Energy
Infrastructure, mining and commodities
Transport
Technology and innovation
Life sciences and healthcare
A guide to
EPCM contracts
A guide to
EPCM contracts
EPCM services 09
Payment 12
Incentives 13
Limitations on liability 15
Contacts 20
A guide to EPCM contracts
Summary
This document provides a description of the EPCM procurement structure and some of
the key issues that should be considered by any junior miner contemplating its use for
mining infrastructure delivery.
Whilst often confused with the EPC contracting solution, the EPCM and EPC contracting
solutions are very different in terms of the nature of the obligations undertaken and the
risk allocation assumed by the respective contractors.
An important difference between the two is that an EPCM contractor will not accept cost
and/or time risk for the delivery of the project, this is a risk retained by the employer.
The employer will therefore need to manage these risks with the professional assistance
and support of the EPCM contractor through the construction and equipment/plant
supply chain.
Save as highlighted in this document, the quality of the EPCM contractor’s performance
will generally be determined by reference to the extent to which it has performed its
services in accordance with the level of skill and care required by the EPCM contract,
rather than by reference to the achievement of overall project budgetary or scheduling
targets.
Historically, the mining sector has tended to see quite an unsophisticated approach to
EPCM contracting when compared to other sectors where the model is commonly used
(for instance, in the petrochemicals industries).
Well advised employers in the mining sector are however seeing that contractors
undertaking EPCM services are increasingly willing to accommodate a more onerous
risk profile under which the EPCM contractor may be more effectively incentivised
to manage time and cost overrun exposure for employers (see ‘Incentives’ below).
The drivers for this development are numerous but clearly economic pressure during
a downturn, and so competition for work, is key.
The EPCM solution will allow employers to retain ultimate control over
design development throughout construction
This will provide flexibility to allow employers to adapt design to suit precise (and
sometimes changing) requirements and to allow optimisation and value engineering
where relevant to control capital costs. Such flexibility is not possible under an EPC
solution (at least not without significant price consequences) since design development
will be controlled by the EPC contractor.
But the advantage of lower costs and increased flexibility under an EPCM solution
should always be balanced against the significant additional risks being retained by
the employer in project delivery. As mentioned above, the employer under an EPCM
solution will not be insulated from cost overrun risk in the same way as they would be
under a fixed price EPC solution.
The employer’s role in the management of the works in parallel with the EPCM
contractor is therefore paramount. For successful project implementation, the EPCM
solution requires a well-equipped and mobilised employer’s team to take a hands-on
and intrusive role in the management and administration of the works.
Form of contract –
what should be the starting point?
There is no international standard form template contract for the EPCM contracting
solution, unlike for EPC turnkey or traditional build contracts.
In our experience:
In our experience, significant time and cost can be saved by the employer taking the
initiative in this regard and delivering terms to the EPCM contractor which represent
those on which it is prepared to negotiate.
EPCM services
EPCM services typically fall into the following categories:
Where the EPCM contractor has not produced basic design, the EPCM contractor should
accept the risk of the accuracy and completeness of the basic design or at least verifying
the same to the employer.
The EPCM will advise on the timing of the letting of the relevant packages and will
advise the employer on the terms available and will typically negotiate the contract
packages on the employer’s behalf.
It is usual for the employer to enter into the works and supply contracts directly but
we have seen exceptions to this approach under which the EPCM contractor enters into
contracts as the employer’s agent.
The construction management services will also typically include the management of
health and safety at the site, the management of disputes between the employer, the
works contractors and/or the suppliers, the establishment of quality assurance systems
and the management of the remedying of defective works and/or services provided by
other parties.
In all cases, it is important that the nature and extent of the services being provided are
well defined and that appropriate levels of contractual flexibility are created to allow the
scope of services to be adapted through the execution of the project in a manner which
does not expose the employer to de-scoping ‘penalties’ or inflated pricing for enhanced
services.
The above allocation of responsibility is not the only solution. Hybrid solutions have also
become more common, for instance where employers wholly retain the management
function through the owner’s team to create an EP/CM split. The appropriateness of the
structure proposed will always be something that the employer should consider with its
technical, commercial and legal advisers on a case-by-case basis.
Key to this will be the separation of the works into appropriate works and supply
packages which should each be procured on robust terms which seek to insulate the
employer from time and cost overrun risk. The procurement strategy should seek to
avoid where possible the creation of time, design and works interfaces and where
the creation of such interfaces is unavoidable, a clear strategy for the management
of them should be established by the EPCM contractor (and indeed this should be a
contractual requirement).
The role of the employer’s team in monitoring, supporting and supplementing the
services of the EPCM contractor is extremely important to achieve successful project
execution and delivery within project budgetary constraints.
