Вы находитесь на странице: 1из 37

JAZAN ECONOMIC CITY

Jizan, Kingdom of Saudi Arabia

PHASE 1A DEVELOPMENT WATER UTILITIES POTABLE WATER

TENDER DOCUMENTS FOR THE CONSTRUCTION OF

POTABLE WATER - PACKAGE 1


VOLUME III BILL OF QUANTITIES

Jan - 2011

GENERAL SUMMARY

BILL NO. 1
GENERAL & PRELIMINARIES

BILL NO. 2
SITE FORMATION AND ANCILLARY WORKS

BILL NO. 3
PIPELINES

BILL NO. 4
VALVES AND FITTINGS

BILL NO. 5
INSTRUMENTATION SYSTEM

PREAMBLE

SCHEDULE OF DAYWORKS

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 Jizan - Saudi Arabia

BILLS OF QUANTITIES

General Summary
SAWACO Amount Bill No. 1 Bill No. 2 Bill No. 3 Bill No. 4 Bill No. 5 General and Preliminaries Site Formation and Ancillary Works Pipelines Valves and Fittings Instrumentation System POWARY Amount 2,100,000.00 1,947,900.00 6,907,187.00 251,000.00 146,000.00 SALCO Amount

TOTAL CARRIED TO FORM OF TENDER SR. Total Amount after deducting 5% added on the original price for POWARY Tender Sum (in words) : .

11,352,087.00
10811511.43

I:\910A\DOCUMENT\BQ\218931469.xlsx.ms_office

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 1 - GENERAL & PRELIMINARIES SAWACO Amount Rate (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item

Description General Notes on General & Preliminaries

Quantity

Unit

Rate (SR)

Rate (SR)

The Tender Sum shall be FIX LUMP SUM. The Tender Sum shall be deemed to have included for all requirements, obligations and work as stated in any of the Contract & Tender Documents. The Quantities set out in the Bills of Quantities are deemed to have been verified by the Contractor as being the quantities of the whole works required to be executed by him in accordance with the Contract Drawings and Contract Documents and will be subject to re-measurement on completion. The Contractor may add new items as he may find necessary to include for all the works or obligations required by the Contractor as defined or stated in the Tender and the Contract Documents. (New items made by the Contractor shall be at the "end of the item" in the Bill provided for). The Contractor is to provide the Engineer when required by the Engineer a breakdown of each unit rate into materials, labour, plant, overhead and profit. Each unit rate shall correspond to that included in the Schedule of Rates.

D These Preliminaries are applicable to the whole of the Works. If the Tenderer wishes to price any of the items contained herein then each such item, clause or sub-clause must be individually priced. Where an item, clause or sub-clause of the Preliminaries has not been priced, it will be deemed that the value of such item, clause or sub-clause is included in the rates entered elsewhere in the Bills of Quantities. The description included in the Bills of Quantities to describe the workmanship and materials necessary for each item are not necessarily complete. The Tenderer is referred to the Specifications, Conditions of Contract and other documents and the Drawings for further information concerning the works and no claim or variation will be considered on account of his failure to acquaint himself with such information. The Contractor shall satisfy himself as to the meaning of every item in the Bills of Quantities, the correctness, completeness, and with rates and prices inserted by the Contractor will be deemed to cover all his obligations under the Contract and all matters and things necessary for the proper construction, completion and maintenance of the Works (including, but not by way of limitation), for all temporary works required (including any that may be required by sub-Contractors, whether nominated or otherwise).

Carried to Collection

0.00

I:\910A\DOCUMENT\BQ\Flie]

BQ1-11

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 1 - GENERAL & PRELIMINARIES SAWACO Amount Rate (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item Pricing Generally

Description

Quantity

Unit

Rate (SR)

Rate (SR)

The price shall include for all materials and labour and for the provision and use of all plant-whether mechanical or non mechanical - required for the expeditious carrying out of the works in their proper sequence-for shifting, altering and adapting such temporary work and plant as may be required during the progress of the works and removing at completion and making good any surfaces disturbed; and if not included in any prices inserted against the clauses of the Conditions of Contract above, for the Guarantees and bonds required; for the costs of preparing a Tender; and the final account; and for all other establishment charges and on costs of whatever nature. No claim for additional payment will be allowed for any error or misunderstanding by the Contractor in these respects. Mobilization & Demobilization 1.1 Mobilisation and demobilisation at the site of all required construction plants, equipments and labour for the proper execution of the Works and the subsequent removal of these and cleaning up of site upon completion of the Works. Insurance and Bank Guarantee 1.2 The Contractor shall provide and maintain with an approved Insurance Company, Contractor's All Risk Insurance, Third Party Insurance, Workmen's Compensation Insurance, etc and as required in the Conditions of Contract, all in accordance with the latest applicable laws and labour regulations of the Government, and update the same if new laws, regulations or amendments were introduced by the Government until the final completion. Performance Bond and Advance Payment Bond as required in the Conditions of Contract.

LS

350,000

350,000

Item

35,000

35,000

1.3

Item

50,000

50,000

Surveying Works 1.4 Setting out, levelling, cross-sectioning and checking of the Works with reference to the established Survey Bench Mark on site and the provision of agreed site survey prior to commencement of any permanent work all in accordance with the Drawings.

