Вы находитесь на странице: 1из 66

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

STANDARD OPERATING PRACTICES


1X 20 MW CAPTIVE POWER PLANT

TRINETRA CEMENTS ,BANSWARA,RAJASTHAN

THERMAX

POWER DIVISION
THERMAX LTD,
PUNE

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

THERMAX LTD.
POWER DIVISION (O& M)

1X 20 MW POWER PLANT
OPERATING PRESSURE: - 88 KG/ Sq. cm.
OPERATING TEMPERATURE: - 5205 Degree C.
STEAM GENERATION: - 95 TPH BFG BOILER

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

THIS SECTION COVERS BOILER ACCESSORIES AND


MOUNTING DETAILS & SOP
WATER TUBE,
SINGLE DRUM, TOP SUPPORTED,
CFBC BOILER
OPERATING PRESSURE: - 43.0 Kg. / SQ.CM.
OPERATING TEMPERATURE: - 4405 0 CEN.
STEAM GENERATION: - 22 TPH BFG FIRED BOILER
SAFETY VALVES

NOS.-03

DESCRIPTION

DRUM 1

DRUM 2

SH

MAKE

TYCO SANMAR LTD.

TYCO SANMAR LTD.

TYCO
LTD.

SET PR.

53 KG/CM2

54 KG/CM2

50.5 KG/CM2

TAG NO.

1-PSV 2196

1-PSV 2197

1-PSV 2193

RELIEVING CAP.

9680 KG/HR

9680 KG/HR

4840 KG/HR

TYPE

SPRING LOADED

SPRING LOADED

SPRING LOADED

SIZE ORIFICE

1.5 H2 3

1.5 H2 3

1.5 H2 3

FLUID

SAT. STEAM

SAT. STEAM

SH STEAM

Prepared by: Thermax Limited, Power Division (O&M)

SANMAR

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

OPERATING TEMP.

270C

BOILER FEED PUMPS

SOP

270C

NOS.-02

MAKE

KSB PUMPS, PUNE

TYPE

HAD 50/14

SL. NO.

5111016442

CAPACITY

27 M3 /HR.

HEAD

655 MTRS

SPEED

2900 RPM

PUMP POWER

76.9 KW

BEARING OIL

SERVO VG 46

SPECIFIC GRAVITY

0.9429

SHUT OFF HEAD


NPSH

772 M
4.1 M

NOM.EFFICIENCY

60%

SHAFT SEAL TYPE &


SIZE
MOTOR

MECHANICAL
SEAL,ESSIL NFAF
P13
CGL(90KW/2960)

COUPLING
MAKE/TYPE/SIZE
BFP MOTOR BRG.
D.E./ND.E

MAKE RATHI/GEAR
TYPE WITH SPACER
6315 FOR BOTH
ENDS

BURNER

Prepared by: Thermax Limited, Power Division (O&M)

445C

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

MAKE

SOP

THERMAX BABCOCK
AND WILCOX LTD.
FORCED

OPERATING
DRAUGHT TYPE
TYPE OF AIR
CONTROL
ACCOSSORIES
AIR QUANTITY FOR
BURNER
EXCESS AIR
FUEL FLOW AT
MCR(INDICATIVE)
NO.OF FLAME
SCANNER

LEAD LAG
ARRANGEMENT,VALVE
AT FAN SUCTION
CONTROL
24805KG/HR FOR BFG
33% BFG
33117 KG/HR (100%) BFG
2NOS

DM WATER TRANSFER PUMP 02


MAKE

GRUNDFOS

MODEL NO

A96571029P10938

TYPE

CRNCM5-13A-FGJ-G-VHQQV

DISCHARGE

5.8 M3 /HR

HEAD

66.1 MTRS

SPEED

2899 RPM

MOTOR MAKE

CG

MOTOR TYPE

MMG0901-2-24-FT-115-E2

MOTOR
POWER

2.2 KW

BRG.D.E/N.D.E

6305ZZ/6205ZZ

FANS
DUTY
CONDITION

UNIT

MAKE
MODEL
QUANTITY

NO.

FD FAN

ID FAN

SCANNER COOILNG
FAN

FLAKTWOOD(INDIA)
LTD.
HABB-7-063-115-02-6-1

FLAKTWOOD(INDIA)
LTD.
HABB-7-112-183-04-18
1X100%

FLAKTWOOD(INDIA)
LTD.
HD-8-41-C-R3

1X100%

Prepared by: Thermax Limited, Power Division (O&M)

2X100%

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

NATURE OF
MEDIUM
DESIGN MASS
AIRFLOW
AIR TEMP. AT
FAN INLET
ABSORBED
POWER AT
OPERATING
TEMP.WITH
SPEED
CONTROL
FAN SPEED

SOP

CLEAN AIR

CLEAN AIR

CLEAN AIR

KG/SEC

8.3

19.3

0.07M/SEC

DEG.CEN.

55

195

40

KW

35

95

1.3

RPM

1447

980

2900

22218 CK,
HOUSING SNA 518
,SAME FOR BOTH
ENDS
45KW,4 POLE,FRAME
SIZE-ND 250M,MAKE
CG
RESILIENT
TYPE,MAKE-GBM
NO-8MC-108Z-MZ67

22222 EK/C3
HOUSING SNA 522,
SAME FOR BOTH
ENDS
110KW,6
POLE,FRAME SIZEND 315 LX,MAKE CG
RESILIENT
TYPE,MAKE-GBM
NO-11MC111Z-M-308

HOUSING NO. SNA


508-607,BRG.FOR
OUTLET DAMPER
FL204(UC 202)
3.7 KW,2 POLE,
,MAKE MARATHON

FREE/FIXED
BEARING
MOTOR
COUPLING
MODEL
/MAKE

RESILIENT
TYPE,MAKE-GBM
NO-IFC-101ZK-K18/35

LP DOSING SYSTEM
SL
NO.

DESCRIPTION

PARAMETER
HP DOSING SYSTEM

LP DOSING SYSTEM

MAKE

RAVI INDUSTRIES

RAVI INDUSTRIES

I.D.750X750HTX5THK./300LI
T.
0-10LPH. 61 KG/CM

I.D.750X750HTX5THK./300LIT

TANK(SS) SIZE
VOLUME
PUMP
CAPACITY/PRESSURE
PUMP MAKE

METACHEM

METACHEM

TYPE & SPEED

RECIPROCATING
PLUNGER,VARIABLE
STROKE

RECIPROCATING
PLUNGER,VARIABLE
STROKE

NO. OF PUMPS

2 SET

2 SET

0-10LPH. 6KG/CM

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

MOTOR

MOTORIED
AGITATOR / MOTOR
PRESSURE RELIF
VALVE SET
PRESSURE

SOP

0.5HP,0.37KW,1500RPM,450
V,TEFC IP55
0.5HP,0.37KW,1500RPM,450
V,TEFC IP55
75 KG/CM

0.5HP,0.37KW,1500RPM,450V,
TEFC IP55
0.5HP,0.37KW,1500RPM,450V,
TEFC IP55
10KG/CM

MOUNTINGS
DRUM GAUGE GLASS - LHS & RHS
MAKE
PRODUCT S.NO.

CHEMTROLS SAMIL (I)


PVT.LTD.
LG-2579/2578

VISIBILITY

320 MM

TAG No.

1LG-2199/2198

SIZE

1X600 #,C/C500 MM

ATTEMPERATOR

NOS. -01

ACTUATOR
MAKE

FISHER

SIZE

34 INCH

SR. NO.

