Вы находитесь на странице: 1из 473

INDEX

RATE ANALYSIS FIRST HALF OF 2004 IN

Analysis (page) Summary (page)


1 DEMOLISHER 1--9 1--3
2 EXCAVATOR 10--11 4--4
3 CONCRETOR 12--23 5--7
4 BLOCK MASONRY 24--24 7--7
5 BRICKLAYER 25--30 8--9
6 MASON 31--31 9--9
7 PAVIOR 32--33 10--10
8 PLASTERER 34--39 11--12
9 ROOFER 40--42 13--13
10 CARPENTER & JOINTER 43--58 14--17
11 PAINTER & DECORATOR 59--64 18--19
12 BRASS FOUNDER 65--68 20--21
13 IRON MONGER 69--69 22--22
14 TINKER 70--71 22--22
15 PLUMBER 72--86 23--26
16 MISCELLANEOUS 87--90 27--27
17 ANGLE IRON 91--95 28--29
18 ALUMINIUM WORK 96--99 30--30

Analysis 1st half - Mullaitivu


Page 2 of 473

SUMMARY.

APPROVED B.S.R FOR THE FIRST HALF 0F 2004 IN


DEMOLISHER.
NO DESCRIPTION OF WORK UNIT RATE (1st)
1/1 Brick work in Cement, demolished brick Cube 973.00
stacked and debris cleared. m3 344.00

2/1 Brick work in lime, demolished brick stacked Cube 778.00


and debris cleared. m3 275.00

5/2 Ceiling, existing removed materials stacked Sqr 247.00


and debris cleared. m2 26.60

6/2 Cement concrete demolished, and debris Sqr 1667.00


cleared away. m2 179.00

7/2 Cement concrete, reinforced demolished in


suspended floors reinforcement removed and Sqr 2408.00
debris cleared. m2 259.00

8/2 Corrugated Sheets, Iron, Asbestoes or


Aluminium Alloy removed from roof or walls Sqr 281.00
and stacked. m2 30.20

9/3 Corrugated sheets iron or asbestos or aluminium alloy Sqr 304.00


removed from roofs or walls of 2 storeyed buildings m2 33.00

11/3 Door or Window, size up to 40 S.ft removed


from existing walls and door or stacked. No 371.00

12/3 Doors for window, size over 40 S.ft removed


- do - - do - No 556.00

13/4 Door or window, sash only, up to 40 S.ft


removed from existing walls and stacked. No 57.00

14/4 Door or window, sash only, over 40 S.ft


- do - - do - No 86.00

15/4 Down pipes, 4" to 6" dia G.I old or decayed, L.ft 3.90
removed from existing building and stacked. L.m 12.80

Analysis 1st half - Mullaitivu


Page 3 of 473

16/4 Drains demolished and debris cleared L.ft 12.00

18/5 Fence uprooted, barbed wire rolled up and


all materials stacked (length of fencing to L.ft 18.00
measured). L.m 59.00

Analysis 1st half - Mullaitivu


Page 4 of 473

NO DESCRIPTION OF WORK UNIT RATE (1st)

19/5 Floors brick paved, demolished and debris Sqr 278.00


cleared away. m2 30.00

20/6 Gate sash removed and stacked after


demolishing cement concrete blocks or
removing posts and separating pintols (demolishing
brick work where necessary paid for separately). No 371.00

21/6 Glass panes in doors, windows and fanlights Sq.ft 16.90


removed and stacked. m2 182.00

22/6 Gutter, Eaves, removed and stacked from roofs of L.ft 2.40
single story buildings. L.m 7.90

23/6 Gutter, Eaves removed from roofs of two storeyed L.ft 3.60
buildings and stracked. L.m 11.80

25/7 Partitions removed and stacked at side, including Sq.ft 14.20


making goodnes two walls and floors. m2 153.00

26/7 Lime plastering shipped and debris cleared away. Sqr 139.00

27/4 Rendering cement, chipped and debris cleared away Sqr 416.00
from brick walls and floors. m2 45.00

28/8 Rendering cement, chipped and debris cleared away Sqr 625.00
from cement concrete floors and walls. m2 67.00

29/8 Roofing removing tiles and timber stacking, serviceable


materials and cleaning debris in single storey Sqr 524.00
building. m2 56.00

30/8 Roof, removing tiles and timber stacking serviceable Sqr 719.00
material and cleaning debris in two storeyed building. m2 77.00

32/9 Rubble masonry in cement, demolished rubble Cube 1216.00


stacked and debris cleared away. m3 430.00

33/9 Rubble masonry in lime demolished rubble stacked and Cube 778.00
debris cleared away m3 275.00

Analysis 1st half - Mullaitivu


Page 5 of 473

34/9 Tiles glazed demolished and debris cleared away. Sqr 741.00

35/10 Tiles calicut or half round, removed from roof of Sqr 195.00
single storey buildings and stacked. m2 21.00

36/10 Tiles calicut of half round removed from Sqr 292.00


roof of 2 storeyed buildings and stacked. m2 31.00
NO DESCRIPTION OF WORK UNIT RATE (1st)

28 Tiles calicut of half round removed from roof of


two storeyed buildings and stacked. Sqr 224.00

39/11 Ceiling asbestoes removing including timber frame


work, stacking serviceable materials single storey Sqr 931.00
building (and debris cleared away in single). m2 100.00

40/11 Ceiling asbestos removing including timber frame Sqr 1125.00


work, - do - - do - in two m2 121.00
storeyed building.
41/11 Valance/ Barge boarding removed materials stacked L.ft 2.40
and debris cleared away in single storey building. L.m 7.90

42/11 Valance/ Barge boarding removed - do - L.ft 3.60


- do - in 2 storeyed building. L.m 11.80

43/12 Cement plastering, soffit chipped and debris cleared Sq.ft 542.00
away. m2 58.00

Analysis 1st half - Mullaitivu


Page 6 of 473

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU


EXCAVATOR.
NO DESCRIPTION OF WORK UNIT RATE (1st)
1 Drains, earth, in any soil except rock
requiring blasting cut to gradient and cube 529.00
shaped as directed soil deposited m3 187.00
within site.

2/13 Excavation in any soil except rock requiring cube 622.00


blasting part returnfill in and ram, and m3 220.00
surplus disposed of within site as directed.

4/14 Filling under floor with gravel or other cube 725.00


approved quality of filling, spread, m3 256.00
watered and well rammed in 3" layers
with available earth.

6/14 Filling under floor with gravel or other cube 3001.00


approved quality of filling spread water m3 1060.00
and rammed in 3" layers (material not
available at site).

7/15 External Filling.(Material not available at site) cube 2314.00


m3 818.00

8/15 External Filling.(Material available at site) cube 205.00

Analysis 1st half - Mullaitivu


Page 7 of 473

m3 73.00

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU


CONCRETOR.
NO DESCRIPTION OF WORK UNIT RATE (1st)
1/15 Cement concrete 1:3:6 with 2" metel, above one cube Cube 20647.00
(shuttering paid for seperately). m3 7296.00

2/15 Cement concrete 1:3:6 (2") upto one cube shuttering Cube 21388.00
paid for seperately. m3 7558.00

3/15 Cement concrete 1:2 1/2:5 (1") above one cube Cube 22842.00
(shuttering paid for seperately). m3 8071.00

2a/16 Cement concrete 1:3:6 (1 1/2") above 1 Cube 20840.00


cube (shuttering paid for seperately). m3 7364.00

2c/16 Cement concrete 1:3:6 (1") above 1 Cube 21353.00


cube (shuttering paid for seperately). m3 7545.00

Analysis 1st half - Mullaitivu


Page 8 of 473

4/16 Cement concrete 1:2 1/2:5 (1") upto one cube Cube 23583.00
(shuttering paid for seperately). m3 8333.00

5/16 Cement concrete 1:2:4 (3/4") above one cube Cube 24675.00
(shuttering paid for seperately). m3 8719.00

6/16 Cement concrete 1:2:4 (3/4") upto one cube Cube 25416.00
(shuttering paid for seperately). m3 8981.00

11/18 Drains, semi circular, in cement concrete 1:3:6 (1") 9"


wide and 9" average depth, with 3" thick sides and base
inclusive of 1/2" cement rendering 1:3 and expansion L.ft 286.00
joints as necessary excavation (without ramp). L.m 938.00

12/19 Lintol cement concrete 1:2:4 (3/4") 4 1/2"x6" L.ft 120.00


(Reinforcement paid seperately). L.m 394.00

13/19 Lintol cement concrete 1:2:4 (3/4") 9"x6" (Reinforcement L.ft 162.00
paid seperately). L.m 531.00

14/20 Lintol cement concrete 1:2:4 (3/4") 9"x9" )Reinforcement L.ft 218.00
paid seperately). L.m 715.00

19/22 Padstones, cement concrete 1:2:4 (3/4") precast


or in situ.Size 1-6x1-1 1/2x0-6 No 315.00

19a/22 Padstones, cement concrete 1:2:4 (3/4") precast


or in situ.Size 1-6x0-6x0-6 No 118.00

21/23 Slabs over drain, cement concrete 3" thick 1:2:4(3/4")


reinforced with expended metal and 1/2" cement rendered S.ft 111.00
1:2 (R/F paid for seperately). m2 1195.00
NO DESCRIPTION OF WORK UNIT RATE (1st)
21a/23 Slabs over drain, cement concrete 3" thick 1:2:4(3/4")
reinforced with expended metal and 1/2" cement rendered S.ft 79.00
1:2 (R/F paid for seperately). m2 850.00

25a/25 Cement concrete 1:1 1/2:3 (3/4"). Cube 27551.00


m3 9735.00

23/24 Supr stone, cement concrete 1:2:4 (3/4") for door posts
supplied and fixed. No 29.00

Analysis 1st half - Mullaitivu


Page 9 of 473

25/25 Cement concrete 1:2 1/2":5(1") using


mixer and vibrator (shuttering paid for Cube 24048.00
seperately). m3 8498.00

26/25 Cement concrete 1:2:4(3/4") in column shafts


(Reinforcement shuttering and finishes paid for seperately) Cube 26830.00
in guard floor using mixer and vibrator. m3 9481.00

27/25 Cement concrete as per Item 61 in 1st floor. Cube 27571.00


m3 9742.00

28/25 Cement concrete as per Item 61 in 2nd floor. Cube 28682.00


m3 10135.00

29/26 Cement concrete 1:2:4 (3/4") in beams in ground floor Cube 26700.00
(reinforcements shuttering and finishes paid for seperately) m3 9435.00
using mixer and vibrator.

30/26 Cement concrete as per Item 29 in 1st floor. Cube 27441.00


m3 9696.00

31/26 Cement concrete as per Item 29 in 2nd floor. Cube 28552.00


m3 10089.00

32/26 Shuttering for floor slab concrete and dismantling. Sqr 3988.00
m2 429.00

33/27 Shuttering for column shaft and diamantling (for column Sq.ft 60.00
9"x9"x4" 4 ft heigh I.e 4 1/2" ft box). m2 646.00

33a/27 Shuttering for footing and walls etc. Sq.ft 16.00


m2 172.16

34/27 Shuttering for beam including dismantling (12"x18" Sq.ft 43.00


beam 20 ft long). m2 463.00

35/28 Cement concrete 1:2"4(3/4") lintol in ground floor


Reinforcement and shuttering paid for seperately using Cube 26678.00
mixer and vobrator. m3 9427.00
NO DESCRIPTION OF WORK UNIT RATE (1st)

Analysis 1st half - Mullaitivu


Page 10 of 473

36/28 Cement concrete lintols as per Item (71) in 1st floor. Cube 27419.00
m3 9689.00

37/28 4" thick R..C.C 1:2:4 (3/4") in first floor slab (reinforcement Sqr 8838.00
and shuttering paid seperately) using mixer and vibrator. m2 951.00

38/29 5" thick R.C.C in 1st floor - do - Sqr 10712.00


- do - - do - m2 1153.00

39/29 Drains semi circular in cement concrete 1:3:6 (1") wide


and 9" average depth, 3" thick sides and base, inclusive of
1/2" cement rendering 1:3 with necessary expension, joints L.ft 0.00
and excavation, but without ramp L.m 0.00

40/29 Drains in cement concrete 1:3:6(1") as above L.ft 463.00


But with ramp 2' 6" wide L.m 1518.00

BLOCK MASONRY
1 Cement sand block in 1:6 mix in cement Cube 16630.00
sand 1:5 mix m3 5876.00

2 4" thick cement sand block 1:6 mix masonry Sqr 6081.00
in cement sand 1:5 mix m2 655.00

Analysis 1st half - Mullaitivu


Page 11 of 473

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU


BRICKLAYER.
NO DESCRIPTION OF WORK UNIT RATE (1st)
2/30 Brick work in cement mortar (1:5) above 1 cube (up to 1st Cube 16820.00
floor level). m3 5943.00

3/30 - do - up to one cube - do - Cube 17690.00


- do - m3 6251.00

4/31 Brick work in cement mortar 1:5 in piers (in ground floor). Cube 18559.00
m3 6558.00

6/31 Brick work 4 1/2" thick in cement mortar 1:5 above 1 square. Sqr 6593.00
m2 710.00

7/32 - do - up to one Sqrs. Sqr 6982.00


m2 752.00

12/33 Extra over Item 2-5 and 9-11 for brick Cube 584.00
work from 1st floor level up 2nd floor. m3 206.00

14/34 Extra over Items 6-8 for brickwork from Sqrs 195.00
1st floor level to 2nd floor. m2 21.00

19/35 Coping, brick in cement 1:5 weathered and throated on L.ft 117.31
4 1/2" walls, cement renedered 1/2", 1:3 complete. L.m 384.00

20/35 Coping, brick in cement 1:5 weathered throated on 9" walls L.ft 164.00
and 1/2" cement rendered 1:3 complete. L.m 538.00

24/37 Doors or window inserted in existing walls including No 4121.00


Making.
25/37 Drains brick in cement 1:5,9" average depth 12" wide and
cement rendered 1/2" thick 1:3 complete with expansion joints
as necessary, including necessary excavation (apron paid L.ft 329.00
for seperately). L.m 1079.00

Analysis 1st half - Mullaitivu


Page 12 of 473

26/38 Drains brick in cement 1:5,6" average depth 9" wide and
cement rendered 1/2" thick 1:3 complete with expansion joints
as necessary, including necessary excavation (apron paid L.ft 217.00
for seperately). L.m 712.00

28/38 Steps 12" wide and 6" to 9" high masonary or brick work in
cement mortar 1:5 rendered 1/2" cement 1:2 with foundation L.ft 170.00
6" below ground. L.m 558.00
30/39 Brick work in cement and sand 1:8 in foundation and upto Cube 15894.00
D.P.C. m3 5616.00

31/40 Brick work in cement and sand 1:8 in super structure Cube 16357.00
in ground floor. m3 5780.00

Analysis 1st half - Mullaitivu


Page 13 of 473

NO DESCRIPTION OF WORK UNIT RATE (1st)

32/40 - do - in 1st floor. Cube 16941.00


m3 5986.00

33/40 - do - in 2nd floor. Cube 18108.00


m3 6399.00

MASON.

NO DESCRIPTION OF WORK UNIT RATE (1st)

1/41 Random Rubble Masonary in cement mortar 1:5 above Cube 15823.00
1 cube. m3 5591.00

2/41 - do - up to one cube. Cube 16379.00


m3 5788.00

Analysis 1st half - Mullaitivu


Page 14 of 473

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU


PAVIOR.
NO DESCRIPTION OF WORK UNIT RATE (1st)
1/43 Exapansion joints in brick floors, filled with bitumen L.ft 7.00
and sand. L.m 23.00

2/43 Exapansion joints in concrete floors filled with bitumen and L.ft 17.00
sand(to full depth of concrete and rendering). L.m 56.00

5/44 Floors, cement concrete 1:2 1/2:5(1") 3" cement rendered 1/2", Sqr 7868.00
1:2, with expansion joints filled with cement and sand. m2 611.00

12/46 Tiles glazed colour 6"x6" with all specials, supplied and S.ft 107.00
fixed to walls including raking plaster and bedding in m2 847.00
cement mortar 1:2.

12/46 Tiles glazed(colour)6"x6", with all S.ft 128.00


specials, supplied and fixed to walls m2 1378.00
including raking plaster and bedding
in cement mortar 1:2.

12d/46 Tiles 8"x8", pressed of approved pattern and S.ft 125.00


colour, supplied and fixed. m2 1350.00

Analysis 1st half - Mullaitivu


Page 15 of 473

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU


PLASTERER.
NO DESCRIPTION OF WORK UNIT RATE (1st)
4/139 Cracks in wall, plastered in cement 1:3 L.ft 12.00
after chipping 2" to 4" wide m 39.00

9/141 Flashing or plaster bands laid over tiles L.ft 20.00


4" to 6" wide on roof in cement and lime L.m 66.00
mortar 1:1:4

14/142 Rendering cement 1/2", 1:2 above 1 Sqr 1971.00


Square. m2 212.00

15/142 Rendering cement 1/2", 1:2 upto 1 square Sqr 2110.00


m2 227.00

16/143 Rendering cement 1/2", 1:3 above 1 Square. Sqr 1716.00


m2 185.00

17/143 Rendering cement 1/2", 1:3 upto 1 Square Sqr 1855.00


m2 200.00

18/143 Rendering, cement 3/4", 1:2 above 1 Sqr 2790.00


Square. m2 300.00

19/143 Rendering, cement 3/4", 1:2 upto 1 square Sqr 2975.00


m2 320.00

Analysis 1st half - Mullaitivu


Page 16 of 473

20/144 Rendering, cement 3/4", 1:3 above 1 Sqr 2493.00


Square. m2 268.00

21/144 Rendering, cement 3/4", 1:3 upto 1 square Sqr 2679.00


m2 288.00

22/144 Rendering, cement, floating coat using Red


cement finished smooth with Carborandum Sqr 587.00
stone m2 63.00

25/145 Rendering cement 3/4", 1:2 with Pudlo 5lbs Sqrs 3228.00
to 100 lbs cement m2 347.00

26/145 Skirting in cement mortar 1:3, 1/2"x4" L.ft 30.00


projected or flush with wall, and L.m 98.00
including forming groove.

27/145 Skirting in cement mortar 1:3, 1/2"x6"


projected or flush with all finished with
Red cement floating, including forming L.ft 51.00
groove. L.m 167.00

NO DESCRIPTION OF WORK UNIT RATE (1st)


28/146 3/8" thick plastering to RCC beams, slab Sqrs 2601.00
soffit in cement sand 1:3 .with lime putty m2 280.00

29/146 D.P.C. 3/4" thick in cement, sand 1:2 Sqrs 3681.00


finished smooth with 2 coats of hot tar. m2 396.00

29a/146 3/8" thick cement and sand plastering to Sqrs 2348.00


column and beam m2 253.00

29b/146 1/2" thick cement plastering 1:4 mix Sqrs 1615.00


m2 174.00

29c/146 5/8" thick cement plastering 1:4 mix Sqrs 1681.00


m2 181.00

29d/146 Cracks in wall Plastered in cement 1:3 L.ft 13.00


after chipping 2" to 4" wide L.m 42.00

Analysis 1st half - Mullaitivu


Page 17 of 473

29e/146 Plinth plastering 1/2" thick 1:3 cement and Sqrs 2303.00
sand with red cement floating m2 248.00

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU


ROOFER.
NO DESCRIPTION OF WORK UNIT RATE (1st)
5/49 Corrugated asbestos sheet roofing on
special upper cl. Timber/kempas purlines
supplied and fixed complete including
treating timber with wood preservative Sqrs 10298.00
two coats (ridging measured seperately). m2 1109.00

7/50 Corrugated asbestos sheet fixed to roof


or wall on existing frame work with

Analysis 1st half - Mullaitivu


Page 18 of 473

necessary coach screws and limpet Sqrs 4705.00


washers, or hook bolts.& with 2 coats wood m2 506.00
Preservative to existing frame work

18/53 Ridging, calicut pattern bedded in


Cement and lime mortar 1:1:4, Coloured L.ft 78.00
to match tiles. L.m 256.00

19/53 Ridging, Calicut Pattern bedded in


cement and lime mortar 1:1:4 coloured L.ft 49.00
to match tiles (tiles available at site) L.m 161.00

21/54 Ridging with asbestos cement close


fitting ridges fixed complete with L.ft 149.00
roofing screws or hook bolts. L.m 489.00

26/55 Tiles, calicut pattern, flat supplied and


laid up to 5 tiles in single storey building No 28.00

27/56 Tiles, calicut pattern flat supplied and


laid (above 5 and up to 25) in single
storey Building. No 24.00

30/56 Tiles calicut pattern supplied and laid Sqr 2750.00


in any Building. m2 296.00

31/56 Tiles, calicut pattern, laid in any Sqr 185.00


Buildings(tiles available at site). m2 20.00

43/53 Shifting and re-laying calicut pattern Sqr 370.00


tiles. m2 40.00

44/59 Supplying and laying half round tiles Sqr 2649.00


on the existing asbestos roof. m2 285.00

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU


CARPENTER & JOINTER.
NO DESCRIPTION OF WORK UNIT RATE (1st)

Analysis 1st half - Mullaitivu


Page 19 of 473

8/63 Boards, Barge, Valance, Fascia, 3/4" to


1" thick in class.II Local timber fixed
complete with necessary Brass screws new or
renewed above 1 C.ft.( 9" width) with 1 coat L.ft 95.00
primer & 2 coat of enamel painting L.m 310.00

12/64 Boardes, Barge, Valance, Facia,


available fixed including cutting and s.ft 42.00
minor repairs.with 2 coats enamel painting m2 452.00

3/61A Beadings, Class I local timber 1 1/2" to


2"x1/2" plain chamfered, fixed with brass L.ft 11.00
screws L.m 36.00

14/65 Ceiling asbestos, flat fixed with clout


headed nails to 4"x2" joists at 4'crs & 2"x 2"
bearers at 2' crs of spl.upper class. Timber/
kempas including 1 1/2" x 1/2" cover fillets
and 2 1/2" x 1/2" coves of Halmills timber.
Rate to include 2 coats tarnap to joists
and bearers primer and '2 coats of enamel
painting to beadings 'and mouldingd 2 coats
of white washing to ceiling.
Making holes in wall and fixing joists and
bearers 'Per 1.95 Sqrs (15'-0"x13'-0"). Sqr 12087.00
m2 1299.68

14a/65 Ceiling asbestos, flat in eves fixed with clout


headed nails to 2" x 2"& 2"x1" spacer
bearers not exceading 2'-0 centrs both ways
bearers of spl.upper class/ kempus timber
including Aluminium beading 1" wide with
Rubber fillets fixed not exceedaing 2'-0" crs
bothways Rate to include 2 coats tarnap to Sqr 14211.00
timber and 2 coats emulsion m2 1530.00
paint to abestos sheet

14b/65 Ceiling asbestos, flat fixed with clout


headed nails to 4"x2" joists 4'-0 crs & 2"x2"
bearers of spl.upper class/kempus timber 2'-0" crs
and 2"x1" spacer bearers not exceding 2'-0crs
including Aluminium beading 1" wide with

Analysis 1st half - Mullaitivu


Page 20 of 473

rubber fillets not exceeding 2'-0 crs fixed bothways Sqr 14911.00
Rate to include 2 coats tarnap to timber m2 1603.00
and 2 coats emulsion paint
to abestos sheet

NO DESCRIPTION OF WORK UNIT RATE (1st)


14c/65 As per Item No.14 with only 2"x2"beares Sqr 10874.00
in eaves ceiling. -do- -do- m2 1171.00

14d/65 White washing to ceiling 2 coats and


2 coats of oil paint to beading and Sqr 1018.00
moulding. m2 109.46

14e/65 Ceiling, upper side cleaned and debris Sqr 92.00


cleared away. m2 10.00

26/68A Cove mouldings Cl.I 2 1/2"x1 1/2" fixed


with brass screws and plugs new or L.ft 16.00
renewed. L.m 54.00

28/69 Doors or Windows, ledged, braced and


battened with grooved and tongured
joint,3 3/4" x 2 3/4" frames in spl upper class
/ kempas and 3/4" to
7/8" thick sashes in class1 timber S.ft 394.00
with brass fittings. m2 4234.00

30/70 - do - - do -
Sash only, in class 1 timber S.ft 252.00
fixed with brass furniture. m2 2717.00

32/70 Doors or Windows, framed and battened,


sash 1" to 1 1/8" thick in Special
upper Class timber/kempas fixed complete S.ft 509.00
with brass furniture. m2 5472.00

32a/70 Battened sash only 1" to 11/8" thick in sp. S.ft 377.00
upper class timber/kempas fixed completed with m2 4061.00
brass fittings

42/74 Doors or Windows, glazed and/or


pannelled with 3 3/4"x2 3/4" frames and

Analysis 1st half - Mullaitivu


Page 21 of 473

1 1/8" to 1 1/4" sashes in special upper S.ft 479.00


Class I timber/kempas fixed. m2 5155.00

44/75 Doors or Windows, glazed or


pannelled sash only 1 1/8" to 1 1/4" thick
in Special upper class timber/kempas with brass S.ft 416.00
furniture. m2 4474.00

44a/75 Doors pannelled and terllised/B.R.C.


weld mesh No. 32 with 3 3/4"x2 3/4"
frames and 1 1/8" thick sashes in special
upper class timber/kempas, fixed complete with S.ft 425.00
brass furniture. m2 4568.00
NO DESCRIPTION OF WORK UNIT RATE (1st)

52/78 Doors pannelled with 3 3/4"x2 3/4" frames


and 1 - 1 1/8"sashes in Special upper S.ft 487.00
Class timber /kempasfixed.with brass fittings m2 5244.00

53/78 Door or Window, removing easing and Per


re-fixing. sash 171.00

54/78 Door or Window, easing only. Per sash 67.00

55/79 Door or Window frames renewed in


short lengths with special upper Class L.ft 304.00
timber/kempas. L.m 997.12
Assume 3'-0" Length of frame renewed

100/92 Reepers 2"x1" in Class I timber supplied L.ft 12.00


and fixed new or renewed with iron L.m 41.00
nails, up to 100 L.ft (shiffting of tiles paid
for seperately).
re-fixed in new position.

101/92 - do - - do - L.ft 11.00


over 100 L.ft. L.m 36.00
Per 100 L.ft

107/94 Roof with calicut pattern tiles on spl upper


class/Kempus frame work complete with ridges, Sqr 14294.00
hips etc. m2 1539.00

Analysis 1st half - Mullaitivu


Page 22 of 473

107a/94 gable end roof - do - Sqr 12093.00


- do - - do -. m2 1302.00

117/97 Timber available, sorted out, cut to


required sizes and fixed in roof and C.ft 436.00
other carpentry work. m3 15387.00

121/98 Timber special upper Class/kempas fixed or


renewed in roof and other carpentry C.ft 1861.00
work. m3 65672.00

135/101 Trellis partition with 1/2"x1/2" laths fixed


2" apart diagonally or horizontally and S.ft 504.00
vertically on 4"x2" Milla timber framing. m2 5425.00

138/102 Door frame 4"x3" in spl upper class timber/kempas S.ft 239.00
supplied and fixed in position m2 2575.00

118/97 Timber fixed or renewed in post and frames C.ft 2152.00


NO DESCRIPTION OF WORK UNIT RATE (1st)

140/103 Door 1 1/4" thick plywood ordinary sash


single (ordinary finish) hung on 4"x3"
frame in Special upper class timber/kempas and S.ft 321.00
complete with brass furniture with mortice lock m2 3458.00

140a/103 As per Item No 140 -do- -do- but with marine type S.ft 365.00
2'3"x6'9". m2 3927.00

142/104 Supplying and fixing Plywood door 1 1/4" thick S.ft 207.00
single (Ordinary finish) to the existing frame m2 2230.00
with brass fittings with mortice lock

143/104 -do- -do- plywood Marine type 1 1/4" thick S.ft 219.00
single hung to existing frame with fitting m2 2356.00

Analysis 1st half - Mullaitivu


Page 23 of 473

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU


PAINTER & DECORATOR.
NO DESCRIPTION OF WORK UNIT RATE (1st)
13/165 Lettering 1" to 1 1/2" painted in sinhalese
English or Tamil, including painting Per
ground. Letter 42.00

14/165 Lettering 2" to 3" - do - Per


- do - - do -. Letter 50.00

15/166 Lettering 4" to 5" - do - Per


- do - - do -. Letter 70.00

23/168 Painting, enamel paint including washing

Analysis 1st half - Mullaitivu


Page 24 of 473

cleaning and smoothing down with sand Sqr 741.00


paper, 1 coat. m2 80.00

24/168 Painting enamel paint - do - Sqr 1415.00


- do - 2 coats. m2 152.00

25/168 Painting New wood 1 Coat primer & 2 Coats Sqr 2114.00
Enamel paint m2 228.00

25a/168 Painting new wood work and 2 coats of Sqr 1405.00


enamel paint. m2 151.00

27/169 Painting Steel work, 1 coat, with Sqr 616.00


Anticrosive paint including removing m2 66.00
scale and wire brushing.

28/169 Painting Steel work, 2 coats, with Red


oxide including removing scale and Sqr 1136.00
wire brushing. m2 122.00

30/169 Painting walls with emulsion paint 1 coat Sqr 534.00


(new coat). m2 58.00

30a/169 Painting walls with weather shield 1 coat Sqr 607.00


( New work ) m2 65.00

31/170 Painting walls with Emulsion paint, 2 Sqr 957.00


coats (new work). m2 103.00

31a/170 Painting walls with 2 coats of weather shield paint Sqr 1118.00
( New work ) m2 120.00

32/170 Painting walls with Emulsion paint, 1


coat including preparing surface of old Sqr 625.00
work. m2 67.00

NO DESCRIPTION OF WORK UNIT RATE (1st)


32a/170 Painting walls with weather shield paint Sqr 698.00
1 coat ( Old work ) m2 75.00

33/170 - do - - do - Sqr 1049.00


2 coats - do - - do -. m2 113.00

Analysis 1st half - Mullaitivu


Page 25 of 473

33a/170 Painting walls with weather shield paint Sqr 1210.00


2 coat ( Old work ) m2 130.00

40/172 Tarnap or other wood preservative, Sqr 253.00


applied to wood work 1 coat (old work). m2 27.00

41/172 Tarnap or other wood preservative, Sqr 460.00


applied to wood work 2 coats (new work). m2 50.00

44/173 Varnishing with best copal varnish after Sqr 867.00


washing down and sand papering 1 coat. m2 93.00

45/173 - do - - do - Sqr 1507.00


- do - 2 coats. m2 162.00

49/174 White or colourwashing walls of single


storey buildings 1 coat, including Sqr 120.00
patching and preparing surface. m2 12.90

50/174 - do - - do - Sqr 208.00


2 coats - do -. m2 22.00

Analysis 1st half - Mullaitivu


Page 26 of 473

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU


BRASS FOUNDER.
Item Description Unit RATE (1st)
4/127 Bolts barrel 4", brass oxidised heavy
quality supplied and fixed with brass
screws. No 138.00

6/128 - do - 6" - do -
- do - - do - No 185.00

18/130 Casement fastner with mortice plate, brass oxidised


heavy quality supplied and fixed with brass screws. No 170.00

19/130 Casement stays 10", brass oxidised heavy


quality supplied and fixed. No 154.00

21/131 Fanlight Catches brass oxidised heavy


quality with brass screws fixed complete. No 102.00

27/132 But hinges 4"x3" brass oxidised heavy quality


supplied and fixed with brass screws complete. No 300.00

29/132 - do - 4"x4" - do -
- do - - do - No 379.00

29a/132 - do - 4"x2 1/2" - do -


- do - - do - No 277.00

31/133 Hinges centre pivot (consisting of 2 pieces)


brass oxidised heavy quality supplied and
fixed with brass screws complete. Set 128.00

31a/133 Rings, brass 1 3/4" to 1 1/2" supplied


and fixed to doors and windows with
brass screws. No 56.00

51/137 Lock Mortice Vinion /concord single supplied


and fixed. No 869.00

52/137 Lock Mortice Vinion/concord double, supplied

Analysis 1st half - Mullaitivu


Page 27 of 473

and fixed. No 1442.00

53/137 Mortice Lock Union ( English) single


supplied and fixed. No 2066.00

54/137 Mortice Lock Union ( English) double


supplied and fixed. No 3728.00

Item Description Unit RATE (1st)


53a/137 Lock Night Latch supplied and fixed with
duplicate keys approved quality No 601.00

63/123 Tor steel rods in reinforcing. Kg 128.00

64/123 Tor steel rods reinforcement in foundation Kg 123.00

63a/123 Mild Steel rods in reinforcing lintols or beams. Kg 126.00

64a/123 Mild Steel rods in Foundation . Kg 121.00

Analysis 1st half - Mullaitivu


Page 28 of 473

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU


IRON MONGER.
Item DESCRIPTION OF WORK Unit RATE (1st)
49/119 Hinges T, 10" Iron, heavy quality supplied
and fixed with iron screws complete. Pair 298.00

60/121 Locks, rim 6" iron, superior quality, heavy


type, s/f. with iron screws complete. No 636.00

67/123 M.S.Bars 5/8" dia supplied & fixed in


window frame at 4" cetres & painted L.ft 60.00
with one coat red lead & 2 coats aluminium L.m 199.00

67e/123 1/2" dia - do - - do - L.ft 37.00


L.m 124.00

Analysis 1st half - Mullaitivu


Page 29 of 473

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU


TINKER.

Item DESCRIPTION OF WORK Unit RATE (1st)

9/150 Flashing G.I.22 B.W.G. 1'6" wide, fixed


with 6" turned up along, and top edge
tucked well into wall in cement and L.ft 152.00
lime mortar. L,m 498.00

29/156 Gutters, Valley 20 B.W.G 36" wide,


renewed on existing board, sheets
tarred, joints soldered and cement, L.ft 342.00
lime filletting complete. L,m 1121.00

34/158 -Do- renewed including 1" thick timber


boarding sheet tarred, joints soldered and L.ft 572.00
cement lime filletting complete. L,m 1875.00

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU


PLUMBER.
Item DESCRIPTION OF WORK Unit RATE (1st)
1/179 Ball valve 1/2" supplied and fixed No 165.00

2/179 Ball valve 3/4" supplied and fixed No 231.00

13/181 Wash' Basin, Lavatory, 22"x16" with one tap,


water plug, new brackets, supplied &
fixed complete. (Additional tap, trap,
and outlet pipe paid for seperately). No 2979.00

17/182 Basin, sink or urinal including all fittings


removed and walls made good No 485.00

Analysis 1st half - Mullaitivu


Page 30 of 473

31/185 Closet, pedestal type available at site, fixed


with cement concrete after breaking concrete
floor and making good and connections to soil
and flush pipes No 889.00

32/186 Closet, pedestal type, disconnecting and


plugging sewer connection and making good
all affected walls and floors No 612.00

34/186 Closet, pedestal type, with low level


glazed earthenware flushing cistern
flush pipe, double plastic sheet cover,
1/2" stop cork, trap etc. supplied &
fixed completed. No 6891.00

35/186 Closet squatting type, with trap supplied


& fixed. No 2022.00

36/187 Closet, squatting type, removed, sewer


connections plugged and floor made
good. No 866.00

40/188 Cocks, brass bib 1/2" supplied & fixed


(Heavy quality). No 232.00

66/193 Flushing Cistern fixed complete low level


(Ceremics).meterial available No 619.00

66a/193 Flushing cistern, low level, plastic


supplied and fixed complete. No 2061.00

86/197 Mirror, bath room type, supplied &


fixed to wall with Rawl plugs and
plastic frames. No 785.00
Item Description Unit RATE (1st)
147/214 Shower rose, 6" pvc supplied & fixed. No 599.00

153/215 Sink, glazed, earthenware 24"x15"x8"


supplied and fixed with waste plug,
complete (pedestal paid seperately). No 2936.00

Analysis 1st half - Mullaitivu


Page 31 of 473

147a/214 Towel rail 2'-0" long 3/4" dia chromium


plated. No 410.00

171/219 Soap tray, white porcelain, supplied and


fixed to wall with rawl plugs. No 293.00

173/220 Stop cocks, 1/2" supplied & fixed No 234.00


Plastic L.D. make).

174/220 Stop cocks, 3/4" supplied and fixed.


Plastic L.D. make). No 267.00

175/220 Stop cocks, 1" supplied and fixed.


Plastic L.D. make). No 280.00

176/220 Stop cocks, 1 1/4" supplied and fixed.


( Plastic L.D. Model ) No 433.00

177/220 Stop cocks, 1 1/2" supplied and fixed.


Plastic L.D. make). No 463.00

178/221 Stop cocks, 2" supplied and fixed.


Plastic L.D. make). No 538.00

178a/221 As per Item No. 178a (Gate valve 2") No 1005.00


English make

178b/221 Non return valve English 2" dia No #N/A

200/228 Tooth brush holder, chromium plated


supplied and fixed to wall with Rawl
plugs. No 320.00

292/240 Pipes pvc 1/2" supplied & fixed. L.ft 13.00


L.m 42.00
293/240 Pipes pvc 3/4" supplied & fixed. L.ft 20.00
L.m 65.00

294/240 Pipes pvc 1" supplied & fixed 1000 type. L.ft 39.00
L.m 129.00

294a/240 pipes pvc 1" supplied & fixed 600 type. L.ft 28.00

Analysis 1st half - Mullaitivu


Page 32 of 473

L.m 92.00
Item Description Unit RATE (1st)

295/240 Pipes pvc 1 1/4" supplied & fixed 1000 type. L.ft 53.00
L.m 175.00

295a/240 Pipes pvc 1 1/4" supplied & fixed 600 type. L.ft 42.00
L.m 138.00

296/241 Pipes pvc 1 1/2" supplied & fixed. L.ft 73.00

296a/241 pvc pipe 1 1/2" (1000 type) supplied & L.ft 65.00
fixed with out excavation. L.m 213.00

296b/241 pvc pipe 1 1/2" (600 type) supplied & L.ft 47.00
fixed with excavation. L.m 154.00

296c/240 pvc pipe 1 1/2" (600 type) supplied & L.ft 38.00
fixed with out excavation. L.m 126.00

297/241 Pipes pvc 2" (1000 type) supplied & fixed. L.ft 118.00
With excavation L.m 388.00

297a/241 pvc pipe 2" (1000 type) supplied & L.ft 110.00
fixed with out excavation. L.m 361.00

297b/241 pvc pipe 2" (600 type) supplied & L.ft 71.00
fixed with excavation. L.m 233.00

297c/241 pvc pipe 2" (600 type) supplied & L.ft 63.00
fixed with out excavation. L.m 206.00

310/243 Eaves gutters 6" square type pvc fixed L.ft 88.00
with PVC brackets. (1' - 6 " Crs) L.m 288.00

311/244 Down Pipe 3 1/2" Dia P.V.C Fixed with L.ft 81.00
Wooden Plug to wall etc. L.m 264.00

311a/244 PVC 4" ( 600 type ) pipe supplied and fixed on walls L.ft 227.00
L.m 743.00

Analysis 1st half - Mullaitivu


Page 33 of 473

5/245 Drains, pvc 400 type 4" laid on cement


concrete 6" thick upto 2'-0" depth of
invert including excavation and cement L.ft 357.00
concrete haunching (1:3:6 - 1" metal). L.m 1171.00

13/246 Gulley pvc 6" supplied & fixed including


gulley box. No 627.00

Item Description Unit RATE (1st)


18/247 Manhole 2'x2' and upto 2'-0" deep, 9"
thick brick in cement 1:3 walls & cement
rendered 1/2" (1:2) with 6" cement conc.
foundation 1:3:6 (1" metal) including
forming channels but without cover. No 5097.00

19/247 Manhole 3'6"x2'3" & 2'0" to 4'0" deep


- do - - do -. No 8842.00

20/248 Manhold 3' 6" x 2' 3" & 4' to 6' deep 9" thick No 13518.00
-do -do-

23/248 Manhole cover reinforced concrete 3"


thick 2'-0x2'-0" approx. supplied & fixed no 797.00
reinforced with 1/4" dia M.S.rods at
3" centres both ways.

