Академический Документы
Профессиональный Документы
Культура Документы
Name:
Project
Name:
Code
1
1.1
1.2
1.3
1.4
Task Name
Tendering
Publish Project Details on E-Tenders
Expressions of Interest
Review Tender Pack
Preparation of BoQ
Start
Keadue, Co.
01/03/2014 17/06/2014
PROJECT SCHEDULE
Duration
52
30
23
7
7
Start
01/03/2014
01/03/2014
08/03/2014
01/04/2014
15/04/2014
Finish
22/04/2014
31/03/2014
31/03/2014
08/04/2014
22/04/2014
Total Project
Duration:
Total
Construction
Duration:
138
18.5
Predecessors
1.1
1.2
1.3
Cost
3,835.00
35.00
300.00
500.00
3,000.00
2.1.1
2.1.2
2.1.3
2.1.4
2.1.5
2.1.6
2.1.7
2.1.8
2.1.9
2 Procurement
2.1 Feasability
WWTP Selection
Site Layouts
Permits
Contractor Submissions
Material Submissions
Plant Submissions
Health & Safety Audits
Human resources
Procurement Completion
47
27
2
3
2
3
3
3
2
2
1
12/04/2014
12/04/2014
30/04/2014
02/05/2014
30/04/2014
12/04/2014
12/04/2014
12/04/2014
04/05/2014
06/05/2014
08/05/2014
09/05/2014
09/05/2014
02/05/2014
05/05/2014
02/05/2014
15/04/2014
15/04/2014
15/04/2014
06/05/2014
08/05/2014
09/05/2014
2.1.1
2.2.6
2.1.1
2.1.1
2.1.1
2.2.6
2.1.7
2.1.8
4,800.00
4,200.00
200.00
500.00
500.00
250.00
250.00
250.00
1,000.00
1,000.00
250.00
2.2.1
2.2.2
2.2.3
2.2.4
2.2.5
2.2.6
20
2
2
2
2
0
0
09/04/2014
09/04/2014
09/04/2014
09/04/2014
09/04/2014
22/04/2014
29/04/2014
29/04/2014
11/04/2014
11/04/2014
11/04/2014
11/04/2014
22/04/2014
29/04/2014
1.2
1.2
1.2
1.2
1.3
2.2.5
600.00
100.00
100.00
100.00
100.00
100.00
100.00
3 Preliminaries
3.1 Insurance
3.2 Employers' Liability Insurance
0.5
0.5
0.5
06/05/2014 06/05/2014
06/05/2014 06/05/2014
06/05/2014 06/05/2014
2.2.6
2.2.6
8,000.00
6,000.00
2,000.00
4 Construction
4.1 Commencing on Site
Site Office
Office Equipment
25
0.5
3.1
3.1
188,140.00
1,500.00
1,000.00
500.00
4.1.1
4.1.2
13/05/2014
13/05/2014
0.5 13/05/2014
0.5 13/05/2014
07/06/2014
14/05/2014
14/05/2014
14/05/2014
4.2.1
4.2.2
4.2.3
4.2.4
4.2.5
4.2.6
4.2 Mobilisation
Traffic Management
Site Safety Induction
Road Brushing
Site Clearing Plant & Equipment
Excavation Equipment
Paving Equipment
1
1
1
1
1
1
1
13/05/2014
13/05/2014
13/05/2014
13/05/2014
13/05/2014
13/05/2014
13/05/2014
14/05/2014
14/05/2014
14/05/2014
14/05/2014
14/05/2014
14/05/2014
14/05/2014
3.1
3.1
3.1
3.1
3.1
3.1
1,200.00
200.00
200.00
200.00
200.00
200.00
200.00
4.3.1
4.3.2
4.3.3
4.3.4
1
1
1
1
1
13/05/2014
13/05/2014
13/05/2014
13/05/2014
13/05/2014
14/05/2014
14/05/2014
14/05/2014
14/05/2014
14/05/2014
3.1
3.1
3.1
3.1
1,900.00
500.00
200.00
200.00
1,000.00
4.4.1
4.4.2
4.4.3
4.4.4
4.4.5
4.4.6
3
1
1
1
1
1
1
15/05/2014
15/05/2014
15/05/2014
15/05/2014
15/05/2014
16/05/2014
17/05/2014
18/05/2014
16/05/2014
16/05/2014
16/05/2014
16/05/2014
17/05/2014
18/05/2014
4.4.1
4.4.2
4.4.3
4.4.4
4.4.5
5,500.00
1,000.00
1,000.00
200.00
1,000.00
300.00
2,000.00
4.5.1
4.5.2
4.5.3
4.5.4
4.5.5
4.5.6
4.5.7
4.5.8
4.5.9
4.5.10
4.5.11
15.5
1
2
1
4
4
19/05/2014
19/05/2014
20/05/2014
22/05/2014
24/05/2014
29/05/2014
13/06/2014
20/05/2014
22/05/2014
23/05/2014
28/05/2014
02/06/2014
4.4.6
4.5.1
4.5.2
4.5.3
4.5.4
40,200.00
200.00
1,000.00
4,000.00
8,000.00
12,000.00
3
7
03/06/2014
06/06/2014
06/06/2014
13/06/2014
4.5.5
4.5.7
1,500.00
9,500.00
0.5
5
28/05/2014
30/05/2014
29/05/2014
04/06/2014
4.5.4
4.5.5
1,000.00
3,000.00
17.5
0
15/05/2014
06/06/2014
