Pre-Test for XL

Phase III -- BTS3900 Testing


S12/12/12 Power Consumption & TOC with High Traffic





Huawei Technologies Co., Ltd.
All rights reserved
26
th
-May, 2009

BTS3900 S12/12/12 Power Consumption & TOC with High Traffic


2009-5-26 All Rights Reserved by Huawei 2

1. Target of the Phase III Testing

Before lock other cells:
BTS3900 S12/12/12 Power Consumption & TOC with High Traffic

After lock other cells:
BTS3900 S12/12/12 Power Consumption & TOC with High Traffic


2. Test Scenario

1> The target cells info













BTS3900 S12/12/12 Power Consumption & TOC with High Traffic


2009-5-26 All Rights Reserved by Huawei 3


The names of target cells (TRX of BCCH and TCH) which to be shutdown are as
following:
4675_Selindung-8
4676_PangklBalam-8
4676_PangklBalam-9
1817L1_PklBalam2-5
1817L1_PklBalam2-6
4655_PangkalPng-1
5812_PngklPinang2-4
4674_KacangPdg-7
1816L1_KcngPdg2-4
4132_TuaTunu-4

The Traffic of other cells above will be moved to the Gabek Site cells.
4154_GabekGreenBTS(1800)-1
4154_GabekGreenBTS(1800)-2
4154_GabekGreenBTS(1800)-3
4154_GabekGreenBTS-1
4154_GabekGreenBTS-2
4154_GabekGreenBTS-3

2> Busy Hour in Gabek Site.
20:00 to 22:00

3. Test steps

1> Observe the traffic of the target cells and capture their statement before
lock other cells around Gabek Site.














BTS3900 S12/12/12 Power Consumption & TOC with High Traffic


2009-5-26 All Rights Reserved by Huawei 4


Sector name Traffic Time Capture
4675_Selindung-8 25% 20:36
4676_PangklBalam-8 42% 20:37
4676_PangklBalam-9 30% 20:37
1817L1_PklBalam2-5 67% 20:35
1817L1_PklBalam2-6 42% 20:35
4655_PangkalPng-1 87% 20:36
5812_PngklPinang2-4 74% 20:39
4674_KacangPdg-7 36% 20:38
1816L1_KcngPdg2-4 100% 20:35
4132_TuaTunu-4 - -
4154_GabekGreenBTS(1800)-1 6% 20:41
4154_GabekGreenBTS(1800)-2 29% 20:41
4154_GabekGreenBTS(1800)-3 8% 20:41
4154_GabekGreenBTS-1 27% 20:40
4154_GabekGreenBTS-2 36% 20:40
4154_GabekGreenBTS-3 44% 20:41

Total Transmit
Power (TOC)
Site
Name
BTS
Type
Sector
name
Config
dBm Watt
Per TRX
Static
Output
Power
Setting in
LMT (W)
Traffic
Time
25th-May-09
1st S6 15.78 10 27% 20:08
2nd S6 24.79 10 55% 20:13 900MHz
3rd S6 22.16 10 43% 20:18
1st S6 12.32 10 9% 20:22
2nd S6 18.40 10 32% 20:27
Green
BTS_1
1800MHz
3rd S6 13.94 10 10% 20:29











BTS3900 S12/12/12 Power Consumption & TOC with High Traffic


2009-5-26 All Rights Reserved by Huawei 5

Power consumption in
Fluke Meter
Site
name
BTS
Type
Config
Volt Ampere Watt
Time
25th-May-09
3900 12/12/12 53.5 22.1 1,182 20:08
3900 12/12/12 53.5 22.4 1,198 20:10
3900 12/12/12 53.5 21.7 1,160 20:12
3900 12/12/12 53.5 21.9 1,171 20:16
3900 12/12/12 53.5 22.0 1,177 20:20
Green
BTS_1
3900 12/12/12 53.5 22.2 1,187 20:24



2> After shutdown all the TRXs (BCCH and TCH) of other cells below.