26/249 Wire dome for 2" pipe supplied and fixed no 85.00

1/D 110mm PVC inspection joint supplied and fixed No 533.00

2D 110mm PVC inspection "Y" joint supplied and fixed No 611.00

3D 110mm PVC Bend ( 11 Deg.) supplied and fixed No 246.00

4D 110mm PVC Bend ( 22 Deg.) supplied and fixed No 250.00

5D 110mm PVC Bend ( 60 Deg.) supplied and fixed No 341.00

6D 110mm PVC Bend ( 88 Deg.) supplied and fixed No 485.00

7D 110mm PVC "T" Junction supplied and fixed No 744.00

Analysis 1st half - Mullaitivu


Page 34 of 473

8D 110mm PVC "Y" Joint supplied and fixed No 713.00

9D 50mm Bottle trap supplied and fixed No 302.00

10D 110mm PVC Inspection bend supplied and fixed No 557.00

11D 63mm PVC "Y" Joint supplied and fixed No 86.00

12D 110mm PVC Elbow supplied and fixed No 457.00

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU


MISCELLANEOUS

Item Description Unit RATE (1st)

6/251 Fence barbed wire ,14 gauge,


4 points, 3" sparts, supplied and fixed in L.ft 4.20
existing timber posts with G.I staples. L.m 13.80

15/253 Intermediate fence posts or structs, cement


concrete 1:1 1/2:3(3/4") reinforced with
4 Nos. 1/4 dia. M.S.rods 5'-7" high square
section 4" to 6" fixed complete as per
drawing No.68 of 22.07.1936. per post 808.00

16/253 - do - - do - 7'6" high - do -. per post 901.00

17/253 End post and strut for Type barbed wire


fence fixed complete in cement concrete
as per Drg. 68 of 1936. per post 4818.00

18/254 Fence barbed wire, 7 strands 14


B.W.G with 4 points at 3" centres and
R.C.C posts (1:2:4) 3/4" metal reinforced
with 4 Nos. 1/4 rods with 14 B.W.G

Analysis 1st half - Mullaitivu


Page 35 of 473

stirrups at 8" centres including post to


be fixed at 8'-0 crs' excavation cement
concrete foundation '1:3:6(1 1/2") metal
to corner posts and 'structs and straining
bolts, all as per type 'plan 68 of
22.07.1936 structs to be 'reinforced
with 4 Nos. 3/8" rods and 'corner posts
with 4 Nos. 1/2" rods. ( including L.ft 208.00
white washing 2 coats) L.m 683.00

18A/254 - Do - - do - - do -
- do - 6 Strands - do - - do - L.ft 214.00
- do - - do - - do - L.m 703.00

19/254 Straining Bolts 1/2" dia made and fixed


18" long (Approx). No 292.00

21/255 Well, bailing out water 5' to 7' dia. Upto


20' depth including cleaning well. L.ft 111.00

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN MULLAITIVU


ANGLE IRON
Item Description Unit RATE (1st)
1/A Supplying and fixing 50mmx50mmx6mm thick
Angle iron purlin fixed to wall at not exeeding
900mm centres and joints should be bolted with
2Nos 12mm dia bolts and nuts other site welding
with cleats minimum length 450mm in next reduced
angle iron including two coats of Anticorrosive paint
as directed & including anchoring purlins with 2 nos
10mm tor steel welded to purlins where ever necessary and L.ft 121.00
with 1:2:4 concreting. L.m 397.00

2/A 62.5mmx62.5mmx6mm Angle iron purlin L.ft 145.00


-DO- -DO- L.m 474.00

3/A 75mm x 75mm x 6mm Angle Iron purlin L.ft 173.00

Analysis 1st half - Mullaitivu


Page 36 of 473

-DO- -DO- L.m 569.00

4/A End Truss-2/50mm x 50mm x 6mm L.ft 363.00


Per 7'-0" including 1:2:4(3/4) concreting 2nos L.m 1192.00
12mm dia 9" long welded to end truss
with 2 coats of anticorrosive paint

5/A End Truss-2/62.5mm x 62.5mm x 6mm L.ft 403.00


-DO- -DO- L.m 1323.00

6/A End Truss-2/75mm x 75mm x 6mm L.ft 455.00


-DO- -DO- L.m 1491.00

7/A 25mm x 6mm - Flat Iron - 1'-0" long


weld to end purlin as bracket to fix valance
board with two coats of anticorrosive paint
& bolts & nuts No 41.00

8/A 31mm x 6mm - Flat Iron - 1'-0" long No 49.00


-DO- -DO-

9/A 2/3" x 3" x 1/4"(2/75mm x 75mm x 6mm) L.ft 453.00


angle iron slope beam including 1:2:4(3/4") L.m 1485.00
concreting with 4 nos 16mm 9" long Rag bolt
with 2 nos 9"x9" 10mm Ms base plate

10/A Supplying & fixing 'H' iron 6" x 3" 6mm L.ft #N/A
with necessary cleats to housing props L.m #N/A
including 2 coats of anticorrosive painting

11/A Supplying & fixing ' H ' Iron 8" x 4" L.ft 81.00
(6mm) with necessary cleats -do- L.m 265.00
Item Description Unit RATE (1st)
12/A G.I. Gate with 12'-0" x 4'-6" hight 2 Nos sashes made
out of 1 1/2" dia G.I. heavy quality frame with
6mm M.S. rod welded 3" c/c both ways all as per
Drg. No. 409853 fixed with 9" x 9" RCC pillar in
1:2:4(3/4") concrete 4Y12 reinforced and R6 at 6" crs.
stirrups rate include for Excavation base concrete
footing R/F with
Y10 @ 8" c/c both way 5/8" thick 1:4 plastering 4 Nos. pintol
and stirrups locking divice barrel bolt etc. and 2 coats

Analysis 1st half - Mullaitivu


Page 37 of 473

Anticorrosive paint and 2 coats enamel paint per piller 21610.00


& 2 coats ofwhite washing to pillers as directed

APPROVED B.S.R FOR THE FIRST HALF OF 2004 IN


ALUMINIUM WORK

Analysis 1st half - Mullaitivu


Page 38 of 473

Item Description Unit RATE (1st)

1/AL Aluminium Partition with sliding door S.ft 353.00


m2 3797.00

2/AL Aluminium Casement with project S.ft 610.00


m2 6569.00

3/AL Aluminium Door frame only S.ft 143.00


m2 1544.00

4/AL Aluminium door fully glazed double hung S.ft 735.00


m2 7906.00

5/AL Al Double hung Door with panneled and S.ft 733.00


glazed m2 7885.00

6/AL Al single hung Door with fully glazed S.ft 702.00


m2 7550.00

7/AL Al Single hung Door with panneled and S.ft 700.00


glazed m2 7528.00

Analysis 1st half - Mullaitivu


Page 39

RATE ANALYSIS FIRST HALF OF 2004 IN


DEMOLISHER.
No Qty Unit Code Description Unit Rate Rate Amount
1/1 Brick work in cement, demolished
brick stacked and debris cleared.

Per cube

2 1/2 Days 257 labourer 325.00 812.50


Allow for scaffolding 40.63 853.13
Over heads 119.44
Per cube 972.56
Say Rs Per cube 973.00
Per m3 343.82
Say Per m3 344.00

2/1 Brick work in lime, demolished brick


- do - - do -.

Per cube

2 Days 257 Labourer 325.00 650.00


Allow for scaffolding 32.50 682.50
Over heads 95.55
Per cube 778.05
Say Per cube 778.00
Per m3 274.91
Say Per m3 275.00

5/2 Ceiling,existing,removed materials


stacked and debris cleared.

Per Sqrs.

1 1/2 Hour 214 Carpenter 475.00 89.06


3 Hour 257 Labourer 325.00 121.88
Allow for scaffolding 6.09 217.03
Over heads 30.38
Per square 247.42
Say per sqrs 247.00
Per m2 26.59
Say Per m2 26.60

6/2 Cement concrete demolished, and


debris cleared away.

Per Sqrs (6" floor)

4 Day 257 Labourers 325.00 1,300.00


1/2 Day 257 Labourer for Transporting 325.00 162.50 1,462.50
Over heads 204.75
Say per Sqrs/ 0.5 cube 1,667.25
Say per sqrs Rs 1,667.00
Per m2 179.44
Say per m2 179.00
No Qty Unit Code Description Unit Rate Rate Amount

Analysis 1st half - Mullaitivu


Page 40

7/2 Cement concrete,reinforced,demolished


in suspended floors,reinforcement
removed and debris cleared.

Per Sqrs. (4" floor)

6 Day 257 Labourers 325.00 1,950.00


1/2 Day 257 Labourers for Transporting 325.00 162.50 2,112.50
Over heads 295.75
Per Sqrs/ per 1/3 cube 2,408.25
Say per Sqrs/ per 1/3 cube 2,408.00
Per m2 259.20
Say per m2 259.00

8/2 Corrugated sheets, Iron, Asbestoes or


Aluminium Alloy, removed from roof or
walls and stacked. For single storey

Per Sqrs.

2 Hour 214 Blacksmith 475.00 118.75


3 Hour 257 Labourer 325.00 121.88
Allow for scaffolding 6.09 246.72
Over heads 34.54
Per square 281.26
Say per Sqrs 281.00
Per m2 30.25
Say per m2 30.20

9/3 Corrugated sheets asbestos or aluminium


alloy removed from roofs or walls of
2storeyed buildings

Per square

2 Hrs 214 Blacksmith 475.00 118.75


3 Hrs 257 Labourer 325.00 121.88
0.5 Hrs 257 Labourer (add for extra Height) 325.00 20.31
Allow for scaffolding 6.09 267.03
Overheads 37.38
per square 304.42
Say per square 304.00
per m2 32.72
Say per m2 33.00

11/3 Door or window,size up to 40 S.ft removed


from existing walls and stacked per door
or window.
Per No.

2 1/2Day 257 Labourers 325.00 325.00 325.00


Over heads 45.50
Per No 370.50
Say Rs 371.00

No Qty Unit Code Description Unit Rate Rate Amount

Analysis 1st half - Mullaitivu


Page 41

12/3 Door window, size over 40 S.ft removed


- do - - do -
Per No.

3 1/2Day 257 Labourers 325.00 487.50 487.50


Over heads 68.25
Per No 555.75
Say Rs 556.00

13/4 Door or window, sash only, upto 40 S.ft


removed from existing walls and stacked.

Per Sash.

1/2 Hour 214 Carpenter 475.00 29.69


1/2 Hour 257 Labourer 325.00 20.31 50.00
Over heads 7.00
Per sash 57.00
Say Rs 57.00

14/4 Door or window, sash only, over 40 S.ft


- do - - do -
Per Sash.

3/4 Hour 214 Carpenter 475.00 44.53


3/4 Hour 257 Labourer 325.00 30.47 75.00
Over heads 10.50
Per sash 85.50
Say Rs 86.00

15/4 Down pipes, 4" to 6" dia. G.I old or


decayed, removed from existing building
and stacked.

Per 12.0 L.ft.


1 Hour 257 Labourer 325.00 40.63 40.63
Over heads 5.69
Per L.ft 3.86
Say per L.ft. 3.90
Per L.m 12.79
Say per L.m. 12.80

16/4 Drains demolished and debris cleared.


Per 10.0 L.ft
0.13 Cube Brick in cement demolished (as in Item A.1 812.50 105.63 105.63
less scaffolding)
Over heads 14.79
Per L.ft 12.04
Say per L.ft. 12.00
Per L.m 39.36
Say per L.m. 39.40
No Qty Unit Code Description Unit Rate Rate Amount
18/5 Fence uprooted, Barbed wire rolled up
and all materials stacked (length of
fencing to measured).

Analysis 1st half - Mullaitivu


Page 42

Per 50 L.ft. (6 posts)

3 Hour 257 Labourers 325.00 121.88


2 Day 257 Labourers 325.00 650.00 771.88
Over heads 108.06
Per L.ft 17.60
Say per L.ft. 18.00
Per L.m 59.04
Say per L.m. 59.00

19/5 Floors brick paved, demolished and


debris cleared away.

Per Sqrs 3" thick

1/4 Cube demolition as in item 2 (less scaffolding). 650.00 162.50


Add 50% for extra difficulty. 81.25 243.75
Overheads 34.13
Per square 3" thick 277.88
Say per Sqrs 278.00
Per m2 29.92
Say per m2 30.00

20/6 Gate sash removed and stacked after


demolishing cement concrete blocks
or removing posts and separating
pintles (demolishing brick work where
necessary paid for seperately).

2 1/2Days 257 Labourers 325.00 325.00 325.00


Overheads 45.50
Per No 370.50
Say Rs 371.00

21/6 Glass panes in doors and windows and


fanlight removed and stacked.

Per 6 S.ft.

1 1/2 Hour 214 Carpenter 475.00 89.06 89.06


Over heads 12.47
Per 6 S.ft 101.53
Per S.ft 16.92
Say per S.ft. 16.90
Per m2 182.08
Say per m2 182.00

No Qty Unit Code Description Unit Rate Rate Amount


22/6 Gutter, eaves, removed and stacked-
from roof of single storeyed building

Per 40.0 L.ft.

Analysis 1st half - Mullaitivu


Page 43

2 1Hour 257 Labourers 325.00 81.25


Allow for scaffolding 4.06 85.31
Over heads 11.94
Per 40 L.ft 97.26
Per L.ft 2.43
Say per L.ft. 2.40
Per L.m 7.87
Say per L.m. 7.90

23/6 Gutter, eaves, removed from roofs of 2


storeyed building and stacked.
Per 40.0 L.ft.

2 1Hour 257 Labourers 325.00 81.25


Add 50% 40.63
Allow for scaffolding 5% 6.09 127.97
Over heads 17.92
Per L.ft 3.65
Say per L.ft. 3.60
Per L.m 11.81
Say per L.m. 11.80

25/7 Partitions removed and stacked at site,


including making good to walls and floors.

Per 105.0 Sq.ft.

1 Day 214 Carpenter 475.00 475.00


2 Day 257 Labourers 325.00 650.00
1/4 Day 214 Mason 475.00 118.75
Allow for cement, sand etc. 65.00 1,308.75
Over heads 183.23
Per S.ft 14.21
Say per S.ft. 14.20
Per m2 152.89
Say per m2 153.00

26/7 Lime plastering chipped and debris


cleared away.

Per Sqrs.

3 Hour 257 Labourer 325.00 121.88 121.88


Overheads 17.06
Per square 138.94
Say per Sqrs 139.00
Per m2 14.96
Say per m2 15.00

No Qty Unit Code Description Unit Rate Rate Amount


27/4 Rendering, cement, chipped and debris
cleared away from brick walls and floors.

Per Sqrs.

Analysis 1st half - Mullaitivu


Page 44

9 Hour 257 Labourer 325.00 365.63 365.63


Over heads 51.19
Per square 416.81
Say per Sqrs 416.00
Per m2 44.78
Say per m2 45.00

28/8 Rendering, cement, shipped and debris


cleared away from cement concrete
floors and walls.

Per Sqrs.

9 Hour 257 Labourer 325.00 365.63


Add 50% 182.81 548.44
Over heads 76.78
Per square 625.22
Say per sqrs 625.00
per m2 67.28
Say per m2 67.00

29/8 Roof, removing tiles and timber, stacking


serviceable material and cleaning debris
in single storeyed building.

Per Sqrs.

1/4 Day 214 Carpenter 475.00 118.75


4 1/4Day 257 Labourers 325.00 325.00
Allow for scaffolding 16.25 460.00
Over heads 64.40
Per square 524.40
Say per square 524.00
Per m2 56.40
Say per m2 56.00

30/8 Roof, removing tiles and timber - do -


- do - in 2 storeyed buildings.

Per Sqrs.

1/4 Day 214 Carpenter 475.00 118.75


4 1/4Day 257 Labourer 325.00 325.00
2 1/4Day 257 Labourer 325.00 162.50
Allow for scaffolding 24.38 630.63
Over heads 88.29
Per square 718.91
Say per square 719.00
Per m2 77.40
Say per m2 77.00

No Qty Unit Code Description Unit Rate Rate Amount


32/9 Rubble masonary in cement, demolished,
rubble stacked and debris cleared.

Per Cube.

Analysis 1st half - Mullaitivu


Page 45

2 1/2 Day 257 Labourer 325.00 812.50


Add 25% 203.13
Allow for scaffolding 50.78 1,066.41
Over heads 149.30
Per cube 1,215.70
Say per cube 1,216.00
Per m3 429.68
Say per m3 430.00

33/9 Rubble masonry in lime demolished


rubble stacked and debris cleared away

Per Cube

2 Day 257 Labourer 325.00 650.00


Allow for scaffolding 32.50 682.50
Overheads 95.55
Per cube 778.05
Say per Cube 778.00
Per m3 274.91
Say per m3 275.00

34/9 Tiles, glazed demolished and debris


cleared.

Per Sqrs.

2 Day 257 Labourer 325.00 650.00 650.00


Overheads 91.00
Per Square 741.00
Say per square 741.00
Per m2 79.76
Say per m2 80.00

35/10 Tiles calicut or half round, removed from


roof of single storeyed buildings and
stacked at site.

Per Sqrs.

4 Hour 257 Labourer 325.00 162.50


Allow for scaffolding 8.13 170.63
Over heads 23.89
Per square 194.51
Say per square 195.00
Per m2 20.99
Say per m2 21.00

No Qty Unit Code Description Unit Rate Rate Amount


36/10 Tiles calicut of half round removed from
roof of 2 storeyed buildings and stacked.

Per Sqrs.

Analysis 1st half - Mullaitivu


Page 46

4 Hour 257 Labourer 325.00 162.50


2 Hour 257 Labourer 325.00 81.25
Allow for scaffolding 12.19 255.94
Overheads 35.83
Per square 291.77
Say per square 292.00
Per m2 31.43
Say per m2 31.00

39/11 Ceiling Asbestoes, removing including


timber frame work, stacking serviceable
materials storeyed building- (and debris
cleared away in single).

Per Sqrs.
1 Day 214 Carpenter 475.00 475.00
1 Day 257 Labourer 325.00 325.00
Allow for scaffolding 16.25 816.25
Over heads 114.28
Per square 930.53
Say Rs 931.00
Per m2 100.22
Say per m2 100.00

40/11 Ceiling Asbestoes removing including


timber frame work - do - - do -
in 2 storeyed building.
Per Sqrs.
1 Day 214 Carpenter 475.00 475.00
1 Day 257 Labourer 325.00 325.00
1/4 Day 257 Labourer (02) 325.00 162.50
Allow for scaffolding 24.38 986.88
Over heads 138.16
Per square 1,125.04
Say per square 1,125.00
Per m2 121.10
Say per m2 121.00
41/11 Valance/Barge boarding removed,
materials stacked and debris cleared
away in single storeyed building.
Per 40.0 L.ft
2 1Hour 257 Labourer 325.00 81.25
Allow for scaffolding 4.06 85.31
Over Heads 11.94
Per L.ft 2.43
Say per L.ft. 2.40
Per L.m 7.87
Say per L.m. 7.90
No Qty Unit Code Description Unit Rate Rate Amount
42/11 Valance/Barge boarding removed - do -
- do - in 2 storeyed building.

Per 40.0 L.ft.

2 11/2hr 257 Labourer 325.00 121.88


Scaffolding 6.09 127.97

Analysis 1st half - Mullaitivu


Page 47

Over Heads 17.92


Per L.ft 3.65
Say per L.ft. 3.60
Per L.m. 11.81
Say per L.m. 11.80

43/12 Cement plastering, soffit chipped, and


debris cleared away.

Per Sqrs.

1 1/8 Day 257 Labourer 325.00 365.63


Add 25% for extra difficulty 91.41
Allow for scaffolding 5% 18.28 475.31
Over Heads 66.54
Per square 541.86
Say per square 542.00
Per m2 58.34
Say per m2 58.00

RATE ANALYSIS FIRST HALF OF 2004 IN


EXCAVATOR
No Qty Unit Code Description Unit Rate Rate Amount
1 Drains, earth, in any soil except rock
requiring blasting cut to gradient and
shaped as directed soil deposited
within site.

Analysis 1st half - Mullaitivu


Page 48

Per Cube.
1 3/8 day 257 Labourer 325 446.88
1/3 no 24 Basket 52.5 17.50 464.38
Overheads 65.01
Per Cube 529.39
Say per cube 529.00
Per m3 186.93
Say per m3 187.00
2/13 Excavation in any soil except rock requiring
blasting part returnfill in and ram, and
surplus disposed of within site as directed.
Per Cube.
1 5/8 day 257 Labourer 325 528.13
1/3 no 24 Basket 52.5 17.50 545.63
Overheads 76.39
Per Cube 622.01
Say per cube 622.00
Per m3 219.79
Say per m3 220.00
4/14 Filling under floor with gravel or other
approved quality of filling, spread,
watered and well rammed in 3" layers
with available earth.
Per Cube.
1 3/4 day 257 Labourer 325 568.75
413 Allow for water 50 50.00
1/3 24 Basket 52.5 17.50 636.25
Overheads 89.08
Per Cube 725.33
Say per cube 725.00
Per m3 256.18
Say per m3 256.00
6/14 Filling under floor with gravel or other
approved quality of filling spread water
and rammed in 3" layers (material not
available at site).
Per Cube.
1 Cube 61 Earth 1850 1,850.00
2 day 257 Labourer 325 650.00
Allow for compactive 10% 65 65.00
413 Allow for water 50 50.00
1/3 24 Basket 52.5 17.50 2,632.50
Overheads 368.55
Per Cube 3,001.05
Say per cube 3,001.00
Per m3 1,060.42
Say per m3 1,060.00
No Qty Unit Code Description Unit Rate Rate Amount
7/15 External Filling.(Material not available at site)

Per Cube.
1 Cube 61 Earth 1850 1,850.00
1/2 day 257 Labourer 325 162.50
1/3 no 24 Basket 52.5 17.50 2,030.00
Overheads 284.20
Per Cube 2,314.20

Analysis 1st half - Mullaitivu


Page 49

Say per cube 2,314.00


Per m3 817.67
Say per m3 818.00

8/15 External Filling.(Material available at site)

Per Cube.
1/2 day 257 Labourer 325 162.50
1/3 no 24 Basket 52.5 17.50 180.00
Overheads 25.20
Per Cube 205.20
Say per Cube 205.00
Per m3 72.51
Say per m3 73.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU


CONCRETOR.
No Qty Unit Description Unit Rate Rate Amount

1/15 Cement concrete 1:3:6 with 2" metal,


above one cube. (Shuttering paid for
seperately).

Per Cube.

Analysis 1st half - Mullaitivu


Page 50

11.25 Cwts 46 Cement 520.00 5,850.00


0.56 Cube 197 Sand 2100.00 1,176.00
1 Cube 137 2" Metal 7850.00 7,850.00
1 Day 214 Mason 475.00 475.00
8 Day 257 Labourer 325.00 2,600.00
2/3 24 Basket 52.50 35.00
410 Allow for water 125.00 125.00 18,111.00
Over heads 2,535.54
Per cube 20,646.54
Say per cube 20,647.00
Per m3 7,295.76
Say per m3 7,296.00

2/15 Cement concrete 1:3:6 (2") upto 1 cube.


(Shuttering paid for seperately).

Per Cube.

As in Item 1 18,111.00
Add 25% of Cost of labourer 650.00 18,761.00
Over heads 2,626.54
Per cube 21,387.54
Say per cube 21,388.00
Per m3 7,557.60
Say per m3 7,558.00

Cement concrete 1:2 1/2:5 (1") above 1


3/15 cube (Shuttering paid for seperately).
Per Cube.

13.6 Cwts 46 Cement 520.00 7,072.00


0.6 Cube 197 Sand 2100.00 1,260.00
1 Cube 136 1" metal 8470.00 8,470.00
1 Day 214 Mason 475.00 475.00
8 Day 257 Labourer 325.00 2,600.00
2/3 24 Baskets 52.50 35.00
410 Allow for water 125.00 125.00 20,037.00
Over heads 2,805.18
Per cube 22,842.18
Say per cube 22,842.00
Per m3 8,071.38
Say per m3 8,071.00

No Qty Unit Description Unit Rate Rate Amount


2a/16 Cement concrete 1:3:6 (1 1/2") above 1
cube (shuttering paid for seperately).

Per Cube.

11.25 Cwt 46 Cement 520.00 5,850.00


1 cube 135 Metal (1 1/2") 8020.00 8,020.00
0.56 cube 197 Sand 2100.00 1,176.00
2/3 No 24 Basket 52.50 35.00

Analysis 1st half - Mullaitivu


Page 51

410 Allow for water 125.00 125.00


1 day 214 Mason 475.00 475.00
8 day 257 Labourer 325.00 2,600.00 18,281.00
Over heads 2,559.34
Per cube 20,840.34
Say per cube 20,840.00
per m3 7,363.96
Say per m3 7,364.00

2c/16 Cement concrete 1:3:6 (1") above 1


cube (shuttering paid for seperately).

Per Cube.

11.25 Cwt 46 Cement 520.00 5,850.00


1 cube 136 1" Metal 8470.00 8,470.00
0.56 cube 197 Sand 2100.00 1,176.00
2/3 24 Basket 52.50 35.00
410 Allow for water 125.00 125.00
1 day 214 Mason 475.00 475.00
8 day 257 Labourer 325.00 2,600.00 18,731.00
Over heads 2,622.34
Per cube 21,353.34
Say per cube 21,353.00
per m3 7,545.23
Say per m3 7,545.00

4/16 Cement concrete 1:2 1/2:5 (1") upto one


cube (Shuttering paid for seperately).

Per Cube.

As in Item 3 20,037.00
Add 25% of Cost of labourer 650.00 20,687.00
Over heads 2,896.18
Per cube 23,583.18
Say per cube 23,583.00
Per m3 8,333.22
Say per m3 8,333.00

No Qty Unit Code Description Unit Rate Rate Amount


5/16 Cement concrete 1:2:4 (3/4") above 1 cube
(Shuttering paid for seperately).

Per Cube.

16 Cwts 46 Cement 520.00 8,320.00


0.6 Cube 197 Sand 2100.00 1,260.00
1 Cube 138 3/4" metal 8830.00 8,830.00
1 Day 214 Mason 475.00 475.00

Analysis 1st half - Mullaitivu


Page 52

8 Day 257 Labourer 325.00 2,600.00


2/3 24 Basket 52.50 35.00
410 Allow for water 125.00 125.00 21,645.00
Over heads 3,030.30
Per cube 24,675.30
Say per cube 24,675.00
Per m3 8,719.08
Say per m3 8,719.00

6/16 Cement concrete 1:2:4 (3/4") upto 1 cube


(Shuttering paid for seperately).

Per Cube.

As in Item 5 21,645.00
Add 25% of Cost of Labourer 650.00 22,295.00
Over heads 3,121.30
Per cube 25,416.30
Say per cube 25,416.00
Per m3 8,980.92
Say per m3 8,981.00

11/18 Drains, semi circular, in cement concrete


1:3:6 (1") 9" wide and 9" average depth,
with 3" thick sides and base, inclusive
of 1/2" cement rendering 1:3 and
expansion joints as necessary, including
necessary excavation (without ramp).

Per 10.0 L.ft.

1.25 Cwts 46 Cement 520.00 650.00


0.06 Cube 197 Sand 2100.00 126.00
0.08 Cube 136 1" metal 8470.00 677.60
1/2 Day 214 Mason 475.00 237.50
1 Day 257 Labourer 325.00 325.00
1/2 Day 214 Mason (Rendering) 475.00 237.50
1/2 Day 257 Labourer (Rendering) 325.00 162.50
Allow for shuttering, baskets etc.10% 96.25 2,512.35
Over heads 351.73
Per 10 L.ft 2,864.08
Per L.ft 286.41
Say per L.ft. 286.00
Per L.m. 938.08
Say per L.m. 938.00

No Qty Unit Code Description Unit Rate Rate Amount


12/19 Lintol cement concrete 1:2:4 (3/4")
4 1/2"x6" (Reinforcement paid for seperately)
with form work
Per 10.0 L.ft.

0.3 Cwts 46 Cement 520.00 156.00


0.01 Cube 197 Sand 2100.00 21.00
0.02 Cube 138 3/4" metal 8830.00 176.60
14 S.ft 182 Planks (1/4 new cost) 50.00 175.00

Analysis 1st half - Mullaitivu


Page 53

Allow for use of timber props and nails 40.63 40.63


2 Hour 214 Carpenter 475.00 118.75
2 Hour 257 Labourer 325.00 81.25
2 Hour 214 Mason 475.00 118.75
2 Hour 257 2 Labourers 325.00 162.50 1,050.48
Over heads 147.07
Per 10 L.ft 1,197.54
Per L.ft 119.75
Say per L.ft 120.00
Per L.m. 393.60
Say per L.m. 394.00
13/19 Lintol, cement concrete 1:2:4 (3/4") 9"x6"
(Reinforcement paid for seperately).
with form work
Per 10.0 L.ft.
0.6 Cwts 46 Cement 520.00 312.00
0.02 Cube 197 Sand 2100.00 42.00
0.035 Cube 138 3/4" metal 8830.00 309.05
17 S.ft 182 Planks (1/4 new cost) 50.00 212.50
Allow for use of timber props & nails water etc 65.63 65.63
2 Hour 214 Carpenter 475.00 118.75
2 Hour 257 Labourer 325.00 81.25
2 Hour 214 Mason 475.00 118.75
2 Hour 257 2 Labourers 325.00 162.50 1,422.43
Over heads 199.14
Per 10 L.ft 1,621.56
Per L.ft 162.16
Say per L.ft. 162.00
Say per L.m. 531.00
14/20 Lintol, cement, concrete, 1:2:4 (3/4"),
9"x9" (Reinforcement paid for seperately).
with form work
Per 15.0 L.ft.
1.35 Cwts 46 Cement 520.00 702.00
0.04 Cube 197 Sand 2100.00 84.00
0.08 Cube 138 3/4" Metal 8830.00 706.40
34 S.ft 182 Planks (1/4 new cost) 50.00 425.00
Allow for nails & props & water. 90.63 90.63
3 Hour 214 Carpenter 475.00 178.13
3 Hour 257 Labourer 325.00 121.88
1/2 Day 257 Labourer (02) 325.00 325.00
1/2 Day 214 Mason 475.00 237.50 2,870.53
Over heads 401.87
Per 15 L.ft 3,272.40
Per L.ft 218.16
Say per L.ft 218.00
Say per L.m 715.00
No Qty Unit Code Description Unit Rate Rate Amount
19/22 Padstones, cement, concrete 1:2:4 (3/4"
metal) precast or in situ.
Per 4 Nos. = Size 1-6x1-1 1/2x0-6
0.58 Cwts 46 Cement 520.00 301.60
0.02 Cube 197 Sand 2100.00 42.00
0.035 Cube 138 3/4" Metal 8830.00 309.05
12 S.ft 182 Planks (1/4 new cost) 50.00 150.00
2 Hour 214 Mason 475.00 118.75
2 Hour 257 Labourer (02) 325.00 162.50

Analysis 1st half - Mullaitivu


Page 54

allow for water 20.31 20.31 1,104.21


Over heads 154.59
Per 4 Nos. 1,258.80
Per No. 314.70
Say per No. 315.00

19a/22 Padstones, cement, concrete 1:2:4 (3/4"


metal) precast or in situ.
Per 4 Nos. - Size - 1-0x0-6x0-6

.17 Cwts 46 Cement 520.00 88.40


0.01 Cube 197 Sand 2100.00 21.00
.01 Cube 138 3/4" Metal 8830.00 88.30
6 S.ft 182 Planks (1/4 new cost) 50.00 75.00
2 hour Labour 325.00 81.25
1 hour mason 475.00 59.38
413.33
Overheads 57.87
Per 4 Nos 471.19
Per no 117.80
Say per No 118.00

21/23 Slabs over drain, cement concrete 3"


thick, 1:2:4 (3/4" metal) reinforced with
expended metal and 1/2" cement
rendered 1:2 (R/F paid for seperately).

Per 15.0 S.ft.

0.6 Cwts 46 Cement( For slab) 520.00 312.00


0.02 Cube 197 Sand 2100.00 42.00
0.04 Cube 138 3/4" Metal 8830.00 353.20
16 S.ft 182 Shuttering planks (1/4 new cost) 50.00 200.00
2 Hour 214 Mason 475.00 118.75
2 Hour 257 Labourer (02) 325.00 162.50
1,188.45
0.23 Cwts 46 Cement(For rendering) 520.00 119.60
0.01 Cube 200 Sand 2100.00 21.00
1 Hour 214 Mason 475.00 59.38
1 Hour 257 Labourer 325.00 40.63
414 Allow for water 25.00 25.00 1,454.05
Over heads 203.57
Per 15 S.ft 1,657.62
Per S.ft 110.51
Say per S.ft. 111.00
Per M2 1,194.83
Say Per M2 1,195.00
No Qty Unit Code Description Unit Rate Rate Amount
21a/23 Slabs over drain, cement concrete 2"
thick, 1:2:4 (3/4" metal) reinforced with
expended metal and 1/2" cement
rendered 1:2 (R/F paid for seperately).
Per 15 L.ft
As in item 21 ('2" concrete for slab x 2/3) 792.30
0.23 Cwts 46 Cement(For rendering) 520.00 119.60
0.01 Cube 200 Sand 2100.00 21.00
1 Hour 214 Mason 475.00 59.38

Analysis 1st half - Mullaitivu


Page 55

1 Hour 257 Labourer 325.00 40.63


Allow for water 5.08 5.08 1,037.98
Over heads 145.32
Per 15 S.ft 1,183.30
Per S.ft 78.89
Say per S.ft. 79.00
Per M2 850.38
Say Per M2 850.00

25a/25 Cement concrete 1:1 1/2:3 (3/4").

Per Cube.
23 Cwt 46 Cement 520.00 11,960.00
0.82 cube 138 3/4" Metal 8830.00 7,240.60
0.42 cube 197 Sand 2100.00 882.00
1 day 214 Mason 475.00 475.00
6 day 257 Labourer 325.00 1,950.00
1/3 day 97 Hire of mixure, vibrator etc. 4500.00 1,500.00
410 Allow for water 125.00 125.00
2/3 24 Basket 52.50 35.00 24,167.60
Over heads 3,383.46
Per cube 27,551.06
Say per cube 27,551.00
Per m3 9,735.34
Say per m3 9,735.00

23/24 Spur Stones, cement concrete 1:2:4 (3/4")


for door posts supplied and fixed.

Per 10.0 Stone.


0.15 Cu.ft 138 3/4" Metal 88.30 13.25
0.07 Cu.ft 197 Sand 21.00 1.47
Allow for moulds 32.50 32.50
0.03 Cwt 46 Cement 520.00 15.60
2 Hour 214 Mason 475.00 118.75
2 Hour 257 Labourer 325.00 81.25 262.82
Over heads 36.79
Per 10 Stones 299.61
Per Stone 29.96
Say per stone 29.00

No Qty Unit Code Description Unit Rate Rate Amount


25/25 Cement concrete 1:2 1/2:5 (1") using
concrete mixer and vibrator
(Shuttering paid for seperately).

Per cube.

14 Cwts 46 Cement 520.00 7,280.00


0.6 Cube 197 Sand 2100.00 1,260.00
1 Cube 136 1" Metal 8470.00 8,470.00

Analysis 1st half - Mullaitivu


Page 56

1 Day 214 Mason 475.00 475.00


6 Day 257 Labourer 325.00 1,950.00
2/3 24 Basket 52.50 35.00
410 Allow for water and curing 125.00 125.00
1/3 Day 97 Hire of mixer, vibrator,wages of operator fuel 4500.00 1,500.00 21,095.00
Over heads 2,953.30
Per cube 24,048.30
Say per cube 24,048.00
Per m3 8,497.53
Say per m3 8,498.00

26/25 Cement concrete 1:2:4 (3/4") in Column


shafts (Reinforcements shuttering and
finishes paid for seperately) in ground
floor using mixer and vibrator.

Per Cube.
18 Cwts 46 Cement 520.00 9,360.00
0.6 Cube 197Sand 2100.00 1,260.00
1 Cube 1383/4" Metal 8830.00 8,830.00
1 Day 214Mason 475.00 475.00
6 Day 257Labourer 325.00 1,950.00
2/3 24 Basket 52.50 35.00
Allow for water and curing 125.00 125.00
1/3 Day 97 Hire ofmixer,vibrator,wagesof operator and fuel. 4500.00 1,500.00 23,535.00
Over heads 3,294.90
Per cube 26,829.90
Say per cube 26,830.00
Per m3 9,480.57
Say per m3 9,481.00

27/25 Cement concrete as per Item 26 in 1st


floor.

As per Item 26 23535.00 23,535.00


2 Day 257 Labourer 325.00 650.00 24,185.00
Over heads 3,385.90
Per cube 27,570.90
Say per cube 27,571.00
Per m3 9,742.40
Say per m3 9,742.00

No Qty Unit Code Description Unit Rate Rate Amount


28/25 Cement concrete as per Item 26 in 2nd
floor.
As per Item 26 23535.00 23,535.00
5 Day 257 Labourer 325.00 1,625.00 25,160.00
Over heads 3,522.40
Per cube 28,682.40
Say per cube 28,682.00
Per m3 10,134.98
Say per m3 10,135.00

Analysis 1st half - Mullaitivu


Page 57

29/26 Cement concrete 1:2:4 (3/4") in beams in


ground floor (reinforcements shuttering
and finishes paid for seperately) using
mixer and vibrator.

Per 2 Cube.
36 Cwts 46 Cement 520.00 18,720.00
1.2 Cube 197 Sand 2100.00 2,520.00
1.8 Cube 138 3/4" Metal 8830.00 15,894.00
2 1/2 Day 214 Mason 475.00 1,187.50
16 Day 257 Labourer 325.00 5,200.00
1 1/3 24 Basket 52.50 70.00
411 Allow for water and curing 250.00 250.00
2/3 Day 97 Hire of concrete mixer vibrators, Operators
Salary, fuel 4500.00 3,000.00
46,841.50
Over heads 6,557.81
Per 2 cube 53,399.31
Per cube 26,699.66
Say per cube 26,700.00
Per m3 9,434.63
Say per m3 9,435.00

30/26 Cement concrete as per Item 29 in 1st


floor.
Per Cube.

As per Item (29) per cube 23420.75 23,420.75


2 Day 257 Labourer 325.00 650.00 24,070.75
Over heads 3,369.91
Per cube 27,440.66
Say per cube 27,441.00
Per m3 9,696.47
Say per m3 9,696.00

31/26 Cement concrete as per Item 29 in 2 nd


floor.
Per 1Cube.
As per Item 29 per cube 23420.75 23,420.75
5 Day 257 Labourer 325.00 1,625.00 25,045.75
Over heads 3,506.41
Per cube 28,552.16
Per Cube 28,552.16
Say per cube 28,552.00
Per m3 10,089.05
Say per m3 10,089.00
No Qty Unit Code Description Unit Rate Rate Amount
32/26 Shuttering for floor slab concrete and
dismantling.

Per Sqrs.

115 S.ft 57 Planks Rubber(1/2new cost) 20.00 1,150.00


50 L.ft 123 4"x2" Class II joists (1/10 cost) 40.00 200.00
30 props 19 30 props (10-12) feet 4"x2" coconut (1/15cost) 300.00 600.00
2 Ibs 267a Wire nails 2" 36.50 73.00
1/4 Gallon 147 Mould oil 100.00 25.00

Analysis 1st half - Mullaitivu


Page 58

1 Day 214 Carpenter 475.00 475.00


3 Day 257 Labourer 325.00 975.00 3,498.00
Over heads 489.72
Per square 3,987.72
Say per sqrs 3,988.00
Per m2 429.28
Say per m2 429.00

33/27 Shuttering for column shaft and


dismantling (for column 9"x9"x4 ft. heigh
I.e 4 1/2 ft. box).

Per 12.0 Sq.ft.


16 1/2 S.ft 182
1"planks/15mm plywood/Ginisappu 1/4 cost 50.00 206.25
15 L.ft 300
2"x2" Class II battens (1/6 cost) 13.00 32.50
0.03 gal 147
Mould oil 100.00 3.00
6 Nos 301
3/8" dia 18" bolts, nuts and washers(1/15 cost) 13.00 5.20
Allow for screws and nails 32.50 32.50
5 Props 19 Coconut rafters (1/30 cost) 300.00 50.00
3/8 Day 214 Carpenter 475.00 178.13
3/8 Day 257 Labourer 325.00 121.88 629.45
Over heads 88.12
Per 12 S.ft 717.57
Per S.ft 59.80
Say per S.ft. 60.00
Per m2 645.86
Say per m2:- 646.00

33a/27 Shuttering for footing and walls etc.

Per 80 S.ft
86 S.ft 57 Rubber planks ( 1/2 new cost) 20.00 860.00
2 Lbs 267a 2" Nails 36.50 73.00
1/8 Gal 147 Mould Oil 100.00 12.50
1/4 Day 214 Carpenter 475.00 118.75
1/4 Day 257 Labourer 325.00 81.25 1,145.50
overheads 160.37
Per 80 S.ft 1,305.87
per S,ft 16.32
Say per Sft 16.00
Say per m2 172.16

No Qty Unit Code Description Unit Rate Rate Amount


34/27 Shuttering for beam including dismantling
(12"x18" beam 20 ft. long).

Per 80.0 Sq.ft.


86 S.ft 182 Ginisapu planks / Plywood 15mm thick 1/4 cost 50.00 1,075.00
200 L.ft 300 2"x2" Class II timber 1/4cost 13.00 650.00
14 No 19 Coconut rafters(each 10' ) (1/20 cost) 300.00 210.00
7 Ibs 267a 2" to 3" wire nails 36.50 255.50
1/8 Glns 147 Mould oil 100.00 12.50
1 day 257 Labourer 325.00 325.00

Analysis 1st half - Mullaitivu


Page 59

1 Day 214 Carpenter 475.00 475.00 3,003.00


Over heads 420.42
Per 80 S.ft of beam surface ( 3 sides) 3,423.42
There 1 S.ft of beam surface (3 sides) 42.79
Say per S.ft. 43.00
Say per m2 463.00

35/28 Cement concrete 1:2:4(3/4") lintol in


ground floor (reinforcement and
shuttering paid for seperately) using
mixer and vibrator.

Per Cube.
18 Cwt 46 Cement 520.00 9,360.00
0.6 Cube 197 Sand 2100.00 1,260.00
0.9 Cube 138 Metal 8830.00 7,947.00
1 Day 214 Mason 475.00 475.00
6 Day 257 Labourer 325.00 1,950.00
410 Allow for water and curing 125.00 125.00
2/3 No 24 Basket 52.50 35.00
1/2 Day 97 Hire of mixer, vibrator, wages of operators & fuel 4500.00 2,250.00 23,402.00
Over heads 3,276.28
Per cube 26,678.28
Say per cube 26,678.00
Per m3 9,426.86
Say per m3 9,427.00

36/28 Cement concrete lontols as per Item (35)


in 1st floor.

Per Cube.35
As per Item 35 in groung floor 23402.00 23,402.00
2 Day 257 Labourer 325.00 650.00 24,052.00
Over heads 3,367.28
Per cube 27,419.28
Say per cube 27,419.00
Per m3 9,688.69
Say per m3 9,689.00

No Qty Unit Code Description Unit Rate Rate Amount


37/28 4" thick R.C.C 1:2:4 (3/4") in first floor slab
(reinforcement and shuttering paid for
seperately) using mixer and bibrator.

Per 8.0 Sqrs.


