Milestone List Project: Upgrade Works to WWTP at Keadue, Co. Roscommon Milestone Mandatory/Optional Commencement Date
Tendering Procurement Preliminaries Construction Testing Completion Mandatory Mandatory Mandatory Mandatory Mandatory Mandatory 01/03/2014 12/04/2014 06/05/2014 13/05/2014 25/05/2014 05/06/2014
Completion Date
22/04/2014 09/05/2014 06/05/2014 07/06/2014 26/05/2014 17/06/2014
Verification
Project Manager Project Manager Project Manager Site Engineer Site Engineer Client