Вы находитесь на странице: 1из 182

400KV PROTECTION

PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)

BASICS OF ONE AND HALF CIRCUIT BREAKER SCHEME


PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)

ONE & HALF BREAKER DESCRIPTION


BUS-1 1-52 CB
MAIN BAY(1ST BAY) FOR FEEDER-1

LINE-1

2-52 CB

LINE-2
MAIN BAY(3RD BAY) FOR FEEDER-2

1. IN THIS TWO BUSES ARE PRIOVIDED. 2. THESE TWO BUSES ARE INTER CONNECTED BY THREE BREAKERS. 3. THEY ARE DESIGNATED AS 1-52 CB, 2-52 CB, 3-52 CB. 4. LINE-1 IS CONNECTED IN BETWEEN 1-52 CB & 2-52 CB. 5. LINE-2 IS CONNECTED IN BETWEEN 3-52 CB & 2-52 CB. 6. LINE-1 HAVING TWO FEEDING PATHS i.e A. VIA BUS-1 & 1-52 CB B. VIA BUS-2, 3-52 CB & 2-52 CB 7. LINE-2 HAVING TWO FEEDING PATHS i.e A. VIA BUS-2 & 3-52 CB B. VIA BUS-1, 1-52 CB & 2-52 CB 8. FOR INTURUPTING LINE-1 THE 1-52CB AND 2-52CB IS TO BE TRIPPED. 9. FOR INTURUPTING LINE-2 THE 3-52CB & 2-52CB IS TO BE TRIPPED. 10. FOR ANY PROBLEM IN LINE-1 OR LINE-2 ALONG WITH MAIN BREAKER THE MIDDLE BREAKER(2-52 CB) MUST TRIP. 11. NORMALLY IN ALL TYPES OF BUSBAR CONFIGUARATIONS ONE BREAKER IS SUFFICIENT FOR ONE FEEDER. 12. HERE TWO FEEDERS ARE CONTROLED BY THREE BREAKERS. 13. SO THESE TWO FEEDERS CONTROLLED BY THREE CIRCUIT BREAKERS IT IS CALLED ONE & HALF BREAKER SYSTEM. 14. THE BAY BETWEEN BUS-1 & LINE-1 IS CALLED MAIN BAY FOR FEEDER-1. 15. THE BAY BETWEEN LINE-1 & LINE-2 IS CALLED TIE BAY FOR FEEDER-1 & 2. 16. THE BAY BETWEEN BUS-2 & LINE-2 IS CALLED MAIN BAY FOR FEEDER-2. 17. IN THIS SYSTEM FULL DIA MEANS 2 FEEDERS CONTROLLED BY 3 CBs. 18. HALF DIA MEANS 1 FEEDER CONTROLLED BY 2 CBs.

3-52 CB BUS-2

TIE BAY (2ND BAY ) FOR FEEDER-1 & 2

GOPALA KRISHNA PALEPU ADE/MRT/ T&C/400KV SS/ O/O CE/400KV / L&SS/ VS APTRANSCO, HYDERABAD

ADVANTAGES & DISADVANTAGES OF ONE & HALF BREAKER SYSTEM


A.
1. 2. 3. 4. 5. 6. 7. 8.

ADVANTAGES:
THREE CIRCUIT BREAKERS IN A FULL DIA ARE ALWAYS INSERVICE. IF MAIN CB PROBLEM / FOR PERIODICAL MAINTANENCE, DURING THAT PERIOD THE FEEDER IS FEEDING FROM TIE CB. NEED NOT REQUIRE TRANSFER THE FEEDER. IF TIE CB PROBLEM / FOR PERIODICAL MAINTANENCE, DURING THAT PERIOD THE FEEDER IS FEEDING FROM MAIN CB. EVEN IF BOTH MAIN BREAKERS UNDER TROUBLE, DURING THAT PERIOD ONE FEEDER IS WORKS AS INCOMING AND OTHER FEEDER IS WORKS AS OUTGOING VIA TIE CB. (WITHOUT INTERUPTION TO FEEDERS) IF BUSBAR-1 OPERATED / FOR PERIODICAL MAINTANENCE, ONLY THE MAIN BREAKERS CONNECTED TO BUSBAR-1 WILL TRIP. DURING THAT PERIOD THE FEEDERS CONNECTED TO BUS-1 ARE FEEDING VIA TIE CB FROM BUS-2. IF BUSBAR-2 OPERATED / FOR PERIODICAL MAINTANENCE, ONLY THE MAIN BREAKERS CONNECTED TO BUSBAR-2 WILL TRIP. DURING THAT PERIOD THE FEEDERS CONNECTED TO BUS-2 ARE FEEDING VIA TIE CB FROM BUS-1. IN THIS BUSBAR PROTECTION IS SIMPLE AND NEED NOT REQUIRE SELECTION OF ISOLATOR. IT IS MORE RELIABLE SYSTEM FOR OPERATION & MAINTANENCE POINT OF VIEW.

B.
1. 2. 3. 4.

DISADVANTAGES
CT CONNECTIONS & PROTECTION TRIP LOGICS ARE SOME WHAT COMPLICATED. COST TOWARDS CTs, CIRCUIT BREAKERS & PANELS ARE TO BE INCREASED DUE TO EXTRA BAY. THE COST COMPARISION TABLE SHOWN IN NEXT PRESENTATION. THE OPERATIONS FOR OPERATOR POINT OF VIEW IS LITTLE BIT COMPLICATED WHEN COMPARED TO CONVENTIONAL SYSTEM. SPACE OCUPATION FOR BAY IS MORE i.e COST OF LAND IS INCREASE.

COST COMPARISION BETWEEN CONVENTIONAL SYSTEM & ONE AND HALF BREAKER SYSTEM FOR FEEDER
S.No
1.

EQUIPMENT
CIRCUIT BREAKERS CURRENT TRANSFORMERS 3 CT METHOD

CONVENTIONAL SYSTEM
1 No

ONE & HALF BREAKER SYSTEM FULL DIA (FOR 2 FEEDERS)


3 Nos

% INCREASE IN COST
50%

HALF DIA % INCREASE (FOR 1 FEEDER) IN COST


2 Nos 100%

INCLUDES THE COST OF CT MARSHELLING BOXES. 3 Nos 1 No 4 Nos 5 Nos 6 Nos I SET 3 SETS 50% 100% 125% 200% 30% 2 Nos 2 Nos 3 Nos 3 Nos 2 SETS 100% 100% 200% 200% 30%

2.

4 CT METHOD 5 CT METHOD 6 CT METHOD

3.

CONTROL & RELAY PANELS BAY MARSHALLING BOXES CONTROL CABLES

NORMALLY EXTRA PANEL IS TIE BAY PANEL. IT IS ARROUND 30% COST OF MAIN PANEL. BECAUSE IT IS NOT HAVING PROTECTION RELAYS( MM-1 & MM-2 AND OTHER RELAYS) . ONLY TIE CB TRIPPING RELAYS.

4.

1 No

3 Nos

50%

2 Nos

30%

5.

8 KM

30 KM

100%

20 KM

150%

SUBSTATION DESIGN/LAYOUT
(I-CONFIGUARATION)
FEEDER1 FEEDER3 FEEDER5 FEEDER7 FEEDER9 FEEDER11

BUS-1
BAY10 BAY13 BAY16 BAY1 BAY4 BAY7

BAY11

BAY14

BAY12

BAY15

BUS-2

FEEDER2

FEEDER4

FEEDER6

FEEDER8

FEEDER10

FEEDER12

BAY18

BAY3

BAY6

BAY9

BAY17

BAY2

BAY5

BAY8

SUBSTATION DESIGN/LAYOUT
(H-CONFIGUARATION)
FEEDER1
BAY2

FEEDER2

FEEDER5
BAY8

FEEDER6

FEEDER9

FEEDER10
BAY14

BAY13

BAY9

BUS-1

BUS-2
BAY10 BAY12 BAY16 BAY4 BAY18 BAY17 BAY6

BAY5

BAY11

FEEDER3

FEEDER4

FEEDER7

FEEDER8

FEEDER11

FEEDER12

BAY15

BAY1

BAY3

BAY7

CT METHODS IN ONE AND HALF CIRCUIT BREAKER SCHEME


PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)

DIFFERENT CT METHODS OF ONE & HALF BREAKER SYSTEM

CB LINE CB LINE CB LINE LINE CB LINE LINE CB CB

CB 3 CTs METHOD CB 4 CTs METHOD CB 5 CTs METHOD CB 6 CTs METHOD CB 6 CTs METHOD CB 6 CTs METHOD

CB AT/F CB AT/F CB CB CB CB AT/F AT/F AT/F AT/F

ONE & HALF BREAKER SYSTEM


(3CTS METHOD)
BUS-1 1-89 BUS-2 3-89

1-52CB 1-CT 1-89A 2-CT

3-52CB

3P1

P2

P2

3-CT 3 P1 3-89A

2-89A 2-52CB 1-89L

P1

3 3

P2

2-89B 3-89T

LINE 1 T/F-1

ONE & HALF BREAKER SYSTEM


(4CTS METHOD)
BUS-1 1-89 BUS-2 3-89

1-52CB 1-CT 1-89A 2-ACT 2-BCT


P1

3-52CB

3P1

P2

P2

3-CT 3 P1 3-89A

P2

2-89A 1-89L

P1

P2

2-52CB

2-89B 3-89T

LINE 1 T/F-1

ONE & HALF BREAKER SYSTEM


(5CTS METHOD)
BUS-1 1-89 BUS-2 3-89

1-52CB 1-CT 1-89A 2-CT


P1

3-52CB

3P1

P2

P2 P1

3 3-CT
3-89A

2-89A 1-89L 1L-CT

P2

2-52CB

2-89B 3-89T

3P1

P2

P2 P1

3 3T-CT

LINE 1 T/F-1

ONE & HALF BREAKER SYSTEM


(6CTS METHOD)
BUS-1 1-89
P2

BUS-2 3-89

1A-CT 3 P1

3A-CT

1-52CB
P2

3 P1 3
P2 P1

P2

3-52CB

P1

1B-CT

3B-CT

1-89A 2A-CT
P2

3-89A 2B-CT

P1

2-89A 1-89L

2-52CB

P1

P2

2-89B 3-89T

T/F-1 LINE 1

ONE & HALF BREAKER SYSTEM


(6CTS METHOD)
BUS-1 1-89 BUS-2 3-89

1-52CB
P2

3-52CB

P1

1-CT

3-CT

P2 P1

1-89A 2A-CT
P2

3-89A 2B-CT

P1

2-89A 1-89L
P2

2-52CB

P1

P2

2-89B 3-89T

3 1L-CT P1
LINE 1

3T-CT

3 P1

P2

T/F-1

ONE & HALF BREAKER SYSTEM


(6CTS METHOD)
BUS-1 1-89
P2 P1

BUS-2
P2

3 1-CT

P1

3 3-CT

3-89

1-52CB

3-52CB

1-89A 2A-CT
P2

3-89A 2B-CT

P1

2-89A 1-89L
P2

2-52CB

P1

P2

2-89B 3-89T

3 1L-CT P1
LINE 1

3T-CT

3 P1

P2

T/F-1

TYPICAL ONE & HALF BREAKER SYSTEM ADOPTED IN GIS


DS : DISCONNECTOR SWITCH, GS: GROUNDING SWITCH, CT: CURRENT TRANSFORMER, VD: VOLTAGE DIVIDER

TYPICAL ONE & HALF BREAKER SYSTEM ADOPTED IN GIS


DS : DISCONNECTOR SWITCH, GS: GROUNDING SWITCH, CT: CURRENT TRANSFORMER, VD: VOLTAGE DIVIDER

1-1/2 CB SYSTEM (SIEMENS VATECH)


VD VD GS GS GS GS GS VD GS GS GS VD

CT DS CB

CT DS DS

CT CB

CT DS DS

CT CB

CT DS

CORE WISE APLICATION OF CTs IN ONE AND HALF CIRCUIT BREAKER SCHEME
PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)

CURRENT TRANSFORMER CONNECTIONS IN 3CT METHOD 1 CT 2 CT 3 CT BUSBAR-1 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CORE 1
( PS)

PROTECTION

CONNECTED TO MAIN PROTECTION FOR TRANSFORMER

CORE 2
( PS)

BUSBAR-1 CHECKUP PROTECTION (SPARE) SPARE

2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO BACKUP PROTECTION AFTER LBB/BFR FOR TRANSFORMER METERING & ENERGY METER FOR AT/F SPARE BUSBAR-2 CHECKUP PROTECTION (SPARE) BUSBAR-2 PROTECTION

CORE 3
( 0.5 / 0.2)

CORE 4
(0.5 / 0.2)

METERING & ENERGY METER FOR FEEDER 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-2 PROTECTION AFTER LBB/BFR FOR FEEDER 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-1 PROTECTION FOR FEEDER

CORE 5
( PS)

CORE 6
( PS)

CURRENT TRANSFORMER CONNECTIONS IN 4CT METHOD 1- CT 2-BCT 2-ACT 3-CT CT SECONDARY CT SECONDARY SPARE SPARE CORE-1 CORE IS CORE IS
(PS)
CONNECTED TO BUSBAR-1 PROTECTION BUSBAR-1 CHECKUP PROTECTION (SPARE) CONNECTED TO BUSBAR-2 PROTECTION

CORE-2
(PS)

SPARE

SPARE

BUSBAR-2 CHECKUP PROTECTION (SPARE)

CORE-3
(0.5/0.2)

2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO PANEL METERS & ENERGY METER 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-2 PROTECTION AFTER LBB/BFR 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-1 PROTECTION

2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO PANEL METERS & ENERGY METER 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO BACKUP PROTECTION AFTER LBB/BFR 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN PROTECTION

CORE-4
(PS)

CORE-5
(PS)

CURRENT TRANSFORMER CONNECTIONS IN 5CT METHOD


1-CT CORE-1 (PS) CORE-2 (PS) CORE-3 (0.5/0.2) CORE-4 (PS) CORE-5 (PS)
BUSBAR-1 PROTECTION BUSBAR-1 CHECKUP PROTECTION (SPARE)

1-LCT
TEED PROT-1 (BAY 1&2) TEED PROT-2 (BAY 1&2)

2-CT
TEED PROT-1 (BAY 2&3) TEED PROT-2 (BAY 2&3)

3-TCT
TEED PROT-1 (BAY 2&3) TEED PROT-2 (BAY 2&3)

3-CT
BUSBAR-2 PROTECTION BUSBAR-2 CHECKUP PROTECTION (SPARE)

SPARE
TEED PROT-2 (BAY 1&2) AFTER LBB/BFR (1-52) TEED PROT-1 (BAY 1&2)

METERING & ENERGY METER MAIN-2 PROTECTION

SPARE
TEED PROT-2 (BAY 1&2) AFTER LBB/BFR (2-52) TEED PROT-1 (BAY 1&2)

METERING & ENERGY METER BACKUP PROTECTION

SPARE
TEED PROT-2 (BAY 2&3) AFTER LBB/BFR (3-52) TEED PROT-1 (BAY 2&3)

MAIN-1 PROTECTION

MAIN PROTECTION

CURRENT TRANSFORMER CONNECTIONS IN 6CT METHOD


(GIS or AIS with DEAD TANK CBs)
1B-CT CORE-1 (PS) CORE-2 (PS)
BUSBAR-1
PROTECTION

1A-CT

2B-CT

2A-CT

3A-CT

3B-CT
BUSBAR-2
PROTECTION

2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-1 PROTECTION 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-2 PROTECTION AFTER LBB/BFR 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO PANEL METERS & ENERGY METER

2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO MAIN-1 PROTECTION 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO BACKUP PROTECTION AFTER LBB/BFR 2CTs SECONDARIES ARE CONNECTED IN PARALLEL AND CONNECTED TO PANEL METERS & ENERGY METER

BUSBAR-1 CHECKUP
PROTECTION

BUSBAR-2 CHECKUP
PROTECTION

(SPARE)

(SPARE)

CORE-3 (0.5/0.2)

SPARE

SPARE

CURRENT TRANSFORMER CONNECTIONS IN 6CT METHOD


1-CT CORE-1 (PS) CORE-2 (PS) CORE-3 (0.5/0.2) CORE-4 (PS) CORE-5 (PS)
BUSBAR-1 PROTECTION BUSBAR-1 CHECKUP
PROTECTION (SPARE)

1L-CT
TEED PROT-1 (BAY 1&2) TEED PROT-2 (BAY 1&2) METERING & ENERGY METER MAIN-2 PROTECTION MAIN-1 PROTECTION

2A-CT
SPARE SPARE

2B-CT
SPARE SPARE

3T-CT
TEED PROT-1 (BAY 2&3) TEED PROT-2 (BAY 2&3) METERING & ENERGY METER BACKUP PROTECTION MAIN PROTECTION

3-CT
BUSBAR-2 PROTECTION BUSBAR-2 CHECKUP
PROTECTION (SPARE)

SPARE

SPARE

SPARE

SPARE

TEED PROT-2 (BAY 1&2)


AFTER LBB/BFR (1-52)

TEED PROT-2 (BAY 2&3) TEED PROT-1 (BAY 2&3)

TEED PROT-2 (BAY 1&2)


AFTER LBB/BFR (2-52)

TEED PROT-2 (BAY 2&3)


AFTER LBB/BFR (3-52)

TEED PROT-1 (BAY 1&2)

TEED PROT-1 (BAY 1&2)

TEED PROT-1 (BAY 2&3)

CT CORE CONEECTION DIAGRAMS IN ONE AND HALF CIRCUIT BREAKER SCHEME


PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)

BUS

3 3 3
3 1-52CB 2 1
P2

BUS BAR PROTECTION

BUS BAR CHECKUP PROT METERING

MAIN-2/BACKUP PROTECTION
MAIN-1 PROTECTION

3 3 3
1 2 3

3
1-89 1 2

3 3 3 3 3
P1

1-CT 5 1-89L 1-CVT

SINGLE BUS SYSTEM


CORES 3 4

ONE & HALF BREAKER ( 3 CT METHOD) WITH PROTECTION SCHEME


87BB1 BUSBAR-1 79 CVT VBB1 VBB1 VL1 / VL2 OR VBB2 25 BF 87L 21M2 VL1 CVT VL1 FEEDER1 / LINE1 79 VL1 / VBB1 VL2 / VBB2 25 21M1 VL1

BF

FEEDER2 / LINE2 MAIN-1 BF VBB2 CVT VBB2 VL2 / VL1 OR VBB1 79 25 BUSBAR-2 87BB2 MAIN-2 CVT VL2 PROTECTION OF LINE2 (OR TRANSFORMER, IF APPLICABLE)

ONE & HALF BREAKER ( 4 CT METHOD) WITH PROTECTION SCHEME


87BB1 BUSBAR-1 79 CVT VBB1 VBB1 VL1 / VL2 OR VBB2 25 BF 87L 21M2 VL1 CVT VL1 FEEDER1 / LINE1 21M1 VL1

79 VL1 / VBB1 VL2 / VBB2 25 BF

FEEDER2 / LINE2 MAIN-1 BF VBB2 CVT VBB2 VL2 / VL1 OR VBB1 79 25 BUSBAR-2 87BB2 MAIN-2 CVT VL2 PROTECTION OF LINE2 (OR TRANSFORMER, IF APPLICABLE)

ONE & HALF BREAKER ( 6 CT METHOD) WITH PROTECTION SCHEME


87BB1 BUSBAR-1 CVT VBB1 79 VBB1 VL1 / VL2 OR VBB2 25 BF VL1 21M1 VL1

87L

21M2

CVT

VL1 FEEDER1 / LINE1

79 VL1 / VBB1 VL2 / VBB2 25 BF

FEEDER2 / LINE2 MAIN-1 VL2 / VL1 OR VBB1 VBB2 BF MAIN-2 CVT VL2 PROTECTION OF LINE2 (OR TRANSFORMER, IF APPLICABLE)

VBB2 CVT

79 25

BUSBAR-2 87BB2

ONE & HALF BREAKER ( 5 CT METHOD) WITH PROTECTION SCHEME


87BB1 BUSBAR-1 79 CVT VBB1 VBB1 VL1 / VL2 OR VBB2 25 BF 21M1 87 TD1 HZ 87L 21M2 VL1 VL1

87 TD2 LZ

CVT

VL1 FEEDER1 / LINE1

79 VL1 / VBB1 VL2 / VBB2 25

BF

FEEDER2 / LINE2

.
BF VBB2 CVT VBB2 VL2 / VL1 OR VBB1 79 25 87 TD1 HZ BUSBAR-2 87BB2 87 TD2 LZ

CVT VL2 MAIN-1 PROTECTION OF LINE2 (OR TRANSFORMER, IF APPLICABLE) MAIN-2

ONE & HALF BREAKER ( 6 CT METHOD) WITH PROTECTION SCHEME


87BB1 BUSBAR-1 79 CVT VBB1 VBB1 VL1 / VL2 OR VBB2 25 BF 21M1 87 TD1 HZ 87L 21M2 VL1 VL1

87 TD2 LZ

CVT

VL1 FEEDER1 / LINE1

79 VL1 / VBB1 VL2 / VBB2 25

BF

FEEDER2 / LINE2

.
BF VBB2 CVT VBB2 VL2 / VL1 OR VBB1 79 25 87 TD1 HZ BUSBAR-2 87BB2 87 TD2 LZ

CVT VL2 MAIN-1 PROTECTION OF LINE2 (OR TRANSFORMER, IF APPLICABLE) MAIN-2

ONE & HALF BREAKER ( 6 CT METHOD) WITH PROTECTION SCHEME


87BB1 BUSBAR-1 21M1 CVT VBB1 79 VBB1 VL1 / VL2 OR VBB2 25 FEEDER1 / LINE1 BF 87 TD2 LZ 87 TD1 HZ 87L 21M2 VL1 VL1

CVT

VL1

79 VL1 / VBB1 VL2 / VBB2 25

BF

VL2 / VL1 OR VBB1 VBB2 VBB2 CVT

FEEDER2 / LINE2 79 CVT VL2 25 87 TD2 LZ BF 87 TD1 HZ BUSBAR-2 87BB2 MAIN-1 PROTECTION OF LINE2 (OR TRANSFORMER, IF APPLICABLE) MAIN-2

LINE PROTECTION
BUSBAR CHECKUP PROT
(CT CONNECTIONS IN 3CTs METHOD)

BUS BAR PROTECTION

BUS-1 1-89

BUS-2 3-89

1-52CB
P2

3-52CB

P1

3 3 3 3 3

CORES 12 3 4 5 2-89A

1-CT 2-CT 2-52CB 1 CORES 2 3 4 5 6 3-89A 3-89T

1-89A 1-89L

. . .