LS

25,000

25,000

Carried to Collection

460,000.0

0.00

I:\910A\DOCUMENT\BQ\Flie]

BQ1-12

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 1 - GENERAL & PRELIMINARIES SAWACO Amount Rate (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item

Description Contractor's Administrative & Management Arrangements

Quantity

Unit

Rate (SR)

Rate (SR)

1.5

Allow for all costs of Contractor's site administration, supervision, technical and other management staff inclusive of all their direct and indirect costs, security, safety, health & welfare of work people and inclusive of all Contractor's main office costs and overheads all related to the management execution and administration of this project. Work Programme & Quality Assurance Plan

LS

950,000

950,000

1.6

Prepare, implementing and updating of work programme utilising Critical Path Analysis (CPM) techniques. Submission of Quality Assurance & Quality Control Plan prior to commencement of work.

LS

20,000

20,000 0 20,000 0 0 0 0

1.7

LS

20,000

Contractor's Office, Accommodation, Workshops and Maintenance. 1.8

Stores

and

Establishment, maintenance and removal of Contractor's offices, workshops, stores, living facilities etc., inclusive of utilities and services. Client Representative Site Office and Maintenance The Contractor shall deliver and hand-over to the Employer at the end of the Contract free of charge on completion of the works, the above mentioned Site Office, furniture, equipment and fittings, computer and accessories, including relocation within the site, the timing of which is at the Employer discretion.

LS

350,000

350,000 0 0 0

0 0 1 1 LS LS 0 0 0 0 0 0 0 0 0 0 0 0 0 0

1.9

Establishment, maintenance and removal of Client Representative office, etc., inclusive of utilities and services.

1.10 Ditto but Maintenance during the DLP period Protection and Maintenance of the Works 1.11 Maintenance and protection of COMPLETED roads and road furnitures, as per the Specification during Defect Liability Period. Project Signboard 1.12 Provide and install Project signboard. Progress Report 1.13 Preparation of 3-sets monthly progress reports to be submitted in approved format during the Contract Period including photograph required thereof.

months

No.

Month

0 0 1,340,000.0

Carried to Collection

I:\910A\DOCUMENT\BQ\Flie]

BQ1-13

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 1 - GENERAL & PRELIMINARIES SAWACO Amount Rate (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item As-Built Drawings

Description

Quantity

Unit

Rate (SR)

Rate (SR)

1.14 Preparation of as-built drawings progressively upon completion of section of the works and submit the completed as-built drawings to Employer : a) For verification and approval by the Employer :i) 3 sets of hard copy (A1 size) b) Upon verification and approval by the Employer :i) 1 set of transparancies ii) 6 sets of hard copy (A1 size) 6 sets of computer compact disc in the Computer Aided iii) Design (CAD) format

LS

50,000

50,000 0 0 0 0 0 0 0 0 0 0 0 0

Temporary Water and Electricity Supply 1.15 Arrangement for Temporary water supply and electricity supply necessary for the execution of Works. Environmental Protection 1.16 Establishment, maintenance and removal of necessary activities and prevention measures for the protection of the environment during the contract period inclusive of control of noise and pollution. Health, Safety and Environment Requirement 1.17 Allow for the provision and maintenance of Health, Safety and Environment requirement on site including the provision of the following items :a) Personal Protection Equipment such as protective gear, safety helmets, flourescent jackets, safety boots, ear protectors, eye protectors, gloves, etc. to all Contractor's site personnel. b) Establish and enforce health, safety & environment measures. c) Provision of full time Health, Safety and Environment Officer.

LS

150,000

150,000 0 0 0

LS

50,000

50,000 0 0 0

LS

50,000

50,000 0

Carried to Collection

300,000.0

I:\910A\DOCUMENT\BQ\Flie]

BQ1-14

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 1 - GENERAL & PRELIMINARIES SAWACO Amount Rate (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item Other Items

Description

Quantity

Unit

Rate (SR)

Rate (SR)

1.18 Other items not listed above but considered necessary for complying with all the requirements of the Conditions of Contract, the Specifications, the Drawings and Bills of Quantities etc. as and when directed by the Engineer for the Construction and Completion of the whole of the Works. (Please specify the items and price separately hereunder) a) .. b) .. c) .. d) .. e) ..

Carried to Collection

I:\910A\DOCUMENT\BQ\Flie]

BQ1-15

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 1 - GENERAL & PRELIMINARIES SAWACO Amount Rate (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item

Description COLLECTION FOR BILL NO. 1

Quantity

Unit

Rate (SR)

Rate (SR)

PAGE BQ1 - 1

PAGE BQ1 - 2

460,000

PAGE BQ1 - 3

1,340,000

PAGE BQ1 - 4

300,000

PAGE BQ1 - 5

Total BILL NO. 1 Carried to Summary

2,100,000.00

I:\910A\DOCUMENT\BQ\Flie]

BQ1-16

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 2 - SITE FORMATION AND ANCILLARY WORKS SAWACO Rate Amount (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item

Description

Quantity

Unit

Rate (SR)

Rate (SR)

EARTHWORKS Bulk Excavation Excavate all material below original ground to formation level for pipeworks within the pipeline corridor. Rate to include stockpiling of suitable materials for use as fill, levelling, trimming, shaping and compacting to slope and formation level and disposal of unsuitable and excess materials. Backfilling Transport and place suitable materials from cutting within the pipeline corridor to form embankment, including spreading, levelling, trimming to formation levels, shaping and compacting. Trench Excavation Excavate in all materials below original ground and/or beyond nominal limits of bulk excavation. Trench excavation shall be measured by length along the center of the pipe and once only to the full depth of the trench. 2.4 2.5 2.6 2.7 2.8 2.9 For DN 400 mm dia MS pipe not exceeding 2.5 m deep. Ditto exceeding 2.5 m but not exceeding 5.0 m deep. For DN 300 mm dia MS pipe not exceeding 2.5 m deep. Ditto exceeding 2.5 m but not exceeding 5.0 m deep. For DN 250 mm dia MS pipe not exceeding 2.5 m deep. Ditto exceeding 2.5 m but not exceeding 5.0 m deep. 2,300 100 6,500 100 800 50 m m m m m m 95 115 85 95 0 95

