Вы находитесь на странице: 1из 8

ADT 300D Production Estimating Program

Read instruction sheet before starting. Yellow colored cells are for job entry data; light blue cells contain information; gray cells contain the grade calculator if needed. Material Density (lbs. per bank cubic yard) Load Factor (see instructions) ADT Payload (lbs) #DIV/0! Excavator Bucket Size (heaped c.y.) Fill Factor (see instructions) Base Cycle Time of Excavator (sec.) Loose material 17 sec. Medium material 22 sec. Hard material 27 sec. Excavator wait & repositioning allowance (sec.) Normally 1.5 sec. if next ADT is in position; Calculated excavator cycles per ADT would be Enter x in the yellow cell (B17) to select Haul (see below) Distance (ft) Section A Section B Section C Section D Section E Section F Section G Section H Section I Section J Section K Tot. Dist. 0 Grade % Adverse Rated ADT payload is 60,186 lbs. Rated capacity is 21.6 c.y. heaped

#DIV/0! #DIV/0! #DIV/0!

Total Cycle Time sec. if not in position

Sec. 0

Min. 0.00

The actual number is #DIV/0! cycles. as the number of excavator cycles. Number of cycles selected #DIV/0! Grade % Haul Road Total Time Favorable Factor Resistance (min) MPH 0 0.00 0.0 0 0.00 0.0 0 0.00 0.0 0 0.00 0.0 0 0.00 0.0 0 0.00 0.0 0 0.00 0.0 0 0.00 0.0 0 0.00 0.0 0 0.00 0.0 0 0.00 0.0 Tot. Time 0.00 #DIV/0! Avg. MPH Factor 1 2 3 4 5 6 8 14 20 26 32

Haul Road Description Very firm and smooth, well maintained Firm and well maintained Firm with flexing or gradual undulations Giving but fairly smooth: 1" tire penetration Soft, smooth surface: 2" of tire penetration Soft, smooth surface: 3" of tire penetration Very soft with 4" of tire penetration Very soft with 8" of tire penetration Extremely soft with 12" of tire penetration Extremely soft with 16" of tire penetration Extremely soft with 20" of tire penetration Important: Payload is #DIV/0! resistance factor was automatically

Use whole numbers only. Max calculated total resistance is 49 on the haul and 60 on the return. If vehicle speed will be reduced by the driver for safety or other reasons on any section, select a haul road factor that will result in the desired speed. Example: ADT will be negotiating curves on a downslope where the computed speed would be 30 mph, but desired safe speed would be 10-12 mph. Select a haul road factor that would result in a total resistance of 4 on the haul or 10 on the return.

lbs. over/ ( - if under) rated load. The total haul road #DIV/0! #DIV/0! for each haul section.

Release Date: March, 2002 1

1/11/2014

Grade Calculator Enter degree of grade (up to 16 deg.)


Enter first number of ratio to one, e.g. 12 in a 12:1

1 1

Read % of grade Read % of grade

2 100

Fill Positioning and dump time (sec.) Fast .5 15 min. Sec. Average 45 .75 Sec. min. Return (see below) Distance (ft) Section Section Section Section Section Section Section Section Section Section Section Tot. Dist. 0 Grade % Adverse

Slow > 75 Sec. Time (min) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Grade % Haul Road Total Favorable Factor Resistance 0 0 0 0 0 0 0 0 0 0 0 Tot. Time

MPH 0 0 0 0 0 0 0 0 0 0 0 #DIV/0!

Avg. MPH

Default Delay (Acceleration/deceleration calculated by spreadsheet) 11 Sec. (haul and return) Additional Delay (Record any anticipated maneuver/delay time for each ADT cycle in sec.) Examples of additional delays are: Making sharp turns on high speed sections (8 sec. delay per turn), crossing highway, going up short slope for which there is not a separate section, intentionally driving at slower than max speed on any high speed sections (if not accounted for in haul road factors). Do not include wait at loading area--account for that in cell F13.) Total number of BCY to be moved Number of hours for job completion or Tons to be moved per hour 0 Weeks (40 hr)

Release Date: March, 2002 2

1/11/2014

PRODUCTION ESTIMATE
Estimated Load (BCY) Time (min) Load #DIV/0! Time (sec) Load #DIV/0! #DIV/0! Actual excavator cycles per load* Effective cycles per load Return 0.00 Delay 0.18 Total #DIV/0! #DIV/0! #DIV/0!

