Академический Документы
Профессиональный Документы
Культура Документы
)
PROJECT : JUMEIRAH BEACH RESIDENCE - JBR 04 CHECK SHEET FOR IN-SITU REINFORCED CONCRETE SHEET No. SITE NO.: 583
H.E.E. LOCATION Item 1 Check falsework design and issue permit to load 2 Check quality of shutter lining for required finish 3 Check formwork ereceted and restrained as per approved drawings Checked Checked by by HEE QC E F GF E F F F E/MEP F E F F P.E./E.R. L F L E F P.E./E.R. F F Date
4 Check dimensions, line and level 5 Check preparation of forms inc. support, tie rods, release agents, cleanliness
6 Check plumbness and spacing props. 7 Check tightness of bolts and wedges 8 Check special built-in items, inserts, mechanical, electrical & plumbing embedments
9 Check stop-ends, waterbar, dowels, flexcell, etc. REINFORCEMENT 10 Check bar placement as per approved bar bending schedule
11 Check tie wires, spacers, cover 12 Clean out loose material (tie-wires, nails etc.) APPROVAL TO POUR PLACING CONCRETE 13 Check correct mix, slump, temp. 14 Check correct placing, compaction, grout loss control
15 Take concrete test cubes and log 16 Recheck line and level 17 Protection against weather condition APPROVAL TO STRIKE STRIKING FORMWORK 18 Check surface for blemishes 19 Check cleanliness of forms after striking
E-ENGINEER, F-FOREMAN, GF-GENERAL FOREMAN, MEP-MEP COORDINATOR, ER-ENGINEER'S REPRESENTATIVE, LLABORATORY TECHNICIAN
c:\mnj\222647875.xlsx.ms_office.xls
CO. (L.L.C.)
SITE NO.: 583 SHEET No.
Checked by A&BT
Date
GINEER'S REPRESENTATIVE, L-
c:\mnj\222647875.xlsx.ms_office.xls
H.E.E. LOCATION Item 1 Check falsework design and issue permit to load 2 Check quality of shutter lining for required finish 3 Check formwork ereceted and restrained as per approved drawings Checked Checked by by HEE QC E F GF E F F F E/MEP F E F F P.E./E.R. L F L E F P.E./E.R. F F Date
4 Check dimensions, line and level 5 Check preparation of forms inc. support, tie rods, release agents, cleanliness
6 Check plumbness and spacing props. 7 Check tightness of bolts and wedges 8 Check special built-in items, inserts, mechanical, electrical & plumbing embedments
9 Check stop-ends, waterbar, dowels, flexcell, etc. REINFORCEMENT 10 Check bar placement as per approved bar bending schedule
11 Check tie wires, spacers, cover 12 Clean out loose material (tie-wires, nails etc.) APPROVAL TO POUR PLACING CONCRETE 13 Check correct mix, slump, temp. 14 Check correct placing, compaction, grout loss control
15 Take concrete test cubes and log 16 Recheck line and level 17 Protection against weather condition APPROVAL TO STRIKE STRIKING FORMWORK 18 Check surface for blemishes 19 Check cleanliness of forms after striking
E-ENGINEER, F-FOREMAN, GF-GENERAL FOREMAN, MEP-MEP COORDINATOR, ER-ENGINEER'S REPRESENTATIVE, LLABORATORY TECHNICIAN
c:\mnj\222647875.xlsx.ms_office.xls
CO. (L.L.C.)
SITE NO.: 583 SHEET No.
Checked by A&BT
Date
GINEER'S REPRESENTATIVE, L-
c:\mnj\222647875.xlsx.ms_office.xls
QC/STR/1-583 Rev.01(Sept.2004)
H.E.E. LOCATION Item 1 Check falsework design and issue permit to load 2 Check quality of shutter lining for required finish 3 Check formwork ereceted and restrained as per approved drawings Checked by HEE E F GF E F F F E/MEP F E F F E/CR L F L E F E/CR F F Date Checked by A&BT Date
4 Check dimensions, line and level 5 Check preparation of forms inc. support, tie rods, release agents, cleanliness
6 Check plumbness and spacing props. 7 Check tightness of bolts and wedges 8 Check special built-in items, inserts, mechanical, electrical & plumbing embedments
9 Check stop-ends, waterbar, dowels, flexcell, etc. REINFORCEMENT 10 Check bar placement as per approved bar bending schedule
11 Check tie wires, spacers, cover 12 Clean out loose material (tie-wires, nails etc.) APPROVAL TO POUR PLACING CONCRETE 13 Check correct mix, slump, temp. 14 Check correct placing, compaction, grout loss control
15 Take concrete test cubes and log 16 Recheck line and level 17 Protection against weather condition APPROVAL TO STRIKE STRIKING FORMWORK 18 Check surface for blemishes 19 Check cleanliness of forms after striking
E-ENGINEER, F-FOREMAN, GF-GENERAL FOREMAN, MEP-MEP COORDINATOR, CR-CONSULTANT'S REPRESENTATIVE, L-LABORATORY TECHNICIAN
c:\mnj\222647875.xlsx.ms_office.xls
CHECK SHEET FOR IN-SITU REINFORCED CONCRETE SUSPENDEED SLAB Related I.R. ref.
SECTION OF WORK
LOCATION
CHECKED BY SUBCONTRACTOR / DATE CHECKED BY HMR / DATE CHECKED BY CONSULTANT / DATE
Stage
Item
1. Check falsework design and issue permit to load. Check formwork erected and restrained as per approved drawings. Check construction joints to conform approved shop 3. drawing. 2. 4. Check dimensions, line and level. 5. Check quality of shutter lining for required finish. FORMWORK (Before Concreting) 6. Check preparation of shutters including support, tie rods, release agents, cleanliness.
SE/PE SE/PE SE/PE SUE/PE SE/PE SE/PE SE/PE SE/PE SE/PE MEP / BK Gulf SO/PE SE/PE SE/PE SE/PE SE/PE QCE
LAB. TECH. / QCE LAB. TECH.
7. Check verticality and spacing of props. 8. Check tightness of bolts and wedges. Check end stoppers, waterbars, hyrib, flexcell sheet etc. Check embedded items, inserts and mechanical, 10. electrical and plumbing provisions. 9. 11. Check adequacy of working flatforms. 1. Check bar placement as per approved bar bending schedule.
2. Check tie wires, chairs,spacers, cover REINFORCEMENT 3. Check stop-ends, waterbar, dowels, flexcell, etc. 4. Clean out loose material (tie-wires, nails etc.) APPROVAL TO POUR 1. Check concrete mix, temperature and slump. 2. Take concrete test cubes,and log / record. PLACING OF CONCRETE 3. Check proper placing, concrete compaction and grout loose control.
4. Recheck line and level. 5. Provide protection against weather. APPROVAL TO STRIKE FORMWORK STRIKING OF FORMWORKS 1. Check concrete surface for blemishes. 2. Check cleanliness of forms after striking.
LAB TECH.-LABORATORY TECHNICIAN, SUE-SURVEY ENGINEER, SO-SAFETY OFFICER, SE-SITE ENGINEER, PEPROJECT ENGINEER, MEP COORD.-MEP COORDINATOR, QCE- QUALITY CONTROL ENGINEER
Rev. 01