The Badak LNG Plant is located in Bontang, east kalimantan, Indonesia, and owned by Pertamina (indonesian government oil company) This paper will explore the Badak LNG Plant experiences to apply Management of Change starting with the initial implementation.
The Badak LNG Plant is located in Bontang, east kalimantan, Indonesia, and owned by Pertamina (indonesian government oil company) This paper will explore the Badak LNG Plant experiences to apply Management of Change starting with the initial implementation.
Авторское право:
Attribution Non-Commercial (BY-NC)
Доступные форматы
Скачайте в формате PDF, TXT или читайте онлайн в Scribd
The Badak LNG Plant is located in Bontang, east kalimantan, Indonesia, and owned by Pertamina (indonesian government oil company) This paper will explore the Badak LNG Plant experiences to apply Management of Change starting with the initial implementation.
Авторское право:
Attribution Non-Commercial (BY-NC)
Доступные форматы
Скачайте в формате PDF, TXT или читайте онлайн в Scribd
MISE EN PRATIQUE DE LA GESTION DE LA SCURIT PERTAMINA USINE DE PT BADAK
Munir Amsyari PT Badak NGL, Indonesia
John Sunarmo PT Badak NGL, Indonesia
ABSTRACT
The Badak LNG Plant is located in Bontang, East Kalimantan, Indonesia, and owned by Pertamina (Indonesian Government Oil Company). The total production is about 18.00 million tones per annum of LNG. In the year 2000 the total LNG production of the Badak LNG Plant will be about 21.64 million tones per annum, produced from eight LNG Trains. These company milestones and other achievements are based on the Pertamina initiatives in 1977 to build two LNG Trains in Bontang. In order to maintain continuous supply of LNG to the buyers, Badak LNG Plant Management has established The Company Philosophy i.e. To Operate the Badak LNG Plant Safely, Reliably and Efficiently. Process Safety Management has been implemented in the Badak LNG Plant to fulfill The Company Policy. Management of Change, one of the Process Safety Management elements, is considered the most important element in the support of the Plant operations of the Badak LNG Plant. This paper will explore the Badak LNG Plant Experiences to apply Management Of Change starting with the initial implementation. The Badak LNG Plant Management Of Change is divided into three stages i.e. Evaluation/Study Stage, Safety Review Stage and Documentation Stage. These three stages are combined into a single component referred to as the Project Flow Of Work. In order to ensure that the Safety Review Stage can be conducted in a timely manner to support the Project Flow of Work, the Badak LNG Plant has developed and established a Hazops Committee. This group consists of multi disciplined members and is chaired by the Process Engineering Section Head. A high commitment and consistent application of Management Of Change has helped the Badak LNG Plant succeed to fulfill the Company Philosophy especially related to Safety. Up to the end of July 1999, the Badak LNG Plant had achieved 50 Million Working Hours without a lost time accident.
RESUME
Lusine de GNL de PT Badak est situe Bontang, Kalimantan Est (anciennement Borno), Indonsie. Elle appartient Pertamina (Socit Nationale Indonsienne des Hydrocarbures). Cette usine produit environ 18 millions de tonnes de GNL par an. Sa capacit de production sera porte 21,64 millions de tonnes par an partir de lan 2000, ce grce au 8e train de liqufaction. Ces rsultats sont le fruit le la dcision de Pertamina, prise en 1977, de construire deux trains de liqufaction Bontang. Afin dassurer la continuit de lapprovisionnement en GNL requise par les acheteurs, la direction de lusine a dfini la Philosophie de la compagnie : faire fonctionner lusine de PT Badak en toute scurit, de faon fiable et efficace. cet effet, PT Badak a dvelopp un systme de gestion de la scurit. La Gestion du changement est considre comme le principal lment de la gestion de la scurit assurant le bon fonctionnement de lusine Badak LNG . Cet expos dcrit lexprience de PT Badak dans lapplication de la Gestion du changement depuis sa mise en oeuvre. La Gestion du changement comprend 3 tapes : valuation/Phase dtude, Bilan de la scurit et Documentation. Ces trois tapes sont combines en un seul lment, appel Circulation des tches projet . Afin de sassurer que les bilans de scurit sont effectus au moment requis par les projets, PT Badak a mis en place un Comit Hazops . Ce groupe multidisciplinaire est dirig par le responsable de la section Procds. Lengagement considrable de PT Badak et lapplication scrupuleuse de la Gestion du changement ont permis de satisfaire la Philosophie de la compagnie, notamment au niveau de la scurit. En juillet 1999, PT Badak a comptabilis 50 millions dheures travailles sans accident avec arrt de travail. 1 - INTRODUCTION
1.1 - General
The Badak LNG Plant located in Bontang, East Kalimantan, Indonesia, is operated by PT Badak Natural Gas Liquefaction, an Indonesian corporation owned 55 % by Pertamina, the Indonesian State Oil Company, 30 % by Gas Producers group (Vico, Total Indonesie, and Unocal), and 15 % by JILCO representing the Japanese Buyers. The Badak LNG Plant has seven LNG Trains in operation capable of producing 18.00 million tons of LNG annually. The eight Train is under start- up and is expected to produce LNG by the end of 1999. By having eight LNG Trains in operation at the end of 1999, the total LNG production from the Badak LNG Plant will be about 21.64 million tons annually.