45 1/3 Cwts 46 Cement 520.00 23,573.33
2.4 Cube 138 Metal 3/4" 8830.00 21,192.00
1.6 Cube 197 Sand 2100.00 3,360.00
1 Day 97 Hire of mixer, vibrator with operator and fuel 4500.00 4,500.00
4 Day 214 Mason 475.00 1,900.00

Analysis 1st half - Mullaitivu


Page 60

22 Day 257 Labourer 325.00 7,150.00


411 Allow for water curing 250.00 250.00
1 4/5 No 24 Basket 52.50 94.50 62,019.83
Over heads 8,682.78
Per 8 Sqrs 70,702.61
Per Sqrs 8,837.83
Say per Sqrs 8,838.00
Per m2 951.35
Say per m2 951.00

38/29 5" thick R.C.C in 1st floor - do -


- do - - do -
- do - - do -

8.0 Sqrs.
56 2/3 Cwt 46 Cement 520.00 29,466.67
3 Cube 138 Metal 3/4" 8830.00 26,490.00
2 Cube 197 Sand 2100.00 4,200.00
4 Day 214 Mason 475.00 1,900.00
25 Day 257 Labourer 325.00 8,125.00
411 Allow for water curing 375.00 375.00
1 Day 97 Hire of mixer vibrator operators wages and 4500.00 4,500.00
fuel
2 1/5 No 24 Basket 52.50 115.50 75,172.17
Over heads 10,524.10
Per 8 Sqrs 85,696.27
Per Sqrs 10,712.03
Say per Sqrs 10,712.00
Say Per m2 1,153.00
per cube 25,708.80
Say per cube 25,708.00

No Qty Unit Code Description Unit Rate Rate Amount

40/29 Drains in cement concrete 1:3:6(1") as above


But with ramp 2' 6" wide

Per 10 L.ft

Drains as per Item 39 2,864.08


6.25 C.ft 1:3:6 (1") Concrete 213.53 1,334.56
25 S.ft 1:3 Rendering 17.16 429.00
Per 10 L,ft 4,627.64

Analysis 1st half - Mullaitivu


Page 61

Say per L.ft 463.00


Say per L.m 1,518.00

BLOCK MASONRY
1 Cement sand block in 1:6 mix in cement
sand 1:5 mix

Per Cube

Casting of blocks
12 Cwt 46 Cement 520.00 6,240.00
1 Cube 197 Sand fine 2100.00 2,100.00
3 Day 214 Mason 475.00 1,425.00

Analysis 1st half - Mullaitivu


Page 62

6 Day 257 Labourer 325.00 1,950.00


411 Allow for water for curing & mould 250.00 250.00

1.5 Cwt 46 Cement 520.00 780.00


0.10 Cube 197 Sand 2100.00 210.00
2 Day 214 Mason 475.00 950.00
2 Day 257 Labourer 325.00 650.00
Allow for scaffolding 32.50 14,587.50
Overheads 2,042.25
Per cube 16,629.75
Say per Cube 16,630.00
Per m3 5,876.33
Say per m3 5,876.00

2 4" thick cement sand block 1:6 mix masonry


in cement sand 1:5 mix

Per Sqr
Casting of blocks
3 Cwt 46 Cement 520.00 1,560.00
0.333 Cube 197 Sand 2100.00 699.30
1 Day 214 Mason 475.00 475.00
2 Day 257 Labourer 325.00 650.00
410 Allow for water for curing & mould 125.00 125.00
Masonry
1 Cwt 46 Cement 520.00 520.00
0.07 Cube 197 Sand 2100.00 147.00
1 Day 214 Mason 475.00 475.00
2 Day 257 Labourer 325.00 650.00
Allow for scaffolding 32.50 5,333.80
Overheads 746.73
Per sqr 6,080.53
Say per sqr 6,081.00
Per m2 654.52
Say per m2 655.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU


BRICKLAYER
No Qty Unit Description Unit Rate Rate Amount
2/30 Brick work in cement Mortar (1:5) above
1 cube (up to 1st floor level).

Per Cube.

1450 No 41 Bricks 5.70 8,265.00


Add 10% wastage 826.50

Analysis 1st half - Mullaitivu


Page 63

23 Cu.ft 197 Sand 2100.00 483.00


3.7 Cwts 46 Cement 520.00 1,924.00
410 Allow for water 125.00 125.00
3 Day 214 Mason 475.00 1,425.00
5 Day 257 Labourer 325.00 1,625.00
Allow for scaffolding 5% of Labour 81.25 14,754.75
Over heads 2,065.67
per cube 16,820.42
Say per cube 16,820.00
Per m3 5,943.46
Say per m3 5,943.00

3/30 Brick work in cement mortar (1:5) up to


1 cube (up to 1st floor level).

Per Cube.

As in Item 2 14,754.75 14,754.75


3/4 Day 214 Mason 475.00 356.25
1 1/4 Day 257 Labourer 325.00 406.25 15,517.25
Over heads 2,172.42
Per cube 17,689.67
Say per cube 17,690.00
Per m3 6,250.88
Say per m3 6,251.00

4/31 Brick work in cement mortar 1:5 in piers


(in ground floor).

Per Cube.
As in Item 2 14,754.75 14,754.75
1 1/2 Day 214 Mason 475.00 712.50
2 1/2 Day 257 Labourer 325.00 812.50 16,279.75
Over heads 2,279.17
Per cube 18,558.92
Say per Cube 18,559.00
Per m3 6,557.95
Say per m3 6,558.00

No Qty Unit Description Unit Rate Rate Amount


6/31 Brick work 4 1/2" thick in cement mortar
1:5 above 1 Square

Per Sqrs.

550 No 41 Bricks 5.70 3,135.00


Add 10% wastage 313.50
9 C.ft 197 Sand 2100.00 189.00
1.3 Cwt 46 Cement 520.00 676.00
412 Allow for water 75.00 75.00

Analysis 1st half - Mullaitivu


Page 64

1 1/2 Day 214 Mason 475.00 712.50


2 Day 257 Labourer 325.00 650.00
Allow for scaffolding 32.50 32.50 5,783.50
Over heads 809.69
Per square 6,593.19
Say per sqrs 6,593.00
Per m2 709.69
Say per m2 710.00

7/32 Brick work 4 1/2" thick in cement 1:5 up


to 1 square.

Per Sqrs.

As in Item 6 5,783.50 5,783.50


3/8 Day 214 Mason 475.00 178.13
1/2 Day 257 Labourer 325.00 162.50 6,124.13
Over heads 857.38
Per square 6,981.50
Say per Sqrs 6,982.00
Per m2 751.56
Say per m2 752.00

12/33 Extra over Item 2 for brick


work from 1st floor level up 2nd floor.
Per Cube.
1 1/2 Day 257 Labourer 325.00 487.50
Add for scaffolding 24.38 24.38 511.88
Over heads 71.66
Per cube 583.54
Say per cube 584.00
Per m3 206.36
Say per m3 206.00

14/34 Extra over Items 6-8 for brickwork from


1st floor level to 2nd floor.
Per Sqrs.

1/2 Day 257 Labourer 325.00 162.50


Add for scaffolding 8.13 8.13 170.63
Over heads 23.89
Per square 194.51
Say per Sqrs 195.00
Per m2 20.99
ay per m2 21.00

No Qty Unit Code Description Unit Rate Rate Amount


19/35 Coping, brick in cement 1:5, weathered
and threated on 4 1/2" walls, cement
rendered 1/2", 1:3 complete.

Per 100.0 L.ft.


400 No 41 Bricks 5.70 2,280.00
0.23 Cube 200 Sand 2100.00 483.00
5.1 Cwts 46 Cement 520.00 2,652.00
6 Day 214 Mason 475.00 2,850.00
6 Day 257 Labourer 325.00 1,950.00

Analysis 1st half - Mullaitivu


Page 65

412 Allow for water 75.00 75.00 10,290.00


Over heads 1,440.60
Per 100 L.ft 11,730.60
Per L.ft 117.31
Say per L.ft. 117.00
Per L.m. 383.76
Say per L.m 384.00

20/35 Coping, brick in cement 1:5, weathered


threated, on 9" walls and 1/2" cement
rendered 1:3 complete.

Per 10.0 L.ft.


67 No 41 Bricks 5.70 381.90
3.3 Cu.ft 200 Sand 2100.00 69.30
0.72 Cwts 46 Cement 520.00 374.40
3/4 Day 214 Mason 475.00 356.25
Allow for water 12.19
3/4 Day 257 Labourer 325.00 243.75 1,437.79
Over heads 201.29
Per 10 L.ft 1,639.08
Per L.ft 163.91
Say per L.ft. 164.00
Per L.m. 537.92
Say per L.m. 538.00

24/37 Door or Window inserted in existing walls


including making, opening and making
good to floor and walls (Lintol or Arch,
and door or window paid seperately).

Per No.
1/2 Day 257
2 Labourer 325.00 325.00
190 No 41Bricks 5.70 1,083.00
3 C.ft 200
Sand 2100.00 63.00
0.52 Cwts 46Cement 520.00 270.40
1 Day 214
Mason 475.00 475.00
1 Day 257
Labourer 325.00 325.00
0.75 Cwts 46Cement( for rendering) 520.00 390.00
5 Cu.ft 200
Sand 2100.00 105.00
1/2 Day 214
Mason 475.00 237.50
allow for water 16.25
1 Day 257 Labourer 325.00 325.00 3,615.15
Over heads 506.12
Per No 4,121.27
Say per No 4,121.00
No Qty Unit Code Description Unit Rate Rate Amount
25/37 Drains, brick incement 1:5,9" average
depth 12" wide, and cement rendered
1/2" thick 1:2 complete with expansion
joints as necessary excavation (apron
paid for seperately).

Per 10.0 L.ft.


1/4 Day 257 Labourer (for excavation) 325.00 81.25
200 No 41 Bricks ( for building drain) 5.70 1,140.00
1 Cwt 46 Cement 520.00 520.00

Analysis 1st half - Mullaitivu


Page 66

6 Cu.ft 200 Sand 2100.00 126.00


1 1/4 Day 214 Mason 475.00 593.75
Allow for water 5% of labour 20.31
1 1/4 Day 257 Labourer 325.00 406.25 2,887.56
Over heads 404.26
Per 10 L.ft 3,291.82
Per L.ft 329.18
Say per L.ft. 329.00
Per L.m 1,079.12
Say per L.m 1,079.00

26/38 Drains, brick in cement 1:5 6"-9" average


depth and 9" wide, cement rendered 1/2"
1:2 complete with expansion (apron paid
for seperately).

Per 10.0 L.ft.


1/4 Day 257 Labourer(for excavation) 325.00 81.25
100 Nos 41 Bricks(For Building drain) 5.70 570.00
4 Cu.ft 200 Sand 2100.00 84.00
0.68 Cwts 46 Cement 520.00 353.60
1 Day 214 Mason 475.00 475.00
414 Allow for water 16.25
1 Day 257 Labourer 325.00 325.00 1,905.10
Over heads 266.71
Per 10 L.ft 2,171.81
Per L.ft 217.18
Say per L.ft. 217.00
Per L.m. 711.76
Say per L.m. 712.00

No Qty Unit Code Description Unit Rate Rate Amount


28/38 Steps, 12" wide and 6" to 9" high
masonary or brick work in cement mortar
1:3 rendered 1/2" cement 1:2 with
foundation 6" below ground.

Per 10.0 L.ft.

120 No 41 Bricks 5.70 684.00


0.6 Cwt 46 Cement 520.00 312.00
4 Cu.ft 200 Sand 2100.00 84.00

Analysis 1st half - Mullaitivu


Page 67

1/2 Day 214 Mason 475.00 237.50


Allow for water 5% of labour 8.13
1/2 Day 257 Labourer 325.00 162.50 1,488.13
Over heads 208.34
Per 10 L.ft 1,696.46
Per L.ft 169.65
Say per L.ft 170.00
Per L.m. 557.60
Say per L.m. 558.00

30/39 Brick work in cement sand 1:8 in


foundation and up to D.P.C.

Per Cube.
1450 No41 Bricks 5.70 8,265.00
Add 10% for breakage 826.50
2 1/3 Cwt 46 Cement 520.00 1,213.33
0.375 Cube 197 Sand 2100.00 787.50
3 Day 214 Mason 475.00 1,425.00
4 Day 257 Labourer 325.00 1,300.00
410 Allow for water 125.00 125.00 13,942.33
Over heads 1,951.93
Per cube 15,894.26
Say per cube 15,894.00
Per m3 5,616.25
Say per m3 5,616.00

31/40 Brick work in cement sand 1:8 in


superstructure in ground floor.

Per Cube.
1450 No 41 Bricks 5.70 8,265.00
Add 10% for breakage 826.50
2 1/3 Cwt 46 Cement 520.00 1,213.33
3/8 Cube 197 Sand 2100.00 787.50
3 Day 214 Mason 475.00 1,425.00
5 Day 257 Labourer 325.00 1,625.00
410 Allow for water 125.00 125.00
Allow for scaffolding 5% of labour 81.25 81.25 14,348.58
Over heads 2,008.80
Per cube 16,357.39
Say per cube 16,357.00
Per m3 5,779.86
Say per m3 5,780.00

No Qty Unit Description Rate Amount


32/40 Brick work in cement and sand 1:8
in 1st floor.

Per Cube.
As per Item 31 Per cube 14,348.58 14,348.58
1 1/2 Day 257 Labourer 325.00 487.50

Allow for extra scaffolding and water 5% of labour 24.38 24.38 14,860.46
Over heads 2,080.46
Per cube 16,940.92

Analysis 1st half - Mullaitivu


Page 68

Say per cube 16,941.00


Per m3 5,986.22
Say per m3 5,986.00

33/40 Brick work in cement and sand 1:8 in


2nd floor.

Per Cube.
As per Item No. 31 14,348.58 14,348.58
4 1/2 Day 257 Labourer 325.00 1,462.50
Allow for extra scaffolding 5% of labour 73.13 73.13 15,884.21
Over heads 2,223.79
Per cube 18,108.00
Say per cube 18,108.00
Per m3 6,398.59
Say per m3 6,399.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU


MASON.
No Qty Unit Description Rate Amount

1/41 Random Rubble Masonary in cement


Mortar 1:5 above 1 cube.

Per Cube.

1 Cube 139 Rubble 5715.00 5,715.00

Analysis 1st half - Mullaitivu


Page 69

0.45 Cube 197 Sand 2100.00 945.00


7.25 Cwts 46 Cement 520.00 3,770.00
3 Day 214 Mason 475.00 1,425.00
412 Allow for water 75.00 75.00
6 Day 257 Labourer 325.00 1,950.00 13,880.00
Over heads 1,943.20
Per cube 15,823.20
Say per cube 15,823.00
Per m3 5,591.17
Say per m3 5,591.00

2/41 Randam rubble masonary in cement


mortar 1:5 up to 1 cube.

Per Cube.

As in item 1 13,880.00 13,880.00


Add 25% on labour. 487.50 14,367.50
Over heads 2,011.45
Per Cube 16,378.95
Say per cube 16,379.00
Per m3 5,787.63
Say per m3 5,788.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU


PAVIOR.
No Qty Unit Description Rate Amount

1/43 Exapansion joints in brick floors, filled


with bitumen and sand.

Per 20.0 L.ft.

1 Hour 214 Mason 475.00 59.38

Analysis 1st half - Mullaitivu


Page 70

1 Hour 257 Labourer 325.00 40.63


Allow for sand and bitumen 50% of labour 20.31 120.31
Over heads 16.84
Per 20 L.ft 137.16
Per L.ft 6.86
Say per L.ft. 7.00
Per L.m. 22.96
Say per L.m. 23.00

2/43 Exapansion joints in concrete floors


filled with bitumen and sand (to full depth
of concrete and rendering).
Per 20.0 L.ft.
2 Hour 214 Mason 475.00 118.75
2 Hour 257 Labourer 325.00 81.25
1/4 Cu.ft 200 Sand 2100.00 5.25
1/4 Gallon 32 Bitumen 347.00 86.75 292.00
Over heads 40.88
Per 20 L.ft 332.88
Per L.ft 16.64
Say per L.ft. 17.00
Per L.m. 55.76
Say Per L.m. 56.00
5/44 Floors ,cement concrete 1:21/2:5 (1") 3"
thick cement rendered 1/2", 1:2, with
expansion joints filled with cement and
sand.
Per Sqrs.
0.25 Cube 136 1" Metal 8470.00 2,117.50
0.18 Cube 197 Sand 2100.00 378.00
5 Cwts 46 Cement 520.00 2,600.00
1 1/4 Day 214 Mason 475.00 593.75
412 Allow for water 75.00 75.00
3 1/2 Day 257 Labourer 325.00 1,137.50 6,901.75
Over heads 966.25
Per square 7,868.00
Say per Sqrs 7,868.00
Per m2 846.93
Say per m2 847.00

No Qty Unit Code Description Unit Rate Rate Amount


12/46 Tiles glazed(colour)6"x6", with all
specials, supplied and fixed to walls
including raking plaster and bedding
in cement mortar 1:2.
Per 100 Sq.ft.
400 no 236a Tiles 6"x6" colour 15.00 6,000.00
Add 25% for specials wastage in cutting etc. 1,500.00
2 1/2 Cwts 46 Cement 520.00 1,300.00
0.11 Cube 200 Sand 2100.00 231.00
1 Day 215 Special mason 475.00 475.00

Analysis 1st half - Mullaitivu


Page 71

2 Day 214 Mason 475.00 950.00


2 Day 257 Labourer 325.00 650.00
415 Allow for white cement for painting 100.00 100.00 11,206.00
Over heads 1,568.84
Per 100 S.ft 12,774.84
Per S.ft 127.75
Say per Sq.ft 128.00
per m2: 1,377.83
Say per m2: 1,378.00

12d/46 Tiles 8"x8", pressed of approved pattern and


colour, supplied and fixed.
Per 100.0 S.ft.
240 Nos 189 floor tiles (8"x8") (including wastage) 32.00 7,680.00
1 1/4 Cwts 46 Cement 520.00 650.00
7 Cu.ft 200 Sand 2100.00 147.00
1 Day 215 Special mason 475.00 475.00
2 Day 214 Mason 475.00 950.00
3 Day 257 Labourer 325.00 975.00
415 Allow for coloured cement 100.00 100.00
414 Allow for clearing 25.00 25.00 11,002.00
Over heads 1,540.28
Per 100 S.ft 12,542.28
Per S.ft 125.42
Say per S.ft. 125.00
Say per m2 1,350.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU


PLASTERER.
No Qty Unit Description Unit Rate Rate Amount

4/139 Cracks in wall, plastered in cement 1:3


after chipping 2" to 4" wide

Per 10 L.ft

0.5 hour 214 Mason 475.00 29.69

Analysis 1st half - Mullaitivu


Page 72

1 hour 257 Labourer 325.00 40.63


0.04 cwt 46 Cement 520.00 20.80
Allow for sand 10.16 101.27
Overheads 14.18
Per 10 L.ft 115.45
Per 1 L.ft 11.54
Say per L.ft 12.00
Per L.m 39.36
Say per L.m 39.00

9/141 Flashing or plaster bands laid over tiles


4" to 6" wide on roof in cement and lime
mortar 1:1:4
Per 20 Lft

1 Cft 200 Sand 2100.00 21.00


0.16 Cwt 46 Cement 520.00 83.20
1/6 Bushel 126 Lime 257.00 42.83
1.5 Hrs 214 Mason 475.00 89.06
3 Hrs 257 Labourer 325.00 121.88 357.97
Overheads 50.12
Per 20 Lft 408.09
Per Lft 20.00
Per Lm 65.60
Say Per Lm 66.00

14/142 Rendering cement 1/2", 1:2 above 1


Square.

Per Sqrs.

1.5 Cwts 46 Cement 520.00 780.00


5 Cu.ft 200 Sand 2100.00 105.00
3/4 Day 214 Mason 475.00 356.25
1 1/2 Day 257 Labourer 325.00 487.50 1,728.75
Over heads 242.03
Per square 1,970.78
Say per sqrs. 1,971.00
Per m2 212.16
Say per m2 212.00

No Qty Unit Code Description Unit Rate Rate Amount


15/142 Rendering cement 1/2", 1:2 upto 1 square

Per Square

As in Item 14 1,728.75
Add 25% on labour 121.88 1,850.63
Overheads 259.09
Per square 2,109.71
Say per square 2,110.00
Per m2 227.13

Analysis 1st half - Mullaitivu


Page 73

Say per m2 227.00

16/143 Rendering cement 1/2", 1:3 above 1


Square.

Per Sqrs.

1.07 Cwts 46 Cement 520.00 556.40


5 Cu.ft 200 Sand 2100.00 105.00
3/4 Day 214 Mason 475.00 356.25
1 1/2 Day 257 Labourer 325.00 487.50 1,505.15
Over heads 210.72
Per square 1,715.87
Say per sqrs. 1,716.00
Per m2 184.71
Say per m2 185.00

17/143 Rendering cement 1/2", 1:3 upto 1 Square

Per Square

As in Item 16 1,505.15
Add 25% on labour 121.88 1,627.03
Overheads 227.78
Per square 1,854.81
Say per square 1,855.00
Per m2 199.66
Say per m2 200.00

18/143 Rendering, cement 3/4", 1:2 above 1


Square.

Per Sqrs.

2.25 Cwts 46 Cement 520.00 1,170.00


7 1/4 Cu.ft 200 Sand 2100.00 152.25
1 Day 214 Mason 475.00 475.00
2 Day 257 Labourer 325.00 650.00 2,447.25
Over heads 342.62
Per Square 2,789.87
Say per sqrs 2,790.00
Per m2 300.32
Say per m2 300.00

No Qty Unit Code Description Unit Rate Rate Amount


19/143 Rendering, cement 3/4", 1:2 upto 1 square

Per square

As in Item 18 2,447.25
Add 25% on labour 162.50 2,609.75
Overheads 365.37
Per sqr 2,975.12
Say per sqr 2,975.00
Per m2 320.24

Analysis 1st half - Mullaitivu


Page 74

Say per m2 320.00

20/144 Rendering, cement 3/4", 1:3 above 1


Square.

Per Sqrs.

1.75 Cwts 46 Cement 520.00 910.00


7 1/4 Cu.ft 200 Sand 2100.00 152.25
1 Day 214 Mason 475.00 475.00
2 Day 257 Labourer 325.00 650.00 2,187.25
Over heads 306.22
Per square 2,493.47
Say per Sqrs. 2,493.00
Per m2 268.35
Say per m2 268.00

21/144 Rendering, cement 3/4", 1:3 upto 1 square

Per Sqrs

As in Item 20 2,187.25
Add 25% on labour 162.50 2,349.75
Overheads 328.97
Per sqr 2,678.72
Say per sqr 2,679.00
Per m2 288.34
Say per m2 288.00

22/144 Rendering, cement, floating coat, using


Red cement finished smooth.

Per Sqrs.

0.14 cwt 46 Grey cement 520.00 72.80


1 Kg 192 Red cement 342.00 342.00
1 Hour 214 Mason 475.00 59.38
1 Hour 257 Labourer 325.00 40.63 514.80
Over heads 72.07
Per Square 586.87
Say per sqrs. 587.00
Per m2 63.19
Say per m2 63.00

No Qty Unit Code Description Unit Rate Rate Amount


25/145 Rendering cement 3/4", 1:2 with Pudlo 5lbs
to 100 lbs cement

Per sqr

As in Item 18 2,447.25
12 lbs 191 Pudlo 32 384.00 2,831.25
Overheads 396.38
Per sqr 3,227.63
Say per sqr 3,228.00

Analysis 1st half - Mullaitivu


Page 75

Per m2 347.43
Say per m2 347.00

26/145 Skirting in cement mortar 1:3, 1/2"x4"


projected or flush with wall, and
including forming groove.with red
cement floating
Per 10.0 L.ft.

0.22 Cu.ft 200 Sand 2100.00 4.62


0.07 Cwts 46 Cement 520.00 36.40
2 Hour 214 Mason 475.00 118.75
2 Hour 257 Labourer 325.00 81.25
add red cement floating as 22/144( x 0.042) 21.62 262.64
Over heads 36.77
Per 10 L.ft 299.41
Per L.ft 29.94
Say per L.ft. 30.00
Per L.m. 98.40
Say per L.m. 98.00

27/145 Skirting in cement mortar 1:3, 1/2"x6"


projected or flush with all finished with
Red cement floating, including forming
groove.

Per 10.0 L.ft.

As in Item 26 x 3/2 393.96 393.96


0.06 Kg 192 Red cement 342 20.52
1/2 hrs 214 Mason 475 29.69 444.17
Over heads 62.18
Per 10 L.ft 506.35
Per L.ft 50.64
Say per L.ft. 51.00
Per L.m. 167.28
Say per L.m. 167.00

No Qty Unit Code Description Unit Rate Rate Amount


28/146 3/8" thick plastering to RCC beams, slab
soffit in cement sand 1:3 .with limeputty

Per sqr
0.8 Cwt 46 Cement 520 416.00
0.05 Cube 200 Sand 2100 105.00
0.40 Bushel 126 Lime 257 102.80
2.0 Day 214 Mason 475 950.00
2.0 Day 257 Labourer 325 650.00
Allow for Scaffolding 32.50

Analysis 1st half - Mullaitivu


Page 76

414 Allow for water 25 25.00 2,281.30


Overheads 319.38
Per sqr 2,600.68
Say per sqr 2,601.00
Per m2 279.98
Say m2 280.00

29/146 D.P.C. 3/4" thick in cement, sand 1:2


finished smooth with 2 coats of hot tar.

Per Sqrs.
2.25 Cwts 46 Cement 520 1,170.00
11 Cu.ft 200 Sand 2100 231.00
1 1/4 Day 214 Mason 475 593.75
1 Gal 32 bitumen 347 347.00
2 1/2 Day 257 Labourer 325 812.50
412 Allow for fire wood and water 75 75.00 3,229.25
Over heads 452.10
Per square 3,681.35
Say per sqrs. 3,681.00
Per m2 396.23
Say per m2 396.00

29a/146 3/8" thick cement and sand plastering to


column and beam and soffit
Per sqr
0.8 Cwt 46 Cement 520 416.00
0.05 Cube 200 Sand 2100 105.00
1.75 Day 214 Mason 475 831.25
2 Day 257 Labourer 325 650.00
Allow for scaffolding 32.50
414 Allow for water 25 25.00 2,059.75
Overheads 288.37
Per sqr 2,348.12
Say per sqr 2,348.00
per m2 252.76
Say per m2 253.00

No Qty Unit Code Description Unit Rate Rate Amount


29b/146 1/2" thick cement plastering 1:4 mix

Per Sqr
0.90 Cwt 46 Cement 520 468.00
5.0 C.ft 200 Sand 2100 105.00
0.75 Day 214 Mason 475 356.25
1.50 Day 257 Labourer 325 487.50 1,416.75
Overheads 198.35
Per sqr 1,615.10
Say per sqr 1,615.00
per m2 173.85

Analysis 1st half - Mullaitivu


Page 77

Say per m2 174.00

29c/146 5/8" thick cement plastering 1:4 mix

Per Sqr

0.93 Cwt 46 Cement 520 483.60


0.07 Cube 200 Sand 2100 147.00
0.75 Day 214 Mason 475 356.25
1.50 Day 257 Labourer 325 487.50 1,474.35
Overheads 206.41
Per sqr 1,680.76
Say per sqr 1,681.00
Per m2 180.92
Say per m2 181.00

29d/146 Cracks in wall Plastered in cement 1:3


after chipping 2" to 4" wide

Per 10 Lft
0.04 Cwt 46 Cement 520 20.80
0.5 Hrs 214 Mason 475 29.69
1.0 Hrs 257 Labourer 325 40.63
1.0 Cft 200 Allow for sand 2100 21.00 112.11
Overheads 15.70
Per 10 Lft 127.81
Per Lft 12.78
Say per Lft 13.00
Per Lm 41.92
Say per Lm 42.00

29e/146 Plinth plastering 1/2" thick 1:3 cement and


sand with red cement floating
per Sqr

1.07 Cwt 46 Cement 520 556.40


5 C.ft 200 Sand 2100 105.00
0.75 Day 214 Mason 475 356.25
1.5 Day 257 Labourer 325 487.50
Red cement floating as item 22 514.80 2,019.95
Overheads 282.79
Per sqr 2,302.74
Say Rs 2,303.00
Per m2 247.87
Say Rs 248.00
RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU
ROOFER.
No Qty Unit Description Unit Rate Rate Amount

5/49 Corrugated asbestos sheet roofing on


special upper cl. Timber / kempus purlines
supplied and fixed complete including
treating timber with wood preservative
two coats (ridging measured seperately).

Per 3.60 Sqrs.

Analysis 1st half - Mullaitivu


Page 78

420 S.ft 15 Asbestos sheet 29 12,180.00


13 1/4 Cu.ft 246 Timber in purlins 1250 16,562.50
72 Nos 198 Roofing screws and washers 6 432.00
1 1/4 Day 214 Carpenter(Fixing Purlins) 475 593.75
1 1/4 Day 257 Labourer 325 406.25
415 Allow for spikes for purlins 100 100.00
3 Hour 257 Labourer(2) (hosting sheet) 325 243.75
2 Days 214 Carpenter (fixing sheet) 475 950.00
2 Days 257 Labourer 325 650.00
1/2 Gal 268a Wood preservative 315 157.50
3/4 Day 257 Labourer 325 243.75 32,519.50
Over heads 4,552.73
Per 3.6 Sqrs. 37,072.23
Per Sqrs. 10,297.84
Say per sqrs. 10,298.00
Per m2 1,108.50
Say per m2 1,109.00

7/50 Corrugated asbestos sheet fixed to roof


or wall on existing frame work with
necessary coach screws and limpet
washers, or hook bolts.& with 2 coats wood
Preservative to existing frame work
Per 3.60 Sqrs.
420 Sq.ft 15 Asbestoes sheets. 29 12,180.00
72 Nos. 198 Drive screws 4 1/2"&washers 6 432.00
6 Hour 257 Labourers. 325 243.75
2 Days 214 Carpenter 475 950.00
2 Days 257 Labourers. 325 650.00
0.5 gal 268a Wood preservative 315 157.50
0.75 Days 257 Labourers. 325 243.75 14,857.00
Overheads 2,079.98
Per 3.6 Sqrs. 16,936.98
Per Sqrs. 4,704.72
Say per sqrs. 4,705.00
Per m2 506.46
Say per m2 506.00

No Qty Unit Description Unit Rate Rate Amount


18/53 Ridging, calicut pattern bedded in
Cement and lime mortar 1:1:4, Coloured
to match tiles.
Per 12.0 L.ft.
9 No 194 Ridge tiles 35 315.00
2 Cu.ft 200 Sand 2100 42.00
1/3 Bushel 126 Lime 257 85.67
1/3 Cwt. 46 Cement 520 173.33
1/4 Day 214 Mason 475 118.75
1/4 Day 257 Labourer 325 81.25
Allow for colouring powder 10 10.00 826.00

Analysis 1st half - Mullaitivu


Page 79

Over Heads 115.64


Per 12 L.ft. 941.64
Per L.ft 78.47
Say per L.ft. 78.00
Per L.m. 255.84
Say per L.m 256.00

19/53 Ridging, Calicut Pattern bedded in


cement and lime mortar 1:1:4 coloured
to match tiles (tiles available at site)
Per 12.0 L.ft.
As in item 18 826.00 826.00
Less tiles 315.00 511.00
Over heads 71.54
Per 12 L.ft. 582.54
Per L.ft. 48.55
Say per L.ft. 49.00
Per L.m. 160.72
Say per L.m. 161.00

21/54 Ridging with asbestos cement close


fitting ridges fixed complete with
roofing screws or hook bolts.

Per 13'-4" L.FT


4 pairs 14 Asbestos ridging 363 1,452.00
16 Nos 198 Roofing screws 4 1/2" 6 96.00
2 Hour 214 Carpenter 475 118.75
2 Hour 257 Labourers 325 81.25 1,748.00
Over heads 244.72
Per 13' 4" L.ft 1,992.72
Per L..ft. 149.49
Say per L.ft 149.00
Per L.m. 488.72
Say per L.m. 489.00
26/55 Tiles, calicut pattern, flat supplied and
laid up to 5 tiles in single storey building
Per 3 tiles.

3 Nos 70 Tiles. 18 54.00


1/2 Hour 257 Labourer 325 20.31 74.31
Over heads 10.40
Per 3 tiles 84.72
Per tiles 28.24
Say per tiles 28.00
No Qty Unit Description Unit Rate Rate Amount
27/56 Tiles, calicut pattern flat supplied and
laid (above 5 and up to 25) in single
storey Building.

Per 15.0 tiles.

15 Nos 70 Tiles. 18 270.00


1 Hour 257 Labourer 325 40.63 310.63
Over Heads 43.49
Per 15 tiles 354.11
Per tiles 23.61

Analysis 1st half - Mullaitivu


Page 80

Say per tile 24.00

30/56 Tiles calicut pattern supplied and laid


in any Building.

Per Sqrs.

125 Nos. 70 Tiles. 18 2,250.00


1/4 Day 257 Labourers (02) 325 162.50 2,412.50
Over heads 337.75
Per Square 2,750.25
Say per sqrs. 2,750.00
Say per m2 296.00

31/56 Tiles, calicut pattern, laid in any


Buildings(tiles available at site).
Per Sqrs.
1/4 Day 257 Labourer (02) 325 162.50 162.50
Overheads 22.75
Per Sqrs. 185.25
Say per sqrs. 185.00
Per m2 19.91
Say per m2 20.00

43/59 Shifting and re-laying calicut pattern


tiles.
Per Sqrs.
1 Day 257 Labourer 325 325.00 325.00
Over heads 45.50
Per Sqrs. 370.50
Say per Sqrs. 370.00
Per m2 39.83
Say per m2 40.00

44/59 Supplying and laying half round tiles


on the existing asbestos roof.
Per Sqrs.
320 Nos. 91 Half round tiles. 6.5 2,080.00
3/8 Day 257 Labourers (02) 325 243.75 2,323.75
Overheads 325.33
Per Sqrs. 2,649.08
Say per sqrs. 2,649.00
Per m2 285.15
Say per m2 285.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU


CARPENTER AND JOINER.

No Qty Unit Description Unit Rate Rate Amount

8/63 Boards, Barge, Valance, Fascia, 3/4" to


1" thick in class.I Local timber fixed
complete with necessary Brass screws new or
renewed above 1 C.ft.( 9" width) with 1 coat
primer & 2 coat of enamel painting

Analysis 1st half - Mullaitivu


Page 81

Per 100.0 L.ft.


82.5 Sq.ft 35 3/4" planks 50 4,125.00
4 Doz 207b Brass screws 2" 69.00 276.00
Scaffolding 8.13
2 Day 214 Carpenter 475 950.00
1/2 Day 257 Labourer 325 162.50
1 1/2 sqrs painting as per item 25/168 1,854.25 2,781.38 8,303.00
Overheads 1,162.42
Per 100 L.ft. 9,465.42
Per L.ft. 94.65
Say Rs. 95.00
Per Lm 310.47
Say Rs. 310.00

12/64 Boardes, Barge, Valance, Facia,


available fixed including cutting and
minor repairs.with 2 coats enamel painting
per 100 l.ft (9"x1")
1/2 day 214 Carpenter 475 237.50
1/2 day 214 Carpenter 475 237.50
1/2 day 257 Labourer 325 162.50
4 Doz 207b Screws, 2" brass 69 276.00
1.5 sqrs painting as per item 24/168 1,241.28 1,861.91 2,775.41
Over heads 388.56
Per 75 Sq.ft or 100 l.ft 3,163.97
Per Sq.ft. 42.19
Say Rs. 42.00
Per m2 451.92
Say per m2 452.00

3/61A Beadings, Class I local timber 1 1/2" to


2"x1/2" plain chamfered, fixed with brass
screws

Per 100 L.ft


105 L.ft 354 Fillets 3.25 341.25
4 Doz 40a Screws 1 1/2" brass 52.5 210.00
0.5 Day 214 Carpenter 475 237.50
0.5 Day 257 Labourer 325 162.50 951.25
Overheads 133.18
Per 100 L.ft 1,084.43
Per L.ft 10.84
Say per L.ft 11.00
Per Lm 35.57
Say per Lm 36.00

No Qty Unit Description Unit Rate Rate Amount


14/65 Ceiling asbestos, flat fixed with clout
headed nails to 4"x2" joists at 4'crs & 2"x 2"
bearers at 2' crs of spl.upper class. Timber
/kempus including 1 1/2" x 1/2" cover fillets
and 2 1/2" x 1/2" coves of Halmills timber.
Rate to include 2 coats tarnap to joists
and bearers primer and '2 coats of enamel
painting to beadings 'and mouldingd 2 coats
of white washing to ceiling.
Making holes in wall and fixing joists and

Analysis 1st half - Mullaitivu


Page 82

bearers 'Per 1.95 Sqrs (15'-0"x13'-0").


4.2 Cu.ft 246 Timber.(4"x2") 1250.00 5,250.00
3.8 Cu.ft 245 Timber.(2"x2") 1250.00 4,750.00
1 Lb. 150 2" nails 34.00 34.00
1 1/2 Day 214 Carpenter 475.00 712.50
1 1/2 Day 257 Labourer 325.00 487.50
Fixing joists in wall and making good holes
2 Hour 214 Mason 475.00 118.75
2 Hour 257 Labourer 325.00 81.25
413 Allow for cement and sand. 50.00 50.00
Treating Timber with tarnap.
1/3 Gallon 268a Wood preservative. 315.00 105.00
1/2 Day 257 Labourer 325.00 162.50
Cutting and nailing sheets.
210 Sq.ft 13 Asbestos sheets 18.00 3,780.00
1/4 Lb. 153 G.I. nails 3/4" 34.00 8.50
1 Day 214 Carpenter 475.00 475.00
1 1/2 Day 257 Labourer 325.00 487.50
Fixing beading
125 L.ft 25 Beading 4.00 500.00
6 Doz 40a Screws 1 1/2" Brass 52.50 315.00
3/4 Day 214 Carpenter 475.00 356.25
3/4 Day 257 Labourer 325.00 243.75
Fixing cove mouldings
60 L.ft 147a Mouldings. 4.50 270.00
1/4 Day 214 Carpenter 475.00 118.75
1/4 Day 257 Labourer to assist 325.00 81.25
White Washing
0.25 bushel 216 Lime 270.00 67.50
1 Day 214 Painter 475.00 475.00
1 Day 257 Labourer 325.00 325.00
1/4 Gall. 65 Paint(Primer under coat and oil paint) 1785.00 446.25
1 3/4 Day 214 Painter 475.00 831.25
Allow for scaffolding 93.44 93.44
413 Allow for brushes. 50.00 50.00 20,675.94
Over heads 2,894.63
Per 1.95 Sqrs 23,570.57
Per Sqrs 12,087.47
Say Rs. 12,087.00
Say m2 1,299.68

No Qty Unit Description Unit Rate Rate Amount


14a/65 Ceiling asbestos, flat in eves fixed with clout
headed nails to 2" x 2"& 2"x1" spacer
bearers not exceading 2'-0 centrs both ways
bearers of spl.upper class/ kempus timber
including Aluminium beading 1" wide with
Rubber fillets fixed not exceedaing 2'-0" crs
bothways Rate to include 2 coats tarnap to
timber and 2 coats emulsion
paint to abestos sheet
65'-0"x3'-0" = 195 sq.ft

Analysis 1st half - Mullaitivu


Page 83

Per 1.95 Sqrs


6.50 Cu.ft 245 Timber.2"x2" 1250.00 8,125.00
72 L.ft 193 2"x1"reppers 8.00 576.00
1 Lb. 150 2" nails 34.00 34.00
2 Day 214 Carpenter 475.00 950.00
2 Day 257 Labourer 325.00 650.00
Fixing joists in wall and making good holes
2 Hour 214 Mason 475.00 118.75
2 Hour 257 Labourer 325.00 81.25
413 Allow for cement and sand. 50.00 50.00
Treating Timber with tarnap.
1/3 Gallon 268a Wood preservative. 315.00 105.00
1/2 Day 257 Labourer 325.00 162.50
Cutting and nailing sheets.
210 Sq.ft 13 Asbestos sheets 18.00 3,780.00
1/4 Lb. 153 G.I. nails 3/4" 34.00 8.50
1 Day 214 Carpenter 475.00 475.00
1 1/2 Day 257 Labourer 325.00 487.50
Fixing Aluminium rubber beading
300 L.ft 397 Beading Aluminium 12.80 3,840.00
6 Doz 40a Screws 3/4" 52.50 315.00
300 L.ft 408 Rubber Beading 3.00 900.00
2 Day 214 Carpenter 475.00 950.00
2 Day 257 Labourer 325.00 650.00
Emulsion Painting
0.67 Gallon 64 Emulsion Paint 1415.00 948.05
2 Day 214 Painter 475.00 950.00
Allow for scaffolding 101.56 101.56
Allow for brushes. 50.00 50.00 24,308.11
Over heads 3,403.14
Per 1.95 Sqrs 27,711.25
Per Sqrs 14,210.90
Say Rs. 14,211.00
Per m2 1,529.71
Say m2 1,530.00

No Qty Unit Description Unit Rate Rate Amount


14b/65 Ceiling asbestos, flat fixed with clout
headed nails to 4"x2" joists 4'-0 crs & 2"x2"
bearers of spl.upper class/kempus timber 2'-0" crs
and 2"x1" spacer bearers not exceding 2'-0crs
including Aluminium beading 1" wide with
rubber fillets not exceeding 2'-0 crs fixed bothways
Rate to include 2 coats tarnap to timber
and 2 coats emulsion paint
to abestos sheet

Analysis 1st half - Mullaitivu


Page 84

Per 1.95 Sqrs


4.2 Cu.ft 246 Timber. 4"x2" 1250.00 5,250.00
3.8 Cu.ft 245 Timber. 2"x2" 1250.00 4,750.00
1 Lb. 150 2" nails 34.00 34.00
60.0 L.ft 193 reepes 8.00 480.00
2 Day 214 Carpenter 475.00 950.00
2 Day 257 Labourer 325.00 650.00
Fixing joists in wall and making good holes
2 Hour 214 Mason 475.00 118.75
2 Hour 257 Labourer 325.00 81.25
413 Allow for cement and sand. 50.00 50.00
Treating Timber with tarnap.
1/3 Gallon 268a Wood preservative. 315.00 105.00
1/2 Day 257 Labourer 325.00 162.50
Cutting and nailing sheets.
210 Sq.ft 13 Asbestos sheets 18.00 3,780.00
1/4 Lb. 153 G.I. nails 3/4" 34.00 8.50
1 Day 214 Carpenter 475.00 475.00
1 1/2 Day 257 Labourer 325.00 487.50
Fixing Aluminium beading
260 L.ft 397 Beading Aluminium 12.80 3,328.00
6 Doz 40a Screws 3/4" 52.50 315.00
260 L.ft 408 Rubber Beading 3.00 780.00
2 Day 214 Carpenter 475.00 950.00
2 Day 257 Labourer 325.00 650.00
Emulsion Painting
0.67 gal 64 Emulsion Paint 1415 948.05
2 Day 214 Painter 475.00 950.00
Allow for scaffolding 101.56 101.56
415 Allow for brushes. 100.00 100.00 25,505.11
Over heads 3,570.72
Per 1.95 Sqrs 29,075.83
Per Sqrs 14,910.68
Say Rs. 14,911.00
Say m2 1,603.00

No Qty Unit Description Unit Rate Rate Amount


14c/65 As per Item No.14 with only 2"x2"beares
in eaves ceiling. -do- -do-
65'-0"x3'-0" = 195 sq.ft
Per 1.95 Sqrs.
As per Item No.14 20,675.94
Less for Timber 10,000.00
10,675.94
6 1/2 Cu.ft 245 Timber 2"x2" 1250 8,125.00 18,800.94
Less for Timber work
1/4 Day 214 Carpenter 475 118.75

Analysis 1st half - Mullaitivu


Page 85

1/4 Day 257 Labour 325 81.25 200.00


18,600.94
Over heads 2,604.13
Rate per Sqrs 21,205.07
Per 1.95 Sqrs. 21,205.00
Per Sqre 10,874.36
Say Per Sqr 10,874.00
say per M2 1,171.00

14d/65 White washing to ceiling 2 coats and


2 coats of oil paint to beading and
moulding.
Per 1.95 Sqrs
1/8 Day 214 Painter preparing surfaces 475 59.38
0.25 Bushel 216 Lime 270 67.50
1/8 Gall. 65 Oil paint 1785 223.13
413 Allow for sand paper 50 50.00
1 Day 257 Labourer 325 325.00
2 day 214 Painter 475 950.00
Allow for scafolding 16.25 16.25
413 Allow for brush 50 50.00 1,741.25
Over Heads 243.78
Per 1.95 Sqrs 1,985.03
Per Sqrs 1,017.96
Say Rs. 1,018.00
Per M2 109.46

14e/65 Ceiling, upper side cleaned and debris


cleared away.
1/4 Day 257 Labourer 325 81.25 81.25
Over heads 11.38
Per Square 92.63
Say Rs. 92.00
Per m2 10.00

No Qty Unit Description Unit Rate Rate Amount


26/68A Cove mouldings Cl.I 2 1/2"x1 1/2" fixed
with brass screws and plugs new or
renewed.
Per 50 L.ft
55 L.ft 147a Cove mouldings 4.5 247.50
20 nos 184 Wood plugs 2 40.00
1 1/2 Hour 214 Mason 475 89.06
3/4 Day 257 Labourer 325 243.75
1 1/2 Doz 207b Screws 2" 69 103.50 723.81
Over heads 101.33

Analysis 1st half - Mullaitivu


Page 86

Per 50 L.ft 825.15


Per L.ft 16.50
Say Rs 16.00
Say per L.m 54.00

28/69 Doors or Windows, ledged, braced and


battened with grooved and tongured
joint,3 3/4" x 2 3/4" frames in spl.upper
class timber/kempus & 3/4" to 7/8" thick
sashes in class1 timber
with brass fittings.
Per 2-6x6-6 = 16.25 Sft

1.5 Cu.ft 246 Timber for frames spl. Upper class 1250 1,875.00
21 S.ft 182 1" Planks (Ginnisappu) 50 1,050.00
3 Doz 40a Brass screw 1 1/2" 52.5 157.50
2 Nos 220 Spur. Stones 22.5 45.00
4 Nos 199 Rawl plugs and 2" screws 15 60.00
414 Allow for Dowels 25 25.00
3 Day 214 Carpenter 475 1,425.00
1.25 Day 257 Labourer 325 406.25
Fittings
3 no 119 T- hinges 10" 58 174.00
2 no 23 6" Barrel bolt 120 240.00
2 doz 40a 1 1/2" screws 52.5 105.00
0.5 doz 40d 1" screws 45 22.50
414 Allow sand paper 25 25.00 5,610.25
14% Over heads 785.44
Per 16.25 Sq.ft 6,395.69
Per Sq.ft 393.58
Say per S.ft 394.00
Per m2 4,234.30
Say per m2 4,234.00

No Qty Unit Description Unit Rate Rate Amount


30/70 - do - - do -
Sash only, in class 1 timber
fixed with brass furniture.

