Creating LOE Tasks in Microsoft Project | Ten Six Consulting

Ten Six Consulting

Creating LOE Tasks in Microsoft Project


05/16/13

Search the site

Creating LOE Tasks in Microsoft Project


by TheP6ProThis article looks at a lesser-known and tricky to find feature of Microsoft Project that allows you to create a Level of Effort task. Level of Effort (LOE) tasks are often required in a critical path network to represent ongoing work that doesnt typically represent a specific deliverable. For example, you may wish to plan the hours for a project manager over the life-cycle of a project. You could simply create a Management task that spans the entire duration of the project by setting its duration to that of the project. However, in all likelihood this duration will change during the execution of the project, requiring you to constantly change the duration of the management activity. A better solution would be to create a task whos duration is dependent on the start and finish dates of other activities. This is commonly referred to as a Level of Effort or Hammock task.

An LOE tasks can be created in Microsoft Project by using the Paste Link feature to link the start and finish dates of tasks over which the LOE task is to be stretched. With these dates linked, the LOE tasks duration will adjust if the linked dates change.

Example Heres how to setup an LOE task in Microsoft Project. In this example you can see a simple schedule that requires a Management task that spans the critical path of the project. Currently the management task is a one day task with a Project Manager assigned at 100% (8 hours). 1. Right-click in the Start date cell of task A 2. Select Copy Cell

3. Right-click on the Start date cell for the Management task and select Paste Special 4. In the Paste Special dialog, click on the Paste Link radio button.

www.tensixconsulting.com/2013/05/creating-loe-tasks-in-microsoft-project/

1/4

19/08/13

Creating LOE Tasks in Microsoft Project | Ten Six Consulting

5. Click OK 6. Now right-click in the Finish date cell for task E 7. Select Copy Cell 8. Right-click in the Management tasks Finish date field 9. Select Paste Special | Paste Link as previously described. Note how the Management task is now spanning all the tasks between the two linked dates. This is now functioning as an LOE. Also note how Microsoft Project has recalculated the hour for the Project Manager from 8 to 400 hours over 50 days duration.

Important Note in order for this to work you should not have any constraint dates defined for the LOE task. The Task Type should also be Fixed Units and Effort Driven should not be checked. Use the Task Information dialog to verify these settings. From now on, any changes to the linked tasks in the network will change the duration of the LOE task without the need to maintain it manually. This will help in predicting changes in the hours/cost values for the assigned resources in Microsoft Project. 2013-05-20: Weve recieved some great feedback on this article and have added some useful information and ideas about using this feature in a follow-on blog: More About Level of Effort Tasks in Microsoft Project.

Posted in: Microsoft Project Tags: Hammock, Level Of Effort, Microsoft Project Deltek Insight 13 Earned Value Management Haiku
Join our mailing list. JOIN

CONTACT US
(703) 910-2600
Name Email C o m m e n t

SUBMIT

www.tensixconsulting.com/2013/05/creating-loe-tasks-in-microsoft-project/

2/4

19/08/13

Creating LOE Tasks in Microsoft Project | Ten Six Consulting

Categories
Deltek Cobra Earned Value Mgmt Microsoft Project News Primavera P6 Project Management Training

Archives
[+] 2013 [+] 2012 [+] 2011 Consulting Services Project Management Services Project Management Office Implementation Assessments and Health Checks Project Governance Project Management Tool Selection Project Manager Leadership Development Scheduling Services Project Management Staff Augmentation Earned Value Management Services EVMS RFP Support EVMS Assessments Earned Value Management Tool Selection EVMS System Description and Process Development Integrated Baseline Review (IBR) Preparation and Conduct Integrated Master Schedule (IMS) Health Check Earned Value Data Analysis and Reporting WBS Guidelines for Government Acquisition Programs EVMS Staff Augmentation Portfolio Management Services IT Portfolio Management Corporate Governance Portfolio Management Product Portfolio Management Public Sector Portfolio Management New Product Development Portfolio Management Software Services Primavera Implementation Consulting Primavera P6 Application Consulting Primavera P6 Knowledge Transfer, Mentoring and Coaching Primavera P6 Technical Consulting Primavera P6 Integration Primavera P6 BI Publisher Services Primavera P6 Staff Augmentation Deltek Cobra Implementation Consulting Deltek Cobra Application Consulting Deltek Cobra Knowledge Transfer, Coaching and Mentoring Deltek Cobra Integration Deltek Cobra Staff Augmentation Microsoft Project Implementation Services Building an Integrated Master Schedule (IMS) Integrating Microsoft Project with Deltek Cobra Migrating From Microsoft Project To Oracle Primavera P6 Microsoft Project to Primavera P6 Conversion Service Deltek GCS and Cognos Impromptu Services Training Earned Value Management Training EVMS Executive Overview Training EVMS Training EVMS On-Line Training (with live Instructor) EVMS Variance Analysis Training Integrated Baseline Review (IBR) Training Deltek Training Deltek Cobra Fundamentals Deltek Cobra Fundamentals (On-line) Deltek Cobra Administrator Deltek Cobra Report Developer
www.tensixconsulting.com/2013/05/creating-loe-tasks-in-microsoft-project/ 3/4

19/08/13

Creating LOE Tasks in Microsoft Project | Ten Six Consulting

Deltek Cobra Integration Workshop Deltek MPM Training Deltek wInsight Fundamentals Deltek wInsight Administrator Using Cognos Impromptu With Deltek GCS Premier Fundamentals Primavera P6 Training Online Video Training Primavera P6 Professional R8.3 Primavera P6 Professional R8.x Fundamentals Primavera P6 Professional Fundamentals for E&C Primavera P6 EPPM R8.x Fundamentals Primavera P6 EPPM Administrator Whats New in Primavera P6 R8.2 Workshop BI Publisher for Primavera P6 BI Publisher for Primavera Contract Management Microsoft Project Fundamentals Open Training Class Dates Ten Six Training Policies Blog Clients About Ten Six Ten Six Movie Partners Newsletter Archive 2012 Archive 2011 Archive Training at Virginia Beach Careers Job Openings Ten Six Gives Back Legal Notice Contact Us 2011-2013 Ten Six Consulting, LLC | (703) 910-2600

www.tensixconsulting.com/2013/05/creating-loe-tasks-in-microsoft-project/

4/4

Вам также может понравиться