For guiding company operation, an Operational Plant Philosophy was established since the beginning of the LNG production in 1977. This Philosophy covers three aspects: Plant Reliability, Plant Efficiency and Plant Safety. By maintaining this philosophy it is expected that the commitment of the LNG shipments to the Japanese, Korean and Chinese buyers can be maintained indefinitely. Since the beginning of LNG shipments in 1977, there has been no cargoes delayed to the customers. This achievement continues to strengthen the Morale and spirit of the Badak LNG plant personnel to keep and maintain the Operational Plant Philosophy.
1.2 - Development of the Plant Philosophy
The Management of Badak LNG Plant realizes that the strength and viability of the company depends on the healthy interaction between the Employees and the Management of the Company. This healthy interaction can be established and maintained by mutual understanding between the Management and the Employees by establishing a Corporate Company Culture, which consists of Company Vision, a Mission Statement, Strategic Objectives, Tactical Objectives, and Company Basic Policy (see figure 1).
Company Vision The Badak LNG Plant is the largest LNG supplier in the world, one of the main sources of National Income for Indonesia and the Agent of Community Development, all employees strive to make this facility the best LNG Plant in the world.
Company Mission The company mission is to supply LNG to the Buyers in a reliable manner.
Strategic Objectives The Badak LNG Plant is to build and maintain the buyers trust, and to prepare for future markets.
Tactical Objectives The Operational Philosophy is to operate the LNG Plant in a Safe, Reliable and Efficient manner, to enhance the Technology, and to establish a Master Plan/Technology.
Company Basic Policy The Basic Policy of the Company covers the following philosophies : Personnel Development, Operational, Safety, Maintenance Philosophy, Environment Development. Design, Construction and Expansion philosophies are also included in this Basic Policy.
MAN PERS. DEV. SAFE, RELIABLE BUILD/MAINTAIN TO SUPPLY WORLD PHIL. AND EFFICIENT BUYERS THRUST LNG TO THE LAGEST MONEY OPERATION OPERATION BUYERS IN A LNG PHIL. RELIABLE WAY SUPPLIER MATERIAL SAFETY PHIL. TECHNOLOGY MAINTENAN- ENHANCEMENT NATIONAL MACHINERY CE PHIL. INCOME MASTER PLAN/ PREPARE FOR METHOD TECHNOLOGY FUTURE MARKET AGENT OF ESTABLISHMENT COMMUNITY ENVIRONMENT ENVIRONMENT DEVELOP- DEV. PHILOSO- MENT PHY DESIGN PHIL. CONSTRUCT. PHIL. THE BEST EXPANSION LNG PLANT PHIL. IN THE WORLD
It is PT Badaks policy that Process Safety Management is applied to achieve Safety Excellence, a general guideline for all personnel to follow the policy is set forth in a dedicated and comprehensive manual called PT Badak NGL. Process Safety Management Manual. This manual was officially issued in early 1996. PTB believes that the implementation of Process Safety Management will be an integral part of the business considerations i.e. production, cost, quality, benefits and employee relations. Based on PTB requirements for operating the plant, PTB selected 12 elements for supporting PSM implementation in the Badak LNG Plant. This paper will share and explore PTB experiences in applying the Management of Change element.