LINE 1

1-CVT

P1

3 3 3 3 3 3

P2

METERING
MAIN-2 PROTECTION MAIN-1 PROTECTION

3 3 3

2-89B

T/F-1

TRANSFORMER PROTECTION
1

(CT CONNECTIONS IN 3CTs METHOD)

1-89

3-89

1-52CB

3-52CB CORES 2 3 4 5 6
P2

3-CT 2-CT 1-89A 1-89L 2-52CB


P1

3 3 3 3 3 3

2-89A

CORES 2 3 4 5

P1

6
P22-89B

3-89A 3-89T

3 3 3

LINE 1

METERING MAIN-2 PROTECTION


LV CT

. .

T/F-1

MAIN-1 PROTECTION

BUS BAR PROTECTION

3 3 3 3 3

BUS-1

BUS-2

BUSBAR CHECKUP PROT

3 3 3

3 3 3

1 2 3

3 2 1

LINE PROTECTION
BUSBAR CHECKUP PROT
(CT CONNECTIONS IN 4CTs METHOD)

BUS BAR PROTECTION

BUS-1 1-89

BUS-2 3-89

1-52CB
P2

3-52CB

P1

3 3 3 3 3

1 CORES 2 3 4 5 2-89A 2-52CB 1 1-CT 2B-CT CORES 2 3 4 5


P2

1-89A 1-89L

3-89A 2-89B 3-89T

. . .

LINE 1

1-CVT

P1

3 3 3 3 3

METERING
MAIN-2 PROTECTION MAIN-1 PROTECTION

3 3 3

T/F-1

TRANSFORMER PROTECTION
1

(CT CONNECTIONS IN 4CTs METHOD)

1-89

3-89

1-52CB

3-52CB
P2

3-CT 2A-CT 1-89A 1-89L 1 CORES 2 3 4 5 2-52CB


P1

CORES 4 3 2

P1

3 3 3 3 3

2-89A

3-89A 2-89B 3-89T

3 3 3

P2

LINE 1

METERING MAIN-2 PROTECTION


LV CT

. .

T/F-1

MAIN-1 PROTECTION

BUS BAR PROTECTION

3 3 3 3 3

BUS-1

BUS-2

BUSBAR CHECKUP PROT

3 3 3

3 3 3

1 2 3

3 2 1

BUSBAR CHECKUP PROT

BUS BAR PROTECTION

BUS-1 1-89

LINE PROTECTION
(CT CONNECTIONS IN 5CTs METHOD)

BUS-2 3-89

TEED-2 PROT (BAY1&2)

1-52CB
P2

TEED-2 PROT (BAY2&3) TEED-1 PROT (BAY2&3)

TEED-1 PROT (BAY1&2)

3-52CB

1-CT

3 3 3

CORES 1 2 3

P1

1-89A 1-89L

1L-CT

P1

1-CVT

LINE 1

3 3 3

3 3 3 3 3

P2

CORES 4 3 2

3 3

.
2-89A 2-52CB 3-89A

P1

METERING MAIN-2 PROTECTION MAIN-1 PROTECTION

3 3 3 3 3
5 4 3 2 CORES 2-CT 1 2-89B
P2

3-89T

T/F-1

(CT CONNECTIONS IN 5CTs METHOD)


3 3

1-89

3 3 3

3-89

TEED-2 PROT (BAY1&2)

1-52CB

TEED-2 PROT (BAY2&3) TEED-1 PROT (BAY2&3)

TEED-1 PROT (BAY1&2)

3-52CB
P2

.
1-89A 1-89L 2-89A 2-52CB P1 5 2-CT 4 3 2 CORES

.
P2

3 3 3
2-89B

3-CT

3-89A 3-89T

P1

LV CT

METERING MAIN-2 PROTECTION MAIN-1 PROTECTION

3 3 3 3 3

P2

3T-CT

1-CVT

P1

LINE 1

T/F-1

BUSBAR CHECKUP PROT

BUS BAR PROTECTION

BUS-1

T/F PROTECTION
3

BUS-2

3 3

3 3 3
CORES 3 4 5 1 CORES 2 3 4 5

3 3 3 3 3

3 3 3

COMPARISION BETWEEN DIFFERENT CT METHODS


CT PURPOSE
BUSBAR & BUSBAR CHECKUP PROTECTION MAIN-1 MAIN-2 PROTECTION & METERING ADDITIONAL PROTECTION AVAILABLE

3 CT METHOD

4 CT METHOD

6 CT (S) METHOD

5 CT METHOD

6 CT (T1) METHOD

6 CT (T2) METHOD

1 CT FOR BUS-1 & 3 CT FOR BUS-2


1 CT & 2 CT

1 CT FOR BUS-1 1B CT FOR BUS-1 1 CT FOR BUS-1 & & & 3 CT FOR BUS-2 3B CT FOR BUS-2 3 CT FOR BUS-2
1 CT & 2B CT 1A CT & 2B CT 1L CT

1 CT FOR BUS-1 & 3 CT FOR BUS-2


1L CT ABOVE FOR FEEDER-1 BELOW FOR FEEDER-2

1 CT FOR BUS-1 & 3 CT FOR BUS-2


1L CT

ABOVE CT SECONDARIES ARE CONNECTED PARALLEL FOR FEEDER-1 BELOW CT SECONDARIES ARE CONNECTED PARALLEL FOR FEEDER-2 3 CT & 2 CT
STUB-1 & STUB-2 PROTECTION FOR LINE & AT/F

3 CT & 2A CT
STUB-1 & STUB-2 PROTECTION FOR LINE & AT/F

3A CT & 2A CT
STUB-1 & STUB-2 PROTECTION FOR LINE & ICT

3L CT
TEED-1 & TEED-2 PROTECTION FOR LINE & AT/F

3L CT
TEED-1 & TEED-2 PROTECTION FOR LINE & AT/F

3L CT
TEED-1 & TEED-2 PROTECTION FOR LINE & AT/F

STUB-1 & STUB-2 PROTECTION IS A NORMALLY INBUILT PROTECTION FOR MAIN-1 & MAIN-2 RELAYS IN CASE OF LATEST NUMERICAL RELAYS. STUB PROTECTION WORKS WHEN LINE ISOLATOR OPEN CONDITION ONLY.

TEED1 IS NORMALLY HIGH IMPEDENCE DIFFERENTIAL RELAY & TEED-2 IS NORMALLY LOW IMPEDENCE DIFFERENTIAL RELAY THESE ARE NOT INBUILT IN MAIN-1 & MAIN-2 RELAYS

BLIND ZONE

A FAULT BETWEEN CIRCUIT BREAKERS AND CT (END FAULT) MAY THEN STILL BE FED FROM ONE SIDE EVEN WHEN THE BREAKER HAS BEEN OPENED. CONSEQUENTLY, FINAL FAULT CLEARING BY CASCADED TRIPPING HAS TO BE ACCEPTED IN THIS CASE. THIS SITUATION LBB/BFR OPERATES AND TIME TAKEN TO CLEAR FAULT IS ABOUT 300 mSECs. THIS IS BLIND ZONE AREA MINIMUM CTs METHOD. REDUCING THE COST OF CTs TIE CB BLIND ZONE AREA IS TAKEN CARE. MAIN CB & TIE CB BLIND ZONE AREA IS TAKEN CARE BLIND ZONE FOR MAIN CB & TIE CB TIE CB BLIND ZONE AREA IS TAKEN CARE MAIN CB & TIE CB BLIND ZONE AREA IS TAKEN CARE

ADVANTAGES

WHEN THE FAULT IS TAKEN PLACE BETWEEN THE MAIN CB, TIE CB & LINE ISOLATOR DURING SERVICE ONLY DISTANCE SCHEME SHOULD TAKE CARE

WHEN THE FAULT IS TAKEN PLACE BETWEEN THE MAIN CB, TIE CB & LINE ISOLATOR DURING SERVICE ONLY TEED PROTECTION IN ADDITION TO DISTANCE SCHEME SHOULD TAKE CARE

400KV C.T. INFORMATION


PRIMARY CONNECTIONS : P1 P2 CURRENT RATING : 2000 AMPS

P1 P1 P2

P2

CORES CORE-1 CORE-2

CLASS PS PS

PURPOSE BUSBAR PROTECTION

SECONDARY CONNECTIONS CURRENT RATING : 1A 2000/ 1A 1S1 1S3 1000/ 1A 1S1 1S2 1S2 1S3 2S1 2S2 2S2 2S3 3S1 3S3 500/ 1A __

1S1 1S2 1S3

CORE-4 CORE-5

PS PS

4S1 4S2 5S1 5S2

MAIN-1 5S1 5S4 PROTECTION

5S1 5S3

EYE BOLT DESIGN

DEAD TANK DESIGN

MAIN-2 4S1 4S4 4S1 4S3 PROTECTION

2S1 2S23 2S

CORE-3 0.5 / 0.2

METERING

3S1 3S4

3S1 3S2

1 1 S1 1SS2 3

1 5S S2 5 S3 5 S4 5

4S1 4S2 4S3 4S4

HAIR PIN / U SHAPE DESIGN

BUSBAR CHECKUP 2S1 2S3 PROTECTION

__

2S1 2S2 2S3

3 3

3 3

5S1 5S2 5S3 5S4 4S1 4S2 4S3 4S4

U U

3S1 3S2 3S3 3S4

U
3S1 3S2 3S3 3S4

CT LOAD FLOW DIAGRAMS WHEN 1-52 CB OPEN (3 CT METHOD)


1000A LINE 1-CT 1-52CB
2000-1000-500/1A
0A

CORECORE- 1, 2, 3 FOR 0500/1A CORECORE- 4, 5, 6 FOR 1000/1A

AT/F 3-CT

500A

2-CT 2-52CB
P1 2000-1000-500/1A
1000A 1000A

2000-1000-500/1A
1500A

3-52CB

3 3
2.0A

S1

0A 0A

S1

S2 S3

S2

1.0A

1.0A 2.0A 3.0A

0A

1.0A

1.0A

1.0A 3.0A 2.0A 2.0A

1.0A 1.0A

MAIN-1/ MAIN-2/ METER FOR LINE

MAIN-1/ MAIN-2/ METER FOR AT/F

3
3.0A

P2

P1 S3

P2 S1

P1

P2 S1

CT LOAD FLOW DIAGRAMS WHEN 2-52 CB OPEN (3 CT METHOD)


1000A LINE 1-CT 1-52CB
2000-1000-500/1A
1000A

CORECORE- 1, 2, 3 FOR 0500/1A CORECORE- 4, 5, 6 FOR 1000/1A

AT/F 3-CT

500A

2-CT 2-52CB
P1 2000-1000-500/1A
0A 0A

2000-1000-500/1A
0500A

3-52CB

3 3
0A

S1

1.0A 1.0A

S2

S1 S3

S2

0A

0A 0A 1.0A

1.0A

0A

0A

0A 1.0A 0A 0A

1.0A 1.0A

MAIN-1/ MAIN-2/ METER FOR LINE

MAIN-1/ MAIN-2/ METER FOR AT/F

3
1.0A

P2

P1 S3

P2 S1

P1

P2 S1

CT LOAD FLOW DIAGRAMS WHEN 3-52 CB OPEN (3 CT METHOD)


1000A LINE 1-CT 1-52CB
2000-1000-500/1A
1500A

CORECORE- 1, 2, 3 FOR 0500/1A CORECORE- 4, 5, 6 FOR 1000/1A

AT/F 3-CT

500A

2-CT 2-52CB
P1 2000-1000-500/1A
500A 500A

2000-1000-500/1A
0A

3-52CB

3 3
1.0A

S1

1.5A 1.5A

S1

S2 S3

S2

0.5A

0.5A 1.0A 0A

1.5A

0.5A

0.5A

0.5A 0A 1.0A 1.0A

1.0A 1.0A

MAIN-1/ MAIN-2/ METER FOR LINE

MAIN-1/ MAIN-2/ METER FOR AT/F

3
0A

P2

P1 S3

P2 S1

P1

P2 S1

CT LOAD FLOW DIAGRAMS (3 CT METHOD)


1000A LINE-1 1-CT 1-52CB
2000-1000-500/1A
750A

LINE-2 2-CT 2-52CB


P1 2000-1000-500/1A
250A 250A

500A

3-CT
2000-1000-500/1A
750A

3-52CB

3 3
0.25A

S1

0.75A 0.75A

S1

S3 S3

S3

0.25A

0.25A 0.25A 0.75A

0.75A

0.25A

0.25A

0.25A 0.75A 0.25A 0.25A

1.0A 0.5A

MAIN-1/ MAIN-2/ METER FOR LINE-1

MAIN-1/ MAIN-2/ METER FOR LINE-2

3
0.75A

P2

P1 S3

P2 S1

P1

P2 S1

CT LOAD FLOW DIAGRAMS WHEN 1-52 CB OPEN ( 4 CT METHOD)


1000A LINE 1-CT 1-52CB
2000-1000-500/1A
0A

AT/F 2-ACT
2000-1000-500/1A
1000A

500A

2-BCT 2-52CB
1000A

3-CT
1500A

2000-1000-500/1A 2000-1000-500/1A

3-52CB

3
1.0A

S1

0A 0A

S1

S3

S2

2.0A 2.0A 1.0A

3.0A

0A

1.0A 2.0A 1.0A

1.0A

1.0A 3.0A 2.0A

1.0A

MAIN-1/ MAIN-2/ METER FOR LINE

MAIN-1/ MAIN-2/ METER FOR AT/F

3
3.0A

P2

P1 S3

P2

P1 S2

P1

P2 S1

P1

P2 S1

CT LOAD FLOW DIAGRAMS WHEN 2-52 CB OPEN (4 CT METHOD)


1000A LINE 1-CT 1-52CB
2000-1000-500/1A
1000A

AT/F 2-ACT
2000-1000-500/1A
0A

500A

2-BCT 2-52CB
0A

3-CT
500A

2000-1000-500/1A 2000-1000-500/1A

3-52CB

3
0A

S1

1.0A 1.0A

S1

S3

S2

0A 0A 0A

1.0A

1.0A

0A 0A

0A

0A 1.0A 0A

1.0A 1.0A

MAIN-1/ MAIN-2/ METER FOR LINE

MAIN-1/ MAIN-2/ METER FOR AT/F

3
1.0A

P2

P1 S3

P2

P1 S2

P1

P2 S1

P1

P2 S1

CT LOAD FLOW DIAGRAMS WHEN 3-52 CB OPEN ( 4 CT METHOD)


1000A LINE 1-CT 1-52CB
2000-1000-500/1A
1500A

AT/F 2-ACT
2000-1000-500/1A
500A

500A

2-BCT 2-52CB
500A

3-CT
0A

2000-1000-500/1A 2000-1000-500/1A

3-52CB

3
0.5A

S1

1.5A 1.5A

S1

S3
0.5A

S2

1.0A 1.0A

0A

1.5A

0.5A 1.0A

0.5A

0.5A 0A 1.0A

1.0A 1.0A

MAIN-1/ MAIN-2/ METER FOR LINE

MAIN-1/ MAIN-2/ METER FOR AT/F

3
0A

P2

P1 S3

P2

P1 S2

P1

P2 S1

P1

P2 S1

CT LOAD FLOW DIAGRAMS ( 4 CT METHOD)


500A LINE-1 1-CT 1-52CB
2000-1000-500/1A
750A

LINE-2 2-ACT
2000-1000-500/1A
250A

1000A

2-BCT 2-52CB
250A

3-CT
750A

2000-1000-500/1A 2000-1000-500/1A

3-52CB

3
0.25A

S1

0.75A 0.75A

S1

S3

S3

0.25A 0.25A 0.25A

0.75A

0.75A

0.75A

0.25A 0.25A

0.25A 0.25A 0.75A 0.25A

0.5A 1.0A

MAIN-1/ MAIN-2/ METER FOR LINE-1

MAIN-1/ MAIN-2/ METER FOR LINE-2

P2

P1 S3

P2

P1 S3

P1

P2 S1

P1

P2 S1

TRIP LOGICS OF ONE AND HALF CIRCUIT BREAKER SCHEME


PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)

PROTECTION TRIP SCHEME


86-A MTR/ HSTR ABB REL521 MAIN-1 86-A MTR/ HSTR ABB RET521 MAIN-1 86-A MTR/ HSTR

TRIP COIL-1 1-52CB TRIP COIL-2 BUS-1 86 ABB -B REL521 MTR/ MAIN HSTR -1 ABB REL316 MAIN-2

TRIP COIL-1 2-52CB TRIP COIL-2

TRIP COIL-1 3-52CB TRIP COIL-2 BUS-2 ABB RET316 MAIN-2 86-B MTR/ HSTR

86-B MTR/ HSTR

86-A : GROUP-A MASTER TRIP RELAY / HIGH SPEED TRIP RELAY 86-B : GROUP-B MASTER TRIP RELAY / HIGH SPEED TRIP RELAY

MAIN-1/ MAIN-2 ZONE-1 & SINGLE PHASE FAULT


INITIATE MAIN CB GR-A 1-PH TRIP UNIT ( INTURN IT WILL TRIP 1-POLE )

REL 521
ACTIVE START TRIP

INITIATE TIE CB GR-A 1-PH TRIP UNIT ( INTURN IT WILL TRIP 1-POLE ) START MAIN CB AUTO RECLOSURE START TIE CB AUTO RECLOSURE

DISPLAY

CARRIER SEND INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA ) TO LBB/BFR INITIATION

REL 316
ACTIVE START TRIP

INITIATE MAIN CB GR-B 1-PH TRIP UNIT ( INTURN IT WILL TRIP 1-POLE ) INITIATE TIE CB GR-B 1-PH TRIP UNIT ( INTURN IT WILL TRIP 1-POLE ) START MAIN CB AUTO RECLOSURE START TIE CB AUTO RECLOSURE

DISPLAY

CARRIER SEND INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES)

INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA ) TO LBB/BFR INITIATION

CONDITIONS REQUIRED FOR A/R OPERATION


1. 2. 3. 4. 5. 6. 7. 7. 8. 9. 1. 2. 3. 4.

AUTO RECLOSURE

CB CLOSE CONDITION. TIME LAPSED MORE THAN RECLAIM TIME. OPERATING PRESSURE OF CB SUITABLE FOR AUTORECLOSURE OPERATION. DC SUPPLY TO AUTORECLOSURE SHOULD BE AVAILABLE. PREPARE 3-PH TRIP RELAY SHOULD BE RELEASED CONDITION. NO BLOCKING SIGNAL TO AUTORECLOSURE RELAY. POLE DISTURBANCE RELAY TIME SHOULD BE MORE THAN TWICE OF DEAD TIME OF AUTO RECLOSURE. CARRIER FAIL SIGNAL SHOULD NOT COME AT BOTH ENDS. CARRIER SWITCH SHOULD BE IN SERVICE CONDITION. SINGLE PHASE & ZONE-1 FAULT ONLY. TRIP MAIN CB SINGLE POLE. TRIP TIE CB SINGLE POLE. CLOSE MAIN CB AFTER DEAD TIME. IF A/R SUCCESS FOR MAIN CB THEN AFTER SUPPLEMENTARY TIME DELAY CLOSE TIE CB.(NORMALLY SUPPLEMENTARY TIME DELAY IS DEAD TIME) IF A/R UNSUCCESS THEN TRIP MAIN & TIE CBs. IF MAIN CB OPEN CONDITION, THEN NO SUPPLEMENTARY DELAY TIME FOR TIE A/R. IT WILL OPERATE ITs OWN DEAD TIME.

AUTO RECLOSURE OPERATION

5. 6.

MAIN-1/ MAIN-2 ZONE-1 & TWO / THREE PHASE FAULT


INITIATE MAIN CB GR-A 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES )

REL 521
ACTIVE START TRIP

INITIATE TIE CB GR-A 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE

DISPLAY

CARRIER SEND INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION CAME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA ) TO LBB/BFR INITIATION

REL 316
ACTIVE START TRIP

INITIATE MAIN CB GR-B 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES ) INITIATE TIE CB GR-B 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE

DISPLAY

CARRIER SEND INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES)

INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA ) TO LBB/BFR INITIATION

MAIN-1/ MAIN-2 ZONE-2 & 1 / 2 / 3 PHASE FAULT


INITIATE MAIN CB GR-A 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES ) CARRIER SIGNAL RECEIVED & ZONE-2 STARTER IS PICKUP CONDITION

REL 521
ACTIVE START TRIP

INITIATE TIE CB GR-A 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE

DISPLAY

TO LBB/BFR INITIATION INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION CAME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA )

CARRIER SIGNAL RECEIVED & ZONE-2 STARTER IS PICKUP CONDITION

REL 316
ACTIVE START TRIP

INITIATE MAIN CB GR-B 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES ) INITIATE TIE CB GR-B 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE

DISPLAY

CARRIER SEND ( IF PUTT OR2 SCHEME SELECTED ) INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES)

INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA ) TO LBB/BFR INITIATION

MAIN-1/ MAIN-2 ZONE- 3/4/5 & 1 / 2 / 3 PHASE FAULT


INITIATE MAIN CB GR-A 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES )

REL 521
ACTIVE START TRIP

INITIATE TIE CB GR-A 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE

DISPLAY

TO LBB/BFR INITIATION INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION CAME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA )

REL 316
ACTIVE START TRIP

INITIATE MAIN CB GR-B 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES ) INITIATE TIE CB GR-B 1-PH TRIP UNITS ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE

DISPLAY

TO LBB/BFR INITIATION INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES)

INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA )

86-GA & 86 GB MASTER TRIP / HIGH SPEED TRIP LOCKOUT RELAY OPERATION
TRIP COIL-1 TRIP COIL -1
86-GA MASTER TRIP / HIGH SPEED TRIP RELAY
OVER VOLTAGE STAGE-1 (INBUILT MAIN-1) DIRECT TRIP CHANNEL-1 RECEIVED SOTF PROTECTION (INBUILT MAIN-1) DEF,TOC, BOC, STUB (INBUILT MAIN-1) TEED-1 PROTECTION

86-GA MASTER TRIP / HIGH SPEED TRIP RELAY

TIE CB

MAIN CB

OVER VOLTAGE STAGE-1 ( IN BUILT MAIN-2 )

TRIP COIL-2

86-GB MASTER TRIP / HIGH SPEED TRIP RELAY

DIRECT TRIP CHANNEL-2 RECEIVED SOTF PROTECTION ( IN BUILT MAIN-2 ) OVER VOLTAGE STAGE-2 DEF, TOC, BOC, STUB ( IN BUILT MAIN-2 ) MAIN LBB OPERATED TIE LBB OPERATED TEED-2 PROTECTION

86-GB MASTER TRIP / HIGH SPEED TRIP RELAY

TRIP COIL -2

MASTER TRIP RELAYS HIGH SPEED TRIP RELAYS LOCKOUT RELAYS


PUSH BUTTON FOR RESETTING. TO CLOSING INTERLOCK OF CONCERNED BAY CB

86-GA MASTER TRIP / HIGH SPEED TRIP RELAY

TO INITIATE LBB/BFR OF CONCERNED BAY BLOCK AUTO RECLOSURE OF CONCERNED BAY TO TRIP COIL-1 CONCERNED BAY CB TO TRIP COIL-2 CONCERNED BAY CB INITIATE FLAG RELAY (FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER (MAIN-1 & MAIN-2) TO EVENT RECORDER ( SOE/ SCADA )

PUSH BUTTON FOR RESETTING.

