Академический Документы
Профессиональный Документы
Культура Документы
We would like to express our sincere gratitude and appreciation to Professor Amrit
Man Nakarmi for giving us an opportunity to do project work on financial and
economical analysis of a project.
We studied feasibility study of different MHP project collected in Pulchowk campus
library that helped us understand the purpose of financial and economic analysis and
interpret result more clearly. Thanks goes to reference section of library for providing
full access to us.
We would like to thank Mr Nawaraj Bhattrai, Deputy Director of Center for energy
studies, for providing us related information regarding the current situation of MHP.
On the basis of information provided by him we were able to perform the study.
Executive Summary
From the study of different MHP report it is easily understood that one of the major
problem among other is the running of MHP under low load factor.
In this small project work study of the effect of plant load factor was done and its
impact on economic and financial parameters was analyzed. For case study we have
used hypothetical data but it is similar one to that of a typical micro hydropower plant.
. Initially a MHP running with a low plant factor of only 0.25 is assumed. At this low
plant factor it has ENPV for life of 15 years is calculated as Rs 34601. EIRR is
10.08%. Benefit/cost ratio is 1.01. Again for a good design plant factor is assumed to
be above 0.4 initial year and above 0.6 in later years. For study purpose financial and
economic analysis was done assuming initial plant factor is 0.4 and it increases 4%
per annum.
Table of Contents
Table of Contents.........................................................................................................3
INTRODUCTION........................................................................................................4
1.1 Introduction..........................................................................................................4
1.2 Objectives.............................................................................................................4
1.3 Methodology........................................................................................................5
Hypothetical MHP.......................................................................................................6
2.1 Hypothetical Technical details.............................................................................6
2.2 Major components of Micro Hydro.....................................................................6
2.3Financial and economical analysis of MH project................................................6
FINANCIAL ANALYSIS............................................................................................8
3.1 Net Present Worth (NPW) Criterion....................................................................8
3.2Annual Equivalent.................................................................................................9
3.3Internal Rate of Return (IRR)................................................................................9
3.4Unit energy cost....................................................................................................9
3.5Benefit Cost ratio..................................................................................................9
3.6Subsidy policy of AEPC in MHP........................................................................10
3.7Assumptions for economic and financial analysis..............................................10
RESULT......................................................................................................................11
4.1 Total revenue......................................................................................................11
4.2 Annual cost.........................................................................................................11
4.3 Financial analysis without subsidy.....................................................................12
4.4 Financial analysis with subsidy..........................................................................13
4.5 Economic benefit................................................................................................14
4.6 Economic analysis without subsidy...................................................................15
4.7 Economic Analysis with subsidy.......................................................................17
4.8 Unit cost calculation...........................................................................................18
References...................................................................................................................21
CHAPTER ONE
INTRODUCTION
1.1 Introduction
In Nepal, there is large potential of electricity from Micro hydro. Although there is
large potential, demand of electricity is low in rural areas. In rural areas electricity is
used mainly for lighting in evenings and night. There are possibilities for end use but
not in operation in many areas. The end use application can made Micro Hydro
Projects financially and economically viable.
In this project work, financial and economical analysis of a hypothetical MHP is done
by considering a plant factor of 0.25 only. The project is financially infeasible. Taking
economic benefits from saving of dry cell batteries for electric appliances and
kerosene for lighting, heating and cooking only make the project feasible.
A good design will aim for a predicted plant factors of above 0.4 even in the first
years after installation and above 0.6 in later years. (Harvey, 1993) In this small
project work, financial and economic analysis was done assuming initial plant factor
is 0.4 (it means demand is 40% of total capacity) and it increases 4% per annum. The
analysis was done based on these assumptions.
1.2 Objectives
Main objective is
To compare calculated analysis with initial conditions having only plant factor
0.25
4
To study effect on financial and economic analysis due to plant load factor
1.3 Methodology
The following method was used for analysis
Literature review of few Micro Hydro and economic analysis were done.
All costs are assumed to increase by different inflation factors. As the analysis
was done for present inflation of 5 years was taken approximately.