2 - PTB PROCESS SAFETY MANAGEMENT
The elements of Process Safety Management have been known and applied in the activities of the Badak LNG Plant since the beginning of company business in 1977. Therefore, developing and implementing Process Safety Management is actually an effort to develop a model and socializing it to all PTB personnel. The model is described in the PT Badak Process Safety Management Manual, as the integration of three major components of the Badak LNG Plant i.e. Personnel, Technology and Facilities. PTB decided that 12 elements are adequate to meet the standard requirements for establishing PTBs PSM. The integration of these 12 elements to the three major components of the Badak LNG Plant is as follows (see figure 2):
PT. BADAK CORPORATE CULTURE AFTER OFFICE HOURS ACTIVITIES MANAGEMENT POLICY BASIC POLICY TACTICAL OBJECTIVE STRATEGIC OBJECTIVE MISSION VISION GOAL/ OBJECTIVE Figure 1 : PT. Badak Corporate Culture
Technology Personnel
- Process Safety Information . - Training - Process Hazard Analysis . - Contractor - Operating Procedure . - Accident/Incident Investigation - Safe Work Practices . - Emergency Planning and Response - Management Of Change . - Audit - Management of Change
Facilities
- Mechanical Integrity. - Pre Start-up Safety Review. - Management Of Change.
The effect of the Management of Change on each component described, expresses PTBs concern that the Management of change plays a key role and can not be separated from any activities related to the 12 elements of the PTBs PSM.
2.1 - Steps of PSM Implementation
Implementation of PSM in the PTB facilities is an integrated effort, accomplished through the following steps:
PROCESS SAFETY OPERATING PROCEDURES SAFETY MANAGEMENT OF CHANGE PRE START-UP SAFETY REVIEWS MECHANICAL INTEGRITY & QUALITY MANAGEMENT OF CHANGE PROCESS HAZARD TRAINING EMERGENCY PLANNING AND MANAGEMENT OF CHANGE INCIDENT INVESTIGATION CONTRACTOR AUDITING BADAK LN G
Figure 2 : Elements of PTB - PSM 2.1.1 - Introduction Phase
A PSM expert (consultant) was invited to evaluate the application of the PSM elements in PTB in September 1992, followed by providing PSM training to the key personnel PTB. The training was conducted in two ways i.e. sending PTB employees to attend overseas PSM training and conferences, and in-house training for the Supervisors up to the Manager level. Upon completion of this training, PSM was introduced to all employees through Safety Talks and Fire & Safety Refresher courses.
2.1.2 - Commitment Phase
After the PSM concept was understood by our PTB employees, a commitment or policy as the foundation of PSM program implementation was established, - Develop PSM Manual Procedure no. PSM-01. - Include PSM methodology in to the PTB Basic Safety Policy (see figure 3).
MAN
MONEY
MATERIAL
MACHINERY
METHOD
ENVIRONMENT
2.1.3 - Preparation Phase
All the elements of PSM, which were being applied within PTB were reviewed to determine the need for further program development. PTB decided to apply 12 elements of the PSM program, which were adopted from the combination of OSHA 29 CFR, 1910.119, API RP-750 and the DuPont Program as PTB consultant during conducting Introduction Phase of PSM. The summary of PTB PSM Elements can be found in table 1 : - SAFETY INSPECTOR
- SCALE OF PRIORITY
- QUALITY ASSURANCE SPECIFICATION
- FAIL SAFE DESIGN
- P.S.M. - CODES & STANDARDS
- ENVIRONMENT IS DEVELOPED TO SUPPORT THE COMPANY BASIC POLICY TACTICAL TARGET STRATEGIC TARGET MISSION VISION ZERO ACCIDENT
LOW SEVERITY RATE
LOW FREQ. RATE
EQUIPMENT ZERO FAILURE SAFETY HEALTH AS OBJECTIVE SAFETY EXCELLENCE ACHIEVEMENT HEALTH, SAFETY & ENVIRONMENT AL PROTECTION IS AN INTEGRAL PART OF THE LIVES OF ALL Figure 3 : PTB Safety Culture
OSHA 29 CFR 1910.119 API RP 750 PT. BADAK NGL. CO. Employee Participation -- -- Process Hazards Analysis Process Hazard Analysis Process Hazard Analysis Process Safety Information Process Safety Information Process Safety Information Operating Procedures Operating Procedures Operating Procedures Training Training Training Contractors -- Contractors Pre Start-Up Safety Review
Mechanical Integrity Pre Start-Up Safety Review Assuring the Quality and Mechanical Integrity of Critical Equipment Pre Start-Up Safety Review
Mechanical Integrity and Quality Assurance Hot Work Permits Safe Work Permits Safe Work Permits Management of Change Management of Change Management of Change Incident Investigation Investigation of Process Related Incidents Incident Investigation Emergency Planning and Response Emergency Response and Control Audit of Process Hazards Management Emergency Planning and Response Compliance Safety Audits Systems Audit -- General --
2.1.4 - Implementation Phase
Continual refinement of the PSM elements during this implementation phase must be done by PTB as long as the company philosophy is not changed. Consequently, all Departments within PTB must monitor and ensure that their activities meet and are consistent with the elements of PTBs PSM.
