OMRON HEALTHCARE VIETNAM FACTORY PROJECT

CONSTRUCTION METHOD AND


QUALITY CONTROL PLANNING
For

CONCRETE WORK

OBAYASHI VIETNAM CORPORATION


BINH DUONG – VSIP II SITE OFFICE
2007

Project Manager Site Manager Building Engineer

1
CONTENTS

1- GENERAL
1.1 Scope
1.2 Alteration

2- OUTLINE OF PROJECT
2.1 General parameters
2.2 Concrete parameters

3- CONCRETE MIXES
3.1 Type of concrete
3.2 Production of concrete
3.3 Transportation of concrete

4- REQUIREMENTS OF EXECUTION
4.1 Preparation of concreting
4.2 Construction joint
4.3 Concrete casting
4.4 Concrete curing
4.5 Concrete defect treatment

5- CONTROL AND SAFETY


5.1 Quality control
5.2 Safety

6- INSPECTION FORMS, PLANNING AND RECORDING FORMS

7- CONCRETE CASTING FLOW CHART

2
1- GENERAL

1.1 Scope
This Construction Method and Quality Control Planning shall be applied to
concrete work, including all kinds of concrete made elements. Based on the
design and specification, this document provides a proper procedure and
management of the concrete work.

1.2 Alteration
This Construction Method and Quality Control Planning may be subject to
change or alter due to its revision. In that case, corrected or adjusted
requirements shall prevail after its official written approval.

2- OUTLINE OF PROJECT
2.1-General parameters:
* Name of the project: OMRON HEALTHCARE VIETNAM FACTORY
* Location: 28 Road No. 2, VSIP II, Ben Cat Dist., Binh Duong Province.
* Client: OMRON HEALTHCARE MANUFACTURING VIETNAM Co., Ltd
* Design: OBAYASHI VIETNAM CORPORATION
* Contractor: OBAYASHI VIETNAM CORPORATION
* Construction period: June 08th 2007 to November 23rd 2007
* Land area: 38,369.1 m2
* Building area: 6,538.57 m2

2.2-Concrete parameters:
• Lean concrete quantity:
• Structure concrete :

3- CONCRETE MIXES

3.1 Type of concrete


The table below gives the different types of concrete, which used in the various
structures of building.

Minimum
Type of Grade of Compressive Strength
Applied to
Concrete Concrete at28 days
(Cylinder strength*)

All the concrete works for the structural works,


A Normal 210 kg/cm2
unless other type of concrete is specified.

B Normal 150 kg/cm2 Lean Concrete

3.2 Production of concrete


The concrete used to structure shall be ready mixed concrete. Concrete shall
be ordered in accordance with the specified design strength, being subject to
quality control as indicated herein.

3
3.2.1 Supplier of ready mixed concrete:
* LE PHAN CONSTRUCTION Co.,LTD
-Address: 97 Nguyen Duy Vuong St., Ward 9, Dist.5 HCMC.
-Tel : 84-8-8300152
-Fax : 84-8-8350449
-Capacity :
.Plant No.1 : 75m3/hour
.Plant No.2 : 77m3/hour
-Distance from Site Omron Project:
.Plant No.1, No.2 : ~ 15 km.

3.2.2 Material
Type of cement Portland Cement
CEMENT
Maker of cement NGHI SON
COARSE AGGREGATE Stone of Hoa An mining –
Location of mining
(Crushed stone) Dong Nai
FINE AGGREGATE (sand) Location of mining Sand of Tan Ba – Binh Duong
Type of admixture Water reducing
Sikament 2000AT, Plastiment
ADMIXTURE Product name
96
Maker SIKA
MIXING WATER   Well Water

3.2.3 The designed mix proportion


No. DESCRIPTION Type A
1 Designed strength (cube) (kg/cm2) 250
2 Slump (cm) 10.0 (±2)
Cement (kg) 341.00
Fine
Weight in 1 (m3) 0.447
aggregate
3 (m3)
coarse
concrete (m3) 0.838
aggregate
Admixture (ml)

3.3 Transportation of concrete:


a- Mixing trucks shall be cleaned thoroughly after completing each concrete
supplying trip. Remaining hardened concrete or any foreign material inside
concrete compartment must be cleaned out
.
b- Time of transportation from the batching plant to site shall not exceed 02
hours (otherwise truck of concrete shall be returned to the batching plant).
Record of each mixing truck shall be made.

c- Any segregated concrete or any defective concrete shall be rejected.

