GIOVE B
GIOVE Workshop
ESTEC (NL), 13 October 2008
Content
1. Introduction
2. Giove B, Element of Galileo
3. Giove B Performances
This document is the property of Astrium. It shall not be communicated to third parties without prior written agreement. Its content shall not be disclosed.
1. Payload
2. Platform
4. Giove B Steps to Space
1. Development
2. Integration and Tests
3. Launch Campaign (Baikonur)
5. Giove B In-Orbit Signal
6. Giove B Payload Features
in cooperation with
ESA as customer
Telespazio for operations
GIOVE Workshop Estec - GIOVE B
13 / 10 / 08 p5
Earth Observation, Navigation
& Science
3. GIOVE B Performances
Payload
Clocks
1 Passive Hydrogen Maser (S-PHM): Drift
This document is the property of Astrium. It shall not be communicated to third parties without prior written agreement. Its content shall not be disclosed.
3. GIOVE B Performances
Platform
Avionics
Integrated Control and Data Unit (ICDU)
This document is the property of Astrium. It shall not be communicated to third parties without prior written agreement. Its content shall not be disclosed.
3. GIOVE B Performances
Platform
TT&C
2 S-Band Transponders
This document is the property of Astrium. It shall not be communicated to third parties without prior written agreement. Its content shall not be disclosed.
Alignment Checks
Radiated EMC Tests
Launch Vehicle Compatibility (Umbilical Tests)
Solar Array Pyro Deployments Tests
Propulsion System Tests
Integrated System Test#2 and System
Validation Test#2 with Ground Station
Alignment Checks
Radiated EMC Tests
Launch Vehicle Compatibility (Umbilical Tests)
Solar Array Pyro Deployments Tests
Propulsion System Tests
Integrated System Test#2 and System
Validation Test#2 with Ground Station
Alignment Checks
Radiated EMC Tests
Launch Vehicle Compatibility (Umbilical Tests)
Solar Array Pyro Deployments Tests
Propulsion System Tests
Integrated System Test#2 and System
Validation Test#2 with Ground Station
Alignment Checks
Radiated EMC Tests
Launch Vehicle Compatibility (Umbilical Tests)
Solar Array Pyro Deployments Tests
Propulsion System Tests
Integrated System Test#2 and System
Validation Test#2 with Ground Station
Alignment Checks
Radiated EMC Tests
Launch Vehicle Compatibility (Umbilical Tests)
Solar Array Pyro Deployments Tests
Propulsion System Tests
Integrated System Test#2 and System
Validation Test#2 with Ground Station
Alignment Checks
Radiated EMC Tests
Launch Vehicle Compatibility (Umbilical Tests)
Solar Array Pyro Deployments Tests
Propulsion System Tests
Integrated System Test#2 and System
Validation Test#2 with Ground Station
Alignment Checks
Radiated EMC Tests
Launch Vehicle Compatibility (Umbilical Tests)
Solar Array Pyro Deployments Tests
Propulsion System Tests
Integrated System Test#2 and System
Validation Test#2 with Ground Station
Launch Campaign
Campaign in Baikonur (Kazakhstan)
Functional Tests
This document is the property of Astrium. It shall not be communicated to third parties without prior written agreement. Its content shall not be disclosed.
Fueling of Spacecraft
Integration onto the Launch Vehicle Adapter
Integration onto Fregat
Tilting and Encapsulation
Integration of Upper Composite onto the 3rd
Stage
Integration onto the 1st and 2nd Stage
Roll out to launch pad
Count Down
Launch Campaign
Campaign in Baikonur (Kazakhstan)
Functional Tests
This document is the property of Astrium. It shall not be communicated to third parties without prior written agreement. Its content shall not be disclosed.
Fueling of Spacecraft
Integration onto the Launch Vehicle Adapter
Integration onto Fregat
Tilting and Encapsulation
Integration of Upper Composite onto the 3rd
Stage
Integration onto the 1st and 2nd Stage
Roll out to launch pad
Count Down
Launch Campaign
Campaign in Baikonur (Kazakhstan)
Functional Tests
This document is the property of Astrium. It shall not be communicated to third parties without prior written agreement. Its content shall not be disclosed.