TA45844

TRAVEL

INCH

VALVE BODY
MAKE

FISHER

SIZE

1 INCH

SR. NO.

TA45844

TYPE

FZ

PORT SIZE

1/4INCH

ATING

600RF

PLUG

316 SST/COCR-A FQL-2

STEM

316 SST

BODY

WCC

SEAT

316SST/COCR-A

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

SOOT BLOWER
MAKE- SITSON INDIA LIMITED
SL
NO.

DESCRIPTION

TYPE OF SOOT BLOWER


ROTARY SB

SB NUMBER

SB 1

SB 2

SB 3& 4

SB 5& 6

QUANTITY

1 EACH

1 EACH

1 EACH

1 EACH

LOCATION

PSH

SSH

ECONOMISER

BLOWING PRESSURE
KG/CM (G)
BLOWING ANGLE
DEGREES
STEAM CONSUMPTION
(KG/NOZZLE/MIN)
NOZZLE

21

21

21

CONVECTION
BANK
21

360

360

SB 3-180
SB-4-360
2

SB- 5 360
SB-6 180
2

20 ODX 20 LG

20 OD X 20 LG

20 OD X 20 LG

20 OD X 20 LG

BLOWING
TIME/BLOWER (MIN)

1&2

1&2

1&2

1&2

5
6
7
8

INDUCED DRAFT FAN (ID FAN).


START UP: For starting Boiler ID Fan proceed as stated below.
Ensure the tightness of all the foundation bolts, & the coupling bolts.
Ensure all interlocks (Motor & Fan) are Healthy.
Ensure Drum level is at NWL.
Ensure suction damper is in CLOSE condition.
Get the Required clearance from Field Engineer.
Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

Start the fan from LPB (LCS) or from PLC.


Open the suction damper as per requirement & observe Furnace Draft.
Check all parameters, Bearing temperatures, vibrations, Motor body
temperatures etc.
STOPPING: To Stop INDUCED DRAFT FAN follow below mentioned Steps.
Close the suction damper.
Give STOP command either from LPB (LCS) or from PLC.
ALLOWING FOR MAINTENANCE:
Local Push Button should be pressed.
Isolate from Electrical side.
FORCED DRAFT FAN (FD FAN).
START UP: For starting Boiler FD Fan proceed as stated below.
Ensure the tightness of all the foundation bolts, & the coupling bolts.
Ensure all interlocks (Motor & Fan) are Healthy.
Ensure ID fan is Running.
Ensure FD fan suction damper is in closed condition.
Ensure Furnace pressure is Normal.
Get the Required clearance from Field Engineer.
Start the fan from LPB (LCS) or from PLC.
Open the suction damper as per requirement & observe the FD air flow.

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

10

Check all parameters, Bearing temperatures, vibrations, Motor body


temperatures etc.
STOPPING: To Stop FORCED DRAFT FAN follow below mentioned Steps.
Close the Suction damper.
Give STOP command either from LPB (LCS) or from PLC.
ALLOWING FOR MAINTENANCE:
Local Push Button should be pressed.
Isolate from Electrical side.
SCANNER COOLING AIR FAN
START UP: For starting Scanner cooling air Fan proceed as stated below.
Ensure the tightness of all the foundation bolts, & the coupling bolts.
Get the Required clearance from Field Engineer.
Start the fan from LPB (LCS).
Open the manual suction damper.
Check all parameters, Bearing temperatures, vibrations, Motor body
temperatures etc.
STOPPING: To Stop Scanner cooling air fan follow below mentioned Steps.
Close the Suction damper.
Give STOP command either from LPB (LCS) or from PLC.
ALLOWING FOR MAINTENANCE:
Local Push Button should be pressed.
Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

11

Isolate from Electrical side.


BOILER FEED WATER PUMP (BFP).
START UP: For starting Boiler Feed Water pump proceed as stated below.
Ensure Deaerator level is Healthy.
Ensure all interlocks (Motor & also Pump) are Healthy and in Service.
Pump and Motor are properly lubricated and Oil cups contain Oil up to
NORMAL LEVEL.
Keep Feed control valve (FCV) & its by-pass valve are in closed position.
Ensure CT sump level is NORMAL, CT Fans are running, ACW pump is
running.
Ensure cooling water I/L & O/L valves for Bearings cooling, Gland cooling &
etc. are opened.
Ensure SUCTION DP is below 0.2 kg/cm2.
Open SUCTION Valve.
Keep DISCHARGE valve closed.
Ensure Min Re-circulation & Balancing Leak off line Valves are opened.
START pump either from LPB (LCS) or PLC.
Gradually open DISCHARGE Valve.
Check all parameters, Bearing temperatures, vibrations, Suction/Discharge
pressures, balance leak off pressure Motor winding temperatures etc.
STOPPING: To Stop BOILER FEED PUMP follow below mentioned Steps.

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

12

Isolate the feed water control valve and Discharge valve.


Give STOP command either from LPB (LCS) or from PLC.
IF THE PUMP IS KEPT AS STAND BY:
Dont Isolate:
a).Gland Cooling Water, Bearing Cooling Water Lines.
b).Suction Valve, Balancing Leak-Off Valve, Discharge Valve,
ALLOWING FOR MAINTENANCE:
Isolate the bearing cooling water Line valves.
Isolate Gland Cooling Water.
Isolate the Suction Valve.
Isolate Discharge and min-recirculation valves.
Isolate Balancing Leak-Off Valves.
Isolate from Electrical side.
BOILER GAUGE GLASS OPERATION
This procedure is applicable wherever maintenance activities of gauge glass has been
completed, and cleared for service. Assume that all the isolating valves on steam and
waterside are closed and drains and vents are open. Follow the below steps to take
boiler gauge glass in service.

Close gauge glass vent valve (s).

Open steam side isolation valve partly.

Allow steam to flow through drain to heat up gauge glass at least for
fifteen minutes.

Close drain and see that steam is getting condensed in the gauge glass
to build up level.
Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

13

When condensate level in gauge glass is found to be more than 50%,


open water side valve gradually.

See that the level is stabilized at 50% of gauge glass.

Open both steam and water side valves full.

Match level of gauge glass with that of control room indication.

TO FLUSH GAUGE GLASS


Follow the steps given below to flush the gauge glass. Flushing of gauge glass should
be carried out at least once in a day.

Close steam side valve.

See that gauge glass is filled with water.

Close waterside valve and drain valve of gauge glass.

Crack open steam side valve.

See that gauge glass gets emptied.

Repeat above said activities at least twice.

Normalize the gauge glass valves and match local level with that of
control room indication

CHARGING OF MAIN STEAM LINE:

Ensure that boiler has achieved at least 60% of its rated pressure.

Ensure that all the drain line valves are open along with steam trap by
pass.

Open MSSV by pass when the steam pressure reaches 10 Kg/cm2, and
ensure heating of line till dry steam is coming out of all the drains.
Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

14

Increase the pressure by throttling all the drains and heat up for another
10 min.

Once dry steam is observed to come out from all the drains, close the
steam trap by pass and keep all the traps in service.

Increase pressure of the steam line by throttling all the drains in such a
way that pressure before and after MSSV should be near about same
then open the Boiler MSSV.

Increase pressure and temperature as required for turbine start up.

It is to be noted that increase of temperature up to 300 C should be 3-5


C per minute. Above 300 C the increase of main steam line should be
5-7 C per minute.

