Вы находитесь на странице: 1из 19

2/1/2013

1
CIVE 585, CIVE 685, ENMG 698 Construction Planning & Scheduling
Instructor: Farook Hamzeh, Ph.D.
2- Critical Path Method
Overview

CPM History
CPM Methodology
Network calculations
Forward Pass
Backward Pass
Float
Time-Scaled Network Diagrams
2/1/2013
2
CPM History
The Critical Path Method (CPM) emerged in
the mid-1950s.
US Navy- Polaris Missile System
DuPont & Remington Rand


Benefits of
Scheduling & Evaluation
Without some kind of periodic and consistent
measurement system--it's close to impossible to
make critical judgments with confidence that the
facts are in hand.
Better decision making
Better resource management
Better time management
2/1/2013
3
Managing Small Projects
And Why Scheduling Still Matters
Multiple projects to manage
Higher risk
Limited resources
Short duration
Overtime?
Activity Priority

Requested Project Duration
Estimated Project Duration
Q: How long will it take?
We often neglect consideration of such factors as:

Mobilization
Paper Work
Material and Equipment Deliveries
Subcontractors Availability
A: We can handle it Attitude:
We typically respond with the time we think
it would take us to do the work, when
actually it will be done by others.
The Most Common Q&A:
2/1/2013
4
The Benefits: Decision Making
The Benefits: Decision Making
2/1/2013
5
The Benefits: Resource Management
The Benefits: Multi Project Management
2/1/2013
6
Advantages
Shows the Construction Logic
Identifies the Critical Activities (80 20 Rule)
Allows Management to set Priorities
Shows the Effects of a Change Order or Delay
Is Self-adjusting when updated
Easy to Follow Visually See the Big Picture
Potentially it is the most effective scheduling system
Helps to Analyze Different Methods or Sequences
Useful for Court Cases Keeps You Out of Court
Serves as a Basis for Systems Control
Forces the Management Team to Plan and Think in Detail
Communicates the Process to Every Team Member
Promotes Teamwork

Disadvantages
Can Become Complex - It is the Most
Sophisticated Scheduling System
Requires Training to Become an Effective User
Due to Not Fully Understanding CPM and Its
Complexity, It is Often Abandoned
8
8
2/1/2013
7
Network
Activity on Node (AON)
Activity
A

Activity
B

Relationship
Successor Predecessor
Critical Path Method (CPM)
Provides a timetable for performing the tasks which comprise
a project
Acts as a tool for examining activity relationships and resource
utilization
Supplies data for reports and graphics that aid in decision
making
The longest continuous path of activities through a project
determines the project end date.
A delay in a critical activity delays other activities and the
project as a whole

2/1/2013
8
A CPM Network
Name
ES EF
LS LF
TF FF
Duration
(TF, FF, IF, INDF)
Construction Flow Chart
Shows Preceding Activities
Shows Succeeding Activities
Shows Concurrent Activities
Shows the Critical Path Activities
Shows the Amount of Float
2/1/2013
9
How to Create a CPM Schedule
Review the Plans and Specifications
Get the Project into Your Head
Brain Storm the Project with the Project Team
Make Sure the Project Manager and
Supervisors are involved Check with the
Estimator
Discuss the Overall Job Approach
Discuss Problem Areas Anticipated
Any Special Conditions or Features?
Steps to Create A CPM Schedule
1) Breakdown the project into activities
2) Construct the Logic Diagram
3) Add the Durations
4) Calculate the Early Dates (forward pass)
5) Calculate the Late Dates (backward pass)
6) Calculate the Total Float
7) Mark the Critical Path
2/1/2013
10
Break the Project into Activities
Could use a Work Breakdown Structure (WBS)
Keep trades and contractual divisions separate
May even want to separate crews
Keep field work separate from shop or office work
Determine the level of Detail
Include submittal process?
Include procurement of material?
Include curing time for concrete?

