Construction details

Foot - facade
Example for anchoring on base plate Comments on executing the inner gasket level: 1. The controlled drainage of rebate areas is only ensured if the gasket areas overlap in such a manner that no moisture can penetrate under the gaskets or foils. Run foil as moisture barrier until it lies under the cross-beam gasket and then bond with steel construction. In accordance with DIN 18195 Part 5, the waterproofing must be at least 150 mm above the water-conducting layer. Bond foil with building moisture barrier in accordance with DIN 18195. The rebate area is ventilated via the open ends of the vertical cover strips. The illustrated flush-mounted execution of the beam with the floor is not mandatory. Ensure vapour-tight execution of the connection. The anchoring of the posts must be adequately dimensioned through static calculation. The required edge clearances of the base plates and in the structural elements must be observed. Heat insulation in the connection area must be carried out in such a manner that thermal bridges are avoided. Steel parts in the hidden installed area must also be treated with adequate corrosion protection. Weather protection sheets must be formed in line with the structural requirements. Adequate rear ventilation must be ensured.

Timber Glass Facades 40.03.02 Page 1

2.

40 3

3. 4. 5. 6.

7. 8. 9.

dauerelastische Fuge mit Hinterfllung

Abstandshalter z.B. Z 0601 Bodenbelag Mglichkeit der Falzraumbelftung und Entwsserung Dmmung Feuchtigkeitssperre Wetterschutzblech

Bauwerksabdichtunbg

Dmmung

Baukrper

200308-1.dxf

01.04.2008

Construction details
Connection in front of the floor structure
Continuous or separated posts

Timber Glass Facades 40.03.02 Page 2

Depending on the structural requirements, posts are either formed continuously as multiple span girders or they are separated floor-by-floor. Reasons for floor-by-floor post separation can vary widely, e.g. soundproofing, structural expansion, fire protection, etc. If the separation joint is used for expansion compensation, then, in addition to the degrees of freedom required for the posts, the slide possibilities of the installed elements must be taken into consideration.

40 3

The multiple girder principle comes into effect for continuous supports and corresponding supports from a static perspective. There is less deflexion through influences. As a result, the required inertia torque is reduced, for instance, by a factor of 0.42 when using a 2span girder. A stress analysis is, however, always required.

01.04.2008

Construction details
Eave with glass roof connection
Different implementation variants Implementation with stepped-edge glazing

Timber Glass Facades 40.03.02 Page 3

Depending on the post formation, implementation with or without a rain gutter and the selection between steppededge glazing or closing ceiling strip, result in different implementation variants. Irrespective of the variant used, ensure consistent drainage of condensation and moisture on the eave. Our thermal calculations show a somewhat less favourable isotherm shift with stepped-edge glazing compared cov-

40 3

Folie unter Dichtung auf Holz verkleben

Kondensatabfhrung ber Sparrendichtung, die ber Traufe eingezogen wird. Pfosten- und Sparrendichtung verkleben. Distanzleiste im Bereich des Pfostens unterbrechen. zustzliche Folie als Feutigkeitssperre

20.03.08-4.dxf

ered glass edges. In addition, ensure that a UV-resistant glass edge composite is selected for stepped-edge glazing. These composite edge systems are usually silicone based and, due to their limited impermeability to gas, do not attain the same high soundproofing and heat insulation values as traditional systems. Stepped-edge glazing must also be structurally dimensioned against wind suction in accordance with its reduced fixing. Additional thermal stress on stepped-edge glazing should be countered by using single-pane safety glass.

01.04.2008

Construction details
Implementation without stepped-edge glazing

Timber Glass Facades 40.03.02 Page 4

Horizontal press strips hinder rainwater run-off. Our bevelled cover strips significantly reduce damming in front of the cover strip. Ensure precise sealing of outer gasket area.
Stoabdichtung mit butylkaschiertem Edelstahlblech Z0501 bzw. Z0601

Folie unter Dichtung auf Holz verkleben

40 3

Kondensatabfhrung ber Sparrendichtung, die ber Traufe eingezogen wird. Pfosten- und Sparrendichtung verkleben. Distanzleiste im Bereich des Pfostens unterbrechen. zustzliche Folie als Feutigkeitssperre

20.03.08-5.dxf

In combination with out joint seals made of butyl-lined, stainless steel plates, the glass roofing with four-sided press strip covering also achieves a high safety standard. Ensure a continuous inner gasket level which provides safe drainage for condensation.