DEAERATOR CHARGING:
Follow the steps below for charging of deaerator.

Ensure that deaerator is filled with DM water with above


60% level.
Deaerator vent is open.

Open the trap by pass drains in the Auxiliary line and


remains open till no condensate found.

Open the isolation valve of PCV slowly and operate the


PCV and TCV to maintain the 10 kg/cm2 pressure and 250C Temp.

Ensure that steam line is charged and Pegging steam line is


heated up to the Pegging steam PCV.

Open the Pegging steam PCV in such a way to maintain the


Deaerator operating pressure of 1 kg/cm2.

While charging steam to deaerator hammering/ rolling sound


will be observed from deaerator.

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

15

If the sound / noise is beyond tolerable limit, reduce the


steam pressure.
See that FW temperature is gradually increasing.

SOP

Once deaerator pressure at 1 kg/cm2 is achieved and


temperature is being maintained at 120 deg C, put PCV & TCV on
auto.
If bleed steam is available for change over, proceed as

follows.

Heat up the bleed line by opening the drain lines.

Ensure that Turbine inlet steam flow is 12 TPH before


charging the bleed line.

Ensure that turbine bleed steam pressure is around 10


kg/cm2, open the QCNRV.

Ensure that the steam has charged up to the Pegging steam


PCV, and then operate the pegging steam PCV in such a way to
maintain the deaerator operating pressure.
SOP FOR CHARGING PROCESS STEAM LINE.

Ensure drain before and after Process PCV is open.


Ensure that T.G Bleed steam pressure is around 10Kg/cm2g.
Communicate with BF control room to open the header drain.
After getting clearance from BF control room open manual isolation
valve fully & maintain the pressure of 6Kg/cm2g & Flow of 1.2 TPH
through PCV & FCV.
Ensure steam flow at BF battery limit.
Close all the Trap By-Pass drain valves once it is ensured no condensate
is entrapped in the system.
Incase bleed is not available maintain the same through Boiler PRDS-1
system.
Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

16

SOP OF PUMPS
DM TRANSFER PUMP
START UP: For starting DM transfer pump proceed as stated below.
When a PUMP is kept in Remote & Auto MODE Its Suction & Discharge will be kept open, unless specific logic & Protection
is implemented & its minimum recirculation valve is open condition.
START UP CHECKS
Ensure clearance from maintenance and get clearance from Field Operator to
start.
Ensure DM storage tank level is Normal.
All field instruments are in service.
Ensure SUCTION valve is in OPEN condition.
Coupling Guard is in position & fastened firmly.
Ensure DISCHARGE Valve is in CLOSED condition.
Ensure Deaerator Make Up control valve & its by- pass valve are in closed
condition.
Ensure Boiler initial filling line valve is in closed condition.
Ensure its minimum recirculation valve is in open condition.
Ensure that all the protections & interlocks are in service.
Give START command by operating LPB (LCS) or from PLC.
Once Pump achieves normal speed, Open DISCHARGE valve slowly.
Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

17

Check for any abnormal Sound, Current, Vibration, Bearing Temperatures etc
& Record.
STOPPING: To Stop a DM transfer Pump follow below mentioned Steps.
Give STOP command either from LPB (LCS) or from PLC.
IF THE PUMP IS KEPT AS STAND BY:
Dont Isolate:
A).Suction Valve, Minimum Recirculation Valve, Discharge Valve,
ALLOWING FOR MAINTENANCE:
START UP CHECKS: To Take MCW & ACW in to Service, Proceed as stated
below.
Coupling Guard is in position and fastened firmly.
Ensure all interlocks are Healthy (Motor).
Ensure that Cooling Tower sump level is up to Normal Working level.
Ensure Cooling Water Return line Valves inlet to CT is in OPEN condition.
Charge BFP cooling water, LO cooler, Generator cooler, sample cooler.
Ensure Pump SUCTION is in OPEN condition.
Ensure Pump DISCHARGE is in CLOSED condition.
Prime the Pump by opening Air Release valve on the Pump.
Start MCW & ACW pump and after ensuring pump rotates with full RPM,
gradually open DISCHARGE valve.
Check Motor Amps, Discharge pressure, vibration, bearing temperatures.

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

18

Maintain Required FLOW & HEADER PRESSURE by throttling Cooling


Water Return line Valves inlet to CT as per requirement.
Maintain the Sump level is Normal.
NOTE: Before putting MCW/ACW pump in AUTO
Isolate the Suction Valve.
Isolate Discharge valve.
Isolate from Electrical side.
COOLING WATER PUMP (MCW/ACW)
STAND-BY) Mode, Ensure pumps Suction and Discharge valves are open and
Priming of Pump is done.
STOPPING: To Stop MCW/ACW Pump follow below mentioned Steps.
Close DISCHARGE valve.
Give STOP command either from LPB (LCS) or from PLC.
ALLOWING FOR MAINTENANCE:
Close the Suction Valve.
Close Discharge Valve.
Isolate from Electrical side.
CONDENSATE EXTRACTION PUMP (CEP)
START UP CHECKS: To Take CEP in to Service, Proceed as stated below.
Ensure clearance from maintenance and get clearance from Field Operator to
start.
Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

19

Ensure Hotwell level is Normal.


Ensure Gland cooling & sealing water line valves are OPEN.
Ensure Hotwell level is just above NWL (Around 40%, before Starting CEP).
Vacuum balancing line valve is in OPEN condition.
Ensure Suction & Discharge Valves are in OPEN Condition.
Ensure Hotwell Level Control Valve is in CLOSE condition and Recirculation
control valve is in OPEN condition (Up-stream and Down-stream isolation
valves are in open condition and bypass valve is in CLOSE condition).
Ensure condensate I/L & O/L valve of Ejector condenser is opened.
Check Suction Strainer Differential Pressure (DP - < 0.5 kg/cm).
START pump either from LPB (LCS) or from PLC.
Put the pump in Re-circulation (Hotwell level control valve position 0)
mode, if passing through Hotwell level control valve is observed close
isolation valve before Hotwell level control valve.
After starting CEP adjust Discharge pressure by opening Recirculation
By- pass valve.
STOPPING: To Stop CEP follow below mentioned Steps.
Close DISCHARGE valve.
Give STOP command either from LPB (LCS) or from PLC.
IF THE PUMP IS KEPT AS STAND BY:
Dont Isolate:
a).Gland Cooling Water, Bearing Cooling Water Lines.
b).Suction Valve, Balancing Leak-Off Valve, Discharge Valve,
ALLOWING FOR MAINTENANCE:
Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

20

Isolate Gland Cooling Water.


Isolate the Suction Valve.
Isolate Discharge and min-recirculation valves.
Isolate vacuum Balancing line Valve.
Isolate from Electrical side.

SOP FOR FILTER CHANGE OVER AND CLEANING


CHANGE OVER: Follow the below mentioned steps for change over of filter. This
procedure is valid for duplex filter.
Filter DP (0.8) is high enough to change the running filter on to stand by
filter.
Ensure that stand by filter is provided with filter element, which is cleaned
or replaced with a new one.
Open the vent of the filter.
Open the filter equalizer line.
See that air is coming out of filter, close vent as soon as full bore liquid
comes out of it.
Change the position of the lever watching arrow facing to the direction of
stand by filter.
Observe that filter DP has come down to minimum DP position in the
indicator.
Close the equalizer line. Now choked filter is isolated and fresh stand by
filter is in service.
Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

21

SOP FOR CLEANING OF CHOKED FILTER ELEMENT


Follow below steps to clean or replace filter element.

