Академический Документы
Профессиональный Документы
Культура Документы
Table of Contents
1.0 Introduction 2.0 Human Resources 2.1 Acquire final Team 2.2 Develop Project Team 2.3 Resolve issues and problems 3.0 Perform Quality Assurance 4.0 Communication 5.0 Change Request
1.0 Introduction
The purpose of the project execution plan prepared by ABC Limited for the proper and efficient execution of the various hospital projects is to help complete the proposed works to meet the projects objective of timeliness, cost effectiveness and quality. Our focus therefore, will be to manage people, processes and resources through; 1. Following processes and procedures, 2. Performing quality assurance, 3. Communicating effectively with stakeholders including holding progress meetings, and 4. Managing change requests. During this process the Project Manager and his team will constantly refer to the project management plan which will be the road map of the project.
One of the cardinal values of ABC is being proactive. Therefore, management will operate an open-door policy that will allow individual team members to have easy access to voice out their concerns. Attempts will be made to deal with these individual concerns to their satisfaction by an Industrial Relations Officer of ABC. However, should this fail to work and the concern grow to become a conflict/issue/problem, management of ABC will then step in to resolve. Where it is a conflict between two or more of the team members thesemembers will be encouragedto resolve their own conflict as they arise. Whatever they are unable to resolve on their own it should be escalated to their immediate bosses. ABC will maintain an issue log that will contain the following data: 1. Issue number 2. Issue description 3. Issue raised by 4. Issue raised date 5. Issue priority 6. Issue resolution initiation date and 7. Issue resolution actual end date.
Quality assurance metrics: WBS Ref. Requirement From (Client through) Main Contractor Specification Specific and measurable Assurance Activity What is to be done Schedule Resources Responsibility Who should do it
4.0 Communication
Project progress meetings will be held daily, weekly and monthly and the minutes or reports sent to the main contractor. The daily progress meetings will be arranged and overseen by the Construction Manager on site 30 minutes each day before the start of the days work. The minutes of the meeting will contain the following information, among others: 1. What works were completed the previous day 2. What is preventing members from completing their activities, if any 3. What works are plannedfor the day of the meeting 4. What resources are needed for the days work? At the end of the meeting the report will be sent to the team, senior management and the main contractor. The process will continue daily until the project is completed. Weekly meetings will be held and the report of the meeting will be submitted with: a. Milestones achieved for the week b. Milestones missed for the week c. Milestones planned for the following week d. Any issues identified/encountered/envisaged that require Main Contractors attention or intervention e. Results of any quality assurance test undertaken f. Materials on site and in transit g. Payments received from Main Contractor h. Claims/certificates raised but yet to be honoured by Main Contractor Monthly meetings will be held and the report will be similar to the above. In addition to these, ABCs senior management shall be available to attend any meeting called by the Client or Main Contractor, particularly Technical Meetings.