Per 14.4 Sft

21 Sq.ft 182 1" Planks(Ginnisappu) 50 1,050.00


3 Doz 40a Screws 1 1/2" 52.5 157.50
1/2 Doz 40d Screws 1" 45 22.50
2 1/4 Day 214 Carpenter 475 1,068.75

Analysis 1st half - Mullaitivu


Page 87

1 Day 257 Labourer 325 325.00


414 Allow for sand paper etc 25 25.00
3 Nos 119 T-hinges-10" 58 174.00
2 Nos 23 6" Barrel bolt 120 240.00
2 Doz 40a 11/2" screws 52.5 105.00
0.5 Doz 40d 1" screws 45 22.50 3,190.25
Over heads 446.64
Per 14.4 S.ft 3,636.89
Per S.ft 252.56
Say Rs 252.00
Say per m2 2,717.00

32/70 Doors or Windows, framed and battened,


sash 1" to 1 1/8" thick in Special
upper Class timber/kempus fixed complete
with brass furniture.
Per 16.25 sq.ft
1.5 Cu.ft 246 Timber 1250 1,875.00
8 S.ft 181 1 1/4" Planks 135 1,080.00
13 1/4 S.ft 182b 3/4" Planks 105 1,391.25
2 Doz 207a 1 1/4" brass screws 45 90.00
1/2 Doz 40d 1" Screws 45 22.50
414 Allow dowels 25 25.00
2.5 Day 214 Carpenter 475 1,187.50
1.25 Day 257 Labourer 325 406.25
2 Nos 220 Spur stone 22.5 45.00
4 Nos 199 Rawl plugs 15 60.00
1.5 pair 22 4"Brass hinges 79 118.50
1 Nos 196 6" rim lock 446 446.00
0.75 Day 214 Carpenter (frame) 475 356.25
0.375 Day 257 Labourer 325 121.88
414 Allow for sand paper etc. 25 25.00 7,250.13
Over heads 1,015.02
Per 16.25 S.ft 8,265.14
Per S.ft 508.62
Say Rs 509.00
Say per m2 5,472.00

No Qty Unit Description Unit Rate Rate Amount


32a/70 Battened sash only 1" to 11/8" thick in sp.
upper class timber/kempus fixed completed with
brass fittings

Per 14.4 sq.ft


8 sq.ft 181 11/4" planks 135 1,080.00
13.25 sq.ft 182b 3/4" planks 105 1,391.25
2 Doz 207a 11/4" brass screw 45 90.00
0.5 Doz 40d 1" brass screw 45 22.50
2.5 Day 214 Carpenters 475 1,187.50

Analysis 1st half - Mullaitivu


Page 88

1.25 Day 257 Labourers 325 406.25


1.5 Pair 22 4" brass hinges 79 118.50
1 No 196 6" Rim Lock 446 446.00
414 Allow for sand paper 25 25.00 4,767.00
Over head 667.38
Per 14.4 sq.ft 5,434.38
per 1sq.ft 377.39
say per sq.ft 377.00
per m2 4,060.69
Say per m2 4,061.00

42/74 Doors or windows,glazed & or pannelled with


3 3/4"x2 3/4" frames & 1 1/8" to 1 1/4"sashes
in special upper class local timber/kempus fixed

Per 28 S.ft (4'-0"x7'-0")


1.7 C.ft 246 Timber in frames 1250 2,125.00
18 S.ft 181 1 1/4"-1 1/2" Planks 135 2,430.00
7 S.ft 182b 3/4" Planks 105 735.00
14 L.ft 205 1 1/2"x1 1/2" Sash bars 19 266.00
45 L.ft 354 Fillets 3.25 146.25
10 S.ft 81 Glass panes 50 500.00
2 Nos 220 Spur. Stones 22.5 45.00
4 Nos 199 Rawl plugs and screws 15 60.00
413 Allow for Dowels 50 50.00
3/4 Day 214 Carpenter (frame) 475 356.25
3/8 Day 257 Labourer 325 121.88
6 Day 214 Carpenter (sash) 475 2,850.00
1.75 Day 257 Labourer 325 568.75 10,254.13
Fittings
3 pairs 94 4"x3" brass hinges 136 408.00
1 Nos 117 10" Skilton bolt 136 136.00
1 Nos 23 6" barrel bolt 120 120.00
1 Nos 142 concord 525 525.00
4 Doz 40a 11/2" Brass screws 52.5 210.00
2 Doz 40d 1" Brass screws 45 90.00
414 Allow for sand paper 25 25.00 1,514.00
11,768.13
Over heads 1,647.54
Per 28 S.ft 13,415.66
Per S.ft 479.13
Say Rs 479.00
Say per m2 5,155.00

No Qty Unit Description Unit Rate Rate Amount


44/75 Doors or Windows, glazed or
pannelled sash only 1 1/8" to 1 1/4" thick
in Special upper class timber/kempus with brass
furniture.
Per 24.7 Sq.ft (3'-7 1/2"x6'-9 3/4")
Timber and glass panes as in Item 42 4,077.25
Labourer as in Item 42 3,418.75
Fitting as in item 42 1,514.00 9,010.00
Over heads 1,261.40
Per 24.7 Sq.ft 10,271.40

Analysis 1st half - Mullaitivu


Page 89

Per Sq.ft 415.85


Say Rs 416.00
Say per m2 4,474.00

44a/75 Doors pannelled and terllised/B.R.C.


weld mesh No. 32 with 3 3/4"x2 3/4"
frames and 1 1/8" thick sashes in special
upper class timber/kempus, fixed complete with
brass furniture.
Per 21 S.ft
1.65 Cu.ft 246 Timber in frame 1250 2,062.50
11 S.ft 181 1 1/4" Planks 135 1,485.00
6 S.ft 182b 3/4" Planks 105 630.00
7 1/2 S.ft 409 Weldmesh 10 75.00
415 Allow for Dowels 100 100.00
2 Nos 220 Spur stones 22.5 45.00
3/4 day 214 Carpenter 475 356.25
3/4 day 257 Labour 325 243.75
3.187 day 214 Carpenter 475 1,513.83
FITTING
1.500 pair 95 4" Brass hinges 205 307.50
1.000 Nos 142 Mortice lock 525 525.00
2.000 Doz 40A 1 1/2" Brass screws 52.5 105.00
0.500 Doz 40D 1" Brass screws 45 22.50
414 Allow for sand paper 25 25.00
1 day 257 Labour 325 325.00 7,821.33
Over heads 1,094.99
Per 21 S.ft 8,916.31
Per S.ft 424.59
Say Rs 425.00
Say per m2 4,568.00

No Qty Unit Description Unit Rate Rate Amount


52/78 Doors pannelled with 3 3/4"x2 3/4" frames
and 1 - 1 1/8"sashes in Special upper
Class timber fixed/kempus.with brass fittings
Per 21.0sq.ft
1.65 C.ft 246 Timber 1250 2,062.50
14 S.ft 181 1 1/8" Planks 135 1,890.00
11 S.ft 182b 3/4" Planks 105 1,155.00
2 No 220 Spur Stones 22.5 45.00
4 No 199 Rawl plugs and screws 15 60.00
415 Allow for Dowels 100 100.00

Analysis 1st half - Mullaitivu


Page 90

3/4 Day 214 Carpenter 475 356.25


3/8 Day 257 Labourer 325 121.88
4 Day 214 Carpenter 475 1,900.00
1 1/4 Day 257 Labourer 325 406.25
fitting
1 1/2 pair 94 4"x3" Brass hinges 136 204.00
1 No 142 Mortice lock concord 525 525.00
2 Doz 40a 1 1/2" Brass screws 52.5 105.00
0.5 Doz 40d 1" - Do - 45 22.50
414 Allow for sand paper 25 25.00 8,978.38
Over heads 1,256.97
Per 21 S.ft 10,235.35
Per S.ft 487.40
Say Rs 487.00
Say per m2 5,244.00

53/78 Door or Window, removing easing and


re-fixing.

1 1/2 Hour 214 Carpenter 475 89.06


1 1/2 Hour 257 Labourer 325 60.94 150.00
Over heads 21.00
Per sash 171.00
Say Rs 171.00

54/78 Door or Window, easing only.

1 Hour 214 Carpenter 475 59.38 59.38


Over heads 8.31
Per sash 67.69
Say Rs 67.00

55/79 Door or Window frames renewed in


short lengths with special upper Class
timber/kempus.
Assume 3'-0" Length of frame renewed

0.45 Cu.ft 246 Timber 4" x 3" 1250 562.50


1/2 Day 214 Carpenter 475 237.50 800.00
Over heads 112.00
Per 3 l.ft 912.00
Per l.ft 304.00
Say Rs 304.00
Say per L.m 997.12

No Qty Unit Description Unit Rate Rate Amount


100/92 Reepers 2"x1" in Class I timber/kempus supplied
and fixed new or renewed with iron
nails, up to 100 L.ft (shiffting of tiles paid
for seperately).
Per 50 l.ft
55 L.ft 193 Reepers 8 440.00
1 Hour 214 Carpenter 475 59.38
1 Hour 257 Labourer 325 40.63
1/8 Lbs 150 Nails 2" 34 4.25 544.25
Over heads 76.20

Analysis 1st half - Mullaitivu


Page 91

Per 50 L.ft 620.45


Per L.ft 12.41
Say Rs 12.00
Say per L.m 41.00

101/92 - do - - do -
over 100 L.ft.
Per 100 L.ft
100 L.ft 193 Reepers 8 800.00
1 1/2 Hour 214 Carpenter 475 89.06
1 1/2 Hour 257 Labourer 325 60.94
1/4 Lbs 150 Nails 2" 34 8.50 958.50
Over heads 134.19
Per 100 L.ft 1,092.69
Per L.ft 10.93
Say Rs 11.00
Say per L.m 36.00

107/94 Roof with calicut pattern tiles on spl upper


class/Kempus frame work complete with ridges,
hips etc.

Per 6 sqrs

34 Cu.ft 246 Timber 1250 42,500.00


660 L.ft 193 Reepers sp . Upper class 8 5,280.00
750 No 70 Tiles 18 13,500.00
52 No 194 Ridge tiles 35 1,820.00
8 Lbs 267a 6" wire nails 36.5 292.00
2 Lbs 267a 2" wire nails 36.5 73.00
2 1/2 Gal 268a Wood preservative 315 787.50
3 Cwt 46 Cement 520 1,560.00
8 Cu.ft 200 Sand 2100 168.00
413 Allow for colouring powder etc 50 50.00
10 Day 214 Carpenter 475 4,750.00
4 Day 257 Labourer 325 1,300.00
3 Day 257 Labourer 325 975.00
3 Day 257 Labourer 325 975.00
1 1/2 Day 214 Mason 475 712.50
1 1/2 Day 257 Labourer 325 487.50 75,230.50
Over heads 10,532.27
Per 6 Sqrs 85,762.77
Per square 14,293.80
Say per sqr 14,294.00
Per m2 1,538.62
Say per m2 1,539.00
No Qty Unit Description Unit Rate Rate Amount
107a/94 gable end roof - do -
- do - - do -.
27 Cu.ft 246 Timber 1250 33,750.00
660 L.ft 193 2"x1" Reeper sp .upper class 8 5,280.00
750 Nos 70 Tile 18 13,500.00
35 Nos 194 Ridge tiles 35 1,225.00
7 Lbs 267a 6" Wire nails 36.5 255.50
2 Lbs 150 2" Nails 34 68.00
2 1/4 Gal 268a Wood preservative 315 708.75
1 Cwt 46 Cement 520 520.00

Analysis 1st half - Mullaitivu


Page 92

0.06 Cube 197 Sand 2100 126.00


413 Allow for colouring powder etcs 50 50.00
Labour frame work
9 Day 214 Carpenter 475 4,275.00
3 3/4 Day 257 Labourer 325 1,218.75
Treating work
2 3/4 Day 257 Labourer 325 893.75
Laying
3 Day 257 Labourer 325 975.00
Ridging
1 Day 214 Mason 475 475.00
1 Day 257 Labourer 325 325.00 63,645.75
Over heads 8,910.41
Per 6 Sqrs 72,556.16
Per sqrs 12,092.69
Say Rs 12,093.00
Say per m2 1,302.00

Timber available, sorted out, cut to


117/97 required sizes and fixed in roof and
other carpentry work.
Per 5/6 Cu.ft
3 Hour 214 Carpenter 475 178.13
1 Hour 257 Labourer 325 40.63
415 Allow for nails, spikes etc 100 100.00 318.75
Over heads 44.63
Per 5/6 Cu.ft 363.38
Per Cu.ft 436.05
Say Rs 436.00
Say per m3 15,387.00

Timber special upper Class fixed or


121/98 renewed in roof and other carpentry
work.
5/6 Cu.ft 246 Timber 1250 1,041.67
Labourer as in Item 117 318.75 318.75 1,360.42
Over heads 190.46
Per 5/6 Cu.ft 1,550.88
Per Cu.ft 1,861.05
Say Rs 1,861.00
Say per m3 65,672.00

No Qty Unit Description Unit Rate Rate Amount


Trellis partition with 1/2"x1/2" laths fixed
135/101 2" apart diagonally or horizontally and
vertically on 4"x2" Milla timber framing.
Per 24 S.ft (6'-0"x4'-0")
2 Cu.ft 246 4"x2" Timber 1250 2,500.00
310 L.ft 205 1/2"x1/2" Laths 19 5,890.00
20 L.ft 26 2"x1/2" Beading 4 80.00
1 Lb 150 1" Nails 34 34.00
414 Allow for 2" nails 25 25.00
4 Day 214 Carpenter 475 1,900.00

Analysis 1st half - Mullaitivu


Page 93

1/2 Day 257 Labourer 325 162.50


414 Allow for 4 plugs fixed to walls 25 25.00 10,616.50
Over heads 1,486.31
Per 24 S.ft 12,102.81
Per S.ft 504.28
Say Rs 504.00
Say per m2 5,425.00

Door frame 4"x3" in spl upper class timber/kempus


138/102 supplied and fixed in position

per'16.25 Sft

1.7 Cu.ft 246 Timber 1250 2,125.00


1 Day 214 Carpenter 475 475.00
1 Day 257 Labourer 325 325.00
1/2 day 214 Mason 475 237.50
1/8 Day 214 Labourer 475 59.38
412 Allow for cement sand 75 75.00
2 Nos 220 Spur stones 22.5 45.00
4 Nos 98 Rawl plug 17.5 70.00 3,411.88
Over heads 477.66
Per 16.25 S.ft 3,889.54
Per s.ft 239.36
Say per sft 239.00
Per m2 2,575.09
Say per m2 2,575.00

118/97 Timber fixed or renewed in post and frames


special upper class/kempus
Per 1/2 Cu.ft

0.5 c.ft 246 Timber 1,250.00 625.00


0.5 Day 214 Carpenter 475.00 237.50
0.25 Day 257 Labourer 325 81.25 943.75
Overheads 132.13
per 1/2 c.ft 1,075.88
per c.ft 2,151.75
Say per c.ft 2,152.00
Per m3 75,929.99
Say per m3 75,930.00

No Qty Unit Description Unit Rate Rate Amount


140/103 Door 1 1/4" thick plywood ordinary sash
single (ordinary finish) hung on 4"x3"
frame in Special upper class timber/kempus and
complete with brass furnishers & lock
Per 22.75 sq.ft (3'-3"x7'-0")
1.6 Cu.ft 246 Timber 1250 2,000.00
2 Nos 220 Spur stone 22.5 45.00
4 Nos 98 Rawl plugs 17.5 70.00
414 Allow for dowels 25 25.00
1 Day 214 Carpenter 475 475.00

Analysis 1st half - Mullaitivu


Page 94

1 Day 257 Labourer 325 325.00


1/8 Day 214 Mason 475 59.38
1/8 Day 257 Labourer 325 40.63
fittings
1 1/2 Pairs 94 4"x3" Brass hinges 136 204.00
1 Nos 117 10" skelton bolt 136 136.00
1 Nos 23 6" Barrel bolt 120 120.00
1 Nos 142 Mortice lock 525 525.00
1 Doz 40a 11/2" Brass screw 52.5 52.50
2 Doz 40d 1" - Do - 45 90.00
1 Doz 40c 3/4" -Do - 31.5 31.50
413 Allow for cement 50 50.00
Door sash plywood (ordinary finish)
1 No 188 plywood door ( 6'-9" x 2'-9") 1765 1,765.00
0.5 Day 214 Carpenter 475 237.50
0.5 Day 257 Labourer 325 162.50 6,414.00
Over heads 897.96
Per 22.75 Sq.ft 7,311.96
Per s.ft 321.40
Say per s.ft 321.00
per m2 3,457.80
Say per m2 3,458.00

No Qty Unit Description Unit Rate Rate Amount


140a/103 As per Item No 140 but with marine type
2'-8"x 7'-0"
Per 18.62sq.ft
1.6 Cu.ft 246 Timber 1,250.00 2,000.00
2 No 220 Spur Stone 22.50 45.00
4 No 98 Rawl plug 17.50 70.00
414 Allow for Dowels 25.00 25.00
1 Day 214 Carpenter 475.00 475.00
1 Day 257 Labour 325.00 325.00
0.13 Day 214 Mason 475.00 61.75

Analysis 1st half - Mullaitivu


Page 95

0.13 Day 257 Labour 325.00 42.25


Marine Door Sash
1 no 187 Ply wood Door 1,848.00 1,848.00
0.5 Day 214 Carpenter 475.00 237.50
0.5 Day 257 Labour 325.00 162.50
1.5 pair 94 4" x 3" Brass hinges 136.00 204.00
2 Nos 23 6" barrel bolt 120.00 240.00
2 Nos 60 Draw rings 25.00 50.00
1 Doz 40a 11/2" Brass screw 52.50 52.50
2 Doz 40d 1" - do - 45.00 90.00
1 Doz 40c 3/4" -do- 31.50 31.50 5,960.00
Over head 834.40
Per18.62 Sq.ft 6,794.40
Per Sq.ft 364.90
Say Rs 365.00
Say per m2 3,927.40
per m2 3,927.00
142/104 Supplying and fixing Plywood door 1 1/4" thick
single (Ordinary finish) to the existing frame
with brass fittings
2' 9" x 6' 9" = 18.56 S.ft
1 1/2 Pairs 94 4"x3" Brass hinges 136.00 204.00
1 Nos 117 10" skelton bolt 136.00 136.00
1 Nos 23 6" Barrel bolt 120.00 120.00
1 Nos 142 Mortice lock 525.00 525.00
1 Doz 40a 11/2" Brass screw 52.50 52.50
2 Doz 40d 1" - Do - 45.00 90.00
1 Doz 40c 3/4" -Do - 31.50 31.50
413 Allow for cement 50 50.00
Door sash plywood (ordinary finish)
1 No 188 plywood door ( 6'-9" x 2'-9") 1765 1,765.00
0.5 Day 214 Carpenter 475 237.50
0.5 Day 257 Labourer 325 162.50 3,374.00
Over heads 472.36
Per 18.56 S.ft 3,846.36
Per S.ft 207.24
Say Per S.ft 207.00
Per m2 2,229.56
Say Per m2 2,230.00

No Qty Unit Description Unit Rate Rate Amount


143/104 -do- -do- plywood Marine type 1 1/4" thick
single hung to existing frame with fitting

2' 3" x 6' 9" = 15.18S.ft


Marine Door Sash
1 Nos 187 Ply wood Door 1848 1,848.00
0.5 Day 214 Carpenter 475 237.50
0.5 Day 257 Labour 325 162.50
1.5 pair 94 4" x 3" Brass hinges 136 204.00
2 Nos 23 6" barrel bolt 120 240.00

Analysis 1st half - Mullaitivu


Page 96

2 Nos 60 Draw rings 25 50.00


1 Doz 40a 11/2" Brass screw 52.5 52.50
2 Doz 40d 1" - do - 45 90.00
1 Doz 40c 3/4" -do- 31.5 31.50 2,916.00
Overheads 408.24
Per 15.18 S.ft 3,324.24
Per S.ft 218.99
Say per S.ft 219.00
Per m2 2,355.96
Say per m2 2,356.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU


PAINTER & DECORATOR.

No Qty Unit Description Unit Rate Rate Amount


Lettering 1" to 1 1/2" painted in sinhalese
13/165 English or Tamil, including painting
ground.
Per 6 letters
1 Hour 206 Signboard painter 375 46.88

Analysis 1st half - Mullaitivu


Page 97

416 Allow for painting background 2 coats 150 150.00


414 Allow for brushes paint etc 25 25.00 221.88
Over heads 31.06
Per 6 letters 252.94
Per letter 42.16
Say Rs 42.00

14/165 Lettering 2" to 3" - do -


- do - - do -.
Per 5 letters
1 Hour 206 Signboard painter 375 46.88
414 Allow for brushes, paint 25 25.00
416 Allow for painting backround 2 coats 150 150.00 221.88
Over heads 31.06
Per 5 letters 252.94
Per letter 50.59
Say Rs 50.00

15/166 Lettering 4" to 5" - do -


- do - - do -.
Per 4 letters
1 Hour 206 Signboard painter 375 46.88
413 Allow for brushes, paint etc 50 50.00
416 Allow for painting backround 2 coats 150 150.00 246.88
Over heads 34.56
Per 4 letters 281.44
Per letter 70.36
Say Rs 70.00

23/168 Painting, enamel paint including washing


cleaning and smoothing down with sand
paper, 1 coat.
Per square
0.17 gal 171 Oil paint 1785 303.45
5 Hour 214 Painter cleaning down and painting 475 296.88
413 Allow for brushes sand paper washing soda 50 50.00 650.33
Over heads 91.05
Per square 741.37
Say Rs 741.00
Per m2 79.80
Say per m2 80.00

No Qty Unit Code Description Unit Rate Rate Amount


Painting enamel paint - do -
24/168 - do - 2 coats.
Per square
1st coat as in Item 23 650.33 650.33
0.17 gal 171 Paint ( 2 nd coat ) 1785 303.45
4 Hour 214 Painter 475 237.50
413 Allow for brushes etc 50 50.00 1,241.28
Over heads 173.78
Per square 1,415.05
Say per Sqr 1,415.00

Analysis 1st half - Mullaitivu


Page 98

Per m2 152.32
Say per m2 152.00

25/168 Painting New wood 1 Coat primer & 2 Coats


Enamel paint
Per sqrs
0.17 gal 190 Primer 1560 265.20
0.33 gal 65 Enamel paint 1785 589.05
2 Day 214 Painter 475 950.00
413 Allow Sand paper & brushes 50 50.00 1,854.25
Over heads 259.60
Per square 2,113.85
Say per Sqr 2,114.00
Per m2 227.56
Say per m2 228.00
25a/168 Painting new wood work and 2 coats of
enamel paint.
Per square
0.33 gal 65 Gloss paint(enamel) 1785 589.05
1.25 Day 214 Painter 475 593.75
413 Allow for sand paper brushes etc 50 50.00 1,232.80
Over heads 172.59
Per square 1,405.39
Say per sqr 1,405.00
Per m2 151.28
Per m2 151.00

Painting Steel work, 1 coat, with


27/169 Anticrosive paint including removing
scale and wire brushing.
Per square
0.17 gal 12b Anticrosive paint 1139 193.63
5 Hour 214 Painter pareparing surface and painting 475 296.88
413 Allow for brushes 50 50.00 540.51
Over heads 75.67
Per square 616.18
Say per sqr 616.00
per m2 66.33
Say per m2 66.00

No Qty Unit Code Description Unit Rate Rate Amount


Painting Steel work, 2 coats, with Red
28/169 oxide including removing scale and
wire brushing.
Per square
1st coat as in Item 27 540.51 540.51
0.17 gal 12b Paint 1139 193.63
4 Hour 214 Painter 475 237.50
414 Allow for brushes etc 25 25.00 996.64
Over heads 139.53
Per square 1,136.16
Say per sqr 1,136.00

Analysis 1st half - Mullaitivu


Page 99

Per m2 122.30
Say per m2 122.00

30/169 Painting walls with emulsion paint 1 coat


(new coat).

0.17 gal 64 Emulsion paint 1415 240.55


3 Hour 214 Painter 475 178.13
413 Allow for brushes 50 50.00 468.68
Over heads 65.61
Per square 534.29
Say per sqr 534.00
per m2 57.51
Say per m2 58.00

30a/169 Painting walls with weather shield 1 coat


( New work )
Per square
0.17 gal 63 weather shield paint 1790 304.30
3 Hour 214 Painter 475 178.13
413 Allow for brushes etc 50 50.00 532.43
Overheads 74.54
Per Sqr 606.96
Say Per Sqr 607.00
Per m2 65.34
Say Per m2 65.00

Painting walls with Emulsion paint, 2


31/170 coats (new work).
Per square
1st coat as in Item 30 468.68 468.68
0.14 gal 64 Emulsion paint 1415 198.10
2 1/2 Hour 214 Painter 475 148.44
414 Allow for brushes etc 25 25.00 840.21
Over heads 117.63
Per square 957.84
Say per sqr 957.00
Per m2 103.10
Say per m2 103.00

No Qty Unit Code Description Unit Rate Rate Amount


31a/170 Painting walls with 2 coats of weather shield paint
( New work )
Per square
1 st coat as in Iten 30a 532.43
0.14 gal 63 2 nd coat w.s. paint 1790 250.60
2.5 Hrs 214 Painter 475 148.44
413 Allow for brushes 50 50.00 981.46
Over heads 137.40
Per square 1,118.87
Say per sqr 1,118.00
Per m2 120.44

Analysis 1st half - Mullaitivu


Page 100

Say per m2 120.00


Painting walls with Emulsion paint, 1
32/170 coat including preparing surface of old
work.
Per square
As I Item 30 468.68 468.68
1/2 Hour 214 Painter 475 29.69
413 Allow for wire brushes sand paper etc 50 50.00 548.36
Over heads 76.77
Per square 625.13
Say per sqr 625.00
Per m2 67.29
Say per m2 67.00
32a/170 Painting walls with weather shield paint
1 coat ( Old work )
Per square
As I Item 30a 532.43 532.43
0.5 Hrs 214 Painter for preparing surface 475 29.69
413 Allow for wire brushes 50 50.00 612.11
Over heads 85.70
Per square 697.81
Say per sqr 698.00
Per m2 75.11
Say per m2 75.00
- do - - do -
33/170 2 coats - do - - do -.
Per square
As in Item 31 840.21 840.21
Preparing surface as in Item 32 79.69 79.69 919.90
Over heads 128.79
Per square 1,048.69
Say per sqr 1,049.00
Per m2 112.88
Say per m2 113.00
33a/170 Painting walls with weather shield paint
2 coat ( Old work )
Per square
As in Item 31a 981.46
0.5 Hrs 214 Painter for preparing surface 475 29.69
413 Allow for wire brushes 50 50.00 1,061.15
Over heads 148.56
Per square 1,209.71
Say per sqr 1,210.00
Per m2 130.22
Say per m2 130.00
No Qty Unit Code Description Unit Rate Rate Amount
40/172 Tarnap or other wood preservative,
applied to wood work 1 coat (old work).
Per square
0.25 gal 268a Wood preservative 315 78.75
2 Hour 214 Painter 475 118.75
414 Allow for brushes etc 25 25.00 222.50
Over heads 31.15
Per square 253.65
Say per sqr 253.00
Per m2 27.30
Say per m2 27.00

Analysis 1st half - Mullaitivu


Page 101

Tarnap or other wood preservative,


41/172 applied to wood work 2 coats (new work).
Per square
0.45 gal 268a Wood preservative 315 141.75
4 Hour 214 Painter 475 237.50
414 Allow for brushes 25 25.00 404.25
Over heads 56.60
Per square 460.85
Say per sqr 460.00
Per m2 49.61
Say per m2 50.00

Varnishing with best copal varnish after


44/173 washing down and sand papering 1 coat.
Per sqrs

3 Hour 257 Labourer 325 121.88


4 Hour 214 Painter 475 237.50
413 Allow for sandpaper, brushes etc 50 50.00
0.2 gal 260 Varnish 1756 351.20 760.58
Over heads 106.48
Per square 867.06
Say per sqr 867.00
Per m2 93.33
Say per m2 93.00

- do - - do -
45/173 - do - 2 coats.
Per square
1st coat as in Item 44 760.58 760.58
0.17 gal 260 Varnish 1756 298.52
4 Hour 214 Painter 475 237.50
414 Add for brushes etc 25 25.00 1,321.60
Over heads 185.02
Per square 1,506.62
Say per sqr 1,507.00
Per m2 162.18
Say per m2 162.00

No Qty Unit Code Description Unit Rate Rate Amount


49/174 White or colourwashing walls of single
storey buildings 1 coat, including
patching and preparing surface.
Per 10 sqrs
1 Day 214 Painter 475 475.00
1 Day 257 Labourer 325 325.00
3/4 Bushel 216 Boiled lime 270 202.50
1/4 Lb 85 Glue 86 21.50
414 Allow for brushes 25 25.00
1/4 Lb 269 Yellow Ochre 0 0.00 1,049.00
Over heads 146.86

Analysis 1st half - Mullaitivu


Page 102

Per 10 sqrs 1,195.86


Per square 119.59
Say per sqr 120.00
Per m2 12.87
Say per m2 12.90

- do - - do -
50/174 2 coats - do -.
Per 10 squares
1 3/4 Day 214 Painter 475 831.25
1 3/4 Day 257 Labourer 325 568.75
1 1/4 Bushel 216 Lime 270 337.50
1/2 Lb 85 Glue 86 43.00
413 Allow for brushes etc 50 50.00
1/2 Lb 269 Yellow Ochre 0 0.00 1,830.50
Over heads 256.27
Per 10 squares 2,086.77
Per square 208.68
Say Rs 208.00
Per m2 22.46
Say per m2 22.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU


BRASS FOUNDER.
No Qty Unit Code Description Unit Rate Rate Amount
Bolts barrel 4", brass oxidised heavy
4/127 quality supplied and fixed with brass
screws.

Per No
1 no 22 4" Brass barrel bolt 79 79.00
1/2 Doz 207a 1" screws brass 45 22.50
1/3 hr 214 Carpenter 475 19.79 121.29

Analysis 1st half - Mullaitivu


Page 103

Over heads 16.98


Per No 138.27
Say Rs 138.00

6/128 - do - 6" - do -
- do - - do -
Per No
1 no 23 6" Brass barrel bolt. 120 120.00
Screws and labour as in Item 4 42.29 42.29 162.29
Over heads 22.72
Per No 185.01
Say Rs 185.00

18/130 Casement fastner with mortice plate, brass oxidised


heavy quality supplied and fixed with brass screws.
Per No
1 no 45 Casement fastner 90.00 90.00
1/3 Doz 207a 1" Screws 45 15.00
3/4 hr 214 Carpenter 475 44.53 149.53
Over heads 20.93
Per No 170.47
Say Rs 170.00

Casement stays 10", brass oxidised heavy


19/130 quality supplied and fixed.
Per No
1 No 44 10" Casement stay 90 90.00
1/3 Doz 207a 1" Screws 45 15.00
1/2 hr 214 Carpenter 475 29.69 134.69
Over heads 18.86
Per No 153.54
Say Rs 154.00

21/131 Fanlight Catches brass oxidised heavy


quality with brass screws fixed complete.
Per No
1 No 66 Fanlight Catch 30 30.00
1/3 Doz 40d 1" Screws 45 15.00
3/4 hr 214 Carpenter 475 44.53 89.53
Over heads 12.53
Per No 102.07
Say Rs 102.00

No Qty Unit Code Description Unit Rate Rate Amount


27/132 But hinges 4"x3" brass oxidised heavy quality
supplied and fixed with brass screws complete.
Per No
1 Pair 94 Hinges per pair 136 136.00
1 Doz 40a 1 1/2" screws 52.5 52.50
3/4 hr 214 Carpenter 475 44.53
3/4 hr 257 Labour 325 30.47 263.50
Over heads 36.89
Per No 300.39
Say Rs 300.00

Analysis 1st half - Mullaitivu


Page 104

29/132 - do - 4"x4" - do -
- do - - do -
Per No
1 Pair 95 4" x 4" hinges per pair 205 205.00
Screws and labour as in Item 27 127.50 127.50 332.50
Over heads 46.55
Per No 379.05
Say Rs 379.00

29a/132 - do - 4"x2 1/2" - do -


- do - - do -
Per No
1 Pair 95a 4"x2 1/2" hinges per pair 115.5 115.50
Screws and labour as in Item 27 127.50 127.50 243.00
Over heads 34.02
Per No 277.02
Say Rs 277.00

31/133 Hinges centre pivot (consisting of 2 pieces)


brass oxidised heavy quality supplied and
fixed with brass screws complete.

2 Set 47 3" Centre pivots, set of 4 pieces 45 90.00


3/4 Doz 40d 1" Screws 45 33.75
1 hr 214 Carpenter 475 59.38
1 hr 257 Labourer 325 40.63 223.75
Over heads 31.33
Per set of 4 Nos 255.08
Per set of 2 Nos 128.00

31a/133 Rings, brass 1 3/4" to 1 1/2" supplied


and fixed to doors and windows with
brass screws.
Per No
1 no 198a Ring 1 1/2" 26.25 26.25
1/4 Doz 40c Brass Screws 3/4" 31.5 7.88
1/4 hr 214 Carpenter 475 14.84 48.97
Over heads 6.86
Per No 55.82
Say Rs 56.00

No Qty Unit Code Description Unit Rate Rate Amount


51/137 Lock Mortice Vinion single supplied
and fixed.
Per No
1 No 142 Mortice Lock (single) 525 525.00
1/2 Day 214 Carpenter 475 237.50 762.50
Over heads 106.75
Per No 869.25
Say Rs 869.00

52/137 Lock Mortice Vinion double, supplied


and fixed.

Analysis 1st half - Mullaitivu


Page 105

Per No
1 No 143 Mortice Lock (double) 790 790.00
1 Day 214 Carpenter 475 475.00 1,265.00
Over heads 177.10
Per No 1,442.10
Say Rs 1,442.00

53/137 Mortice Lock Union ( English) single


supplied and fixed.
Per No
1 No 145 Mortice Lock Union (single) 1575 1,575.00
1/2 Day 214 Carpenter 475 237.50 1,812.50
Over heads 253.75
Per No 2,066.25
Say Rs 2,066.00

54/157 Mortice Lock Union ( English) double


supplied and fixed.
Per No
1 No 146 Mortice Lock Union (double) 2795 2,795.00
1 Day 214 Carpenter 475 475.00 3,270.00
Over heads 457.80
Per No 3,727.80
Say Rs 3,728.00

53a/137 Lock Night Latch supplied and fixed with


duplicate keys approved quality
Per No
1 No 144 Lock Night Latch 290 290.00
0.5 Day 214 Carpenter 475 237.50 527.50
Overheads 73.85
Per No 601.35
Say per no 601.00
63/123 Tor steel rods in reinforcing.
Per cwt.
1 Cwt. 249 Tor steel rods 4330 4,330.00
Allow for 10% Wastage 433 433.00
1 day 215 Smith 475 475.00
1 day 257 Labour 325 325.00
1 lbs 31 14 B.W.G. Wire 40 40.00 5,603.00
Over heads 784.42
Per cwt. 6,387.42
Say per Cwt 6,387.00
per kg 127.75
Say per kg 128.00
No Qty Unit Code Description Unit Rate Rate Amount
64/123 Tor steel rods reinforcement in foundation
Per cwt.
1 Cwt. 249 Tor steel rods 4330 4,330.00
Allow for 10% Wastage 433 433.00
3/4 day 215 Smith 475 356.25
3/4 day 257 Labour 325 243.75
1 lbs 31 14 B.W.G. Wire 40 40.00 5,403.00
Over heads 756.42
Per cwt. 6,159.42
Say per cwt 6,159.00
Per kg 123.19

Analysis 1st half - Mullaitivu


Page 106

Say per kg 123.00

63a/123 Mild Steel rods in reinforcing lintols or beams.


Per cwt.
1 Cwt 140 Mild Steel rods 4240 4,240.00
Allow westage 10% 424.00 424.00
1 day 215 Smith 475 475.00
1 day 257 Labour 325 325.00
1 lbs 31 14 B.W.G. Wire 40 40.00 5,504.00
Over heads 770.56
Per cwt. 6,274.56
Say per cwt 6,275.00
Per kg 125.50
Say per kg 126.00

64a/123 Mild Steel rods in Foundation .


Per cwt.
1 Cwt 140 Mild Steel rods 4240 4,240.00
Allow westage 10% 424 424.00
3/4 day 215 Smith 475 356.25
3/4 day 257 Labour 325 243.75
1 lbs 31 14 B.W.G. Wire 40 40.00 5,304.00
Over heads 742.56
Per cwt. 6,046.56
Say per cwt 6,047.00
Per kg 120.93
Say per kg 121.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU


IRONMONGER.
No Qty Unit Code Description Unit Rate Rate Amount
Hinges T, 10" Iron, heavy quality supplied
49/119 and fixed with iron screws complete.
Per Pair
1 Pair 119 10" hinges 58 58.00
1 1/2 doz 40a 1 1/2" Screws 52.5 78.75
1 1/4 hr 214 Carpenter 475 74.22
1 1/4 hr 257 Labourer 325 50.78 261.75
Over heads 36.65

Analysis 1st half - Mullaitivu


Page 107

Per Pair 298.40


Say Rs 298.00

60/121 Locks, rim 6" iron, superior quality, heavy


type, s/f. with iron screws complete.
Per no
1 no 196 6" Rim lock 446 446.00
0.5 doz 40d 1" Brass Screws 45 22.50
1 1/2 Hour 214 Carpenter 475 89.06 557.56
Over heads 78.06
Per no 635.62
Say Rs 636.00

No Qty Unit Code Description Unit Rate Rate Amount


67/123 M.S.Bars 5/8" dia supplied & fixed in
window frame at 4" cetres & painted
with one coat red lead & 2 coats aluminium
Per'4 Rods or 17 l.ft
0.17 cwt 140 M.S.Rods 4240 720.80
1 hr 214 Carpenter 475 59.38
1 hr 257 Labourer 325 40.63
1 hr 214 Painter 475 59.38
414 Allow for paint 25 25.00 905.18
Over heads 126.72
Per 17 L.ft 1,031.90
Per L.ft 60.70
Say Rs 60.00
Say per L.m 199.00

67e/123 1/2" dia - do - - do -


0.09 cwt 140 M.S.Rods 4240 381.60
Labour paint etc. as in Item 67 184.38 184.38 565.98
Over heads 79.24
Per 17 L.ft 645.21
Per L.ft 37.95
Say Rs 37.00
Say per L.m 124.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU


TINKER.
No Qty Unit Code Description Unit Rate Rate Amount
9/150 Flashing G.I.22 B.W.G. 1' 6" wide, fixed
with 6" turned up along, and top edge
tucked well into wall in cement and
lime mortar.

Per 14 L.ft
23 s.ft 74 22 B.W.G sheets 55 1,265.00
4 hrs 215 Tinker cutting & bending to shape and 475 237.50

Analysis 1st half - Mullaitivu


Page 108

fixing in place
1 hr 214 Mason, caulking 475 59.38
5 hrs 257 Labour, assisting tinker and mason 325 203.13
413 Allow for cement sand etc 50 50.00
413 Allow for lead 50 50.00 1,865.00
Overheads 261.10
Per 14 L.ft 2,126.10
PerL.ft 151.86
Say per Lft 152.00
Per Lm 498.11
Say per L.m 498.00

29/156 Gutters, Valley 20 B.W.G 36" wide,


renewed on existing board, sheets
tarred, joints soldered and cement,
lime filletting complete.

