical Elements Reinforcement


Vertical Elements Formwork

Fire Water Pump Station


Stat
Superstructure
A17360

Roof Formwork & reinforcement

Precast Fence
422P-140480
422P-140490

Activity %
Complete

24-Nov-13 A
05-Dec-13
12-Dec-13
22-Dec-13
24-Nov-13 A

Structural Works

N234435
N22P-128425-1
N22P-1323423

Finish

6.00
6.00
8.00
2.00
6.00

District Cooling Plant

422P-128425-1
Mezzanine level
N22P-128415

Start

8.00
6.00
8.00
2.00
8.00

Right Wing
422-CN-C120-31-3062

RD

Reinforcement For RC Plinths (Transformer Area)


Reinforcement & Concrete For 300mm Ground Bearing Slab
Reinforcement For Vertical Elements till GF level
Concreting For Vertical Elements till GF level

Left Wing
422-CN-C120-31-3072

OD

Precast Column Placement and Grouting (55)


Precast Panels Installation

Remaining Work
Actual Work
Critical Remaining...

Data Date : 02-Dec-13


Project Start : 11-Jan-11
Project Completion : 9-Jan-14

Nov 23
M T W Thr Fri Sat S

2013
Dec 07
M T W Thr Fri Sat S

Dec 14
M T W Thr Fri Sat S

Dec 21
Dec 28
M T W Thr Fri Sat S M T

0%

80%

0%
0%

Three Week Look Ahead Schedule


Page 2 of 2

Nov 30
M T W Thr Fri Sat S

Date
02-Dec-13

Revision
Three Week Lookahead Schedule

Checked

Approved

Вам также может понравиться