2.1.5 - Monitoring Phase
Regular audits of PTBs PSM program will be conducted by a PSM expert, who is hired by the share holders. The results of the audit are used to monitor and control PTB achievements in implementing the PTBs PSM. Any deviation and inconsistency related to the elements of PTBs PSM must be followed up with a corrective action to ensure that the PTB vision can be achieved.
By following the above phases, the implementation of the PTBs PSM program can be achieved smoothly. PTB personnels understanding of the PTB philosophy, which has been consistent since the start of the company, supports this smooth implementation. An individual commitment to follow the PSM elements is the key success factor to ensure that PSM can be implemented. However, human nature can not guarantee that all personnel have the same commitment. Therefore, clear and straight guidelines are required. Among the 12 elements of the PTBs PSM, the most difficult part to be maintained and to be followed consistently is handling or implementing Management of Change. As mentioned in the previous section that "Management of Change plays a key role and can not be separated from any activities related to the 12 elements of the PTB-PSM", this is because human nature adds complexity to the change process. Table 1 : PTB PSM Elements
2.2 - Management of Change of PTB-PSM
The policy behind the Management of Change of PTB-PSM is "any changes without the proper consideration of their impact can render all previous reviews and safe guards null and void. It is necessary that written procedures shall be made to manage and control technological, physical equipment and personnel changes that may effect the process". In order to meet the policy, a change is defined as any addition, deletion, or alteration of process technology, personnel and facility outside of established limits. The list of the categories of changes, which covers procedure, responsibility and file location is developed to ensure that PTB personnel can follow any required action if necessary (see table 2).
CATEGORY
RESPONSIBLE DEPARTMENT OTHER DEPARTMENT SUPPORT/ PARTICIPATION
- Implementation of Management of Change/Facilities Changes. - Review and evaluated any Facilities Changes
- Technology - Operation - Main Control Room - Library ICS
- Personnel Changes
- All Departments
- Personnel
- Implementation of Management of Change/Personnel Changes. - Review and evaluate any Personnel Changes
- All Departments - Personnel
- Documentation
- Operation - Technical
- Project - ICS/Main Library
- Updated continually a change occurs and revised when feasible. - Accessible to operating personnel.
- Technical - Operation - Main Control Room - Project/Drafting/ Library - Main Library/ICS
2.2.1 - Process Technology Change
Process technology change is any addition, deletion or alteration of process technology such as, production rates, materials, equipment, catalyst, operating condition. Some items which include in the process technology change are as follows:
Process Chemicals - Feedstock. - Product Specifications. - By Products / Waste Products. - Maximum Intended Inventory - Additives such as : * Corrosion Inhibitors. * Antifoulants. * Antifoam Agents. * Stabilizers. * Dispersants. Table 2 : Management of Change Responsibility of File Location
Process Technology - Process Flow Scheme. - Capacity. - Operating Parameters Such As : * Temperature. * Pressure. * Level. * Composition. - Catalyst. - Catalyst Condition Procedures. - Catalyst Environmental Control. - Operating Procedures. - Base or Advance Level Control Philosophy. - Control System Software. - Emergency Depressurizing Capacity. - PSV Design Basis. - Flare System Design Basis.
2.2.2 - Facilities Change
Facilities changes is the addition, deletion, alteration of facilities (process equipment) such as : construction material, equipment specification, piping pre arrangement, alarm and interlocks. The following items are included in the facilities change :
- Equipment on Existing or New Facilities including : * Tie-In. * Removal of Equipment or Instrumentation from a Working Process. * Demolition of Idle Equipment. * Demolition of a Process Unit.