Per 22 L.ft
72 S.ft 73 G.I. Sheets 75 5,400.00
1/2 day 214 Tinker 475 237.50
1/2 day 257 Labourer 325 162.50
413 Allow for nails, soldering materials etc 50 50.00
1/3 gal 232 Coaltar 90 30.00
4 hrs 257 Labourer 325 162.50
1 hrs 257 Labourer 325 40.63
2 hrs 214 Mason 475 118.75
4 hrs 257 Labourer 325 162.50
0.16 Cwts 46 Cement 520 83.20
1/6 Bus 216 Lime 270 45.00
1 Cu.ft 200 Sand 2100 21.00
2 hrs 257 Labourer 325 81.25 6,594.83
Overheads 923.28
Per 22 L.ft 7,518.10
Per L.ft 341.73
Say per L.ft 342.00
Per L.m 1,120.88
Say Per L.m 1,121.00

No Qty Unit Code Description Unit Rate Rate Amount


34/158 -Do- renewed including 1" thick timber
boarding sheet tarred, joints soldered and
cement lime filletting complete.
per 22 l.ft
As per Item 29 6,594.83 6,594.83
72 S.ft 35 1" thick boarding 50 3,600.00
1 Ibs 267a Wire nails 1" 36.5 36.50
1 day 214 Carpenter 475 475.00
1 day 257 Labourer 325 325.00 11,031.33
Overheads 1,544.39
Per 22 L.ft 12,575.71

Analysis 1st half - Mullaitivu


Page 109

Per L.ft 571.62


Say per L.ft 572.00
Per L.m 1,874.92
Say per L.m 1,875.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU


PLUMBER.
No Qty Unit Code Description Unit Rate Rate Amount
1/179 Ball valve 1/2" supplied and fixed

1 No 355 1/2" Ball valve 94.5 94.50


0.5 Hrs 214 Plumber 475 29.69
0.5 Hrs 257 Labourer 325 20.31 144.50
Overheads 20.23
Per no. 164.73
Say 165.00

Analysis 1st half - Mullaitivu


Page 110

2/179 Ball valve 3/4" supplied and fixed

1 No 356 3/4" Ball valve 152.25 152.25


Labourer as in Item 1 50.00 202.25
Overheads 28.32
Per no 230.57
Say 231.00

13/181 Wash Basin, Lavatory, 22"x16" with one tap,


water plug, new brackets, supplied &
fixed complete. (Additional tap, trap,
and outlet pipe paid for seperately).

1 No 263 22"x16" basin complete with brackets, tap 1780 1,780.00


etc. and transport
fixing plugs in wall
4 No 184 Plugs 2 8.00
1 Hrs 214 Mason 475 59.38
1 Hrs 257 labourer 325 40.63
Fixing basin and taps
0.75 Day 214 Plumber 475 356.25
0.75 Day 257 labourer 325 243.75
Making holes in wall and making good
1 Hrs 214 Mason 475 59.38
1 Hrs 257 labourer 325 40.63
414 Allow for screws, cement, red lead etc. 25 25.00 2,613.00
Over heads 365.82
Per No 2,978.82
Say Rs 2,979.00

17/182 Wash 'Basin, sink or urinal including all fittings


removed and walls made good

3 Hrs 214 Plumber ( removing basin, brackets and pipes ) 475 178.13
3 Hrs 257 Labourer ( to assist ) 325 121.88
1 Hrs 214 Mason ( making godd to walls and floor ) 475 59.38
1 Hrs 257 Labourer ( to assist ) 325 40.63
414 Allow for cement, lime etc. 25 25.00 425.00
Overheads 59.50
Per no. 484.50
Say 485.00

No Qty Unit Code Description Unit Rate Rate Amount


31/185 Closet, pedestal type available at site, fixed
with cement concrete after breaking concrete
floor and making good and connections to soil
and flush pipes

0.25 Cwt 46 Cement 520 130.00


413 Allow for metal,sand, red lead hemp etc. 50 50.00
0.75 Day 214 Plumber 475 356.25
0.75 Day 257 Labourer 325 243.75 780.00
Overheads 109.20

Analysis 1st half - Mullaitivu


Page 111

Per No 889.20
Say 889.00

32/186 Closet, pedestal type, disconnecting and


plugging sewer connection and making good
all affected walls and floors

1/6 Cwt 46 cement 520 86.67


413 Allow for metal, sand etc, 50 50.00
0.5 Day 214 Plumber 475 237.50
0.5 Day 257 Labourer 325 162.50 536.67
Overheads 75.13
Per No 611.80
Say 612.00

34/186 Closet, pedestal type, with low level


glazed earthenware flushing cistern
flush pipe, double plastic sheet cover,
1/2" stop cork, trap etc. supplied &
fixed completed.

1 no 50 Low level closet suite 4100 4,100.00


1 Item 358 Fittings 367.5 367.50
1 no 359 Seat cover ( Double ) 420 420.00
1 Item 360 Brackets 62 62.00
1 no 361 Flush bend 39.8 39.80
1 no 227 1/2" stop cock 105 105.00
415 Allow for transport 100 100.00
413 Cement, Metal, Sand etc. (Item 31) 50 50.00
1 day 214 Plumber 475 475.00
1 day 257 Labourer 325 325.00 6,044.30
Over heads 846.20
Per No 6,890.50
Say Rs 6,891.00
35/186 Closet squatting type, with trap supplied
& fixed.
1 no 222 Squatting pan & trap 700 700.00
413 Allow for transport 50 50.00
1/3 Cwt 46 Cement 520 173.33
413 Allow for metal, sand etc. 50 50.00
1 day 214 Plumber 475 475.00
1 day 257 Labourer 325 325.00 1,773.33
Over heads 248.27
Per No 2,021.60
Say Rs 2,022.00

Qty Unit Code Description Unit Rate Rate Amount


36/187 Closet, squatting type, removed, sewer
connections plugged and floor made
good.

1/2 Cwt 46 Cement 520 260.00


415 Allow for metal, and sand etc. 100 100.00
1/2 day 214 Plumber 475 237.50
1/2 day 257 Labourer 325 162.50 760.00
Over heads 106.40

Analysis 1st half - Mullaitivu


Page 112

Per No 866.40
Say Rs 866.00

40/188 Cocks, brass bib 1/2" supplied & fixed


(Heavy quality).

1 no 36 1/2" brass bib cock 145 145.00


414 Allow for solvant 25 25.00
1/3 hour 214 Plumber 475 19.79
1/3 hour 257 Labourer 325 13.54 203.33
Over heads 28.47
Per No 231.80
Say Rs 232.00

66/193 Flushing Cistern fixed complete


low level '(Ceremics).

4 No 184 Plugs 2 8.00


1 hour 214 Mason 475 59.38
1 hour 257 Labourer 325 40.63
414 Allow for cement etc. 25 25.00
1/2 day 214 Plumber 475 237.50
1/2 day 257 Plumber's mate at allow for solvent cement 325 172.50 543.00
Over heads 76.02
Per No 619.02
Say Rs 619.00

66a/193 Flushing cistern, low level, plastic


supplied and fixed complete.
4 No 184 Plugs 2 8.00
1 hour 214 Mason 475 59.38
1 hour 257 Labourer 325 40.63
414 Allow for cement etc. 25 25.00
1 no 183 Low level plastic cistern 1265 1,265.00
1/2 day 214 Plumber 475 237.50
1/2 day 257 Plumber's mate 325 162.50
417 Allow for cement etc. 10 10.00 1,808.00
Over heads 253.12
Per No 2,061.12
Say Rs 2,061.00

No Qty Unit Code Description Unit Rate Rate Amount


86/197 Mirror, bath room type, supplied &
fixed to wall with Rawl plugs and
plastic frames.

1 no 141 Mirror with fittings 520 520.00


413 Allow for Rawl plugs and screws 50 50.00
2 hour 214 Plumber 475 118.75 688.75
Over heads 96.43
Per No 785.18

Analysis 1st half - Mullaitivu


Page 113

Say Rs 785.00

147/214 Shower rose, 3" jet supplied & fixed.

1 no 314 6" Shower rose 500 500.00


0.25 Hrs 214 Plumber 475 14.84
0.25 Hrs 257 Labourer 325 10.16 525.00
Over heads 73.50
Per No 598.50
Say Rs 599.00

153/215 Sink, glazed, earthenware 24"x15"x8"


supplied and fixed with waste plug,
complete (pedestal paid seperately).

1 no 211 Sink 24"x15"x8" with waste plug & chain 2100 2,100.00
413 Allow for transport 50 50.00
1/2 day 214 Plumber 475 237.50
1/2 day 257 labourer 325 162.50
414 Allow for cement 25 25.00 2,575.00
Over heads 360.50
Per No 2,935.50
Say Rs 2,936.00

147a/214 Towel rail 2'-0" long 3/4" dia chromium


plated.

1 no 250 Chromium plated towel rail 275 275.00


1 hour 214 Plumber 475 59.38
414 Allow for rawl plug & screws 25 25.00 359.38
Over heads 50.31
Per No 409.69
Say Rs 410.00

171/219 Soap tray, white porcelain, supplied and


fixed to wall with rawl plugs.

1 no 218 Soap tray 173 173.00


1 hour 214 Plumber 475 59.38
414 Allow for rawl plugs and screws 25 25.00 257.38
Over heads 36.03
Per No 293.41
Say Rs 293.00

No Qty Unit Code Description Unit Rate Rate Amount


173/220 Stop cocks, 1/2" supplied & fixed
Plastic L.D. make).

1 no 227 1/2" Stop cock 105 105.00


1/2 hour 214 Plumber 475 29.69
1/2 hour 257 Labourer 325 20.31
413 Allow for solvert cement 50 50.00 205.00
Over heads 28.70
Per No 233.70

Analysis 1st half - Mullaitivu


Page 114

Say Rs 234.00

174/220 Stop cocks, 3/4" supplied and fixed.


Plastic L.D. make).
1 no 309 3/4" stop cock 134.4 134.40
Labour etc. as in Item 173 100.00 100.00 234.40
Over heads 32.82
Per No 267.22
Say Rs 267.00

175/220 Stop cocks, 1" supplied and fixed.


Plastic L.D. make).
1 no 310 1" stop cock 145.6 145.60
Labour etc. as in Item 173 100.00 100.00 245.60
Over heads 34.38
Per No 279.98
Say Rs 280.00

176/220 Stop cocks, 1 1/4" supplied and fixed.


( Plastic L.D. Model )
1 no 311 1 1/4" stop cock 280 280.00
Labour etc. as in Item 173 100.00 100.00 380.00
Over heads 53.20
Per No 433.20
Say Rs 433.00

177/220 Stop cocks, 1 1/2" supplied and fixed.


Plastic L.D. make).
1 no 312 1 1/2" stop cock 306 306.00
Labour etc. as in Item 173 100.00 100.00 406.00
Over heads 56.84
Per No 462.84
Say Rs 463.00

178/221 Stop cocks, 2" supplied and fixed.


Plastic L.D. make).
1 no 313 2" stop cock 372 372.00
Labour etc. as in Item 173 100.00 100.00 472.00
Over heads 66.08
Per No 538.08
Say Rs 538.00

No Qty Unit Code Description Unit Rate Rate Amount


178a/221 As per Item No. 178a (Gate valve 2")
English make
1 No 308 Gate valve 2" 357 357.00
5/8 Hour 214 Plumber 475 296.88
5/8 Hour 257 Mate (labour) 325 203.13
414 Allow for cement 25 25.00 882.00
Over heads 123.48
Per No 1,005.48
Say Rs 1,005.00

Analysis 1st half - Mullaitivu


Page 115

178b/221 Non return valve English 2" dia

1 No Non Return Valve English 2" dia. #N/A #N/A


5/8 Hour 214 Plumber 475 37.11
5/8 Hour 257 Mate (labour) 325 25.39
414 Allow for cement 25 25.00 #N/A
Over heads #N/A
Per No #N/A
Say Rs #N/A

200/228 Tooth brush holder, chromium plated


supplied and fixed to wall with Rawl
plugs.
1 no 248 Tooth brush holder 196 196.00
1 hour 214 Plumber 475 59.38
414 Allow for Rawl plugs & holder 25 25.00 280.38
Over heads 39.25
Per No 319.63
Say Rs 320.00
292/240 Pipes pvc 1/2" supplied & fixed.
Per 100 L.ft.
100 L.ft 7 1/2" pipe 7 700.00
Add 25% for specials 175 175.00
2 hour 214 Plumber 475 118.75
2 hour 257 Labourer 325 81.25
413 Allow for sol. Cement petrol blow lamp etc. 50 50.00 1,125.00
Over heads 157.50
Per 100 L.ft. 1,282.50
Per L.ft 12.83
Say Rs 13.00
Per L.m 42.07
Say Rs 42.00
293/240 Pipes pvc 3/4" supplied & fixed.
Per 100 L.ft.
100 L.ft 10 3/4" pipe 12 1,200.00
Add 25% for specials 300.00
2 hour 214 Plumber 475 118.75
2 hour 257 Labourer 325 81.25
413 Allow for sol. Cement petrol blow lamp etc. 50 50.00 1,750.00
Over heads 245.00
Per 100 L.ft. 1,995.00
Per L.ft 19.95
Say Rs 20.00
Per L.m 65.44
Say Rs 65.00

No Qty Unit Code Description Unit Rate Rate Amount


294/240 Pipes pvc 1" supplied & fixed 1000 type.

100 L.ft 5 1" pipe 19 1,900.00


Add 25% for specials 475.00
1 1/2 day 257 Labourer ( for excavation) 325 487.50
3/4 day 257 Labourer ( for Back Filling) 325 243.75
3 hour 214 Plumber 475 178.13
3 hour 257 Labourer 325 121.88
413 Allow for sol. Cement petrol blow lamp etc. 50 50.00 3,456.25

Analysis 1st half - Mullaitivu


Page 116

Over heads 483.88


Per 100 L.ft. 3,940.13
Per L.ft 39.40
Say Rs 39.00
Per L.m 129.24
Say Rs 129.00

294a/240 pipes pvc 1" supplied & fixed 600 type.

100 L.ft 6 1" pipe 11 1,100.00


Add 25% for specials 275.00
1 1/2 day 257 Labourer 325 487.50
3/4 day 257 Labourer 325 243.75
3 hour 214 Plumber 475 178.13
3 hour 257 Labourer 325 121.88
413 Allow for sol. Cement petrol blow lamp etc. 50 50.00 2,456.25
Over heads 343.88
Per 100 L.ft. 2,800.13
Per L.ft 28.00
Say Rs 28.00
Per L.m 91.84
Say Rs 92.00

295/240 Pipes pvc 1 1/4" supplied & fixed 1000 type.

100 L.ft 3 1 1/4" pipe 28 2,800.00


Add 25% for specials 700.00
Labour for Exc. & Refill as Per 294 731.25 731.25
4 hour 257 Plumber 325 162.50
4 hour 214 Labourer 475 237.50
413 Allow for sol. Cement petrol blow lamp etc. 50 50.00 4,681.25
Over heads 655.38
Per 100 L.ft. 5,336.63
Per L.ft 53.37
Say Rs 53.00
Per L.m 175.04
Say Rs 175.00

No Qty Unit Code Description Unit Rate Rate Amount


295a/240 Pipes pvc 1 1/4" supplied & fixed 600 type.

100 L.ft 4 1 1/4" pipe 20 2,000.00


Add 25% for specials 500.00
Labour for Exc. & Refill as Per 294 731.25 731.25
4 hour 214 Plumber 475 237.50
4 hour 257 Labourer 325 162.50
413 Allow for sol. Cement petrol blow lamp etc. 50 50.00 3,681.25
Over heads 515.38

Analysis 1st half - Mullaitivu


Page 117

Per 100 L.ft. 4,196.63


Per L.ft 41.97
Say Rs 42.00
Per L.m 137.65
Say Rs 138.00

296/241 Pipes pvc 1 1/2" supplied & fixed.

Excavation & Refilling as in Item 294 731.25 731.25


100 L.ft 1 1 1/2" pipe (1000 type) 42 4,200.00
Add 25% for specials 1,050.00
4 hour 214 Plumber 475 237.50
4 hour 257 Labourer 325 162.50
413 Allow for sol. Cement petrol blow lamp etc. 50 50.00 6,431.25
Over heads 900.38
Per 100 L.ft. 7,331.63
73.32
Say Rs Per L.ft 73.00
240.48
Say Rs Per L.m 240.00

296a/241 pvc pipe 1 1/2" (1000 type) supplied &


fixed with out excavation.

As per Item 296 6,431.25 6,431.25


Less Excavation 294 731.25 5,700.00
Over heads 798.00
Per 100 L.ft. 6,498.00
64.98
Say Rs Per L.ft 65.00
213.13
Say Rs Per L.m 213.00

296b/241 pvc pipe 1 1/2" (600 type) supplied &


fixed with excavation.

100 L.ft 2 1 1/2" pvc 600 type 27 2,700.00


25% Specials 675.00
Labour & etc as per 294 731.25 731.25 4,106.25
Over heads 574.88
Per 100 L.ft. 4,681.13
Per L.ft 46.81
Say Rs 47.00
Per L.m 153.54
Say Rs 154.00

No Qty Unit Code Description Unit Rate Rate Amount


296c/241 pvc pipe 1 1/2" (600 type) supplied &
fixed with out excavation.
As per Item 296b 4,106.25 4,106.25
Less Excavation as per 294 731.25 3,375.00
Over heads 472.50
Per 100 L.ft. 3,847.50
Per L.ft 38.48
Say Rs 38.00
Per L.m 126.20

Analysis 1st half - Mullaitivu


Page 118

Say Rs 126.00

297/241 Pipes pvc 2" (1000 type) supplied & fixed.


With excavation
Excavation & Refilling as in Item 294 731.25 731.25
100 L.ft 8 2" pipe 73 7,300.00
Add 25% for specials 1,825.00
5 hour 214 Plumber 475 296.88
5 hour 257 Labourer 325 203.13
414 Allow for sol. Cement petrol blow lamp etc. 25 25.00 10,381.25
Over heads 1,453.38
Per 100 L.ft. 11,834.63
Per L.ft 118.35
Say Rs 118.00
Per L.m 388.18
Say Rs 388.00

297a/241 pvc pipe 2" (1000 type) supplied &


fixed with out excavation.
As per Item 297 10,381.25 10,381.25
Less Excavation 294 731.25 9,650.00
Over heads 1,351.00
Per 100 L.ft. 11,001.00
Per L.ft 110.01
Say Rs 110.00
Per L.m 360.83
Say Rs 361.00

297b/241 pvc pipe 2" (600 type) supplied &


fixed with excavation.

100 L.ft 9 2" pvc (600 type) 44 4,400.00


25% Specials 1,100.00
Labour & etc. As per 294 731.25 6,231.25
Over heads 872.38
Per 100 L.ft. 7,103.63
Per No 71.04
Say Rs 71.00
Per L.m 233.00
Say Rs 233.00

No Qty Unit Code Description Unit Rate Rate Amount


297c/241 pvc pipe 2" (600 type) supplied &
fixed with out excavation.

As per Item 297b 6,231.25 6,231.25


Less Excavation as per 294 731.25 5,500.00
Over heads 770.00
Per 100 L.ft. 6,270.00
Per L.ft 62.70
Say Rs 63.00

Analysis 1st half - Mullaitivu


Page 119

Per L.m 205.66


Say Rs 206.00

310/243 Eaves gutters 6" square type pvc fixed


with PVC brackets. (1' - 6 " Crs)
Per 24.0 L.ft
24.5 L.ft 161 PVC gutter 6" 38.5 943.25
1 No 157 End cap 44.8 44.80
1/2 No 159 Mitre joint 164 82.00
1 1/2 No 158 Gutter joiners 51.5 77.25
17 Nos. 317 pvc gutter brackets 9.2 156.40
1 No 160 running head 107 107.00
1 tin 318 50 grm solvent cement 43 43.00
3 doz 40c 3/4" screws Brass 31.5 94.50
415 Allow for scaffolding 100 100.00
2 hour 214 Plumber 475 118.75
2 hour 257 Labour 325 81.25 1,848.20
Over heads 258.75
Per 24 L.ft. 2,106.95
Per L.ft 87.79
Say Lft 88.00
Per Lm 287.95
Say Lm 288.00

311/244 Down Pipe 3 1/2" Dia P.V.C Fixed with


Wooden Plug to wall etc.
Per 24.0 L.ft
2 length 370 3 1/2" Dia PVC Pipe 416 832.00
1 No 371 Socket 3 1/2" Dia 47.25 47.25
2 No 368 Bends 3 1/2" Dia 64 128.00
2 No 372 Elbow 3 1/2" Dia 64 128.00
4 No 21 Wooden Block 5 20.00
4 No 373 Clips 3 1/2" Dia 9.5 38.00
0.66 Doz 40c 3/4" Brass Screw 31.5 20.79
1 1/2 tin 318 50 grs solvent ct. 43 64.50
Allow for scaffolding 16.25
2 hrs 214 Plumber 475 118.75
2 hrs 257 labours 325 81.25
2 hrs 214 mason 475 118.75
2 hrs 257 labours 325 81.25 1,694.79
Over head 237.27
Per 24.0 L.ft 1,932.06
Per L.ft 80.50
Say Per L.ft 81.00
Per .L.m 264.05
Say Per .L.m 264.00

No Qty Unit Code Description Unit Rate Rate Amount


5/245 Drains, pvc 400 type 4" laid on cement
concrete 6" thick upto 2'-0" depth of
invert including excavation and cement
concrete haunching (1:3:6 - 1" metal).
Per 100 L.ft.
5 cube Excavation & refilling concrete 545.63 2,728.13
bed 16"x6" comes from item 2/13
0.67 cube Cement concrete(1:3:6) 1"as per item 2c/16 18,731.00 12,549.77
0.10 cube Concrete (1:2:4) 3/4" 21,645.00 2,164.50

Analysis 1st half - Mullaitivu


Page 120

Add 50% on Labour as item 5/16 1,537.50 1,537.50


1 1/2 day 214 Plumber 475 712.50
1.5 day 257 Mate (labour) 325 487.50
Allow for solvent cement 50 50.00
1/2 day 214 Plumber 475 237.50
1/2 day 257 Mate (labour) 325 162.50
100 L.ft 169 pvc 4" pipe (400 type) including transport 107 10,700.00 31,329.90
Over heads 4,386.19
Per 100 L.ft. 35,716.08
Per No 357.16
Say Lft 357.00
Per Lm 1,171.49
Say Lm 1,171.00

311a/244 PVC 4" ( 600 type ) pipe supplied and fixed on walls
Per 24 L.ft
24 L.ft 168 PVC 4" ( 600 type ) pipe 48.5 1,164.00
Add 25% for specials & clips , plugs etc. 291.00
4 Hrs 214 Plumber 475 1,900.00
4 Hrs 257 Labourer 325 1,300.00
413 Allow for solvent cement 50 50.00
Allow for scaffolding 65.00 4,770.00
Over heads 667.80
Per 24 L.ft 5,437.80
Per L.ft 226.58
Say Rs 227.00
Per L.m 743.17
Say Rs 743.00

13/246 Gulley pvc 6" supplied & fixed including


gulley box.

1 no 90 6" Gulley box 290 290.00


1/4 hour 257 Labourer 325 10.16
2 hour 214 Mason 475 118.75
2 hour 257 Labourer 325 81.25
413 Allow for cement,metal & sand 50 50.00 550.16
Over heads 77.02
Per No 627.18
Say Rs 627.00

No Qty Unit Code Description Unit Rate Rate Amount


18/247 Manhole 2'x2' and upto 2'-0" deep, 9"
thick brick in cement 1:3 walls & cement
rendered 1/2" (1:2) with 6" cement conc.
foundation 1:3:6 (1" metal) including
forming channels but without cover.

1/2 day 257 Labourer digging & transporting surplus 325 162.50
250 Nos. 41 Bricks 5.7 1,425.00
6 C.ft 136 1" Metal 8470 508.20

Analysis 1st half - Mullaitivu


Page 121

10 C.ft 197 Sand 2100 210.00


2 cwt 46 Cement 520 1,040.00
1 day 214 Mason 475 475.00
2 day 257 Labourer 325 650.00 4,470.70
Over heads 625.90
Per No. 5,096.60
Say Rs 5,097.00

19/247 Manhole 3'6"x2'3" & 2'0" to 4'0" deep


- do - - do -.

1/2 day 257 2 Labourers digging & transporting soil 325 325.00
500 Nos. 41 Bricks 5.7 2,850.00
0.10 Cube 136 1" Metal 8470 847.00
0.17 Cube 197 Sand 2100 357.00
3 1/4 Cwt 46 Cement 520 1,690.00
1 1/2 day 214 Mason 475 712.50
3 day 257 Labourer 325 975.00 7,756.50
Over heads 1,085.91
Per no 8,842.41
Say Rs 8,842.00
20/248 Manhold 3' 6" x 2' 3" & 4' to 6' deep 9" thick
-do -do-
1 day 257 2 labours digging & transporting soil 325 325.00
875 No 41 Bricks 5.7 4,987.50
0.1 Cube 136 1" Metal 8470 847.00
0.26 Cube 197 Sand 2100 546.00
4 1/2 Cwt 46 Cement 520 2,340.00
2 1/2 day 214 Mason 475 1,187.50
5 day 257 Labourer 325 1,625.00 11,858.00
Over heads 1,660.12
Per no 13,518.12
Say Rs 13,518.00

No Qty Unit Code Description Unit Rate Rate Amount


23/248 Manhole cover reinforced concrete 3"
thick 2'-0x2'-0" approx. supplied & fixed
reinforced with 1/4" dia M.S.rods at
3" centres both ways.

1 C.ft 138 metal ( 3/4") 8830 88.30


1/2 C.ft 197 Sand 2100 10.50
0.20 Cwt 46 Cement 520 104.00
0.05 cwt 249 Steel rods 4330 216.50

Analysis 1st half - Mullaitivu


Page 122

413 Allow for binding wire use of moulds etc. 50 50.00


1/2 hour 214 Smith 475 29.69
2 hour 257 Mate (labour) 325 81.25
2 hour 214 Mason 475 118.75 698.99
Over heads 97.86
Per No 796.85
Say Rs 797.00
Per 4 sq.ft (per no) 797.00
Per sq.ft 199.25
Say Rs 199.00

26/249 Wire dome for 2" pipe supplied and fixed

1 No 270 Dome for 2" pipe 60 60.00


0.25 Hrs 214 Plumber 475 14.84 74.84
Over heads 10.48
Per no 85.32
Say Rs 85.00

1/D 110mm PVC inspection joint supplied and fixed

1 No 162 110mm PVC inspection joint 367.5 367.50


0.5 Hrs 214 Plumber 475 29.69
0.5 Hrs 257 Labourer 325 20.31
413 Allow for solvent cement 50 50.00 467.50
Over heads 65.45
Per No 532.95
Say Rs 533.00

2/D 110mm PVC inspection "Y" joint supplied and fixed


1 No 163 110mm PVC "Y" inspection joint 436 436.00
0.5 Hrs 214 Plumber 475 29.69
0.5 Hrs 257 Labourer 325 20.31
Allow for solvent cement 50 50.00 536.00
Over heads 75.04
Per No 611.04
Say Rs 611.00

3/D 110mm PVC Bend ( 11 Deg.) supplied and fixed


1 No 164 110mm PVC Bend ( 11 Deg.) 115.5 115.50
0.5 Hrs 214 Plumber 475 29.69
0.5 Hrs 257 Labourer 325 20.31
Allow for solvent cement 50 50.00 215.50
Over heads 30.17
Per No 245.67
Say Rs 246.00

No Qty Unit Code Description Unit Rate Rate Amount


4/D 110mm PVC Bend ( 22 Deg.) supplied and fixed

1 No 165 110mm PVC Bend ( 22 Deg.) 119 119.00


0.5 Hrs 214 Plumber 475 29.69
0.5 Hrs 257 Labourer 325 20.31
Allow for solvent cement 50 50.00 219.00
Over heads 30.66
Per No 249.66
Say Rs 250.00

Analysis 1st half - Mullaitivu


Page 123

5/D 110mm PVC Bend ( 60 Deg.) supplied and fixed

1 No 166 110mm PVC Bend ( 60 Deg.) 199.5 199.50


0.5 Hrs 214 Plumber 475 29.69
0.5 Hrs 257 Labourer 325 20.31
Allow for solvent cement 50 50.00 299.50
Over heads 41.93
Per No 341.43
Say Rs 341.00

6/D 110mm PVC Bend ( 88 Deg.) supplied and fixed

1 No 167 110mm PVC Bend ( 88 Deg.) 325.5 325.50


0.5 Hrs 214 Plumber 475 29.69
0.5 Hrs 257 Labourer 325 20.31
Allow for solvent cement 50 50.00 425.50
Over heads 59.57
Per No 485.07
Say Rs 485.00

7/D 110mm PVC "T" Junction supplied and fixed

1 No 364 110mm PVC "T" Junction 552.5 552.50


0.5 Hrs 214 Plumber 475 29.69
0.5 Hrs 257 Labourer 325 20.31
Allow for solvent cement 50 50.00 652.50
Over heads 91.35
Per No 743.85
Say Rs 744.00

8/D 110mm PVC "Y" Joint supplied and fixed

1 No 365 110mm PVC "Y" Joint 525 525.00


0.5 Hrs 214 Plumber 475 29.69
0.5 Hrs 257 Labourer 325 20.31
Allow for solvent cement 50 50.00 625.00
Over heads 87.50
Say Rs 713.00

No Qty Unit Code Description Unit Rate Rate Amount


9/D 50mm Bottle trap supplied and fixed
1 No 366 50mm Bottle trap 165 165.00
0.5 Hrs 214 Plumber 475 29.69
0.5 Hrs 257 Labourer 325 20.31
Allow for solvent cement 50 50.00 265.00
Over heads 37.10
Say Rs 302.00

10/D 110mm PVC Inspection bend supplied and fixed

Analysis 1st half - Mullaitivu


Page 124

1 No 367 110mm PVC Inspection Bend 388.5 388.50


0.5 Hrs 214 Plumber 475 29.69
0.5 Hrs 257 Labourer 325 20.31
Allow for solvent cement 50 50.00 488.50
Over heads 68.39
Say Rs 557.00

11/D 63mm PVC "Y" Joint supplied and fixed

1 No 63mm PVC "Y" Joint 0 0.00


0.5 Hrs 214 Plumber 475 29.69
0.5 Hrs 257 Labourer 325 20.31
414 Allow for solvent cement 25 25.00 75.00
Over heads 10.50
Say Rs 86.00

12/D 110mm PVC Elbow supplied and fixed

1 No 369 110mm PVC Elbow 301 301.00


0.5 Hrs 214 Plumber 475 29.69
0.5 Hrs 257 Labourer 325 20.31
413 Allow for solvent cement 50 50.00 401.00
Over heads 56.14
Say Rs 457.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU


MISCELLANEOUS
No Qty Unit Code Description Unit Rate Rate Amount
6/251 Fence barbed wire ,14 gauge,
4 points, 3" sparts, supplied and fixed in
existing timber posts with G.I staples.
Per 100.0 L.ft.

100 L.ft 20 Barbed wire 2.5 250.00

Analysis 1st half - Mullaitivu


Page 125

1 Doz 225 Staples 20 20.00


1 Hr 214 Fitter 475 59.38
1 Hr 257 Labourer 325 40.63 370.00
14% Over Heads 51.80
Per 100.0 L.ft 421.80
Per L.ft 4.22
Say Rs. 4.20
Per L.m 13.84
Say Rs. 13.80

15/253 Intermediate fence posts or structs, cement


concrete 1:1 1/2:3(3/4") reinforced with
4 Nos. 1/4 dia. M.S.rods 5'-7" high square
section 4" to 6" fixed complete as per
drawing No.68 of 22.07.1936.
Per Post
1 Cu.ft 138 3/4" Metal 8830 88.30
0.5 Cu.ft 197 Sand 2100 10.50
0.25 Cwt 46 Cement 520 130.00
0.04 cwt 140 1/4" rods 4240 169.60
0.5 Ibs 31 14 B.W.G wire 40 20.00
1 hr 214 Black smith cutting rods and bind wire 475 59.38
1 hr 214 Mason, cleaning moulds filling and removing 475 59.38
2 hrs 257 Labourer assisting mason 325 81.25
414 Allow for moulds 25 25.00
414 Allow for curing 25 25.00
0.5 hr 257 Fixing in ground 2 labours 325 40.63 709.03
14% Over heads 99.26
Per Post 808.29
Say Rs 808.00
16/253 - do - - do - 7'6" high - do -.
Per Post.
1.25 C.ft 138 3/4" Metal 8830 110.38
0.625 C.ft 197 Sand 2100 13.13
0.34 Cwt 46 Cement 520 176.80
0.04 cwt 140 1/4" rods 4240 169.60
0.75 Ibs 31 14 B.W.G wire 40 30.00
Labour & mould etc as in item 15 290.63 290.63 790.53
14% Over heads 110.67
Per Post 901.20
Say Rs 901.00

No Qty Unit Code Description Unit Rate Rate Amount


17/253 End post and strut for Type barbed wire
fence fixed complete in cement concrete
as per Drg. 68 of 1936.
Per set
7 Cu.ft 135 1 1/2" Metal 8020 561.40
3.25 Cu.ft 138 3/4" Metal 8830 286.98
6 Cu.ft 197 Sand 2100 126.00
1.75 Cwt 46 Cement 520 910.00
0.32 Cwt 140 M.S.rods 4240 1,356.80

Analysis 1st half - Mullaitivu


Page 126

1 Ib 31 14 B.W.G wire 40 40.00


3 hrs 214 Black smith 475 178.13
3 hrs 214 Mason 475 178.13
6 hrs 257 Labourer 325 243.75
414 Allow for moulds 25 25.00
414 Allow for curing 25 25.00
1/3 hrs 257 Labour - excavation foundation 325 13.54
2 hrs 214 Mason 475 118.75
4 hrs 257 Labour - planning posts 325 162.50 4,225.97
14% Over heads 591.64
Per Post 4,817.60
Say Rs 4,818.00

No Qty Unit Code Description Unit Rate Rate Amount


18/254 Fence barbed wire, 7 strands 14
B.W.G with 4 points at 3" centres and
R.C.C posts (1:2:4) 3/4" metal reinforced
with 4 Nos. 1/4 rods with 14 B.W.G
stirrups at 8" centres including post to
be fixed at 8'-0 crs' excavation cement
concrete foundation '1:3:6(1 1/2") metal
to corner posts and 'structs and straining
bolts, all as per type 'plan 68 of

Analysis 1st half - Mullaitivu


Page 127

22.07.1936 structs to be 'reinforced


with 4 Nos. 3/8" rods and 'corner posts
with 4 Nos. 1/2" rods. ( including
white washing 2 coats)
Per 100.0 L.ft (with corner post).

End post and strut as in item 17 4,225.97 4,225.97


12 Nos. Intermediate post - do - 15 709.03 8,508.30
700 L.ft 20 Barbed wire 2.5 1,750.00
75 Nos. 76a G.I.Hook bolts 6.5 487.50
1 day 214 Fitter 475 475.00
1 day 257 2 Labourers 325 650.00
add for 1 strut.
0.1 cwt 140 Steel 4240 424.00
1 Cu.ft 138 3/4" Metal 8830 88.30
2/5 Ibs 31 Wire 14 BWG 40 16.00
1 Cu.ft 135 1 1/2" Metal 8020 80.20
1 Cu.ft 197 Sand 2100 21.00
0.44 Cwt 46 Cement 520 228.80
Labourer and moulds as in Item 15 290.63 290.63
0.5 hr 214 Mason 475 29.69
0.5 hr 257 2 Labourers 325 40.63
7 Nos. 224 Straining bolts 112 784.00
1.5 Sqr White washing 104.90 157.35 18,257.35
14% Over heads 2,556.03
Per 100.0 L.ft 20,813.38
Per L.ft 208.13
Say Rs 208.00
Per L.m 682.68
Say Rs 683.00

18A/254 - Do - - do - - do -
- do - 8 Strands - do - - do -
- do - - do - - do -
Per 100 L.ft
As in Item no 18 18,257.35 18,257.35
100 L.ft 20 Barbed wire 2.5 250.00
1 No 224 Straining balts 112 112.00
11 No 76a G I hooks 6.5 71.50
2.5 Hrs 257 Labourer 325 101.56 18,792.42
Overheads 2,630.94
Per 100 L.ft 21,423.36
Per L.ft 214.23
Say Rs 214.00
Per L.m 702.69
Say Rs 703.00

No Qty Unit Code Description Unit Rate Rate Amount


19/254 Straining Bolts 1/2" dia made and fixed
18" long (Approx).

0.01 cwt 249 1/2" rods 4330.00 43.30


1 No 264 1/2" Nut & Washers 3.00 3.00
2 hrs 215 Blacksmith 475.00 118.75
2 hrs 257 Labour 325.00 81.25
417 Allow for coal etc. 10.00 10.00 256.30
14% Over heads 35.88

Analysis 1st half - Mullaitivu


Page 128

Per No 292.18
Say Rs 292.00

21/255 Well, bailing out water 5' to 7' dia. Upto


20' depth including cleaning well.
Say 5'-0" depth of water
3 hrs 257 4 Labourers (1 1/2 day ) 325.00 487.50 487.50
14% Over heads 68.25
Per 5 L.ft 555.75
Per L.ft depth 111.15
Say Rs 111.00

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU


ANGLE IRON
No Qty Unit Code Description Unit Rate Rate Amount
1/A Supplying and fixing 50mmx50mmx6mm thick
Angle iron purlin fixed to wall at not exeeding
900mm centres and joints should be bolted with
2Nos 12mm dia bolts and nuts other site welding
with cleats minimum length 450mm in next reduced
angle iron including two coats of Anticorrosive paint

Analysis 1st half - Mullaitivu


Page 129

as directed & including anchoring purlins with 2 nos


10mm tor steel welded to purlins where ever necessary and
with 1:2:4 concreting.
Per 100 L.ft
100 L.ft 344 2"x2"x1/4" Angle iron 85 8,500.00
7.5 l.ft 345 1'-6" long 1 1/2"x1 1/2"x1/4" Angle iron 56.5 423.75
Cutting
0.25 Day 215 Blacksmith 475 118.75
0.25 Day 257 Labourer 325 81.25
10 Nos 352 1/2"x1" Bolts & Nuts with washer 6 60.00
10 Nos 348 Making holes 20 200.00
Hoisting & Placing
0.5 Day 215 Blacksmith 475 237.50
0.5 Day 257 Labourer 325 162.50
0.70 Sqr Two coats of Anticorrosive paint 540.51 378.35
413 Transport and Scaffolding cost 50 50.00
Welding charge with electricity 300.00
Allow for concreting etc(25% of men) 100.00 10,612.10
14% Overheads 1,485.69
Per 100 L.ft 12,097.80
Per L.ft 120.98
Say Rs 121.00
Per L.m 396.81
Say Rs 397.00
2/A 62.5mmx62.5mmx6mm Angle iron purlin
-'do- -do-
Per 100 L.ft
100 L.ft 346 2 1/2"x2 1/2"x1/4" Angle iron 102.5 10,250.00
7.5 l.ft 344 1'-6" long 2"x2"x1/4" Angle iron 85 637.50
Cutting
0.25 Day 215 Black smith 475 118.75
0.25 Day 257 Labourer 325 81.25
10 Nos 352 1/2"x1" Bolts & Nuts with washer 6 60.00
10 Nos 348 Making holes 20 200.00
Hoisting & Placing
0.5 Day 215 Black smith 475 237.50
0.5 Day 257 Labourer 325 162.50
0.9 Sqr Two coats of Anticorrosive painting 540.51 486.45
413 Transport and scaffolding cost 50 50.00
Allow for concreting etc(25% of men) 100.00
Welding charge with electricity 300.00 12,683.95
14% overheads 1,775.75
Per 100 L.ft 14,459.71
Per L.ft 144.60
Say Rs 145.00
Per L.m 474.28
Say Rs 474.00
No Qty Unit Code Description Unit Rate Rate Amount
3/A 75mm x 75mm x 6mm Angle Iron purlin
-do- -do-
100 L.ft 347 75mmx75mmx6mm Angle Iron 125 12,500.00
7.5 l.ft 346 1" -6" long 62.5mmx62.5mmx6mm Angle Iron 102.5 768.75
Cutting
3 Hrs. 215 Black Smith 475 178.13
3 Hrs. 257 Labourer 325 121.88
10 Nos. 352 1/2" x 1" Bolts & Nuts with washer 6 60.00
10 Nos. 348 Making holes 20 200.00

Analysis 1st half - Mullaitivu


Page 130

Hoisting & placing


0.5 Day 215 Black smith 475 237.50
0.5 Day 257 Labourer 325 162.50
1.0 Sqr. Two coats of Anticorrosive painting 540.51 540.51
413 Transport and Scaffolding cost 50 50.00
Allow for concreting etc(25% of men) 100.00
411 Welding charge cost with electricity 300 300.00 15,219.26
Add 14% 2,130.70
Per 100 l.ft cost 17,349.95
Per L.ft. 173.50
Say Rs. 173.00
Per L.m. 569.08
Say Rs. 569.00

4/A End Truss-2/50mm x 50mm x 6mm


Per 7'-0" including 1:2:4(3/4) concreting 2nos
12mm dia 9" long welded to end truss
with 2 coats of anticorrosive paint
14 L.ft. 344 2/7' -0" - 50mm x 50mm x 6mm Angle iron 85 1,190.00
0.02 cwt 249 12mm dia 9" long Tor steel rods. 4330 86.60
2.25 L.ft. 344 0'-9" long cleats 50mm x 50mm x 6mm 85 191.25
Cutting
0.25 Day 215 Black Smith 475 118.75
0.25 Day 257 Labourer 325 81.25
Hoisting & Placing
Allow for hoisting 60 60.00
0.1 Sqr. Two coats of Anticorrosive painting 540.51 54.05
413 Transport and Scaffolding cost 50 50.00
411 Welding charge cost with electricity 300 300.00
allow for 1:2:4(3/4") con. Etc 100 100.00 2,231.90
Add 14% 312.47
Per 7 L.ft cost 2,544.37
Per L.ft 363.48
Say Rs. 363.00
Per L.m 1,192.22
Say Rs. 1,192.00

No Qty Unit Code Description Unit Rate Rate Amount


5/A End Truss-2/62.5mm x 62.5mm x 6mm
-do- -do-
Per 7'-0"
14 L.ft. 346 2/7' -0" - 62.5mm x 62.5mm x 6mm Angle iron 102.5 1,435.00
As in Item no 4/A 1,041.90 1,041.90 2,476.90
Add 14% 346.77
Per 7 L.ft cost 2,823.67
Per L.ft 403.38
Say Rs. 403.00

Analysis 1st half - Mullaitivu


Page 131

per l.m 1,323.09


Say Rs. 1,323.00

6/A End Truss-2/75mm x 75mm x 6mm


-do- -do-
Per 7'-0"
14 L.ft. 347 2/7' -0" - 75mm x 75mm x 6mm Angle iron 125 1,750.00
As in Item no 4/a 1,041.90 1,041.90 2,791.90
Add 14% 390.87
Per 7 L.ft cost 3,182.77
Per L.ft 454.68
Say Rs. 455.00
Per L.m 1,491.35
Say Rs. 1,491.00

7/A 25mm x 6mm - Flat Iron - 1'-0" long


weld to end purlin as bracket to fix valance
board with two coats of anticorrosive paint
& bolts & nuts
Per 50 Nos.

