Вы находитесь на странице: 1из 12

INDEX

S.NO

LIST OF PROGRAMS

DATE

SIGNATURE

1

Work Breakdown Structure


2

Product Flow Diagram


3

Precedence Network


4

PERT Chart and Critical Path


5

CPM Network


6
Using MS-Project define CPM for
Manufacturing Chairs


7
Using MS-Project define CPM for dividing
Job Schedule


8
Using MS-Project define CPM for dividing
Work Schedule of a project.


9
Using MS-Project define WBS for an
Algorithm


10
Using MS-Project define WBS for
Animation Project




WORK BREAKDOWN STRUCTURE


Introduction
The Work Planning process is divided into three phases, viz. Work Breakdown Structure (WBS)
Development, Time and Cost estimation, and Schedule development.
The Work Breakdown Structure (WBS) is a hierarchical description of all the work that must be
done to meet the needs of the customer. While the three activities, viz. WBS development,
time and cost estimation, and schedule development are listed in a certain order in the
framework, a Project Manager who has gained some experience in the process may actually
perform the three activities in a different order.
No particular software or tool is recommended for a project work plan. The Project Manager
could use MS Project, MS Excel, or even a whiteboard (reserved for the project through the
project life cycle).

Work Plan- Work Breakdown StructureActivity Definition
Purpose:
The objective of this activity is to identify and organize the project into activities, sub-tasks, and
work packages needed to achieve goals. This establishes the base for the Project Manager to
estimate the duration of the project, determine the required resources and schedule the work.
The Work Breakdown Structure (WBS) is a hierarchical description of all the work that must be
done to meet the needs of the customer.
Participants:
The Project Manager develops the Work Breakdown Structure in consultation with the core
project team.
Inputs:
Project Request Approval Form [1], Project Overview Statement [1], Quality Strategy [1],
Project Approach [2], Business Case [4]

Process:

1. Two approaches can be used to identify project activities.

2. The first is the top-down approach.

a. Be clear about the goal in the Project Overview Statement.

b. Break down the goal into deliverables.

c. Identify activities that must be performed from the beginning to the completion of
the project.

d. Break down the deliverables into activities.

e. Successively decompose work into smaller, more manageable components until you
are satisfied that the work is defined at a sufficient level of detail to allow you to
estimate time, cost and resource requirements. The purpose is to provide better
management control.

3. Another approach to identify project activities is the bottom-up approach.

a. The entire planning team agrees to the first-level breakdown.

b. The team is divided into as many groups as there are first-level activities.

c. Each group then makes a list of the activities that need to be completed in order to
complete the first-level activities.

d. Someone in the group identifies an activity and tells it to the group. If the group
agrees, then the activity is written on a slip of paper and put in the middle of the
table. The process repeats itself until no new ideas are forthcoming.

e. The group then sorts the slips into activities that seem to be related to one another.
This helps the planning team add missing activities or remove redundant ones.

f. Once the team is satisfied it has completed the activity list for the first-level
breakdown, the members are finished. Each group then reports to the entire
planning team the results of its work. Final critiques are given, missing activities
added, redundant activities removed.



4. Define for each task how the work will actually be organized and accomplished.

5. Check that all deliverables have been accounted for.

6. Account for reviewing tasks and documentation.

7. Verify to see if the lower-level items are both necessary and sufficient for completion
of the decomposed items.

8. Verify to see if each item is clearly and completely defined.



Outputs:
Work Breakdown Structure

WORK BREAKDOWN STRUCTURE EXAMPLE





PRODUCT FLOW DIAGRAM

The Product Flow Diagram (PFD) is created from the Product Breakdown Structure. The Product
Flow Diagram shows the sequence of development of the products of the plan and any
dependencies between them. It also identifies products outside the scope of the plan.
In a PFD time flows in one direction only, from top to bottom or from left to right. Each Product
to be developed within the plan is enclosed in a box. Arrows connect the boxes, showing the
sequence in which they are created. Any products that already exist or come from work outside
the scope of the project are identified by using a different shape enclosure (ie. ellipse).
It is sensible to create the PFD from the specialist products and then add any relevant
management products. For example, when the project PFD is done, it may be a useful basis for
deciding where the stage boundaries should go.

PRECEDENCE NETWORK


Before scheduling is done, a Work Breakdown Structure (WBS) should be developed. To
illustrate how a schedule is constructed from a WBS, we consider a simple job of maintaining
the yard around a home.



The first step is to create a work breakdown table. The table will show the name of each task
(usually each task is also given a letter code), the duration of the task and what events must be
completed before the task can begin. The list of preceding tasks are only those that
immediately precede an individual task, not a list of all the tasks that occurred earlier. As an
example for the lawn case a work breakdown table would appear as follows:

A network diagram can be drawn from the information in the work breakdown table. D is the
task duration and arrows indicate precedence.