TO CLOSING INTERLOCK OF CONCERNED BAY CB

86-GB MASTER TRIP / HIGH SPEED TRIP RELAY

TO INITIATE LBB/BFR OF CONCERNED BAY BLOCK AUTO RECLOSURE OF CONCERNED BAY TO TRIP COIL-1 CONCERNED BAY CB TO TRIP COIL-2 CONCERNED BAY CB INITIATE FLAG RELAY (FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER (MAIN-1 & MAIN-2) TO EVENT RECORDER ( SOE/ SCADA )

MAIN-1/ MAIN-2 OVER VOLTAGE STAGE-1


INITIATE MAIN CB 86-GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) 110% OF V 4 SECS FOR FEEDER-1 5 SECS FOR FEEDER-2

REL 521
ACTIVE START TRIP

INITIATE TIE CB 86-GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB & TIE CB AUTO RECLOSURE DIRECT TRANSFER TRIP-1 CARRIER SEND TO OTHER END

DISPLAY

DIRECT TRANSFER TRIP-2 CARRIER SEND TO OTHER END CLOSE INTERLOCK OF MAIN CB & TIE CB INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA )

110% OF V 4 SECS FOR FEEDER-1 5 SECS FOR FEEDER-2

REL 316
ACTIVE START TRIP

INITIATE MAIN CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE TIE CB 86-GR-a 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB & TIE CB AUTO RECLOSURE DIRECT TRANSFER TRIP-1 CARRIER SEND TO OTHER END

DISPLAY

DIRECT TRANSFER TRIP-2 CARRIER SEND TO OTHER END CLOSE INTERLOCK OF MAIN CB & TIE CB

INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA )

OVER VOLTAGE STAGE-2


INITIATE MAIN CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )

RXEG 21
ACTIVE START TRIP

INITIATE TIE CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB & TIE CB AUTO RECLOSURE DIRECT TRANSFER TRIP-1 CARRIER SEND TO OTHER END

120% OF V 20m SECS

DISPLAY

DIRECT TRANSFER TRIP-2 CARRIER SEND TO OTHER END CLOSE INTERLOCK OF MAIN CB & TIE CB INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER (MAIN-1 & MAIN-2) TO EVENT RECORDER ( SOE/ SCADA )

UNDER VOLTAGE RELAY


RXEG 21
ACTIVE START TRIP

1O% OF V

DISPLAY

LINE EARTH SWITCH CLOSE PERMISSION ONLY.

INITIATION
1-PH TRIP RELAYS OF MAIN-1 PROTECTION

MAIN LBB
INITIATE BUSBAR PROTECTION ( INTURN IT WILL TRIP CONNECTED BUS CBs)

RAICA
ACTIVE START TRIP

INITIATE TIE CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB & TIE CB AUTO RECLOSURE DIRECT TRANSFER TRIP-1 CARRIER SEND TO OTHER END DIRECT TRANSFER TRIP-2 CARRIER SEND TO OTHER END

1-PH TRIP RELAYS OF MAIN-2 PROTECTION

DISPLAY
86-GR-A MASTER TRIP RELAY 86-GR-B MASTER TRIP RELAY 96 BB BUSBAR RELAY

CLOSE INTERLOCK OF MAIN CB & TIE CB INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES)

INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER

TO EVENT RECORDER ( SOE/ SCADA )

INITIATION
1-PH TRIP RELAYS OF MAIN-1 PROTECTION OF LINE-1(BAY1) & LINE-2 (BAY3) 1-PH TRIP RELAYS OF MAIN-2 PROTECTION OF LINE-1 (BAY1) & LINE-2 (BAY 3) 86-GR-A MASTER TRIP RELAY

TIE LBB
INITIATE MAIN CB 86-GR-B 3-PH TRIP UNIT (TRIP BAY1 CB 3-POLES )

RAICA
ACTIVE START TRIP

INITIATE MAIN CB 86-GR-B 3-PH TRIP UNIT ( TRIP BAY3 CB 3-POLES ) BLOCK MAIN CB OF BAY1 & BAY3 AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE CLOSE INTERLOCK OF MAIN CB OF BAY1 & BAY 3 CLOSE INTERLOCK OF TIE CB

DISPLAY

DIRECT TRANSFER TRIP-1 CARRIER SEND TO BAY1 & BAY3 LINES DIRECT TRANSFER TRIP-2 CARRIER SEND TO BAY1 & BAY3 LINES

C
86-GR-B MASTER TRIP RELAY

INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER (BAY1 & BAY3)

TO EVENT RECORDER ( SOE/ SCADA )

DIRECT TRANSFER TRIP CHANNEL 1 / 2 RECEIVED


INITIATE MAIN CB 86-GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )

85 LO X1
ACTIVE START TRIP

INITIATE TIE CB 86-GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE

DIRECT TRIP CHANNEL-1 RECEIVED

DISPLAY

CLOSE INTERLOCK OF MAIN CB CLOSE INTERLOCK OF TIE CB INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA )

85 LO X2
ACTIVE START TRIP

INITIATE MAIN CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE TIE CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) BLOCK MAIN CB AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE

DIRECT TRIP CHANNEL-2 RECEIVED.

DISPLAY

CLOSE INTERLOCK OF MAIN CB CLOSE INTERLOCK OF TIE CB

INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER TO EVENT RECORDER ( SOE/ SCADA )

STUB PROTECTION TRIP SCHEME


LINE/TRANSFORMER ISOLATOR OPENS THIS INTERLOCK WILL INITIATE MAIN-1 REL 521/ RET 521 & CONVERTED STUB-1 PROTECTION 86-A MTR/ HSTR ABB REL521 STUB-1 86-A MTR/ HSTR ABB RET521 STUB-1 86-A MTR/ HSTR

TRIP COIL-1 1-52CB TRIP COIL-2 BUS-1 86 ABB -B REL521 MTR/ MAIN HSTR -1 ABB REL316 STUB-2

TRIP COIL-1 2-52CB TRIP COIL-2

TRIP COIL-1 3-52CB TRIP COIL-2 BUS-2 ABB RET316 STUB-2 86-B MTR/ HSTR

86-B MTR/ HSTR

LINE ISOLATOR OPENS THIS INTERLOCK WILL INITIATE MAIN-2 REL 316 / RET 316 & CONVERTED STUB-2 PROTECTION

86-A : GROUP-A MASTER TRIP RELAY / HIGH SPEED TRIP RELAY 86-B : GROUP-B MASTER TRIP RELAY / HIGH SPEED TRIP RELAY

TEED PROTECTION TRIP SCHEME


86-A MTR/ HSTR ABB RADHA TEED-1 86-A MTR/ HSTR ABB RADHA TEED-1 86-A MTR/ HSTR

TRIP COIL-1 1-52CB TRIP COIL-2 BUS-1 86 ABB -B REL521 MTR/ MAIN HSTR -1 ABB RADSB TEED-2

TRIP COIL-1 2-52CB TRIP COIL-2

TRIP COIL-1 3-52CB TRIP COIL-2 BUS-2 ABB RADSB TEED-2 86-B MTR/ HSTR

86-B MTR/ HSTR

86-A : GROUP-A MASTER TRIP RELAY / HIGH SPEED TRIP RELAY 86-B : GROUP-B MASTER TRIP RELAY / HIGH SPEED TRIP RELAY

CLOSING INTERLOCK OF MAIN & TIE CB


96 BB 86 GR-A 86 GR-B + VE T N C CB REMOTE CLOSE 21M1 AR MAIN CB

21M2 AR

86 GR-A

86 GR-B + VE T N C TIE CB CB REMOTE CLOSE

TIE

AR

TRANSFORMER PROTECTION
INITIATE 400KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )

RADSB

INITIATE 400KV TIE CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV TBC CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )

87 T

ACTIVE

START

TRIP

DISPLAY

INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO EVENT RECORDER ( SOE/ SCADA )

RADHD
ACTIVE START TRIP

INITIATE 400KV MAIN CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 400KV TIE CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV MAIN CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV TBC CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )

64 REF

DISPLAY

INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME)

TO EVENT RECORDER ( SOE/ SCADA )

TRANSFORMER PROTECTION
INITIATE 400KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )

RAPDK

INITIATE 400KV TIE CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV TBC CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )

67 HV ABCN

ACTIVE

START

TRIP

DISPLAY

INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO EVENT RECORDER ( SOE/ SCADA )

RAPDK
ACTIVE START TRIP

INITIATE 400KV MAIN CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 400KV TIE CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV MAIN CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV TBC CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )

67 LV ABCN

DISPLAY

INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME)

TO EVENT RECORDER ( SOE/ SCADA )

TRANSFORMER PROTECTION
INITIATE 400KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )

RALK

INITIATE 400KV TIE CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV TBC CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )

99T HV

ACTIVE

START

TRIP

DISPLAY

INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO EVENT RECORDER ( SOE/ SCADA )

RATUB
ACTIVE START TRIP

INITIATE 400KV MAIN CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 400KV TIE CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV MAIN CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV TBC CB GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )

99T LV

DISPLAY

INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME)

TO EVENT RECORDER ( SOE/ SCADA )

TRANSFORMER PROTECTION
INITIATE 400KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )

RXIG 21

INITIATE 400KV TIE CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV TBC CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )

51 O/L

ACTIVE

START

TRIP

DISPLAY

INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO EVENT RECORDER ( SOE/ SCADA )

RAEDK1
ACTIVE START TRIP

INITIATE 400KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 400KV TIE CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV MAIN CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INITIATE 220KV TBC CB GR-A 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES )

NDR

DISPLAY

INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME)

TO EVENT RECORDER ( SOE/ SCADA )

86-GA & 86 GB MASTER TRIP / HIGH SPEED TRIP LOCKOUT RELAY OPERATION
TRIP COIL-1 TRIP COIL -1
86-GA MASTER TRIP / HIGH SPEED TRIP RELAY
T/F DIFFERENTIAL RELAY 87 T B/U O/C & E/F PROTN RLY 67 ABCN INTER TRIP FROM LV SIDE ICT TROUBLES GR-A PROTECTION TRIP ICT HV OVER FLUX RELAY

86-GA MASTER TRIP / HIGH SPEED TRIP RELAY

TIE CB

MAIN CB

RESTRICTED EARTH FAULT RELAY 64 REF/T

TRIP COIL-2

86-GB MASTER TRIP / HIGH SPEED TRIP RELAY

INTER TRIP FROM LV SIDE ICT TROUBLES GR-B PROTECTION TRIP STUB RELAY 50ST MAIN LBB OPERATED TIE LBB OPERATED ICT LV OVER FLUX RELAY INTER TRIP FROM TBC LBB & MANUAL TRIP OF 220KV

86-GB MASTER TRIP / HIGH SPEED TRIP RELAY

TRIP COIL -2

INITIATION
86-GR-A MASTER TRIP RELAY 86-GR-B MASTER TRIP RELAY 96 BB BUSBAR RELAY

MAIN LBB
INITIATE BUSBAR PROTECTION ( INTURN IT WILL TRIP CONNECTED BUS CBs)

RAICA
ACTIVE START TRIP

INITIATE TIE CB 86-GR-B 3-PH TRIP UNIT ( INTURN IT WILL TRIP 3-POLES ) INTER TRIP TO 220KV LV MAIN CB INTER TRIP TO 220KV LV TBC CB CLOSE INTERLOCK OF MAIN CB & TIE CB

DISPLAY

INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME)

TO EVENT RECORDER ( SOE/ SCADA )

INITIATION
1-PH TRIP RELAYS OF MAIN-1 PROTECTION OF LINE-1(BAY1)

TIE LBB
INITIATE MAIN CB 86-GR-B 3-PH TRIP UNIT (TRIP BAY1 CB 3-POLES )

RAICA
ACTIVE START TRIP

INITIATE MAIN CB 86-GR-B 3-PH TRIP UNIT ( TRIP BAY3 CB 3-POLES ) BLOCK MAIN CB OF BAY1 AUTO RECLOSURE BLOCK TIE CB AUTO RECLOSURE CLOSE INTERLOCK OF MAIN CB OF BAY1 & BAY 3 CLOSE INTERLOCK OF TIE CB

1-PH TRIP RELAYS OF MAIN-2 PROTECTION OF LINE-1 (BAY1)

DISPLAY
86-GR-A MASTER TRIP RELAY

DIRECT TRANSFER TRIP-1 CARRIER SEND TO BAY1 & BAY3 LINES DIRECT TRANSFER TRIP-2 CARRIER SEND TO BAY1 & BAY3 LINES

C
86-GR-B MASTER TRIP RELAY

INITIATE FLAG RELAY (INTURN FLAG RELAY OPERATES) INITIATE ALARM (ANNUNCIATION COME) TO DISTURBANCE RECORDER (BAY1)

TO EVENT RECORDER ( SOE/ SCADA )

MAIN-1, MAIN-2 PROTECTION & METERING FOR LINE ADOPTED IN ONE AND HALF CIRCUIT BREAKER SCHEME

PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)

NORMS OF PROTECTION FOLLOWED IN APTRANSCO


FOR TRANSMISIION LINES & DISTRIBUTION LINES ( FEEDER / LINE PROTECTION )

Sr.No
1. 2. 3. 4. 5. 6.

VOLTAGE

MAIN- 1 PROTECTION
2 O/L + E/F ( 51 + 51N ) 3 O/L + E/F ( 51 + 51N ) SWITCHED DISTANCE SCHEME OR NUMERICAL DISTANCE SCHEME (21P+ 21N) NON SWITCHED DISTANCE SCHEME OR NUMERICAL DISTANCE SCHEME (21P + 21N) NON SWITCHED DISTANCE SCHEME OR

MAIN-2 PROTECTION/ BACKUP PROTECTION

11 KV LINES 33 KV LINES 66 KV LINES 132 KV LINES 220 KV LINES

3 O/L + E/F ( 50 + 50N + 51 + 51N + 67 + 67N ) SWITCHED DISTANCE SCHEME OR NUMERICAL DISTANCE SCHEME (21P+ 21N) NON SWITCHED DISTANCE SCHEME OR

400 KV LINES NUMERICAL DISTANCE SCHEME (21P + 21N) NUMERICAL DISTANCE SCHEME (21P + 21N)

IF MAIN-1 & MAIN-2 ARE NUMERICAL RELAYS, BOTH SHOULD BE SEPARATE MEASURING PRINCIPLES (CHARECTERESTICS), MODELS AND ALGORITHAMS (SHOULD NOT BE DUPLICATED) AND ALL FEATURES SHOULD BE AVAILABLE IN BOTH SCHEMES AND BOTH RELAYS SHOULD BE 100% REDENDENCY IN ALL ASPECTS ( COMPLEMENTARY TO EACH OTHER ). DISSIMILAR CARRIER SCHEMES ARE TO BE SELECTED ( POTT&PUTT ). ZONE-1: 80% OF MAIN LINE ZONE-2: 100% OF MAIN LINE + 50% OF SHORTEST LINE AT OTHER END ZONE-3: 100% OF MAIN LINE + 100% OF SHORTEST LINE AT OTHER END ZONE-4: 100% OF MAIN LINE + (100% OF SHORTEST LINE + 20% OF LONGEST LINE) AT OTHER END.

MAIN-1 PROTECTION FOR LINE


P2 P2 P2 1-CT
CTR: 2000-1000-500/1A

CT MB

(4CT METHOD)
IR5 / A511 IY5 / A531 IB5 / A551 VR11 / E111

CLASS: PS

2-BCT
CTR: 2000-1000-500/1A

CLASS: PS

3 3 3

CORE-5

3 3 3
5S4 5S4 5S2 5S2 5S2 5S2 5S4 5S4

CORE-5

REL 521
ACTIVE START TRIP

5S4 5S2

VY11 / E131 VB11 / E151 VN11 / E171 1-CVT

IN5 / A571

DISPLAY C E
CT MB

CORE 1 200VA CLASS: 3P

5S2 5S4

P2 P2 P2

MAIN-1 PROTECTION FOR LINE


(4CT METHOD) (NEW DEVELOPMENT)
P2 P2 P2 1-CT
CTR: 2000-1000-500/1A

CT MB IR5 / A511 IY5 / A531 IB5 / A551

CLASS: PS

2-BCT
CTR: 2000-1000-500/1A

CLASS: PS

3 3 3

CORE-5

3 3 3
5S4 5S4 5S2 5S2 5S2 5S2 5S4 5S4

CORE-5

5S4 5S2

IN5 / A571

IA =250.10 A IB =250.10 A IC =250.10 A VAB =400.0 KV VBC =400.0 KV VCA =400.0 KV

VR11 / E111 VY11 / E131 VB11 / E151 VN11 / E171

1-CVT CORE 1 200VA CLASS: 3P

ESC

ENT

CT MB

ENABLED TRIP

TARGET RESET

IN5 / A571
5S2 5S4

INST TIME COMM SOTF ZONE1 ZONE2 ZONE3 ZONE4

PH-A PH-B PH-C GND 50 51 79 RESET 79 LOCKOUT

IB5 / A551 IY5 / A531 IR5 / A511

P2 P2 P2

SEL

SEL- 421
PROTECTION AUTOMATION CONTROL

MAIN-1 PROTECTION FOR LINE


(5CT METHOD)
P2 P2 P2 1-LCT
CTR: 2000-1000-500/1A

CT MB IR5 / A511 IY5 / A531 IB5 / A551 VR11 / E111 VY11 / E131 VB11 / E151 VN11 / E171 1-CVT

CLASS: PS

3 3 3
5S4 5S4 5S2 5S2

CORE-5

REL 521
ACTIVE START TRIP

5S4 5S2

IN5 / A571

DISPLAY C E

CORE 1 200VA CLASS: 3P

MAIN-2 PROTECTION FOR LINE


(4CT METHOD)
50Z
P2 P2 P2 1-CT
CTR: 2000-1000-500/1A

CT MB

RAICA
4S4 4S4 4S4 4S2

CLASS: PS

2-BCT
CTR: 2000-1000-500/1A

CLASS: PS

3 3 3

CORE-4

3 3 3
4S2 4S2 4S2 4S2 4S4 4S4

CORE-4

IR4 / C411 IY4 / C431 IB4 / C451 IN4 / C471

LBB / BFR

REL 316
ACTIVE START TRIP

VR21 / E211 VY21 / E231 VB21 / E251 VN21 / E271 1-CVT

DISPLAY C E
CT MB

CORE 2 200VA CLASS: 3P

4S2 4S4

RAICA
LBB / BFR
P2 P2 P2

50ZT

MAIN-2 PROTECTION FOR LINE


(4CT METHOD) ( NEW DEVELOPMENT)
P2 P2 P2 1-CT
CTR: 2000-1000-500/1A

CT MB IR4 / C411 IY4 / C431 IB4 / C451 VR21 / E211 VY21 / E231 VB21 / E251 VN21 / E271

1-CVT CORE 2 200VA CLASS: 3P

CLASS: PS

2-BCT
CTR: 2000-1000-500/1A

CLASS: PS

3 3 3

CORE-4

3 3 3
4S4 4S4 4S2 4S2 4S2 4S2 4S4 4S4

CORE-4

4S4 4S2

IN4 / C471

CT MB

IN4 / C471
4S2 4S4

IB4 / C451 IY4 / C431 IR4 / C411

P2 P2 P2

MULTI FUNCTION NUMERICAL RELAY FOR MULTI BREAKER, MULTI CT & CVT/PT APPLICATION
(NEW APPLICATION) (ONE & HALF BREAKER SYSTEM or RING BUS SYSTEM)

1-52 CB

2-52 CB

3-52 CB

59

50 BF-1 50 BF-2 25-2


1-52,2-52: MAIN & TIE CIRCUIT BREAKER 21P: PHASE DISTANCE PROTECTION 21N: GROUND DISTANCE PROTECTION 27: UNDER VOLTAGE RELAY 67: DIRECTIONAL RELAY 50: INST OVER CURRENT RELAY 51: TIME OVER CURRENT RELAY 59: OVER VOLTAGE RELAY 64: EARTH FAULT RELAY 50BF-1: LBB/BFR OF MAIN CB 50BF-2: LBB/BFR OF TIE CB 79-1,2: AUTO RECLOSURE RELAY OF MAIN & TIE CB 25-1,2: CHECK SYNCHRONISAM RELAY FOR MAIN & TIE CB

79-1 79-2 25-1

21P 50P 51P 67P 27 21N 50N 51N 67N

3 LINE CVT
LINE

BUS-1 PT

BUS-2 PT

MAIN-2 PROTECTION FOR LINE


(5CT METHOD)
P2 P2 P2 1-LCT
CTR: 2000-1000-500/1A

CT MB IR4 / C411 IY4 / C431 IB4 / C451 VR21 / E211 VY21 / E231 VB21 / E251 VN21 / E271 1-CVT

CLASS: PS

3 3 3
4S4 4S4 4S2 4S2

CORE-4

REL 316
ACTIVE START TRIP

4S4 4S2

IN4 / C471

DISPLAY C E

CORE 2 200VA CLASS: 3P

MULTI FUNCTION PANEL METERING & ENERGY METER


(4CT METHOD)
P2 P2 P2 1-CT
CTR: 2000-1000-500/1A

CT MB IR3 / D311 IY3 / D331 IB3 / D351

CLASS: 0.5

2-BCT
CTR: 2000-1000-500/1A

CLASS: 0.5

3 3 3

CORE-3

3 3 3
3S4 3S4 3S2 3S2 3S2 3S2 3S4 3S4

CORE-3

3S4 3S2

IN3 / D371

CT MB

VR31 / E311 VY31 / E331 VB31 / E351 VN31 / E371 1-CVT CORE 3 100VA

3S2 3S4

P2 P2 P2

CLASS: 0.5

MULTI FUNCTION PANEL METERING & ENERGY METER


(5CT METHOD)
P2 P2 P2 1-LCT
CTR: 2000-1000-500/1A

CT MB IR3 / D311 IY3 / D331 IB3 / D351

CLASS: 0.5/0.2 IN3 / D371

3 3 3
3S4 3S4 3S2 3S2

CORE-3

3S4 3S2

VR31 / E311 VY31 / E331 VB31 / E351 VN31 / E371 1-CVT CORE 3 100VA CLASS: 0.5/0.2

BUSBAR PROTECTION SCHEMES ADOPTED IN ONE AND HALF CIRCUIT BREAKER SCHEME

PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)

BASICS OF BUSBAR PROTECTION


NEED FOR BUSBAR PROTECTION
IN ITS ABSENCE FAULT CLEARING TAKES PLACE IN ZONE-2 OF DISTANCE RELAY BY REMOTE END TRIPPING. THIS MEANS SLOW AND UNSELECTIVE TRIPPING AND WIDE SPREAD BLACKOUT.