- Mechanical Design such as : * Rotational or Reciprocating Speed. * Materials Handling. * Thickness. * Gauges.
- Materials of Construction. - Interlock System. - Instrumentation. - By pass Connections. - Preventive Maintenance List. - Hoses, Tubing, or Piping including : * Hot Taps. * Pipe Clamps. * On Stream Leak Repair.
- Blinds, Safety Control Devices, or Electrical Circuits including Jumper Wires. - Gasket Material of Type of Constructions. - Relief Valves including : * Set Pressure. * Orifice Size. * Bellows Material.
- Pumps & Compressors including : * Seal Type. * Configuration. * Material. * Fire Protection Equipment. * Sewer System.
2.2.3 - Personnel Changes
Personnel changes are defined as : new employees, job rotation, restructuring of organization, etc.
There are three stages (evaluation/study, safety review and documentation) are combined into a single component called Project Flow of Work as the detail working procedure and guideline for implementing the Management of Change, especially to handle process technology and facilities changes. This procedure is called the PT. Badak Policy Procedure Guide (PP Guide) which consists of two parts i.e Project Procedures and Hazops & Hazan.
2.3 - Project Procedures PP Guide
The Project Procedure PP Guide covers the company to encourage PT. Badak employees and engineers to follow a standard administrative approach when issuing a Request for Engineering Service (RES) and processing the RES implementation of the required solution as the initial step of the Project Flow of Work.
This procedure applies to all Departments dealing with RES : Facilities Engineering, Inspection, Process Engineering Sections of Technical Department, Project Engineering Section of Project Department, Safety Engineering & Environmental Control Section of Loss Prevention Department and Technology Section for preparing a conceptual study. Process Engineering, Facilities Engineering and Project Engineering Section for issuing simple detailed designs, Facilities Engineering and Project Engineering Section for issuing complete detailed designs.
Any employee may create a Request for Engineering Service (RES) when he sees a problem which may require technical investigation or needs engineering assistance. The content of the RES includes a background of the problem and a request to find the solution. The reason for the concern and justification for writing a RES are:
* Plant safety, * Plant improvement, * Plant modification, * Non-plant related improvement and * Company contribution to local government.
After writing the RES, the originator shall obtain the approval of his supervisor and his department manager. Then the RES is submitted to the custodian for the custodian managers approval. The custodian manager then submits the plant related RES to the Technical Manager, or to the Project Department Manager for a non-plant related RES/civil work job, or to the Loss Prevention Manager for a safety related RES.
For Plant related projects, the Technical Manager will check whether the RES is acceptable. He will check with the originator if required. If it is not acceptable, it shall be rejected and sent back to the custodian manager. If it is acceptable, the Technical Manager will discuss internally and select the proper department or section for the study. If the RES is related to Fire Safety and Environmental aspects, it shall be sent to Loss Prevention Manager. After reviewing the RES the Technical Manager or Loss Prevention Manager will modify the priority of the RES, if required, and distribute it to the appropriate section, based on the result of Technical or Loss Prevention Department discussion. If there are any additional questions on the RES, the assigned Section Head clarifies them to the Technical Manager or Loss Prevention Manager. Non plant related projects will be directly handled by Project Engineering Section.
The Section Head shall obtain a project number for the RES from the project administrative assistant in the Project Engineering Section and assign an engineer within the section to handle the RES FROM ORIGINATOR RES APPROVED BY CUSTODIAN PROJECT FLOW START (NEXT PAGE RES TO TECHNICAL, LOSS PREVENTION, OR TECHNOLOGY SECTION HEAD ASSIGNS ENGINEER AND OBTAINS PROJECT NUMBER RES PROJECT ENG. SECTION DOES THE RES DEAL WITH PLANT RELATED PROBLEM ENGINERING ASSISTANT ASSIGNS PROJECT NUMBER RES REVIEW BY TECHNICAL MANAGEMENT RES. The Section Head will then distribute the RES to the appropriate parties listed on the lower part of the RES. To proceed the project task, the engineer must look at the priority of the RES and always execute the RES with the higher priority first, and follow the project flow chart (see figure 4) for reference. The assigned engineer is responsible for the project from concept through execution as well as for keeping the project file for the project organized in a comprehensive and timely manner.