Open drain and vent of choked filter.

Ensure complete draining of filter body.

Open the filter flange and remove the filter element(s).

Clean the filter body from inside.

Clean the filter element with fresh water and dry it with dry air.

Close the filter flange.

Close the drain of filter

Open the equalizer of filter to prime the filter.

Close filter vent when air is completely removed.

Check for any leakage from the flange. If no leakage persists, close
equalizer.

SOP FOR OIL COOLER CHANGE OVER:


This procedure is valid where duplex type oil cooler is provided. When running cooler
is required to do maintenance due to leakage, non-performing etc., it needs to change
over to standby one. Proceed as per below mentioned steps for cooler change
operation.
Ensure stand-by one ready for operation.

Ensure vents on both tube and shell side of the incoming cooler is
open.

Ensure the cooler drains are closed.

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

22

Charge Cooling water in the cooler and close waterside vents after
removing entrapped air.

Open cooler oil equalizer line. It takes some times to fill a cooler.

Close oil vent once entrapped air is completely removed.


Change the position of the lever watching arrow facing to the direction
of stand by cooler.

Check all the parameters of oil and cooling water.

Control oil temperature by operating CW valve.


SOP FOR EJECTOR SYSTEM

TO TAKE HOGGER IN SERVICE

Ensure that all the drains in the auxiliary steam line are in open
condition.

Before going for vaccum pulling seal the glands of Turbine.

Ensure air line valves are closed for service air ejectors.

Vacuum breaker valve is in closed condition.

Ensure that Steam for ejector is available at its design pressure &
temperature.

Open steam valve for hogger ejector and wait for few minutes till it is
ensured no water vapour is coming out fro the exhaust line.

Open the air valve of hogger ejector.

See that vacuum is being built up in the turbine exhaust system.

TO TAKE SERVICE EJECTOR OPERATION


Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

23

Ensure that CEP is in operation and Hotwell level is being maintained


on auto.

Ensure minimum quantity of condensate is flowing through ejector


condenser.

Identify the ejector set and Open steam for second stage ejector of
service ejector.

Open air line for second stage ejector.

Open steam for 1st stage ejector.

Open air lines for 1st stage ejectors.

Now hogger ejector and service ejector are in line.

ISOLATION OF HOGGER EJECTOR

Close air valve for hogger ejector.

Close steam for hogger ejector.

See that vacuum is being maintained by service ejector set

TURBINE-GENERATOR SECTION
TURBINE: - MAKE- SIEMENS
ALTERNATOR: - TD POWER SYSTEMS LTD.
GEAR BOX
:- TRIVENI ENGINEERING & INDUSRY LTD.

THIS SECTION GIVES YOU DETAILS OF TURBINE-GENERATOR AND OTHER RELATED


EQUPMENTS

& SOP
Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

24

TURBINE
MAKE-

SIEMENS

TYPE

HORIZONTAL,IMPULSE,MULTI STAGE,MULTI VALVE,AXIAL


FLOW,CONDENSING

MODEL NO.- SST200VE25A


POWER RATED : 4700KW
MAX.
: 4700KW
P INLET
41 KG/CM2

T INLET

P EXTR. 1

10 KG/CM2

T EXTR. 1

P EXHAUST

-0.9 KG/CM2

T EXHAUST

435 C
274.2 C
45.5 C

ALTERNATOR
MAKE TOYO DENKI POWER SYSTEMS LTD.
( AC GENERATOR )
OUTPUT

5875KVA

SPEED

1500 RPM

TYPE

TC125

NO. OF POLES

NO. OF PHASE

COOLING SYSTEM

IC81W7

ENCLOUSER SYSTEM

IP54

CURRENT AC

514 A

VOLTAGE AC

6600V

FREQUENCY

50HZ

TURBINE & GENERATOR GEAR BOX


Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

25

MAKE TRIVENI ENGINEERING & INDUSTRY LTD.


WORK NO.

2908

OIL VISCOSITY

ISOVG-46

SL. NO.

0600x000006HSGH

RATED SPEED
INPUT/OUTPUT

12056/1500
(RPM)

RATED POWER

5050 KW

RATIO

8.037

CONDENSER
MAKE :- GODAVARI ENGG. LTD.
ORDER NO

9422

NO OF
TUBES

1442

DESIGN

CONDENSER SURFACE
AREA
TUBE SIDE

PRESSURE

5 KG/CM

TEMPERATURE

50C

SHELL SIDE
1 KG/CM
100C

OIL CIRCULATION SYSTEM


MAIN OIL TANK

MAKE- ENPRO IMDUSTRIES PVT.LTD.


RESERVOIR
CAPACITY

445m

7000 LTRS

EMERGENCY OIL PUMP (DC DRIVE)


ROTARY GEAR PUMP

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

MAKE

SOP

26

MODEL

RDRN-200L

SIZE

DELPD PUMPS &


GEARS (P) LTD.
50 NB

PRESSURE

1.5 KG/CM2

SPEED

1500RPM

FLOW

200 LPM

MOTOR
MAKE

CROMPTOM
GREAVES

FREQUENCY

50HZ

POWER

2.2 KW

SPEED

1500 RPM

CURRENT

28AMPS

AUXILIARY OIL PUMP


MAKE

TUSHACO

PUMP MODEL

T3ST 70/54

PUMP CAPACITY

495 LPM

SPEED

1450 rpm

DISCHARG PRESSURE

5 KG/CM

MOTOR
MAKE

CROMPTON
GRAVES

TYPE

1LA0133-AY81

POWER

7.5 KW

SPEED

1450 RPM

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

FREQUENCY

SOP

27

50HZ

OVEF EXHAUST FAN


FAN
MAKE

TCF-NADI
INDUSTRIAL FANS

MODEL

TBR-R13V

VOLUME

700CMH

STATIC PRESSURE

150 MMWC

MOTOR
MAKE

CROMPTOM
GREAVES

TYPE

1LA0090-24A80

POWER

1.5 KW

SPEED

2860 RPM

LUBE OIL FILTER

02 Nos.

MAKE BHAGWATI FILTER LTD


TYPE

BASKET

DESIGN PR.

4 BAR

FLOW

325 LPM

MESH RATING

25 MICRON

CONTROL OIL FILTER

02 Nos.

MESH RATING

10 MICRONS

FLOW

46 LPM

PRESSURE

9.5 BARG

TYPE

BASKET

OIL COOLER
Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

28

MAKE - ENPRO INDUSTRIES PVT. LTD.


WORK ORDER :: 8080
MODEL

BEM

HEAT DUTY

170457 KACAL/HR

TEST PR

10.5 BAR

OIL CENTRIFUGE
MAKE- ALFA LEVEL
.
TYPE

MAB-103B-24

PUMP NO

4180365

SL NO

4180365/09

BOWL

524700-88

PRODUCT NO

881145-09-01

MAX.SPEED (BOL)

8571RPM

SPEED(MOTOR

1500RPM

POWER

MAX.DENSITY OF
FEED

1100KG/CU.MTR

MAX.DENSITY OF
SEDIMENT

PROCESS TEMP.
MIN/MAX

0/100 DEG.CENT

CONDENSATE EXTRACTION PUMP

5000KG/CU.MTR

02 NOS

MAKE

KSB

CAPACITY

22 M 3 /HR

TYPE

CPX-EO-40-250

HEAD

70 MT

SL. NO.