EFFECT OF DELAYED CLEARENCE


GREATER DAMAGE AT FAULT POINT. INDIRECT SHOCK TO CONNECTED EQUIPMENT LIKE SHAFTS OF GENERATOR AND WINDINGS OF TRANSFORMER.

BASIC THEORY
KIRCHOFFs CURRENT LAW STATES THAT THE SUM OF THE CURRENTS ENTERING A GIVEN NODE MUST BE EQUAL TO THE CURRENTS LEAVING AT THAT NODE.

BUS BAR PROTECTION SYSTEMS


LOW IMPEDENCE DIFFERENTIAL PROTECTION
THE MOST SUITABLE PROTECTION SCHEME FOR DOUBLE AND MULTIPLE BUSBAR SYSTEMS (WITH OR WITHOUT TRANSFER BUS) WITH FEEDERS BEING SWITCHED BETWEEN SECTIONS OF BUSBAR, WHICH OPERATES WITH FULL SELECTIVITY FOR ALL POSSIBLE BUSBAR CONFIGUARATIONS.

HIGH IMPEDENCE DIFFERENCIAL PROTECTION


THE HIGH IMPEDENCE PROTECTION SCHEME, ON THE OTHER HAND, IS A GOOD SOLUTION FOR SINGLE BUSBAR ARRANGEMENTS , ONE & HALF BREAKER SYSTEMS OR RING BUSBARS, PROVIDING THAT APPROPRIATE DEDICATED CT CORES ARE AVAILABLE FOR THIS USE ALONE.

HIGH IMPEDENCE DIFFERENCIAL PROTECTION


SENSTIVE, STABLE & FAST PROTECTION FOR SINGLE BUSBAR ARRANGEMENTS AND ONE & HALF BREAKER SYSTEMS. THE SYSTEM HAS LIMITS WHEN USED IN COMPLEX BUSBAR CONFIGUARATIONS. HOWEVER, SPECIAL CT REQUIREMENTS, ADDITIONAL HIGH VOLTAGE DEVICE PROTECTION, DEMANDING MAINTANENCE ETC PUT RESTRICTIONS IN ITS APPLICATIONS.

LIMITATIONS OF CONVENTIONAL HIGH IMPEDENCE DIFFERENTIAL RELAY


PUTS STRINGENT REQUIREMENTS ON CTs. NEED FOR DEDICATED CT CORES. IDENTICAL CT RATIO, MAGNETISING IMPEDENCE. AUX CTs RATIO CORRECTIONS UNACCEPTABLE. IN ABILITY TO COPE WITH INCREASING FAULT CURRENT. SLOW RESPONSE. BASIC OPERATING TIME EXCLUDING RELAY TIME IS 15 20ms. THIS RELAY REQUIRES CHECK ZONE FEATURE. THE TRIP COMMAND IS ONLY GIVEN WHEN BOTH A DISCRIMINATING & CHECK ZONE SYSTEM OPERATES.

LOW IMPEDENCE DIFFERENTIAL PROTECTION


LOW IMPEDENCE PROTECTION(PERCENTAGE BIASED BUS DIFFERENTIAL RELAY) IS PREFARABLE FOR THE PROTECTION OF DOUBLE AND MULTIPLE BUSBAR SYSTEMS.

ADVANTAGES
FREE OF ANY NEED FOR MATCHED CT CHARACTERESTICS OR RATIOs, LOW LEAKAGE REACTANCE OR RESISTANCE. OTHER PROTECTIVE RELAYS CAN BE INCLUDED IN THE SAME CIRCUIT. STABLE FOR INFINITE FAULT LEVELS. INSENSITIVE TO CT SATURATION. DETECTS FAULTS WITHIN 1 2ms & INITIATES TRIPPING WITHIN 5 7ms.

BASICS OF BUS BAR PROTECTION


BASIC THEORY
KIRCHOFFs CURENT LAW STATES THAT THE SUM OF THE CURRENTS ENTERING A GIVEN NODE MUST BE EQUAL TO THE CURRENTS LEAVING THAT NODE

EXTERNAL FAULT
I1 I2 I3 I4 I5 I6 I5 I3 I1

INTERNAL FAULT
IF

I2

I4

I6

IF

IF= I6= I1+I2+I3+I4+I5

IF= I1+I2+I3+I4+I5+I6

HIGH IMPEDENCE BUSBAR PROTECTION


87BBC
96 BBC : BUSBAR CHECK TRIPPING RELAY

87BBM

U U

U U U U U U U U

U U

U U U U U U U U U U U U
52 CIRCUIT BREAKER TRIP COIL

- VE + VE

96 BBM : BUSBAR MAIN TRIPPING RELAY

U U

U U

U U

U U

U U
Is

OPERATING COIL

OVER CURRENT COIL

52 CIRCUIT BREAKER TRIP COIL

LOW IMPEDENCE BUSBAR PROTECTION

96 BUSB BAR TRIPPING RELAY

OVER CURRENT STARTER RELAYS

U U
RESTRAINT COIL

Id

+VE

-VE

DIFFERENCE BETWEEN BUSBAR SCHEMES


DETAILS
PRINCIPLE CTs

HIGH IMPEDENCE BUSBAR PROTECTION


THE CURRENTS ENTERING AND LEAVING THE BUSBAR ARE COMPARED CONTINUOSLY. IT INVOLVES CHOOSING OF IMPEDENCE HIGH ENOUGH STABLISE THE RELAY FOR HEAVY EXTERNAL FAULTS IT REQUIRES ALL IDENTICAL CT RATIOs & TURNS RATIO. LOW RESISTANCE OF SECONDARY WINDING MINIMUM KNEE POINT VOLTAGE OF 300300-500V. LOW MAGNETISING CURRENT(FEW MILLIAMPS).

PERCENTAGE BIASED LOW IMPEDENCE BUS BAR PROTECTION


IT HAS DIFFERENTIAL AND BIAS SETTING. THE RESULTANT BIAS IS PROPOTIONAL TO ARITHMATIC SUM OF ALL CURRENTS, WHEREAS THE OPERATING CURRENT IS VECTOR SUM OF ALL CIRCUIT CURRENTS. IT CAN WORK WITH CTs OF UNEQUAL RATIOS ALSO. FREE OF ANY NEED OF MATCHED CT CHARACTERESTIC OR RATIOs LOW LEAKAGE REACTANCE OR RESISTANCE. OTHER PROTECTIVE RELAYS CAN BE INCLUDED IN THE SAME CIRCUIT. IMPOSES LESS BURDEN ON CTs. AUXILIARY CTs HAVE NO EFFECT ON PERFORMANCE OF SCHEME. OPERATION OF SCHEME EVEN WHEN CTs GET SATURATED DURING INTERNAL FAULTS. INSENSITIVE TO CT SATURATION. MOST SUITABLE FOR DOUBLE AND MULTIPLE BUSBAR SYSTEMS ( WITH OR WITHOUT TRANSFER BUS). DETECTS FAULTS WITH IN 1 2 mS AND INITIATES TRIPPING WITH IN 55-7mS. STABLE FOR INFINITE FAULT LEVEL. HIGHLY SENSITIVE FOR INTERNAL FAULTS AND COMPLETELY STABLE FOR EXTERNAL FAULTS. THIS RELAY HAS IN BUILT CHECK ZONE FEATURE (NO SEPARATE CHECKZONE FEATURE) i.e OVER CURRENT STARTING RELAY PROVIDED.

BURDEN CT SATURATION UTILISATION OPERATING TIME STABILITY PERFORMANCE ADDITIONAL PROTECTION

IMPOSES COMPARATIVELY HIGH BURDEN ON CTs. AUXILIARY CTs REDUCE THE PERFORMANCE OF THE SCHEME OPERATION OF SCHEME EVEN WHEN CTs GET SATURATED DURING INTERNAL FAULTS. IT IS GOOD SOLUTION FOR SINGLE BUSBAR ARRANGEMENTS, ONE & HALF BREAKER SYSTEMS OR RING BUSBAR SYSTEMS. BASIC OPERATING TIME EXCLUDING RELAY TIME IS 15 20 mS. mS. INABILITY TO COPE WITH INCREASING FAULT CURRENT HIGHLY SENSITIVE FOR INTERNAL FAULTS AND COMPLETELY STABLE FOR EXTERNAL FAULTS. THIS RELAY REQUIRES CHECK ZONE FEATURE. THE TRIP COMMAND IS ONLY GIVEN WHEN BOTH A DISCRIMINATING & CHECK ZONE SYSTEM OPERATES.

BUS BAR PROTECTION


(4CT & 5CT METHOD)
P2 P2 P2 1-CT
CTR: 2000-1000/1A

CT MB

CLASS: PS

3-CT
CTR: 2000-1000/1A

CLASS: PS

3 3 3

CORE-1

3 3 3
1S3 1S3 1S1 1S1 1S1 1S1 1S3 1S3

CORE-1

IN1 / B171
1S3 1S1

REB 521
ACTIVE START TRIP

IB1 / B151 IY1 / B131 IR1 / B111

BUS BAR PROTECTION FOR BUS-1

DISPLAY C E REB 316


ACTIVE START TRIP

CT MB IR1 / B111 IY1 / B131 IB1 / B151


1S1 1S3

IN1 / B171

DISPLAY C E

P2 P2 P2

BUS BAR PROTECTION FOR BUS-2

3-52 3-CT 1-CT

BUS-2

BUS-1

U U
2-52

U U
1-52

ABB
6-52 6-CT 4-CT

U U
5-52

U U
4-52

9-52 9-CT

U U
8-52

7-CT

U U

7-52

12-52

12-CT

U U

11-52

10-CT

U U

10-52

15-52

15-CT

U U

14-52

13-CT

U U

13-52

18-52

BUS BAR PROTECTION

ABB RADSS 87 - BB BUS BAR-1 PROTECTION


16-52 17-52 18-CT 16-CT

RADSS 87 - BB BUS BAR-2 PROTECTION U U U U


21-52 21-CT

U U

20-52

19-CT

U U

19-52

BUSBAR-1 PROTECTION TRIPPING SCHEME


1-52 CB PANEL
TRIP FROM 50 LBB TO START 50 LBB

HIGH SPEED TRIP RELAY FOR 1-52 CB HIGH SPEED TRIP RELAY FOR 4-52 CB HIGH SPEED TRIP RELAY FOR 7-52 CB HIGH SPEED TRIP RELAY FOR 1010-52 CB HIGH SPEED TRIP RELAY FOR 1313-52 CB HIGH SPEED TRIP RELAY FOR 1616-52 CB
+VE

1-52 CB PANEL
TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER

4-52 CB PANEL

4-52 CB PANEL
TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER

REB 521
ACTIVE START TRIP

TRIP FROM 50 LBB TO START 50 LBB

7-52 CB PANEL
TRIP FROM 50 LBB TO START 50 LBB

7-52 CB PANEL
TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER

DISPLAY
1010-52 CB PANEL
TRIP FROM 50 LBB

10-52CB PANEL
TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER

TO START 50 LBB

13-52 CB PANEL
TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER

1313-52 CB PANEL
TRIP FROM 50 LBB TO START 50 LBB

1616-52 CB PANEL
TRIP FROM 50 LBB TO START 50 LBB

16-52 CB PANEL
TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER

BUSBAR PANEL

BUSBAR-2 PROTECTION TRIPPING SCHEME


3-52 CB PANEL
TRIP FROM 50 LBB TO START 50 LBB

HIGH SPEED TRIP RELAY FOR 3-52 CB HIGH SPEED TRIP RELAY FOR 6-52 CB HIGH SPEED TRIP RELAY FOR 9-52 CB HIGH SPEED TRIP RELAY FOR 1212-52 CB HIGH SPEED TRIP RELAY FOR 1515-52 CB HIGH SPEED TRIP RELAY FOR 1818-52 CB
+VE

3-52 CB PANEL
TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER

6-52 CB PANEL

6-52 CB PANEL
TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER

REB 316
ACTIVE START TRIP

TRIP FROM 50 LBB TO START 50 LBB

9-52 CB PANEL
TRIP FROM 50 LBB TO START 50 LBB

9-52 CB PANEL
TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER

DISPLAY
1212-52 CB PANEL
TRIP FROM 50 LBB

12-52CB PANEL
TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER

TO START 50 LBB

15-52 CB PANEL
TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER

1515-52 CB PANEL
TRIP FROM 50 LBB TO START 50 LBB

1818-52 CB PANEL
TRIP FROM 50 LBB TO START 50 LBB

18-52 CB PANEL
TO CLOSE CKT INTERLOCK TO BLOCK A/R TO TRIP COIL-1 TO TRIP COIL-2 DIRECT TRIP SEND CH-1 DIRECT TRIP SEND CH-2 TO DISTURBENCE RECORDER

BUSBAR PANEL

NUMERICAL CENTRALISED & DISTRIBUTED BUS BAR PROTECTION


(REB 500) ABB (7 SS 52) SIEMENS (MICOM P740) ALSTOM

OR
BUS-1

OR

10-52

11-52

BUS-2

OR

OR

12-52

15-52

3-52

6-52

9-52

14-52

2-52

5-52

8-52

13-52

1-52

4-52

7-52

MISCELENEOUS RELAYS & PROTECTIONS ADOPTED FOR LINE IN ONE AND HALF CIRCUIT BREAKER SCHEME
(STUB, TEED, LBB/BFR AND AUTO RECLOSURE FUNCTIONS) PREPARED BY
GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)

STUB-1/ STUB-2 PROTECTION


3 3
BUS-1 1-52CB

2-52CB

3-52CB

BUS-2

LINE-1

STUB-1&2 (BAY 1&2) 1-89L REL 521 REL 316

AT/F-1 DISTANCE RELAYS CONVERTED TO STUB/BUS OVER LOAD RELAYS WHEN LINE ISOLATOR OPENS

WHEN A LINE IS SUPPLIED VIA TWO CIRCUIT BREAKERS IN A ONE & HALF CIRCUIT BREAKER ARRANGEMENT, THE LINE PROTECTION INCLUDES THE AREA BETWEEN THE TWO CTs. HOWEVER, WHEN THE LINE ISOLATOR IS OPEN THE LINE CVTs FOR THE DISTANCE PROTECTION ARE CONNECTED TO THE LINE AND CANNOT PROVIDE THE CORRECT VOLTAGE FOR THE STUB END.(i.e THE AREA BETWEEN THE LINE ISOLATOR AND CTs) (STUB = DEAD END) TO PROVIDE PROTECTION FOR A FAULT IN THIS AREA, REL 521/ REL 316 IS PROVIDED WITH A STUB PROTECTION WHICH GIVES AN BUS OVER CURRENT TRIP IF THE LINE ISOLATOR IS OPEN AND THE CURRENT EXCEEDS THE SET VALUE IN ANY PHASE.

STUB-1 (BAY 1&2)


OPERATES

IT OPERATES THE 3PH TRIP GR-A MAIN CB (1-52CB) AND 3PH TRIP GR-A TIE CB (2-52CB) IT OPERATES THE 3PH TRIP GR-B MAIN CB (1-52CB) AND 3PH TRIP GR-B TIE CB (2-52CB)

STUB-2 (BAY 1&2)


OPERATES

STUB PROTECTION TRIP SCHEME


LINE/TRANSFORMER ISOLATOR OPENS THIS INTERLOCK WILL INITIATE MAIN-1 REL 521/ RET 521 & CONVERTED STUB-1 PROTECTION 86-A MTR/ HSTR ABB REL521 STUB-1 86-A MTR/ HSTR ABB RET521 STUB-1 86-A MTR/ HSTR

TRIP COIL-1 1-52CB TRIP COIL-2 BUS-1 86 ABB -B REL521 MTR/ MAIN HSTR -1 ABB REL316 STUB-2

TRIP COIL-1 2-52CB TRIP COIL-2

TRIP COIL-1 3-52CB TRIP COIL-2 BUS-2 ABB RET316 STUB-2 86-B MTR/ HSTR

86-B MTR/ HSTR

LINE ISOLATOR OPENS THIS INTERLOCK WILL INITIATE MAIN-2 REL 316 / RET 316 & CONVERTED STUB-2 PROTECTION

86-A : GROUP-A MASTER TRIP RELAY / HIGH SPEED TRIP RELAY 86-B : GROUP-B MASTER TRIP RELAY / HIGH SPEED TRIP RELAY

TEED-1 PROTECTION
P2 P2 P2 1-CT
CTR: 2000-1000-500/1A

{BAY1&2}(5CT METHOD) IR5 IY5 IB5

CLASS: PS P1 P1 P1 P2 P2 P2 2-CT
CTR: 2000-1000-500/1A

CLASS: PS

1-LCT
CTR: 2000-1000/1A

CLASS: PS

3 3 3

CORE-1

3 3 3

CORE-5

3 3 3
5S4 5S4 5S2 5S2 5S4 5S4 5S2 5S2 1S4 1S4 1S1 1S1

CORE-5

5S4 5S2

IN5

RADHA
IR5 IY5 IB5 IN5
P1 P1 P1 P2 P2 P2
ACTIVE START TRIP

5S4 5S2

DISPLAY C E

IN1
1S4 1S1

IB1 IY1 IR1


P1 P1 P1

TEED-1 PROTECTION FOR BAY 2&3 IS ALSO SAME AS ABOVE AND THE FOLLOWING CTs & CORES ARE USED 3-CT(CORE-5), 2-CT(CORE-1) & 3-TCT(CORE-1) ARE STARRED AND CONNECTED TO TEED-1 PROTECTION

TEED-2 PROTECTION
RAICA LBB/BFR
P2 P2 P2 1-CT
CTR: 2000-1000-500/1A

{BAY1&2}(5CT METHOD)
CT MB CT MB P2 P2 P2

CLASS: PS

1-LCT
CTR: 2000-1000/1A

CLASS: PS

3 3 3

CORE-2

3 3 3
4S4 4S4 4S2 4S2 2S3 2S3 2S2 2S2

CORE-4

4S4 4S2

RAICA LBB/BFR

RADSB
ACTIVE START TRIP

4S4 4S2

3 3 3
4S2 4S2

4S4

4S4

2-CT

DISPLAY
P2 P2 P2 CT MB

CORE-4
CTR: 2000-1000-500/1A

CLASS: PS

C
2S3 2S2

TEED-2 PROTECTION FOR BAY 2&3 IS ALSO SAME AS ABOVE AND THE FOLLOWING CTs & CORES ARE USED 3-CT(CORE-4), 2-CT(CORE-2) & 3-TCT(CORE-2) ARE CONNECTED TO TEED-2 PROTECTION

TEED-1/ TEED-2 PROTECTION


3 3 3
BUS-1 1-52CB TEED-1&2 (BAY 1&2) 2-52CB 3-52CB TEED-1&2 (BAY 2&3) BUS-2

LINE-1 AT/F-1 TEED PROTECTION IS BASED ON KIRCHOFFS CURRENT LAW. THREE SETS OF CTS ARE CONNECTED IN STAR FASHION. SOME OF THE CURRENTS MUST BE ZERO. IF ANY UNBALANCE CURRENTS ARE NOTICED THEN IMMEDIATELY TEED PROTECTION OPERATES. IF TEED PROTECTION BAY 1&2 OPERATED THEN IT TRIPS 1-52CB & 2-52CB. SIMILARLY IF TEED PROTECTION BAY 2&3 OPERATED THEN IT TRIPS 2-52CB & 3-52CB.

TEED-1 PROTECTION TEED-2 PROTECTION

SUMMATION OF INDIVIDUAL PHASES OF T-SHAPED 3 CTs BEFORE REACHING TO RELAY. THE CURRENT FLOWING THROUGH IN 3-PHASES AFTER SUMMATION IS ZERO DURING BALANCED CONDITION. HIGH IMPENDENCE THREE PHASE DIFFERENTIAL RELAY IS USED AS TEED-1 PROTECTION. T- SHAPED 3 CTs ARE CONNECTED TO RELAY. THE RELAY HAVING OPERATING COIL & RESTAIRING COIL. BASED ON THE DIFFERENTIAL CURRENT FLOWING THROUGH THE OPERATING COIL THE RELAY OPERATES. LOW IMPEDENCE PERCENTAGE BIASED THREE TERMINAL THREE PHASE DIFFERENTIAL RELAY IS USED AS TEED-2 PROTECTION.