2.2

15,420

m3

45

693900 0 0

2.3

1,000

m3

45

45000 0 0

Incidental Excavation 2.10 Excavate in all materials outside and below limits of bulk excavation and trench excavation for isolation valve, washout, air valve, future tapping, outfall chambers, anchor blocks and support for pipes. CONCRETE AND FORMWORK Mass Concrete Class B 2.11 In surround to pipes. Rate to include all necessary formwork. Reinforced Concrete Class S 2.12 In valve chambers and washout outfall structures. 2.13 Vertical Class F1 formwork to faces below ground

0 0 218500 0 11500 0 552500 0 9500 0 0 0 4750 0 0

1,200

m3

45

10

m3

450

20 192

m3 m2

1,250.00 225

54000 0 0 0 0 4500 0 0 25000 0 43200

Carried to Collection

1662350

I:\910A\DOCUMENT\BQ\Phase 1A Tender\Package 1

BQ2-17

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 2 - SITE FORMATION AND ANCILLARY WORKS SAWACO Rate Amount (SR) (SR) POWARY Amount (SR) 19800 0 9000 0 0 0 1400 0 11200 0 21000 0 0 0 0 0 0 4500 0 29900 0 0 0 0 0 6750 0 34500 0 0 0 25000 0 0 0 0 28000 0 0 0 0 0 4000 0 0 0 0 4000 0 0 0 0 199050 SALCO Amount (SR)

Item

Description

Quantity

Unit

Rate (SR) 225 225

Rate (SR)

2.14 Vertical Class F2 formwork to exposed faces 2.15 Soffit Class F2 formwork STEEL REINFORCEMENT 2.16 12 mm and below dia epoxy coated mild steel bars 2.17 12 mm and below dia epoxy coated high tensile steel bars 2.18 16 mm and above dia epoxy coated high tensile steel bars PC Chamber Construct precast (pc) washout chambers as shown in the Drawings. Rate to include Class B mass concrete surround, cover slab with heavy duty plate complete with lifting holes, JEC logo etc. 2.19 Type 2 for DN 400 mm 2.20 Type 2 for DN 300 mm Construct precast (pc) air valve chambers as shown in the Drawings. Rate to include Class B mass concrete surround, cover slab with heavy duty plate complete with lifting holes, JEC logo etc. 2.21 Type 1 for DN 400 mm 2.22 Type 1 for DN 300 mm MISCELLANEOUS WORKS 2.23 Supply, fix and paint concrete marker post for valve chambers and pipelines. Rate to include excavation, backfilling and mass concrete. 2.24 Suppy, fix and install 225 mm wide x 25 mm dia epoxy coated high tensile bar step irons to valve chambers as shown in Drawings. 2.25 Suppy, fix and install 600 mm dia heavy duty FRP manhole cover to valve chambers as shown in Drawings. Rate to include building into concrete cover slab and all holding down bolts as recommended by the manufacturer. Shop drawings to be submitted for approval by the Engineer. 2.26 Suppy, fix and install 100 mm dia Class C PVC pipe with cover over valve spindle to valve chambers as shown in Drawings. Rate to include building into concrete cover slab and shop drawings to be submitted for approval by the Engineer. 2.27 Suppy, fix and install extension valve spindle not exceeding 2 meters long with bracket support to valve in chambers as shown in Drawings. Rate to fixing into concrete wall and shop drawings to be submitted for approval by the Engineer. Carried to Collection

88 40

m2 m2

200 1,600 3,000

kg kg kg

7 7 7

2 13

No. No.

2,250 2,300

3 15

No. No.

2,250 2,300

50

No.

500

No.

3,500

No.

500

No.

500

I:\910A\DOCUMENT\BQ\Phase 1A Tender\Package 1

BQ2-18

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 2 - SITE FORMATION AND ANCILLARY WORKS SAWACO Rate Amount (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item

Description

Quantity

Unit

Rate (SR)

Rate (SR)

2.28 Water pressure testing of pipelines as specified. Rate to include for provision of all plant, equipment and labour to complete the works. 2.29 Sterilising and flushing of pipelines as specified. Rate to include for provision of all water, chemicals, plant, equipment and labour to complete the works. Construct reinforced concrete chamber for DN 250mm dia. pressure reducing valve assembly (dimensions shown in the standard detail 2.30 drawing T/UW1/P1A/WS/SD/1.10rev.1), with heavy duty manhole cover, ladder rungs and all other associated items to complete the work. Shop drawings to be submitted for approval by the Engineer. Construct reinforced concrete chamber for DN 250mm dia. battery operated electromagnetic Flow Meter Assembly (dimensions shown in the standard detail drawing T/UW1/P1A/WS/SD/1.10rev.1), with heavy 2.31 duty manhole cover, ladder rungs and all other associated items to complete the work. Shop drawings to be submitted for approval by the Engineer. Construct reinforced concrete chamber for DN 200mm dia. battery operated electromagnetic Flow Meter Assembly at SOLB (dimensions shown in the standard detail drawing T/UW1/P1A/WS/SD/1.10rev.1), 2.32 with heavy duty manhole cover, ladder rungs and all other associated items to complete the work. Shop drawings to be submitted for approval by the Engineer. OTHER ITEMS 2.33 Other items not listed above but considered necessary for the pipeworks for complying with all the requirements of the Conditions of a). b) c) d)