Financial and economic analysis was done with subsidy and without subsidy.
CHAPTER TWO
Hypothetical MHP
24kW
Design flow
82 lps
Gross Head
58.50m
Turbine type
Pelton
CHAPTER THREE
FINANCIAL ANALYSIS
Determine the interest rate that the firm wishes to earn in its investments. This
interest rate is called as Minimum Attractive Rate of Return (MARR).
Estimate the cash inflow for each period over the service life,
Find the present worth of each net cash flow at the MARR. Add up these
present worth figures, their sum is defined as the projects NPW.
PW (i) = An/ (1+i) n
Where PW (i) = NPW calculated at i
An= Net cash flow at the end of period n
i=MARR
n= Project life
A positive NPW means that the equivalent worth of the inflow is greater than
the equivalent worth of the outflows. This means the project makes a profit.
If PW (i)>0, accept the investment.
3.2Annual Equivalent
Annual equivalent worth (AE) criterion provides a basis for measuring investment
worth by determining equal payments on an annual basis. Knowing that net present
worth, annual equivalent can be calculated by multiplying amount by the capital
recovery factor.
If AE (i)>0, accept the investment.
If AE (i) =0, remain indifferent
If AE (i) <0, reject the investment.
Three staffs one manager and two operators are sufficient to manage plant.
The salary of manager is Rs 5000/month and increases Rs 250/month in a
year. The operators salary is Rs 3500/month and increases Rs 200/month in
every year.
Replacement cost for wooden poles occur each 5 years. The price increases by
5% in next period.
10
CHAPTER FOUR
RESULT
4.1 Total revenue
For total revenue, cost of 1 kWh is taken as Rs 5.Initially plant factor is taken as 0.4.
Initially demand is taken as 84096 units. The demand is assumed to increase 4% per
annum.
Energy
demand (in
kWh)
Year
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
84096
87460
90958
94597
98380
102316
106408
110665
115091
119695
124483
129462
134640
140026
145627
Revenue
(in Rs)
420480
437299
454791
472983
491902
511578
532041
553323
575456
598474
622413
647310
673202
700130
728135
Year
0
1
2
Manager
60000
63000
operato
r1
42000
44400
operato
r2
42000
44400
Total
salary
144000
151800
Office
expenses
5000
5200
Miscellan
eous
4000
4160
Operation
and
Maintainen
ce cost
Replace
ment
cost
72726
72726
Total Annual
cost (in Rs)
225726
233886
11
3
4
5
6
7
8
9
10
11
12
13
14
15
66000
69000
72000
75000
78000
81000
84000
87000
90000
93000
96000
99000
102000
46800
49200
51600
54000
56400
58800
61200
63600
66000
68400
70800
73200
75600
46800
49200
51600
54000
56400
58800
61200
63600
66000
68400
70800
73200
75600
159600
167400
175200
183000
190800
198600
206400
214200
222000
229800
237600
245400
253200
5408
5624
5849
6083
6327
6580
6843
7117
7401
7697
8005
8325
8658
4326
4499
4679
4867
5061
5264
5474
5693
5921
6158
6404
6660
6927
72726
72726
72726
72726
72726
72726
72726
72726
72726
72726
72726
72726
72726
23520
24696
25931
Total
Total
Net
Net cash flow
revenue cost
Depreciation profit
(Rs)
363630
0
-3636300
420480 225726
242420 -47666
194754
437299 233886
242420 -39007
203413
454791 242060
242420 -29689
212731
472983 250250
242420 -19687
222733
491902 281975
242420 -32493
209927
511578 266676
242420
2482
244902
532041 274914
242420 14707
257127
553323 283169
242420 27734
270154
575456 291443
242420 41593
284013
598474 324432
242420 31622
274042
622413 308048
242420 71945
314365
647310 316381
242420 88509
330929
10604
673202 324735
242420
7
348467
12459
700130 333112
242420
8
367018
11827
728135 367442
242420
3
360693
NPV of cash flows from year 1 to 10
NPV
AE (10%)
Rs1,909,346.02
(Rs1,726,953.98)
(Rs227,049.16)
12
242060
250250
281975
266676
274914
283169
291443
324432
308048
316381
324735
333112
367442
IRR
1.365%
10
11
12
13
14
15
-1000000
-1500000
-2000000
-2500000
-3000000
-3500000
-4000000
Year
NPV value is negative. This shows project is financially infeasible. IRR is very low.
