INTRODUCTION. A. Background PT. PIM was established on 24 February 1982 before the notary saoeliaman ardjasama, No.

SH appropriate certificate. 54 with the name of PT. young isakandar fertilizer, which is a state-owned enterprises (BUMN) under the auspices of Minister of State. utilization of state-owned enterprises. PIM plant construction project was originally dirintisa by PT. PUSRI palembang saejak 1981, supported by natural resources and water, which is the main raw material of urea fertilizer, plant construction site set in Krueng Geukuh, North Aceh district. 1. Utility unit This unit is used to process the raw material supply needs such as: a. Clean water for the raw materials, water for cooling, mineral-free water for ketei vapor, water vapor (steam), instrument air, power lisatrik and oxygen. 2. raw materials obtained from the Krueng Peusangan water, power lisatrik Genarator dubangkitkan by gas turbines with a capacity of 15 MW. 3. Air raw materials obtained from fractional colum in the free air cooled by the dew point difference, so that the elements oxygen and nitrogen can be separated again.

As for the units in the utility plant are as follows: a. water intake unit facilty b.unit water treatment - clarifier - Gravity sand filter - Actived carbon filter - demineralizer c. steam generating unit - Package boiler - Waste heat d. unit instrument air / plant air e. air separation plant unit f. unit mettering gas station g. the waste processing unit h. generating units lisatrik - Main generator - Stand-by generator - Emergency generator The main generator is the main electricity generating units driven by gas turbines, generators with a capacity of 15 MW generated voltage 13.8 KV, three phase in the switch room in the utility, of the bus was set to switch another room with lowered voltage through a transformer down (13.8 KV - 2.4 KV) and lowered again by a stepdown transformer 480 V to foam, then lowered again to the stepdown transformer to 220 V. Problematic if the main generator, the electricity will be charged to the stand-by generator, the generator has two functions, namely diesel fuel and can also fuel natural gas stand-by generator with a capacity of 1.5 MW to 2.4 KV voltage generated, three phase.

before the stand-by generators take over the load first working emergency generator, it will take work before this generator is loaded generator is driven by solar. - Most welding operations performed manually with high labor costs proseas welding-most dangerous because of the use of energy types of welding processes welding can be divided into two groups - Melting-welding -solid-welding Melting welding process uses heat to melt the parent metal melting welding is done by heating the metal filler and part number. from the parent metal through melting with using electric arc heat source.

Вам также может понравиться