LS

35000

35000

LS

35000

35000

No. 5,500.00 5,500.00

No. 5,500.00 5,500.00

No. 5,500.00 5,500.00

Carried to Collection

86500

I:\910A\DOCUMENT\BQ\Phase 1A Tender\Package 1

BQ2-19

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 2 - SITE FORMATION AND ANCILLARY WORKS SAWACO Rate Amount (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item

Description

Quantity

Unit

Rate (SR)

Rate (SR)

COLLECTION FOR BILL NO. 2

PAGE BQ2 - 1 PAGE BQ2 - 2 PAGE BQ2 - 3

1662350 199050 86500

Total BILL NO. 2 Carried to Summary

1,947,900.00

I:\910A\DOCUMENT\BQ\Phase 1A Tender\Package 1

BQ2-20

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 3 - PIPELINES SAWACO Rate Amount (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item PIPELINES

Description

Quantity

Unit

Rate (SR)

Rate (SR)

Supply, deliver, laying and fixing Supply, deliver and laying in position ready for jointing and/or building in and painting as specified steel pipes, specials, joints and fittings. Unless otherwise stated :All spigot and socket ended pipes shall be suitable for internally and external welded slip joints. All plain ended pipes and specials shall be suitable for internally and externally welded collar joints, mechanical coupling joints or flanged adaptor joints. All pipes and specials shall be internally epoxy or rubber lined and externally coated and wrapped. All flanges of joints and valves shall be suitable for a pressure rating of PN 16 unless otherwise stated. The dimensions shall be in accordance with the details shown in the Specifications. The thickness of steel shells shall be as stated in the Specifications. The rates shall include the supply of jointing materials like nuts, bolts, washers, gaskets etc The thickness of collar shall be 1.5 mm more than the larger thickness of the two adjoining pipes and specials. PIPEWORKS Straight Pipes For the purpose of payment, the length of standard, half length or cut length pipes shall be "effective length as laid" measured along the center line of the pipes. 3.1 DN 400 mm dia in standard, half and cut length spigot and socket ended pipes DN 300 mm dia ditto DN 250 mm dia ditto Plain Ended Straight Pipes DN 400 mm dia in standard, half and cut length plain ended pipes suitable for collar or mechanical coupling joints. DN 300 mm dia ditto DN 250 mm dia ditto DN 100 mm dia ditto

2,300 6,500

m m Refer to item 3.60 m

773 561

3.2 3.3 3.4

1777900 0 3646500 0 22000 0 0 49000 10610 0 49080 5555090

20

1100

3.5 3.6 3.7

40 10 40

m m m

1,225.00 1,061.00 1,227

Carried to Collection

BQ3-21

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 3 - PIPELINES SAWACO Rate Amount (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item 3.8

Description DN 400 mm dia X 1000 mm long c/w puddle flange suitable for isolation valve as shown in the Drawings.

Quantity

Unit

Rate (SR)

Rate (SR)

2 5 1 6 2 13

No. No. No. No. No. No.

4000 3200 0 2284 3352 945

3.9 DN 300 mm ditto 3.9a DN 300 mm ditto and 50 dia flange ended branch. 3.10 DN 250 mm ditto 3.11 DN 250 mm X 2000 mm long ditto 3.12 DN 100 mm X 1000 mm long ditto Plain and Flange Ended Straight Pipes 3.13 DN 400 mm dia X 1000 mm long c/w puddle flange suitable for isolation valve as shown in the Drawings. 3.14 3.14a 3.14b 3.15 DN 300 mm ditto DN 300 mm ditto and 50 dia flange ended branch. DN 300 mm ditto but w/o puddle flange. DN 250 mm ditto

No.

4000

5 1 2 6 2 1 13

No. No. No. No. No. No. No.

3200 0 0 2000 3352 3254 945

3.16 DN 250 mm X 2000 mm long ditto 3.17 DN 250 mm X 500 mm long ditto 3.18 DN 100 mm X 1000 mm long ditto Double Flange Ended Straight Pipes 3.19 DN 250 mm dia X 500 mm long c/w puddle flange suitable for isolation valve as shown in the Drawings. Bends DN 300 mm Plain Ended 3.20 More than 45 degree and up to 90 degree bend DN 250 mm Plain Ended 3.21 Up to 45 degree bend 3.22 More than 45 degree and up to 90 degree bend Tees Concentric Tee 3.23 DN 400 mm plain ended barrel with DN 80 mm flange ended branch for air valve 3.24 DN 300 mm plain ended barrel with DN 50 mm flange ended branch for air valve 3.25 DN 400 mm plain ended barrel with DN 400 mm plain ended branch

No.

2200

No.

7000

2 3

No. No.

2652 2368

No.

3200

15 2

No. No.

