ID Duration Start Finish Predeces

Task Name
1 Database Development 10 days Fri 10/16/09 Thu 10/29/09
2 Graphical User Interface Development 18 days Fri 10/16/09 Tue 11/10/09
3 GUI for Web Application 6 days Fri 10/16/09 Fri 10/23/09
4 GUI for Desktop Application 6 days Mon 10/26/09 Mon 11/2/09 3
5 GUI for Communication Portal 6 days Tue 11/3/09 Tue 11/10/09 4
6 Web application 16 days Fri 10/30/09 Fri 11/20/09
7 Student Portal 4 days Fri 10/30/09 Wed 11/4/09
8 Create Student Account 2 days Fri 10/30/09 Mon 11/2/09 1,3
9 Update Information 1 day Tue 11/3/09 Tue 11/3/09 8
10 Schedule Class 3 days Fri 10/30/09 Tue 11/3/09 1,3
11 Rate the teacher 1 day Wed 11/4/09 Wed 11/4/09 10
12 View class history 1 day Wed 11/4/09 Wed 11/4/09 9
13 Teacher Portal 3 days Fri 10/30/09 Tue 11/3/09
14 Create teacher account 2 days Fri 10/30/09 Mon 11/2/09 1,3
15 View Information 1 day Tue 11/3/09 Tue 11/3/09 14
16 Update information 1 day Fri 10/30/09 Fri 10/30/09 1,3
17 Rate the student 1 day Mon 11/2/09 Mon 11/2/09 16
18 View history of classes 1 day Fri 10/30/09 Fri 10/30/09 1
19 Admin Portal 12 days Thu 11/5/09 Fri 11/20/09 12,18
20 Student control panel 5 days Thu 11/5/09 Wed 11/11/09 1,3
21 Teacher control panel 5 days Thu 11/12/09 Wed 11/18/09 20
22 Add Classes 2 days Thu 11/5/09 Fri 11/6/09 1,3
23 Schedule Classes 3 days Mon 11/9/09 Wed 11/11/09 22
24 View user login history 1 day Thu 11/12/09 Thu 11/12/09 23
25 View student/teacher rating 2 days Thu 11/19/09 Fri 11/20/09 21
26 Desktop Application 15 days Mon 11/23/09 Fri 12/11/09 6
27 Desktop Client for Student 15 days Mon 11/23/09 Fri 12/11/09 1,4
28 Communication Portal 13 days Wed 11/4/09 Fri 11/20/09
29 Login , logout , take class through web service and flash 2 days Wed 11/11/09 Thu 11/12/09 5,1,11
30 Communication Portal Development using flash media s 5 days Fri 11/13/09 Thu 11/19/09 29
31 Voice Chat Module 4 days Wed 11/4/09 Mon 11/9/09 15
32 Web cam module 5 days Wed 11/11/09 Tue 11/17/09 5,1

Task Milestone External Tasks


Project: MTP.mpp
Split Summary External Milestone
Date: Mon 11/23/09
Progress Project Summary Deadline

Page 1
ID Duration Start Finish Predeces
Task Name
33 White board module 4 days Thu 11/5/09 Tue 11/10/09 12
34 login / logout functionality 1 day Fri 11/20/09 Fri 11/20/09 30
35
36 Testing 22 days Mon 11/23/09 Tue 12/22/09
37 Testing of Web Application 7 days Mon 11/23/09 Tue 12/1/09 25
38 Testing of Desktop application 7 days Mon 12/14/09 Tue 12/22/09 27
39 Testing of Communication Portal 7 days Mon 11/23/09 Tue 12/1/09 34
40 Integration Testing 5 days Wed 12/2/09 Tue 12/8/09 37,39

Task Milestone External Tasks


Project: MTP.mpp
Split Summary External Milestone
Date: Mon 11/23/09
Progress Project Summary Deadline

Page 2
Resource Names Oct 18, '09 Oct 25, '09 Nov 1, '09 Nov 8, '09
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Abdul Ghaffar,Ghazanffer Javaid,Syed Noman Ahmad Abdul Ghaffar,Ghazanffer Javaid,Syed Noman Ahmad

Omair Khan Omair Khan


Omair Khan Omair Khan
Omair Khan Omair Kha

Ghazanffer Javaid Ghazanffer Javaid


Ghazanffer Javaid Ghazanffer Javaid
Kamran Khatri Kamran Khatri
Kamran Khatri Kamran Khatri
Ghazanffer Javaid Ghazanffer Javaid

Adnan Ahmad Adnan Ahmad


Adnan Ahmad Adnan Ahmad
Abdul Ghaffar Abdul Ghaffar
Abdul Ghaffar Abdul Ghaffar
Kamran Khatri Kamran Khatri

Syed Noman Ahmad Syed N


Syed Noman Ahmad
Moiz Chinoy Moiz Chinoy
Moiz Chinoy Moiz C
Moiz Chinoy Mo
Syed Noman Ahmad

Sajjad walibhai

Kamran Khatri Ka
Kamran Khatri
Adnan Ahmad Adnan Ahmad
Mukarram Yar Khan

Task Milestone External Tasks


Project: MTP.mpp
Split Summary External Milestone
Date: Mon 11/23/09
Progress Project Summary Deadline

Page 3
Resource Names Oct 18, '09 Oct 25, '09 Nov 1, '09 Nov 8, '09
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Ghazanffer Javaid Ghazanffer
Kamran Khatri

Shaukat Leghari
Shaukat Leghari
Mukarram Yar Khan
Shaukat Leghari,Mukarram Yar Khan

Task Milestone External Tasks


Project: MTP.mpp
Split Summary External Milestone
Date: Mon 11/23/09
Progress Project Summary Deadline

Page 4
Nov 15, '09 Nov 22, '09 Nov 29, '09 Dec 6, '09 Dec 13, '09 Dec 20, '09
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

oman Ahmad
Syed Noman Ahmad

hinoy
iz Chinoy
Syed Noman Ahmad

Sajjad walibhai

mran Khatri
Kamran Khatri

Mukarram Yar Khan

Task Milestone External Tasks


Project: MTP.mpp
Split Summary External Milestone
Date: Mon 11/23/09
Progress Project Summary Deadline

Page 5
Nov 15, '09 Nov 22, '09 Nov 29, '09 Dec 6, '09 Dec 13, '09 Dec 20, '09
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Javaid
Kamran Khatri

Shaukat Leghari
Shaukat Leghar
Mukarram Yar Khan
Shaukat Leghari,Mukarram Yar Khan

Task Milestone External Tasks


Project: MTP.mpp
Split Summary External Milestone
Date: Mon 11/23/09
Progress Project Summary Deadline