Payment
The usual basis of payment for EPCM contractors is as follows:
• payment on a cost reimbursable basis for the man hours expended at agreed rates
(rates should reflect the actual and verifiable cost and the contract should expressly
provide that these rates should usually NOT include profit) plus
• a fixed fee element representing the EPCM contractor’s profit. Employer’s should
seek to agree to fix this amount at day 1 and not permit any increase in the event of
project cost and/or time overruns (ie, to avoid any indirect disincentive to the control
of overruns).
The EPCM contractor should warrant that the agreed rates in that the agreed rates in
the first two bullet points above do not contain any profit element, and the employer
should have the right to claw-back any profit element subsequently identified through
agreed audit rights or as disclosed by the EPCM contractor.
The value of the hours expended by the EPCM contractor in providing the required
services are not typically subject to an overall cap or limit, although employers
sometimes offer incentive payment for the achievement of budgeted man hours.
However, with a competitive market, there are contractors who may be willing to accept
delivery of all the EPCM services for a fixed amount. The only exceptions to this would
be subject to negotiation but might include: variations to the EPCM or trade contracts;
breach by the Employer of the EPCM contract or trade contracts and possibly ‘force
majeure’ type events.
On the face of it, capping the amounts payable to the EPCM contractor appears
commercially sensible but employers need to be aware that where matters have
taken a turn for the worse – for instance where the project has fallen into delay (which
may be for reasons beyond the reasonable control of the EPCM contractor), employers
will want to avoid effectively putting a halt to the services or disincentivising the EPCM
contractor from applying appropriate resource to the project to assist in rectifying the
relevant issues.
Incentives
The EPCM contractor will not backstop project delivery risk and, importantly, the
achievement of key project targets. The EPCM contractor will however be responsible
for managing the same on behalf of the employer.
The challenge for employers will be to incentivise the EPCM contractor to effectively
and proactively manage project delivery and the achievement of key project targets.
• bonus payments for the works being completed on time or within a fixed period
following the scheduled completion date
• bonus payments for the works being completed for an overall outturn cost below or
within a fixed amount over the outturn cost budget
• bonus payments based on the health and safety record at the site
• bonus payments for completing the required EPCM services within the projected
budget for such services (based on projected man hours at the agreed rates)
but there will always be variations on the approaches outlined above and the proposed
approach will tend to be shaped by the concerns the employer may have in respect of
key aspects of project delivery.
It will be a matter for the employer to consider commercially whether the incentives
should remain payable where extraneous circumstances outside of the control of the
EPCM contractor have undermined the achievement of the relevant project targets. We
have seen varying approaches in this regard.
Since the EPCM contractor will typically set key project targets (eg, the project budget
and the project programme), appropriate due diligence will need to be undertaken
by the employer to establish that the project targets are sensible in the context of the
project proposed.
More recently, we have seen EPCM contractors willing to accept negative incentives
around the achievement of the key project targets, such that they are prepared to place
an element of their profit at risk. This approach has been commonplace in other sectors
using the EPCM model for some time but it is now becoming more common now in the
mining sector.
Limitations on liability
All EPCM Contractors will expect to cap their liability under the terms of the
EPCM contract.
The liability accepted by the EPCM contractor must be appropriately sized but the ethos
of EPCM contracting is that the EPCM contractor is providing consultancy services
only and is not underwriting project risk. The size of the liability caps under the EPCM
contract (compared to the overall project cost) and security package (if any) supporting
the EPCM contract will be reflective of this.
In addition, there is usually an agreed list of further liabilities that will not count
towards the liability limit. This is usually a matter for commercial negotiation and will,
to a certain extent, be driven by project specific concerns.
Consequential losses
Liability for consequential losses (ie, the losses that arise indirectly from the failure,
act or omission of the EPCM contractor) is a key issue:
• employers will be concerned about the cost of its ‘trade’ contractors having to re-
perform works as a result of defective services or design by the EPCM contractor
• the extent of liability typically accepted by EPCM contractors will leave the employer
exposed given the likely quantum of these liabilities
• the allocation of insurance deductible risk will be a matter for commercial negotiation.
• this is a difficult concept for an employer to accept particularly given the above
described trade contractor losses
• employers should resist this since any such re-performance should be treated as a
cost of performing the services and is not a liability as such
• many liabilities that should be captured by the EPCM contract liability regime
may not be remediable through re-performance of defective services alone, so this
approach will not provide for an appropriate remedy in many circumstances
It would be unusual for any contractor to bear withholding tax risk and, if it did, then
it would simply become a ‘cost’ to the project that would add to the overall project
economics. It is important therefore:
• to obtain the early buy-in by the local tax authorities (either directly or through
local advisers) to those arrangements.
