Currently the existing Banuwati-A, which started up in 2007, is the main gas production platform in Central Area, whose gas is delivered to Widuri P platform in North Area for power generation and to a gas plant in Pabelokan island for further gas conditioning. Gradually the well pressure from Banuwati-A is expected to be deplete over years, so a new Banuwati Gas Compressor Platform (Banuwati-K) will be installed alongside Banuwati-A for Boosting pressure to increase operating pressure of Banuwati-A to normal level to ensure gas flow to Pabelokan gas plant and Widuri platform. In addition to Banuwati-A gas, the gas from Asti-A and Mila-A will also be compressed by booster compressors on Banuwati-K. This new Banuwati Gas Compressor Platform (Banuwati-K) shall accommodate all equipment such as gas compressors, etc. for gas pressure boost and it will be bridge connected to Banuwati-A platform so the operators from Banuwati-A can access and operate it.
2.0 PROJECT OVERVIEW
Table 1.1. below briefly shows the basic scope of the project.
No. Item Description 1. Field or Site General Location Banuwati Facility is located at 120-160 km off the north coast of West J ava. The new booster compressor platform, BWK, will be bridge connected to Banuwati-A. 2. Description of Banuwati-K Gas Compression Platform. - Design flow to BWK is 100 MMscfd wet gas (ref.2) - 2 x 50% sets of Gas Turbine driven booster compressors will be accommodated on BWK for processing 100 MMscfd wet gas. Each compressor has it own dedicated 021.5 3115-BWK-PRQ-021.5 suction and discharge scrubber and after cooler. 3. Condensate stabilization Condensate that will be produced needs to be stabilized (by flashing) prior to sending into the 6 Kartini pipeline. Condensate stabilization will be executed in the existing closed drain vessel, V-370 on BWA and in new closed drain vessel, V-500 on BWK. 4. Utilities Several utilities will be installed on BWK. Diesel will be taken from BWA. Supply boat landing facility is also provided diesel. 5. Cooling and separation process Since the operating pressure will be reduced from 620 psig (normal) to 175 psig, an adequate check on the existing production cooler, E-200A/B and the existing production separator, V-210 has been executed. As a result of feed study an additional production cooler e-900A/B will be installed on BWK.
3.0 SCOPE
This specification covers the preparation and acceptance criteria for the cleaning and flushing of components and piping used in lube, seal and hydraulic systems on Solar packages. Proper cleaning and flushing will remove the contamination built into components and systems before operation so that sensitive components do not fail prematurely. Components to be cleaned and flushed include, but may not be limited to the following: o Lube oil supply and drain lines o Seal oil supply and drain lines o Servo system supply and drain lines o Hydraulic start system supply and drain lines o Power take off system supply and drain lines 021.5 3115-BWK-PRQ-021.5 o Lube oil reservoir level control (auto fill) system Seal oil interconnect lines o Lube oil coolers o Lube oil interconnect lines
Reservoirs, tanks, and tank vent piping require mechanical cleaning only, per Appendix A.
Note: this specification covers the flushing requirements for components (such as the turbine package, the lube oil cooler assembly and interconnect piping) both, at the manufacturing plant and in the field. The procedures described herein have a universal application.
The turbine package is normally flushed prior to delivery and only the external cooler interconnect lines and the coolers need to be flushed in the field if the turbine package integrity is maintained and if the fill oil meets the cleanliness requirements of Section 7.0 of this specification. Any residual debris on the turbine package that is generated during shipment should be easily and immediately removed with the package filter.
The lube oil coolers are pre-flushed, to the cleanliness levels of this specification, at the suppliers facility, but a field flushing of the oil cooler is recommended as a result of external factors related to transportation and storage prior to the lube oil cooler installation.
Any interconnect piping that is used to connect the cooler to the package shall be cleaned to the Acceptance Criteria of this specification, as shown in section 7.0.