TEED PROTECTION TRIP SCHEME


86-A MTR/ HSTR ABB RADHA TEED-1 86-A MTR/ HSTR ABB RADHA TEED-1 86-A MTR/ HSTR

TRIP COIL-1 1-52CB TRIP COIL-2 BUS-1 86 ABB -B REL521 MTR/ MAIN HSTR -1 ABB RADSB TEED-2

TRIP COIL-1 2-52CB TRIP COIL-2

TRIP COIL-1 3-52CB TRIP COIL-2 BUS-2 ABB RADSB TEED-2 86-B MTR/ HSTR

86-B MTR/ HSTR

86-A : GROUP-A MASTER TRIP RELAY / HIGH SPEED TRIP RELAY 86-B : GROUP-B MASTER TRIP RELAY / HIGH SPEED TRIP RELAY

BASICS OF LBB/BFR PROTECTION


LOCAL BREAKER BACKUP PROTECTION
A PROTECTION WHICH IS DESIGNED TO CLEAR A SYSTEM FAULTY BY INITIATING TRIPPING OTHER CIRCUIT BREAKER(S) IN THE CASE OF FAILURE TO TRIP OF THE APPROPRIATE CIRCUIT BREAKER. IN MODERN NETWORKS THE CRITICAL FAULT CLEARING TIME MAY BE LESS THAN 200ms. HENCE, IF THE FAULT IS NOT CLEARED DUE TO FAILURE OF THE PRIMARY PROTECTIVE RELAYS OR THEIR ASSOCIATED CIRCUIT BREAKER, A FAST ACTING BACKUP PROTECTIVE RELAY MUST CLEAR THE FAULT. THERE ARE TWO BASIC FORMS. REMOTE BACK-UP. LOCAL BACK-UP.

REMOTE BACK-UP
PROVIDES BACK-UP PROTECTION FOR THE BOTH THE RELAYS (MAIN-1 & MAIN-2) AND BREAKERS AT REMOTE SUBSTATION.

LOCAL BACK-UP
LOCAL BACK-UP PROTECTION CAN BE DEVIDED INTO TWO CATAGORIES. RELAY BACK-UP BREAKER BACK-UP

RELAY BACK-UP

DUPLICATE PRIMARY PROTECTION. i.e ONE IS NON SWITCHED DISTANCE PROTECTION AND ANOTHER IS SWITCHED DISTANCE SCHEME OR OTHER WISE BOTH SCHEMES CHARECTERSTICS ARE DIFFERENT (QUADRALATERAL, MHO CIRCULAR, TAMOTO & OPTICAL ) OR DIFFERENT MANUFACTURERS(ABB, ALSTOM, SIEMENS, EASUN REYROLL, SEL, GE, NXT PHASE OR BASLER) OR DIFFERENT METHODS (i.e ELECTROMECHANICAL, STATIC, NUMERICAL{MICROPROCESSOR &DSP}). IF MAIN-1 & MAIN-2 ARE NUMERICAL RELAYS BOTH SHOULD BE SEPARATE CHARECTERESTICS AND SEPARATE MODELS AND ALL FEATURES SHOULD BE AVAILABLE IN BOTH SCHEMES AND BOTH RELAYS SHOULD BE 100% REDENDENCY IN ALL ASPECTS TO INCREASE THE SECURITY, THE CIRCUIT BREAKER HAS TWO TRIP COILS, ONE IS CONNECTED TO MAIN-1 PROTECTION AND ANOTHER IS CONNECTED TO MAIN-2 PROTECTION. BECAUSE OF THE HIGH COST OF HIGH VOLTAGE CIRCUIT BREAKERS, IT IS NOT FEASIBLE TO DUPLICATE THEM. IN CASE OF A BREAKER FAILURE THE OTHER CIRCUIT BREAKERS CONNECTED TO THE SAME BUS AS THE FAULTED BREAKER MUST THERE FORE BE TRIPPED.

BREAKER BACK-UP

LBB/BFR FLOW CHART


MAIN PROTECTION OPERATED YES TRIP MAIN BREAKER FAULT CLEARED YES RESET BREAKER FAILURE SCHEME

NO

YES

INITIATE BFR

WAIT FOR FAULT CLEARENCE

AND

TRIP BACK-UP BREAKERS

LBB/BFR TIME CO-ORDINATION CHART


FAULT OCCURS

NORMAL CLEARING TIME

NORMAL CLEARING
PROTECTIVE RELAY FOR EX: DISTANCE RELAY BREAKER INTURUPTING TIME RESETTING TIME OF THE CURRENT MEASURING UNITS

MARGIN

~30ms

~60ms

<12ms
TRIPPING RELAY TIME BACK-UP BREAKER INTERUPTING TIME MARGIN

SET TIME OF THE TIME MEASURING UNIT

INOPERATIVE BREAKER

BREAKER FAILURE RELAY START TOTAL CLEARING TIME OF THE BREAKER FAILURE RELAY MAXIMUM FAULT CLEARING TIME BEFORE SYSTEM INSTABILITY

LBB/BFR LOGIC
CURRENT INPUTS PHASE L1 PHASE L2/E PHASE L3

A/D CONVERTER

PHASE CURRENT SET POINT

~
|||

I > ISET I > ISET


EARTH CURRENT SET POINT

& &

LED (PHASE START) ALARM RELAY (PHASE START)

>1
ALARM RELAY (EARTH START) LED (EARTH START)

OUT PUT OF DISTANCE RELAY OR SHORT CIRCUIT CURRENT RELAY BINARY INPUT CIRCUIT BREAKER FAILURE INITIATE

TIMING/OUTPUT STAGE

TIME STAGE T1

TRIP T1 RELAY

&
0
TIME STAGE T2 SWITCHED OFF TIME STAGE T2

LED

&
>1 O&

ALARM T1 RELAY TRIP T2 RELAY

LED LED
CB FAILURE INITIATE

LBB/BFR PROTECTION
LINE1 BUS-1 1-52CB 2-52CB 3-52CB AT/F-1 BUS-2

RAICA
LBB / BFR 50Z

RAICA
LBB / BFR 50ZT

RAICA
LBB / BFR 50Z

LBB/BFR IS LOCAL BREAKER BACKUP PROTECTION/ BREAKER FAILURE RELAY. 1No RELAY IS PROVIDED FOR EACH BREAKER. THIS IS CURRENT OPERATED RELAY. THIS RELAY IS ENERGISED WHEN MASTER TRIP RELAY(86-A OR/AND 86-B) OPERATES AND GIVEN SIGNAL TO BREAKER FOR TRIP. IN THIS RELAY TIME DELAY IS PROVIDED. THIS RELAY OPERATES WHEN THE BREAKER IS UNDER TROUBLE/ FAILS TO OPERATE. AFTER ENERGISED THE RELAY AND TIME DELAY COMPLETES, EVEN CURRENT IS THERE THIS THINKS BREAKER FAIL TO OPERATE AND GIVEN SIGNAL AS PER SCHEME DESCRIBED NEXT PRESENTATION.

1-52 CB LBB/BFR OPERATION


ABB REL521 MAIN-1 86-A 86-A 2-52CB TC-2 TC-1 86-B

ABB REL316 MAIN-2

DIRECT TRIP 1&2 VIA CARRIER TO OTHER END BUSBAR-1 PROTECTION OPTD AND BUSBAR-1 ISOLATED

INITIALISATION

LBB/BFR
TIME DELAY

1-52CB TC-1 BUS-1 TC-2

86-B

3-52CB BUS-2

2-52 CB LBB/BFR OPERATION


ABB REL521 MAIN-1 ABB RET521 MAIN-1 86-A

ABB REL316 MAIN-2


DIRECT TRIP 1&2 VIA CARRIER TO OTHER END TO 86-B TRIP RELAY OF LINE CB(1-52CB)
INITIALISATION

ABB RET316 MAIN-2


INTER TRIP TO LVCB & TBCCB TO 86-B TRIP RELAY OF AT/F(ICT) CB (3-52CB)

LBB/BFR
TIME DELAY

1-52CB TC-1 BUS-1

2-52CB TC-2

86-B

3-52CB BUS-2

3-52 CB LBB/BFR OPERATION


ABB RET521 MAIN-1 86-A 86-A 86-B

ABB RET316 MAIN-2

86-B

INITIALISATION

INTER TRIP TO LV CB & TBC CB BUSBAR-2 PROTECTION OPTD AND BUSBAR-2 ISOLATED

LBB/BFR
TIME DELAY

1-52CB TC-1 BUS-1

2-52CB TC-2 TC-2

3-52CB TC-1 BUS-2

AUTO RECLOSURE BASICS


FAULTS ARE THREE TYPES 1. TRANSIENT FAULT: These are cleared by the immediate tripping of Circuit Breakers and do not reoccur when the line is re-energized. 2. SEMI-PERMANENT FAULTS: These require a time interval to disappear before a line is charged again. 3. PERMANENT FAULTS: These are to be located and repaired before the line is re-energized. About 80-90% of the faults occurring are transient in nature. Hence the Automatic Reclosure of breaker (after tripping on Fault) will result in the line being successfully re-energized. ADVANTAGES: A. Decreasing outage time. B. Improving Reliability. C. Improving system stability. D. Reduce fault damage and Maintenance Time. DEAD TIME: The time between the Auto-reclosing Scheme being energized and the operation of the contacts which energize the Circuit Breaker closing circuit. RECLAIM TIME: The Time Following a successful closing operation measured from the instant the Auto-Reclosing relay closing contacts make which must elapse before the Auto-Reclosing relay initiates another reclosing attempt. In other words, it may be said to be the time between 1st and 2nd Auto-Reclosure.

TYPES OF AUTO-RECLOSING SCHEMES: 1. BASED ON PHASE A. THREE PHASE AUTO-RECLOSING: This type of Auto-Reclosing causes an immediate drift part of the two systems and hence no interchange of synchronizing power can take place during the dead time. B. SINGLE PHASE AUTO-RECLOSING: In this, only the faulty phase(only SLG Faults) is reclosed without causing interruption in interchange synchronizing power between two systems through other two healthy phases. 2. BASED ON ATTEMPTS OF RECLOSURE A. SINGLE SHOT AUTO-RECLOSING: In this scheme, Breaker is reclosed only once on a given fault before lockout of Circuit Breaker Occurs. High-Speed Auto-Reclosing for EHT System is invariably Single Shot. B. MULTI-SHOT AUTO-RECLOSING: In this scheme, more than one reclosing attempts made for a given fault before lockout of Circuit Breaker occurs. B.I. DISADVANTAGES: Repeated closure attempts has with high fault level would seriously affect the Circuit Breaker, Equipment and System Stability. B.ii. CIRCUIT BREAKER LIMITATIONS: Ability of Circuit Breaker to Perform several Trip Close operations in quick succession. B. iii. SYSTEM CONDITIONS: In the percentage of the semi-Permanent faults (which could be burnt out) is moderate, For example on the lines through the forest, multi shot Auto-Reclosing is followed. 3. DEPENDING ON SPEED: A. HIGH-SPEED AUTO-RECLOSING: This aids in fast restoration of supply but should be done by taking into account the following factors. I. System disturbance time can be tolerated without loss of system stability. ii. Characteristics of Protection Schemes and Circuit Breaker. B. LOW SPEED OR DELAYED AUTO RECLOSING: This is suitable for highly interconnected systems where the loss of a single line is unlikely to cause two sections of the system to drift apart and loose synchronism.

METHOD OF ADOPTION IN ONE AND HALF BREAKER SYSTEM: The Auto-Reclosure Functions used for the Bus Breakers 1-52CB & 3-52CB are set as Masters and one for the Center Breaker 2-52CB(TIE) as Follower. Co-ordination is required between the Auto-Reclosure Functions. A Synchrocheck function is also loaded in each Relay to permit 3 pole Auto-Reclosing. Each Line Protection relays starts both MAIN & TIE Circuit Breakers to trip for the Concerned line. After a Successful reclosure of the Main Breaker, The Tie Breaker will be reclosed after a supplementary time delay. Should the Main CB AutoReclosure relay not be successful in its reclosing attempts, the Tie CB AutoReclosure is blocked. If the Main CB is Open or its Auto-Reclosure Relay is not ready or Out of service, The TIE CB Auto-Reclosure will reclose The TIE Breaker after its own dead time without any supplementary time delay. CHOICES OF EHV SYSTEM: 1. CHOICE OF DEAD TIME: A. Lower limit is decided by deionising of Circuit Breaker. B. Upper Limit is decided by Transient Stability and Synchronism. C. Longer Transmission Lines Require Longer dead Time. D. The dead time for High Speed Auto-Reclosing scheme with EHV System is 0.3 to 1.2 sec. 2. CHOICE OF RECLAIM TIME: This should not be set to such a low value that the operating cycle of Breaker is exceeded when two faults incident occurs close together. The reclaim time will be in the range of 10 to 30 sec., depending the breaker opening and closing mechanisms. 3. CHOICE OF ZONE: This should normally kept in Zone-1. It is a Zone-1 fault and SLG fault only autoreclosure is comes in to picture. In other zones the auto reclosure is blocked.

AUTO-RECLOSURE FOR ONE & HALF BREAKER SCHEME


TRIP COMMANDS AUTO RECLOSURE COMMANDS

79 (A/R)+ 25(SYNC) RAAAM RASC

79 (A/R)+ 25(SYNC) RAAAM RASC

79 (A/R)+ 25(SYNC) RAAAM RASC

1-52CB

2-52CB

3-52CB

21 L1 MAINMAIN-1 REL 521

LINE-1

21 L2 MAINMAIN-2 REL 316

21 L1 MAINMAIN-1 REL 521

LINE-2

21 L2 MAINMAIN-2 REL 316

AUTO RECLOSING TIMING CHART


INSTANT OF FAULT
OPERATES RESETS PROTECTION

TRANSIENT FAULT

OPERATING TIME

ARC CONTACTS TRIP COIL CONTACTS ENERGISED SEPARATE EXTINGUISHED FULLY OPEN

CLOSING COIL CONTACTS CONTACTS MAKE FULLY CLOSED ENERGISED

CIRCUIT BREAKER
OPENING TIME ARCING TIME RESETS CLOSING TIME DEAD TIME OPERATES RESETS

OPERATING TIME OPERATES

PROTECTION

PERMANENT FAULT

OPERATING TIME

RECLOSE ON TO FAULT

TRIP COIL CONTACTS ARC CONTACTS ENERGISED SEPARATE EXTINGUISHED FULLY OPEN

CLOSING COIL CONTACTS CONTACTS ENERGISED MAKE FULLY CLOSED

CONTACTS ARC CONTACTS SEPARATE EXTINGUISHED FULLY OPEN

CIRCUIT BREAKER

OPENING TIME

ARCING TIME SYSTEM DISTURBANCE TIME

CLOSING TIME DEAD TIME

OPERATING TIME RECLOSE INITIATED BY PROTECTION

TRIP COIL ENERGISED

AUTO RECLOSE RELAY


DEAD TIME CLOSING PULSE TIME RECLAIM TIME

RELAY READY TO RESPOND TO FURTHER FAULT INCIDENTS (AFTER SUCEESFUL RECLOSRE)

TIME

CARRIER INTERTRIPPING SCHEMES ADOPTED IN ONE AND HALF CIRCUIT BREAKER SCHEME
PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)

PROTECTION COUPLER PANEL


15

ALARM-1 250V DC

NSD 50/ NSD 70


ACTIVE START TRIP

C S

2+ 5C R

TX TRIP A(C)

1C S

2+ 5C R

TX TRIP C(A)

6+

RX TRIP A(C)

6+

RX TRIP C(A)

DISPLAY C
7

ALARM-2 250V DC

C S

910+ 1314+

TX TRIP B(D)

9C S

10+ 13C R

TX TRIP D(B)

E
G4AA TB: V9LB

C R

RX TRIP B(D)

14+

RX TRIP D(B)

G4AC TB: V9LC

GA4D TB:V9LC

PROTECTION COUPLERS FOR 400KV LINE


FOR EACH LINE 2Nos PROTECTION COUPLER PANELS PROVIDED. FOR EACH LINE 1NO CARRIER SPEECH PANEL PROVIDED. SO, 1 LINE REQUIRES TOTAL 3 PANELS. CARRIER SPEECH PANEL PURELY FOR VOICE COMMUNICATION BETWEEN TWO SUBSTATIONS, i.e THE LINE CONNECTED SUBSTATIONS. THE VOICE COMMUNICATION ARE TWO METHODS PROVIDED. ONE IS HOTLINE COMMUNICATION/DEDICATED/ LIFT&TALK METHOD. ANOTHER IS DIAL METHOD. IN PROTECTION COUPLER PANEL-1 TOTAL 3 CARDS ARE IMPORTANT FOR SENDING & RECEIVING TRIP SIGNALS. ONE CARD FOR ALARM i.e G4AA. ONE CARD FOR PERMISSIVE/PROTECTION TRIP i.e G4AC & ANOTHER CARD FOR DIRECT TRIPS i.e G4AD. IN PROTECTION COUPLER-2 PANEL ALSO 3 CARDS ARE PROVIDED SIMILAR TO PROTECTION COUPLER-1 PANEL. THE PROTECTION COUPLER PANEL DRAWING IS SHOWN IN PREVIOUS MENU. 1SET TX & RX FOR PERMISSIVE/ PROTECTION TRIP(G4AC) 1SET TX & RX FOR BACKUP FOR PERMISSIVE/ PROTECTION IN ANOTHER PANEL(G4AC). 1SET TX & RX FOR DIRECT TRIP CHANNEL-1( G4AD). 1SET TX & RX FOR SPARE UNDER EMERGENCY(G4AD). THE ABOVE ARRANGEMENT SIMILAR FOR PROTECTION COUPLER PANEL-2. G4AA CARD FOR ALARM.

MAIN-1 PROTECTION CARRIER INTER TRIPPING


NSD 50
G4AC V9LC 1 G4AC V9LC 6 G4AC V9LC 5 G4AC V9LC 2
IN OUT CARRIER RECEIVE

ABB

REL521
CR -VE

CS
CARRIER SEND

ABB

G4AA V9LB 5 G4AA V9LB 6


PANEL-1
ALARM

+VE

-VE

NSD 50

G4AC V9LC 10 G4AC V9LC 13 G4AC V9LC 14 G4AC V9LC 9 THIS IS BACKUP FOR PERMISSIVE/ PROTECTION TRIP AND CONNECTED IN ANOTHER PANEL

ABB
PANEL-2

MAIN-2 PROTECTION CARRIER INTER TRIPPING


NSD 50
G4AC V9LC 1 G4AC V9LC 6 G4AC V9LC 5 G4AC V9LC 2
IN OUT CARRIER RECEIVE

ABB

REL316
CR -VE

CS
CARRIER SEND

ABB

G4AA V9LB 5 G4AA V9LB 6


PANEL-2
ALARM

+VE

-VE

NSD 50

G4AC V9LC 10 G4AC V9LC 13 G4AC V9LC 14 G4AC V9LC 9 THIS IS BACKUP FOR PERMISSIVE/ PROTECTION TRIP AND CONNECTED IN ANOTHER PANEL

ABB
PANEL-1

DIRECT TRIP SEND CARRIER CHANNEL-1


96 BUSBAR PROT-2 PANEL 87 BUSBAR TRIP (ZONE-2) 96 BUSBAR PROT-1 PANEL 87 BUSBAR TRIP (ZONE-1) CONTROL PANEL T NC

PANEL-1

ABB NSD 50
DC +VE FROM PANEL

MAIN CB(1-52CB)
T NC

TIE CB (2-52 CB)

TIE CB(2-52CB)
50 LBB/BFR FOR MAIN CB / RAICA 59L1 / OVER VOLTAGE STAGE-1 59L2 / OVER VOLTAGE STAGE-2 87 TEED1 / TEED-1 PROTECTION 87 TEED2 / TEED-2 PROTECTION 50 LBB/BFR FOR TIE CB / RAICA

G4AD V9LC 2 G4AD V9LC 1

MAIN CB (1-52 CB)

DC VE FROM PANEL CONDITIONS FOR DIRECT TRIP 1. TIE CB OPEN CONDITION + MAIN CB REMOTE HAND TRIP GIVEN. 2. MAIN CB OPEN CONDITION + TIE CB REMOTE HAND TRIP GIVEN. 3. TIE CB OPEN CONDITION + 96 BUSBAR-1 OPERATED. 4. MAIN CB OPEN CONDITION + 96 BUSBAR-2 OPERATED (FOR HALF DIA ONLY). 5. MAIN CB 50 LBB/BFR OPERATED. 6. TIE CB 50 LBB/BFR OPERATED. 7. 59L1 OVER VOLTAGE STAGE-1 OPERATED. 8. 59L2 OVER VOLTAGE STAGE-2 OPERATED. 9. 87 TEED-1 PROTECTION OPERATED 10. 87 TEED-2 PROTECTION OPERATED.

DIRECT TRIP SEND CARRIER CHANNEL-2


96 BUSBAR PROT-2 PANEL 87 BUSBAR TRIP (ZONE-2) 96 BUSBAR PROT-1 PANEL 87 BUSBAR TRIP (ZONE-1) CONTROL PANEL T NC

PANEL-2

ABB NSD 50
DC +VE FROM PANEL

MAIN CB(1-52CB)
T NC

TIE CB (2-52 CB)

TIE CB(2-52CB)
50 LBB/BFR FOR MAIN CB / RAICA 59L1 / OVER VOLTAGE STAGE-1 59L2 / OVER VOLTAGE STAGE-2 87 TEED1 / TEED-1 PROTECTION 87 TEED2 / TEED-2 PROTECTION 50 LBB/BFR FOR TIE CB / RAICA

G4AD V9LC 2 G4AD V9LC 1

MAIN CB (1-52 CB)

DC VE FROM PANEL CONDITIONS FOR DIRECT TRIP 1. TIE CB OPEN CONDITION + MAIN CB REMOTE HAND TRIP GIVEN. 2. MAIN CB OPEN CONDITION + TIE CB REMOTE HAND TRIP GIVEN. 3. TIE CB OPEN CONDITION + 96 BUSBAR-1 OPERATED. 4. MAIN CB OPEN CONDITION + 96 BUSBAR-2 OPERATED (FOR HALF DIA ONLY). 5. MAIN CB 50 LBB/BFR OPERATED. 6. TIE CB 50 LBB/BFR OPERATED. 7. 59L1 OVER VOLTAGE STAGE-1 OPERATED. 8. 59L2 OVER VOLTAGE STAGE-2 OPERATED. 9. 87 TEED-1 PROTECTION OPERATED 10. 87 TEED-2 PROTECTION OPERATED.