2333 3700

8000 0 16000 0 13704 0 6704 0 12285 0 0 8000 0 0 16000 0 0 12000 0 6704 0 3254 0 12285 0 0 2200 0 0 0 0 7000 0 0 5304 0 7104 0 0 0 0 9600 0 0 34995 0 7400

Carried to Collection

188539

BQ3-22

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 3 - PIPELINES SAWACO Rate Amount (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item

Description

Quantity

Unit

Rate (SR)

Rate (SR)

3.26 DN 400 mm plain ended barrel with DN 300 mm plain ended branch 3.27 DN 300 mm plain ended barrel with DN 300 mm plain ended branch 3.28 DN 300 mm plain and flange ended barrel with DN 100 mm plain ended branch for washout 3.29 DN 400 mm plain and 8 mm thick welded end cap barrel with DN 150 mm plain ended branch for washout 3.30 DN 300 mm plain and 8 mm thick welded end cap barrel with DN 100 mm plain ended branch for washout 3.31 DN 400 mm plain ended barrel with DN 250 mm flange ended branch for future connection 3.32 DN 300 mm plain ended barrel with DN 250 mm flange ended branch for future connection Level Invert Tee 3.33 DN 400 mm plain ended barrel with DN 150 mm plain ended branch for washout 3.34 DN 300 mm plain ended barrel with DN 100 mm plain ended branch for washout 3.35 DN 250 mm plain ended barrel with DN 100 mm plain ended branch for washout Taper 3.36 DN 250 to DN 400 plain ended level top taper X 1500 mm long 3.37 DN 400 to DN 300 plain ended level top taper X 1200 mm long 3.38 DN 300 to DN 250 plain ended level top taper X 900 mm long Blank Flange 3.39 Complete with all jointing materials, nuts, bolts and washers For DN 300 mm pipe PIPE CUTTING AND JOINTING Cutting Pipe The Contract Rates shall include for preparing pipe ends of cut pipe suitable for making flange adaptor and mechanical coupling joints or internally and externally welded collar joints and making good external coating and internal lining. 3.40 Cutting DN 400 mm pipe

1 4

No. No.

5200 3250

13

No.

2385

No.

2200

13

No.

2000

No.

5200

No.

7000

No.

2200

13

No.

2385

No.

2613

1 1 1

No. No. No.

2000 5200 6250

13

No.

690

5200 0 13000 0 0 31005 0 0 0 0 0 26000 0 0 5200 0 0 7000 0 0 0 0 0 0 31005 0 0 0 0 0 2000 0 5200 0 6250 0 0 0 8970

Cost to be included in item 3.1 & 3.4

Carried to Collection

140830

BQ3-23

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 3 - PIPELINES SAWACO Rate Amount (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item 3.41 Cutting DN 300 mm pipe 3.42 Cutting DN 250 mm pipe 3.43 Cutting DN 100 mm pipe

Description

Quantity

Unit

Rate (SR)

Rate (SR)

Cost to be included in item 3.2 & 3.5 Cost to be included in item 3.6 & 3.60 Cost to be included in item 3.7

Jointing Pipeworks The Contract Rates for making all joints shall include supplying, delivery, storing, handling and placing in position mechanical couplings, blank flanges, flange adaptors, all jointing materials and collars. It shall include for making good and complete the external and internal protection of pipes and joints unless otherwise specified. Making welded slip joints shall include for one external and one internal circumferential welds and air testing the annular space formed unless otherwise specified. Making welded collar joints shall include for two external and two internal circumferential welds and one butt weld and air testing the two annular spaces so formed unless otherwise specified.

Welded Joint 3.43 Making welded slip joints on DN 400 mm socket and spigot ended pipes. 3.44 Making welded slip joints on DN 300 mm socket and spigot ended pipes. 3.45 Making welded slip joints on DN 250 mm socket and spigot ended pipes. 3.46 Making welded collar joints on DN 400 mm plain ended pipes and specials. 3.47 Making welded collar joints on DN 300 mm plain ended pipes and specials. 3.48 Making welded collar joints on DN 250 mm plain ended pipes and specials. 3.49 Making welded collar joints on DN 100 mm plain ended pipes and specials. Flange Joint 3.50 Making flanged joint on DN 400 mm pipes, specials and valves. 3.51 Making flanged joint on DN 300 mm pipes, specials and valves. 3.52 Making flanged joint on DN 250 mm pipes, specials and valves.

Cost to be included in item 3.1

Cost to be included in item 3.2

Cost to be included in item 3.60 Cost to be included in item 3.4,3.8, 3.13,3.23,3.25,3.26,3.31,3.37 Cost to be included item 3.5,3.9, 3.14,3.20,3.24,3.27,3.28,3.32,3.34,3.38 Cost to be included in item 3.6,3.10, 3.11,3.16,3.17,3.21,3.22,3.35 Cost to be included in item 3.7,3.12,3.18

2 5 6

No. No. No.

1500 1250 1250

3000 0 6250 0 7500

Carried to Collection

16750

BQ3-24

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 3 - PIPELINES SAWACO Rate Amount (SR) (SR) POWARY Amount (SR) 10140 0 18000 0 0 0 2400 0 5500 0 4000 0 10400 SALCO Amount (SR)

Item

Description

Quantity 13 30

Unit No. No.

Rate (SR) 780 600

Rate (SR)

3.53 Making flanged joint on DN 100 mm pipes, specials and valves. 3.54 Making flanged joint on DN 80 mm pipes, specials and valves. Flange Adaptor 3.55 Making flange adaptor joint on DN 400 mm pipes, specials and valves. 3.56 Ditto DN 300 mm ditto 3.57 Ditto DN 250 mm ditto 3.57a Ditto DN 250 mm for tied flange adaptor ditto 3.58 Ditto DN 100 mm ditto

2 5 4 2 13

No. No. No. No. No.

1200 1100 1000 0 800

3.59 CATHODIC PROTECTION Supply, lay and install complete cathodic protection system as specified in the Specifications and as detailed in the Schedule of Particulars. Rate to include soil resistivity measurements and compliance with all clauses in the Specifications.