4.0 REFERENCES
Solar Specifications
ES2184 Cleaning and flushing of Hydraulic System / Components ES 9-224 Specification For Lubricating Oils For Use In Solar Gas Turbines 021.5 3115-BWK-PRQ-021.5
ES 9-248 Corrosion Preventive Oil For Long Term Preservation
Other
ISO 4406 ISO Cleanliness Code ISO 11171 Calibration of Automatic Particle Counters
ASTM D6439 -05 Standard Guide for Cleaning, Flushing, and Purification of Steam, Gas, and Hydroelectric Turbine Lubrication Systems
5.0 PREPARATION FOR FLUSHING
Rust, scale, machining chips, grit blast, weld slag, etc. shall be thoroughly removed from all tanks, vessels, pipes, etc. prior to flushing.
Tank internal surfaces, tank vent pipi ng and vessels shall be cleaned per Appendix A. Pickling and passivation of carbon steel pipe work and equipment shall be treated, prior to being flushed, as per Appendix B. Stainless steel piping is recommended, as it does not need to be pickled. Interconnect piping needs to be designed in a fashion that facilitates proper cleaning, as referred by ASTM D6439 -05. Sensitive components (bearings, seals, valve, etc) shall be removed or bypassed during the cleaning and flushing to avoid contamination.
Equipment required: (See Figure 1 for typical flushing system)
1. Flushing pump of sufficient capacity. 2. Flushing fluid heater. 3. Flushing fluid filter rated at 5 micron with an efficiency of 99.5% or better (Beta ratio, 25=200 or better) to remove contamination from flushing loop. 4. Flushing fluid strainer(s) (100 mesh or finer) or filter bag(s) (25 micron or finer) at end of each pipe run or component being flushed for cleanliness verification. 021.5 3115-BWK-PRQ-021.5 5. Particle Counter (per ISO 11171) to determine fluid cleanliness (ISO 4406) or optical filter patch kit. 6. Flow measurement device for each piping leg or component. 7. Thermometer (s). 8. Dead blow hammers or pneumatic vibrators. 9. Flushing fluid that is compatible with the mineral based oils in Solar ES 9- 224. 10. Flushing oil reservoir. The reservoir is normally contained in a flushing rig external to the package. However, if the package lube from the lube oil tank is used to flush, then an extra flush loop filter should be installed where the flushing oil re -enters the tank (see Fig.1, Note 4).
6.0 PROCEDURE
The following flushing sequence is required to minimize the possibility of contamination of components and assemblies. It is to be followed at the manufacturing facilities and in the field. Adherence to this sequence as prescribed in Figure 1, will substantially minimize the effort and the time necessary to successfully complete the flushing operations. Each flow line, cooler, etc. shall be flushed at a flow rate and temperature so that a minimum Reynolds number of 4000 is achieved through each section, or 150% of design flow, whichever is applicable.
Required Flushing Sequence a) Pre-filter the package fill oil or flushing oil to ISO 16/14/12 cleanliness level. b) Loop flush/filter the flushing rig, and any associated piping, that is considered part of the flushing system, at the maximum capacity of the rig/ flushing system to ISO 16/14/12 and no 100 -mesh screen captured particles. (Note: Steps a & b can be done together if the flushing rig has its own oil reservoir). c) (This step does not appl y for cooler manufacturers.) Do not flush package oil lines through the bearings of the engine, driven equipment, and 021.5 3115-BWK-PRQ-021.5 gearboxes. Disconnect package oil lines from bearing inlet ports, and loop these lines back to the flushing reservoir. Then flush/filter to ISO 16/14/12 and no 100 mesh screen captured particles. d) (Thi s step does not appl y for cool er manufacturers.) Add the off-skid cooler interconnect piping to the flush loop (without package or cooler connection) and flush/filter to ISO 16/14/12 and no 100 mesh screen captured particles. Other means of cleaning the cooler interconnect piping may be used, however, the same ISO 16/14/12 cleanliness requirements shall be met.