4
4- REQUIREMENT OF EXECUTION

4.1 Preparation of concreting:


a- General Inspection before concrete order shall be done by Obayashi engineers,
The inspection shall include:
+ Reinforcement steel bar and anchorage, in accordance with Re-bar list and all
specification in concern.
+ Form work, including necessary temporary stage or scaffolding for concrete
casting.
+ Confirmation of embedded M/E devices and location. Also during concrete
casting, these M/E device’s condition shall be checked by M/E sub-con staff.

b- Before concreting, the moist condition shall be provided to all form work and
to previous construction joint surface with water spraying.

c- Before concreting, tools, equipments, electric power supply and labor shall
stand by on site.

d- The use of other concrete transportation means, (concrete pump, buckets,


chutes) shall be planned and all these equipments shall be cleaned and sprayed
with water before use.

e- Top level of concrete to be cast shall be made by marking on form with nail or
red adhesive tape (at interval of 1,500 ~ 2,000mm). In case of slab concrete, level
shall be used for checking.

4.2 Construction joint:


a- Construction joints for slab shall follow specification on structure drawings.

b- The constructions joint for beams shall be located at 1/3 of span in concern;
for columns, it shall be the bottom level of beams.

c- The previous construction joint surface shall be cleaned and free of laitance,
being roughened with wire brush before the next concrete.

4.3 Concrete casting:


a- Concreting process shall be done continuously until all the planned casting
finish.

b- In all cases, the height of concrete drop position to concreting place shall be
less than 1.5 m, otherwise a chute shall be used or intermediate height casting
opening shall be made.

c- The concrete shall be vibrated properly. Interval of vibration spot is about


600mm and duration of operation is about 20 seconds.
d- For long and thin element, combination of vibration and tapping of form work
shall be used.

4.4 Concrete curing:

5
a- The new cast concrete surface shall be protected by keeping completely free of
any load for at least 24 hours after the completion of concrete pouring.

b- For concrete curing and marking work, entering cast area is allowed after 01
day. But concrete surface shall not be loaded with any kind of material,
equipment, machine or tool until concrete curing is finished.

c- In case of rain just after concreting, concrete surface shall be protected by


vinyl sheets.

d- The moist condition shall be kept to concrete surface by water spraying at


least 2 days after casting to avoid quick hardening.

4.5 Concrete defect treatment:

a- Laitance (if any) on concrete surface shall be taken out for the next concrete or
for finishing work.

b- After removal of form, concrete surface shall be checked. If any defect exists
(honeycomb, cold joint, unusual drying out ), it shall be reported. After
consulting with Obayashi engineers, it shall be repaired immediately with proper
method.

5. CONTROLS AND SAFETY


5.1 Quality control
a- General checking:
- Before casting concrete, general checking shall be done including form work,
rebar, levels and cleaning.
- During casting concrete, any movement of form and re-bar shall be checked
carefully.
- During trowel of floor surface, the top level shall be checked at all times.

b- Slump test
Before casting concrete, the concrete slump must be checked and recorded.
(frequency: at the same time that test cube sample is taken)
c- Concrete temperature checking
Before casting concrete, concrete temperature shall be checked with
thermometer and recorded.
(frequency: at the same time that slump test is done)
d- Sample and Compressive Test
- 09 samples of concrete shall be made for each casting :
.03 samples for 7-days test
.03 samples for 28-days test
.03 samples for extra test
(For determination or prospect of the time of form & shoring removal)
- Above each 03 samples shall be taken evenly from total numbers of concrete
trucks.
- Basically the sampling is prepared for every 150m3 of cast concrete.
However, for main elements of building, concrete samples shall be taken on
every concrete casting.
- Sample making, curing and testing shall be done by concrete supplier with
instruction of Obayashi engineers.

6
- Concrete samples shall be cured in curing water tank on site until the day of
test. Curing condition (water temperature, cleanliness) shall be maintained
properly. The information of casting (date,building,element) must be
indicated on each sample surface.
- Compressive test for 7days age shall be done by concrete supplier at their
laboratory.
- Compressive test for 28days age and extra age shall be done by xxx
- Test results and photos shall be recorded for each sample by Obayashi
engineers.

e- Concrete casting flow chart. (See attached)

5.2 Safety
a- Material shall be put in order; safety passage shall be provided.
b- Safety regulations and rules on site are applied also to concrete work
c- Daily cleaning shall be done by sub-contractor to ensure the site completely
clean in the area of working.

6. INSPECTION FORMS, PLANNING AND RECORDING FORMS

7
7. CONCRETE CASTING FLOW CHART

PLANNING
SCHEDULE
CONFIRMATION
W/SUPPLYER

INSPECTION

FORM WORK RE-BAR WORK CONC. CASTING


CHECK SHEET CHECK SHEET PLAN &RECORD

CONC. VOLUME
ESTIMATION APPROVAL

ORDER

DELIVERLY

SLUMP TEST
QUALITY CHECK
SUPERVISION
*FORM RE- BAR CHECK TEST CUBE
*LEVEL TROWELING CHECK SAMPLING
*M&E SLEEVE, PIPING CHECK
*SAFETY CHECK
* etc. CURING
CASTING
COMPRESSIVE
TEST

GETTING
TEST RESULT

CONC. CASTING CONC. CASTING


CURING PLAN &RECORD PROGRESS
REPORT
CONSULTING

FORM
REMOVAL

CONC. SURFACE
CHECKING
REPAIRING