When it comes to your projects Critical Path, there are few topics more important to your client. The expectation is that YOU, dear scheduler, are the expert. So YOU had better know your projects Critical Path inside and out. But wait! Is it the Critical Path you should be reporting on, or the Longest Path? The terms Critical Path and Longest Path are often used interchangeably when discussing your projects super-high-priority sequence of work to deliver on time. Its confusing to many. And there are some great debates about the differences. The good news is that there IS an important distinction between your projects Critical Path and the Longest Path and well explain it to you here.
A. No Project Deadline.
When we set a deadline on our project (ie: a Must Finish By date in Primavera P6), it results in the appearance of negative Total Float if you are late, and positive float if you are early. Thus, the path of 0float activities vanishes.
B. No Constraints.
Constraints affect an activitys Total Float value. Constrained activities can show negative Total Float and can drive negative float to their successors or predecessors. Applying contraints throughout a project will affect what activities are Critical. And so, again the path of 0-total float through the project eludes you.
C. No Actuals.
A project with actuals may not show a path of 0-float either. The actuals and the order of execution can affect the activities Total Float as well.
So it seems that the age-old path of 0 Total Float definition doesnt fit in our complex project environments. And if you care to do some digging online, youll find that our attempts to clear up the concept of Critical Path has led to numerous new ways to define the term Critical for a project. Search and you are likely to run into terms like: Criticality Critical Chain Near-Critical Critical Risk So which activities are critical? It all boils down to this it depends. What will be your projects Critical Path depends on how you end up defining the term Critical and specifying what activities are Critical in your eyes. You may have activities that you deem Critical regardless of what the software says their Total Float values are. You may have activities that have positive Total Float but are Critical in the clients eyes. You may want to track a specific path of activities through a project. This is called real-world project controls.
Critical Path is a path through your project which has activities YOU consider critical.
The Longest Path is the path through a project network from start to finish where the Total Duration is longer than any other path.
It makes sense to focus on a projects Longest Path as it is definitely the path where deviations from plan will affect the projects finish date.