7.0 ACCEPTANCE CRITERIA
The following flushing acceptance criteria shall be met for the following conditions. A. Flushing of components at the manufacturing facility: such as turbine package and lube oil cooler assembly shall meet Section 7.1 and 7.2. B. Field flushing of: the oil fill, flushing rig, cooler lines and cooler assembly shall meet Section 7.1 at a minimum. 7.1 The ISO 4406 cleanliness code range numbers for 4, 6 and 14 micron levels are 16/14/12 or lower (particle counter calibration per ISO 11171). 7.2 There are no visible particles on the 100 mesh screen, or no more than 5 non-metallic particles no larger than 0.010 inch (0.254 mm) in the 25 micron ba g(s).
8.0 POT FLUSH PROCEDURE
After flushing, the piping, system, and components shall be sealed with metal blind flanges or metal plugs to prevent recontamination. If the piping or component will be in storage for any length of time it shall be completely drained and flushed with preservative oil per Solar ES 9-248 or partially filled with a vaporizing preservative oil that is compatible with the mineral based oils in Solar ES 9-224. Preservative 021.5 3115-BWK-PRQ-021.5 oils shall be filtered to meet the cleanliness requirements of this specification. Tanks and vessels shall be preserved per Appendix B.
The Reynolds number can be calculated by:
Nr= 3160.GPM CS.D
Where : GPM =flushing fluid flow rate - gallons per minute CS =flushing fluid viscosity - centistokes D =pipe/tube inside diameter - inches
Table 1 shows the minimum required flow rates for several pipe and tube sizes. Reynolds numbers in excess of 4000 will increase the effectiveness of the flush and will decrease the flushing time required to achieve the required cleanliness. Proper cleaning of individual details before assembly as well as clean assembly processes will also reduce flush times and reduce contamination hideout.
9.0 LUBE OIL COOLERS
Air/Oil Coolers Air to oil coolers are to be flushed per the procedure shown in section 4.0 and shall meet the cleanliness acceptance criteria of section 5.0 of this specification.
Water to Oil Coolers 1. Plate and Frame Water to Oil Coolers Since the plate and frame type water to oil coolers can be inherently clean with clean assembly procedures and controls and since a Reynolds number of 4000 may not be achievable, these coolers should only need to be flushed to the following conditions. a. Flow: 1.5 times the design flow b. Temperature: 150 F 021.5 3115-BWK-PRQ-021.5 c. Duration: At least 1-hour before a fluid sample can be taken and the strainers or filter bags at the outlet of the flushing rig can be inspected. d. Direction: The direction of the oil flow shall be both in the forward and reverse, starting with the reverse direction of flow first. e. Cleanliness Acceptance Criteria: These coolers must meet the acceptance criteria of section 7.0 of this specification.
2. Shell and Tube Water to Oil Coolers On a shell and tube cooler the oil flows through the baffles and not the tubes. The pressure created inside the cooler when trying to achieve a turbulent flow that is equivalent to a 4000 Reynolds number, may surpass the vessels design pressure. Based on the above reasons, it is recommended that the shell and tube type water to oil coolers be flushed to the following conditions: a. Flow: 1.5 times the design flow b. Temperature: 150 F c. Duration: At least 1-hour before a fluid sample can be taken and the strainers or filter bags at the outlet of the flushing rig can be inspected d. Direction: The direction of the oil flow shall be both in the forward and reverse, starting with the reverse direction of flow first. e. Cleanliness Acceptance Criteria: These coolers must meet the acceptance criteria of section 8.0 of this specification.
3. Dual coolers with transfer valves assemblies Every precaution shall be taken to ensure and maximize the cleanliness of the internal sections of the transfer valve and interconnect piping assembly prior to assembly. Doing this will reduce the total flushing time required to achieve the Cleanliness Acceptance Criteria. The complete dual water to oil cooler and transfer valve assembly shall meet the same cleanliness acceptance criteria of section 7.0 of this specification prior to shipment.
