Академический Документы
Профессиональный Документы
Культура Документы
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc.
Where economic decisions occur over a considerable period of time we also need to consider:
interest inflation
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc.
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc.
Simple Interest
Interest that is computed only on the original sum or principal Total interest earned = I = P x i x n
Where
P present sum of money i interest rate n number of periods (years)
Future Value of a Loan with Simple Interest Amount of money due at the end of a loan
F = P + P i n or F = P (1 + i n ) Where
F = future value
F = $100 (1 + .09 x 2) = $118 Would you accept payment with simple interest terms? Would a bank?
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc. 6
Compound Interest
Interest that is computed on the original unpaid debt and the unpaid interest Total interest earned = In = P (1+i)n - P
Where
P present sum of money i interest rate n number of periods (years)
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc.
Future Value of a Loan with Compound Interest Amount of money due at the end of a loan
F = P(1+i)1(1+i)2..(1+i)n or F = P (1 + i)n Where
F = future value
F = $100 (1 + .09)2 = $118.81 Would you be more likely to accept payment with compound interest terms? Would a bank?
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc. 8
Simple and compound interest Single payment Principal = Interest = 100.00 9.00%
Short or long? When is the $ difference significant? You pick the time period.
Simple Compound Period amount factor amount factor Find Fs Given P Find F Given P n Fs/P F/P 0 100.000 100.000 1 109.000 109.000 2 118.000 118.810 3 127.000 129.503 4 136.000 141.158 5 145.000 153.862 6 154.000 167.710 7 163.000 182.804 8 172.000 199.256 9 181.000 217.189 10 190.000 236.736 11 199.000 258.043 12 208.000 281.266 13 217.000 306.580 14 226.000 334.173 15 235.000 364.248 16 244.000 397.031 17 253.000 432.763 Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc. 9 18 262.000 471.712 19 271.000 514.166 20 280.000 560.441
1 2 3 4
Repay Repay Interest Principal Equal annual Interest on installments unpaid balance End of loan Interest on unpaid balance Equal annual installments End of loan Compound and pay at end of loan
Interest Earned Declines Constant Declines at increasing rate Compounds at increasing rate until end of loan
1 0
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc.
This calculator is partially complete. If you complete the calculator you can earn 10 bonus points for your team.
$5,000 Principal 10.00% Interest rate (enter as .1 for 10%) 10 Years Plan 1 Enter 1 through 4 Principal payment Equal annual installments Interest payment EOY on unpaid principal
Amount owed at the beginning of the year Interest owed for that year Total owed at the end of year Total end of year payment
Years
Principal payment
1 2 3 4 5 6 7 8 9 10
5,000 4,500 4,000 3,500 3,000 2,500 2,000 1,500 1,000 500
500 450 400 350 300 250 200 150 100 50 2,750 500 500 500 500 500 2,500 500 450 400 350 300 2,000 500 550 605 666 732 3,053
5,500 4,950 4,400 3,850 3,300 2,750 2,200 1,650 1,100 550
500 500 500 500 500 500 500 500 500 500 5,000 0 0 0 0 5,000 5,000 314 345 380 418 459 1,915 -500 -550 -605 -666 7,321 5,000
1,000 950 900 850 800 750 700 650 600 550 7,750 500 500 500 500 5,500 7,500 814 814 814 814 814 4,069 0 0 0 0 8,053 1 8,053
1 2 3 4 5
1 2 3 4 5
1 2 3 4 5
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc.
Equivalence (1)
When an organization is indifferent as to whether it has a present sum of money now or the assurance of some other sum of money (or series of sums of money) in the future, we say that the present sum of money is equivalent to the future sum or series of sums.
Each of the plans on the previous slide is equivalent because each repays $5000 at the same 10% interest rate.
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc. 1 2
Equivalence (2)
Example : Four plans for repayment of $5000 in five years at 8% interest : - Plan 1 : At end of each year pay $1000 principle plus interest due.
(1) Year (2) Amount owed at beginning of year 5000 4000 3000 (3) Interest owed for that year (4) Total owed at end of year (5) Principle payment (6) Total end of year payment
[8% x (2)]
1 2 3 400 320 240
[(2) + (3)}
5400 4320 3240 1000 1000 1000 1400 1320 1240
4
5 Total
2000
1000
160
80 1200
2160
1080
1000
1000 5000
1160
1080 6200
13
Equivalence (3)
- Plan 2: Pay Interest due at end of each year and principal at end of five years
(1) (2) Amount owed at beginning of year (3) Interest owed for that year [8% x (2)] 1 2 3 4 5 Total 5000 5000 5000 5000 5000 400 400 400 400 400 2000 (4) Total owed at end of year [(2) + (3)} 5400 5400 5400 5400 5400 0 0 0 0 5000 5000 400 400 400 400 5400 7000
14
Year
Equivalence (4)
- Plan 3 : Pay in five equal end-of-year payments.
(1) Year (2) (3) (4) (5) (6)
Principl e payment
5000
4148 3227 2233 1159
400
331 258 178 93 1260
5400
4479 3485 2411 1252
852
921 994 1074 1159 5000
1252
1252 1252 1252 1252 6260
15
2
3 4 5 Total
Equivalence (5)
- Plan 4 : Pay interest and principal at the end of periods.