50 l.ft 351 1'-0" long 1"-1/4" flat iron 15 750.00


Cutting and making holes
0.5 Day 215 Black Smth 475 237.50
0.5 Day 257 Labourer 325 162.50
Hoisting & Placing
Welding charge including electricity 300 300.00
Transport and scaffolding cost 50 50.00
0.1 Sqr. Two coats of Anticorrosive painting 540.51 54.05
50 nos allow for bolts & nuts 5.00 250.00 1,804.05
Add 14% 252.57
Per 50 Nos. cost 2,056.62
Per No. 41.13
Say Rs. 41.00

8/A 31mm x 6mm - Flat Iron - 1'-0" long


- do- -do-
Per 50 Nos.
50 l.ft 374 1'-0" long 1 1/4"x1/4" flat iron 22.00 1,100.00
As in Item No 7/A 1054.05 1,054.05 2,154.05
Add 14% 301.57
Per 50 Nos. cost 2,455.62
Per No. 49.11
Say Rs. 49.00

No Qty Unit Code Description Unit Rate Rate Amount


9/A 2/3" x 3" x 1/4"(2/75mm x 75mm x 6mm)
angle iron slope beam including 1:2:4(3/4")
concreting with 2 nos 16mm 9" long with
2 coats of anticorrosive painting rag bolt
fixed to base plate 9"x9"x10mm & 9" long
necessary cleats
Per 20'

40 L.ft 347 (2/20'-0") double Angle Iron ( 75 x 75 x 6 ) 125 5,000.00

Analysis 1st half - Mullaitivu


Page 132

3.5 l.ft 347 0'-6" long cleats 3" x 3" x 1/4" 125 437.50
2 Nos. 376 9" x 9" 3/8" M.S.base plate 110 220.00
4 Nos. 96a 16 mm 9" Rag bolt 140 560.00
Cutting
0.5 Day 215 Black Smith 475 237.50
0.5 Day 257 Labourer 325 162.50
Hoisting & Placing

0.5 Day 257 Labourer 325 162.50


1.50 Sqr. Two coats of Anticorrosive paint 540.51 810.76
Transport and scaffolding cost 50.00 50.00
Welding charge cost with electricity 300 300.00 7,940.76
Add 14% 1,111.71
Per 20 l.ft cost 9,052.46
Per L.ft 452.62
Say Rs. 453.00
Per L.m 1,484.60
Say Rs. 1,485.00

10/A Supplying & fixing 'H' iron 6" x 3" 6mm


with necessary cleats to housing props
including 2 coats of anticorrosive painting
Per 16'-0"

19.5 L.ft H' Iron #N/A #N/A


Cutting and welding cleasts
3 hr 215 Black Smith 475 1,425.00
3 hr 257 Labourer 86.00 258.00
Hoisting & placing
0.25 Day 257 2 'Labourer 325 81.25
Welding charge with electricity 300 300.00
0.40 Sqr. Two coats of Anticorrosive painting 540.51 216.20 #N/A
Add 14% #N/A
Per 16 L.ft cost #N/A
Per l.ft #N/A
Say Rs. #N/A
Per L.m #N/A
Say Rs. #N/A

No Qty Unit Code Description Unit Rate Rate Amount


11/A Supplying & fixing ' H ' Iron 8" x 4"
(6mm) with necessary cleats
-do -
Per 16'-0"
19.5 L.ft. 350 H ' Iron 0 0.00
Cutting and welding
0.5 Day 215 Black smith 475 237.50
0.5 Day 257 Labourer 325 162.50
Hoisting & placing

Analysis 1st half - Mullaitivu


Page 133

0.25 Day 257 2 'Labourer 325 162.50


Welding charge with electricity 300 300.00
0.5 Sqr. Two coats of Anticorrosive painting 540.51 270.25 1,132.75
Add 14% 158.59
Per 16 L.ft cost 1,291.34
Per L.ft 80.71
Say Rs. 81.00
Per L.m 264.72
Say Rs. 265.00

GATE WITH PILLARS

No Qty Unit Code Description Unit Rate Rate Amount


12/A G.I. Gate with 12'-0" x 4'-6" hight 2 Nos sashes made
out of 1 1/2" dia G.I. heavy quality frame with
6mm M.S. rod welded 3" c/c both ways all as per
Drg. No. 409853 fixed with 9" x 9" RCC pillar in
1:2:4(3/4") concrete 4Y12 reinforced and R6 at 6" crs.
stirrups rate include for Excavation base concrete
footing R/F with
Y10 @ 8" c/c both way 5/8" thick 1:4 plastering 4 Nos. pintol
and stirrups locking divice barrel bolt etc. and 2 coats
Anticorrosive paint and 2 coats enamel paint
& 2 coats ofwhite washing to pillers as directed
Per Pillar

0.32 Cube Excavation 622.00 199.04


0.13 Sqr. Lean concrete 1:3:6 (1") 5,338.25 693.97
0.04 Cube Footing concrete 1:2:4 (3/4") 25,416.00 1,016.64
0.07 Cube Column concrete 1:2:4 (3/4") 25,416.00 1,779.12
0.36 Sqr. Shuttering 5,979.78 2,152.72
0.17 Cwt. Footing 10mm tor steel 6,159.00 1,047.03
0.34 Cwt. Shaft 12mm tor steel 6,387.00 2,171.58
0.09 Cwt. Reinforcement (M.S. Rods) 6,275.00 564.75
0.36 Sqr. Plastering 1,681.00 605.16
0.36 Sqr. Colour washing 208.00 74.88
10,304.89
per pillars 10,305.00
2 Nos. Pillars 20,610.00
Allow for 'Painting 700.00
Allow'Fixing Charges 300.00
Gate sash (12'-0" x 4'-6")
14% Overheads for Gate only 0.00
* 0.00
say per 2 pillars 21,610.00
Say Rs.

RATE ANALYSIS FIRST HALF OF 2004 IN MULLAITIVU


ALUMINIUM WORK
No Qty Unit Code Description Unit Rate Rate Amount
Labour Distribution for aluminium work
Per 10 S.ft
0.75 Day 215 Sp.skilled Labourer 475 356.25
1 Day 257 Un skilled labourer 325 325.00
Per 10 S.ft 681.25
Labour rate per S.ft 68.13

Analysis 1st half - Mullaitivu


Page 134

1/AL Aluminium Partition

Size 11' 0" x 7' 0" = 77 S.ft


39.6 L.ft 385 Mian frame 70S-3002-1 85 3,366.00
8.8 L.ft 399 Mild frame PT-5157 56.3 495.44
27.5 L.ft 400 2" x 1" Box iron P-1113 40.75 1,120.63
32 S.ft 405 5mm Tintaed glass 60 1,920.00
52.8 S.ft 406 6mm Plywood (Marin) 20.85 1,100.88
52.8 S.ft 407 Formica sheet 18 950.40
35.2 L.ft 388 Glass beading 100D - 1917 32.8 1,154.56
35.2 L.ft 387 Glass beading 100D - 1914 24.3 855.36
17.6 L.ft 398 Beading bottom PT - 5154 30.5 536.80
19.8 L.ft 397 M.Channel beading PT - 5153 12.8 253.44
Door
15.4 L.ft 384 Vertical frame 70S - 1704 - A 79.4 1,222.76
3.3 L.ft 401 Mild frame 80S-1801 57.85 190.91
3.3 L.ft 383 Bottom Horri 70S - 1503 - A 78.1 257.73
3.3 L.ft 382 Top Horri 70S -1402 - 1 52.9 174.57
7.7 L.ft 379 Top rail 70S - 1002 -1 64.6 497.42
7.7 L.ft 380 Bottom rail 70S - 1102 - 1 44.5 342.65
7.7 L.ft 381 Lock vertical rail 70S - 1202 - 1 46.4 357.28
9.9 S.ft 406 6mm plywood sheet 20.85 206.42
13.2 S.ft 405 5mm Tinted glass 60 792.00
19.8 S.ft 407 Formica sheet 18 356.40
1.0 No 403 Lock alfa 750 750.00
Allow for rubber gacscut reverd brass screws,
celicone sealent etc. 10% 1,690.16

77 Sft Labourer 68.13 5,245.63 23,837.42


Overheads 3,337.24
Per 77 Sq.ft 27,174.66
Per Sq.ft 352.92
Say per S.ft 353.00
Say per m2 3,797.00

No Qty Unit Code Description Unit Rate Rate Amount


2/AL Aluminium Casement with project

Size 4' 0"x5' 6" = 22 S.ft


20.9 L.ft 394 Side frame CA - 1001 84.3 1,761.87
10.45 L.ft 395 Midle frame CA - 1002 134.2 1,402.39
41.8 L.ft 396 Sash frame CA-2001-A 88.9 3,716.02
41.8 L.ft 387 Beading 100D-1914 24.3 1,015.74
24.2 S.ft 405 Tinted glass 5mm 60 1,452.00
Allow for bar hinges, selicone rubber
gasscut brass screws riveres etc. 10% 934.80

Analysis 1st half - Mullaitivu


Page 135

22 S.ft Labourer 68.13 1,498.75 11,781.57


Overheads 1,649.42
Per 22 S.ft 13,430.99
Per S.ft 610.50
Say Per S.ft 610.00
Say per m2 6,569.00

3/AL Aluminium Door frame only

Size 7'-0" x 3'-0" = 21 S.ft


18.7 L.ft 385 Side frame 70S - 3002 - 1 85 1,589.50
11.0 L.ft 386 Beading 70D - 1910 24.3 267.30
Allow for revert 10% 185.68
0.75 Day 215 Sp.skilled Labourer 475 356.25
0.75 Day 257 Un skilled Labourer 325 243.75 2,642.48
14% Overhead 369.95
Per 21 Sft 3,012.43
Per Sft 143.45
Say per S.ft 143.00
Say per m2 1,544.00

4/AL Aluminium door fully glazed double hung

Size 6' 6"x 5' 0" = 32.5 Sq.ft


14.3 L.ft 392 Side vertical member 100D - 3502 148.7 2,126.41
14.3 L.ft 393 Vertical lock member 100D - 3503-A 160.9 2,300.87
5.5 L.ft 391 Bottom rail member 100D-3207 169 929.50
5.5 L.ft 390 Top rail member 100D-3203 129.1 710.05
5.5 L.ft 389 Mid lock rail 100D-3004-A 124.5 684.75
50.6 L.ft 387 Beading 100D-1914 24.3 1,229.58
1.0 No 403 Lock 750 750.00
2 Pair 402 Handle 350 700.00
2 No 404 Door closer 1645 3,290.00
35.75 S.ft 405 5mm glass 60 2,145.00
19.8 L.ft 385 Door frame 70S - 3002 - 1 85 1,683.00
19.8 L.ft 386 Beading 70D - 1910 24.3 481.14
Allow 10% 1,703.03
32.5 S.ft Labourer 68.13 2,214.06 20,947.39
14% Overhead 2,932.63
Per 32.5 S.ft 23,880.03
Per S.ft 734.77
Say per S.ft 735.00
Say per m2 7,906.00

No Qty Unit Code Description Unit Rate Rate Amount


5/AL Al Double hung Door with panneled and
glazed

Size 6' 6" x 5' 0" = 32.5 Sq.ft


14.3 L.ft 392 Side vertical member (sash) 100D - 3502 148.7 2,126.41
14.3 L.ft 393 Vertical lock member 100D - 3503 A 160.9 2,300.87
5.5 L.ft 391 Bottom rail 100D - 3207 169 929.50
5.5 L.ft 390 Top rail 100D - 3203 129.1 710.05
5.5 L.ft 389 Mild Lock rail 100D - 3004 A 124.5 684.75
50.6 L.ft 387 Bead 100D - 1914 24.3 1,229.58

Analysis 1st half - Mullaitivu


Page 136

1.0 No 403 Lock (alpha) 750 750.00


2 Pair 402 Handle 350 700.00
2 No 404 Door closer 2 nos. 1645 3,290.00
19.25 S.ft 405 5mm glass tinted 60 1,155.00
16.5 S.ft 406 6mm plywood 20.85 344.03
33 S.ft 407 Formica 18 594.00
19.8 L.ft 385 Door frame 70S - 3002 - 1 85 1,683.00
19.8 L.ft 386 Beading 70D- 1910 24.3 481.14
Allow for rivets, gasscut, rubber brass screws
Doorhinges silicone tie rods etc.( 10%) 1,697.83
32.5 S.ft Labourer 68.13 2,214.06 20,890.22
14% Overheads 2,924.63
Per 32.5 Sq.ft. 23,814.85
Per S.ft 732.76
Say per S.ft 733.00
Say per m2 7,885.00

6/AL Al single hung Door with fully glazed

Size 6' 6" x 3' 3" = 21.12. Sq.ft.

7.15 L.ft 392 Side vertical member (sash) 100D - 3502 148.7 1,063.21
7.15 L.ft 393 Vertical lock member 100D - 3503 A 160.9 1,150.44
3.57 L.ft 391 Bottom rail 100D - 3207 169 603.33
3.57 L.ft 390 Top rail 100D - 3203 129.1 460.89
3.57 L.ft 389 Mid Lock rail 100D - 3004 A 124.5 444.47
28.6 L.ft 387 Bead 100D - 1914 24.3 694.98
1 No 403 Lock (alpha) 750 750.00
1 Pair 402 Handle 350 350.00
1 No 404 Door closer 1645 1,645.00
23.24 S.ft 405 5mm glass tinted 60 1,394.40
17.87 L.ft 385 Door frame 70S - 3002 - 1 85 1,518.95
17.87 L.ft 386 Beading 70D- 1910 24.3 434.24
Allow 10% for rivets, gascut, rubber brass screws 1,050.99
21.12 S.ft Labour 68.13 1,438.80 12,999.68
14% Overheads 1,819.96
Per 21.12 Sq.ft. 14,819.64
Per Sft 701.69
Say per S.ft 702.00
Say per m2 7,550.00

No Qty Unit Code Description Unit Rate Rate Amount


7/AL Al Single hung Door with panneled and
glazed

Size 6' 6" x 3' 3" = 21.12. Sq.ft.


7.15 L.ft 392 Side vertical member (sash) 100D - 3502 148.7 1,063.21
7.15 L.ft 393 Vertical lock member 100D - 3503 A 160.9 1,150.44
3.57 L.ft 391 Bottom rail 100D - 3207 169 603.33
3.57 L.ft 390 Top rail 100D - 3203 129.1 460.89
3.57 L.ft 389 Mild Lock rail 100D - 3004 A 124.5 444.47
28.6 L.ft 387 Bead 100D - 1914 24.3 694.98

Analysis 1st half - Mullaitivu


Page 137

1 No 403 Lock (alpha) 750 750.00


1 Pair 402 Handle 350 350.00
1 No 404 Door closer 2 nos. 1645 1,645.00
12.51 S.ft 405 5mm glass tinted 60 750.60
10.72 S.ft 406 6mm plywood 20.85 223.51
21.45 S.ft 407 Formica 18 386.10
17.87 L.ft 385 Door frame 70S - 3002 - 1 85 1,518.95
17.87 L.ft 386 Beading 70D- 1910 24.3 434.24
Allow for rivets, gasscut, rubber brass screws
Doorhinges silicone tie rods etc.( 10%) 1,047.57
21.12 S.ft Labourer 68.13 1,438.80 12,962.08
14% Overheads 1,814.69
Per 21.12 Sq.ft. 14,776.77
Per S.ft 699.66
Say per S.ft 700.00
Say per m2 7,528.00

49 Channels 2" semi-circular, formed in


7 cement concrete floors and 1/2" cement
rendered 1:2 (extra over concrete floors).

Per 10 L.ft.

2 Hour 214 Mason 475.00 118.75


1 Hour 257 Labourer 325.00 40.63
Allow for cement and sand 100.00 259.38
Over heads 36.31

Analysis 1st half - Mullaitivu


Page 138

Per 10 L.ft 295.69


Per L.ft 29.57
Say per L.ft. :- 23/10 30.00
Per L.m. 98.40
Say per L.m. :- 76/= 98.00

50 Channels 4" - do -
8 - do - - do -.

Per 10 L.ft.

4 Hour 214 Mason 475.00 237.50


2 Hour 257 Labourer 325.00 81.25
Allow for cement, sand etc 100.00 418.75
Over heads 58.63
Per 10 L.ft 477.38
Per L.ft 47.74
Say per L.ft. :- 34.80 48.00
Per L.m. 157.44
Say per L.m. :- 114/= 157.00

51 Curb in cement concrete 1:2:4 (3/4") 9"


10 heigh and 3" thick, cement rendered 1/2"
thick including excavation.

Per 10.0 L.ft

2 Cu.ft Materials for concrete as in Item 47 184.10 368.20


1/8 Cwt 46 Cement for 7 1/2 S.ft rendering 520.00 65.00
Allow for sand for rendering 100.00 100.00
1 Day 214 Mason 475.00 475.00
1 Day 257 Labourer #N/A #N/A
Allow for shuttering, excavation,curing etc 150.00 150.00 #N/A
Over heads #N/A
Per 10 L.ft #N/A
Per L.ft #N/A
Say per L.ft. :- 125/= #N/A
Per L.m #N/A
Say per L.m. :- 410/= #N/A

97 Floors, brick paved, 3" thick, set in lime


3 mortar 2:5 and cement rendered 1/2",
1:2.

Per Sqrs.

350 No 41 Bricks 5.7 1,995.00


0.15 Cube 200 Sand 2100 315.00
1.7 Cwts 46 Cement 520 884.00
2 Day 214 Mason 475 950.00
4 Day 257 Labourer 325 1,300.00 5,444.00
Over heads 762.16
Per square 6,206.16

Analysis 1st half - Mullaitivu


Page 139

Say per Sqrs = 6,206.00


Per m2 668.03
Say per m2 :- 471/= 668.00

SECOND HALF OF 2001 IN MANNAR


ELECTRICAL.
1 Main switch (3 phase, 30 amp.).

1 No 131 Main switch 30 amp. 1 1.00


40 m 1000 7/.044 single core wire, 40m 82.00 32.80
35 Board 50 50.00
2 Nos. 339 Brass Screws 2"x10 #REF! #REF!
2 Nos. 340 Brass Screws 1"x6 #REF! #REF!
2 Meter 52a Conduit pipe 1" #REF! #REF!
0.5 day 257 Labour 325 162.50
1/2 day 214 Electrician 475 237.50 #REF!
Over heads #REF!
Per No #REF!
Say Rs #REF!

2 Main switch (60 Amp, 3 phase).

1 No 132 Main switch 60 Amp English 1 1.00


40 m 1001 7/0.064 Single core wire 40m #REF! #REF!
35 Board 50 50.00
2 Nos. 339 Brass Screws 2"x10 #REF! #REF!
2 Nos. 340 Brass Screws 1"x6 #REF! #REF!
2 Meter 52a Conduit pipe #REF! #REF!
1/2 day 257 labourer 325 162.50
1/2 day 214 Electrician 475 237.50 #REF!
Over heads #REF!
Per No #REF!
Say Rs #REF!

3 Earth wire

15 m 10 plug points #N/A #N/A


1 No 321 Earth pipe 2"x5' 43 43.00
1/2 day Electrician labourer #N/A #N/A #N/A
Over heads #N/A
Per No #N/A
Say Rs #N/A

Analysis 1st half - Mullaitivu


Page 140

4 Main switch single phase 30 Amp.

1 no 131 Main switch 30 Amp English 1 1.00


10 Meter 1000 7/0.044 wire 10m #REF! #REF!
1 Nos. 35 Board 50 50.00
2 Nos. 339 Screws 2"x10 #REF! #REF!
2 Nos. 340 Screws 1"x6 #REF! #REF!
2 Meter 52a Conduit pipe #REF! #REF!
1/2 day Electrician labourer #N/A #N/A #REF!
Over heads #REF!
Per No #REF!
Say Rs #REF!

5 15 Amp. Plug.

1 no 322 Plug with switch (clipsal) 43 43.00


25 m 323 3/.036 wire, 25 meters 43 1,075.00
2 No 336 Brass Screws (1 1/2"x6), #REF! #REF!
1 no 324 Sunk box 43 43.00
2 No 337 Brass Screws 1 1/2"x10" #REF! #REF!
15 m 326 Earth wire 7/.029 43 645.00
327 Wiring clips and panel pins (Allow) 43 43.00
2 m 52a Conduit pipe #REF! #REF!
1/2 day Electrician labourere #N/A #N/A #REF!
Over heads #REF!
Per No #REF!
Say Rs #REF!

6 Light Fitting.

1 no 328 Round plug 43 43.00


1 no 329 Ceiling rose 43 43.00
1 no 330 Holder 43 43.00
1 m 331 Flexible wire 43 43.00
2 No 336 Brass Screw 1/2"x6 #REF! #REF!
1 No 40a Brass Screw 1 1/2" 90 90.00
1 no 333 Switch clipsal 43 43.00
1 no 324 Sunk box 43 43.00
1 No Brass screw 2" 90 90.00
25 m 334 1/.044 wire 43 1,075.00
2 m 52a Conduit pipe #REF! #REF!
327 Wiring clips & pannel pins 43 43.00
1/2 day 214 Electrician 475 237.50 #REF!
Over heads #REF!
Per No #REF!
Say Rs #REF!

7 5 Amp. Plug.

1 Nos. 322 Plug with switch (Clipsal) 43 43.00


2 Nos. 336 Brass screws (1 1/2"x6) #REF! #REF!
1 Nos. 335 Sunk box #REF! #REF!

Analysis 1st half - Mullaitivu


Page 141

2 Nos. 337 Brass screws (1 1/2"x10) #REF! #REF!


25 m 334 1/.044 wire 43 10.75
15 m 326 Earth wire 7/.029 43 6.45
327 Wiring clips & panel pins 43 43.00
1 m 52a Conduit pipe #REF! #REF!
1/2 day 214 Electrician 475 237.50 #REF!
Over heads #REF!
Per No #REF!
Say Rs #REF!

8 Ceiling Fan (USHA).

1 no Ceiling fan 56" #N/A #N/A


1 no Hooks #N/A #N/A
1 no Light point #N/A #N/A
1/2 day 214 Electrician 475 237.50 #N/A
Over heads #N/A
Per No #N/A
Say Rs #N/A

9 Calling Bell.

1 no Bell #N/A #N/A


1 no Bell bush - Clipsal #N/A #N/A
1 no Round block #N/A #N/A
3 Nos. Brass screws 1 1/2" #N/A #N/A
1 no Sunk box #N/A #N/A
25 m 1/.044 wire #N/A #N/A
2 m 52a Conduit pipe #REF! #REF!
Wiring clips & panel pins #N/A #N/A
1/2 day 214 Electrician 475 237.50 #N/A
Over heads #N/A
Per No #N/A
Say Rs #N/A

10 ABC box 500 Type.


5 m 1000 7/.044 wire #REF! #REF!
2 m 52a Conduit pipe #REF! #REF!
2 Nos. Brass Screws 2"x10 #N/A #N/A
2 Nos. Brass Screws 1 1/4"x6 #N/A #N/A
1 Nos. ABC box 500 type #N/A #N/A
1 Nos. Board 10"x10" #N/A #N/A
1/2 day 214 Electrician 475 237.50 #REF!
Over heads #REF!
Per No #REF!
Say Rs #REF!

11 Trip switch (Single phase).

1 No Trip switch crab tree #N/A #N/A


1 No Board #N/A #N/A
2 Nos. Brass Screws 2"x10 #N/A #N/A
2 Nos. Brass Screws 1 1/4"x6 #N/A #N/A
2 m 52a Conduit #REF! #REF!

Analysis 1st half - Mullaitivu


Page 142

1/2 day 214 Electrician 475 237.50 #N/A


Over heads #N/A
Per No #N/A
Say Rs #N/A

12 Pendent lamp / Battern lamp.

1 No Light point #N/A #N/A


1 No Bulb #N/A #N/A #N/A
Over heads #N/A
Per No #N/A
Say Rs #N/A

13 Water light lamp.

1 No Light point #N/A #N/A


1 No Water tight lamp #N/A #N/A #N/A
Over heads #N/A
Per No #N/A
Say Rs #N/A

14 Flourscent lamp 4'-0".

1 No Light point #N/A #N/A


1 No 4'-0" Flourscent set #N/A #N/A #N/A
Over heads #N/A
Per No #N/A
Say Rs #N/A

15 Flourscent Lamp 2'-0".

1 No Light point #N/A #N/A


1 No Flourscent set #N/A #N/A #N/A
Over heads #N/A
Per No #N/A
Say Rs #N/A

16 Hood lamp.

1 No Light point #N/A #N/A


1 No Hood lamp #N/A #N/A #N/A
Over heads #N/A
Per No #N/A
Say Rs #N/A

17 Wall bracket lamp.

1 No Light point #N/A #N/A


1 No Bracket lamp #N/A #N/A #N/A
Over heads #N/A
Per No #N/A

Analysis 1st half - Mullaitivu


Page 143

Say Rs #N/A

18 ABC Box 700 type.

As per Item 10 #REF!


Less 500 type #N/A #REF!
Add 700 type #N/A #REF!
14% Over Heads #REF!
Per No #REF!
Say Rs #REF!

19 ABC Box 900 type.

As per Item 10 #REF!


Less 500 type #N/A #REF!
Add 900 type #N/A #REF!
14% Over Heads #REF!
Per No #REF!
Say Rs #REF!

286 Lanka ceremic (Dulex white)


??
Low level white comode with trap 1843 1,843.00
Cistern only 1375 1,375.00
Fittings 350 350.00
Seat cover 375 375.00
Brackets 54 54.00
Flash band 35.5 35.50
Brackets 26 26.00
Allow for Transport 100 100.00 4,158.50
Labourer as in Item 34 800.00
Over heads 582.19
Per No 4,740.69
Say Rs 4,741.00

287 Closet pedestal with cistern - do -.


34 ??? Indian make.

1 No 306 Low level closet suite 0 0.00


Allow for transport 50 50
1 no 227 1/2" stop cock Brass 105 105.00
Cement, Metal, Sand etc. (Item 31) 50 50.00
1 day 214 Plumber 475 475.00
1 day 257 Labourer 325 325.00 955.00
Over heads 133.70
Per No 1,088.70
Say Rs 1,089.00

Analysis 1st half - Mullaitivu


Page 144

289 Squatting closet 14% Indian made.

1 no 222 Squatting pan & trap 700 700.00


Allow for transport 50 50.00
as per Item 35 less closet 1,073.33 1,073.33 1,823.33
Over heads 255.27
Per No 2,078.60
Say Rs 2,079.00
290 Squatting closet square type.
As per Item 288 less squatting pan 1,073.33 1,073.33
1 No 307 Square type pan 0 0.00 1,073.33
Over heads 150.27
Per No 1,223.60
Say Rs 1,224.00

1 BARBED WIRE FENCE

Intermediate fence posts or structs, cement concrete


1:2 1/2:3 (3/4") reinforced with 4 Nos. 1/4 dia. M.S.rods
5'-7" high square section 4" to 6" fixed complete as
per drawing No. 68 of 22.07.1936.

Per Post

1 C.ft. 138 3/4" Metal 8830 88.30


0.5 C.ft. 197 Sand 2100 10.50
0.25 Cwt. 46 Cement 520 130.00
4 Hrs. 1/4" Rods #N/A #N/A
0.5 Lbs. 31 14 B.W.G. Wire 40 20.00
1 Hr. 214 Black Smith, cutting rods and tieying wire 475 59.38
1 Hr. 214 Mason, cleaningmoulds filing and removing 475 59.38
2 Hrs. 257 Labourer assisting Mason 325 81.25

Analysis 1st half - Mullaitivu


Page 145

Allow for Moulds 30 30.00


Allow for curing 30 30.00
0.5 hrs 257 Fixing in ground 2 Labourers 1/2 Hr. 325 40.63 #N/A
14% Overheads #N/A
Total cost #N/A
Say Rs.

2 End post and struct for Type barbed wire fence fixed
complete in cement concrete as per Drg. Of 68 of
1936
7 C.ft. 135 1 1/2" Metal 8020 561.40
3.75 C.ft. 138 3/4" Metal 8830 331.13
6 C.ft. 197 Sand 2100 126.00
1.75 Cwt. 46 Cement 520 910.00
0.32 Cwt. 140 M.S. Rods 4240 1,356.80
1 Lb. 31 14 B.W.G.Wire 40 40.00
3 Hrs. 214 Black Smith 475 178.13
6 Hrs. 257 Labourer 325 243.75
Allow formoulds 30 30.00
Allow for curing 30 30.00
0.5 Hrs. 257 Excavation foundation & Planting post 1/2 Hrs. 2 Lab 325 40.63 3,847.83
Overheads 538.70
Total cost 4,386.52
Say Rs.

3 Fence barbed wire 5 strands 12 1/2 B.W.G. with 4


points at 3" centres and R.C.C. posts (1:2:4)3/4"
metal reinforced with 4 Nos. 1/4 rods with 14 B.W.G.
stirrups at 8" centres post to be fixed at 8'-0" crs.
including excavation, cement concrete foundation
1:3:6(1 1/2") metal to corner posts and struts, and
straining bolts, all as per type plan 68 of 22.36 structs
to be reinforced with 4 Nos. 3/8" rods and corner
posts with 4 Nos. 1/2" rods.

Per 100 L.ft. (with corner post)

End post and strut as in item 2 3,847.83


12 No. Intermediate post - do - 1 #N/A
500 L.ft. 31 Barbed wire 40
55 No. 76a G.I. Hook bolts 6.5

3/4 Day 214 Fitter 475


3/4 Day 257 2 Labourers 325
Add for strut
11 Lbs. Steel #N/A
1 C.ft. 138 3/4" Metal 8830
2/5 Lbs. 31 Wire 40
1 C.ft. 135 1 1/2" Metal 8020
0.44 Cwt. 46 Cement 520
Labour and moulds
Concrete foundation

Analysis 1st half - Mullaitivu


Page 146

1/2 Hr. Mason #N/A


1/2 Hr. 2 Labourers #N/A
5 Nos. Straining bolts #N/A
1 Sqr. White washing 2 coats #N/A
Overheads
Per 100 L.ft.
Per L.ft.
Say Rs.
Per L.m.
Say Rs.

29 Waterproof Treatment of hot bitumen


38 taken off from flat roof and debris
cleared away.

Per Sqrs.

2 Day 257 Labourer 325.00 650.00 650.00


Over heads 91.00
Per square 741.00
Say per square :- 502/= 741.00
Per m2 79.76
Say per m2 :- 54/- 80.00

11 Tiles, Calicut pattern, flat supplied and


28 laid up to 5 tiles in Buildings of more
than 1 storey.

Per 3 tiles.

3 Nos. 70 Tiles 18 54.00


1 Hour 257 Labourer 325 40.63 94.63
Over heads 13.25
Per 3 tiles 107.87
Per tiles 35.96
Say Rs :- 23/- 36.00

12 Tiles, Calicut pattern, flat, supplied and


29 laid above 5 and up to 25 in Buildings
of more than 1 storey.

Per 15.0 tiles.

15 Nos 70 Tiles. 18 270.00


2 Hour 257 Labourer 325 81.25 351.25
Over heads 49.18
Per 15 tiles 400.43
Per tiles 26.70
Say per tile :- 16/- 27.00

208 Painting new wood work with approved

Analysis 1st half - Mullaitivu


Page 147

26 primer 1 coat.

0.756 Lit 190 Primer 1560 1,179.36


5 Hour 214 Painter preparing surface and painting 475 296.88
Allow for brushes etc 20 20.00 1,496.24
Over heads 209.47
Per square 1,705.71
Say Rs :- 606/- 1,705.00
Say per m2 151.00

Analysis 1st half - Mullaitivu


Page 148

Analysis 1st half - Mullaitivu


Page 149

Analysis 1st half - Mullaitivu


Page 150

Analysis 1st half - Mullaitivu


Page 151

Analysis 1st half - Mullaitivu


Page 152

Analysis 1st half - Mullaitivu


Page 153

Analysis 1st half - Mullaitivu


Page 154

Analysis 1st half - Mullaitivu


Page 155

Analysis 1st half - Mullaitivu


Page 156

Analysis 1st half - Mullaitivu


Page 157

Analysis 1st half - Mullaitivu


Page 158

Analysis 1st half - Mullaitivu


Page 159

Analysis 1st half - Mullaitivu


Page 160

Analysis 1st half - Mullaitivu


Page 161

Analysis 1st half - Mullaitivu


Page 162

Analysis 1st half - Mullaitivu


Page 163

Analysis 1st half - Mullaitivu


Page 164

Analysis 1st half - Mullaitivu


Page 165

Analysis 1st half - Mullaitivu


Page 166

Analysis 1st half - Mullaitivu


Page 167

Analysis 1st half - Mullaitivu


Page 168

Analysis 1st half - Mullaitivu


Page 169

Analysis 1st half - Mullaitivu


Page 170

Analysis 1st half - Mullaitivu


Page 171

Analysis 1st half - Mullaitivu


Page 172

Analysis 1st half - Mullaitivu


Page 173

Analysis 1st half - Mullaitivu


Page 174

Analysis 1st half - Mullaitivu


Page 175

Analysis 1st half - Mullaitivu


Page 176

Analysis 1st half - Mullaitivu


Page 177

Analysis 1st half - Mullaitivu


Page 178

Analysis 1st half - Mullaitivu


Page 179

Analysis 1st half - Mullaitivu


Page 180

Analysis 1st half - Mullaitivu


Page 181

Analysis 1st half - Mullaitivu


Page 182

Analysis 1st half - Mullaitivu


Page 183

Analysis 1st half - Mullaitivu


Page 184

Analysis 1st half - Mullaitivu


Page 185

Analysis 1st half - Mullaitivu


Page 186

Analysis 1st half - Mullaitivu


Page 187

Analysis 1st half - Mullaitivu


Page 188

Analysis 1st half - Mullaitivu


Page 189

Analysis 1st half - Mullaitivu


Page 190

Analysis 1st half - Mullaitivu


Page 191

Analysis 1st half - Mullaitivu


Page 192

Analysis 1st half - Mullaitivu


Page 193

Analysis 1st half - Mullaitivu


Page 194

Analysis 1st half - Mullaitivu


Page 195

Analysis 1st half - Mullaitivu


Page 196

Analysis 1st half - Mullaitivu


Page 197

Analysis 1st half - Mullaitivu


Page 198

Analysis 1st half - Mullaitivu


Page 199

Analysis 1st half - Mullaitivu


Page 200

Analysis 1st half - Mullaitivu


Page 201

Analysis 1st half - Mullaitivu


Page 202

Analysis 1st half - Mullaitivu


Page 203

Analysis 1st half - Mullaitivu


Page 204

Analysis 1st half - Mullaitivu


Page 205

Analysis 1st half - Mullaitivu


Page 206

Analysis 1st half - Mullaitivu


Page 207

Analysis 1st half - Mullaitivu


Page 208

Analysis 1st half - Mullaitivu


Page 209

Analysis 1st half - Mullaitivu


Page 210

Analysis 1st half - Mullaitivu


Page 211

Analysis 1st half - Mullaitivu


Page 212

Analysis 1st half - Mullaitivu


Page 213

Analysis 1st half - Mullaitivu


Page 214

Analysis 1st half - Mullaitivu


Page 215

Analysis 1st half - Mullaitivu


Page 216

Analysis 1st half - Mullaitivu


Page 217

Analysis 1st half - Mullaitivu


Page 218

Analysis 1st half - Mullaitivu


Page 219

Analysis 1st half - Mullaitivu


Page 220

Analysis 1st half - Mullaitivu


Page 221

Analysis 1st half - Mullaitivu


Page 222

Analysis 1st half - Mullaitivu


Page 223

Analysis 1st half - Mullaitivu


Page 224

Analysis 1st half - Mullaitivu


Page 225

Analysis 1st half - Mullaitivu


Page 226

Analysis 1st half - Mullaitivu


Page 227

Analysis 1st half - Mullaitivu


Page 228

Analysis 1st half - Mullaitivu


Page 229

Analysis 1st half - Mullaitivu


Page 230

Analysis 1st half - Mullaitivu


Page 231

Analysis 1st half - Mullaitivu


Page 232

Analysis 1st half - Mullaitivu


Page 233

Analysis 1st half - Mullaitivu


Page 234

Analysis 1st half - Mullaitivu


Page 235

Analysis 1st half - Mullaitivu


Page 236

Analysis 1st half - Mullaitivu


Page 237

Analysis 1st half - Mullaitivu


Page 238

Analysis 1st half - Mullaitivu


Page 239

h983

Analysis 1st half - Mullaitivu


Page 240

Analysis 1st half - Mullaitivu


Page 241

Analysis 1st half - Mullaitivu


Page 242

Analysis 1st half - Mullaitivu


Page 243

Analysis 1st half - Mullaitivu


Page 244

Analysis 1st half - Mullaitivu


Page 245

Analysis 1st half - Mullaitivu


Page 246

Analysis 1st half - Mullaitivu


Page 247

Analysis 1st half - Mullaitivu


Page 248

Analysis 1st half - Mullaitivu


Page 249

Analysis 1st half - Mullaitivu


Page 250

Analysis 1st half - Mullaitivu


Page 251

Analysis 1st half - Mullaitivu


Page 252

Analysis 1st half - Mullaitivu


Page 253

Analysis 1st half - Mullaitivu


Page 254

Analysis 1st half - Mullaitivu


Page 255

Analysis 1st half - Mullaitivu


Page 256

Analysis 1st half - Mullaitivu


Page 257

Rate Amount

Analysis 1st half - Mullaitivu


Page 258

0
0
211

Analysis 1st half - Mullaitivu


Page 259

Analysis 1st half - Mullaitivu


Page 260

Analysis 1st half - Mullaitivu


Page 261

Analysis 1st half - Mullaitivu


Page 262

Analysis 1st half - Mullaitivu


Page 263

Analysis 1st half - Mullaitivu


Page 264

Analysis 1st half - Mullaitivu


Page 265

Analysis 1st half - Mullaitivu


Page 266

Analysis 1st half - Mullaitivu


Page 267

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 268

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 269

Analysis 1st half - Mullaitivu


Page 270

Analysis 1st half - Mullaitivu


Page 271

Analysis 1st half - Mullaitivu


Page 272

Analysis 1st half - Mullaitivu


Page 273

Analysis 1st half - Mullaitivu


Page 274

Analysis 1st half - Mullaitivu


Page 275

Analysis 1st half - Mullaitivu


Page 276

Analysis 1st half - Mullaitivu


Page 277

Analysis 1st half - Mullaitivu


Page 278

Analysis 1st half - Mullaitivu


Page 279

Analysis 1st half - Mullaitivu


Page 280

Analysis 1st half - Mullaitivu


Page 281

Analysis 1st half - Mullaitivu


Page 282

Analysis 1st half - Mullaitivu


Page 283

Analysis 1st half - Mullaitivu


Page 284

Analysis 1st half - Mullaitivu


Page 285

Rate Amount

Analysis 1st half - Mullaitivu


Page 286

Rate Amount

Analysis 1st half - Mullaitivu


Page 287

Analysis 1st half - Mullaitivu


Page 288

Analysis 1st half - Mullaitivu


Page 289

Analysis 1st half - Mullaitivu


Page 290

Analysis 1st half - Mullaitivu


Page 291

Analysis 1st half - Mullaitivu


Page 292

Analysis 1st half - Mullaitivu


Page 293

Analysis 1st half - Mullaitivu


Page 294

Analysis 1st half - Mullaitivu


Page 295

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 296

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 297

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 298

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 299

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 300

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 301

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 302

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 303

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 304

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 305

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 306

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 307

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 308

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 309

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 310

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 311

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 312

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 313

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 314

Rate Add 14%

Analysis 1st half - Mullaitivu


Page 315

Analysis 1st half - Mullaitivu


Page 316

Analysis 1st half - Mullaitivu


Page 317

Analysis 1st half - Mullaitivu


Page 318

Analysis 1st half - Mullaitivu


Page 319

Analysis 1st half - Mullaitivu


Page 320

Analysis 1st half - Mullaitivu


Page 321

Analysis 1st half - Mullaitivu


Page 322

Analysis 1st half - Mullaitivu


Page 323

Analysis 1st half - Mullaitivu


Page 324

Analysis 1st half - Mullaitivu


Page 325

Analysis 1st half - Mullaitivu


Page 326

Analysis 1st half - Mullaitivu


Page 327

Analysis 1st half - Mullaitivu


Page 328

Analysis 1st half - Mullaitivu


Page 329

Analysis 1st half - Mullaitivu


Page 330

Analysis 1st half - Mullaitivu


Page 331

Analysis 1st half - Mullaitivu


Page 332

Analysis 1st half - Mullaitivu


Page 333

Analysis 1st half - Mullaitivu


Page 334

Analysis 1st half - Mullaitivu


Page 335

Analysis 1st half - Mullaitivu


Page 336

Analysis 1st half - Mullaitivu


Page 337

Analysis 1st half - Mullaitivu


Page 338

Analysis 1st half - Mullaitivu


Page 339

Analysis 1st half - Mullaitivu


Page 340

Analysis 1st half - Mullaitivu


Page 341

Analysis 1st half - Mullaitivu


Page 342

Analysis 1st half - Mullaitivu


Page 343

Analysis 1st half - Mullaitivu


Page 344

Analysis 1st half - Mullaitivu


Page 345

Analysis 1st half - Mullaitivu


Page 346

Analysis 1st half - Mullaitivu


Page 347

Analysis 1st half - Mullaitivu


Page 348

Analysis 1st half - Mullaitivu


Page 349

Analysis 1st half - Mullaitivu


Page 350

Analysis 1st half - Mullaitivu


Page 351

Analysis 1st half - Mullaitivu


Page 352

Analysis 1st half - Mullaitivu


Page 353

Analysis 1st half - Mullaitivu


Page 354

Analysis 1st half - Mullaitivu


Page 355

Analysis 1st half - Mullaitivu


Page 356

Analysis 1st half - Mullaitivu


Page 357

Analysis 1st half - Mullaitivu


Page 358

Analysis 1st half - Mullaitivu


Page 359

Analysis 1st half - Mullaitivu


Page 360

Analysis 1st half - Mullaitivu


Page 361

Analysis 1st half - Mullaitivu


Page 362

Analysis 1st half - Mullaitivu


Page 363

Analysis 1st half - Mullaitivu


Page 364

Analysis 1st half - Mullaitivu


Page 365

Analysis 1st half - Mullaitivu


Page 366

PRICE LIST
Code No Description Unit Rate
1 1 1 1/2" dia. Pvc pipe 1000 type L.ft 42.00

