Академический Документы
Профессиональный Документы
Культура Документы
Appendix A
147
Appendix A Conditions of Contract for Plant and Design-Build (1999) (P & DB) The Yellow Book
The P & DB Conditions of Contract are intended for use where the Contractor designs and provides, in accordance with the Employers requirements, fully functional plant and other works which may include architectural, civil, mechanical, electrical or other works. The Employers requirements, which are to be provided with the Invitation to Tender, have to be precisely defined if future claims concerning the scope and quality of the Works are to be avoided. Not only is the Contractor responsible for design of the Works, but he also carries primary responsibility for the commissioning of the Works (including training of the Employers or end-users operational staff). In addition he will also be required to provide extensive documentation including as-built documents and operation manuals. The Red Book, CONS form of contract requires that the Works are to be valued by a process of admeasurement based on a Bill of Quantities. In contrast, P & DB contracts are based on a lump sum (The Accepted Contract Amount), which for evaluation purposes is to be broken down into convenient smaller lump sums. Occasionally hybrid P & DB contracts are encountered, which provide for some of the Works to be evaluated by reference to a Bill of Quantities and other parts to be valued as lump sums. The Employer risks the possibility that the Contractors designer may not be overly concerned at the possibility of quantity overruns. Those clauses of the P & DB contract that are amended from CONS, primarily as a consequence of the Contractors design and commissioning responsibilities, are commented upon below.
An Employers and Engineers Guide to the FIDIC Conditions of Contract, First Edition. Michael D. Robinson. 2013 John Wiley & Sons, Ltd. Published 2013 by John Wiley & Sons, Ltd.
Appendix A
148
Appendices
Sub-Clause 5.5 Training Sub-Clause 5.6 As-Built Drawings Sub-Clause 5.7 Operation and Maintenance Manuals
These three activities are closely interconnected and their preparation and execution can be time-consuming. Adequate time for these activities must be allowed in the preparation of the Programme. Both the Employer (Sub-Clause 5.5 Training) and the Engineer (Sub-Clause 5.6 As-Built Drawings and Sub-Clause 5.7 Operation and Maintenance Manuals) will be involved in the timely completion of these tasks.
Appendix A
Appendix A
149
Appendix A