DIRECT TRIP RECEIVE CHANNEL-1&2


PANEL-1

ABB NSD 50
DC +VE G4AD V9LC 6 G4AD V9LC 5 PANEL-2
DIRECT TRIP-1 CARRIER RECEIVE RELAY

TO 86-A MASTER TRIP RELAY (HIGH SPEED TRIP RELAY) FOR MAIN CB(152CB) TO 86-A MASTER TRIP RELAY (HIGH SPEED TRIP RELAY) FOR TIE CB(252CB)

+VE

-VE TO 86-B MASTER TRIP RELAY (HIGH SPEED TRIP RELAY) FOR MAIN CB(152CB) TO 86-B MASTER TRIP RELAY (HIGH SPEED TRIP RELAY) FOR TIE CB(252CB)

ABB NSD 50
DC +VE G4AD V9LC 6 G4AD V9LC 5
DIRECT TRIP-2 CARRIER RECEIVE RELAY

PLCC CARRIER PROTECTION SYSTEM (TELEPROTECTION)


ABB Network Partner AG REL531 ABB Network Partner AG REL531

REL 521 MAIN-1 PROTECTION


C C E E

ELECTRICAL CONNECTION NSD 50 PANEL PLCC PANEL NSD 50 PANEL ELECTRICAL CONNECTION
ABB Network Partner AG REC 316*4 ABB Network Partner AG REC 316*4 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 1 9 10 11 12 13 14 15 16

NSD 50 PANEL PLCC PANEL NSD 50 PANEL

ELECTRICAL POWER LINE

REL 316 MAIN-2 PROTECTION

2 3 4 5 6 7 8

FIBRE OPTIC PROTECTION SYSTEM (TELEPROTECTION)


ABB Network Partner AG REL531 ABB Network Partner AG REL531

REL 521 MAIN-1 PROTECTION


C C E E

ELECTRICAL CONNECTION NSD 70 PANEL


GECOD/ SIFOX GECOD/ SIFOX
ABB Network Partner AG

NSD 70 PANEL TUNOS TUNOS FOX-U FOX-515 FOX-U FOX-515

NSD 70 PANEL

NSD 70 PANEL

ELECTRICAL CONNECTION
ABB Network Partner AG REC 316*4 REC 316*4 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 1 9 10 11 12 13 14 15 16

REL 316 MAIN-2 PROTECTION

2 3 4 5 6 7 8

FIBRE OPTIC CARRIER PROTECTION SYSTEM (TELEPROTECTION) DIGITAL RELAY CONNECTION VIA FIBRE OPTIC
ABB Network Partner AG REL531 ABB Network Partner AG REL531

REL 521 MAIN-1 PROTECTION


C C E E

OTERM

TUNOS

ABB Network Partner AG

REC 316*4

TUNOS

ABB Network Partner AG

REC 316*4

1 2 3 4 5 6 7 8

9 10 11 12 13 14 15 16

9 10 11 12 13 14 15 16

REL 316 MAIN-2 PROTECTION

2 3 4 5 6 7 8

OTERM
C E

FOX-U FOX-515

FOX-U FOX-515

MAIN-1 & MAIN-2 PROTECTION FOR AUTO TRANSFORMER ADOPTED IN ONE AND HALF CIRCUIT BREAKER SCHEME

PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)

BASICS OF TRANSFORMER PROTECTION


1. PURPOSE OF POWER TRANSFORMER PROTECTION POWER T/F PROTECTION IS USUALLY INSTALLED TO DISCONNECT THE T/F AT: A. INTERNAL SHORT CIRCUITS AND EARTH FAULTS IN THE T/F AND ITS CONNECTED CIRCUITS. B. EXTERNAL FAULTS ON OTHER CIRCUITS. (BACK-UP PROTECTION) C. ABNORMAL SERVICE CONDITIONS SUCH AS OVERLOAD & OVER VOLTAGE. PROTECTION DEVICES INBUILT OR MOUNTED ON POWER T/F A. OIL IMMERSED POWER T/F USUALLY HAVE A GAS DETECTOR AND OIL SURGE. DETECTOR (BUCHHOLZ ALARAM & TRIP DEVICES), WHICH ARE EXCELLENT FOR DETECTING INTERNAL FAULTS. B. LOAD TAPCHANGER COMPARTMENTS MAY HAVE A SIMILAR OVER PRESSURE DEVICE. C. TEMPARATURE MONITORS FOR OIL & WINDING PROVIDE GOOD OVER LOAD PROTECTION. D. PRESSURE RELIEF DEVICE IS PROVIDED TO SAFE GUARD THE T/F FROM HIGH PRESURES. TRANSFORMER DIFFERENTIAL PROTECTION IT IS WIDELY USED AS INSTANTANEOUS PROTECTION FOR SHORT CIRCUIT FAULTS WITH IN THE DIFFERENTIAL ZONE. THIS IS TREATED AS MAIN-1 PROT FOR T/F. THE MOST COMMON TYPE OF PROTECTION IS THE CURRENT RESTRAINT TYPE. SOME TYPE OF DIFFERENTIAL RELAYS REQUIRE INTERPOSING CTs FOR CT RATIO MATCHING AND/OR PHASE SHIFT. HIGH IMPEDENCE DIFFERENTIAL PROTECTION CAN BE USED ON AUTO T/F & REACTORS. IT COVERS ONE GALVANICALLY INTERCONNECTED WINDING (WDG DIFF). BUT NOT A SEPARATE TERTIARY WINDING. IT REQUIRES A THREE PHASE SET OF CTs AT THE NEUTRAL SIDE OF WINDING.

2.

3.

4.

5.

6.

RESTRICTED EARTH FAULT PROTECTION THIS IS A HIGH IMPEDENCE DIFFERENTIAL EARTH FAULT PROTECTION FOR ONE WINDING OR 1-PH. IT IS SOME TIMES USED IN LOW IMPEDENCE EARTHED SYSTEMS TO GIVE AN INSTANTANEOUS PROTECTION. WHICH IS MORE SENSITIVE THAN THE TRANSFORMER DIFFERENTIAL ONE. TYPICAL SENSITIVITY IS 5%. THERE ARE SOME PARTICULAR CT REQUIREMENTS, e.g. EQUAL TURNS RATIO OF THE CTs. INCASE OF T/F HAVING EARTHED STAR WINDING ONE RELAY SUFFICIENT. T/F HAVING STAR/STAR (BOTH EARTHED) APPLY TWO INDEPENDENT RELAYS. BACK UP PROTECTION A VARIETY OF RELAYS ARE AVAILABLE. A. OVER CURRENT & EARTH FAULT PROTECTION. ( 50, 50N, 51, 51N, 67, 67N - ANY COMBINATION OF THESE) B. UNDER IMPEDENCE / DISTANCE ( Z<)(21T). C. NEUTRAL DISPLACEMENT PROTECTION (Un>). OTHER TYPES OF RELAYS A. OVER VOLTAGE RELAY (U >). B. OVER FLUX/ EXCITATION (V/F >)( INVERSE TIME & DIFENITE TIME). FOR 400KV/220KV, 315 MVA & 500MVA TRANSFORMERS BOTH SIDES( i.e HV & LV) OVER FLUX RELAYS ARE PROVIDED BECAUSE BOTH SIDES HAVING GRID.

NORMALLY ADOPTED POWER TRANSFORMERS CAPACITIES IN 400KV / 220KV CAPACITY OF TRANSFORMER 315 MVA 500 MVA HV VOLTAGE 400 KV 400 KV HV CURRENT 454.68 A 721.71 A LV VOLTAGE 220 KV 220 KV LV CURRENT 0826.68 A 1312.20 A

NORMS OF PROTECTION FOLLOWED IN APTRANSCO


FOR POWER TRANSFORMERS & AUTO TRANSFORMERS
BACK UP PROTECTION HV LV

S.No

CAPA CITY

VOLTAGE RATIO

MAIN PROTECTION

ADDITIONAL SPECIAL PROTECTION PROTECTION


BUCHHOLZ, OLTC OSR OIL TEMP WDNG TEMP

7.5 MVA 16 MVA 16 MVA 31.5 MVA 50 MVA 31.5 MVA 50 MVA 100 MVA

132KV/11KV

3 OL + 1 DIR EL 3 OL + 1 DIR EL 3 OL + 1 DIR EL 3 OL + 1 DIR EL

3 OL + 1 EL 3 OL + 1 EL 3 OL + 1 EL 3 OL + 1 DIR EL

2 3 4

132KV/33KV 220KV/33KV 220KV/132KV

NIL BUCHHOLZ OVER FLUX OLTC OSR PRV/PRD OIL TEMP WDNG TEMP

DIFFERENTIAL RELAY

315 MVA 500 MVA

400KV/220KV

3 DIR OL 3 DIR OL (HIGHSET) + (HIGHSET) + 1 DIR EL 1 DIR EL (HIGHSET) (HIGHSET)

REF RELAY, OVER LOAD ALARM RELAY

MAIN-1/ DIFFERENTIAL PROTECTION FOR AT/F


(4 CT METHOD)
P2 P2 P2 3-CT
CTR: 2000-1000-500/1A

CT MB

AUX.CT Y/ 0.91 / 0.577A

CT MB

CLASS: PS

2-ACT
CTR: 2000-1000-500/1A 5S3 5S3 5S3 5S4

CLASS: PS

5S4

5S4

AUX.CT Y/ 0.91 / 0.577A

3 3 3

CORE-5

3 3 3
5S4 5S4 5S3 5S3

CORE-5

5S4 5S3

RET 521/ RET 316 RADSB


ACTIVE START TRIP

AUX.CT Y/ 0.689 / 0.577A

5S1 5S3

3 3 3
5S3 5S3

5S1

5S1

P2 P2 P2 LV-CT

DISPLAY
CT MB

CORE-5
CTR: 1200-800/1A

CLASS: PS

NORMALLY LOW IMPEDENCE BIASED DIFFERENTIAL RELAY IS USED FOR TRANSFORMER DIFFERENTIAL PROTECTION

P2 P2 P2

MAIN-1/ DIFFERENTIAL PROTECTION FOR AT/F


(5 CT METHOD)
CT MB

P2 P2 P2 3-TCT
CTR: 2000-1000-500/1A

CT MB

AUX.CT Y/ 0.91 / 0.577A

RET 521/ RET 316 RADSB


ACTIVE START TRIP

AUX.CT Y/ 0.689 / 0.577A

5S1 5S3

3 3 3
5S3 5S3

5S1

5S1

CLASS: PS

3 3 3
5S4 5S4 5S3 5S3

CORE-5

5S4 5S3

P2 P2 P2 LV-CT

DISPLAY C

CORE-5
CTR: 1200-800/1A

CLASS: PS

SELECTION OF AUX.CTs FOR DIFFERENTIAL PROTECTION


NORMALLY 400KV/220KV AUTO TRANSFORMERS ARE OF CAPACITY 315MVA. FOR MERZ PRICE PROTECTION IF TRANSFORMER IS CONNECTED IN STAR/STAR THEN CT SECONDARIES ARE TO BE CONNECTED IN DELTA/DELTA. CORRECT RATIO CTs ARE NOT AVAILABLE, THEN AUX.CTs ARE TO BE PROVIDED FOR ACHEVING SUITABLE CURRENTS. IF AUX CTs ARE USING THEN MAIN CT SECONDARIES ARE CONNECTED IN STAR. THIS IS BROUGHT TO AUX CTs. AUX CTs PRIMARY IS CONNECTED IN STAR & SECONDARIES ARE CONNECTED IN DELTA. NORMALLY THE RELAY RATED CURRRENT IS 1A. AUX.CT s SECONDARIES ARE CONNECTED IN DELTA. FOR ACHIEVING 1A TO RELAY, AUX.CT SECONDARY CURRENT IS TO BE 0.577A. THE FULL LOAD PRIMARY CURRENT OF 315MVA AT/F IS 454.7A. BUT THE 400KV CTs RATIOs ARE AVAILABLE : 2000-1000-500/1A NEAREST VALUE TO FULL LOAD CURRENT IS 500/1A. HENCE IT IS ADOPTED. HENCE AT FULL LOAD HV CURRENT i.e 454.7A, THEN SECONDARY OF CT CURRENT WILL BE 0.91A. SO HV SIDE AUX.CT RATIO IS 0.91/0.577A. THE FULL LOAD SECONDARY CURRENT OF 315MVA AT/F IS 826.7A. BUT THE 220KV CTs RATIOs ARE AVAILABLE: 1200-800/1A. NEAREST VALUE TO FULL LOAD CURRENT IS 1200/1A. HENCE IT IS ADOPTED. HENCE AT FULL LOAD LV CURRENT i.e 826.7A,THEN SECONDARY OF CT CURRENT WILL BE 0.689A. SO LV SIDE AUX CT RATIO IS 0.689/0.577A. SPECIAL INFORMATION: LATEST NUMERICAL RELAYS NEED NOT REQUIRE AUX CTs. IN THESE RELAYS, CT RATIOS MATCHING CAN BE PROGRAMMED.

MAIN-2/ BACKUP PROTECTION FOR AT/F HV


(4 CT METHOD)
P2 P2 P2 3-CT
CTR: 2000-1000-500/1A

CT MB

CLASS: PS

2-ACT
CTR: 2000-1000-500/1A

CLASS: PS

3 3 3

CORE-4

3 3 3
4S4 4S4 4S3 4S3 4S3 4S3 4S4 4S4

CORE-4

4S4 4S3

IR4 / C411 IY4 / C431 RAICA IB4 / C451 LBB / BFR IN4 / C471 50Z

VR11 / E111

RAPDK DIR O/L & E/F REL 505


ACTIVE START TRIP

VY11 / E131 VB11 / E151 VN11 / E171

3 3 3
E172 E174

3 3

DISPLAY
CT MB

CVT SELECTION BUS-1 CVT / BUS-2 CVT / LINE CVT CORE-1


VA : 200

C
4S3 4S4

IB4 / C451 IY4 / C431 IR4 / C411

CLASS: 3P

P2 P2 P2

MAIN-2/ BACKUP PROTECTION FOR AT/F HV


(5 CT METHOD)
VR11 / E111

P2 P2 P2 3-TCT
CTR: 2000-1000-500/1A

CT MB

CLASS: PS

3 3 3

CORE-4

IR4 / C411 IY4 / C431 IB4 / C451


4S4 4S4 4S4 4S3 4S3 4S3

RAPDK DIR O/L & E/F REL 505


ACTIVE START TRIP

VY11 / E131 VB11 / E151 VN11 / E171

3 3 3
E172 E174

3 3

IN4 / C471

DISPLAY C

CVT SELECTION BUS-1 CVT / BUS-2 CVT / LINE CVT CORE-1


VA : 200

CLASS: 3P

MAIN-2/ BACKUP PROTECTION FOR AT/F LV


P1 P1 P1 LV-CT
CTR: 1200 800 /1A

CT MB

CLASS: PS P2 P2 P2

3 3 3
4S2 4S2 4S1 4S1

CORE-4

4S2 4S1

IR4 / C411 IY4 / C431 RAICA IB4 / C451 LBB / BFR IN4 / C471 50Z

VR11 / E111

RAPDK DIR O/L & E/F REL 505


ACTIVE START TRIP

VY11 / E131 VB11 / E151 VN11 / E171

3 3 3
E172 E174

3 3
VOLTAGE

DISPLAY C

SELECTION BUS-1 PT / BUS-2 PT CORE-1


VA : 200

CLASS: 3P

MISCELLENEOUS RELAYS & PROTECTIONS ADOPTED FOR AUTO TRANSFORMER IN ONE AND HALF CIRCUIT BREAKER SCHEME
(OVER FLUX & REF FUNCTIONS) PREPARED BY
GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)

OVER EXCITATION/FLUX RELAY


{FOR AUTO TRANSFORMER HV & LV}
VOLTAGE SELECTION BUS-1 PT / BUS-2 PT CORE-1
VA : 200

RATUB V/F RELAY HV

CLASS: 3P

CVT SELECTION BUS-1 CVT / BUS-2 CVT / LINE CVT CORE-1


VA : 200

RATUB V/F RELAY LV

CLASS: 3P

315MVA, 400KV/220KV/33KV AT/F RESTRICTED EARTH FAULT RELAY P2 P2 P2


400KV HV CORE-1
CTR: 1000/1A

CLASS: PS P1 P1 P1 P1 P1 P1 NEUTRAL CORE-1


CTR: 1000/ 1A

CLASS: PS P2 P2 P2 P1 P1 P1 220KV LV CORE-1


CTR: 1000/1A

CLASS: PS

3 3 3

BUSHING CT

3 3 3

BUSHING CT

3 3 3
P2 P2 P2

BUSHING CT

RADHD
ACTIVE START TRIP

DISPLAY C E

FOR RESTRICTED EARTH FAULT PROTECTION AT/F BUSHING CTs SECONDARIES ARE CONNECTED IN PARALLEL & TO RELAY. (SINGLE PHASE HIGH IMPEDENCE DIFFERENTIAL RELAY IS USED)

315MVA, 400KV/220KV AT/F VOLAGE SELECTION


BUS-1 1-52CB 2-52CB 3-52CB BUS-2

LINE1

AT/F-1

FEEDER HAVING LINE CVTs &BUSES ARE HAVING BUS CVTs BUT AT/Fs ARE NOT HAVING CVTs. FOR TRANSFORMER PANEL, PT SUPPLY IS SELECTED AS PER SELECTION DESCRIBED BELOW FOR METERING AND PROTECTION, WHICH IS FIRST SELECTED .

BUS-1 CVT BUS-2 CVT LINE CVT

If AT/F is feeding from Bus-1 and 1-52CB & 2-52CB is closed. Then Bus-1 CVT is selected and this supply is extended to Control & Relay Panels for Auto Transformer. If AT/F is feeding from Bus-2 and 3-52 CB is closed & 2-52CB is open. Then Bus-2 CVT is selected and this supply is extended to Control & Relay Panels for Auto Transformer. If AT/F is feeding from Direct Line and 2-52CB is closed & 1-52 CB & 3-52 CB is open and 389T ISO is Closed . Then line CVT is selected and this supply is extended to Control & Relay Panels for Auto Transformer.

MAIN-1 & MAIN-2 PROTECTION FOR SHUNT REACTOR ADOPTED IN ONE AND HALF CIRCUIT BREAKER SCHEME

PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)

BASICS OF SHUNT REACTOR


1. TYPES OF REACTORS : A. BASED ON REACTOR CONNECTION i. SHUNT REACTOR. ii. SERIES REACTOR. B. BASED ON REACTOR LOCATION i. BUS REACTOR ii. LINE REACTOR C. BASED ON CONTROL i. 3-PH OIL IMMERSED REACTOR WITH GAPPED IRON CORE. ii. THYRISTOR CONTROLLED REACTOR (STATIC VAR COMPENSATOR) (APTRANSCO UTILISING SHUNT REACTORS FOR BUS & LINE IN 400KV NETWORK) NEED OF SHUNT REACTOR: A. LINE REACTOR SHUNT REACTORS ARE USED IN ORDER TO COMPENSATE FOR THE CAPACITIVE SHUNT REACTANCE OF TRANSMISSION LINES. THE REACTOR IS CONNECTED PARALLEL TO THE LINE. THE LOCATION OF REACTOR IS OUT GOING SIDE OF LINE i.e AFTER CIRCUIT BREAKER. LENGTH OF LINE IS MORE THERE MAY BE VOLTAGE IS RAISING DUE TO FARANTI EFFECT(CAPACITANCE ) DURING CHARGING. IN CASE OF ZONE-2 (OPEN JUMPER) FAULT, THE FAULT CLEARED BY REMOTE END IS FAST, BUT THIS END IT WILL TAKE TIME DELAY DUE TO ZONE-2. DURING THIS TIME, VOLTAGE MAY RAISING. SO, LINE REACTOR IS USED FOR CONTROLLING THE SWITCHING OVER VOLTAGES AND SAFEGUARD THE OPERATING EQUIPMENT. NORMALLY IT IS ALWAYS IN SERVICE. NORMALLY BOTH ENDS LINE REACTORS ARE PROVIDED. THE ELECTRICAL INTERLOCK IS PROVIDED THAT IF REACTOR ISOLATOR CLOSSED POSITION ONLY WILL GIVE PERMIT TO CLOSE THE LINE ISOLATOR. SIMILARLY FOR OPENING REACTOR ISOLATOR THE LINE ISOLATOR SHOULD BE IN OPEN POSITION.

2.

3.

4.

B. BUS REACTOR THE REACTOR IS CONNECTED PARALLEL TO THE BUS i.e LIKE A FEEDER/LINE. DURING LIGHTLY LOADED CONDITIONS THERE MAY BE POSSIBULITY OF RAISING BUS VOLTAGES. FOR SAFEGUARD THE OPERATING EQUIPMENT BUS REACTORS ARE UTILISING. NORMALLY IT IS NOT IN SERVICE. WHENEVER THE VOLTAGE RAISES TO 4%TO 5% MORE THAN THE RATED VOLTAGE THIS MAY BE KEPT IN SERVICE AND 2% TO 3% LESS THAN THE RATED VOLTAGE THIS MAY BE KEPT OUT OF SERVICE. SELECTION OF REACTOR A. LINE REACTOR NORMALLY LINE REACTORS ARE PROVIDED IF THE LINE IS MORE OR EQUAL TO 250KM. IN APTRANSCO NETWORK MAXIMUM LENTH OF LINE IS 350KM. AS PER SYSTEM STUDIES RECOMANDATIONS IF LINE LENGTH IS 250KM TO 300KM 50MVAR REACTOR IS TO BE USED. IF MORE THAN 300KM 63MVAR REACTOR IS TO BE USED. B. BUS REACTOR NORMALLY BUS REACTORS ARE PROVIDED IF THE SUBSTATION BUS VOLTAGE IS RAISING 5% MORE THAN THE RATED VOLTAGE DURING LIGHTLY LOADED CONDITION. BASED ON THE SYSTEM STUDIES RECOMANDATIONS BUS REACTORS ARE TO BE PROVIDED. CALCULATIONS ARE REQUIRED FOR PROVIDING BUS REACTOR. IN THIS THERE IS NO STANDARDISATION. LOCATION OF REACTORS WITH CAPACITY IN APTRANSCO A. LINE REACTOR 1. 400KV KALAPAKA-KHAMMAM 1 AT BOTH ENDS 63MVAR 2. 400KV KALAPAKA-KHAMMAM 2 AT BOTH ENDS 63MVAR B. BUS REACTOR 1. 400KV KALAPAKA SS 2 X 50 MVAR 2. 400KV NUNNA SS(PGCIL BAYS) 1 x 63 MVAR

5.