1 3.60 PIPEWORKS Supply and install DN250mm dia. pipe from JEC boundary fence to limit of SWCC's interconnection point ( shown in drawings T/UW1/P1A/WS/PP/1.16 rev.0 and T/UW1/P1A/WS/SD/1.10rev.1 ) including all associated works necessary to complete but not limited to survey ( item 1.4), trench excavation ( item 2.8 ), pipe cutting ( item 3.42 ), jointing/welding ( item 3.45 ). OTHER ITEMS 3.61 Other items not listed above but considered necessary for the pipeworks for complying with all the requirements of the Conditions a) b) .. c) .. d) .. e) ..

LS

500000

500000

Lot 453863 453863

Carried to Collection

1004303

BQ3-25

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 3 - PIPELINES SAWACO Rate Amount (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item

Description COLLECTION FOR BILL NO. 3

Quantity

Unit

Rate (SR)

Rate (SR)

PAGE BQ3 - 1 PAGE BQ3 - 2 PAGE BQ3 - 3 PAGE BQ3 - 4 PAGE BQ3 - 5

5555090 188539 140830 18425 1004303

Total BILL NO. 3 Carried to Summary

6,907,187.00

BQ3-26

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 4 - VALVES SAWACO Rate Amount (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item VALVES AND FITTINGS

Description

Quantity

Unit

Rate (SR)

Rate (SR)

Supply, delivery and Installation Unless otherwise stated :All valves shall be suitable for a pressure rating of 16 bars. All valve flanges shall be made to suit connection to adjacent flanged pipes, specials or flanged adaptors. Collect from store on Site, transport, haul, handle and place in position for jointing valves and fittings. Rate to include all jointing materials and painting of all valves after installation. Air Valve DN 80 mm double orifice air valve complete with double flanged isolating butterfly valve. DN 50 mm double orifice air valve complete with double flanged isolating butterfly valve. DN 25 mm double orifice air valve complete with double flanged isolating butterfly valve. Butterfly valve DN 400 mm dia DN 300 mm dia Sluice/Gate valve DN 250 mm PN 40 DN 250 mm DN 100 mm Pressure Reducing Valve DN 250 mm PN 40 complete with pressure gauges and all accessories Fittings Mild steel tee key 1500 mm long with 750 mm long arm suitable for operating 250 mm dia sluice valve Mild steel tee key 1500 mm long with 750 mm long arm suitable for operating 150 mm dia sluice valve

a b

4.1

No.

2500

7500 0 27000 0 2400 0 0 19600 0 37200 0 0 10000 0 22500 0 11700 0 0 0 5000 0 0 0 550 0 0 550

4.2

15

No.

1800

4.3

No.

1200

4.4 4.5

2 6

No. No.

9800 6200

4.6 4.7 4.8

2 5 13

No. No. No.

5000 4500 900

4.9

No.

5000

4.10

No.

550

4.11

No.

550

Carried to Collection

144000

BQ4-27 (Addendum No. 1)

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 4 - VALVES SAWACO Rate Amount (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item

Description Fire Hydrant 100 mm dia double pillar fire hydrant as detailed in the Drawings at locations to be decided by the Engineer. Rate to include all pipe fittings and specials, landing valve, precast chamber and mass concrete supports. Connection to Existing SWCC's branch pipeworks Rate to include all necessary temporary works, trial pit to determine OD of existing pipe, excavation, backfilling and making good to original condition. The Contractor is required to liaise with SWCC for approval prior to carrying out the interconnection works.

Quantity

Unit

Rate (SR)

Rate (SR)

4.12

No.

25,000

100,000

4.13

Carry out interconnection works from new DN 250 mm pipeline to existing 250 mm dia pipe at SWCC's interconnection point. Rate to include pipe cutting, jointing, welding and supply of collar to suit OD of existing pipe. Witness Testing Allow for witness testing of valves at the Manufacturer's works by two (2) representatives of the Employer. (OPTIONAL)

LS

7000

7000

4.14

LS

7000

7000

OTHER ITEMS 4.15 Other items not listed above but considered necessary for the completion of the installation of valves and fittings for a) b) c) d) e)

Carried to Collection

107,000

BQ4-28 (Addendum No. 1)

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 4 - VALVES SAWACO Rate Amount (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item

Description COLLECTION FOR BILL NO. 4

Quantity

Unit

Rate (SR)

Rate (SR)

PAGE BQ4 - 1 PAGE BQ4 - 2

144000 107,000

Total BILL NO. 4 Carried to Summary

251,000.00

BQ4-29 (Addendum No. 1)

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 5 - INSTRUMENTATION SYSTEM SAWACO Rate Amount (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item

Description

Quantity

Unit

Rate (SR)

Rate (SR)

Drawings and Manuals 5.1 General arrangement, construction, installation, layout and other detailed drawings. Instrument general arrangement, construction, installation, layout and other detailed drawings. Electrical block diagrams, loop wiring diagrams, electrical connection and termination details, cable schedule etc Operation and maintenance manuals Record Drawings Witness Testing Allow for witness testing of electromagnetic flowmeters at the Manufacturer's works by two (2) representatives of the Employer. (OPTIONAL) Allow for witness testing of supervisory/instrument panel etc at the Manufacturer's works by two (2) representatives of the Employer. (OPTIONAL) Tests at Manufacturer's Works Test certificates certifying performance Manufacturer's Works.