The project is not self-sustaining.
Year
0
1
2
3
4
5
6
7
8
9
Total
Total
Net
revenue cost
Depreciation profit
Net cash flow (Rs)
159630
0
-1596300
420480 225726
106420 88334
194754
437299 233886
106420 96993
203413
454791 242060
106420 106311
212731
472983 250250
106420 116313
222733
491902 281975
106420 103507
209927
511578 266676
106420 138482
244902
532041 274914
106420 150707
257127
553323 283169
106420 163734
270154
575456 291443
106420 177593
284013
13
10
11
12
13
14
15
598474
622413
647310
673202
700130
728135
324432
308048
316381
324735
333112
367442
106420
106420
106420
106420
106420
106420
167622
207945
224509
242047
260598
254273
274042
314365
330929
348467
367018
360693
Rs1,909,346.02
Rs313,046.02
Rs41,157.34
IRR
12.899%
10 11 12 13 14 15
-500000
-1000000
-1500000
-2000000
14
Quantity
saved
Price
Year
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
6194
6194
6194
6194
6194
6194
6194
6194
6194
6194
6194
6194
6194
6194
6194
Total
Annual cost
(in Rs)
Quantity
saved
Price
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
8532
8532
8532
8532
8532
8532
8532
8532
8532
8532
8532
8532
8532
8532
8532
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
665462
665462
665462
665462
665462
665462
665462
665462
665462
665462
665462
665462
665462
665462
665462
420480
225726
242420
-47666
437299
233886
242420
-39007
454791
242060
242420
-29689
472983
250250
242420
-19687
491902
281975
242420
-32493
511578
266676
242420
2482
532041
274914
242420
14707
553323
283169
242420
27734
9
10
575456
598474
291443
324432
242420
242420
41593
31622
860250
868909
878227
888229
875423
910398
922623
935650
949509
939538
15
11
622413
308048
242420
71945
12
647310
316381
242420
13
673202
324735
242420
14
700130
333112
242420
15
728135
367442
242420
88509
10604
7
12459
8
11827
3
2
66546
2
66546
2
66546
2
66546
2
66546
2
979861
996425
1013963
1032514
1026189
Rs6,971,161.51
Rs3,334,861.51
Rs438,446.84
EIRR
23.616%
Total cost
Total benefit
5713584
9048446
B/C ratio
1.58
10
11
12
13
14
-1000000
-2000000
-3000000
-4000000
Year
16
15
$6,971,161.51
$5,374,861.51
$706,653.34
EIRR
54.826%
Total cost
Total benefit
3673584
9048446
B/C ratio
2.46
17
10 11 12 13 14 15
-1000000
-1500000
-2000000
Year
Year
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
84096
87460
90958
94597
98380
102316
106408
110665
115091
119695
124483
129462
134640
140026
145627
annual
cost
84,096
87,460
90,958
94,597
98,380
102,316
106,408
110,665
115,091
119,695
124,483
129,462
134,640
140,026
145,627
Total Annual
cost (in Rs)
with subsidy
1596300
225726
233886
242060
250250
281975
266676
274914
283169
291443
324432
308048
316381
324735
333112
367442
18
2,077,284
1,596,300
3,673,584
2,077,284
3,636,300
5,713,584
Total cost
Unit cost with subsidy
Unit cost without subsidy
797326.01
4.61
7.17
Unit cost with subsidy is Rs 4.61. Unit cost without subsidy is Rs 7.17. With subsidy
it is less than selling price per unit. Without subsidy, it is little high. Without subsidy
also unit cost is less than that of Nepal Electricity Authority.
19
CHAPTER FIVE
End use applications in micro hydro increase revenues but total cost remains
same. It also reduces cost of electricity per unit.
20
References
http://www.aepcnepal.org
21