Haul 0.00

Dump 0.00

Haul 0

Dump 0

Return 0

Delay 11

Total #DIV/0!

Total Distance (ft)

0 50 min hr #DIV/0! 50 min hr #DIV/0! #DIV/0!

Average Speed (MPH) 60 min hr #DIV/0! 60 min hr #DIV/0! #DIV/0!

0.0

Includes haul, return, and delay.

Cycles per Hour per ADT

Production per ADT in BCY Production per ADT in Tons

Number of ADTs needed to complete job on time (50 min/hr) (May require larger or additional excavators) Maximum number of ADTs that can be employed (Adjusted for excavator bottleneck)
BCY Hours

Ton Job #DIV/0! #DIV/0!


BCY Weeks Tons Hours

Time required for Time required for Time required for

#DIV/0! #DIV/0!

ADTs to complete job ADTs to complete job ADTs to complete job

#DIV/0! #DIV/0! #DIV/0!

#DIV/0! #DIV/0! #DIV/0!

#DIV/0! #DIV/0! #DIV/0!

* Total loading time is based on #DIV/0! #DIV/0! excavator cycles per truck.

full cycles. Production (BCY) is based on

The production estimates are based on gradeability performance calculations and field tests. Results on any given job can vary significantly if trucks are out of specification (especially engine and tire inflation), operators are driving at less than maximum speed for the conditions, etc.

Release Date: March, 2002 3

1/11/2014

Instructions
Enter data in yellow colored cells only. Use tab key to advance to open cells. Obtain the density of the material in bank cubic yards/meters (BCY) or (BCM), the load factor, and the excavator bucket fill factor. ADTs are loaded in loose cubic yards/meters; the spreadsheet will calculate productivity in BCY/BCM or Tons for material handling applications. English Units Matl Clay, Natural Bed Clay, Dry Limestone, Broken Rock and Earth--75%/25% Rock and Earth--50%/50% Rock and Earth--25%/75% Earth, Dry Earth, Wet Loam Sand, Dry Sand, Damp Sand & Clay Sandy Clay Loam Lime Rock w/ Fines Topsoil Metric Units Matl Clay, Natural Bed Clay, Dry Limestone, Broken Rock and Earth--75%/25% Rock and Earth--50%/50% Rock and Earth--25%/75% Earth, Dry Earth, Wet Loam Sand, Dry Sand, Damp Sand & Clay Sandy Clay Loam Lime Rock w/ Fines Topsoil Seconds-Minutes Calculator Enter seconds here: 11 Enter decimal minutes here: Density Bank lb/cy Load Fac. 3400 0.82 3100 0.81 4400 0.60 4700 0.70 3850 0.75 3300 0.80 3200 0.80 3400 0.79 2600 0.81 2700 0.89 3200 0.89 3400 0.79 3000 0.80 3500 0.77 2300 0.70 Density
Bank kg/cm

LCY 2788 2511 2640 3290 2888 2640 2560 2686 2106 2403 2848 2686 2400 2695 1610

Bucket Fill Factor 1.1 1.0 0.8 0.9 0.95 1.0 1.0 1.2 1.2 0.9 1.1 1.1 1.2 1.1 1.0 Bucket Fill Factor 1.1 1.0 0.8 0.9 0.95 1.0 1.0 1.2 1.2 0.9 1.1 1.1 1.2 1.1 1.0

2017 1839 2600 2789 2284 1958 1899 2017 1543 1602 1899 2017 1780 2077 1365

Load Fac. 0.82 0.81 0.60 0.70 0.75 0.80 0.80 0.79 0.81 0.89 0.89 0.79 0.80 0.77 0.70

LCM 1654 1490 1565 1952 1713 1566 1519 1594 1249 1426 1690 1594 1424 1599 955

Read decimal minutes here: 0.18 Read seconds here:

0.18 10.8

Base Cycle Time of Excavator (Can Be Wheel Loader) & Wait-Repositioning Allowance The three listed cycle times are only a guide. Cycle time depends on where the excavator is situated, material hardness, arm length, etc. In mass excavation, a base cycle time of 15 sec. is not uncommon with a skilled operator. Prospect experience is the best guide. Repositioning normally averages only a second or two per cycle. Excavator wait time can affect the job immensely. If the excavator operator cannot immediately load the next truck in position and has to wait until the loaded truck pulls out and the next one pulls into position, you might have a half minute or more of wait time (to be prorated over three or more cycles--whatever is normal for the size of excavator). This can greatly affect the number of trucks put on the job.