Break the Project into Activities
Could Use a Work
Breakdown Structure
WBS example:
1. Preconstruction Phase
1.1 Obtain Permits
1.2 Obtain Bonds
1.3 Obtain Insurance
2. Engineering Phase
2.1 Shop drawings
2.2 Review shop drawings
2.3 Fabrication
3. Job Mobilization Phase
3.1 Set up field office
3.1.1Locate Job Office Trailer
3.1.2 Construct Project Bulletin Board
3.1.3 Construct Deck and Roof Cover
3.2 Install temporary Power
3.3 Set up security Fence
3.4 Telephone Hookup
2/1/2013
11
Make Sure the Logic is Correct
Review Logic Diagram with ALL Team
Members
Ask question #1 of every activity - Does this
activity really have to be done before each of
the following activities can start?
Ask question #2 What other activities need
to be done before this activity can start?
How Do You Determine the Durations of
the Scheduled Activities?
From Subs
Estimating or Productivity Manuals
Company Records of Productivity Rates
Flat out Guess

What was it we were trying to manage?
Add the Durations to the Logic Diagram
2/1/2013
12
Exercise
Activity
Immediate
Predecessor Duration
A H 2
B C 4
C H 1
D A,C 3
E A 1
F B 4
G E,D 2
H ~ 0
I F,G 0
Activity On Node Notation (typical)
ES = Early Start
EF = Early Finish
LS = Late Start
LF = Late Finish
TF = Total Float
FF = Free Float
Name
ES EF
LS LF
TF FF
Duration
2/1/2013
13
CPM -Definitions
Activity: The performance of a task required to complete
the project, such as, design of foundations, review of design,
procure steel contracts, or form concrete columns. An
activity requires time, cost, or both time and cost.
Duration (D): estimated time required to perform an
activity.
Early Start (ES): earliest time an activity can be started.
Early Finish (EF): earliest time an activity can be finished.
Equal to the early start plus the duration.
EF=ES+D
Late Finish (LF): latest time an activity can be finished.
Late Start (LS): latest time an activity can be started without
delaying the projects completion date.
LS=LF-D
Early Start Calculation (Forward Pass)
ES = MAX {EF
predecessors
}
A
B
C
D
EF=2
EF=6
EF=4
ES= 6
Name
ES EF
LS LF
TF FF
Duration
2/1/2013
14
Early Finish Calculation (Forward Pass)
EF = ES + Activity Duration

Framing
ES = 3 EF =
LS LF
TF FF
6
9
Late Finish Calculation (Backward Pass)
Successors
B
C
D
7
LF=
10
7
LS=
LS=
LF = MINIMUM {LS
successors
}
2/1/2013
15
Late Start Calculation (Backward Pass)
Set Anchor Bolts
ES EF
4
LS= LF=16 12
LS = LF - Activity Duration

Total Float (TF): the amount of time an activity may be delayed
without delaying the projects completion date.
TF=LF-EF=LS-ES
Free Float (FF): amount of time an activity may be delayed
without delaying the ES time of the following activity or the
projects completion date .
EF
i
=ES
j
-EF
i
,where the subscript i represents the preceding
activity and the subscript j represents the following activity.
Critical Path: a series of interconnected activities through the
network diagram, with each activity having zero, free and total
float time. The critical path determines the minimum time to
complete the project.
CPM -Definitions
2/1/2013
16
Total Float
0
LF EF ES
TF
TF = LS ES

TF = LF - EF
LS
3 7 10
TF
Total Float
TF = LS ES
TF = LF EF

Activity
3
5
6
8 14
9
TF =
2/1/2013
17
Free Float
Minimum
ES of all
Successors
ES
FF
EF
FF = MIN {ES successors} EF activity

Free Float
FF = MIN {ES successors} EF activity

B
C
D
EF=
1
10
11
12
FF = Min{11,12} 10
= 1
FF=
2/1/2013
18
Time-scaled Network
From: Verzuh, E., (1999). The Fast Forward MBA in Project Management. John Wiley & Sons, Inc., New York, NY.
Types of Float
2/1/2013
19
Calculating Interfering & Independent Float
Managing the Float
Which Type of Float Would You Share with
Subs?
Using Float to Hide Days in the Schedule
Sharing Shared Float in Order to Make the
Schedule More Manageable
Use the Float to Manage Resources

Вам также может понравиться