5111019641

MOTOR POWER

15KW

SPEED

3000 RPM

MOTOR

MAKE-ABB

MOTOR BEARING

DE-6309ZZC3,NDE6308ZZC 3

TYPE

HX160MLD2

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

MAIN COOLING WATER PUMPS


MAKE

SOP

29

02 NOS

PUMP BRG. NO.


D.E./N.D.E
CAPACITY

6309ZZ

TYPE

FLOW MORE PVTD.


LTD.
FIG 5821 SIZE 30H

HEAD

25MT

SPEED

1460 RPM

MOTOR
POWER

MAKE-ABB

MOTOR BEARING

DE - 6319 C3
NDE-6316C3

132 K.W.

AUXILARY COOLING WATER PUMPS NO

1430 M3/HR

02 NOS

MAKE

FLOW MORE PVTD. LTD.

PUMP BRG. NO.


D.E./N.D.E

6307

TYPE

FIG 5823 125X100 SIZE

CAPACITY

140 M3/HR

HEAD

30 MTRS

SPEED

1460 RPM

MOTOR
BEARING

D.E.-6310ZZC3
N.D.E.-6309ZZC3

MOTOR
POWER

MAKE- ABB
18.5 K.W.

STEAM EJECTOR
MOTIVE STEAM PR.

10 KG/CM2

MOTIVE STEAM TEMP.

350C

MOTIVE STEAM CONSUMPTION

300 KG/HR

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

STEAM CONSUMPTION FOR HOGGER

SOP

30

350 KG/HR

STANDARD OPERATION PRACTICE


FOR
TURBINE ROLLING.
COLD START-UP PROCEDURE.
Put Power, cooling water and air in service.
Check all valves of pressure gauges, pressure switches, level switches if they are
open.
Ensure Oil level in MOT (Main Oil Tank) is Healthy i.e. above 30%.
Start Oil Vapor Extraction Fan and energize Heaters in MOT to raise the Oil
Temp to 40-42C.
Start the Auxiliary oil pump, Control oil pump-1 and put the Emergency oil pump
and another control oil pump-2 in AUTO.
Keep the position of changeover valve of Oil Cooler to be taken into service.
Charge the water side of Oil Cooler after ensuring ACW Pump is in service (open
cooling water I/L valve 100% and open the cooling water side vent. Than open
cooling water O/L valve 100% after ensuring water is coming out from the water
side vent and than vent valve is to be closed.). Ensure water side drain valves are
closed. Ensure all water side drain & vent valves of stand by Oil Cooler are
closed.
Open the shell side vent of Oil Cooler to release the air entrapped inside the shell
and ensure drains of shell side are closed. Ensure shell side all drain & vent valves
of stand by Oil Cooler are closed. After ensuring oil is coming out from shell side
vent of Oil Cooler, vent is to be closed.

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

31

Open the Lube Oil Filter vent to release the air entrapped inside the Filter &
ensure drain of Lube Oil Filter is closed. All drain & vent of stand by Lube Oil
Filter are closed. After ensuring oil is coming out from vent of Lube Oil Filter,
vent is to be closed.
Open the Control Oil Filter vent to release the air entrapped inside the Filter &
ensure drain of Control Oil Filter is closed. All drain & vent of stand by Control
Oil Filter are closed. After ensuring oil is coming out from vent of Control Oil
Filter, vent is to be closed.
After Starting AOP Ensure OHOT (Over Head Oil Tank) Level is raised up to the
required Level.
Ensure Lube Oil Header Pressure is above 3.0 kg/cm2.
Ensure Lube Oil Outlet flow through Sight Glasses provided
Put the TG set on Barring gear for the following minimum periods of time:
Shaft Stand Still
Minimum Turning Time
o Less than 1 day
2 Hours
o Up to 7 days
6 Hours
o 7 to 30 days
12 Hours
o More than 30 days
24 Hours
Ensure all the steam drains, warm up vent are in open condition, use trap by- pass
in line during warm up of steam line.
Open Boiler MSSV by-pass at 10 Kg/cm2 and start line heating of PRDS system.
Open the Boiler MSSV at 25 Kg/cm2 and close the By-pass valve.
Close the Trap By-pass and take steam trap in line once it is ensured that all the
condensate is removed from the system.
Charge the gland sealing once the required pressure 10 kg/cm2 and temperature
above 250 C.
Maintain the gland sealing pressure and Temperature as mentioned below.
Front Gland Sealing pressure & Temp. - .08 Kg/cm2 & 400C.
Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

32

Rear Gland Sealing pressure & Temp. - .08 Kg/cm2 & 250C
o To maintain the Gland sealing temperature in Rear side TCV is
provided.
o Keep both the Gland sealing PCV and TCV in Auto.
Pull the Vaccum once the required Aux. Steam pressure 10 Kg/cm2 and Temp.
above 300C is achieved.
Open slowly Turbine MSSV by-pass valve till the pressure reaches 25- 30
Kg/cm2 (g) to ESV inlet.
Open the manual isolation valve of Turbine steam stop valve, once the all the
parameters achieved as mentioned below:
Turbine Inlet Steam Pressure- 40 Kg/cm2.
Turbine Inlet Steam Temperature-420C.
Vaccum Achieved (-0.9 Kg/cm2g).
From the keyboard of control and Protection (PLC) system give Reset and then
Run command to Turbine.
ESV will open with its pilot and thereafter fully open with the pressure rise in the
control valve block.
Check that LP valve demand is 100% closed and HP opening demand is around
18% to 19%.
Ensure in the field that three LEDs of the Solenoid valve will start glow also the
LP servomotor will close fully.
Live steam flows into the control valve block to warm up the valve casing and
then out to the drain. Temperature increases app.4C/min.
Close manually controlled drain from the control valve block after warming-up is
finished.

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

33

The speeding of the turbo set can be started by WOODWARD governor.


Speeding should be carried out according to start-up graphs, respecting the stand
still time (thermal conditions of turbine).
The MOP (main oil pump) feeds the oil system for all duties sufficiently. Cut out
AOP at app. 80-90% normal speed if not switched off automatically. Put AOP on
Auto mode.
Resulting matching of frequency, voltage, phase sequence &rotating field
direction of generator. In Auto synchronization the speed of the turbine,
frequency, voltage will be matched automatically.
After synchronizing increase the load to app. 2% of its rated load in order to avoid
the activation of reverse power relay.
Continue increasing the load according to start-up graphs by pushing the
corresponding keys on the WOODWARD Do not allow exhaust steam
temperature to exceed 105C.For cooling them spray condensate into the exhaust
hood neck.
Once the rated speed of the Turbine is achieved go for synchronizing, which can
be done either manually or Auto.
Manual synchronizing can be done by manually adjusting the speed of the turbine
GOVERNOR.
During loading check all parameters and check also the control stage pressure.
Check the cooling air temperature of generator and open cooling water to the air
cooler if required.
HOT START-UP PROCEDURE
Once the tripping reason is detected and the cause is eliminated, and ready to start
up then follow the steps: Keep the live steam line up to the emergency stop valve pressurized and gland
steam open unless turbine rests far longer than 60 minutes.

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

34

Open the Turbine drains trap by pass, it will be remain open until it is ensured that
no condensate is trapped.
The oil unit remains in full operation, maintain the oil temperature between 45C
to 49C.
Keep the Turning gear in permanent operation.
Open the ESV and raise the speed through WOODWARD GOVERNER.
Once the rated speed is achieved do the synchronization either manually or
automatically.