Instructions
Once you have entered data for the first four cells, the spreadsheet calculates (on the right) the number of unrounded excavator cycles per truck load. If this figure is not a whole number, it will be rounded up to the nearest whole number for the load time calculation. Example: 3.5 will be rounded to 4 because the excavator must make 4 passes for 3.5 bucket fulls. It is often more efficient to make only fully loaded passes, especially if the excavator becomes a bottleneck in the operation (see below). If your prospect makes only fully loaded passes and does not want the excavator cycles automatically rounded up--say, from 3.2 to 4, enter on X in cell B17. Using one fewer cycle per truck load will shorten all cycle times and should allow more trucks to be used on the job. Haul The haul can have several sections. If the grade or haul road condition changes more than nominally, you will need to add a new section. Enter the section distance in feet/meters, the percent of an adverse grade, or a favorable grade, and the haul road factor from the list on the sheet. Use whole numbers only. The maximum total resistance (grade + haul road) is 60. If you have the degree or the ratio of a grade, use the grade calculator to obtain the percent of the grade. Note that the haul road factors must be increased or decreased by a factor of one for each 2,000 lbs. (907 kg) over/under the rated payload (do not round up). The increase or decrease factor is calculated for you in Cell D47, and is limited to three points of increased or decreased resistance. Fill Depending on the size and the amount of maneuvering on the fill area, select a positioning and dump time--three times are listed as guides. Return Note that the return is not necessarily the reverse sections of the haul. The departure spot from the fill may be different, and even the haul road may not be the same. Make careful note of any sharp turns on the return. The program calculates for straight travel. A sharp turn on a high speed haul road will cause a delay usually of 8 - 12 seconds. Delay Confer with the prospect about anticipated delays. The spreadsheet accounts for acceleration and deceleration times between sections, but does not account for sharp turns or obstacles.. Add about 12 seconds for each sharp curve or other obstacle on a high speed section, especially on the haul where it takes longer to accelerate to max speed. Do not factor in any wait time in the loading area. The spreadsheet is based on just-in-time arrival, so any positioning time where the excavator is waiting for the truck to be spotted must be accounted for in the excavator load time.

Total number of BCY/BCM (or Tons) to be moved and Number of hours for job completion Although the spreadsheet will calculate cycle times and production without inputting the two numbers called for above, most users will want to know how many trucks to run on the job, and they would also want to use the separate Job Cost Analysis spreadsheet to calculate cost per yard of material moved and total cost. Use the Tons per Hour entry section for material handling applications.

Production Estimate These are calculated values. Cycle times are listed in minutes and then separately in seconds. Average speed is based on the haul, return, and delay, not on total cycle time. Compare the number of ADTs needed to complete the job on time with the maximum number that can be employed. The latter figure means that you cannot increase production by adding more trucks--excavator size or cycle time or wait time won't permit it. Also computed is the time required for various numbers of ADTs to complete the job. If the prospect wants fewer than what is listed, input the number in the yellow highlighted cell.

ADT 300D Production Estimating Program


Read instruction sheet before starting. Yellow colored cells are for job entry data; green cells contain information; blue cells contain the grade calculator if needed. Material Density (kg per bank cubic meter) Rated ADT payload is 27,300 kg Load Factor (see instructions) Rated capacity is 16.5 c.m. heaped ADT Payload (kg) #DIV/0! Excavator Bucket Size (heaped c.m.) Fill Factor (see instructions) Base Cycle Time of Excavator (sec.) Loose material 17 sec. Medium material 22 sec. Hard material 27 sec. Sec. Min. Excavator wait & repositioning allowance (sec.) Total Cycle Time 0 0.00 Normally 1.5 sec. if next ADT is in position; #DIV/0! sec. if not in position Calculated excavator cycles per ADT would be Enter x in the yellow cell (B17) to select Haul (see below) Distance (m) Section A Section B Section C Section D Section E Section F Section G Section H Section I Section J Section K Tot. Dist. 0 Grade % Adverse #DIV/0! The actual number is #DIV/0! cycles. #DIV/0! as the number of excavator cycles. Number of cycles selected #DIV/0! Grade % Haul Road Total Time Favorable Factor Resistance (min) km/h 0 0.00 0 0 0.00 0 0 0.00 0 0 0.00 0 0 0.00 0 0 0.00 0 0 0.00 0 0 0.00 0 0 0.00 0 0 0.00 0 0 0.00 0 Tot. Time 0.00 #DIV/0! Avg. km/h Factor 1 2 3 4 5 6 8 14 20 26 32