4675_Selindung-8
4676_PangklBalam-8
4676_PangklBalam-9
1817L1_PklBalam2-5
1817L1_PklBalam2-6
4655_PangkalPng-1
5812_PngklPinang2-4
4674_KacangPdg-7
1816L1_KcngPdg2-4
4132_TuaTunu-4

Detailed settings of Traffic moving.

Use modify administrative state! to shutdown all the TRXs of cells
above.
Shutdown the uplink PC function! and downlink PC function! of all the
six cells of site 4154
Shutdown the Load HO Allow! of all the six cells of site 4154
Modify the TCH traffic busy threshold (%)! and AMR TCH/H prior
load threshold! of all the six cells of site 4154, the first parameter is
change to90!, the second parameter is change to89!
Modify the RXLEV_ACCESS_MIN! to0!

3> Observe the traffic of the target cells and capture their statement again,
make the comparison to prove other cells! traffic already move to Gabek
Site.



BTS3900 S12/12/12 Power Consumption & TOC with High Traffic


2009-5-26 All Rights Reserved by Huawei 6

Sector name
Traffic
Before
Traffic
After
Time
4675_Selindung-8 25% 0 21:25
4676_PangklBalam-8 42% 0 21:25
4676_PangklBalam-9 30% 0 21:25
1817L1_PklBalam2-5 67% 0 21:24
1817L1_PklBalam2-6 42% 0 21:24
4655_PangkalPng-1 87% 3% 21:24
5812_PngklPinang2-4 74% 0 21:26
4674_KacangPdg-7 36% 0 21:25
1816L1_KcngPdg2-4 100% 0 21:23
4132_TuaTunu-4 - 0 21:23
4154_GabekGreenBTS(1800)-1 6% 43% 21:26
4154_GabekGreenBTS(1800)-2 29% 98% 21:26
4154_GabekGreenBTS(1800)-3 8% 43% 21:26
4154_GabekGreenBTS-1 27% 82% 21:27
4154_GabekGreenBTS-2 36% 93% 21:27
4154_GabekGreenBTS-3 44% 83% 21:27


4> Activate the Power Control and DTX (Discontinue Transmission) (which
will save the transmit power and total power consumption basing on the
different distance between BTS and Subs, the duration of subs! calling) of
all the six cells of Gabek site.

5> Test BTS3900 S12/12/12 power consumption (activate the Power Control
and DTX), total TOC of each cell (900MHz, 1800MHz), also the
corresponding captures for traffic.

Total Transmit
Power (TOC)
Site
Name
BTS
Type
Sector
name
Config
dBm Watt
Per TRX
Static
Output
Power
Setting in
LMT (W)
Traffic
Time
25th-May-09,
1st S6 24.98 10 69% 21:04
2nd S6 31.36 10 90% 21:08 900MHz
3rd S6 27.07 10 71% 21:11
1st S6 10.75 10 5% 21:15
2nd S6 25.24 10 83% 21:18
Green
BTS_1
1800MHz
3rd S6 14.92 10 34% 21:21


BTS3900 S12/12/12 Power Consumption & TOC with High Traffic


2009-5-26 All Rights Reserved by Huawei 7


Power consumption in
Fluke Meter
Site
name
BTS
Type
Config
Volt Ampere Watt
Time
25th-May-09
3900 12/12/12 53.5 25.3 1,353 21:04
3900 12/12/12 53.5 24.8 1,326 21:06
3900 12/12/12 53.5 24.7 1,321 21:08
3900 12/12/12 53.5 25.0 1,337 21:10
3900 12/12/12 53.5 24.6 1,316 21:12
Green
BTS_1
3900 12/12/12 53.5 25.0 1,337 21:20

6> Deactivate the Power Control and DTX of all the six cells of Gabek site.

7> Test BTS3900 S12/12/12 power consumption (Deactivate the Power
Control and DTX), Total TOC of each cell (900MHz, 1800MHz), also the
corresponding captures for traffic.