RES REJECTED AND CLOSED NO YES Figure 4 : PTB RES and Project Flow Chart IS A JOB STUDY REQUIRED
RES ASSIGNED TO ENGINEER IF A SIMPLE PROJECT, EMERGENCY JOB OR <US$ 2,000 PROCEED WITH A MEMO # 1-S FORM REVISE MEMO # 11 AS REQUIRED A FROM PREVIOUS PAGE IS MEMO # 11-A APPROVED DOES THE MEMO # 11 RECOMMEND AN ENGINEERING MODIFICATION ? CAN PROJECT BE DONE WITH # 1-S FORM ? DOES THE PROJECT REQUIRE ENGINEERING BY OTHER GROUPS ? PERFORM STUDY AND DEVELOP MEMO # 11 SUBMIT MEMO # 11 WITH MEMO # 11-A FOR CUSTODIAN APPROVAL PREPARE MEMO # 9 AND TRANSFER NO NO NO NO NO YES YES YES YES YES CUSTODIAN TO PREPARE AFE PREPARE COST ESTIMATE SUBMIT MEMO # 3 TO CUSTODIAN Figure 4 : PTB RES and Project Flow Chart AFE (MEMO # 3) APPROVED ?
MEMO # 7 APPROVED ? HAZOPS IF PROJECT CAN BE IMPLEMENTED WITH A MEMO # 1-S FORM CORRECT THE SAFETY ITEMS DESIGN - CALCULATION - DRAWINGS NO YES YES NO DRAWINGS PFD, P&ID, ISO, STRUCTURAL, FOUNDATION, ETC. WELDING PROCEDURE MEMO # 4 BILL OF MATERIAL MEMO # 8 SCOPE OF WORK MEMO # 1 MEMO # 1-S COMPLETE ENGINEERING OR SIMPLE PROJECT PACKAGE PACKAGE REVISE AS REQUIRED INSPECTION TO VERIFY QUALITY REVIEW WITH CUSTODIAN REVIEW WITH MAINTENANCE SUBMIT MEMO # 2 MATL AVAILABILITY REVIEW WITH PROJECT WHSE PROJECT EXECUTION APPROVED YES NO COMMISSIONING PROCEDURES DISTRIBUTE MEMO # 5 FOR PROJECT COMPLETION AS BUILT DWGS. COMPLETE PERMANENT FILES UPDATED FIELD WORK COMPLETE PROJECT CRITIQUE ISSUE JOB CLOSURE MEMO # 5 PROBLEM SOLVED TO POINT A PREVIOUS PAGE FURTHER STUDY OR REVIEW NO YES Figure 4 : PTB RES and Project Flow Chart 2.4 - Hazops and Hazan PP Guide
PT. Badak wishes to review plant and community related projects including tie-in jobs, studies and maintenance job preparations, or other changes including operating procedures that impact the safety and reliability of the Badak LNG/LPG Plant and its Community, from a hazards and operability (Hazops) point of view in order to eliminate possible failures when the projects/studies and procedures are implemented. The review includes Hazard Analysis (Hazan), which is used to quantify the risk/consequences if the job execution fails. Both Hazops and Hazan can be conducted independently or combined depending on the requirement. In the case of a combined review, Hazan will follow Hazops based on Hazops recommendation. This is parallel with the mission of PT. Badak to maintain a high standard on the safety and reliability of the Badak LNG/LPG Plant and Community.
To ensure that the Hazops review is consistently implemented, a body (committee) in the PT. Badak organization is established, called Hazops Committee (HC). The review of Hazan is done by the Loss Prevention Department.
2.4.1 - Application
- All plant related projects including tie-in jobs or studies within PT. Badak which directly have a significant affect on the safety and reliability of the Badak LNG/LPG plant. - All plant repairs related to maintenance job preparations within PT. Badak which have a significant effect on the safety and reliability of the Badak LNG/LPG plant. - Other changes including operating procedures that impact to process safety and reliability of the Badak LNG/LPG plant. - Other PT. Badak facilities outside the plant which have been decided to be reviewed by Management from a hazard, operability, and safety point of view. - Outside projects/studies which will be implemented in the Badak LNG/LPG plant.