Fueling of Spacecraft
Integration onto the Launch Vehicle Adapter
Integration onto Fregat
Tilting and Encapsulation
Integration of Upper Composite onto the 3rd
Stage
Integration onto the 1st and 2nd Stage
Roll out to launch pad
Count Down
Launch Campaign
Campaign in Baikonur (Kazakhstan)
Functional Tests
This document is the property of Astrium. It shall not be communicated to third parties without prior written agreement. Its content shall not be disclosed.
Fueling of Spacecraft
Integration onto the Launch Vehicle Adapter
Integration onto Fregat
Tilting and Encapsulation
Integration of Upper Composite onto the 3rd
Stage
Integration onto the 1st and 2nd Stage
Roll out to launch pad
Count Down
Launch Campaign
Campaign in Baikonur (Kazakhstan)
Functional Tests
This document is the property of Astrium. It shall not be communicated to third parties without prior written agreement. Its content shall not be disclosed.
Fueling of Spacecraft
Integration onto the Launch Vehicle Adapter
Integration onto Fregat
Tilting and Encapsulation
Integration of Upper Composite onto the 3rd
Stage
Integration onto the 1st and 2nd Stage
Roll out to launch pad
Count Down
Launch Campaign
Campaign in Baikonur (Kazakhstan)
Functional Tests
This document is the property of Astrium. It shall not be communicated to third parties without prior written agreement. Its content shall not be disclosed.
Fueling of Spacecraft
Integration onto the Launch Vehicle Adapter
Integration onto Fregat
Tilting and Encapsulation
Integration of Upper Composite onto the 3rd
Stage
Integration onto the 1st and 2nd Stage
Roll out to launch pad
Count Down
Launch Campaign
Campaign in Baikonur (Kazakhstan)
Functional Tests
This document is the property of Astrium. It shall not be communicated to third parties without prior written agreement. Its content shall not be disclosed.
Fueling of Spacecraft
Integration onto the Launch Vehicle Adapter
Integration onto Fregat
Tilting and Encapsulation
Integration of Upper Composite onto the 3rd
Stage
Integration onto the 1st and 2nd Stage
Roll out to launch pad
Count Down
Launch Campaign
Campaign in Baikonur (Kazakhstan)
Functional Tests
This document is the property of Astrium. It shall not be communicated to third parties without prior written agreement. Its content shall not be disclosed.
Fueling of Spacecraft
Integration onto the Launch Vehicle Adapter
Integration onto Fregat
Tilting and Encapsulation
Integration of Upper Composite onto the 3rd
Stage
Integration onto the 1st and 2nd Stage
Roll out to launch pad
Count Down
Launch Campaign
Campaign in Baikonur (Kazakhstan)
Functional Tests
This document is the property of Astrium. It shall not be communicated to third parties without prior written agreement. Its content shall not be disclosed.
Fueling of Spacecraft
Integration onto the Launch Vehicle Adapter
Integration onto Fregat
Tilting and Encapsulation
Integration of Upper Composite onto the 3rd
Stage
Integration onto the 1st and 2nd Stage
Roll out to launch pad
Count Down
successful TM acquisition
02:22 Pyro firing
successful S/A deployment
28-04 12:02 Transition to EAM
01-05 08:23 S-PHM Ion Pump Switch ON
05-05 20:04 P/L ON
23:35 S-PHM clock locked
06-05 23:49 SSPA L1 Channel ON
23:50 SSPA E6 Channel ON
performance
Complex EU/US negotiations led to 2007 joint
adoption of MBOC (Multiplexed Binary Offset
Coding) modulation standard
GIOVE-B was first satellite to transmit MBOC
signals from space
Paves the way for future roll-out on Galileo and
GPS-III satellites
TM Value [A]
2.0
1.6
1.5
1.4
09.06.08 PST00003
30.0
Each commissioning phase followed by 25.0
TM Value
20.0
10.0
Redu (B)
Chilbolton (UK)
-10.0
-20.0
-30.0
This document is the property of Astrium. It shall not be communicated to third parties without prior written agreement. Its content shall not be disclosed.
-60.0
13 / 10 / 08
& Science
p35
Earth Observation, Navigation