Академический Документы
Профессиональный Документы
Культура Документы
CONTENTS
353
CONTENTS
354
Even while still in the procurement phase, failure to read specifications may cost a bidder the project. Consider the case of John Carlo, Inc.1 In 2002, the U.S. Army issued a solicitation for the construction of a runway. Part of the Request for Proposals indicated that award would be based not just on price but on the bidders management qualifications. During oral interviews, the individual identified by John Carlo, Inc., as the proposed project superintendent, admitted that he had not read what the U.S. Army considered to be a key specification section dealing with military runways. With this as the primary reason, the U.S. Army excused John Carlo, Inc., from award consideration. John Carlo, Inc., protested this decision with the Comptroller Generals office claiming that the individual correctly answered questions regarding military runways. While the U.S. Army did not dispute this point, the Comptroller Generals office ruled that, . . . despite substantive knowledge, the Army was reasonable in expecting contractors to have read the Project specifications. John Carlo, Inc.s protest was denied. Failing to read the project manual often costs the builder time and money. However, sometimes faithfully following the specifications brings negative consequences as well.
CONTENTS
355
2. Ambiguous specification writing where reasonable people may have more than one, conflicting interpretation of what is to be done As a general rule, courts have used the following guidelines to deal with design deficiency claims. 1. Consider the contract as one document; examine the requirements in their entirety not just the clause(s) in question. 2. Supplementary conditions, those specific to the project, will usually take precedence over the general conditions (i.e., boiler plate provisions used verbatim for every project). 3. Large-scale drawings, generally details, take precedence over small-scale drawings (i.e., a 1 in. 1 ft. scale governs over a 1/8 in. 1 ft. drawing). 4. Specifications take precedence over drawings. 5. Handwritten, initialed provisions take precedence over typed provisions. 6. Standard industry practice may also be utilized to settle such disputes. To receive increased compensation for a design or specification ambiguity, it must be proven to be a latent ambiguity. A patent ambiguity by definition must be . . . an obvious omission, inconsistency, or discrepancy of significance.4 This places a burden on the bidder to notify the procuring authority of the issue at hand, or a concept known as the duty of inquiry. A latent ambiguity by definition is . . . neither glaring nor substantial nor patently obvious.5 The contractor shoulders a heavy burden with regards to liability for contract document compliance. Despite the ambiguous definitions in the previous guidelines, it often seems that builders face insurmountable battles to achieve reimbursement for increased costs. Consider the case of Randa/Madison Joint Venture III (RMJV) and the U.S. Army Corps of Engineers (COE).6 The COE contracted with RMJV for dewatering services for an existing foundation. The contract contained the standard by submitting a bid the contractor warrants that it is familiar with all aspects of the site clause. The contract also indicated that various geological tests were incorporated by reference and available for inspection. RMJV did inspect the site prior to bidding, but it did not review test results. Upon commencement of the work, RMJV determined that what it called latent geological conditions were leading to significant increased costs. It filed a claim for an equitable adjustment. Ultimately, a federal appellate court decided that, by submitting a proposal, the bidder warrants that it reviewed all available data, including that incorporated by reference. Even when a contractor installs a product prescribed by the architect and said product proves to be deficient for the application, the builder is held liable for any necessary corrections. Next consider the case of Newman Glass Works (NGW).7 NGW worked as a glazing subcontractor on a project that required a specific type of glass from a specific manufacturer. After installation, the product began to delaminate. Upon inspection, the architect agreed that the wrong product for that climate and facility had been specified. However, NGW was still directed to replace the glazing at its own expense because the prime contract contained language stating that all work put in place would be free from faults or defects. If not, such work would be replaced at the contractors expense. NGW refused. The trial court ruled that: It is true that here, Defendant (NGW) had virtually no discretion in carrying out its contractual obligations in light of the exacting specifications in the subcontracts. But it is also true that Defendant entered into subcontracts that require it to remove and to replace any defective materials at its own cost and expense. We conclude that the implied warranty by Plaintiff (that prints and specifications issued for bid are accurate and suitable for the implied purpose) based on the specifications of the type and manufacturer of spandrel glass must yield to Defendants express warranties against defective materials.8 In this case, the builder supplied a specific product, specified by the architect, and then properly installed it. At a later date it was determined that the specified product was not suitable for this situation. However, since the contract included sweeping language requiring the builder to guarantee that all materials were suitable, it had to replace said product at its own expense. Per other contract language that has been upheld by courts, even if an architect approves a shop drawing submittal that includes a deviation from the prints or specifications, the constructor is still liable to provide
CONTENTS
356
that which was originally required. Consider the case of Elter S.A.9 The U.S. Navy contracted with Elter S.A. to renovate a port facility. Part of that work included the provision and installation of exterior lighting poles secured with a specific type of anchor bolt. Elter S.A. provided a shop drawing submittal that clearly showed the use of an alternate anchor bolt; the Navy approved this submittal. After completion of all work, the Navy learned that the anchor bolts provided did not conform to the specifications. It instructed Elter S.A. to remove all light poles and replace the foundations so that the specified fastener would be used and then to reinstall the light poles. This represented a significant amount of work. Elter S.A. provided evidence that the anchor bolts submitted and used were satisfactory for the light poles in question. The Navy did not dispute this point. The Armed Service Board of Contract Appeals ruled that a contractor is not relieved from specification requirements by virtue of the approval of nonconforming items. The contractor has a duty to highlight to the reviewing official any deviations from the project requirements. This begs the obvious question of whether the reviewing official has a duty to closely review all submittals.
IN SUMMARY
A contractor who fails to familiarize itself with the specifications opens the door to potential losses. Even when the contractor thinks it understands the directions from the project manual, a later, alternate interpretation by the architect may cause problems. The best course of action is for the prime contractor to meet with its subcontractors and review the prints side by side with the applicable specifications. Should any questions or even possible issues be noted, they should be immediately brought to the architects attention in writing.
End Notes
1. Comptroller Generals Decision No. B-289202, John Carlo, Inc. v. U.S. Army, (2002). 2. United States v. Spearin, 248 U.S. 132 (1918). 3. Seminar on the litigious nature of modern construction projects presented by Gerald Katz, Esq., 48th Annual Construction Specifications Institute Show and Convention, McCormick Place, Chicago, IL (April 23, 2004). 4. Beacon Construction Co. of Mass. v. U.S., 814 F .2d 501, 504 (Ct. C1. 1963). 5. Mountain Home Contractors v. U.S., 425 F .2d 1260, 1264 (Ct. C1. 1970). 6. Randa/Madison Joint Venture III v. Dahlberg, 239 F .3d 1264 (3rd Cir. 2000) 7. Rhone Poulenc Rorer Pharmaceuticals v. Newman Glass Works, 112 F .3d 595 (3rd Cir. 1997). 8. Ibid. 9. Armed Services Board of Contract Appeals, No. 52327, Elter S.A. v. U.S. Navy (2001).