International Labour Office – Bureau of Procurement

ITB N° 12/2009 – EC/MoLISA/ILO Labour Market Projec t

Responses to questions asked


regarding Invitation to Bid
ITB N° 12/2009
EC/MoLISA/ILO Labour Market Project

Questions Responses

1. In Page 82: In Bidding document required Training The bidder should provide a detailed plan, and
Time is during installation period. But what is the estimate the training time, based on the Training and
minimum time for the training? Technology transfer required in the Bidding Document.
While no minimum time is specified, each course
should be sufficient to ensure trainee attain the
knowledge neccessary.

2. Does servers in package 1 and package 2 need to Yes, Keyboard/Mouse must be included.
included Keyboard/Mouse

3. Notebook PC: (Page 68) 2.27kg is for Notebook itself.


Weight: 2.27 kg required is for the Notebook itself?
Or included AC Adapter?

4. On page 6 of ITB, “Please submit one original, You should have the softcopy the same as the
four copies and one soft copy in CDROM in hardcopy. With a multipage scanner you can scan long
MS-Office format of your offer (in a same documents easily. Beside the MS-Office format, we
envelope)”. The underline word shows that also accept PDF format. This is not a criteria for bid
one CDROM in MS-Office format contains all evaluation.
documents with the same content like the hard
copy bidding. It is quite difficult for bidder because
the bidder has many hard copy such as: Audited
tax report, Financial report….. We can not make in
to MS office format.
The question is: Could you cut down unnecessary
documents for us in CDROM? If yes, Please tell us
what documents we must submit in CDROM?

5. What does UOM mean? Please reference on page UOM: Unit of Measure
13 of ITB.

Page 1 of 3
International Labour Office – Bureau of Procurement
ITB N° 12/2009 – EC/MoLISA/ILO Labour Market Projec t

Questions Responses

6. We found that the name of project with the (Important)


different in bid document (page5)
Please use the project name for issuing the Tender
Bond as below:
ITB N° 12/2009 - Labour Market Project

And ILO Office in Vietnam


48-50 Nguyen Thai Hoc Street, Hanoi, Vietnam

What is the correct name for issue Tender Bond?

7. Reference on page 13 of ITB; column Weight The Weight kg/Volume m3 Column is not mandatory.
kg/Volume m3 – This specification must fill all Item
or not? Please confirm.
We welcome bid proposals from all bidders. In your
8. Our company is the highest-level partner of
proposal, please provide us with the evidence of your
manufacturers who provide products required in
capability, quality of goods and services, etc., as
the tender. Therefore, we would like to know
mentioned in the ITB document. All your submission
whether it is possible for us not to submit the letter
materials will be examined and evaluated against the
of authorization when we are allowed to sell their
criteria for determining technically qualified bidders.
products to any international organizations and
All bidders who are assessed technically qualified will
governmental organs. Furthermore, our technical
then have their financial bids opened and contract
team is highly professional and qualified as they
negotiations will commence with the lowest bidder.
got certifications from well-known manufacturers
The financial proposals of Bidders who fail to meet the
and their capabilities are verified through many
technical requirements will not be opened.
similar contracts that we will send with our
proposal for your perusal.

9. Page 7: Tender Bond: A tender bond shall reach The ILO Headquarter will notify the project office when
the ILO Headquarter in Switzerland not later than they get your Tender Bond. Immediately, the project
11Am 7th September 2009 (Geneva time). How office will inform you via email of the successful
ILO will confirm to us that ILO had received the receipt.
Tender Bond or received it on-time?

Page 2 of 3
International Labour Office – Bureau of Procurement
ITB N° 12/2009 – EC/MoLISA/ILO Labour Market Projec t

Questions Responses

10. In Tender Bond form has the following phrase: (Important)


“ has submitted to you his offer No.
dated .”
What is the meaning of this phrase? In our
understanding that phrase is stand for the number
& date of our offer, but our offer only numbered
and dated on one day before the bid close. How
can we inform to the Bank about these number &
date now?

Please follow the below guide:


“has submitted to you his offer No. insert bid proposal
code or name here dated insert date of bid
submission here .”

11. Page 9: Site visit. Will ILO provide Construction Bidders are responsible to do site surveys and prepare
drawing of the site survey to the Bidder? drawings.

12. Backup Server (Page 33): Does this server have This particular backup Server must be included with a
standard optical drive? standard optical drive.

13. In “Detail Technical Specifications and Bidders should decide to use Fiber-optic or Copper
Requirements” table, part 1 – Server Farm Firewall cable, based on their Technical Proposal for the whole
required 4 ports Gigabit Ethernet Adapter. Please system for the LMIC.
revise for the interface of that adapter is using
Fiber-optic cable or Copper cable. If it is Fiber-
optic, then what is the type & standard for it?