01.04.2008

Construction details
Connection to the roof

Timber Glass Facades 40.03.02 Page 5

When connecting to structural elements, movements that may occur should be taken into consideration. In addition to temperature-induced linear expansion of the facade, all linear expansion and movement of the tangential structure must also be taken into account. Addition stress must be prevented.

40 3
Befestigung nach statischen Anforderungen

hinterlftete Wandverkleidung

Dehnungsausgleich durch Langlcher in Anschluwinkel Falzraumentlftung

dampfdichter Anschlu

abgehngte Decke

200308-6.dxf

01.04.2008

Construction details
Connection to installed eave

Timber Glass Facades 40.03.02 Page 6

This connection is suitable for glass roofs which are placed on structural elements such as a skylight. These can be gable roofs, pitch roofs, pyramids or arched roofs.

UV-bestndiger Randverbund Winddichtung z.B. Illmod

dampfdichter Anschlu

40 3

dampfdurchlssige Folie zur Kondensatabfhrung aus den Verglasungsflzen

Wrmedmmung

Al ub

Kondensatabfhrung

le ch

Befestigung nach statischen Anforderungen

bauseitige Folie

200308-7.dxf

Connecting foils The connection of glazing to the structural element requires carefully thought-out construction in many regards. Moisture damage also occurs if room moisture condenses on existing thermal bridges. Consequently, thermal bridges should be avoided and warm room air should be prevented from penetrating too far into the construction or structural element. The required vapour barriers, in the form of vapour-tight connection foils, must be brought as far into the room as possible. This prevents condensation from the room air dampening the construction. An additional foil for rain impermeability must be vapour permeable (mandatory). Dry construction can only be guaranteed in the transition zone if this foil has a vapour diffusion resistance factor of maximum 3000 .

01.04.2008

Construction details
Ridge formation

Timber Glass Facades 40.03.02 Page 7

When forming the ridge cap, ensure that the rafter covering strips are pulled under the ridge cap. The cutouts of the cover strip in the sheet covering must be kept narrow. A foil capable of vapour diffusion that is bonded with the upper glass edges prevents water from penetrating.

Folie mit Glaskanten verklebt Dichtungsband oder GD 0035 selbstklebend

40 3
Sparrendeckleisten unter Blechhaube ziehen

auf dampfdichten Anschlu aller Dichtungen und Firstriegel achten. Andernfalls dampfdichte Folie einkleben

200308-8.dxf

01.04.2008

Construction details
Ridge connection to wall

Timber Glass Facades 40.03.02 Page 8

Ensure vapour impermeability for ridge connections. If the inner gasket area leaks, warm air with high water retention penetrates into the colder zones and allows moisture to penetrate into the connection construction thus leading to construction damage.

40 3

Falzraumentlftung

z.B. selbstklebende Dichtung GD 0035

dampfdichte Folie

200308-9.dxf

Befestigung nach statischen Anforderungen

Regenschutzfolie dampfdiffusionsoffen mit Glasfche verkleben

01.04.2008

Construction details
Horizontal wall connection
Building connection:

Timber Glass Facades 40.03.02 Page 9

Thermal bridges must be avoided through adequate insulation. A waterproof foil that extends into the room-side as far as possible prevents room moisture from condensing in the construction. An outer foil is not necessary if the connection planning so allows.

40 3
dampfdichte Folie

Wrmedmmung

wrmegedmmder Fllstab z.B. Z 0061

200308-10.dxf

01.04.2008

Construction details
Facade corner formation outside corner

Timber Glass Facades 40.03.02 Page 10

At prominent points such as glazed facade corners, ensure that there is sufficient heat insulation to avoid thermal bridges and the hazard on condensation formation. Heat flow calculations provide information on actual heat losses.

40 3

wrmegedmmte Fllstbe z.B.: Z 0061 200308-11.dxf

01.04.2008

Construction details
Facade corner formation inside corner

Timber Glass Facades 40.03.02 Page 11

40 3

200308-12.dxf

01.04.2008

Construction details
Facade polygon

Timber Glass Facades 40.03.02 Page 12

Special gaskets permit a polygon type arrangement of facade posts in angles of 3 to 15 of the glass surface.

40 3

200308-13.dxf

01.04.2008