One of the most common means of mitigating withholding tax exposure is to adopt a
split ‘on-shore’ and ‘off-shore’ contract structure. This usually means that there will
be two contracts, each entered into by a different EPCM contractor entity and each
containing different scope of services. For example, there will usually be:
• one contract for those services which may take place outside of the country in which
the works are being delivered, payment for which may therefore be structured to
avoid withholding tax. This contract will typically be entered into by a non-local
EPCM contractor entity, (the ‘off-shore contract’)
• one contract for those services which must be performed in the country in which
the works are being delivered, such as the EPCM construction management services
(because there must be personnel presence on the ground in order to carry out the
supervision), payment for which may be subject to the relevant local withholding
tax regime. This contract will typically be entered into by a locally registered EPCM
contractor entity (the ‘on-shore contract’).
The obvious risk to the employer with a split structure is that he is required to deal with
two contractors each with a separate scope of work and separate rights and obligations.
It is important therefore that these contracts are well drafted and dovetail together so
that they include, at least, the following provisions:
• a recognition of the joint objectives across the two contracts and a requirement for
coordination
• an acknowledgement that any act, omission or default by one entity will not give rise
to any right of the other entity to relief from or a right to claim against the employer
• a right for the employer to consolidate any dispute against one entity with any
dispute against the other.
The employer will usually look to limit its exposure to breach by the separate on-shore
and off-shore contractors by putting in place further contractual arrangements which
provide for the off-shore EPCM contractor entity (or a suitable parent) providing a
performance and financial guarantee (backed by indemnities and, possibly, suitable
financial security) in respect of discharge by both the on-shore and off-shore entities
of their respective and collective obligations. This guarantee (which could be wrapped
into the off-shore contract) is often referred to as an ‘umbrella agreement’.
However, in jurisdictions where the tax authorities do not recognise this ‘split’ due to
the presence of the guarantee (or ‘wrap’) provided by the umbrella agreement, then
further careful consideration is required in the drafting of the on-shore and off-shore
contracts in order to deal specifically with the above concerns.
English law is the preferred governing law for substantial international contracts
because it carries a guarantee of impartiality and integrity that is recognised worldwide
and provides the ideal balance of predictability and flexibility. It is invariably the
preferred choice of lenders in the EPCM market.
• There are well established international arbitral rules (such as the ICC, LCIA) which
have dedicated resources to deal with all administrative aspects of the arbitral
process including but not limited to nomination of arbitrators, advances on costs
and recommended model clauses.
• Finally the place (or seat) of arbitration needs careful consideration because:
Advice should be sought on a case-by-case basis to ensure that the EPCM contract
contains appropriate dispute resolution provisions which provide clear recourse for
the employer and a high degree of certainty in terms of its ability to enforce any award
made in its favour.
Contacts
Martin McCann
Global head of mining,
infrastructure and commodities
Norton Rose Fulbright LLP
Tel +44 20 7444 3573
martin.mccann@nortonrosefulbright.com
Mark Berry
Partner, London
Norton Rose Fulbright LLP
Tel +44 20 7444 3531
mark.berry@nortonrosefulbright.com
Matthew Hardwick
Senior associate, London
Norton Rose Fulbright LLP
Tel +44 20 7444 5550
matthew.hardwick@nortonrosefulbright.com
Recognized for our industry focus, we are strong across all the key industry sectors:
financial institutions; energy; infrastructure, mining and commodities; transport;
technology and innovation; and life sciences and healthcare.
Wherever we are, we operate in accordance with our global business principles of quality,
unity and integrity. We aim to provide the highest possible standard of legal service in each
of our offices and to maintain that level of quality at every point of contact.
Norton Rose Fulbright LLP, Norton Rose Fulbright Australia, Norton Rose Fulbright Canada
LLP, Norton Rose Fulbright South Africa (incorporated as Deneys Reitz Inc) and Fulbright
& Jaworski LLP, each of which is a separate legal entity, are members (‘the Norton Rose
Fulbright members’) of Norton Rose Fulbright Verein, a Swiss Verein. Norton Rose Fulbright
Verein helps coordinate the activities of the Norton Rose Fulbright members but does not
itself provide legal services to clients.
References to ‘Norton Rose Fulbright’, ‘the law firm’, and ‘legal practice’ are to one or more of the Norton Rose Fulbright members
or to one of their respective affiliates (together ‘Norton Rose Fulbright entity/entities’). No individual who is a member, partner,
shareholder, director, employee or consultant of, in or to any Norton Rose Fulbright entity (whether or not such individual is
described as a ‘partner’) accepts or assumes responsibility, or has any liability, to any person in respect of this communication. Any
reference to a partner or director is to a member, employee or consultant with equivalent standing and qualifications of the relevant
Norton Rose Fulbright entity. The purpose of this communication is to provide information as to developments in the law. It does not
contain a full analysis of the law nor does it constitute an opinion of any Norton Rose Fulbright entity on the points of law discussed.
You must take specific legal advice on any particular matter which concerns you. If you require any advice or further information,
please speak to your usual contact at Norton Rose Fulbright.
© Norton Rose Fulbright LLP NRF15994 06/13 (UK) Extracts may be copied provided their source is acknowledged.
Law around the world
nortonrosefulbright.com