4.6.1
4.6.1.1
4.6.1.2
4.6.1.3
4.6.1.4
82,890.00
4.6.1.5
4.6.1.6
4.6.1.7
4.6.1.8
4.6.2
4.6.2.1
Primary
Claifer
4.6.3
4.6.3.1
4.6.3.2
4.6.3.3
Secoundary
Aerator
Claifer
Chemical
4.6.4
4.6.4.1
Teritary
Inspection of Reed Beds
1
1
15/05/2014
15/05/2014
4.6.5
4.6.5.1
4.6.5.2
4.6.5.3
Storm Tank
Preparation of Sub-base
Pouring Concrete Base
Tank Installation
5
1
1
1
20/05/2014 25/05/2014
20/05/2014 21/05/2014
21/05/2014 22/05/2014
24/05/2014 25/05/2014
4.6.6
4.6.6.1
4.6.6.2
4.6.6.3
4.6.6.4
4.6.6.5
4.6.6.6
4.6.6.7
4.6.6.8
4.6.6.9
Package System
Excavate for Sub-base
Place Hardcore Sub-base
Erect Formwork
Place Reinforcement
Pour Concrete Sub-Base
Strike Formwork
Install BMS units
Connect new infrasturcture
Commission
12.5
1
1
1
1
1
0.5
3
1
2
20/05/2014
20/05/2014
20/05/2014
21/05/2014
22/05/2014
23/05/2014
26/05/2014
28/05/2014
30/05/2014
31/05/2014
4.6.7
4.6.7.1
4.6.7.2
4.6.7.3
4.6.7.4
4.6.7.5
Reinstatement
Placing Concrete Kerbs
Pedestrian Paths
Replacing Top Soil
Seeding
Bitumen layer to Road
4
2
3
2
0.5
1
01/06/2014
01/06/2014
01/06/2014
04/06/2014
06/06/2014
04/06/2014
4.7.1
4.7.2
9
1
2
16/05/2014
16/05/2014
4.4.6
500.00
500.00
4.6.5.1
4.6.5.2
2,700.00
200.00
2,000.00
500.00
02/06/2014
21/05/2014
21/05/2014
22/05/2014
23/05/2014
24/05/2014
27/05/2014
31/05/2014
31/05/2014
02/06/2014
4.6.6.1
4.6.6.2
4.6.6.3
4.6.6.4
4.6.6.5
4.6.6.6
4.6.6.7
4.6.6.8
6,700.00
250.00
250.00
300.00
100.00
2,500.00
100.00
1,000.00
1,000.00
1,200.00
06/06/2014
03/06/2014
04/06/2014
06/06/2014
06/06/2014
05/06/2014
4.6.6.9
4.6.6.9
4.6.7.1
4.6.7.3
4.6.7.2
18,040.00
1,540.00
3,000.00
1,500.00
0.00
12,000.00
4.7.1
2,450.00
50.00
500.00
19/05/2014 28/05/2014
19/05/2014 20/05/2014
19/05/2014 21/05/2014
4.7.3
4.7.4
4.7.5
4.7.6
4.7.7
4.8.1
4.8.2
4.8.3
4.8.4
4.8.5
4.8.6
4.8.7
4.8.8
4.8.9
4.9.1
4.9.2
4.10.1
4.10.2
4.10.3
4.10.4
Testing
Air Testing Sewer Network
Testing BMS Unit
Testing Pump
6
6.1
6.2
6.3
6.4
6.5
6.6
Completion
Final Inspection
Condition Survey of Roads and Paths
CCTV Survey of Pipework
Demobilisation of Site
As Constructed Drawings
Safety File Handover
1
2
1
2
1
21/05/2014
22/05/2014
24/05/2014
25/05/2014
27/05/2014
22/05/2014
24/05/2014
25/05/2014
27/05/2014
28/05/2014
4.7.2
4.7.3
4.7.4
4.7.5
4.7.6
300.00
500.00
300.00
500.00
300.00
6
0.5
0.5
1
0.5
0.5
1
1
1
1
19/05/2014
19/05/2014
19/05/2014
20/05/2014
21/05/2014
21/05/2014
23/05/2014
23/05/2014
24/05/2014
24/05/2014
25/05/2014
20/05/2014
20/05/2014
21/05/2014
21/05/2014
21/05/2014
24/05/2014
24/05/2014
25/05/2014
25/05/2014
4.6.6.9
4.8.1
4.8.2
4.8.3
4.8.4
4.8.5
4.8.6
4.8.7
4.8.8
400.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
200.00
200.00
5
5
5
29/05/2014
29/05/2014
29/05/2014
03/06/2014
03/06/2014
03/06/2014
4.8.9
4.9.1
18,000.00
10,000.00
8,000.00
3
3
3
5
04/06/2014
04/06/2014
04/06/2014
18/05/2014
07/06/2014
07/06/2014
07/06/2014
23/05/2014
4.9.2
4.9.2
4.4.6
34,100.00
7,000.00
1,100.00
26,000.00
1
1
1
1
25/05/2014
25/05/2014
31/05/2014
25/05/2014
26/05/2014
26/05/2014
01/06/2014
26/05/2014
4.8.9
4.8.9
4.8.9
450.00
150.00
150.00
150.00
12.5
1
1
1
0.5
3
10
05/06/2014
05/06/2014
05/06/2014
06/06/2014
07/06/2014
12/06/2014
17/06/2014
17/06/2014
06/06/2014
06/06/2014
07/06/2014
07/06/2014
15/06/2014
17/06/2014
5.3
5.3
5.3
6.1
6.3
6.5
2,350.00
200.00
100.00
350.00
1,000.00
500.00
200.00