2.4.2 - Hazops and Hazan Procedures
Hazops Procedure - Each project/study or a change is sent to the Hazops Committee Chairman (HCC) using memo # 7 or a regular memo complete with a conceptual study/design intent/sequential procedure, detailed drawings, and the result of the department Hazops review (see figure 5). - After receipt of the package, HCC will decide, whether a meeting with the project engineer/Hazops requestor and the Hazops Committee Members (HCM) is required. Calling a Hazops Committee meeting is the prerogative of management and HCC. Requests for a meeting by others can also be made to the chairman. - For simple projects, studies and other changes, the Hazops review is done by the secretary or the HCM and approved by HCC. - For big or complicated projects, studies, and other changes within the existing facilities, a full Hazops Committee meeting is required. Depending on the requirements, Management or expert (s) may be invited to attend this meeting for their advice. In the meeting the project engineer or the Hazops requestor should explain the proposed project, study or other changes to the committee, and all committee members are free to raise questions related to the safety and operability stand-point. For a big project which is not executed by PT. Badak but will be implemented in the plant, or for the existing plant facilities which need to be reviewed from the hazard and operability point of view, a full time hazops study with a full team from various disciplines will be required for a duration of more than 15 working days. In this case a special team called Temporary Hazops Committee, is formed. - During the meeting, the Hazops Committee identifies/assesses the potential hazards, and they will recommend to the project engineers/Hazops requestors to accommodate their findings into their studies.
- In addition to HCC approval for the Hazops of the maintenance job preparation or other changes including operating procedure, the approved Hazops document should be acknowledged by Operation Manager, Plant Technical Manager, Maintenance Manager and Loss Prevention Manager prior to the execution of the job. - If the HCC considers that the request for Hazops for a projects, studies and maintenance job preparation is not appropriate, the HCC will return the memo # 7 or issue a response memo to the project engineer with the note Hazops is not required. - Starting from the receipt of the package, HC will complete their review and comments in a reasonable time but not longer than 15 working days. For every big project, the duration of Hazops review will be defined prior to the start of the work.
Hazan Procedure - PHC or/and Division Manager will recommend to the Loss Prevention Department to conduct a Hazan. - Loss Prevention Department proposes the action plans to cover an unexpected Hazard condition. - The results of the Hazan should be attached to the Hazops result. But if Hazan is done independently, the report can also be issued independently to the requestor.
ENGINEERING STANDARD MEMO # 7
TO : HAZOPS Committee Date : FROM : __________________________________ d d m m y y SUBJECT : HAZOPS REVIEW REQUEST
JOB NUMBER :
JOB TITLE : _______________________________________________________________________ ENGINEER : _____________________________GROUP HEAD : __________________________ SUMMARY OF SCOPE : __________________________________________________________________ Attached to this memo please find the following :
Design Intent (always include) Spec. Sheets :
Conceptual Design Drawings :
Other :
Please review these attachments from a HAZOPS standpoint and indicate the Committees decision by completing the form below and returning it to us.
Section Head
DISTRIBUTION : ( ) number of copies after approval For HAZOPS Committee use only : Not Approved (see comments attached) Not Required
Approved by : Sub-Committee on ________________ Full Committee Meeting held on ___________________
Signed : __________________ _____________________ _______________ (HAZOPS Chairman) (Committee Member) Date (1) Project Eng. Section Head (10) Hazops Committee Members (1) Custodian : ________________ (1) Technical Library Files (1) Engineer : _________________ (1) Technical Project Files Figure # 5
Consistent application of these procedures as a part of Management of Change of the PTBs PSM has contributed to the achievement of the current PTB Safety Record of more than 50 million working hours without a lost time accident.
3 - CONCLUSIONS
1. The corporate culture of PTB is to strengthen a healthy interaction and mutual understanding between management and the employees.
2. The 12 elements of Process Safety Management are adequate to meet the standard requirements of PTBs PSM program.
3. Individual commitment to follow the PSM elements is the key success factor to ensure that PSM can be implemented.
4. Management of Change is considered the most important element of PSM in the support of the plant operations of the Badak LNG Plant.
5. Application of PTBs PSM contributes to the achievement of the current PTB safety record of over 50 million working hours without a lost time accident.
REFERENCES
1. PT. Badak NGL, Process Safety Management Manual. 2. PT. Badak NGL, Policy/Procedure Guide 0304-01. 3. PT. Badak NGL, Policy/Procedure Guide 0305-01.