(1) Year (2) (3) (4) (5) (6)
Principl e payment
5000
5400 5832 6299 6803
400
432 467 504 544 2347
5400
5832 6299 6803 7347
0
0 0 0 5000 5000
0
0 0 0 7347 7347
16
2
3 4 5 Total
Equivalence (6)
ratio = total interest paid /total amount owed at the beginning of year.
Plan Total Interest paid Total amount owed at the beginning of year ratio
1 2
3 4
$ 1200 2000
1260 2347
$ 15000 25000
15767 29334
0,08 0,08
0,08 0,08
From our calculations, we more easily see why the repayment plans require the payment of different total sums of money, yet are actually equivalent to each other.
17
Given the choice of these two plans which would you choose?
Year 1 2 3 4 Plan 1 $1400 1320 1240 1160 Plan 2 $400 400 400 400
5 Total
1080 $6200
5400 $7000
To make a choice the cash flows must be altered so a comparison may be made.
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc. 1 8
Technique of Equivalence
Determine a single equivalent value at a point in time for plan 1. Determine a single equivalent value at a point in time for plan 2.
Both at the same interest rate.
Judge the relative attractiveness of the two alternatives from the comparable equivalent values.
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc. 1 9
$5,000 8.00% 5 Plan 1 Principal payment Equal annual installments Interest payment EOY on unpaid principal
Year s Interest owed for that year Total owed at the end of year
1 2 3 4 5 Totals
1,200 15,000
8.00%
As an example:
$4,876.63 9.00% 5 Plan 1 Principal payment Equal annual installments Interest payment EOY on unpaid principal
Year s Interest owed for that year Total owed at the end of year
1 2 3 4 5 Totals
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc.
20
($3,389.05) ($3,479.68)
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc.
Interest Formulas
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc.
2 2
Beginning balance
P P(1+i)
Ending balance
P(1+i) P(1+i)2
3
n
P(1+i)2
P(1+i)n-1
iP(1+i)2
iP(1+i)n-1
P(1+i)3
P(1+i)n
P at time 0 increases to P(1+i)n at the end of time n. Or a Future sum = present sum (1+i)n
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc. 2 3
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc.
2 4
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc.
2 5
F = P(F/P,i,n)
example : If $500 were deposited in a bank savings account, how much would be in the account 3 years hence if the bank paid 6% interest compounded annualy?
F=?
P = 500
n=3 i = 0,06
26
PF
1 i
F 1 i
P F 1 i
P = F(P/F,i,n)
27
P=?
n=6 i = 0,08
MENCARI F DIKETAHUI P
Rumus F = P (1+i)n Dengan Excel F =FV(i%,n,,-P) Dengan tabel F = P(F/P,i,n) Contoh: Bila sejumlah $500 didepositokan di bank, berapakah jumlahnya 3 tahun yang akan datang kalau bunga bank 6% per tahun?
F=?
P = 500
n=3 i = 0,06
29
MENCARI P DIKETAHUI F
Rumus P F 1 i Dengan Excel P =PV(i%,n,,-F) Dengan tabel P = F(P/F,i,n)
Contoh: Seorang investor dapat membeli tanah yang nilainya akan menjadi $ 10.000 dalam 6 tahun mendatang. Bila nilai tanah naik sebesar 8% setiap tahun, berapakah harga yang harus dibayar investor ini saat sekarang?
F = 10.000
P=?
n=6 i = 0,08
10.00%
Single Amount Factor Compound Amount Factor Present Worth Factor P/F $1.00 $8,052.55 0.90909 $7,320.50 0.82645 $6,655.00 0.75131 $6,050.00 0.68301 $5,500.00 0.62092 $5,000.00 0.56447 $4,545.45 0.51316 $4,132.23 0.46651 $3,756.57 0.42410 $3,415.07 0.38554 $3,104.61 0.35049 $2,822.37 0.31863 $2,565.79 0.28966 $2,332.54 0.26333 $2,120.49 0.23939 $1,927.72 0.21763 $1,752.47 0.19784 $1,593.15 0.17986 $1,448.32 0.16351 $1,316.66 0.14864 $1,196.96 0.09230 $743.22 0.05731 $461.48 0.02209 $177.92 0.00852 $68.60 0.00328 $26.45 0.00105 $8.43 0.00007 $0.58
n 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 25 30 40 50 60 72 100
F/P $1.00 $5,000.00 1.100 $5,500.00 1.210 $6,050.00 1.331 $6,655.00 1.464 $7,320.50 1.611 $8,052.55 1.772 $8,857.81 1.949 $9,743.59 2.144 $10,717.94 2.358 $11,789.74 2.594 $12,968.71 2.853 $14,265.58 3.138 $15,692.14 3.452 $17,261.36 3.797 $18,987.49 4.177 $20,886.24 4.595 $22,974.86 5.054 $25,272.35 5.560 $27,799.59 6.116 $30,579.55 6.727 $33,637.50 10.835 $54,173.53 17.449 $87,247.01 45.259 $226,296.28 117.391 $586,954.26 304.482 $1,522,408.20 955.594 $4,777,969.09 13,780.612 $68,903,061.70
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc.
3 1
Periods/year
Single Amount Factor Compound Amount Factor F/P i 9.00% 0.02% n 1.00 365 $1.00 1.090 1.094 $500.00 $545.00 $547.08 Present Worth Factor P/F $1.00 0.99975 0.91394 $547.08 $501.91 $500.00
3 2
Engineering Economic Analysis - Ninth Edition Newnan/Eschenbach/Lavelle Copyright 2004 by Oxford Unversity Press, Inc.