SIEMENS SYSTEM WRITE UP

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

Prepared by: Thermax Limited, Power Division (O&M)

35

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

Prepared by: Thermax Limited, Power Division (O&M)

36

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

Prepared by: Thermax Limited, Power Division (O&M)

37

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

Prepared by: Thermax Limited, Power Division (O&M)

38

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

Prepared by: Thermax Limited, Power Division (O&M)

39

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

Prepared by: Thermax Limited, Power Division (O&M)

40

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

Prepared by: Thermax Limited, Power Division (O&M)

41

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

Prepared by: Thermax Limited, Power Division (O&M)

42

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

Prepared by: Thermax Limited, Power Division (O&M)

43

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

Prepared by: Thermax Limited, Power Division (O&M)

44

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

45

Boiler Start up procedure

Boiler Hot start up


Boiler hot start up is called when boiler started with in 5-10 Hrs after shut down.
PREPARATION
Resume the power supply .
Ensure instrument air pressure 6.0 kg/cm2.
Aux. cooling water pressure & flow is sufficient.
All drains are closed, MSSV also closed.
All sample cooler inlet v/v should be closed.
There should be no pet coke in surge hopper & in DCF.
Start BFP as per requirement.
Start booster pump.
BOILER START UP PROCEDURE
Open the start up vent.
Fill the drum up to NWL through 40% FCV.
Now start the ID fan open suction & discharge damper and maintain furnace draft -1 or -2
mmWC.
Start SA fan and maintain SA pressure 400 mmWc.
Now start PA fan & opened suction damper 100%.
Gradually increased PA air flow.
Continuously watch on bed temp.
Start DCF at minimum rpm.
Once there will be sudden rise in bed temp, so start screw feeder to control bed temp.
Now watch the bed temp. If it is increased rapidly stop DCF.
Now increased PA air flow 40-45TPH.
Now increased DCF speed as per behavior of bed temp.
Start bed material RAV for bed inventory.
When bed temp. Reached 850-900 degree stable boiler on coal
Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

46

As the steam temp. & pressure achieved charged the steam line.
Closed the start up vent and main steam drain before, after.
Put furnace draft in Auto.
Set SA pressure as per requirement & put both SA fan in auto.
Watch the drum level and put it in auto.

BOILER OPERATING PROCEDURES


1. START UP OF A COLD BOILER
START UP OF A COLD BOILER
Boiler start up can be termed as cold startup when
1. the boiler has been idle for more than 1 or 2 days
2. there is no pressure in steam drum and temp is less than 70 deg C
PREPARATION
Inspect the boiler prior to startup and check the following
Take Power clearance from electrical side also take clearance from instrumentation side.
All the access doors are closed.
All personnel are cleared.
All material are removed from furnace and other circuits.
Starting equipment interlocks are in position
Boiler is filled with D.M water up to NWL.
WATER AND STEAM CIRCUIT
Check the following valves are in closed condition.
Control valves and their bypass valves.
Blow down valves.
Main steam stop valve.
Drain valves of water level gauges.
All drain valves of water wall headers and economizer headers.
Check the following valves are in open condition
All isolation valves before and after feed control valves
Drum air vents
Main steam line drain
Valves of water level gauges, pressure gauges and level transmitters
Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

47

All isolation valves for instruments

AIR AND FLUE GAS CIRCUIT


Ensure the following
I.D. Fan inlet damper is closed.
S.A. Fan inlet damper is closed.
Over fire air damper is closed.
P.A. Fan inlet damper is closed.
Wind box damper is closed.
Manual bed drain gates are closed.
Bed ash cooler drain gates are closed.
ESP and chimney are free from men and materials and doors are closed.
WATER FILL UP IN BOILER

Filling water temp should not be more than 38 deg C of the boiler metal temp and minimum
feed water temp acceptable is 20 deg C.
During filling of a cold boiler, the ambient temp should be used as an indicator of the boiler
metal temp.
Assuming an ambient temp of 40 deg C, the maximum temp of filling water shall be 78 deg C.

Boiler water fill up shall be of following two methods


1.
2.

Normal filling circuit by boiler feed water pump (Top fill up)
Initial startup line through D.M. transfer pump (Bottom fill up) to Eco bottom header.

NORMAL FILLING CIRCUIT (TOP FILL UP)

Ensure Economizer inlet & outlet header vents, steam drum vent, wing wall vents, saturated
steam header vent, and startup vent are all kept full open.
During water fill up, post an attendant at the drum level to monitor the local gauge glass and
to communicate control room when the drum level reached 50 mm below NWL (NWL is 50%
of drum level)
Start boiler feed water pump and open discharge valve gradually to full open condition
Open 40% feed control valve gradually (10 to 15%) and fill the water at a slow rate to ensure
removal of entrapped air from the pressure parts.
Close the air vents one by one after water flows out in the vents in the order of economizer,
steam drum , wing wall , saturated steam header and super heater
Once water comes out of super heater vent, close feed control valve and BFW pump discharge
valve and finally stop BFW pump
Steam drum level has to be brought down to NWL after super heater coils and headers are
filled with water by opening IBD valve

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

48

Before draining ensure vents of wing wall, super heater and drum are opened after BFW pump
is stopped

INITIAL START UP FILLING (BOTTOM FILL UP)

Ensure Economizer inlet & outlet header vents, steam drum vent, wing wall, super heater
vents and startup vent are all kept full open
Ensure the economizer inlet header drain valves are open
Start the transfer pump.
Close the air vents one by one after water flows out in the vents in the order of economizer,
steam drum , wing walls and super heater
Once water comes out of final super heater vent, close the Eco. bottom header initial filling
isolation valve and transfer pump discharge valve and finally transfer pump shall be switched
off
Before draining ensure vents of, super heater and drum, wing walls & saturated steam header
vents are opened after transfer pump is stopped

BED MATERIAL FILLING PROCEDURE

Start I.D. fan


Start S.A. Fan
Start P.A. fan
Maintain the furnace pressure as -2 to -5 mmWc
Start Bed material RAV at full speed.
Slowly increased air flow to avoid any chocking of nozzles.
Continuously watch furnace and co-ordinate with control room.
Bed height should be 700mm from bubble cap.
After getting sufficient bed height give a minimum fluidization.
Not down the wind box pressure for minimum fluidization.
Now decrease the air flow and check the bed that there is uniform fluidization in bed.

BOILER START UP PROCDURES


Start LDO pump at least 3 hours before start up & keep oil in recirculation mode.
Light up the oil burner as per Burner startup procedures and maintain the oil pressure 4.5-5.5
kg/cm2.
Maintain SA air flow for burner 12TPH and furnace pressure -2 to -3 mmWC.
Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

49

Slowly increased PA air flow proper heat transfer through bed material.
After getting 2 kg/cm2 drum pressure gradually increase oil flow.
When the drum pressure reaches 2 kg/cm2 close the drum vent valve, wing walls vents,
saturated steam header vents & super heater vents.
Main steam startup vent valve should be kept in open condition till the boiler is connected to
load to safeguard the super heater coils from overheating.
Now increased the PA air & keep bed in minimum fluidization state.
Gradually increase oil flow and monitor drum level. If necessary, give blow down and
maintain NWL
Observe the bed temp rise in bed. The expected heat up is around 50-70 deg C per hour till
100 deg C
Watch the bed for uniform fluidization. The bed temp will start rising fast due to the radiation
heat of the oil burner.
Once the bed temp reaches around 400 deg C start introduction of coal to the comp.

