Академический Документы
Профессиональный Документы
Культура Документы
st
Report Period: 1 quarter; 2nd quarter; 3rd quarter; 4th quarter
(1st Qtr = Jan – Mar; 2nd Qtr = Apr – Jun; 3rd Qtr = Jul – Sept; 4th Qtr = Oct – Dec)
CWS Fiscal Year: 1st Qtr= Jul – Sep; 2nd Qtr = Oct – Dec; 3rd Qtr = Jan – Mar; 4th Qtr = Apr–Jun
List of Donors:
Donors Expenditures for this Quarter
CWS/NY SED US 13,770.95
EED US$ 63,690.64
NCCA US$ 55,083.80
UMCOR US$ 39,591.48
Total: US 172,136.87
Detail Expenses
Project Activities
Direct Cost Indirect Cost
Direct Services Program (DSP)
Direct Services Program of CWS Cambodia has two sub-projects that currently operate in three
different provinces; Water and Sanitation project is covering two districts of Svay Rieng province and
Village Based Community Development project is covering Kompong Thom and Preah Vihear
provinces.
_____________________________ ___________________________________
Mao Sophal Chhouk Chantha
Direct Services Program Manager Director for Programming