6.

7.

8.

9.

PURPOSE OF SHUNT REACTOR PROTECTION THE PURPOSE OF THE PROTECTION RELAYING IS TO DISCONNECT THE REACTOR AND LIMIT DAMAGE IN CASE OF INTERNAL SHORT CIRCUITS, EARTH FAULTS, INTERTURN FAULTS AND OVER VOLTAGE OR OVER LOAD.THE REACTOR FORMS CERTAIN IMPEDENCE FOR RATED FREQUENCY, AND AS IT IS SHUNT CONNECTED, AS OVER LOAD MAY BE CAUSED BY OVER VOLTAGE OR HARMONICS IN VOLTAGE AND CURRENT. PROTECTION DEVICES INBUILT OR MOUNTED ON REACTOR A. OIL IMMERSED REACTOR USUALLY HAVE A GAS DETECTOR AND OIL SURGE. DETECTOR (BUCHHOLZ ALARAM & TRIP DEVICES), WHICH ARE EXCELLENT FOR DETECTING INTERNAL FAULTS. B. TEMPARATURE MONITORS FOR OIL & WINDING PROVIDE GOOD OVER LOAD PROTECTION. C. PRESSURE RELIEF DEVICE IS PROVIDED TO SAFE GUARD THE REACTOR FROM HIGH PRESURES. REACTOR DIFFERENTIAL PROTECTION IT IS WIDELY USED AS INSTANTANEOUS PROTECTION FOR SHORT CIRCUIT FAULTS WITH IN THE DIFFERENTIAL ZONE. THIS IS TREATED AS MAIN-1 PROT FOR REACTOR. IT CAN BE OF HIGH IMPEDENCE TYPE OR OF A SENSITIVE CURRENT STABILISED TYPE. HIGH IMPEDENCE DIFFERENTIAL PROTECTION RELAYS REQUIRE AN EQUAL CT TURNS RATIO ON THE PHASE AND NEUTRAL SIDE. SENSITIVITY IS 5% OF NOMINAL REACTOR CT CURRENT. BACK-UP PROTECTION A VARIETY OF RELAYS ARE AVAILABLE. A. OVER CURRENT & EARTH FAULT PROTECTION. ( 50, 50N, 51, 51N, 67, 67N - ANY COMBINATION OF THESE) B. UNDER IMPEDENCE / DISTANCE ( Z<)(21R). C. NEUTRAL DISPLACEMENT PROTECTION (Un>). RESTRICTED EARTH FAULT PROTECTION IF, FOR SOME REASON, A SENSITIVE DIFFERENTIAL PROTECTION NOT CHOOSEN A RESTRICTED EARTH FAULT PROTECTION CAN BE UTILISED.

SHUNT REACTOR (BUS & LINE)


(4CTS METHOD)
BUS-1
IL INTER LOCK FACILITY: WHEN 1-89R CLOSES ONLY PERMIT TO CLOSE 1-89L AND 1-89L OPENS ONLY PERMIT TO OPEN 1-89R.

BUS-2 3-89

1-89

1-52CB 1-CT 1-89A 1-89R

3-52CB

3P1

P2

P2

3-CT 3 P1 3-89A

LINE SHUNT REACTOR NEUTRAL REACTOR

P1 3

P2

1-RCT

.
IL

2-ACT

2-BCT
P1

P2

2-89A

P1

P2

2-52CB

2-89B 3-89R

U U U

1-89L

U U U

LINE 1

U U U U

BUS SHUNT REACTOR

SHUNT REACTOR (BUS & LINE)


(5CTS METHOD)
BUS-1
IL INTER LOCK FACILITY: WHEN 1-89R CLOSES ONLY PERMIT TO CLOSE 1-89L AND 1-89L OPENS ONLY PERMIT TO OPEN 1-89R.

BUS-2 3-89

1-89

1-52CB 1-CT 1-89A

3-52CB

3P1

P2

P2 P1

3 3-CT
3-89A

1-89R 1-RCT P1 3
P2 IL

.
2-89A 2-52CB 1-89L

2-CT
P1

P2

LINE SHUNT REACTOR NEUTRAL REACTOR

2-89B
P2

U U U

3-89R
P1

U U U

1-LCT

LINE 1

U U U U

3P1

P2

3 3-RCT

BUS SHUNT REACTOR

SHUNT REACTOR PROTECTION


PROTECTIONS
MAIN-1 PROTECTION, MAIN-2 PROTECTION, METERING, BUSBAR & BUSBAR CHECKUP PROTECTION

3,4,6S - CT METHOD LINE PROTECTION


IN THIS REACTOR CT CURRENT IS OPPOSES THE MAIN&TIE CT CURRENT. VECTOR SUM OF CTs i.e. MAIN, TIE & REACTOR IS LINE CURRENT.

5,6T1,6T2 - CT METHOD
AS USUAL IN 5CT METHOD, 6CT(T1) METHOD, 6CT(T2) METHOD

3CT METHOD, 4CT METHOD, 6CT(S) METHOD

LINE SHUNT REACTOR PROTECTION


MAIN PROTECTION ( 87 R ) (DIFFERENTIAL PROTECTION)
HV BUSHING CT CORE-1 & NEUTRAL BUSHING CT CORE-3 OF LINE SHUNT REACTOR IS CONNECTED TO 3-PH HIGH IMPEDENCE DIFFERENTIAL RELAY. HV BUSHING CT CORE-3 & SELECTED CVT IS CONNECTED TO SINGLE STEP REACTOR IMPEDENCE RELAY. HV BUSHING CT CORE-2 & NEUTRAL REACTOR EARTH BUSHING CT CORE1.2 OF LINE SHUNT REACTOR IS CONNECTED TO 1-PH HIGH IMPEDENCE DIFFERENTIAL RELAY(REF). NEUTRAL BUSHING CT CORE-1 IS CONNECTED TO REACTOR METERING HV BUSHING CT CORE-1 & NEUTRAL BUSHING CT CORE-3 OF LINE SHUNT REACTOR IS CONNECTED TO 3-PH HIGH IMPEDENCE DIFFERENTIAL RELAY. 1-RCT CORE-5 & SELECTED CVT IS CONNECTED TO SINGLE STEP REACTOR IMPEDENCE RELAY. HV BUSHING CT CORE-2 & NEUTRAL REACTOR EARTH BUSHING CT CORE-1.2 OF LINE SHUNT REACTOR IS CONNECTED TO 1-PH HIGH IMPEDENCE DIFFERENTIAL RELAY(REF). NEUTRAL BUSHING CT CORE-1 IS CONNECTED TO REACTOR METERING

BACK UP PROTECTION(21R) ( SINGLE STEP REACTOR IMPEDENCE PROTECTION ) RESTRICTED EARTH FAULT PROTECTION (64 R )

METERING

SHUNT REACTOR PROTECTION


PROTECTIONS
MAIN PROTECTION (87 R) (DIFFERENTIALPROTECTION)

4 CT METHOD
HV BUSHING CT CORE-1 & EARTH BUSHING CT CORE-3 OF BUS SHUNT REACTOR IS CONNECTED TO 3-PH HIGH IMPEDENCE DIFFERENTIAL RELAY. 3-CT CORE-5 & 2-ACT CORE-5 SECONDARIES ARE CONNECTED PARALLEL & SELECTED CVT IS CONNECTED TO SINGLE STEP REACTOR IMPEDENCE RELAY. HV BUSHING CT CORE-2 & EARTH BUSHING CT CORE-2 OF BUS SHUNT REACTOR IS CONNECTED TO 1-PH HIGH IMPEDENCE DIFFERENTIAL RELAY(REF).

5 CT METHOD
HV BUSHING CT CORE-1 & EARTH BUSHING CT CORE-3 OF BUS SHUNT REACTOR IS CONNECTED TO 3-PH HIGH IMPEDENCE DIFFERENTIAL RELAY. 3-RCT CORE-5 & SELECTED CVT IS CONNECTED TO SINGLE STEP REACTOR IMPEDENCE RELAY.

BUS SHUNT REACTOR PROTECTION

BACK UP PROTECTION (21R ) ( SINGLE STEP REACTOR IMPEDENCE PROTECTION )

RISTRICTED EARTH FAULT PROTECTION ( 64 R )

HV BUSHING CT CORE-2 & EARTH BUSHING CT CORE-2 OF BUS SHUNT REACTOR IS CONNECTED TO 1-PH HIGH IMPEDENCE DIFFERENTIAL RELAY(REF).

SPECIAL PROTECTION
LINE SHUNT REACTOR BUS SHUNT REACTOR CVT SELECTION
STUB PROTECTION ___ LINE SHUNT REACTOR: ACCORDING TO ISOLATORS & BREAKERS POSITION BUS-1/ BUS-2/ LINE CVT WILL BE SELECTED. TEED-1: 1-CT, 2-CT, 1-LCT & 1-RCT TEED-2: 1-CT, 2-CT, 1-LCT & 1-RCT TEED-1: 3-CT, 2-CT & 3-RCT TEED-2: 3-CT, 2-CT & 3-RCT BUS SHUNT REACTOR: ACCORDING TO ISOLATORS & BREAKERS POSITION BUS-1/ BUS-2 CVT WILL BE SELECTED.

REACTOR BUSHING CT CONNECTIONS


CORES LINE SHUNT REACTOR
4 CT METHOD
CORE-1 CORE-2 CORE-3*
REACTOR HIGH IMPEDENCE DIFFERENTIAL RELAY RESTRICTED EARTH FAULT PROTECTION REACTOR IMPEDENCE PROTECTION

BUS SHUNT REACTOR


4 CT METHOD
REACTOR HIGH IMPEDENCE DIFFERENTIAL RELAY RESTRICTED EARTH FAULT PROTECTION

5 CT METHOD
REACTOR HIGH IMPEDENCE DIFFERENTIAL RELAY RESTRICTED EARTH FAULT PROTECTION

5 CT METHOD
REACTOR HIGH IMPEDENCE DIFFERENTIAL RELAY RESTRICTED EARTH FAULT PROTECTION

HV (400KV SIDE) BUSHING CTs

SPARE

SPARE

SPARE

NEUTRAL (STAR POINT SIDE) BUSHING CTs


CORE-1 CORE-2 CORE-3
METERING METERING METERING
RESTRICTED EARTH FAULT PROTECTION REACTOR HIGH IMPEDENCE DIFFERENTIAL RELAY

METERING
RESTRICTED EARTH FAULT PROTECTION REACTOR HIGH IMPEDENCE DIFFERENTIAL RELAY

SPARE
REACTOR HIGH IMPEDENCE DIFFERENTIAL RELAY

SPARE
REACTOR HIGH IMPEDENCE DIFFERENTIAL RELAY

NEUTRAL REACTOR (MAIN REACTOR STAR POINT SIDE) BUSHING CTs


CORE-1.1 SPARE SPARE

NEUTRAL REACTOR (EARTH POINT SIDE) BUSHING CTs


CORE-1.2
RESTRICTED EARTH FAULT PROTECTION RESTRICTED EARTH FAULT PROTECTION

*NOTE: NORMALLY CORECORE-3 IS USED FOR REACTOR IMPEDENCE PROTECTION. HERE IN 3 CASES WE ARE NOT UTILISED THE CORECORE-3 FOR REACTOR IMPEDENCE PROTECTION. IN THESE 3 CASES OUTDOOR CTs ARE AVAILABLE. CORECORE-5 OF THESE CTs ARE UTILISING FOR REACTOR IMPEDENCE PROTECTION. SO, FOR REACTOR IMPEDENCE PROTECTION EITHER CORECORE-3 OF HV BUSHING CT OR CORECORE-5 OF EXTERNAL CT MAY BE UTILISED.

LINE SHUNT REACTOR PROTECTION


P1

200/ 1A HV BUSHING (400KV SIDE) CTs

P2

LINESHUNT REACTOR 200/ 1A NEUTRAL BUSHING (STAR PONT SIDE) CTs

P1

200/ 1A

P2

NEUTRAL REACTOR 200/ 1A

P2

. CORE 1.2 .
P1

. . CORE 1.1 .
P2 P1

3 3 3

CORES 3 2 1

3 3 3

. .

(4CTs METHOD)
1-RCT

CORES 3 2 1

CORES 4 3 2

CORECORE-1: 20002000-10001000-500/1 CORECORE-2: 20002000-10001000-500/1 CORECORE-3: 20002000-10001000-500/1 CORECORE-4: 20002000-10001000-500/1 CORECORE-5: 20002000-10001000-500/1

. .

1-89R

3 3 3 3 3

METERING
1-CT 2B2B-CT LINE 1-CT 2B2B-CT LINE 2B2B-CT

LINE

U U U

. . . .

MAIN-2 PROTECTION

MAIN-1 PROTECTION
1-CT

REACTOR DIFFERENTIAL PROTECTION RESTRICTED EARTHFAULT PROTECTION

REACTOR IMPEDENCE PROTECTION REACTOR METERING


SELECTED BUSBUS-1/ BUSBUS-2/ LINE CVT VOLTAGE

U U U

LINE SHUNT REACTOR PROTECTION


P1

200/ 1A HV BUSHING (400KV SIDE) CTs

P2

LINESHUNT REACTOR 200/ 1A NEUTRAL BUSHING (STAR PONT SIDE) CTs

P1

200/ 1A

P2

NEUTRAL REACTOR 200/ 1A

P2

. CORE 1.2 .
P1

. . CORE 1.1 .
P2 P1

3 3 3

CORES 3 2 1

3 3 3

. .

(5CTs METHOD)
1-RCT

CORES 3 2 1

.
P1

CORES 4 3 2

CORECORE-1: 20002000-10001000-500/1 CORECORE-2: 20002000-10001000-500/1 CORECORE-3: 20002000-10001000-500/1 CORECORE-4: 20002000-10001000-500/1 CORECORE-5: 20002000-10001000-500/1

P2 1-LCT CORECORE-1

1-89R

3 3 3 3 3

. .

U U U

TEE DIFFERENTIAL PROTECTION-1


1-CT CORECORE-5 2-CT CORECORE-5 1-CT CORECORE-4

TEE DIFFERENTIAL PROTECTION-2 REACTOR IMPEDENCE PROTECTION

2-CT CORECORE-4 1-LCT CORECORE-2

SELECTED BUSBUS-1/ BUSBUS-2/ LINE CVT VOLTAGE

U U U

REACTOR DIFFERENTIAL PROTECTION

RESTRICTED EARTHFAULT PROTECTION

REACTOR METERING

BUS SHUNT REACTOR PROTECTION


3-89

3-52CB
SELECTED BUSBUS-1/ BUSBUS-2 CVT VOLTAGE P2

BUS BAR PROTECTION

BUS-2

BUSBAR CHECKUP PROT REACTOR DIFFERENTIAL PROTECTION


RESTRICTED EARTHFAULT PROTECTION

(4CTs METHOD)

REACTOR IMPEDENCE PROTECTION


REACTOR METERING
2-52CB

.
2-89B

3 3 3

5 4 3 CORES 3-89A 3-89R

P2

4 3 2 CORES 2A-CT

P1

.
P2

.
P1

NEUTRAL BUSHING CTs 200/ 1A (STAR PONT SIDE)

3 2 1 CORES

P1

P2 3

BUS SHUNT REACTOR 200/ 1A

. UU U

2 1 CORES

HV BUSHING CTs (400KV SIDE)

3 3

3-CT

P1

3 3 3 3 3 3 3 3 3 3 3

REACTOR IMPEDENCE PROTECTION

RESTRICTED EARTHFAULT PROTECTION

SELECTED BUSBUS-1/ BUSBUS-2 CVT VOLTAGE

(5CTs METHOD)
TEED-2 PROT (BAY 1&2) TEED-1 PROT (BAY 1&2)

3-89

REACTOR DIFFERENTIAL PROTECTION

TEED-2 PROT (BAY 2&3) TEED-1 PROT (BAY 2&3)

3-52CB
P2

.
2-52CB P1 5 2-CT 4 3 2 CORES 1
P2

3 3 3
2-89B

3-CT

REACTOR METERING

3-89A 3-89R

P1

. .
P2

NEUTRAL BUSHING CTs 200/ 1A (STAR PONT SIDE)

3 2 1 CORES

P1

P2 3

BUS SHUNT REACTOR 200/ 1A

. UU U

2 1 CORES

P1

3 3 3 3 3

P2

3R-CT

P1

HV BUSHING CTs (400KV SIDE)

BUSBAR CHECKUP PROT

BUS BAR PROTECTION

BUS SHUNT REACTOR PROTECTION BUS-2

3 3

CORES 3 4 5

3 3 3 3 3 3 3 3

1 CORES 2 3 4

3 3 3

CARRIER INTERTRIPPING OF LINE SHUNT REACTOR


LINE SHUNT REACTOR PROTECTION TRIPPINGS WILL BE USED AS DIRECT TRIPPINGS OF LINE IN ADDITION TO OTHER TRIPPINGS. BUS SHUNT REACTOR NEED NOT REQUIRE CARRIER INTER TRIPPING FACILITY.
87R REACTOR DIFFERENTIAL RELAY RADHA 21R REACTOR IMPEDENCE RELAY RAKZB
64R RESTRICTED EARTH FAULT RELAY

ABB NSD 50
DC +VE FROM PANEL

LINE PROTECTION COUPLER PANEL-1

RADHD REACTORS INTERNAL FAULTS GROUP-1/A TRIPPINGS

G4AD V9LC 2 G4AD V9LC 1


DC VE FROM PANEL

87R REACTOR DIFFERENTIAL RELAY RADHA 21R REACTOR IMPEDENCE RELAY RAKZB
64R RESTRICTED EARTH FAULT RELAY

ABB NSD 50
DC +VE FROM PANEL

LINE PROTECTION COUPLER PANEL-2

RADHD REACTORS INTERNAL FAULTS GROUP-2/B TRIPPINGS

G4AD V9LC 2 G4AD V9LC 1


DC VE FROM PANEL

ADDITIONAL AND SPECIAL FUNCTIONS ADOPTED IN ONE AND HALF CIRCUIT BREAKER SCHEME
(EVENT LOGGER & DISTURBANCE RECORDER) PREPARED BY
GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)

400KV SUBSTATION: MAMIDIPALLY


19 MAR 2004 13:00:00 A 13:09:37.090 # 195 A 13:09:37.096 # 188 A 13:09:37.097 # 187 A 13:09:37.100 # 181 A 13:09:37.104 # 162 A 13:09:37.110 # 196 A 13:09:37.110 # 170 A 13:09:37.111 # 161 A 13:09:37.111 # 163 A 13:09:37.111 # 169 A 13:09:37.112 # 168 A 13:09:37.113 # 182 A 13:09:37.126 # 199 A 13:09:37.140 # 185 N 13:09:37.147 # 195 N 13:09:37.148 # 196 N 13:09:37.175 # 187 N 13:09:37.176 # 181 N 13:09:37.176 # 188 N 13:09:37.185 # 182 N 13:09:37.257 # 199 N 13:09:37.279 # 185 19 MAR 2004 14:00:00 N 14:09:48.702 # 163 N 14:09:48.704 # 161 N 14:09:48.720 # 162 N 14:10:00.903 # 169 N 14:10:00.907 # 168 N 14:10:00.907 # 170 19 MAR 2004 15:00:00

EVENT LOGGER EVENTS INFORMATION

400KV SRISAILAM-2 MAIN-2 RAZFE PROT TRIP 400KV SRISAILAM-2 MAIN-1 REL100 PROT STARTY 400KV SRISAILAM-2 MAIN-1 REL100 PROT STARTR 400KV SRISAILAM-2 MAIN-1 REL100 PROT TRIP 400KV SRISAILAM-2 MAIN CB 752 Y-PH OPEN 400KV SRISAILAM-2 MAIN-2 RAZFE CARRIER SEND 400KV SRISAILAM-2 AT/F-2 TIE CB 852 B-PH OPEN 400KV SRISAILAM-2 MAIN CB 752 R-PH OPEN 400KV SRISAILAM-2 MAIN CB 752 B-PH OPEN 400KV SRISAILAM-2 AT/F-2 TIE CB 852 Y-PH OPEN 400KV SRISAILAM-2 AT/F-2 TIE CB 852 R-PH OPEN 400KV SRISAILAM-2 MAIN-1 REL100 CARRIER SEND 400KV SRISAILAM-2 CARRIER PROT CH-2 RECEIVED 400KV SRISAILAM-2 CARRIER PROT CH-1 RECEIVED 400KV SRISAILAM-2 MAIN-2 RAZFE PROT TRIP RESET 400KV SRISAILAM-2 MAIN-2 RAZFE CARRIER SEND RESET 400KV SRISAILAM-2 MAIN-1 REL100 START R RESET 400KV SRISAILAM-2 MAIN-1 REL100 PROT TRIP RESET 400KV SRISAILAM-2 MAIN-1 REL100 START Y RESET 400KV SRISAILAM-2 MAIN-1 REL100 CARRIER SEND RESET 400KV SRISAILAM-2 CARRIER PROT CH-2 RECEIVED RESET 400KV SRISAILAM-2 CARRIER PROT CH-1 RECEIVED RESET 400KV SRISAILAM-2 MAIN CB 752 B-PH CLOSE 400KV SRISAILAM-2 MAIN CB 752 R-PH CLOSE 400KV SRISAILAM-2 MAIN CB 752 Y-PH CLOSE 400KV SRISAILAM-2 AT/F-2 TIE CB 852 Y-PH CLOSE 400KV SRISAILAM-2 AT/F-2 TIE CB 852 R-PH CLOSE 400KV SRISAILAM-2 AT/F-2 TIE CB 852 B-PH CLOSE

DISTURBANCE RECORDER

R PH VOLTAGE Y PH VOLTAGE B PH VOLTAGE OPEN DELTA VOLTAGE R PH CURRENT Y PH CURRENT B PH CURRENT STAR/NEUTRAL CURRENT
MAIN CB R PH OPEN MAIN CB Y PH OPEN MAIN CB B PH OPEN TIE CB R PH OPEN TIE CB Y PH OPEN TIE CB B PH OPEN MAIN/TIE CB LBB OPTD DIRECT TRIP CH-1/2 OPTD BUSBAR PROT OPTD MAIN-1 PROT OPTD MAIN-2 PROT OPTD OVER VOLTAGE STAGE-1/2 OPTD STUB PROT-1/2 OPTD MAIN-1 PROT CARRIER RECEIVE MAIN-2 PROT CARRIER RECEIVE DF/DT OPTD EVENT NO NAME OF FEEDER DATE & TIME

ISOLATOR INTERLOCKS

S.NO BAY - 1 1 2 3 4 5 6 BAY - 2 7 8 9 10 BAY - 3 11 12 13 14 15 16

ISOLATOR OPEN/CLOSE

EQUIPMENT-1

EQUIPMENT-2

EQUIPMENT-3

EQUIPMENT-4

INTERLOCKS REQUIRED FOR CONCERNED ISOLATOR / EARTH SWITCH OPEN OR CLOSE BB189 E 189 A 189 AE 189 A 189 LE 189 L 289 BE 289 B 289 BE 289 B BB289 E 389 A 389 AE 389 A LV89 E2 389 T O O O O O O O O O O O O O O O O 189 AE 189 189 E 189 152 CB UV RELAY 289 AE 289 A 289 AE 289 A 389 AE 389 389 E 389 389 TE LV89 T O O O O O A O O O O O O O O O O 189 E -152 CB -252 CB -252 CB -252 CB -389 E -352 CB -252 CB -O O O O O O O O 152 CB ---------352 CB ---352 CB -O O O -

1 - 89 1 89 E 1 89 A 1 89 AE 1 89 L 1 89 LE 2 89 A 2 89 AE 2 89 B 2 89 BE 3 89 3 89 E 3 89 A 3 89 AE 3 89 T 3 89 TE

ISO ES ISO ES ISO ES ISO ES ISO ES ISO ES ISO ES ISO ES

NOTE: All Earth Switches in the Bay are towards Circuit Breaker side only. The Line and Transformer Earth Switches are towards Line & Transformer. O: OPEN C: CLOSE A: ACTED

BB189E : BUSBAR-1 EARTH SWITCH . BB289E : BUSBAR-2EARTH SWITCH . UV RELAY: UNDER VOLTAGE RELAY.