INTRODUCTION OF COAL TO BED AND STABILISATION

Once the bed temp is around 450 to 500 deg C in any one of the thermocouples, start the drag
chain feeder and run at minimum speed.
Observe the bed and check coal burning or not.
Without flame in the bed do not continue fuel feeding for prolonged time.
Slowly increase the fuel feeding RPM when the bed temp is around 600 deg C and in rising
trend.
Once the fuel is admitted to the bed there will be a rapid bed temp raise and should be
controlled by adjusting the fuel to the combustor and adjusting air flow to the bed.
Also start screw feeder to avoid sudden temp rise of bed.
Bed temp is to be stabilized around 850 deg C for coal and once the temp is stabilized burner
can be withdrawn when the temp rising rate is so fast.
Once the bed temp reaches 850 deg C bed material additions shall be taken up and bed level
shall be raised from the existing level to 1400-1500 mm.
On the water side watch the drum level maintain drum level to NWL by switching on feed
pump

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

Prepared by: Thermax Limited, Power Division (O&M)

50

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

Prepared by: Thermax Limited, Power Division (O&M)

51

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

Prepared by: Thermax Limited, Power Division (O&M)

52

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

Prepared by: Thermax Limited, Power Division (O&M)

53

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

Prepared by: Thermax Limited, Power Division (O&M)

54

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

55

TURBINE ALARM & TRIP SET POINT LIST


4.7 MW Captive Power Plant
S.NO.

Instr.Tag
No.

Description

Unit

Set Values
Alarm

Trip

DPI-501

Lube Oil Filter

Kg/Cm2

0.8

DIP-401

Control Oil Filter

Kg/Cm2

0.8

DPS201A
/DPS201B

CEP Differential Pressure


(DP)

Kg/Cm2

0.5

PI-101

Main steam pressure Low


Low

Kg/Cm2

26

20

PI-101

Main steam pressure High


High

Kg/Cm2

43

44

TI-101

Main steam temperature


Low Low

Deg C

425

420

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

56

TI-101

Main steam temperature


High High

Deg C

435

449

PSL-401

Control Oil Pressure Low


Low

Kg/Cm2

8.5

7.5

PI-103

Exhaust Pressure High


High

Kg/Cm2

-0.85

-0.81

10

TI-103/TI104

Exhaust Temperature
High High

Deg C

105

120

11

OSP- 901

Over Speed trip from


Governor

RPM

12

LSHH-201

Hotwell level High High

13

PBLT1
/PBLT2

Emergency trip (PB) from


Gauge Panel

14

D86GT

Generator Differential
Relay acted

15

PI-502

Lube oil Pressure Low


Low

16

EMG PLC

Emergency trip command


for DCS

17

YI-801B/YI802B

Turbine front bearing


vibration High High

Microns

63

83

18

YI803B/YI804B

Turbine rear bearing


vibration High High

Microns

63

83

19

YI-805B/YI806B

Gearbox Pinion (DE)


bearing vibration High
High-High Speed

Microns

66

125

20

TI - 809

Gearbox Pinion (NDE)


bearing vibration High
High-High Speed

Microns

66

125

Kg/Cm2

13180

70%

90%

2 out of 2

0 = Trip

D86GT

From relay : = 1

2.55

1.8
DCS Push
Button

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

57

21

ZI-801B

Rotor axial displacement


High High

MM

22

TI - 801

Turbine thrust Non-Active


side temperature High
High

Deg C

95

100

23

TI-803

Turbine thrust Active side


temperature High High

Deg C

95

100

24

TI-805

Turbine front journal


bearing temperature High
High

Deg C

110

120

25

TI-806

Turbine rear journal


bearing temperature High
High

Deg C

110

120

26

TI-810

Gearbox pinion shaft (DE)


bearing temperature High
High

Deg C

100

110

27

TI-809

Gearbox pinion shaft


(NDE) bearing
temperature High High

Deg C

100

110

28

TI-807

Gearbox Gear shaft (DE)


bearing temperature High
High

Deg C

100

110

29

TI-808

Gearbox Gear shaft (NDE)


bearing temperature High
High

Deg C

100

110

30

TI-851

Gearbox Gear shaft Thrust


(NDE) Temperature

Deg C

100

110

31

TI-850

Gearbox Gear shaft Thrust


(DE) Temperature

Deg C

100

110

32

TI-811

Alternator front bearing


Temperature High High

Deg C

85

90

33

TI - 811

Alternator rear bearing


Temperature High High

Deg C

85

90

34

ESD - 901

Emergency shutdown
command from Govenror

Governor

0 to trip

0.4/+0.4

Prepared by: Thermax Limited, Power Division (O&M)

0.6/+0.6

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

58

35

TI 811

Alternator front bearing


temperature

Deg C

85

90

36

TI 812

Alternator rear bearing


temperature

Deg C

85

90

37

TI 813

Alternator winding
temperature - U1 phase

Deg C

140

145

38

TI 814

Alternator winding
temperature - V1 phase

Deg C

140

145

39

TI 815

Alternator winding
temperature - W1 phase

Deg C

140

145

40

TI 816

Alternator winding
temperature - U2 phase

Deg C

140

145

41

TI 817

Alternator winding
temperature - V2 phase

Deg C

140

145

42

TI 815

Alternator winding
temperature - W2 phase

Deg C

140

145

43

TI 823

Alternator core
temperature - 1

Deg C

130

135

44

TI 824

Alternator core
temperature - 1

Deg C

130

135

45

TI 825

Alternator core
temperature - 1

Deg C

130

135

46

TI 819

Alternator inlet air


temperature - 1

Deg C

52

47

TI 820

Alternator outlet air


temperature - 1

Deg C

80

48

TI 821

Alternator inlet air


temperature - 1

Deg C

52

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

49

Alternator inlet air


temperature - 1

TI 822

SOP

Deg C

59

80

BOILER ALARM & TRIP SET POINT LIST


4.7 MW Captive Power Plant
S.NO.

Instr.Tag
No.

Description

Unit

Set Values
Alarm

Trip

LI-101
A/B/C

Drum Level Low Low

25

20

LI-101
A/B/C

Drum Level High High

70

80

PI-112

Main steam pressure Low


Low

Kg/Cm2

43

PI-112

Main steam pressure High


High

Kg/Cm2

46

TI-121

Main steam temperature


Low Low

Deg C

420

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

60

TI-121

Main steam temperature


High High

Deg C

460

PI-114 A/B

Furnace Pressure High High

mmwc

130

140

PI-114 A/B

Furnace Pressure Low Low

mmwc

-130

10

PI-116

BFG Presuure High High

mmwc

350

500

11

PI-116

BFG Pressure Low Low

mmwc

150

50

12

PI-206

Deaerator Pressure High

Kg/Cm2

1.5

13

PI-206

Deaerator Pressure Low

Kg/Cm2

0.5

14

LI-201

Deaerator Level Low Low

20

140

10 BFP will
TRIP

START, STOP PERMISSIVE AND INTERLOCKS


TURBINE RESET PERMISSIVE
1.EOP Should be ready and will be selected in Auto mode.
2.Lube oil tank level should be greater than 30%.
3.Overhead oil tank level switch should be healthy.
4.Emergency Push Button from the TSP panel should be released.Reset Command from PLC
At 10800 RPM AOP manual stop and MOP change over function.
Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