LS

15,000

5.2

LS

15,000

5.3

1 1 1

LS LS LS

15,000 15,000 15,000

5.4 5.5

5.6

LS

3,000

5.7

LS

3,000

5.8

of

plant

in

tests

at 1 1 LS LS 3,000

5.9

Training of all operator's personnel as specified. Electromagnetic flowmeter DN 250 mm dia battery operated electromagnetic flowmeter complete with flow head convertor, painted stainless steel weatherproof pedestal panel, flange adaptor, bolts, nuts and washers, all power and signal cabling, indication of flowrate and totaliser on supervisory panel, earthing rings complete with independent earth, etc. for measurement of flow from SWCC's interconnection. DN 200 mm dia battery operated electromagnetic flowmeter complete with flow head convertor, painted stainless steel weatherproof pedestal panel, flange adaptor, bolts, nuts and washers, all power and signal cabling, indication of flowrate and totaliser on supervisory panel, earthing rings complete with independent earth, etc. for measurement of flow to South Steel's interconnection.

5.10

No.

12,000

5.11

No.

11,000

15,000 0 0 15,000 0 0 15,000 0 15,000 0 15,000 0 0 0 3,000 0 0 3,000 0 0 0 3,000 0 0 0 0 0 0 0 0 12,000 0 0 0 0 0 11,000

Carried to Collection

101,000.0

I:\DOCUMENT\BQ\218931469.xlsx.ms_office

BQ5-30

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 5 - INSTRUMENTATION SYSTEM SAWACO Rate Amount (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item

Description

Quantity

Unit

Rate (SR)

Rate (SR)

Painting, Site Tests, Setting to Work, Commissioning and Maintenance 5.12 5.13 5.14 5.15 5.16 5.17 5.18 Painting Site tests Setting to work Test for guarantees and performance at Site Seven (7) days commissioning tests Three (3) months maintenance Further nine (9) months maintenance OTHER ITEMS Other items not listed above but considered necessary for the Instrumentation Works for complying with all the requirements of the Specifications, the Drawings and Bills of Quantities etc. as and when directed by Engineer for the Construction and Completion of the whole of the Works. (Please specify the items and price separately hereunder) a) b) c) d) e) 1 1 1 1 1 1 1 LS LS LS LS LS LS LS 5,000 5,000 5,000 15,000 15,000 5,000 0 5,000 0 5,000 0 15,000 0 15,000

5.19

Carried to Collection

45,000.0

I:\DOCUMENT\BQ\218931469.xlsx.ms_office

BQ5-31

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 BILL NO. 5 - INSTRUMENTATION SYSTEM SAWACO Rate Amount (SR) (SR) POWARY Amount (SR) SALCO Amount (SR)

Item

Description

Quantity

Unit

Rate (SR)

Rate (SR)

COLLECTION FOR BILL NO. 5

PAGE BQ5 - 1 PAGE BQ5 - 2

101,000 45,000

Total of BILL NO. 5 Carried to Summary

146,000.00

I:\DOCUMENT\BQ\218931469.xlsx.ms_office

BQ5-32

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 SCHEDULE OF DAYWORKS PREAMBLE

Any work ordered by the Employer to be carried out by daywork shall be paid for at the rates entered hereunder subject to the following conditions: -

Daily Rate means eight (8) hour day. Should more than eight and less than twenty-four hours be worked consecutively (excluding normal breaks, etc.) the excess hours will be paid pro rate daily rate. Hourly Rate means any hour of any period less than eight (8) hours. The rates entered for labour shall be deemed to include all on-costs associated with the employment of such labour including (inter-alia), head office charges, overhead charges, profit, site supervision and staff, insurances, wages, travelling time and expenses, subsistence allowances, time lost due to inclement weather, bonus, holiday and sick pay and any other employee's fringe benefit(s), provision of protective clothing, ordinary tools, small plant not provided under `Plant' below and consumable stores, temporary equipment such as wagons, temporary tracks, ladders, staging, scaffolding and all items of a similar nature unless these are provided or set up exclusively for the daywork. The time of skilled, semi-skilled and unskilled labour shall be paid for at the appropriate rate, but the time of supervisory staff including site agent shall be deemed to be included in the rates entered for labour. Payment for labour shall be reckoned from the time labour arrives at the job site to execute the particular item of daywork until labour leaves the job site but excluding breaks and rest periods. The rates entered for plant, whether hired or owned by the Contractor shall be deemed to include all overhead charges, profit, site supervision and staff, hire charges, fuel, maintenance, consumable stores, spare parts, insurances, etc., but shall exclude the cost of wages for drivers and operators, which shall be payable separately as dealt with under paragraph 3 above. Payment for Plant shall be made only at such times as the plant is engaged on daywork, and shall exclude all standing, idle, down time or travelling time to and from the place of work. The prices for materials shall include delivery to the local site where daywork is done, checking on site, handling, storage, site haulage, wastage, establishment charges, overheads and profits. The daywork rates shall also cover works carried out on overtime basis or on Friday and public holidays. The Employer reserves the right to order daywork outside normal working hours or on Friday and public holidays. The cost for special watching and lighting necessitated by dayworks shall be included in the rates. If any workman or item of plant on daywork does not readily belong to any classification included in the Schedule or inserted by the Contractor at the time of tendering, the Employer shall determine the equivalent classification to be adopted for such workman or item of plant, and payment for such will be made accordingly. The rates inserted by the Contractor shall be realistic rates in conformity with those on which his tender has been based, and shall be firm from the time to the Contractor commences the Works on Site until the end of the Defects Liability Period. Provision is made for the insertion of rates for additional items which the Contractor may consider likely to be employed. The Employer shall have the power to examine and subsequently ascertain the reasonableness of the rates inserted. Where found to be unreasonable, the Employer shall be empowered to make a fair valuation of the relevant rates