2 2 1 1/2" dia. Pvc pipe 600 type L.ft 27.00

3 3 1 1/4" dia. Pvc pipe 1000 type L.ft 28.00

4 4 1 1/4" dia. Pvc pipe 600 type L.ft 20.00

5 5 1" dia. Pvc pipe 1000 type L.ft 19.00

6 6 1" dia. Pvc pipe 600 type L.ft 11.00

7 7 1/2" dia. Pvc pipe 1000 type L.ft 7.00

8 8 2" dia. Pvc pipe 1000 type L.ft 73.00

9 9 2" dia. Pvc pipe 600 type L.ft 44.00

10 10 3/4" dia. Pvc pipe 1000 type L.ft 12.00

11 11 4" dia. Sewerage (SS) 250 type L.ft 53.00

12 12 4" dia. Sewerage (SS) 400 type L.ft 82.00

13 13 Asbestoes flat sheet 1.2m x 1.2m S.ft 18.00

14 14 Asbestoes ridges Pairs 363.00

15 15 Asbestos corr. Sheet S.ft 29.00

16 19 Coconut rafters(each 10' ) no 300.00

17 20 Barbed wire L.ft 2.50

21 wooden block no 5.00

18 22 Barrel bolt 4" Brass oxidised no 79.00

19 23 Barrel bolt 6" Brass oxidised no 120.00

20 24 Basket no 52.50

21 25 Beading L.ft 4.00

26 Beading 2"x1/2" l.ft 4.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page 367

22 31 Binding wire 14 B.W.G. lbs 40.00

23 32 Bitumen Gal 347.00

24 35 Board 1" thick Valance (10") S.ft 50.00

25 36 Brass Bib Tap 1/2" No 145.00

26 41 Bricks No 5.70

27 44 Castm. stays h. qual 10" brass oxidised No 90.00

28 45 Castm.fast. Brass oxi. H. qlty ,mort.plate No 90.00

29 46 Cement CWT 520.00

30 47 Center pivot hinges br.oxi.h.qual. ( 4 pieces ) Set 45.00

31 50 Closet low level pedestal type (complete ceremic)No 4100.00

32 57 Rubber shuttering planks sq.ft 20.00

33 60 Draw rings 1 1 /2 dia. no 25.00

34 61 Earth ( Gravel Filling) Cube 1850.00

35 63 Emulsion Paint ( Weather shield ) gal 1790.00

64 EMulsion Paint Gal 1415.00

37 65 Enamel Paint Gal 1785.00

38 66 Fanlight catch Brass oxi. Heavy qality No 30.00

39 70 Calicut pattern flat tiles No 18.00

40 73 G.I 20 B.W.G Sheets S,ft 75.00

41 74 G.I. 22 B.W.G.Flat sheet Sft 55.00

42 77 Ginisappu timber 3/4" thick S.ft 50.00

43 81 Glass panes obscured(3mm) S.ft 50.00

44 85 Glue lbs 86.00

45 90 Gulley Box PVC 6" no 290.00

46 91 Half round tiles No 6.50

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page 368

47 94 Hinges 4"x3" Brass oxidised Pair 136.00

48 95 Hinges 4"x4" Brass oxidised Pair 205.00

97 Hire of mixtur, vibrator, wages of operator Day 4500.00

49 98 Hold fast no 17.50

50 117 Skelton bolt 10" brass Doz 136.00

51 119 Iron T.hinges 10" No 58.00

120 Brass T hinges 10" Pair 0.00

123 Joists Class II 4" x 2" L.ft 40.00

126 Lime -Slaked Bushel 257.00

52 127 Limpet washers No 1.00

53 135 Metal 1 1/2" Cube 8020.00

54 136 Metal 1" Cube 8470.00

55 137 Metal 2" Cube 7850.00

56 138 Metal 3/4" cube 8830.00

57 139 Metal 6" to 9" cube 5715.00

58 140 Mild steel cwt 4240.00

59 141 Mirror with fittings no. 520.00

60 142 Mortice Lock Concord No 525.00

61 143 Mortice Lock Vinion double No 790.00

62 144 Lock Night Latch Bird No 290.00

63 145 Mortice lock Union English single leaver No 1575.00

64 146 Mortice lock Union English double leaver no. 2795.00

65 147 Mould oil gal 100.00

66 150 Nails 2" (GI) Ibs 34.00

67 153 Nails 3/4" (GI) lbs 34.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page 369

68 157 P.V.C. end cap (Gutter Cap) no 44.80

69 158 P.V.C. gutter joint no 51.50

70 159 P.V.C. metre joint no 164.00

71 160 P.V.C. running head no 107.00

72 161 P.V.C.gutter 6" L.ft 38.50

73 162 P.V.C.Inspection joint 4" (110mm) No 367.50

74 163 P.V.C.Inspection "Y" joint 4" (110mm) no. 436.00

75 164 P.V.C.Bend (11Deg) - 4" (110mm) no. 115.50

76 165 P.V.C.Bend (22Deg) - 4" (110mm) no. 119.00

77 166 P.V.C.Bend (60Deg) - 4" (110mm) no. 199.50

78 167 P.V.C.Bend (88 Deg) - 4" (110mm) no. 325.50

79 168 P.V.C.Pipe 4" 600 type L.ft. 48.50

80 169 P.V.C.Pipe 4" 400 type L.ft. 107.00

81 171 Paint oil Enamel gal 1785.00

82 181 Planks 1 1/4" special upper Sft 135.00

83 182 Planks 1" Class II (Ginnisappu) s.ft 50.00

84 183 Plastic cistern low level (Plastic ) no 1265.00

85 184 Plugs no. 2.00

86 186 Plywood door 2"-3" x 6'-9" no. 0.00

87 187 Plywood door 2'-3" x 6'-9" ( Mackply) no 1848.00

88 188 Plywood door ord 2'-9" x 6'-9" no 1765.00

89 189 Pressed Tiles 8" x 8" no. 32.00

90 190 Primer gal 1560.00

91 191 Pudlo cement lbs 32.00

92 192 Red cement kg 342.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page 370

93 193 Reepers (2":1") sp. (Micro) L.ft 8.00

94 194 Ridge tile no. 35.00

95 196 Rim lock 6" 2 leaves Brase No 446.00

96 197 River Sand Cube 2100.00

97 198 Drive screws and washers no. 6.00

98 199 Rawl plugs & 2" Screws No 15.00

99 200 Sand Fine (River sand) cube 2100.00

100 205 Sash bars 1 1/2"x1 1/2" L.ft. 19.00

206 Special labour day 375.00

101 207 Screws 1 1/2" doz. 0.00

102 211 Sink 24"x15"x8" with waste plug & chain no 2100.00

103 214 Skilled labour Gr.Il day 475.00

104 215 Skilled labour Gr.I day 475.00

105 216 Boild Lime Bushel 270.00

106 218 Soap tray no 173.00

107 220 Spur stones no. 22.50

108 222 Squating pan with trap no 700.00

109 224 Staining Bolts no. 112.00

110 225 Staples Doz 20.00

111 227 Stop cock L.D model 1/2" no 105.00

112 228 Stop cock L.D model 1 1/4" no. 0.00

113 232 Tar Gal 90.00

114 236 Tiles 6" x 6" white no 0.00

115 245 Timber purlins c.ft. 1250.00

246 Timber sp.class upper / Kempus c.ft. 1250.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page 371

116 248 Tooth brush holder cromium plated no 196.00

117 249 Tor steel cwt 4330.00

118 250 Towel Trail holder chromium plated no 275.00

119 255 transport 1 st Mile 1 mile 0.00

120 257 Unskilled labour day 325.00

121 260 Varnish gal 1756.00

122 263 Wash basin 22"x16" no. 1780.00

123 264 1/2" Nut & Washers No 3.00

124 268 Wood plugs no 0.00

125 269 Yellow ocare lbs 0.00

126 270 Wire dome for 2" pipe No 60.00

127 300 2"X2" Class II Battens Lft 13.00

128 301 3/8" dia 18" Bolts,Nuts & Washers No 13.00

129 302 Grey Cement cwt 393.00

130 303 Rawl Plugs and Screws No 0.00

304 Culicut Tiles No 0.00

131 308 gate valve 2" No 357.00

132 309 Stopcock LD Model 3/4" (Plastic) No 134.40

133 310 Stopcock LD Model 1" (Plastic) No 145.60

134 311 Stopcock LD Model 1 1/4" (Plastic) No 280.00

135 312 Stopcock LD Model 1 1/2" (Plastic) No 306.00

136 313 Stopcock LD Model 2" (Plastic) No 372.00

137 314 Jet Shower 3" Chromium plated No 500.00

138 317 pvc gutter brackets No 9.20

139 318 Solvent cement 50g Tin 43.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page 372

140 344 Angle iron 2"x2"x1/4" L.ft 85.00

141 345 Angle iron 1 1/2"x1 1/2"x1/4" L.ft 56.50

142 346 Angle iron 2 1/2"x2 1/2"x1/4" L.ft 102.50

143 347 Angle iron 3"x3"x1/4" L.ft 125.00

144 348 Making holes on angle iron No 20.00

145 349 H - iron 6"x3" (6mm) L.ft 0.00

146 350 H - iron 8"x4" (6mm) L.ft 0.00

147 351 1" x 1/4" Flat iron L.ft 15.00

148 352 1/2"x1" Bolts & Nuts No 6.00

149 353 Fillets (Class I local timber for beeding) L.ft 0.00

150 354 Fillets 1/2" x 1/2" L.ft 3.25

151 355 Ball valve 1/2" No 94.50

152 356 Ball valve 3/4" No 152.25

153 357 Cistern only ceremice No 1800.00

154 358 Fittings ( For commode & cistern ) Item 367.50

155 359 Seat cover ( Double ) No 420.00

156 360 Brackets (For cistern ) Item 62.00

157 361 Flush bend No 39.80

159 363 4" Sandcrete Block No 0.00

160 364 110mm PVC "T" Junction No 552.50

161 365 110mm PVC "Y" Joint No 525.00

162 366 50mm Bottle trap No 165.00

163 367 110mm PVC Inspection Bend No 388.50

164 368 bends 3.5" No 64.00

165 369 110mm PVC Elbow No 301.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page 373

166 370 PVC down pipe 3 1/2" Length 416.00

167 371 PVC socket 3 1/2" No 47.25

168 372 PVC elbow 3 1/2" No 64.00

169 373 PVC clips 3 1/2" No 9.50

170 374 1 1/4" x 1/4" Flat iron Lft 22.00

171 375 1/2" (12mm) Bolt & Nut No 6.50

172 376 9" x 9" 3/8" M.S. plate No 110.00

173 377 1/2' x 1 1/2" Rag bolt No 6.00

174 378 2" x 1/4" Flat iron L.ft 38.00

175 379 70S-1002-1 L.ft 64.60

176 380 70S-1102-1 L.ft 44.50

177 381 70S-1202-1 L.ft 46.40

382 70S-1402-1 L.ft 52.90

178 383 70S-1503-A L.ft 78.10

179 384 70S-1704-A L.ft 79.40

180 385 70S-3002-1 L.ft 85.00

181 386 70D-1910 L.ft 24.30

387 100D-1914 L.ft 24.30

182 388 100D-1917 L.ft 32.80

183 389 100D-3004-A L.ft 124.50

184 390 100D-3203 L.ft 129.10

185 391 100D-3207 L.ft 169.00

186 392 100D-3502 L.ft 148.70

187 393 100D-3503-A L.ft 160.90

188 394 CA-1001 L.ft 84.30

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page 374

189 395 CA-1002 L.ft 134.20

190 396 CA-2001-A L.ft 88.90

191 397 PT-5153 L.ft 12.80

192 398 PT-5154 L.ft 30.50

193 399 PT-5157 L.ft 56.30

194 400 P-1113 L.ft 40.75

195 401 80S-1801 L.ft 57.85

196 402 BD-1066 ( Handle ) Pair 350.00

197 403 Lock ALPHA No 750.00

198 404 Door Closer No 1645.00

199 405 5mm thick tinted glass S.ft 60.00

200 406 6mm thick Plywood sheet ( ordinary ) S.ft 20.85

201 407 Formica sheet S.ft 18.00

202 408 Rubber Beading for Aluminium fittings L.ft 3.00

203 409 Welded mesh S.ft 10.00

204 410 Type 1 Sum 125.00

205 411 Type 2 Sum 250.00

206 412 Type 3 Sum 75.00

207 413 Type 4 Sum 50.00

208 414 Type 5 Sum 25.00

209 415 Allowance type 1 Sum 100.00

210 416 Allowance type 2 Sum 150.00

211 417 Allowance type 3 Sum 10.00

215 1002 transport every additional Miles 1mile 0.00

216 12b Anticorrosive paint gal 1139.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page 375

217 147a Mouldings L.ft 4.50

218 181a Planks 1" Sp. Upper Class Timber/Kempus sft 125.00

219 182b Planks 3/4" sq.ft. 105.00

220 193a Reepers Cl.II 2"x1" L.ft 0.00

221 198a Ring 1 1/2" Brass no 26.25

222 207a Screws 1" brass Doz 45.00

223 207b Screws 2" doz 69.00

224 232a Tiles 1'-0"x1'-0" floor no 85.00

225 236a Tiles 6"x6" colour no 15.00

226 236b Tiles 4"x4" white no 0.00

227 236c Tiles 4"x4" colour no 8.00

228 267a Wire nails 2" lbs 36.50

229 268a Wood preservative gal 315.00

230 357a Cistern plastic No 1265.00

231 40a Brass screws 1 1/2" Doz 52.50

232 40c Brass screws 3/4" Doz 31.50

233 40d Brass Screws 1" Doz 45.00

234 76a G.I.Hook 5/16"x4 1/4" no 6.50

235 81a Glass Panes Tinted (5mm) S.ft 80.00

236 91a Bras Sancy 1 1/4" Doz 45.00

237 91b Cistern ceremic no 0.00

238 91c Cistern plastic no 1265.00

239 95a Hinges 4"x2 1/2" Brass oxidised Pair 115.50

240 96a 16mm 9" Rag bolt no 140.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page (Page)

Code No Description Unit Rate


1 1 1 1/2" dia. Pvc pipe 1000 type L.ft 38.50

2 2 1 1/2" dia. Pvc pipe 600 type L.ft 25.00

3 3 1 1/4" dia. Pvc pipe 1000 type L.ft 26.00

4 4 1 1/4" dia. Pvc pipe 600 type L.ft 18.50

170 374 1 1/4" x 1/4" Flat iron Lft 20.00

5 5 1" dia. Pvc pipe 1000 type L.ft 17.00

6 6 1" dia. Pvc pipe 600 type L.ft 10.50

147 351 1" x 1/4" Flat iron L.ft 13.75

173 377 1/2' x 1 1/2" Rag bolt No 6.00

171 375 1/2" (12mm) Bolt & Nut No 6.00

7 7 1/2" dia. Pvc pipe 1000 type L.ft 6.30

123 264 1/2" Nut & Washers No 3.00

148 352 1/2"x1" Bolts & Nuts No 6.00

387 100D-1914 L.ft 24.30

182 388 100D-1917 L.ft 32.80

183 389 100D-3004-A L.ft 124.50

184 390 100D-3203 L.ft 129.10

185 391 100D-3207 L.ft 169.00

186 392 100D-3502 L.ft 148.70

187 393 100D-3503-A L.ft 160.90

160 364 110mm PVC "T" Junction No 526.00

161 365 110mm PVC "Y" Joint No 500.00

165 369 110mm PVC Elbow No 287.00

163 367 110mm PVC Inspection Bend No 370.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page (Page)

8 8 2" dia. Pvc pipe 1000 type L.ft 67.00

9 9 2" dia. Pvc pipe 600 type L.ft 40.50

174 378 2" x 1/4" Flat iron L.ft 35.00

127 300 2"X2" Class II Battens Lft 12.00

10 10 3/4" dia. Pvc pipe 1000 type L.ft 11.30

128 301 3/8" dia 18" Bolts,Nuts & Washers No 12.00

11 11 4" dia. Sewerage (SS) 250 type L.ft 48.50

12 12 4" dia. Sewerage (SS) 400 type L.ft 75.00

159 363 4" Sandcrete Block No 0.00

162 366 50mm Bottle trap No 150.00

199 405 5mm thick tinted glass S.ft 60.00

200 406 6mm thick Plywood sheet ( ordinary ) S.ft 20.85

181 386 70D-1910 L.ft 24.30

175 379 70S-1002-1 L.ft 64.60

176 380 70S-1102-1 L.ft 44.50

177 381 70S-1202-1 L.ft 46.40

382 70S-1402-1 L.ft 52.90

178 383 70S-1503-A L.ft 78.10

179 384 70S-1704-A L.ft 79.40

180 385 70S-3002-1 L.ft 85.00

195 401 80S-1801 L.ft 57.85

172 376 9" x 9" 3/8" M.S. plate No 110.00

209 415 Allowance type 1 Sum 100.00

210 416 Allowance type 2 Sum 150.00

211 417 Allowance type 3 Sum 10.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page (Page)

141 345 Angle iron 1 1/2"x1 1/2"x1/4" L.ft 42.75

142 346 Angle iron 2 1/2"x2 1/2"x1/4" L.ft 79.00

140 344 Angle iron 2"x2"x1/4" L.ft 55.50

143 347 Angle iron 3"x3"x1/4" L.ft 99.35

216 12b Anticorrosive paint gal 1085.00

13 13 Asbestoes flat sheet 1.2m x 1.2m S.ft 13.30

14 14 Asbestoes ridges Pairs 267.00

15 15 Asbestos corr. Sheet S.ft 21.35

151 355 Ball valve 1/2" No 90.00

152 356 Ball valve 3/4" No 145.00

17 20 Barbed wire L.ft 1.45

18 22 Barrel bolt 4" Brass oxidised no 75.00

19 23 Barrel bolt 6" Brass oxidised no 115.00

20 24 Basket no 50.00

196 402 BD-1066 ( Handle ) Pair 350.00

21 25 Beading L.ft 4.00

26 Beading 2"x1/2" l.ft 4.00

164 368 bends 3.5" No 61.00

22 31 Binding wire 14 B.W.G. lbs 36.00

23 32 Bitumen Gal 330.00

24 35 Board 1" thick Valance (10") S.ft 46.30

105 216 Boild Lime Bushel 257.00

156 360 Brackets (For cistern ) Item 54.00

236 91a Bras Sancy 1 1/4" Doz 43.00

25 36 Brass Bib Tap 1/2" No 130.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page (Page)

231 40a Brass screws 1 1/2" Doz 50.00

233 40d Brass Screws 1" Doz 39.00

232 40c Brass screws 3/4" Doz 30.00

120 Brass T hinges 10" Pair 0.00

26 41 Bricks No 2.60

188 394 CA-1001 L.ft 84.30

189 395 CA-1002 L.ft 134.20

190 396 CA-2001-A L.ft 88.90

39 70 Calicut pattern flat tiles No 11.00

27 44 Castm. stays h. qual 10" brass oxidised No 90.00

28 45 Castm.fast. Brass oxi. H. qlty ,mort.plate No 90.00

29 46 Cement CWT 345.00

30 47 Center pivot hinges br.oxi.h.qual. ( 4 pieces ) Set 45.00

237 91b Cistern ceremic no 0.00

153 357 Cistern only ceremice No 1400.00

230 357a Cistern plastic No 1150.00

238 91c Cistern plastic no 1150.00

31 50 Closet low level pedestal type (complete ceremic)No 3900.00

16 19 Coconut rafters(each 10' ) no 300.00

304 Culicut Tiles No 0.00

198 404 Door Closer No 1645.00

33 60 Draw rings 1 1 /2 dia. no 25.00

97 198 Drive screws and washers no. 6.00

34 61 Earth ( Gravel Filling) Cube 590.00

64 EMulsion Paint Gal 1345.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page (Page)

35 63 Emulsion Paint ( Weather shield ) gal 1704.00

37 65 Enamel Paint Gal 1698.00

38 66 Fanlight catch Brass oxi. Heavy qality No 30.00

149 353 Fillets (Class I local timber for beeding) L.ft 0.00

150 354 Fillets 1/2" x 1/2" L.ft 3.00

154 358 Fittings ( For commode & cistern ) Item 350.00

157 361 Flush bend No 35.50

201 407 Formica sheet S.ft 18.00

40 73 G.I 20 B.W.G Sheets S,ft 65.00

41 74 G.I. 22 B.W.G.Flat sheet Sft 50.00

234 76a G.I.Hook 5/16"x4 1/4" no 6.00

131 308 gate valve 2" No 340.00

42 77 Ginisappu timber 3/4" thick S.ft 0.00

43 81 Glass panes obscured(3mm) S.ft 45.00

235 81a Glass Panes Tinted (5mm) S.ft 60.00

44 85 Glue lbs 86.00

129 302 Grey Cement cwt 375.00

45 90 Gulley Box PVC 6" no 550.00

145 349 H - iron 6"x3" (6mm) L.ft 0.00

146 350 H - iron 8"x4" (6mm) L.ft 0.00

46 91 Half round tiles No 5.00

239 95a Hinges 4"x2 1/2" Brass oxidised Pair 110.00

47 94 Hinges 4"x3" Brass oxidised Pair 130.00

48 95 Hinges 4"x4" Brass oxidised Pair 195.00

97 Hire of mixtur, vibrator, wages of operator Day 2520.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page (Page)

49 98 Hold fast no 17.50

51 119 Iron T.hinges 10" No 58.00

123 Joists Class II 4" x 2" L.ft 30.00

126 Lime -Slaked Bushel 257.00

52 127 Limpet washers No 1.00

197 403 Lock ALPHA No 750.00

62 144 Lock Night Latch Bird No 275.00

144 348 Making holes on angle iron No 5.00

53 135 Metal 1 1/2" Cube 3500.00

54 136 Metal 1" Cube 3750.00

55 137 Metal 2" Cube 3350.00

56 138 Metal 3/4" cube 4100.00

57 139 Metal 6" to 9" cube 2000.00

58 140 Mild steel cwt 1986.50

59 141 Mirror with fittings no. 390.00

60 142 Mortice Lock Concord No 425.00

64 146 Mortice lock Union English double leaver no. 2660.00

63 145 Mortice lock Union English single leaver No 1500.00

61 143 Mortice Lock Vinion double No 750.00

65 147 Mould oil gal 100.00

217 147a Mouldings L.ft 4.00

66 150 Nails 2" (GI) Ibs 30.00

67 153 Nails 3/4" (GI) lbs 30.00

68 157 P.V.C. end cap (Gutter Cap) no 38.00

69 158 P.V.C. gutter joint no 44.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page (Page)

70 159 P.V.C. metre joint no 142.00

71 160 P.V.C. running head no 102.00

75 164 P.V.C.Bend (11Deg) - 4" (110mm) no. 110.00

76 165 P.V.C.Bend (22Deg) - 4" (110mm) no. 113.00

77 166 P.V.C.Bend (60Deg) - 4" (110mm) no. 190.00

78 167 P.V.C.Bend (88 Deg) - 4" (110mm) no. 310.00

72 161 P.V.C.gutter 6" L.ft 37.00

74 163 P.V.C.Inspection "Y" joint 4" (110mm) no. 415.00

73 162 P.V.C.Inspection joint 4" (110mm) No 350.00

80 169 P.V.C.Pipe 4" 400 type L.ft. 60.00

79 168 P.V.C.Pipe 4" 600 type L.ft. 48.50

194 400 P-1113 L.ft 40.75

81 171 Paint oil Enamel gal 1698.00

82 181 Planks 1 1/4" special upper Sft 114.50

83 182 Planks 1" Class II (Ginnisappu) s.ft 41.70

218 181a Planks 1" Special Upper Class Timber sft 94.00

219 182b Planks 3/4" sq.ft. 69.00

84 183 Plastic cistern low level (Plastic ) no 1150.00

85 184 Plugs no. 2.00

87 187 Plywood door 2'-3" x 6'-9" ( Marine) no 1490.00

86 186 Plywood door 2"-3" x 6'-9" no. 0.00

88 188 Plywood door ord 2'-9" x 6'-9" no 1467.00

89 189 Pressed Tiles 8" x 8" no. 29.00

90 190 Primer gal 1485.00

191 397 PT-5153 L.ft 12.80

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page (Page)

192 398 PT-5154 L.ft 30.50

193 399 PT-5157 L.ft 56.30

91 191 Pudlo cement lbs 30.00

169 373 PVC clips 3 1/2" No 9.00

166 370 PVC down pipe 3 1/2" Length 317.00

168 372 PVC elbow 3 1/2" No 61.00

138 317 pvc gutter brackets No 9.20

167 371 PVC socket 3 1/2" No 45.00

98 199 Rawl plugs & 2" Screws No 15.00

130 303 Rawl Plugs and Screws No 0.00

92 192 Red cement kg 325.00

93 193 Reepers (2":1") sp.upper L.ft 8.00

220 193a Reepers Cl.II 2"x1" L.ft 0.00

94 194 Ridge tile no. 23.00

95 196 Rim lock 6" 2 leaves Brase No 425.00

221 198a Ring 1 1/2" Brass no 25.00

96 197 River Sand Cube 1700.00

202 408 Rubber Beading for Aluminium fittings L.ft 3.00

32 57 Rubber shuttering planks sq.ft 16.70

99 200 Sand Fine cube 1500.00

100 205 Sash bars 1 1/2"x1 1/2" L.ft. 14.30

101 207 Screws 1 1/2" doz. 0.00

222 207a Screws 1" brass Doz 43.00

223 207b Screws 2" doz 66.00

155 359 Seat cover ( Double ) No 350.00

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page (Page)

137 314 Shower Rose 6" No 95.00

102 211 Sink 24"x15"x8" with waste plug & chain no 1810.00

50 117 Skelton bolt 10" brass Doz 130.00

104 215 Skilled labour Gr.I day 500.00

103 214 Skilled labour Gr.Il day 450.00

106 218 Soap tray no 164.00

139 318 Solvent cement 50g Tin 43.00

206 Special labour day 500.00

107 220 Spur stones no. 10.00

108 222 Squating pan with trap no 700.00

109 224 Staining Bolts no. 40.00

110 225 Staples Doz 20.00

112 228 Stop cock L.D model 1 1/4" no. 0.00

111 227 Stop cock L.D model 1/2" no 77.00

135 312 Stopcock LD Model 1 1/2" (Plastic) No 291.50

134 311 Stopcock LD Model 1 1/4" (Plastic) No 213.33

133 310 Stopcock LD Model 1" (Plastic) No 143.00

136 313 Stopcock LD Model 2" (Plastic) No 354.20

132 309 Stopcock LD Model 3/4" (Plastic) No 104.50

113 232 Tar Gal 0.00

224 232a Tiles 1'-0"x1'-0" floor no 65.00

227 236c Tiles 4"x4" colour no 5.75

226 236b Tiles 4"x4" white no 0.00

114 236 Tiles 6" x 6" white no 0.00

225 236a Tiles 6"x6" colour no 13.40

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


Page (Page)

115 245 Timber purlins c.ft. 620.00

246 Timber sp.class upper c.ft. 920.00

116 248 Tooth brush holder cromium plated no 100.00

117 249 Tor steel cwt 2084.00

118 250 Towel Trail holder chromium plated no 275.00

119 255 transport 1 st Mile 1 mile 0.00

215 1002 transport every additional Miles 1mile 0.00

204 410 Type 1 Sum 125.00

205 411 Type 2 Sum 250.00

206 412 Type 3 Sum 75.00

207 413 Type 4 Sum 50.00

208 414 Type 5 Sum 25.00

120 257 Unskilled labour day 300.00

121 260 Varnish gal 1673.00

122 263 Wash basin 22"x16" no. 1473.00

203 409 Welded mesh S.ft 10.00

126 270 Wire dome for 2" pipe No 60.00

228 267a Wire nails 2" lbs 30.00

124 268 Wood plugs no 0.00

229 268a Wood preservative gal 300.00

21 wooden block no 5.00

125 269 Yellow ocare lbs 0.00

240

B.S.R FOR THE 1st HALF OF 2003 IN TRINCOMALEE


SUMMARY.

NO DESCRIPTION OF WORK UNIT

1/1 Brick work in Cement, demolished brick Cube

stacked and debris cleared. m3

2/1 Brick work in lime, demolished brick stacked Cube

and debris cleared. m3

5/2 Ceiling, existing removed materials stacked Sqr

and debris cleared. m2

6/2 Cement concrete demolished, and debris Sqr

cleared away. m2

7/2 Cement concrete, reinforced demolished in

suspended floors reinforcement removed and Sqr

debris cleared. m2

8/2 Corrugated Sheets, Iron, Asbestoes or

Aluminium Alloy removed from roof or walls Sqr

and stacked. m2

9/3 Corrugated sheets iron or asbestos or aluminium alloy Sqr

removed from roofs or walls of 2 storeyed buildings m2

11/3 Door or Window, size up to 40 S.ft removed

from existing walls and door or stacked. No

12/3 Doors for window, size over 40 S.ft removed

- do - - do - No

13/4 Door or window, sash only, up to 40 S.ft

removed from existing walls and stacked. No


14/4 Door or window, sash only, over 40 S.ft

- do - - do - No

15/4 Down pipes, 4" to 6" dia G.I old or decayed, L.ft

removed from existing building and stacked. L.m

16/4 Drains demolished and debris cleared L.ft

NO DESCRIPTION OF WORK UNIT

18/5 Fence uprooted, barbed wire rolled up and

all materials stacked (length of fencing to L.ft

measured). L.m

19/5 Floors brick paved, demolished and debris Sqr

cleared away. m2

20/6 Gate sash removed and stacked after

demolishing cement concrete blocks or

removing posts and separating pintols (demolishing

brick work where necessary paid for separately). No

21/6 Glass panes in doors, windows and fanlights Sq.ft

removed and stacked. m2

22/6 Gutter, Eaves, removed and stacked from roofs of L.ft

single story buildings. L.m

23/6 Gutter, Eaves removed from roofs of two storeyed L.ft

buildings and stracked. L.m

25/7 Partitions removed and stacked at side, including Sq.ft

making goodnes two walls and floors. m2

26/7 Lime plastering shipped and debris cleared away. Sqr


27/4 Rendering cement, chipped and debris cleared away Sqr

from brick walls and floors. m2

28/8 Rendering cement, chipped and debris cleared away Sqr

from cement concrete floors and walls. m2

29/8 Roofing removing tiles and timber stacking, serviceable

materials and cleaning debris in single storey Sqr

building. m2

30/8 Roof, removing tiles and timber stacking serviceable Sqr

material and cleaning debris in two storeyed building. m2

32/9 Rubble masonry in cement, demolished rubble Cube

stacked and debris cleared away. m3

33/9 Rubble masonry in lime demolished rubble stacked and Cube

debris cleared away m3

NO DESCRIPTION OF WORK UNIT

34/9 Tiles glazed demolished and debris cleared away. Sqr

35/10 Tiles calicut or half round, removed from roof of Sqr

single storey buildings and stacked. m2

36/10 Tiles calicut of half round removed from Sqr

roof of 2 storeyed buildings and stacked. m2

28 Tiles calicut of half round removed from roof of

two storeyed buildings and stacked. Sqr

39/11 Ceiling asbestoes removing including timber frame

work, stacking serviceable materials single storey Sqr

building (and debris cleared away in single). m2


40/11 Ceiling asbestos removing including timber frame Sqr

work, - do - - do - in two m2

storeyed building.

41/11 Valance/ Barge boarding removed materials stacked L.ft

and debris cleared away in single storey building. L.m

42/11 Valance/ Barge boarding removed - do - L.ft

- do - in 2 storeyed building. L.m

43/12 Cement plastering, soffit chipped and debris cleared Sq.ft

away. m2

NO DESCRIPTION OF WORK UNIT

1/15 Cement concrete 1:3:6 with 2" metel, above one cube Cube

(shuttering paid for seperately). m3


2/15 Cement concrete 1:3:6 (2") upto one cube shuttering Cube

paid for seperately. m3

3/15 Cement concrete 1:2 1/2:5 (1") above one cube Cube

(shuttering paid for seperately). m3

2a/16 Cement concrete 1:3:6 (1 1/2") above 1 Cube

cube (shuttering paid for seperately). m3

2c/16 Cement concrete 1:3:6 (1") above 1 Cube

cube (shuttering paid for seperately). m3

4/16 Cement concrete 1:2 1/2:5 (1") upto one cube Cube

(shuttering paid for seperately). m3

5/16 Cement concrete 1:2:4 (3/4") above one cube Cube

(shuttering paid for seperately). m3

6/16 Cement concrete 1:2:4 (3/4") upto one cube Cube

(shuttering paid for seperately). m3

11/18 Drains, semi circular, in cement concrete 1:3:6 (1") 9"

wide and 9" average depth, with 3" thick sides and base

inclusive of 1/2" cement rendering 1:3 and expansion L.ft

joints as necessary excavation (without ramp). L.m

12/19 Lintol cement concrete 1:2:4 (3/4") 4 1/2"x6" L.ft

(Reinforcement paid seperately). L.m

13/19 Lintol cement concrete 1:2:4 (3/4") 9"x6" (Reinforcement L.ft

paid seperately). L.m

14/20 Lintol cement concrete 1:2:4 (3/4") 9"x9" )Reinforcement L.ft

paid seperately). L.m

19/22 Padstones, cement concrete 1:2:4 (3/4") precast


or in situ.Size 1-6x1-1 1/2x0-6 No

19a/22 Padstones, cement concrete 1:2:4 (3/4") precast

or in situ.Size 1-6x0-6x0-6 No

21/23 Slabs over drain, cement concrete 3" thick 1:2:4(3/4")

reinforced with expended metal and 1/2" cement rendered S.ft

1:2 (R/F paid for seperately). m2

21a/23 Slabs over drain, cement concrete 3" thick 1:2:4(3/4")

reinforced with expended metal and 1/2" cement rendered S.ft

1:2 (R/F paid for seperately). m2

25a/25 Cement concrete 1:1 1/2:3 (3/4"). Cube

m3

23/24 Supr stone, cement concrete 1:2:4 (3/4") for door posts

supplied and fixed. No

25/25 Cement concrete 1:2 1/2":5(1") using

mixer and vibrator (shuttering paid for Cube

seperately). m3

26/25 Cement concrete 1:2:4(3/4") in column shafts

(Reinforcement shuttering and finishes paid for seperately) Cube

in guard floor using mixer and vibrator. m3

27/25 Cement concrete as per Item 61 in 1st floor. Cube

m3

28/25 Cement concrete as per Item 61 in 2nd floor. Cube

m3

29/26 Cement concrete 1:2:4 (3/4") in beams in ground floor Cube

(reinforcements shuttering and finishes paid for seperately) m3

using mixer and vibrator.


30/26 Cement concrete as per Item 29 in 1st floor. Cube

m3

31/26 Cement concrete as per Item 29 in 2nd floor. Cube

m3

32/26 Shuttering for floor slab concrete and dismantling. Sqr

m2

33/27 Shuttering for column shaft and diamantling (for column Sq.ft

9"x9"x4" 4 ft heigh I.e 4 1/2" ft box). m2

33a/27 Shuttering for footing and walls etc. Sq.ft

m2

34/27 Shuttering for beam including dismantling (12"x18" Sq.ft

beam 20 ft long). m2

35/28 Cement concrete 1:2"4(3/4") lintol in ground floor

Reinforcement and shuttering paid for seperately using Cube

mixer and vobrator. m3

36/28 Cement concrete lintols as per Item (71) in 1st floor. Cube

m3

37/28 4" thick R..C.C 1:2:4 (3/4") in first floor slab (reinforcement Sqr

and shuttering paid seperately) using mixer and vibrator. m2

38/29 5" thick R.C.C in 1st floor - do - Sqr

- do - - do - m2

39/29 Drains semi circular in cement concrete 1:3:6 (1") wide

and 9" average depth, 3" thick sides and base, inclusive of
1/2" cement rendering 1:3 with necessary expension, joints L.ft

and excavation, but without ramp L.m

40/29 Drains in cement concrete 1:3:6(1") as above L.ft

But with ramp 2' 6" wide L.m

BLOCK MASONRY

1 Cement sand block in 1:6 mix in cement Cube

sand 1:5 mix m3

2 4" thick cement sand block 1:6 mix masonry Sqr

in cement sand 1:5 mix m2

NO DESCRIPTION OF WORK UNIT

2/30 Brick work in cement mortar (1:5) above 1 cube (up to 1st Cube

floor level). m3

3/30 - do - up to one cube - do - Cube

- do - m3

4/31 Brick work in cement mortar 1:5 in piers (in ground floor). Cube

m3
6/31 Brick work 4 1/2" thick in cement mortar 1:5 above 1 square. Sqr

m2

7/32 - do - up to one Sqrs. Sqr

m2

12/33 Extra over Item 2-5 and 9-11 for brick Cube

work from 1st floor level up 2nd floor. m3

14/34 Extra over Items 6-8 for brickwork from Sqrs

1st floor level to 2nd floor. m2

19/35 Coping, brick in cement 1:5 weathered and throated on L.ft

4 1/2" walls, cement renedered 1/2", 1:3 complete. L.m

20/35 Coping, brick in cement 1:5 weathered throated on 9" walls L.ft

and 1/2" cement rendered 1:3 complete. L.m

24/37 Doors or window inserted in existing walls including making,

No

25/37 Drains brick in cement 1:5,9" average depth 12" wide and

cement rendered 1/2" thick 1:3 complete with expansion joints

as necessary, including necessary excavation (apron paid L.ft

for seperately). L.m

26/38 Drains brick in cement 1:5,6" average depth 9" wide and

cement rendered 1/2" thick 1:3 complete with expansion joints

as necessary, including necessary excavation (apron paid L.ft

for seperately). L.m

28/38 Steps 12" wide and 6" to 9" high masonary or brick work in

cement mortar 1:5 rendered 1/2" cement 1:2 with foundation L.ft

6" below ground. L.m

30/39 Brick work in cement and sand 1:8 in foundation and upto Cube
D.P.C. m3

31/40 Brick work in cement and sand 1:8 in super structure Cube

in ground floor. m3

32/40 - do - in 1st floor. Cube

m3

33/40 - do - in 2nd floor. Cube

m3

MASON.

NO DESCRIPTION OF WORK UNIT

1/41 Random Rubble Masonary in cement mortar 1:5 above Cube

1 cube. m3

2/41 - do - up to one cube. Cube

m3
NO DESCRIPTION OF WORK UNIT

1/43 Exapansion joints in brick floors, filled with bitumen L.ft

and sand. L.m

2/43 Exapansion joints in concrete floors filled with bitumen and L.ft

sand(to full depth of concrete and rendering). L.m

5/44 Floors, cement concrete 1:2 1/2:5(1") 3" cement rendered 1/2", Sqr

1:2, with expansion joints filled with cement and sand. m2

12/46 Tiles glazed colour 6"x6" with all specials, supplied and S.ft

fixed to walls including raking plaster and bedding in m2

cement mortar 1:2.

12/46 Tiles glazed(colour)6"x6", with all S.ft

specials, supplied and fixed to walls m2

including raking plaster and bedding

in cement mortar 1:2.

12d/46 Tiles 8"x8", pressed of approved pattern and S.ft

colour, supplied and fixed. m2


NO DESCRIPTION OF WORK UNIT

4/139 Cracks in wall, plastered in cement 1:3 L.ft

after chipping 2" to 4" wide m

9/141 Flashing or plaster bands laid over tiles L.ft

4" to 6" wide on roof in cement and lime L.m

mortar 1:1:4

14/142 Rendering cement 1/2", 1:2 above 1 Sqr

Square. m2

15/142 Rendering cement 1/2", 1:2 upto 1 square Sqr

m2

16/143 Rendering cement 1/2", 1:3 above 1 Square. Sqr

m2
17/143 Rendering cement 1/2", 1:3 upto 1 Square Sqr

m2

18/143 Rendering, cement 3/4", 1:2 above 1 Sqr

Square. m2

19/143 Rendering, cement 3/4", 1:2 upto 1 square Sqr

m2

20/144 Rendering, cement 3/4", 1:3 above 1 Sqr

Square. m2

21/144 Rendering, cement 3/4", 1:3 upto 1 square Sqr

m2

22/144 Rendering, cement, floating coat using Red

cement finished smooth with Carborandum Sqr

stone m2

25/145 Rendering cement 3/4", 1:2 with Pudlo 5lbs Sqrs

to 100 lbs cement m2

26/145 Skirting in cement mortar 1:3, 1/2"x4" L.ft

projected or flush with wall, and L.m

including forming groove.

27/145 Skirting in cement mortar 1:3, 1/2"x6"

projected or flush with all finished with

Red cement floating, including forming L.ft

groove. L.m

28/146 3/8" thick plastering to RCC beams, slab Sqrs

soffit in cement sand 1:3 .with lime putty m2


29/146 D.P.C. 3/4" thick in cement, sand 1:2 Sqrs

finished smooth with 2 coats of hot tar. m2

29a/146 3/8" thick cement and sand plastering to Sqrs

column and beam m2

29b/146 1/2" thick cement plastering 1:4 mix Sqrs

m2

29c/146 5/8" thick cement plastering 1:4 mix Sqrs

m2

29d/146 Cracks in wall Plastered in cement 1:3 L.ft

after chipping 2" to 4" wide L.m

29e/146 Plinth plastering 1/2" thick 1:3 cement and Sqrs

sand with red cement floating m2


NO DESCRIPTION OF WORK UNIT

5/49 Corrugated asbestos sheet roofing on

special upper cl. Timber/kempas purlines

supplied and fixed complete including

treating timber with wood preservative Sqrs

two coats (ridging measured seperately). m2

7/50 Corrugated asbestos sheet fixed to roof

or wall on existing frame work with

necessary coach screws and limpet Sqrs

washers, or hook bolts.& with 2 coats wood m2

Preservative to existing frame work

18/53 Ridging, calicut pattern bedded in

Cement and lime mortar 1:1:4, Coloured L.ft

to match tiles. L.m

19/53 Ridging, Calicut Pattern bedded in

cement and lime mortar 1:1:4 coloured L.ft

to match tiles (tiles available at site) L.m

21/54 Ridging with asbestos cement close

fitting ridges fixed complete with L.ft

roofing screws or hook bolts. L.m

26/55 Tiles, calicut pattern, flat supplied and

laid up to 5 tiles in single storey building No

27/56 Tiles, calicut pattern flat supplied and

laid (above 5 and up to 25) in single

storey Building. No
30/56 Tiles calicut pattern supplied and laid Sqr

in any Building. m2

31/56 Tiles, calicut pattern, laid in any Sqr

Buildings(tiles available at site). m2

43/53 Shifting and re-laying calicut pattern Sqr

tiles. m2

44/59 Supplying and laying half round tiles Sqr

on the existing asbestos roof. m2

NO DESCRIPTION OF WORK UNIT

8/63 Boards, Barge, Valance, Fascia, 3/4" to

1" thick in class.II Local timber fixed

complete with necessary Brass screws new or

renewed above 1 C.ft.( 9" width) with 1 coat L.ft

primer & 2 coat of enamel painting L.m

12/64 Boardes, Barge, Valance, Facia,

available fixed including cutting and s.ft

minor repairs.with 2 coats enamel painting m2

3/61A Beadings, Class I local timber 1 1/2" to

2"x1/2" plain chamfered, fixed with brass L.ft

screws L.m

14/65 Ceiling asbestos, flat fixed with clout

headed nails to 4"x2" joists at 4'crs & 2"x 2"

bearers at 2' crs of spl.upper class. Timber/

kempas including 1 1/2" x 1/2" cover fillets

and 2 1/2" x 1/2" coves of Halmills timber.

