construction cost breakdown. Once final approval is given for the AE Review and Cost Review, and all required documents have been submitted and approved, D3G will incorporate any necessary revisions within the draft report and issue the final AEC Review report to the Lender. The table below demonstrates the typical AEC Review timeline.
Start AE PLAN REVIEW Initial Submission of 80% (or better) plans and specs. Completeness Review issued. Initial AE Plan Review issued by D3G. Revised plans and specs submitted. Revised AE Plan Review issued by D3G. Kick-off Call COST ESTIMATE
Finish
Final Approval of plans and specs; requires a final fullsized set of plans and specs delivered to D3G. Lender will also request a number of sets to include with application.
Initial construction cost breakdown submitted. Initial construction cost breakdown Review submitted. Revised construction cost breakdown submitted. Comprehensive Cost Review comments issued by D3G. Revised construction cost breakdown submitted. Revised Comprehensive Cost Review comments issued by D3G. Final Approval of the construction cost breakdown; requires distribution of the original document to Owner, GC and D3G for signatures before submitting to Lender.
DOCUMENT REVIEW/REPORTING All submittal documents identified on D3G checklist, and required per the HUD MAP Guidelines, are sent to D3G for review and inclusion in the report. Checklists are updated periodically and issued to the Lender and project team, and will include dates of receipt and review comments. Documents are submitted as they become available, reviewed and commented on (if necessary); all necessary documents must be submitted to issue the AEC Report. Final Submittal Documents received & checklist completed. Draft Report Issued. Final Report Issued.
The AEC Review process is similar for both HUD MAP and HUD LEAN programs, while LIHTC projects will be reviewed pursuant to applicable simplified and accelerated processing guidelines. D3G will identify the particular needs associated with each individual project during the kick-off call; however, the AEC Review is always a team effort and will rely on communication with the project team to achieve final approval for each project submitted. For HUD projects, D3G has prepared an Instruction Manual, which details each process per the HUD MAP Guidelines and includes copies of necessary forms and documents. For a copy of this manual, please contact Tiffany Kelly at t.kelly@d3g.biz.