2 3

10 11

12

13

14

I:\910A\DOCUMENT\BQ\218931469.xlsx.ms_office

PDW1-33

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 SCHEDULE OF DAYWORKS SAWACO Item Description POWARY SALCO

Rate Rate Rate Rate Rate Rate SR / Hour SR / Day SR / Hour SR / Day SR / Hour SR / Day

A 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

DAY-WORK RATES SCHEDULE FOR LABOUR Surveyor Mechanic Electrician A/C Technician Welder Plant Operator Driver - Light Vehicle Driver - Truck and Heavy Transport Operator Tower Crane Operator Hydraulic Crane Operator Forklift Carpenter Steel Fixer / Bar Worker Mason Bricklayer Plasterer Mechanical / Electrical Labour Helper General Labourer Concrete Worker (Semi skilled) Others (to be inserted by Tenderer) .. .. .. 50 50 50 50 50 50 30 30 40 40 40 20 20 25 25 25 20 15 20 400 400 400 400 400 400 240 240 320 320 320 160 160 200 200 200 160 120 160

I:\910A\DOCUMENT\BQ\218931469.xlsx.ms_office

DW1-34

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 SCHEDULE OF DAYWORKS SAWACO Item Description POWARY SALCO

Rate Rate Rate Rate Rate Rate SR / Hour SR / Day SR / Hour SR / Day SR / Hour SR / Day

B 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

DAY-WORK RATES SCHEDULE FOR PLANT Bulldozer CAT D6 or Equivalent (0.3M3) Bulldozer CAT D67 or Equivalent (3.0M3) Concrete Truck Mixer (5.0M3) Concrete Mixer 7T (0.3M3/HR) Concrete Mixer 2 1/14T (2.0M3/HR) Mobile Crane (5 Tonne) Mobile Crane (10 Tonne) Mobile Crane (15 Tonne) Mobile Crane (20 Tonne) Mobile Crane (50 Tonne) Backhoe (0.15M3) Excavator (1.2M3) Excavator (1.7M3) Excavator (0.9M3) Wheel Loader CAT 950 or Equivalent (2.4M3) Wheel Loader CAT 996 or Equivalent (3.1M3) Motor Grader (12 ft Blade) Scraper Self Loading 7.5 cu m Scraper Self Loading 11 1/2 cu m Steel Wheeled Roller 5-7 tonne Steel Wheeled Roller 10-12 tonne Self propelled vibratory roller 15 tonne compaction force 140 140 140 100 140 140 140 140 140 200 140 140 140 140 140 140 200 200 200 200 200 200

I:\910A\DOCUMENT\BQ\218931469.xlsx.ms_office

DW1-35

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 SCHEDULE OF DAYWORKS SAWACO Item Description POWARY SALCO

Rate Rate Rate Rate Rate Rate SR / Hour SR / Day SR / Hour SR / Day SR / Hour SR / Day

DAY-WORK RATES SCHEDULE FOR PLANT (Con't) 23 24 25 26 27 28 29 30 31 32 33 34 Drawn vibratory roller 15 tonne compaction force Pneumatic Tyred Roller 7-14 tonne Dump Truck 8-10 tonne payload Dump Truck 10-12 tonne payload Water Browser (1500 Gal) Air Compressor (175 CFRM) Air Compressor (370 CFRM) Air Compressor (600 CFRM) Asphalt Paver (120 tonne/hr) Asphalt Paver (100 tonne/hr) Portable compactor Others (to be inserted by Tenderer) .. .. .. 200 200 140 140 140 70 70 70 200 200 140

I:\910A\DOCUMENT\BQ\218931469.xlsx.ms_office

DW1-36

JAZAN ECONOMIC CITY PHASE 1A DEVELOPMENT - WATER UTILITIES POTABLE WATER SUPPLY - PACKAGE 1 SCHEDULE OF DAYWORKS SAWACO Item Description POWARY SALCO

Rate Rate Rate Rate Rate Rate SR / Hour SR / Day SR / Hour SR / Day SR / Hour SR / Day

C 35 36 37 38 39 40 41 42 43 44 45 46 47 46

SCHEDULE RATES FOR MATERIALS Structural Excavation Structural Backfill Epoxy Coated High Strength Reinforcing Steel, Grade 500 Epoxy Coated High Strength Reinforcing Steel, Grade 400 Epoxy Coated Mild Steel Reinforcing Bar STRUCTURAL CONCRETE CLASS S (350 kg/cm2 with micro silica) STRUCTURAL CONCRETE CLASS B (170 kg/cm2 with micro silica) Waterproofing (2 Coat of Bituminous Paint) Expansion Joint Precast Reinforced Concrete Pipe Culvert 3.00m diameter Precast Reinforced Concrete Pipe Culvert 3.30m diameter Precast Reinforced Concrete Pipe Culvert 2.10m diameter Precast Reinforced Concrete Pipe Culvert 3.60m diameter Others (to be inserted by Tenderer) .. .. .. 150 75 6000/ton 6000/ton 6000/ton 400/m3 400/m3 20/m2 175/Lm 7,500 7,500 7,500 8,000

I:\910A\DOCUMENT\BQ\218931469.xlsx.ms_office

DW1-37

Вам также может понравиться