Network Rules and Computation
Three rules are applied to all networks in order to compute network start and finish times.
Rule 1: Before a task can begin, all tasks preceding it must be completed.
Rule 2: Arrows denote which tasks come first.
Rule 3: When two or more activities precede another activity, the earliest time that the final
activity can be started is the larger of the durations of the activities preceding it.
Lets look at an example to clarify what the rules mean. First, let us examine the boxes in the
network diagram below used to calculate the schedule. Each box in the network now contains
three pieces of information, not just the duration as in the network shown above. The box
shows:
D= Duration (of the task)
ES= Earliest Start i.e. the earliest time the task can begin, given all preceding tasks are
completed
EF= Earliest Finish i.e. the earliest time the task can finish, given the completion of all preceding
tasks and the task itself.
Network diagram for yard project used for schedule calculations.
PERT CHART AND CRITICAL PATH


Steps in the PERT Planning Process
PERT planning involves the following steps:
1. Identify the specific activities and milestones.
2. Determine the proper sequence of the activities.
3. Construct a network diagram.
4. Estimate the time required for each activity.
5. Determine the critical path.
6. Update the PERT chart as the project progresses.

1. Identify Activities and Milestones
The activities are the tasks required to complete the project. The milestones are the events
marking the beginning and end of one or more activities. It is helpful to list the tasks in a table
that in later steps can be expanded to include information on sequence and duration.
2. Determine Activity Sequence
This step may be combined with the activity identification step since the activity sequence is
evident for some tasks. Other tasks may require more analysis to determine the exact order in
which they must be performed.
3. Construct the Network Diagram
Using the activity sequence information, a network diagram can be drawn showing the
sequence of the serial and parallel activities. For the original activity-on-arc model, the activities
are depicted by arrowed lines and milestones are depicted by circles or "bubbles".
If done manually, several drafts may be required to correctly portray the relationships among
activities. Software packages simplify this step by automatically converting tabular activity
information into a network diagram.
4. Estimate Activity Times
Weeks are a commonly used unit of time for activity completion, but any consistent unit of time
can be used.
A distinguishing feature of PERT is its ability to deal with uncertainty in activity completion
times. For each activity, the model usually includes three time estimates:
Optimistic time - generally the shortest time in which the activity can be completed. It is
common practice to specify optimistic times to be three standard deviations from the
mean so that there is approximately a 1% chance that the activity will be completed
within the optimistic time.
Most likely time - the completion time having the highest probability. Note that this time
is different from the expected time.
Pessimistic time - the longest time that an activity might require. Three standard
deviations from the mean is commonly used for the pessimistic time.
PERT assumes a beta probability distribution for the time estimates. For a beta distribution, the
expected time for each activity can be approximated using the following weighted average:
Expected time = ( Optimistic + 4 x Most likely + Pessimistic ) / 6
This expected time may be displayed on the network diagram.
To calculate the variance for each activity completion time, if three standard deviation times
were selected for the optimistic and pessimistic times, then there are six standard deviations
between them, so the variance is given by:
[(Pessimistic - Optimistic) / 6]
2

5. Determine the Critical Path
The critical path is determined by adding the times for the activities in each sequence and
determining the longest path in the project. The critical path determines the total calendar time
required for the project. If activities outside the critical path speed up or slow down (within
limits), the total project time does not change. The amount of time that a non-critical path
activity can be delayed without delaying the project is referred to as slack time.
If the critical path is not immediately obvious, it may be helpful to determine the following four
quantities for each activity:


ES - Earliest Start time
EF - Earliest Finish time
LS - Latest Start time
LF - Latest Finish time
These times are calculated using the expected time for the relevant activities. The earliest start
and finish times of each activity are determined by working forward through the network and
determining the earliest time at which an activity can start and finish considering its
predecessor activities. The latest start and finish times are the latest times that an activity can
start and finish without delaying the project. LS and LF are found by working backward through
the network. The difference in the latest and earliest finish of each activity is that activity's
slack. The critical path then is the path through the network in which none of the activities have
slack.
The variance in the project completion time can be calculated by summing the variances in the
completion times of the activities in the critical path. Given this variance, one can calculate the
probability that the project will be completed by a certain date assuming a normal probability
distribution for the critical path. The normal distribution assumption holds if the number of
activities in the path is large enough for the central limit theorem to be applied.
Since the critical path determines the completion date of the project, the project can be
accelerated by adding the resources required to decrease the time for the activities in the
critical path. Such a shortening of the project sometimes is referred to as project crashing.
6. Update as Project Progresses
Make adjustments in the PERT chart as the project progresses. As the project unfolds, the
estimated times can be replaced with actual times. In cases where there are delays, additional
resources may be needed to stay on schedule and the PERT chart may be modified to reflect
the new situation.

Вам также может понравиться