61

COASTING DOWN TESTS


Turbine coasting down time = 6 mins 8 sec.
LOGICS AND INTERLOCKS TEST
1. Auxillary Oil Pump
Start Permissive
1.Pump should be in Remote selection.
2.Pump should not tripped in overload.
AOP will start in Auto
1. When Lube oil header Pressure becomes low of 2.5 Kg/cm2.
AOP will Stop in Auto/Protection
1.When Lube oil header pressure becomes greater than 3 Kg/Cm2.
2.When Turbine speed will achieved 90% of rated RPM with 120 Sec of time delay
3.When AOP motor will trip in overload.
2.Emergency oil pump
Start Permissive
1. EOP ready to start signal will display in
PLC
2. EOP should not trip in overload.
Emergency oil pump will start in Auto/Interlock
1.When Lube oil pressure becomes low low of 1.8Kg/Cm2
2.Incase of Turbine speed is greater than 20 RPM and Lube oil
pressure is low low irrespective of mode selection in PLC,EOP will start
automtaically and cannot be stopped untill the pressure becomes
normal or Turbine speed come to stand still.
3.Barring Gear Motor
Start Permissive
1.Barring Gear motor should not trip in overload.
2.Lube oil pressure is greater than 2.55 Kg/cm2.
3.Turbine speed is less than 20 RPM.
Barring Gear will Start in Auto.
1.When turbine speed is less than 20 RPM.
Auto stop command / Protection
1.When Lube oil header pressure is less than 2.55 Kg/Cm2
2.When turbine speed is greater than 315 RPM
Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

4.Control Oil Pump


Start Permissive
1.Pump should be in Remote selection.
2.No over load trip activated.
3.MOT tank level not low low i.e. greater than 30%
Stand By COP will start in Auto Mode
1.When Control oil pressure becomes low of 8.5 Kg/Cm2.
2.When running Control oil pump tripped in overload.
COP will stop in Auto/Protection
1. When MOT level goes below 30%.
2. When pump will be overloaded.
5. Oil Vapour Extractor Fan - 1
Start Permissive
1.Fan selection should be in Remote.
2.Fan should not be over load trip.
OVEF will start in Auto Mode.
1. Auxiliary oil pump should be in running condition.
2.Emergency oil pump should be in running condition.
3.Turbine speed should be greater than 90% RPM.
Auto Stop command / Protection
1.Vapour extractor fan overload tripped.
6. CONDENSATE EXTRACTION PUMP - 1
Start Permissive
1.Hotwell level should be normal greater than 50%.
2.CEP pump shoullde be Remote selected.
3.Pump should not be over load trip.
CEP will start in Auto
1.Stand By Pump wil start in Auto if Condensate discharge pressure becomes low
i.e. less than 3.0Kg/Cm2.
2.Stand By Pump wil start in Auto if Hotwell level becomes High of 70%.
3.Runnig Condensate extraction pump Tripped.
CEP will Stop in Auto/Protection
1.Pump will trip in Auto if Hotwell level becomes low low 20%.
2.Running Condensate extraction pump Tripped.
7.VACUUM BREAKER VALE (VBV201)
Prepared by: Thermax Limited, Power Division (O&M)

62

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

63

Vaccun Brekaer valve will open in AUTO.


1.When Turbine Axial Displacement is greater than 0.6 mm
2.When Lube oil pressure becomes low low i.e. less than 1.8Kg/Cm2
3.when Generator tripped due to Differential protection.
4.When Turbine speed is less than 70% of rated speed.
Manual Open Command Block
1. If the turbine speed is greater than 8400 RPM manual open command is blocked.
2. Valve can be manually closed when all the protection is normal.
8. DEAREATOR BLEED VALVE
OPEN PERMISSIVE
1. Main steam flow should be greater than 10 TPH.
2.Pressure difference across the bleed valve should be less then 0.1 Kg/Cmm2
3. Turbine should not be in tripped condition.
Bleed valve Auto close/Protection
1. When Turbine inlet Main steam flow less than 9 TPH.
2. When Turbine Trip.

PLANT TRIP INTERLOCK CHECKING FORMAT


STEAM TURBINE
S.No.

DESCRIPTION
Hand Trip test
by Push button
on Local TSP
panel
Remote Trip
test by Push
button on
Governor panel

UOM

SET
VALUE

ACTUAL
VALUE

METHOD OF TESTING

RESULT
EXPECTED

Trip

Put STG on turning


gear, by pass vacuum
protetction,reset STG

Turbine trip
& ESV
close

Trip

as above

as above

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

Over speed Trip


from Governor.

Over speed Trip


from OSP
system

Exhaust
Pressure High
High

Main steam
temperature
High High

8
9

10
11

Main steam
temperature
Low Low
Exhaust
Temperature
High High
Turbine thrust
Non-Active side
temperature
High High
Turbine thrust
Active side
temperature

RPM

RPM

Kg/cm2

SOP

64

13188

Operate the turbine at


working speed and do
the OS testing through
Woodward it is advised
to test the electrical OS
at operating speed by
resetting OS electrical at
operating speed. After
testing normalize the set
value

Turbine trip

13250

Operate the turbine at


working speed and do
the OS testing through
Woodward. it is advised
to test the electrical OS
beyond mechanical OS
value as back up
protection

Turbine trip

-0.81

Put STG on turning


gear, normalize pass
vacuum protection to
reset STG otherwise,
pull some vacuum
above trip value and
reset the STG Now
reduce vaccum by
controlling ejector steam
pressure to trip value.
Note the trip value

STG will not


get reset, in
the second
case turbine
must trip

Turbine trip

deg C

449

Put STG on turning


gear, by pass vacuum
protetcion,reset
STG,simulate through
DCS

deg C

420

as above

Turbine trip

deg C

120

as above

Turbine trip

deg C

100

as above

Turbine trip

deg C

100

as above

Turbine trip

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

SOP

65

High High
12

13

14

15

16

17

18

19

20

Turbine front
journal bearing
temperature
High High
Turbine rear
journal bearing
temperature
High High
Gearbox pinion
shaft (DE)
bearing
temperature
High High
Gearbox pinion
shaft (NDE)
bearing
temperature
High High
Gearbox Gear
shaft (DE)
bearing
temperature
High High
Gearbox Gear
shaft (NDE)
bearing
temperature
High High
Gearbox Gear
shaft Thrust
(NDE)
Temperature
Gearbox Gear
shaft Thrust
(DE)
Temperature
Alternator front
bearing
Temperature
High High
Alternator rear
bearing
Temperature
High High

deg C

120

as above

Turbine trip

deg C

120

as above

Turbine trip

deg C

110

as above

Turbine trip

deg C

110

as above

Turbine trip

deg C

110

as above

Turbine trip

deg C

110

as above

Turbine trip

deg C

110

as above

Turbine trip

deg C

110

as above

Turbine trip

deg C

90

as above

Turbine trip

deg C

90

as above

Turbine trip

Prepared by: Thermax Limited, Power Division (O&M)

POWER DIVISION

THERMAX LIMITED
Project

Document
Title

Rev.

Page

1 x 20 MW CPP

TRINETRA CEMENTS
BANSWARA,RAJASTHAN

26

Hotwell level
High High

90

28

LUB OIL
PRESSURE LL

Kg/cm2

1.8

SOP

66

Reset turbine and check


the hotwell level by
actually rising the same

Prepared by: Thermax Limited, Power Division (O&M)

Turbine trip
Turbine trip

Вам также может понравиться