LIST OF PANELS ADOPTED IN ONE AND HALF CIRCUIT BREAKER SCHEME


PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)

LIST OF PANELS
1. CONTROL PANEL FOR LINE & AT/F (ICT) CP 2. 400KV LINE CB RELAY PANEL RLA 3. 400KV LINE PROTECTION PANEL RLB 4. 400KV TIE CB RELAY PANEL RTB 5. 400KV AT/F(ICT) CB RELAY PANEL RTRA 6. 315MVA AT/F(ICT) PROTECTION PANEL FOR HV (400KV SIDE) RTRB 7. 315MVA AT/F(ICT) PROTECTION PANEL FOR LV RTRC 8. 220KV AT/F(ICT) CB RELAY PANEL RTRD 9. CONTROL PANEL FOR AT/F LV - KT

CONTROL PANEL CP/KT


1. IT IS HAVING PANEL METERS i.e AMMETER, VOLTMETER, MW METER, MVAR METER.(NOW MULTIFUNCTION PANEL METERS ARE AVAILABLE). 2. ANNOUNCIATION FACIA FOR PROBLEMS, ALARMS ENCOUNTERED.(NOW MICROPROCESSOR BASED ANNOUNCIATION FACIA IS AVAILABLE). 3. INDICATING LAMPS FOR RELAYS HEATHINESS & INTERLOCKS. 4. TNC SWITCHES FOR CIRCUIT BREAKER/ ISOLATOR FOR MANUAL TRIP/CLOSE OPERATION. 5. PANEL INDICATING LAMPS FOR CIRCUIT BREAKER/ ISOLATOR POSITION i.e CLOSE/OPEN. 6. SYMAPHORES FOR EARTH SWITCHES POSITION i.e CLOSE/OPEN. 7. SYNCHOROSCOPE SOCKETS ONE No FOR EACH CIRCUIT BREAKER UTILISED AT THE TIME OF CLOSING. 8. ENERGY METERS.

400KV LINE CB RELAY PANEL-RLA


1. ANNOUNCIATION RELAYS. 2. AUTO RECLOUSER WITH CHECK SYNCHRONISING RELAY (79 A/R + 25). 3. MASTER TRIP RELAY GR-A( 86-A WITH 3 Nos 1PH TRIP RELAYS, 1No 3PH TRIP RELAYS, 1No PUSH BUTTON FOR RESET & HEALTHY SUPERVISION). 4. MASTER TRIP RELAY GR-B( 86-B WITH 3 Nos 1PH TRIP RELAYS, 1No 3PH TRIP RELAYS, 1No PUSH BUTTON FOR RESET & HEALTHY SUPERVISION). 5. DC SOURCE-1 (GR-A) HEALTHINESS. 6. DC SOURCE-2 (GR-B) HEALTHINESS. 7. TRIP CIRCUIT-1 SUPERVISION RELAYS FOR MAIN CB (152CB) FOR 3 PHASES. 8. TRIP CIRCUIT-2 SUPERVISION RELAYS FOR MAIN CB (152CB) FOR 3 PHASES. 9. DIRECT TRIP CHANNEL 1/ 2 RECEIVED RELAYS & FLAG RELAYS. 10. LOCAL BREAKER BACKUP/ BREAKER FAILURE RELAY ( 50 LBB) FOR MAIN CB(152CB). 11. UNDER VOLTAGE RELAY FOR LINE EARTH SWITCH INTERLOCK. 12. FLAG RELAYS FOR CIRCUIT BREAKER TROUBLES.

400KV LINE PROTECTION PANEL-RLB


1. 2.
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15.
16.

FUNCTIONS AVAILABLE IN MAIN-1/ MAIN-2(REL521/ REL 316)

MAIN-1 PROTECTION FOR LINE( 29 L1, WITH NECESSARY AUX RELAYS & DC GR-A HEALTHINESS).(TEED(TEED-1 PROTECTION RELAY IN CASE 5CT METHOD ) MAIN-2 PROTECTION FOR LINE( 29 L2, WITH NECESSARY AUX RELAYS & DC GR-B HEALTHINESS).(TEED(TEED-2 PROTECTION RELAY IN CASE 5CT METHOD)
4 TO 6 SETTING IMPEDENCE ZONES WITH 4 TO 6 SETTING GROUPS (21 + 21N). DIR / INST / TIME OVERCURRENT & EARTH FAULT FUNCTION( 50 + 51 + 67 + 50N + 51N + 67N). EIGHT COMMUNICATION SCHEMES. SWITCH ON TO FAULT PROTECTION(21 SOTF). PHASE SELECTION(R,Y,B). POWER SWING BLOCKING(PSB)(68 + 68T). FUSE FAILURE SUPERVISION(PT FFR). AUTO RECLOSER RELAY WITH SYNCHROCHECK AND VOLTAGE CHECK(79 A/R + 25 +86). WEEK END INFEED LOGIC(27 WI). SYSTEM SUPERVISION. STUB PROTECTION(STUB). OVER VOLTAGE/ UNDER VOLTAGE FUNCTION(27+ 59). LBB/BFR FUNCTION(50 BF). DISTANCE TO FAULT LOCATOR(21 FL).(SHOWS IN 1. %, 2. KM & 3. R+JX ) 16 PROGRAMABLE SIGNALLING RELAYS WITH LEDs.
RECORDABLE 10Nos LATEST DISTRUBANCES WITH BASIC EVALUATION DISTURBANCE RECORDER.

17. 18. 19. 20. 21. 22. 23.

EVENT RECORDER RELATED TO RELAY EVENTS. PRE-FAULT, FAULT & POST-FAULT VALUES OF ANALOG POINTS WITH IMPEDENCE DETAILS. USER CAN BE CONFIGUARED PROGRAMABLE LOGIC FUNCTIONS. TELE / CARRIER INTER TRIPPING SCHEMES(85 +21)(PUTT, POTT). TRIP CIRCUIT MONITORING(74 TC). METERING FUNCTION (INSTANTANEOUS VALUES DISPLAY FUNCTION). 4 QUADRANT ENERGY METER FUNCTION (KWH,KVAH,KVARH)(KYZ PULSE OUTPUT).

400KV TIE CB RELAY PANEL-RTB


1. ANNOUNCIATION RELAYS. 2. AUTO RECLOUSER WITH CHECK SYNCHRONISING RELAY (79 A/R + 25). 3. MASTER TRIP RELAY GR-A( 86-A WITH 3 Nos 1PH TRIP RELAYS, 1No 3PH TRIP RELAYS, 1No PUSH BUTTON FOR RESET & HEALTHY SUPERVISION). 4. MASTER TRIP RELAY GR-B( 86-B WITH 3 Nos 1PH TRIP RELAYS, 1No 3PH TRIP RELAYS, 1No PUSH BUTTON FOR RESET & HEALTHY SUPERVISION). 5. DC SOURCE-1 (GR-A) HEALTHINESS. 6. DC SOURCE-2 (GR-B) HEALTHINESS. 7. TRIP CIRCUIT-1 SUPERVISION RELAYS FOR TIE CB (252CB) FOR 3 PHASES. 8. TRIP CIRCUIT-2 SUPERVISION RELAYS FOR TIE CB (252CB) FOR 3 PHASES. 9. LOCAL BREAKER BACKUP/ BREAKER FAILURE RELAY ( 50 LBB) FOR TIE CB(252CB). 10. FLAG RELAYS FOR CIRCUIT BREAKER TROUBLES.

315MVA, 400KV/220KV/33KV AT/F(ICT) HV CB RELAY PANEL (400KV SIDE) - RTRA


1. ANNOUNCIATION RELAYS. 2. MASTER TRIP RELAY GR-A( 86-A WITH 1No 3PH TRIP RELAYS, 1No PUSH BUTTON FOR RESET & HEALTHY SUPERVISION). 3. MASTER TRIP RELAY GR-B( 86-B WITH 1No 3PH TRIP RELAYS, 1No PUSH BUTTON FOR RESET & HEALTHY SUPERVISION). 5. DC SOURCE-1 (GR-A) HEALTHINESS. 6. DC SOURCE-2 (GR-B) HEALTHINESS. 7. TRIP CIRCUIT-1 SUPERVISION RELAYS FOR MAIN CB (352CB) FOR 3 PHASES. 8. TRIP CIRCUIT-2 SUPERVISION RELAYS FOR MAIN CB (352CB) FOR 3 PHASES. 9. LOCAL BREAKER BACKUP/ BREAKER FAILURE RELAY ( 50 LBB) FOR MAIN CB(352CB). 10. VOLTAGE SELECTION RELAYS FOR METERING. 11. FLAG RELAYS FOR CIRCUIT BREAKER TROUBLES.

315MVA, 400KV/220KV/33KV AT/F(ICT) HV PROTECTION PANEL (400KV SIDE) - RTRB


1. 2. 3. 4. 5. MAIN-1 PROTECTION/ DIFFERENTIAL RELAY (87T). HV OVER FLUX RELAY (99T HV). OVER LOAD RELAY/ HIGH CURRENT RELAY (51 O/L). VOLTAGE SELECTION RELAYS FOR PROTECTION. FLAG RELAYS FOR TRANSFORMER INTERNAL FAULTS & PROBLEMS FOR ALARAM & TRIPS. 6. DC SUPERVISION FOR RELAYS. 7. DIRECTIONAL OVER CURRENT & EARTH FAULT RELAYS FOR HV (MAIN-2 PROTECTION)(67 R,Y,B, 67N). 8. FUSE FAILURE RELAY(PT FFR).

315MVA, 400KV/220KV/33KV AT/F(ICT) LV PROTECTION PANEL (220KV SIDE) - RTRC


1. LV OVER FLUX RELAY (99T LV). 2. RESTRICTED EARTH FAULT RELAY, SINGLE PHASE HIGH IMPEDENECE RELAY (64T). 3. VOLTAGE SELECTION RELAYS FOR PROTECTION. 4. FLAG RELAYS FOR TRANSFORMER INTERNAL FAULTS & PROBLEMS FOR ALARAM & TRIPS. 5. DC SUPERVISION FOR RELAYS. 6. DIRECTIONAL OVER CURRENT & EARTH FAULT RELAYS FOR LV (MAIN-2 PROTECTION)(67 R,Y,B, 67N). 7. FUSE FAILURE RELAY(PT FFR).

315MVA, 400KV/220KV/33KV AT/F(ICT) LV CB RELAY PANEL (220KV SIDE) - RTRD


1. ANNOUNCIATION RELAYS. 2. MASTER TRIP RELAY GR-A( 86-A WITH 1No 3PH TRIP RELAYS, 1No PUSH BUTTON FOR RESET & HEALTHY SUPERVISION). 3. MASTER TRIP RELAY GR-B( 86-B WITH 1No 3PH TRIP RELAYS, 1No PUSH BUTTON FOR RESET & HEALTHY SUPERVISION). 4. DC SOURCE-1 (GR-A) HEALTHINESS. 5. DC SOURCE-2 (GR-B) HEALTHINESS. 6. TRIP CIRCUIT-1 SUPERVISION RELAYS FOR LV CB FOR 3 PHASES. 7. TRIP CIRCUIT-2 SUPERVISION RELAYS FOR LV CB FOR 3 PHASES. 8. LOCAL BREAKER BACKUP/ BREAKER FAILURE RELAY ( 50 LBB) FOR LV CB. 9. NEUTRAL DISPLACEMENT RELAY. 10. VOLTAGE SELECTION RELAYS FOR METERING. 11. FLAG RELAYS FOR CIRCUIT BREAKER TROUBLES.

OTHER INFORMATION REGARDING RELAYS AND TESTING EQUIPMENT


PREPARED BY GOPALA KRISHNA PALEPU ADE/MRT(PROTECTION)

ABB RELAYS
ABB Network Partner AG

ABB Network Partner AG

REL 521

ABB Network Partner AG

REL 316*4

10

11

12

13

14

15

16

E E

C E

ABB Relays
ABB Network Partner AG

REL 512

c
E

ALSTOM RELAYS

P443

P444

P442

E-PAC

P437

GE MULTILIN RELAYS

SIEMENS RELAYS

SEL RELAYS
ENABLED

IA =250.10 A IB =250.10 A IC =250.10 A VAB =400.0 KV VBC =400.0 KV VCA =400.0 KV


ESC ENT

TRIP

TARGET RESET

SPT ENABLED COMM ENABLED ALT SETTINGS

MC ENABLED RECLOSE ENABLED CB CLOSED

SEL- 421
PROTECTION AUTOMATION CONTROL

INST TIME COMM SOTF ZONE 1 ZONE 2 ZONE 3 ZONE 4

PH - A PH - B PH - C GND
50 51 79 RESET 79 LOCKOUT

RELAY TEST

CB OPEN

SEL

INST TIME COMM SOTF TRIP EN A B C

2ENABLED 3
TRIP

TARGET RESET

SEL- 321- 5 - 2
PROTECTION AUTOMATION CONTROL

ZONE G Q 51 50 O/C

FAULT TYPE

TARGET TARGET FAULT SET RESET NO / YES / CANCEL SELECT

METER STATUS OTHER GROUP EXIT

SEL

VA TECH REYROLLE RELAYS

NXT PHASE RELAYS

DISTANCE RELAYS

CHARACTERESTICS
1. MHO CIRCULAR CHARACTERSTICS. 2. QUADRILATERAL CHARACTERSTICS. 3. LENS/OPTICAL CHARACTERSTICS. 4. TOMATO CHARACTRESTICS. 5. ABB REL521/316 CHARACTERESTICS.

5 3 4

RELAY MODELS OF LINE (DISTANCE) & TRANSFORMER( M & B ) OF DIFFERENT MANUFACTURERS


MANUFACTURERS ABB ALSTOM SIEMENS ( SIPROTEC ) SEL GE MULTILIN EASUN REYROLL NXT PHASE REYROLL TRANSMISSION LINE PROTECTION MAIN-1 REL 521
MICOM P443/P444/P442

T/F PROTECTION DIFFERENTIAL RET 521 RET 316 MICOM P633 KBCH/ MBCH 7UT 612/ 3 7UT 512/ 3 SEL 387 DTP 32DH SR 7465 --T-PRO DUOBIAS M DIR O/L,E/F REL 505 RAPDK MICOM P141 MICOM P127
7SJ 62/3/4/5 7SJ 52/3/4/5

CURVES
QUAD

MAIN-2 REL 316 REL 512


MICOM P437 E-PAC 3000, OPTIMHO

CURVES
QUAD/ MHO QUAD/ MHO QUAD/ MHO QUAD/ MHO QUAD/ MHO MHO

QUAD/ MHO QUAD/ MHO QUAD/ MHO QUAD/ MHO MHO QUAD/ MHO QUAD/ MHO

SIPROTEC 7SA63 SEL 421 ALPS-L/D THR 4 PE 24 L-PRO OHMEGA 402

SIPROTEC 7SA522 SEL 321 SEL 311C LPS-L/D DLP-L/D, D-6O THR 4 PE 16 THR 3 PE 18 L-PRO OHMEGA 311/308

SEL 351 DMS SR 750/60 --F-PRO ARGUS

LENS/ TOMAT0 QUAD/ MHO

RELAY TESTING EQUIPMENTS


1. PROGRAMA_GE (MODEL: FREEJA-300) 3. OMICRON (MODEL: CMC 256-6) 2. MANTA TEST SYSTEMS (MODEL: MTS 4000) 4. DOBLE ( MODEL: F 6150)

RELAY TESTING EQUIPMENTS


1. MEEGER_AVO (MODEL: MPRT 8430) 3. KOCOS (MODEL: ARTES 440 II) 2. RES (MODEL: APTS 3) 4. EURO SMC ( MODEL: TRES)

400KV SUBSTATIONS IN APTRANSCO


S.No
1. 2. 3. 4.

400KV SUBSTATION
MAMIDIPALLY (HYDERABAD) NURNOOR (KURNOOL) KALAPAKA (VISHAKHAPATNAM) VEMAGIRI (RAJHAMUNDRY)

CAPACITY
2 X 315 MVA 2 X 315 MVA 2 X 315 MVA 2 X 315 MVA

FEEDERS
1. SRISAILAM 1&2 2. KHAMMAM 1&2 3. GHANAPUR (PGCIL) 1. SRISAILAM 2. GHANAPUR (PGCIL) 3. GOOTY (PGCIL) 1. SIMHADRI 1,2,3&4 (NTPC) 2. GAJUWAKA 1&2 (PGCIL) 3. KHAMMAM 1&2 (PGCIL) 4. VEMAGIRI 1&2 1. KALAPAKA 1&2 2. GAJUWAKA 1&2 (PGCIL) 3. NUNNA 1,2,3&4 (PGCIL) 4. GVK STAGESTAGE-2 1&2 (IPP) 5. GOWTHAMI 1&2 (IPP) 6. KONASEEMA 1&2 (IPP) 7. GMR VASAVI 1&2 (IPP) 1. TALLAPALLY 2. RAICHUR 1. CHENNAI RED HILLS 2. KADAPA

5. 6. 7. 8. 9. 10. 11.

KOTTHAKOTA* (MB NAGAR) CHITTOR* NELLORE* DICHPALLY** (NIZAMABAD) NARASARAOPET** (GUNTUR) GAJWEL** (MEDAK) MALKARAM** (SEC BAD)

1 X 315 MVA 1 X 315 MVA 2 X 315 MVA 1 X 315 MVA

1. RAMAGUNDAM

*THESE SUBSTATIONS WORKS UNDER PROGRESS * *THESE SUBSTATIONS ARE PROPOSED

400KV SUBSTATIONS OF PGCIL IN AP


S.No
1. 2. 3. 4. 5. 6. 7. 8. 9.

400KV SUBSTATION
GHANAPUR (HYDERABAD) GAJUWAKA (VISHAKHAPATNAM) NUNNA ( VIJAYAWADA) TALLAPALLY (NAGARJUNA SAGAR) BUDIDAMPADU (KHAMMAM) GOOTY CHINAKAMPALLY (KADAPA) NELLORE PARAKAL* (WARANGAL)

CAPACITY
3 X 315 MVA 1 X 315 MVA 1 X 315 MVA 3 X 315 MVA 1 X 315 MVA 1 X 315 MVA 1 X 315 MVA ----

FEEDERS
1. RAMAGUNDAM 1,2,3&4 2. NAGARJUNA SAGAR 3. MAMIDIPALLY 4. KURNOOL 1. NUNNA 2. KALAPAKA 1&2 3. VEMAGIRI 1& 2 1. GAJUWAKA 2. VEMAGIRI 1,2,3&4 3. KHAMMAM 4. SRISAILAM 1&2 5. NELLORE 1&2 1. RAMAGUNDAM 1&2 2. GHANAPUR 3. RAICHUR TPS(MBNGR) 4. GOOTY 5. CHINAKAMPALLY 1&2 1. RAMAGUNDAM 2. NUNNA 3. KALAPAKA 1&2 4. MAMIDIPALLY 1&2 1. NAGARJUNASAGAR 2. SOMANAHELLY 3. KURNOOL 4. NEELAMANGALA 1. NAGARJUNA SAGAR 1&2 2. SOMANAHALLY 3. MADRAS (CHITTOR) 4. KOLAR 1. NUNNA 1&2 2. MADRAS 1&2

THESE SUBSTATIONS ARE PROPOSED

400KV NETWORK IN AP
GAJUWAKA SIMHADRI RAMAGUNDAM KALAPAKA DICHPALLY TALLAPALLY GAJWEL WARANGAL IPP3 VEMAGIRI IPP4
MALKARAM

IPP1

IPP2

NUNNA

YEDDUMAILARAM

MBNGR

GHANAPUR

CHINAKAMPALLY

KURNOOL

KHAMMAM NR PET

GOOTY
BANGALORE

CHITTOR

NELLORE SRISAILAM CHENNAI BANGALORE MAMIDIPALLY

RAICHUR

CHENNAI

KOLAR

DISPLAY

Вам также может понравиться