These Installation Instructions are valid for antennas in the following version : Reflector 0.9 m (3 ft) Pipe mount for installation on pipe 114 mm ( 89 mm optional) Antenna offset to the left or to the right Standard installation on 114 mm pipe with offset to the left Safety collar for easy installation 2 spindles for fine adjustment of Elevation 15 and Azimuth 5 Reflector without shroud 200 km/h version : No sway bar 250 km/h version : With sway bar 33 mm x 1 m (mandatory)
It is important to mount the antenna exactly as described in this installation instruction. The installed antenna shall be inspected once per year by qualified personnel. RFS disclaims any responsibility for the result of improper or unsafe installation. This installation instruction has been written for qualified, skilled personnel. We reserve the right to alter details, especially with respect to technical improvement
Sales department : Radio Frequency Systems GmbH Kabelkamp 20, D-30179 Hannover (Germany) Tel. +49-511 676-25 20 Fax +49-511 676-25 21 Plant: RFS France Trignac Fax +33 02 40 90 41 43
1/9
1.
Tools required for installation (Tools are not included with antenna)
Hoisting device for 100 daN Torque wrench from 0 to 50 Nm Wrenches for hexagon bolts : M5(8), M6(10), M8(13), M10(17) M12(19) Shackle(s), roll(s), pulley(s) and lifting accessories 2 strong ropes (approx. length 1.5x tower high) 1 strong rope or cable (approx. length 2.5 tower high) Water balance, compass, cutter, tape measure Key for socket screw : M3(2.5)
2.
Antenna offset
Antenna Offset Overview
Reflector TOP at the antenna top
Offset left
Offset right
Holes for feed systems equipped with guy wires
NMT 535-01e
2/9
3.
3.1
3.2
3.3
Steel U-Mount 3 ft
3 screws M10x25 3 SL washer 10 3 washers 10.5 30 (Torque tighten) Eye spindle M10x100 2 brass nuts M10 2 washers 10.5
3.4
3.5
NMT 535-01e
C ar db
3/9
4.
Sway bar clamp installation (Only for antenna provided with a sway bar)
(Tighten the assembly, keeping the sway bar clamp 33 and the sway bar terminal free in rotation without gap) Sway bar clamp 33 (L-Profil 40x40) Sway bar terminal SL nut M8 Washer 8.4 24 Washer 10.5 30 Screw M10x30
Take care to not dust or damage the elevation spindle during manipulation
5. 6.
Feed system installation (refer to Feed Installation Instructions joined) Safety collar installation and orientation on pipe support
For an antenna Offset Left For an antenna Offset Right
Minimum space 35 mm
Minimum Space 35 mm
NMT 535-01e
4/9
7.
Strong rope attached on the reflector casting eye (8.5 mm) with a shackle, and linked to winch
Shackle
Steel mount
Strong rope fixed at the tower top. The rope is slipping through a steel ring attached with 2 shackles on reflector rim
Strong rope or cable fixed to antenna steel mount to avoid collision with the tower structure during hoisting
To winch
NMT 535-01e
5/9
8.
2 U-Bolts M12 4 washers 13 37 4 nuts M12 (handtigthen the V-bolts to permit the antenna free rotation around the pipe, for the azimuth spindle installation) Azimuth safety collar installed on pipe support
NMT 535-01e
6/9
9.
After complete azimuth adjustment, torque tighten the 4 first M12 nuts (V-bolts must have been greased) Steel clamp 4 M12 nuts (tighten with an usual wrench)
Loosen or tighten M10 brass nuts to adjust the azimuth of the antenna
10.
Loosen or tighten M10 brass nuts to adjust the elevation of the antenna
After complete elevation fine adjustment, torque tigthen the 3 M10 bolts, and lock the 2 M10 brass nuts on the steel mount
NMT 535-01e
7/9
11.
Sway bar installation (Only for antenna provided with a sway bar)
For antennas provided with a sway bar, the sway bar installation is mandatory !
Offset Left
Offset Right
Screw M10x70
2 screws M10x25 Alternative config. with optional interface SMA-SKO-48-114 for installation on pipe Sway bar tower structure extremity
Offset Left
Offset Right
25
25
After complete sway bar orientation, torque tighten all bolted joints
12.
Final Check
When the installation of the antenna has been completed, it is necessary to make sure that the installation instructions have been followed in all aspects. It is especially important to check that all bolted joints are torque tightly locked (mandatory).
Torque wrench