Total Transmit
Power (TOC)
Site
Name
BTS
Type
Sector
name
Config
dBm Watt
Per TRX
Static
Output
Power
Setting in
LMT (W)
Traffic
Time
25th-May-09,
1st S6 39.73 10 68% 21:34
2nd S6 55.35 10 97% 21:36 900MHz
3rd S6 47.39 10 89% 21:40
1st S6 15.95 10 13% 21:44
2nd S6 46.57 10 95% 21:47
Green
BTS_1
1800MHz
3rd S6 28.58 10 38% 21:50


Power consumption in
Fluke Meter
Site
name
BTS
Type
Config
Volt Ampere Watt
Time
25th-May-09
3900 12/12/12 53.5 28.7 1,535 21:30
3900 12/12/12 53.5 29.0 1,551 21:32
3900 12/12/12 53.5 28.6 1,530 21:34
3900 12/12/12 53.5 29.2 1,562 21:36
3900 12/12/12 53.5 28.8 1,540 21:38
Green
BTS_1
3900 12/12/12 53.5 30.0 1,605 21:40


BTS3900 S12/12/12 Power Consumption & TOC with High Traffic


2009-5-26 All Rights Reserved by Huawei 8



8> Activate Test Idle Timeslot! switch, to observe BTS3900 S12/12/12
Maximum TOC and Power Consumption.

Considering the different traffic in the different cell is caused by the
different Subs distribution. Wed like to suggest use the !Test Idle
Timeslot" switch to show the S12/12/12 100% traffic condition.

Detailed settings for the "Test Idle Timeslot# switch.

Shutdown the uplink PC function! and downlink PC function! of all the six
cells of site 4154
Activate Test Idle Timeslot! to enable the all the TRXs of site 3900 with
the full transmit power


Total
Transmit
Power
(TOC)
Site
Name
BTS Type
Sector
name
Config
dBm Watt
Per TRX
Static
Output
Power
Setting in
LMT (W)
Traffic
Equals
to
100%
Time
25th-May-09
900MHz 1st S6 61.3 10 100% 22:25 Green
BTS_1 1800MHz 1st S6 60.5 10 100% 22:42


Power consumption in
Fluke Meter
Site
name
BTS
Type
Config
Volt Ampere Watt
Time
25th-May-09
3900 S12/12/12 53.5 36.6 1,958 22:44 Green
BTS_1 3900 S12/12/12 53.5 35.3 1,888 22:48



BTS3900 S12/12/12 Power Consumption & TOC with High Traffic


2009-5-26 All Rights Reserved by Huawei 9



9> After testing, fall back the configuration to the normal and activate the other
cells.




















0
250
500
750
1,000
1,250
1,500
1,750
2,000
2,250
1 2 3 4 5 6
Power Consumption Before Shutdown Other Cells
Power Consumption After Shutdown- Activate PC DTX
Power Consumption After Shutdown- Deactivate PC DTX
Power Consumption Activate "Test Idle Timeslot#

BTS3900 S12/12/12 Power Consumption & TOC with High Traffic


2009-5-26 All Rights Reserved by Huawei 10


4. Test Schedule

23
rd
-May Upgrade BSC to solve SDCCH Congestion TR in Pangkal Pinang
24
th
-May Pre-test the power consumption and TOC of BTS3900 high traffic
25
th
-May Collect and analysis testing data
26
th
-May~27
th
-May XL team will go to Pangkal Pinang to test with Huawei Team



5. Test Team

PIC Santun
Region Gunawan XL
Manager Nana
PIC Charlie
Marketing Rudianto
PM
Hermansyah
(Huawei)
Engineer Wangzhiming
Huawei
(Power Meter,
Fluke Meter)
Engineer Deny






PT EXCELCOMINDO PRATAMA PT HUAWEI TECH INVESTMENT
By (Name) : By (Name) :
Signature : Signature :
Date : Date :