Вы находитесь на странице: 1из 3

Page 1 of 3

Panipat Elevated Expressway Project

Diptimoy Datta, Senior DGM (Bridges), ECC Division L&T, New Delhi

Panipat, the war city of India situated at 90 km from National capital, Delhi, has a glorious past
in the Indian history. It is said that at the time of battle of Mahabharat one of the five villages
which were demanded by the pandavas was "Panpat” which was later on renamed as Panipat.
Three major battles were fought at this place in 1526, 1556 and 1761. Panipat is famous in
India by the name of “City of Weaver.” Panipat district has significant place in international
market for “Handloom products.” It is also the biggest centre for shoddy yarn in the world.

National Highway No. 1 connecting Delhi-Panipat-Ambala-Amritsar and going upto Indo/Pak


border is a very important National highway and connects northern part of the country including

states of Jammu and Kashmir, Punjab, Himachal Pradesh and Haryana with Delhi and rest of
the country. In eventuality of war, this road also serves as a vital link to Wagha border area as
Delhi Cantonment, Ambala Cantonment and Jalandhar Cantonment are situated along side
this road. As a result traffic intensity on the road is very high. The project section through
Panipat is a serious bottleneck to the speedy, smooth and safe flow of traffic mainly on account
of congested ypes of traffic due to Panipat being an industrial city.

The Panipat Elevated Expressway Project (PEEP) has come up in the heart of Panipat. The
entire stretch between km 86.000 & 96.000 has been been developed to a 6 lane access
control highway with elevated 6 lane structure from 88560 to 92160. This 3.6 km flyover is the
longest 6 lane flyover in India till date. This Built Operate and Transfer (BoT) project has been
executed by L&T Panipat Elevated Corridor Limited (L&T PECL). National Highways Authority
of India (NHAI), New Delhi has alloted a 20 year concession to PEEP to finance, design, built,
operate and maintain this new bridge. It is the first BoT project completed 6 months ahead of
schedule.

Project Details

 Access controlled 6 lane highway in the reach km 86.000 to km 96.000.


 Separate 2 lane peripheral road with paved shoulder on either side of access controlled
6 lane highway for the local Panipat traffic.
 Three Underpasses to accommodate 4 lane divided carriageway.
 Construction of 2 New minor Bridges @ Ch: 91.400 & Ch: 96.000.
 Widening / construction /reconstruction of culverts, drains, ducts for services etc.
 Other miscellaneous provisions like Toll Plaza, lighting at Toll Plaza, street lighting, road
furniture, road markings, signalized junctions etc.

Elevated Portion
Page 2 of 3

The 3.6 Km long flyover is the longest 6 lane flyover in India, built by utilizing state of art
technology. The foundation of this bridge consists of 1282 piles done by rotary rig method over
which pile caps and piers have been built upon. I-Girders have been pre–cast at the base
camp and transported to site in specially modified trailers, where the erection work has been
completed using Gantries and high capacity cranes.

For the first time in India, precast deck slabs have been used as a load bearing member in
combination with cast-in-situ. This has most efficiently led to time and cost reduction for
completion of the project. Photographs 1 & 2.

Pavement

The project also included widening of roads from 4 lanes to 10 lanes in the project area.
Throughout the stretch flexible road has been provided apart from Toll Plaza where rigid
pavement has been constructed. The minimum crust thickness for the entire stretch is 695
mm.

Underpasses

In order to provide interconnectivity to peripheral road on either side of the access controlled
main carriageway three underpasses have been provided at Ch: 87.365, Ch:91900 and
Ch:93.600 with a maximum length of 850 mts. These Underpasses have a minimum vertical
clearance of 5.5m with 20m effective span to accommodate 4 lane divided carriageway with
median and 1.5m footpath on either side.

Cross Drainage Works

A total of 10 culverts (7-box, 2-pipe & 1-slab) have been constructed and widened in the
project stretch. The cross drainage works also includes construction of 2 minor bridges at ch:
91.400 & 96.000.

Street lighting

For lighting purpose twisted decorative poles with bird wings have been imported from
malaysia, which gives an added lure to the project. These poles have been used for the first
time in this part of the country.

Toll Plaza

A 20-lane Toll Plaza has been constructed at Ch: 94775 with all the modern facilities imported
from European Countries. It has the provision of smart cards for local vehicles as well as
provision for automatic classification of vehicles. Proper and adequate lighting as well as
Safety measures have been ensured at this location. Rigid Pavement (Pavement Quality
concrete) has been done in Toll Plaza area from Ch: 94775 to Ch: 95118. Photograph 4.

Landscaping

Landscape treatment of the project section has been undertaken through planting of trees and
ground cover of appropriate varieties.

Shrubs of low height have been planted in the median of the project section.

Project Achievements

It is India’s first BoT project to be completed well ahead of schedule and the credit for the early
completion goes to:

i) Utility Shifting
Page 3 of 3

Major Utility Shifting was done on riority basis which has resulted in achieving the progress
without major hindrances at site.

ii) Traffic Management at site

The biggest hurdle for the project was management of traffic at site. As mentioned, Panipat is
an industrial city located on the busy NH-1. So, there is a vast mix of traffic ranging from
bullock carts and cycle rickshaws to heavy industrial vehicles. Hence, it was compulsory to
have a well developed traffic management plan so as to work smoothly as well as smooth
passage of vehicles. Traffic Management at this site has been one of our biggest achievement
and we have been able to achieve proper and safe movement of traffic as well as applaud from
local public and administration. A survey carried out during construction period even indicated
that the average speed of Vehicles in the project stretch increased in comparison to the speed
before start of the project.

iii) Precast Deck Planks

For the first time in India, precast deck slabs have been used as a load bearing members in
combination with cast-in-situ. This has most efficiently led to early completion of the project.

iv.) Precast Girder & Parapet

Precast Girders & Parapet have been used for reducing the duration of superstructure
completion which has led to time saving for the project.

Project Significance

This project has given relieve to the commuters passing through the stretch as well as people
of Panipat from the endless traffic jams and will usher in an era of growth and prosperity. As
mentioned it is the most critical stretch in this section and it used to take up to an hour for
crossing this stretch before construction of this flyover. Trade and commerce will also touch
new high with faster transportation of goods and services.

It is indeed a great example set by India’s largest engineering and construction organization in
completing this landmark BoT project well ahead of schedule. This remarkable and rare feat
has been achieved only due to proper planning of the job and advanced construction
techniques utilized by L&T. Once again L&T has proved that it has the capabilities and
commitment to make enduring contribution to roads, highways and bridges-the lifelines of
nation.

Вам также может понравиться