Haul Road Description Very firm and smooth, well maintained * Firm and well maintained Firm with flexing or gradual undulations Giving but fairly smooth: 2.5 cm tire penetration Soft, smooth surface: 5 cm of tire penetration Soft, smooth surface: 8 cm of tire penetration Very soft with 10 cm of tire penetration Very soft with 20 cm of tire penetration Extremely soft with 30 cm of tire penetration Extremely soft with 40 cm of tire penetration Extremely soft with 50 cm of tire penetration Important: Payload is #DIV/0! resistance factor was automatically

Use whole numbers only. Max calculated total resistance is 49 on the haul and 60 on the return. If vehicle speed will be reduced by the driver for safety or other reasons on any section, select a haul road factor that will result in the desired speed. Example: ADT will be negotiating curves on a downslope where the computed speed would be 30 mph, but desired safe speed would be 10-12 mph. Select a haul road factor that would result in a total resistance of 4 on the haul or 10 on the return.

kg over/ ( - if under) rated load. The total haul road #DIV/0! #DIV/0! for each haul section.

Release Date: March, 2002 6

1/11/2014

Grade Calculator Enter degree of grade (up to 16 deg.)


Enter first number of ratio to one, e.g. 12 in a 12:1

1 1

Read % of grade Read % of grade

2 100

Fill Positioning and dump time Fast .515 min. Sec. Return (see below) Distance (m) Section Section Section Section Section Section Section Section Section Section Section Tot. Dist. 0

Average 45 .75 Sec. min. Grade % Adverse

Slow > 75 Sec. Time (min) 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Grade % Haul Road Total Favorable Factor Resistance 0 0 0 0 0 0 0 0 0 0 0 Tot. Time

km/h 0 0 0 0 0 0 0 0 0 0 0 #DIV/0!

Avg. km/h

Default Delay (Acceleration/deceleration calculated by spreadsheet) 11 Sec. on haul and return Additional Delay (Record any anticipated maneuver/delay time for each ADT cycle in sec.) Examples of additional delays are: Making sharp turns on high speed sections (8 sec. delay per turn), crossing highway, going up short slope for which there is not a separate section, intentionally driving at slower than max speed on any high speed sections. Do not include wait at loading area--account for that in cell F13.) Total number of BCM to be moved Number of hours for job completion or Tons to be moved per hour 0 Weeks (40 hr)

Release Date: March, 2002 7

1/11/2014

PRODUCTION ESTIMATE
Estimated Load (BCM) Time (min) Load #DIV/0! Time (sec) Load #DIV/0! #DIV/0! Actual excavator cycles per load* Effective cycles per load Return 0.00 Delay 0.18 Total #DIV/0! #DIV/0! #DIV/0!

Haul 0.00

Dump 0.00

Haul 0

Dump 0

Return 0

Delay 11

Total #DIV/0!

Total Distance (m)

Average Speed (km/h)

0.0

Includes haul, return, and delay.

Cycles Per Hour

50 min hr 60 min hr #DIV/0! #DIV/0! 50 min hr 60 min hr #DIV/0! #DIV/0! #DIV/0! #DIV/0! Ton Job #DIV/0! #DIV/0! Hours #DIV/0! #DIV/0! #DIV/0! Weeks #DIV/0! #DIV/0! #DIV/0!
Tons Hours

Production in BCM Production per ADT in Tons

Number of ADTs needed to complete job on time (50 min/hr) (May require larger or additional excavators) Maximum number of ADTs that can be employed (Adjusted for excavator bottleneck) Time required for Time required for Time required for #DIV/0! #DIV/0! ADTs to complete job ADTs to complete job ADTs to complete job #DIV/0!

#DIV/0! #DIV/0! #DIV/0!

* Total loading time is based on #DIV/0! cycles.

full cycles. Production (BCM) is based on

The production estimates are based on gradeability performance calculations and field tests. Results on any given job can vary significantly if trucks are out of specification (especially engine and tire inflation), operators are driving at less than maximum speed for the conditions, etc.

Release Date: March, 2002 8

1/11/2014

Вам также может понравиться