Rate to include 2 coats tarnap to joists

and bearers primer and '2 coats of enamel


painting to beadings 'and mouldingd 2 coats

of white washing to ceiling.

Making holes in wall and fixing joists and

bearers 'Per 1.95 Sqrs (15'-0"x13'-0"). Sqr

m2

14a/65 Ceiling asbestos, flat in eves fixed with clout

headed nails to 2" x 2"& 2"x1" spacer

bearers not exceading 2'-0 centrs both ways

bearers of spl.upper class/ kempus timber

including Aluminium beading 1" wide with

Rubber fillets fixed not exceedaing 2'-0" crs

bothways Rate to include 2 coats tarnap to Sqr

timber and 2 coats emulsion m2

paint to abestos sheet

NO DESCRIPTION OF WORK UNIT

14b/65 Ceiling asbestos, flat fixed with clout

headed nails to 4"x2" joists 4'-0 crs & 2"x2"

bearers of spl.upper class/kempus timber 2'-0" crs

and 2"x1" spacer bearers not exceding 2'-0crs

including Aluminium beading 1" wide with

rubber fillets not exceeding 2'-0 crs fixed bothways Sqr

Rate to include 2 coats tarnap to timber m2

and 2 coats emulsion paint

to abestos sheet

14c/65 As per Item No.14 with only 2"x2"beares Sqr

in eaves ceiling. -do- -do- m2


14d/65 White washing to ceiling 2 coats and

2 coats of oil paint to beading and Sqr

moulding. m2

14e/65 Ceiling, upper side cleaned and debris Sqr

cleared away. m2

26/68A Cove mouldings Cl.I 2 1/2"x1 1/2" fixed

with brass screws and plugs new or L.ft

renewed. L.m

28/69 Doors or Windows, ledged, braced and

battened with grooved and tongured

joint,3 3/4" x 2 3/4" frames in spl upper class

/ kempas and 3/4" to

7/8" thick sashes in class1 timber S.ft

with brass fittings. m2

30/70 - do - - do -

Sash only, in class 1 timber S.ft

fixed with brass furniture. m2

32/70 Doors or Windows, framed and battened,

sash 1" to 1 1/8" thick in Special

upper Class timber/kempas fixed complete S.ft

with brass furniture. m2

32a/70 Battened sash only 1" to 11/8" thick in sp. S.ft

upper class timber/kempas fixed completed with m2

brass fittings

NO DESCRIPTION OF WORK UNIT

42/74 Doors or Windows, glazed and/or

pannelled with 3 3/4"x2 3/4" frames and

1 1/8" to 1 1/4" sashes in special upper S.ft


Class I timber/kempas fixed. m2

44/75 Doors or Windows, glazed or

pannelled sash only 1 1/8" to 1 1/4" thick

in Special upper class timber/kempas with brass S.ft

furniture. m2

44a/75 Doors pannelled and terllised/B.R.C.

weld mesh No. 32 with 3 3/4"x2 3/4"

frames and 1 1/8" thick sashes in special

upper class timber/kempas, fixed complete with S.ft

brass furniture. m2

52/78 Doors pannelled with 3 3/4"x2 3/4" frames

and 1 - 1 1/8"sashes in Special upper S.ft

Class timber /kempasfixed.with brass fittings m2

53/78 Door or Window, removing easing and Per

re-fixing. sash

54/78 Door or Window, easing only. Per sash

55/79 Door or Window frames renewed in

short lengths with special upper Class L.ft

timber/kempas. L.m

Assume 3'-0" Length of frame renewed

100/92 Reepers 2"x1" in Class I timber supplied L.ft

and fixed new or renewed with iron L.m

nails, up to 100 L.ft (shiffting of tiles paid

for seperately).

re-fixed in new position.

101/92 - do - - do - L.ft

over 100 L.ft. L.m


Per 100 L.ft

107/94 Roof with calicut pattern tiles on spl upper

class/Kempus frame work complete with ridges, Sqr

hips etc. m2

107a/94 gable end roof - do - Sqr

- do - - do -. m2

117/97 Timber available, sorted out, cut to

required sizes and fixed in roof and C.ft

other carpentry work. m3

121/98 Timber special upper Class/kempas fixed or

renewed in roof and other carpentry C.ft

work. m3

135/101 Trellis partition with 1/2"x1/2" laths fixed

2" apart diagonally or horizontally and S.ft

vertically on 4"x2" Milla timber framing. m2

138/102 Door frame 4"x3" in spl upper class timber/kempas S.ft

supplied and fixed in position m2

118/97 Timber fixed or renewed in post and frames C.ft

140/103 Door 1 1/4" thick plywood ordinary sash

single (ordinary finish) hung on 4"x3"

frame in Special upper class timber/kempas and S.ft

complete with brass furniture with mortice lock m2

140a/103 As per Item No 140 -do- -do- but with marine type S.ft

2'3"x6'9". m2
142/104 Supplying and fixing Plywood door 1 1/4" thick S.ft

single (Ordinary finish) to the existing frame m2

with brass fittings with mortice lock

143/104 -do- -do- plywood Marine type 1 1/4" thick S.ft

single hung to existing frame with fitting m2

NO DESCRIPTION OF WORK UNIT

13/165 Lettering 1" to 1 1/2" painted in sinhalese

English or Tamil, including painting Per

ground. Letter

14/165 Lettering 2" to 3" - do - Per

- do - - do -. Letter

15/166 Lettering 4" to 5" - do - Per

- do - - do -. Letter

23/168 Painting, enamel paint including washing

cleaning and smoothing down with sand Sqr

paper, 1 coat. m2

24/168 Painting enamel paint - do - Sqr


- do - 2 coats. m2

25/168 Painting New wood 1 Coat primer & 2 Coats Sqr

Enamel paint m2

25a/168 Painting new wood work and 2 coats of Sqr

enamel paint. m2

27/169 Painting Steel work, 1 coat, with Sqr

Anticrosive paint including removing m2

scale and wire brushing.

28/169 Painting Steel work, 2 coats, with Red

oxide including removing scale and Sqr

wire brushing. m2

30/169 Painting walls with emulsion paint 1 coat Sqr

(new coat). m2

30a/169 Painting walls with weather shield 1 coat Sqr

( New work ) m2

31/170 Painting walls with Emulsion paint, 2 Sqr

coats (new work). m2

31a/170 Painting walls with 2 coats of weather shield paint Sqr

( New work ) m2

32/170 Painting walls with Emulsion paint, 1

coat including preparing surface of old Sqr

work. m2

32a/170 Painting walls with weather shield paint Sqr

1 coat ( Old work ) m2


33/170 - do - - do - Sqr

2 coats - do - - do -. m2

33a/170 Painting walls with weather shield paint Sqr

2 coat ( Old work ) m2

40/172 Tarnap or other wood preservative, Sqr

applied to wood work 1 coat (old work). m2

41/172 Tarnap or other wood preservative, Sqr

applied to wood work 2 coats (new work). m2

44/173 Varnishing with best copal varnish after Sqr

washing down and sand papering 1 coat. m2

45/173 - do - - do - Sqr

- do - 2 coats. m2

49/174 White or colourwashing walls of single

storey buildings 1 coat, including Sqr

patching and preparing surface. m2

50/174 - do - - do - Sqr

2 coats - do -. m2
Item Description Unit

4/127 Bolts barrel 4", brass oxidised heavy

quality supplied and fixed with brass

screws. No

6/128 - do - 6" - do -

- do - - do - No

18/130 Casement fastner with mortice plate, brass oxidised


heavy quality supplied and fixed with brass screws. No

19/130 Casement stays 10", brass oxidised heavy


quality supplied and fixed. No

21/131 Fanlight Catches brass oxidised heavy

quality with brass screws fixed complete. No

27/132 But hinges 4"x3" brass oxidised heavy quality

supplied and fixed with brass screws complete. No

29/132 - do - 4"x4" - do -

- do - - do - No

29a/132 - do - 4"x2 1/2" - do -

- do - - do - No

31/133 Hinges centre pivot (consisting of 2 pieces)

brass oxidised heavy quality supplied and

fixed with brass screws complete. Set

31a/133 Rings, brass 1 3/4" to 1 1/2" supplied

and fixed to doors and windows with

brass screws. No
51/137 Lock Mortice Vinion /concord single supplied

and fixed. No

52/137 Lock Mortice Vinion/concord double, supplied

and fixed. No

53/137 Mortice Lock Union ( English) single

supplied and fixed. No

54/137 Mortice Lock Union ( English) double


supplied and fixed. No

53a/137 Lock Night Latch supplied and fixed with

duplicate keys approved quality No

63/123 Tor steel rods in reinforcing. Kg

64/123 Tor steel rods reinforcement in foundation Kg

63a/123 Mild Steel rods in reinforcing lintols or beams. Kg

64a/123 Mild Steel rods in Foundation . Kg


Item Description Unit

49/119 Hinges T, 10" Iron, heavy quality supplied

and fixed with iron screws complete. Pair

60/121 Locks, rim 6" iron, superior quality, heavy

type, s/f. with iron screws complete. No

67/123 M.S.Bars 5/8" dia supplied & fixed in

window frame at 4" cetres & painted L.ft

with one coat red lead & 2 coats aluminium L.m


67e/123 1/2" dia - do - - do - L.ft

L.m

RATE ANALYSIS SECOND HALF OF 2003 IN TRINCOMALEE

TINKER.

Item Description Unit

9/150 Flashing G.I.22 B.W.G. 1'6" wide, fixed

with 6" turned up along, and top edge

tucked well into wall in cement and L.ft

lime mortar. L,m

29/156 Gutters, Valley 20 B.W.G 36" wide,

renewed on existing board, sheets

tarred, joints soldered and cement, L.ft

lime filletting complete. L,m

34/158 -Do- renewed including 1" thick timber

boarding sheet tarred, joints soldered and L.ft

cement lime filletting complete. L,m

NO DESCRIPTION OF WORK UNIT


1 Drains, earth, in any soil except rock

requiring blasting cut to gradient and cube

shaped as directed soil deposited m3

within site.

2/13 Excavation in any soil except rock requiring cube

blasting part returnfill in and ram, and m3

surplus disposed of within site as directed.

4/14 Filling under floor with gravel or other cube

approved quality of filling, spread, m3

watered and well rammed in 3" layers

with available earth.

6/14 Filling under floor with gravel or other cube

approved quality of filling spread water m3

and rammed in 3" layers (material not

available at site).

7/15 External Filling.(Material not available at site) cube

m3

8/15 External Filling.(Material available at site) cube

m3
Item Description Unit

1/179 Ball valve 1/2" supplied and fixed No

2/179 Ball valve 3/4" supplied and fixed No

13/181 Wash' Basin, Lavatory, 22"x16" with one tap,

water plug, new brackets, supplied &

fixed complete. (Additional tap, trap,

and outlet pipe paid for seperately). No

17/182 Basin, sink or urinal including all fittings

removed and walls made good No

31/185 Closet, pedestal type available at site, fixed

with cement concrete after breaking concrete

floor and making good and connections to soil

and flush pipes No

32/186 Closet, pedestal type, disconnecting and

plugging sewer connection and making good

all affected walls and floors No

34/186 Closet, pedestal type, with low level

glazed earthenware flushing cistern

flush pipe, double plastic sheet cover,

1/2" stop cork, trap etc. supplied &


fixed completed. No

35/186 Closet squatting type, with trap supplied

& fixed. No

36/187 Closet, squatting type, removed, sewer

connections plugged and floor made

good. No

40/188 Cocks, brass bib 1/2" supplied & fixed

(Heavy quality). No

66/193 Flushing Cistern fixed complete low level

(Ceremics).meterial available No

66a/193 Flushing cistern, low level, plastic

supplied and fixed complete. No

86/197 Mirror, bath room type, supplied &

fixed to wall with Rawl plugs and

plastic frames. No

147/214 Shower rose, 6" pvc supplied & fixed. No

153/215 Sink, glazed, earthenware 24"x15"x8"

supplied and fixed with waste plug,

complete (pedestal paid seperately). No

147a/214 Towel rail 2'-0" long 3/4" dia chromium

plated. No

171/219 Soap tray, white porcelain, supplied and

fixed to wall with rawl plugs. No

173/220 Stop cocks, 1/2" supplied & fixed No

Plastic L.D. make).


174/220 Stop cocks, 3/4" supplied and fixed.

Plastic L.D. make). No

175/220 Stop cocks, 1" supplied and fixed.

Plastic L.D. make). No

176/220 Stop cocks, 1 1/4" supplied and fixed.

( Plastic L.D. Model ) No

177/220 Stop cocks, 1 1/2" supplied and fixed.

Plastic L.D. make). No

178/221 Stop cocks, 2" supplied and fixed.

Plastic L.D. make). No

178a/221 As per Item No. 178a (Gate valve 2") No

English make

178b/221 Non return valve English 2" dia No

200/228 Tooth brush holder, chromium plated

supplied and fixed to wall with Rawl

plugs. No

292/240 Pipes pvc 1/2" supplied & fixed. L.ft

L.m

293/240 Pipes pvc 3/4" supplied & fixed. L.ft

L.m

294/240 Pipes pvc 1" supplied & fixed 1000 type. L.ft

L.m

294a/240 pipes pvc 1" supplied & fixed 600 type. L.ft

L.m
295/240 Pipes pvc 1 1/4" supplied & fixed 1000 type. L.ft

L.m

295a/240 Pipes pvc 1 1/4" supplied & fixed 600 type. L.ft

L.m

296/241 Pipes pvc 1 1/2" supplied & fixed. L.ft

296a/241 pvc pipe 1 1/2" (1000 type) supplied & L.ft

fixed with out excavation. L.m

296b/241 pvc pipe 1 1/2" (600 type) supplied & L.ft

fixed with excavation. L.m

296c/240 pvc pipe 1 1/2" (600 type) supplied & L.ft

fixed with out excavation. L.m

297/241 Pipes pvc 2" (1000 type) supplied & fixed. L.ft

With excavation L.m

297a/241 pvc pipe 2" (1000 type) supplied & L.ft

fixed with out excavation. L.m

297b/241 pvc pipe 2" (600 type) supplied & L.ft

fixed with excavation. L.m

297c/241 pvc pipe 2" (600 type) supplied & L.ft

fixed with out excavation. L.m

310/243 Eaves gutters 6" square type pvc fixed L.ft

with PVC brackets. (1' - 6 " Crs) L.m

311/244 Down Pipe 3 1/2" Dia P.V.C Fixed with L.ft

Wooden Plug to wall etc. L.m


311a/244 PVC 4" ( 600 type ) pipe supplied and fixed on walls L.ft

L.m

5/245 Drains, pvc 400 type 4" laid on cement

concrete 6" thick upto 2'-0" depth of

invert including excavation and cement L.ft

concrete haunching (1:3:6 - 1" metal). L.m

13/246 Gulley pvc 6" supplied & fixed including

gulley box. No

18/247 Manhole 2'x2' and upto 2'-0" deep, 9"

thick brick in cement 1:3 walls & cement

rendered 1/2" (1:2) with 6" cement conc.

foundation 1:3:6 (1" metal) including

forming channels but without cover. No

19/247 Manhole 3'6"x2'3" & 2'0" to 4'0" deep

- do - - do -. No

20/248 Manhold 3' 6" x 2' 3" & 4' to 6' deep 9" thick No

-do -do-

23/248 Manhole cover reinforced concrete 3"

thick 2'-0x2'-0" approx. supplied & fixed no

reinforced with 1/4" dia M.S.rods at

3" centres both ways.

26/249 Wire dome for 2" pipe supplied and fixed no

1/D 110mm PVC inspection joint supplied and fixed No

2D 110mm PVC inspection "Y" joint supplied and fixed No


3D 110mm PVC Bend ( 11 Deg.) supplied and fixed No

4D 110mm PVC Bend ( 22 Deg.) supplied and fixed No

5D 110mm PVC Bend ( 60 Deg.) supplied and fixed No

6D 110mm PVC Bend ( 88 Deg.) supplied and fixed No

7D 110mm PVC "T" Junction supplied and fixed No

8D 110mm PVC "Y" Joint supplied and fixed No

9D 50mm Bottle trap supplied and fixed No

10D 110mm PVC Inspection bend supplied and fixed No

11D 63mm PVC "Y" Joint supplied and fixed No

12D 110mm PVC Elbow supplied and fixed No


'APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE

'MISCELLANEOUS..

Item Description Unit

6/251 Fence barbed wire ,14 gauge,

4 points, 3" sparts, supplied and fixed in L.ft

existing timber posts with G.I staples. L.m

15/253 Intermediate fence posts or structs, cement

concrete 1:1 1/2:3(3/4") reinforced with

4 Nos. 1/4 dia. M.S.rods 5'-7" high square

section 4" to 6" fixed complete as per

drawing No.68 of 22.07.1936. per post

16/253 - do - - do - 7'6" high - do -. per post


17/253 End post and strut for Type barbed wire

fence fixed complete in cement concrete

as per Drg. 68 of 1936. per post

18/254 Fence barbed wire, 7 strands 14

B.W.G with 4 points at 3" centres and

R.C.C posts (1:2:4) 3/4" metal reinforced

with 4 Nos. 1/4 rods with 14 B.W.G

stirrups at 8" centres including post to

be fixed at 8'-0 crs' excavation cement

concrete foundation '1:3:6(1 1/2") metal

to corner posts and 'structs and straining

bolts, all as per type 'plan 68 of

22.07.1936 structs to be 'reinforced

with 4 Nos. 3/8" rods and 'corner posts

with 4 Nos. 1/2" rods. ( including L.ft

white washing 2 coats) L.m

18A/254 - Do - - do - - do -

- do - 6 Strands - do - - do - L.ft

- do - - do - - do - L.m

19/254 Straining Bolts 1/2" dia made and fixed

18" long (Approx). No

21/255 Well, bailing out water 5' to 7' dia. Upto

20' depth including cleaning well. L.ft

^ ^ANGLE IRON
Item Description Unit

1/A Supplying and fixing 50mmx50mmx6mm thick

Angle iron purlin fixed to wall at not exeeding


900mm centres and joints should be bolted with

2Nos 12mm dia bolts and nuts other site welding

with cleats minimum length 450mm in next reduced

angle iron including two coats of Anticorrosive paint

as directed & including anchoring purlins with 2 nos

10mm tor steel welded to purlins where ever necessary and L.ft

with 1:2:4 concreting. L.m

2/A 62.5mmx62.5mmx6mm Angle iron purlin L.ft

-DO- -DO- L.m

3/A 75mm x 75mm x 6mm Angle Iron purlin L.ft

-DO- -DO- L.m

4/A End Truss-2/50mm x 50mm x 6mm L.ft

Per 7'-0" including 1:2:4(3/4) concreting 2nos L.m

12mm dia 9" long welded to end truss

with 2 coats of anticorrosive paint

5/A End Truss-2/62.5mm x 62.5mm x 6mm L.ft

-DO- -DO- L.m

6/A End Truss-2/75mm x 75mm x 6mm L.ft

-DO- -DO- L.m

7/A 25mm x 6mm - Flat Iron - 1'-0" long

weld to end purlin as bracket to fix valance

board with two coats of anticorrosive paint

& bolts & nuts No

8/A 31mm x 6mm - Flat Iron - 1'-0" long No

-DO- -DO-

9/A 2/3" x 3" x 1/4"(2/75mm x 75mm x 6mm) L.ft

angle iron slope beam including 1:2:4(3/4") L.m

concreting with 4 nos 16mm 9" long Rag bolt


with 2 nos 9"x9" 10mm Ms base plate

10/A Supplying & fixing 'H' iron 6" x 3" 6mm L.ft

with necessary cleats to housing props L.m

including 2 coats of anticorrosive painting

11/A Supplying & fixing ' H ' Iron 8" x 4" L.ft

(6mm) with necessary cleats L.m

-do -

12/A G.I. Gate with 12'-0" x 4'-6" hight 2 Nos sashes made

out of 1 1/2" dia G.I. heavy quality frame with

6mm M.S. rod welded 3" c/c both ways all as per

Drg. No. 409853 fixed with 9" x 9" RCC pillar in

1:2:4(3/4") concrete 4Y12 reinforced and R6 at 6" crs.

stirrups rate include for Excavation base concrete

footing R/F with

Y10 @ 8" c/c both way 5/8" thick 1:4 plastering 4 Nos. pintol

and stirrups locking divice barrel bolt etc. and 2 coats

Anticorrosive paint and 2 coats enamel paint per piller

& 2 coats ofwhite washing to pillers as directed


ALUMINIUM WORK

Item Description Unit

1/AL Aluminium Partition with sliding door S.ft

m2

2/AL Aluminium Casement with project S.ft

m2

3/AL Aluminium Door frame only S.ft

m2

4/AL Aluminium door fully glazed double hung S.ft

m2

5/AL Al Double hung Door with panneled and S.ft

glazed m2

6/AL Al single hung Door with fully glazed S.ft

m2
7/AL Al Single hung Door with panneled and S.ft

glazed m2
APPROVED B.S.R FOR THE FIRST HALF 0F 2003 IN TRINCOMALEE

DEMOLISHER.

RATE (1st)

973.00

344.00

778.00

275.00

247.00

26.60

1667.00

179.00

2408.00

259.00

281.00

30.20

304.00

33.00

371.00

556.00

57.00
86.00

3.90

12.80

12.00

RATE (1st)

18.00

59.00

278.00

30.00

371.00

16.90

182.00

2.40

7.90

3.60

11.80

14.20

153.00

139.00
416.00

45.00

625.00

67.00

524.00

56.00

719.00

77.00

1216.00

430.00

778.00

275.00

RATE (1st)

741.00

195.00

21.00

292.00

31.00

224.00

931.00

100.00
1125.00

121.00

2.40

7.90

3.60

11.80

542.00

58.00

APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE

CONCRETOR.

RATE (1st)

20647.00

7296.00
21388.00

7558.00

22842.00

8071.00

20840.00

7364.00

21353.00

7545.00

23583.00

8333.00

24675.00

8719.00

25416.00

8981.00

286.00

938.00

120.00

394.00

162.00

531.00

218.00

715.00
315.00

118.00

111.00

1195.00

79.00

850.00

27551.00

9735.00

29.00

24048.00

8498.00

26830.00

9481.00

27571.00

9742.00

28682.00

10135.00

26700.00

9435.00
27441.00

9696.00

28552.00

10089.00

3988.00

429.00

60.00

646.00

16.00

172.16

43.00

463.00

26678.00

9427.00

27419.00

9689.00

8838.00

951.00

10712.00

1153.00
0.00

0.00

463.00

1518.00

16630.00

5876.00

6081.00

655.00

APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE

BRICKLAYER.

RATE (1st)

16820.00

5943.00

17690.00

6251.00

18559.00

6558.00
6593.00

710.00

6982.00

752.00

584.00

206.00

195.00

21.00

117.31

384.00

164.00

538.00

4121.00

329.00

1079.00

217.00

712.00

170.00

558.00

15894.00
5616.00

16357.00

5780.00

16941.00

5986.00

18108.00

6399.00

RATE (1st)

15823.00

5591.00

16379.00

5788.00
APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE

PAVIOR.

RATE (1st)

7.00

23.00

17.00

56.00

7868.00

611.00

107.00

847.00

128.00

1378.00

125.00

1350.00
APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE

PLASTERER.

RATE (1st)

12.00

39.00

20.00

66.00

1971.00

212.00

2110.00

227.00

1716.00

185.00
1855.00

200.00

2790.00

300.00

2975.00

320.00

2493.00

268.00

2679.00

288.00

587.00

63.00

3228.00

347.00

30.00

98.00

51.00

167.00

2601.00

280.00
3681.00

396.00

2348.00

253.00

1615.00

174.00

1681.00

181.00

13.00

42.00

2303.00

248.00
APPROVED B.S.R FOR THE FIRST HALF 2003 IN TRINCOMALEE

ROOFER.

RATE (1st)

10298.00

1109.00

4705.00

506.00

78.00

256.00

49.00

161.00

149.00

489.00

28.00

24.00
2750.00

296.00

185.00

20.00

370.00

40.00

2649.00

285.00

APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE.

CARPENTER & JOINTER.

RATE (1st)

95.00

310.00

42.00

452.00

11.00

36.00
12087.00

1299.68

14211.00

1530.00

RATE (1st)

14911.00

1603.00

10874.00

1171.00
1018.00

109.46

92.00

10.00

16.00

54.00

394.00

4234.00

252.00

2717.00

509.00

5472.00

377.00

4061.00

RATE (1st)

479.00
5155.00

416.00

4474.00

425.00

4568.00

487.00

5244.00

171.00

67.00

304.00

997.12

12.00

41.00

11.00

36.00
14294.00

1539.00

12093.00

1302.00

436.00

15387.00

1861.00

65672.00

504.00

5425.00

239.00

2575.00

2152.00

321.00

3458.00

365.00

3927.00
207.00

2230.00

219.00

2356.00

APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE.

PAINTER & DECORATOR.

RATE (1st)

42.00

50.00

70.00

741.00

80.00

1415.00
152.00

2114.00

228.00

1405.00

151.00

616.00

66.00

1136.00

122.00

534.00

58.00

607.00

65.00

957.00

103.00

1118.00

120.00

625.00

67.00

698.00

75.00
1049.00

113.00

1210.00

130.00

253.00

27.00

460.00

50.00

867.00

93.00

1507.00

162.00

120.00

12.90

208.00

22.00
APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE
BRASS FOUNDER.
RATE (1st)

138.00

185.00

170.00

154.00

102.00

300.00

379.00

277.00

128.00

56.00
869.00

1442.00

2066.00

3728.00

601.00

128.00

123.00

126.00

121.00
APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE

IRON MONGER.

RATE (1st)

298.00

636.00

60.00

199.00
37.00

124.00

RATE (1st)

152.00

498.00

342.00

1121.00

572.00

1875.00

APPROVED B.S.R FOR THE FIRST HALF OF 2003. IN TRINCOMALEE DISTRICT

EXCAVATOR.

RATE (1st)
529.00

187.00

622.00

220.00

725.00

256.00

3001.00

1060.00

2314.00

818.00

205.00

73.00
APPROVED B.S.R FOR THE FIRST HALF OF 2003 IN TRINCOMALEE

PLUMBER.

RATE (1st)

165.00

231.00

2979.00

485.00

889.00

612.00
6891.00

2022.00

866.00

232.00

619.00

2061.00

785.00

599.00

2936.00

410.00

293.00

234.00
267.00

280.00

433.00

463.00

538.00

1005.00

#N/A

320.00

13.00

42.00

20.00

65.00

39.00

129.00

28.00

92.00
53.00

175.00

42.00

138.00

73.00

65.00

213.00

47.00

154.00

38.00

126.00

118.00

388.00

110.00

361.00

71.00

233.00

63.00

206.00

88.00

288.00

81.00

264.00
227.00

743.00

357.00

1171.00

627.00

5097.00

8842.00

13518.00

797.00

85.00

533.00

611.00
246.00

250.00

341.00

485.00

744.00

713.00

302.00

557.00

86.00

457.00
RATE (1st)

4.20

13.80

808.00

901.00
4818.00

208.00

683.00

214.00

703.00

292.00

111.00

RATE ANALYSIS FIRST HALF OF 2003 IN TRINCOMALEE

RATE (1st)
121.00

397.00

145.00

474.00

173.00

569.00

363.00

1192.00

403.00

1323.00

455.00

1491.00

41.00

49.00

453.00

1485.00
#N/A

#N/A

81.00

265.00

21610.00
RATE ANALYSIS FIRST HALF OF 2003 IN TRINCOMALEE

RATE (1st)

353.00

3797.00

610.00

6569.00

143.00

1544.00

735.00

7906.00

733.00

7885.00

702.00

7550.00
700.00

7528.00
Code No Description Unit Rate
1 1 1/2" dia. Pvc pipe 1000 type L.ft 38.50
2 1 1/2" dia. Pvc pipe 600 type L.ft 25.00
3 1 1/4" dia. Pvc pipe 1000 type L.ft 26.00
4 1 1/4" dia. Pvc pipe 600 type L.ft 18.50
5 1" dia. Pvc pipe 1000 type L.ft 17.00
6 1" dia. Pvc pipe 600 type L.ft 10.50
7 1/2" dia. Pvc pipe 1000 type L.ft 6.30
8 2" dia. Pvc pipe 1000 type L.ft 67.00
9 2" dia. Pvc pipe 600 type L.ft 40.50
10 3/4" dia. Pvc pipe 1000 type L.ft 11.30
11 4" dia. Sewerage (SS) 250 type L.ft 48.50
12 4" dia. Sewerage (SS) 400 type L.ft 75.00
12b Anticorrosive paint gal 1085.00
13 Asbestoes flat sheet 1.2m x 1.2m S.ft 13.30
14 Asbestoes ridges Pairs 267.00
15 Asbestos corr. Sheet S.ft 21.35
19 Bamboos L.ft 120.00
20 Barbed wire L.ft 1.45
22 Barrel bolt 4" Brass oxidised no 75.00
23 Barrel bolt 6" Brass oxidised no 115.00
24 Basket no 50.00
25 Beading L.ft 4.00
31 Binding wire 14 B.W.G. lbs 36.00
32 Bitumen Gal 330.00
35 Board 1" thick (timber) S.ft 45.00
36 Brass Bib Tap 1/2" No 130.00
40a Brass screws 1 1/2" Doz 50.00
40c Brass screws 3/4" Doz 30.00
40d Brass Screws 1" Doz 39.00
41 Bricks No 2.60
44 Castm. stays h. qual 10" brass oxidised No 90.00
45 Castm.fast. Brass oxi. H. qlty ,mort.plate No 90.00
46 Cement CWT 345.00
47 Center pivot hinges br.oxi.h.qual. ( 4 pieces ) Set 45.00
50 Closet low level pedestal type (complete ceremic) No 3900.00
57 Distember Lbs 0.00
60 Draw rings 1 1 /2 dia. no 25.00
61 Earth ( Gravel Filling) Cube 590.00
63 Emulsion Paint ( Weather shield ) gal 1704.00
64 Emulsion Paint Lit 1345.00
65 Enamel Paint Lit 1698.00
66 Fanlight catch Brass oxi. Heavy qality No 30.00
70 Calicut pattern flat tiles No 11.00
73 G.I 20 B.W.G Sheets S,ft 65.00
74 G.I. 22 B.W.G.Flat sheet Sft 50.00
76a G.I.Hook 5/16"x4 1/4" no 6.00
77 Ginisappu timber 3/4" thick S.ft 50.40
81 Glass panes obscured(3mm) S.ft 45.00
81a Glass Panes Tinted (5mm) S.ft 60.00
85 Glue lbs 86.00
90 Gulley Box PVC 6" no 550.00
91 Half round tiles No 5.00
91a Bras Sancy 1 1/4" Doz 43.00
91b Cistern ceremic no 1400.00
91c Cistern plastic no 1150.00
94 Hinges 4"x3" Brass oxidised Pair 130.00
95 Hinges 4"x4" Brass oxidised Pair 195.00
95a Hinges 4"x2 1/2" Brass oxidised Pair 110.00
97 Hire of mixtur, vibrator, wages of operator Day 2520.00
98 Hold fast no 17.50
117 Iron screws 2" Doz 0.00
119 Iron T.hinges 10" No 58.00
120 Brass T hinges 10" Pair 0.00
123 Joists Class II 4" x 2" L.ft 7.50
126 Lime -Slaked Bushel 257.00
127 Limpet washers No 1.00
135 Metal 1 1/2" Cube 3500.00
136 Metal 1" Cube 3750.00
137 Metal 2" Cube 3350.00
138 Metal 3/4" cube 4100.00
139 Metal 6" to 9" cube 2000.00
140 Mild steel cwt 1773.00
141 Mirror with fittings no. 390.00
142 Mortice Lock Concord No 425.00
143 Mortice Lock Vinion double No 750.00
144 Lock Night Latch Bird No 275.00
145 Mortice lock Union English single leaver No 1500.00
146 Mortice lock Union English double leaver no. 2660.00
147 Mould oil gal 100.00
147a Mouldings L.ft 4.00
150 Nails 2" (GI) Ibs 30.00
153 Nails 3/4" (GI) lbs 30.00
157 P.V.C. end cap (Gutter Cap) no 38.00
158 P.V.C. gutter joint lb. 44.00
159 P.V.C. metre joint no 142.00
160 P.V.C. running head no 102.00
161 P.V.C.gutter 6" L.ft 37.00
162 P.V.C.Inspection joint 4" (110mm) No 350.00
163 P.V.C.Inspection "Y" joint 4" (110mm) no. 415.00
164 P.V.C.Bend (11Deg) - 4" (110mm) no. 110.00
165 P.V.C.Bend (22Deg) - 4" (110mm) no. 113.00
166 P.V.C.Bend (60Deg) - 4" (110mm) no. 190.00
167 P.V.C.Bend (88 Deg) - 4" (110mm) no. 310.00
168 P.V.C.Pipe 4" 600 type L.ft. 48.50
169 P.V.C.Pipe 4" 400 type L.ft. 60.00
171 Paint oil Enamel gal 1698.00
181 Planks 1 1/4" Sft 96.00
181a Planks 1" Special Upper Class Timber sft 94.00
182 Planks 1" Class II s.ft 45.00
182b Planks 3/4" sq.ft. 90.00
183 Plastic cistern low level (Plastic ) no 1150.00
184 Plugs no. 2.00
186 Plywood door 2"-3" x 6'-9" no. 0.00
187 Plywood door 2'-3" x 6'-9" ( Marine) no 1490.00
188 Plywood door ord 2'-9" x 6'-9" no 1467.00
189 Pressed Tiles 8" x 8" no. 0.00
190 Primer gal 1485.00
191 Pudlo cement lbs 30.00
192 Red cement lbs 148.00
193 Reepers L.ft 8.00
193a Reepers Cl.II 2"x1" L.ft 8.00
194 Ridge tile no. 23.00
196 Rim lock 6" 2 leaves Brase No 425.00
197 River Sand Cube 1700.00
198 Drive screws and washers no. 6.00
198a Ring 1 1/2" Brass no 25.00
199 Rawl plugs & 2" Screws No 15.00
200 Sand Fine cube 1500.00
205 Sash bars 1 1/2"x1 1/2" L.ft. 8.00
207 Screws 1 1/2" doz. 0.00
207a Screws 1" brass Doz 0.00
207b Screws 2" doz 66.00
211 Sink 24"x15"x8" with waste plug & chain no 1810.00
214 Skilled labour Gr.Il day 450.00
215 Skilled labour Gr.I day 500.00
216 Slacked lime Bushel 0.00
218 Soap tray no 164.00
220 Spur stones no. 10.00
222 Squating pan with trap no 700.00
224 Staining Bolts no. 40.00
225 Staples Doz 20.00
227 Stop cock L.D model 1/2" no 77.00
228 Stop cock L.D model 1 1/4" no. 0.00
232 Tar Gal 0.00
232a Tiles 1'-0"x1'-0" floor no 65.00
236 Tiles 6" x 6" white no 0.00
236a Tiles 6"x6" colour no 13.40
236b Tiles 4"x4" white no 0.00
236c Tiles 4"x4" colour no 5.75
245 Timber purlins c.ft. 1036.00
248 Tooth brush holder cromium plated no 100.00
249 Tor steel cwt 2084.00
250 Towel Trail holder chromium plated no 275.00
255 transport 1 st Mile 1 mile 0.00
1002 transport every additional Miles 1mile 0.00
257 Unskilled labour day 300.00
260 Varnish gal 1673.00
263 Wash basin 22"x16" no. 1473.00
264 1/2" Nut & Washers No 3.00
267a Wire nails 2" lbs 30.00
268 Wood plugs no 0.00
268a Wood preservative gal 300.00
269 Yellow ocare lbs 0.00
270 Wire dome for 2" pipe No 60.00
300 2"X2" Class II Battens Lft 17.50
301 3/8" dia 18" Bolts,Nuts & Washers No 12.00
302 Grey Cement Kg 7.50
303 Rawl Plugs and Screws No 0.00
304 Culicut Tiles No 0.00
308 Stopcock LD Model 1/2" (Plastic) No 0.00
309 Stopcock LD Model 3/4" (Plastic) No 104.50
310 Stopcock LD Model 1" (Plastic) No 143.00
311 Stopcock LD Model 1 1/4" (Plastic) No 213.33
312 Stopcock LD Model 1 1/2" (Plastic) No 291.50
313 Stopcock LD Model 2" (Plastic) No 354.20
314 Shower Rose 6" No 95.00
317 pvc gutter brackets No 9.20
318 Solvent cement 50g Tin 43.00
319 Steel Rods 1/4" dia Lbs
320 Cost of Junction No
321 Earth Pipe 2"x5' No
322 Plug with Switch (clipsal) No
323 3/.036 wire m
324 Sunk box No
325 Screws Brass 1 1/2"x10" No
326 Earth wire 7/.029 m
327 Wiring clips and panel pins (Allow)
328 Round plug No
329 Ceiling rose No
330 Holder No
331 Flexible wire m
332 Screw 1/2"x6 No
333 Switch clipsal No
334 1/.044 wire m
335 Sunk box No
336 Brass screws 1 1/2"x6 No
337 Brass screws 1 1/2"x10 No
338 Brass screws 1 1/4"x6
339 Brass screws 2"x10
340 Brass screws 1"x 6
341 Brass screws 2"x10
342
343
344 Angle iron 2"x2"x1/4" L.ft 55.50
345 Angle iron 1 1/2"x1 1/2"x1/4" L.ft 42.75
346 Angle iron 2 1/2"x2 1/2"x1/4" L.ft 79.00
347 Angle iron 3"x3"x1/4" L.ft 99.35
348 Making holes on angle iron No 5.00
349 H - iron 6"x3" (6mm) L.ft 265.00
350 H - iron 8"x4" (6mm) L.ft 280.00
351 1" x 1/4" Flat iron L.ft 13.75
352 1/2"x1" Bolts & Nuts No 6.00
353 Fillets (Class I local timber for beeding) L.ft 0.00
354 Fillets 1/2" x 1/2" L.ft 3.00
355 Ball valve 1/2" No 90.00
356 Ball valve 3/4" No 145.00
357 Cistern only ceremice No 1400.00
357a Cistern plastic No 1150.00
358 Fittings ( For commode & cistern ) Item 350.00
359 Seat cover ( Double ) No 350.00
360 Brackets (For cistern ) Item 54.00
361 Flush bend No 35.50
362 Tightning hook bolts No
363 4" Sandcrete Block No 0.00
364 110mm PVC "T" Junction No 526.00
365 110mm PVC "Y" Joint No 500.00
366 50mm Bottle trap No 150.00
367 110mm PVC Inspection Bend No 370.00
368 63mm PVC "Y" Joint No 0.00
369 110mm PVC Elbow No 287.00
370 PVC down pipe 3 1/2" Length 317.00
371 PVC socket 3 1/2" No 0.00
372 PVC elbow 3 1/2" No 61.00
373 PVC clips 3 1/2" No 9.00
374 1 1/4" x 1/4" Flat iron Lft 20.00
375 1/2" (12mm) Bolt & Nut No 6.00
376 9" x 9" 3/8" M.S. plate No 110.00
377 1/2' x 1 1/2" Rag bolt No 6.00
378 2" x 1/4" Flat iron L.ft 35.00

ALUMINIUM MEMBERS
379 70S-1002-1 L.ft 64.60
380 70S-1102-1 L.ft 44.50
381 70S-1202-1 L.ft 46.40
382 70S-1402-1 L.ft 52.90
383 70S-1503-A L.ft 78.10
384 70S-1704-A L.ft 79.40
385 70S-3002-1 L.ft 85.00
386 70D-1910 L.ft 24.30
387 100D-1914 L.ft 24.30
388 100D-1917 L.ft 32.80
389 100D-3004-A L.ft 124.50
390 100D-3203 L.ft 129.10
391 100D-3207 L.ft 169.00
392 100D-3502 L.ft 148.70
393 100D-3503-A L.ft 160.90
394 CA-1001 L.ft 84.30
395 CA-1002 L.ft 134.20
396 CA-2001-A L.ft 88.90
397 PT-5153 L.ft 15.50
398 PT-5154 L.ft 30.50
399 PT-5157 L.ft 56.30
400 P-1113 L.ft 40.75
401 80S-1801 L.ft 57.85
402 BD-1066 ( Handle ) Pair 350.00
403 Lock ALPHA No 750.00
404 Door Closer No 1645.00
405 5mm thick tinted glass S.ft 60.00
406 6mm thick Plywood sheet ( ordinary ) S.ft 20.85
407 Formica sheet S.ft 18.00
408 Rubber Beading for Aluminium fittings L.ft 3.00
409 Welded mesh S.ft 10.00
Allowing of water
410 Type 1 Sum 125.00
411 Type 2 Sum 250.00
412 Type 3 Sum 75.00
413 Type 4 Sum 50.00
414 Type 5 Sum 25.00
415 Allowance type 1 Sum 100.00
416 Allowance type 2 Sum 150.00
417 Allowance type 3 Sum 10.00
418 Allowance type 4 Sum
419 Allowance type 5 Sum
420 Allowance type 6 Sum

Вам также может понравиться