PROVISION OF ENGINEERING OF LOW PRESSURE SYSTEM (LPS) AT TOPAZ
PLATFORM, BLOCKS 01&02, OFFSHORE VIETNAM
COMPANY COMMENT SHEET
Page 1 of 5
Owner PETRONAS CARIGALI VIETNAM LIMITED (PCVL) Company PTSC OFFSHORE SERVICES JOINT STOCK COMPANY (POS) DE Contractor TECHNIP VIETNAM COMPANY LIMITED Vendor Package Vapour Recovery Compressor Document No. and Title Revision Transmittal No. Date of Issue
No. DOCUMENT No. TPVN COMMENT SUBCONTRACTOR RESPONSE STATUS 1. General: - All P&IDs are still very preliminary. They need to be updated sufficiently for further detail review. - P&IDs shall be also subject to further review and approval by COMPANY (Petronas)
2. Drawing 76630-101 To indicate battery limit line (BL) clearly and tie- in point tag name (as given on the GA drawings).
This comment is applicable for all tie-in points.
PROVISION OF DETAILED ENGINEERING SERVICES FOR RBDP-A GASLIFT LINE PROJECT COMPANY COMMENT SHEET
Page 2 of 5 No. DOCUMENT No. TPVN COMMENT SUBCONTRACTOR RESPONSE STATUS 3. Drawing 76630-101 Use legend ''LCP'' for Local Control Panel. The command signal should be from LCP, not to LCP, please correct the symbol. (see attached drawing with comments) In addition, please clarify this will be electric or pneumatic signal. The symbol used in drawing indicates tubing, means pneumatic. Please confirm. Electric signal is preferred.
This is typical comment applicable for all other similar signal
4. Drawing 76630-101 To provide SDV on the scrubber drain line for emergency shutdown from LCP. To provide temporary strainer for commissioning & start-up (Removable) Please clarify what is the cooling medium used for inter & after gas coolers. Note that platform does not have cooling water system. To clarify the position of Start Gas Vent on Package Vent Header. Vendor to show the interfacing signals between LCP and COMPANY control system in the P&ID (see attached drawing with comments).
PROVISION OF DETAILED ENGINEERING SERVICES FOR RBDP-A GASLIFT LINE PROJECT COMPANY COMMENT SHEET
Page 3 of 5 No. DOCUMENT No. TPVN COMMENT SUBCONTRACTOR RESPONSE STATUS 5. Drawing 76630-101 Vendor to provide: - Relief load calculation (PSV and Blowdown) including minimum temperature experienced during blowdown - Liquid Low low level protection should be provided for V-101 and V-201 - Setting points (pressure, temperature, level)
6. Drawing 76630-102 Vendor To provide: - P&ID for Machinery Monitoring System. Compressor Rod drop detection, Compressor & Engine vibration detection, Compressor & Engine bearing temperature detection, speed sensor are normally required. - P&ID for Instrument Gas System to all required instruments. - P&ID for Engine Air Intake System and Combustion Gas System. - Utility consumptions (separately) - Electrical load consumption list (separately)
7. Drawing 76630-102 Water P&ID EJW Pump & Aux Pump should be shaft driven. Please confirm. Please confirm the position for Engine Oil Cooler.
PROVISION OF DETAILED ENGINEERING SERVICES FOR RBDP-A GASLIFT LINE PROJECT COMPANY COMMENT SHEET
Page 4 of 5 No. DOCUMENT No. TPVN COMMENT SUBCONTRACTOR RESPONSE STATUS 8. Drawing 76630-102 Lube Oil P&ID To clarify how lube oil will be supplied to the engine and compressor after emergency shutdown. To show cylinder lubrication system. Note that cylinder lubrication oil must be separate from compressor frame lube oil. To provide compressor prelube oil pump (not manual pump). To show in detail engine lube oil system. Please clarify clearly the purpose of Lube Oil In and Lube Oil Drain connections. With the packing vent and packing drain combined, Pot is required to separate liquid and gas.
9. Drawing 76630-102 Fuel & Start P&ID There is only one FG tie-in connection shown on GA. But this P&ID shows two connections. Please check and confirm. One tie-in connection is preferred. Please revise the symbol of PCV on the Start Gas line. The prelube pump shall be running for some time before starting. How this can be achieved with this arrangement of prelube system? Please check and confirm.
PROVISION OF DETAILED ENGINEERING SERVICES FOR RBDP-A GASLIFT LINE PROJECT COMPANY COMMENT SHEET
Page 5 of 5 No. DOCUMENT No. TPVN COMMENT SUBCONTRACTOR RESPONSE STATUS 10. Drawing 1090-3 Add tie-in connection for combustion exhaust pipe (outlet of GT Silencer) and provide sufficient connection information for this tie-in point. Consider option to separate into sub-skid for offshore installation using platform crane (15MT SWL) if achievable in separate drawings. If not, provide justification. To provide and show drip pan drain connection. To confirm if any electric motor & heater is used. If any, please provide Location of motors, heaters, terminal box, and cable entries information (e.g. gland size) for Purchaser cable routing.