021.5 3115-BWK-PRQ-021.5
FM1 - Flow Meter FS1 - Strainer, Flush Pump Suction FS2 - Filter, Flush Loop FS3 - Inspection Screen or Filter Bag FS4 - Strainer, Fill Pump Suction FS5 - Filter, Fill System FS6 - Filter, Flush Loop H1 - Heater (may be in tank) P1 - Pump, Flush Loop P2 - Pump, Fill System TI1 - Temperature Indicator VH1 - Valve, Sample
Figure 1. Typical Flushing System FS1 P1 H1 FS2 TI1 FM1 FS6 FS3 VH1 FS4 FS5 P2 SECTION OR COMPONENT BEING FLUSHED 021.5 3115-BWK-PRQ-021.5 NOTES 1. Delta P indicators across filters are required. 2. Pump relief valves are required if positive displacement pumps are used. 3. Flow control valves, bypassing for positive displacement pumps, throttling for centrifugal pumps are required. 4. If the required flushing sequence on page 2 isnt followed or if the package lube oil tank is used instead of a separate fill system, then FS6 should be installed to prevent contamination of the package lube oil tank.
TABLE 1 FLOW RATES FOR REYNOLDS NUMBER (NR) = 4000
021.5 3115-BWK-PRQ-021.5 APPENDIX A CLEANING OF OIL TANK INTERNAL SURFACES AND TANK VENT PIPING
1.0 Surface Preparation A. Abrasive blast to produce a grayish metallic near white surface with 1 mil minimum profile depth.
B. Steel plugs shall be used for thread protection during the blast and paint process. These plugs shall be removed from all threaded openings and the grit removed by using shop air or vacuuming. Brayco 785 shall be applied to the threads and plastic plugs insert ed into the ports. C. All flange gasket surfaces must be protected during the blast and paint process. Brayco 785 shall be applied to the flange gasket surfaces and shipping covers shall be installed to protect the flange surface and avoid contamination of the lube oil tank. D. All pipe assemblies that will become part of the base assembly must be blasted internally and swabbed clean before being installed. E. Lube oil tank covers are to be painted to Solar system E unless otherwise specified by engineering drawing F. Manifolds which are welded into oil tank covers shall be unpainted on the section that is internal to the tank. G. Tank associated vent piping is to be mechanically cleaned per section 2.0.
2.0 All residual grit, scale, flakes, or other foreign matter shall be thoroughly removed from the tank or piping internal surfaces before the application of Brayco 785 or other approved preservative fluid.
021.5 3115-BWK-PRQ-021.5 Pipe and manifold sections which are part of the tank assembly as well as the tank vent piping shall be thoroughly cleaned with shop air and have a clean swab or pig drawn through them until the swab or pig is clean of any detectable grit or debris.
No residual grit is permitted. No flaky rust or mill scale is permitted. The assembly shall be considered clean when foreign material such as scale, rust, metal shavings, and sand are not visible to the eye and grittiness is not detectable to the touch.
Cleaned and preserved piping shall be installed in the system and thoroughly sealed against subsequent external source contamination as soon as practical.
3.0 Application of Brayco 785 or Other Approved Preservative Fluid - Brayco 785 can be applied to a surface showing slight discoloration or oxidation provided that the surface does not have flaky rust or mill scale. Brayco 785 may be applied by spray, roller, or other means as required for coverage of all unpainted surfaces. Other approved preservative fluids shall be applied per the manufacturers instructions. 021.5 3115-BWK-PRQ-021.5
APPENDIX B PICKLING AND PASSIVATION OF PIPEWORK AND EQUIPMENT
1.0 All carbon steel piping shall be pickled to the following minimum requirements:
A. Ensure that all statutory and safety precautions are taken for carrying out the work and as determined by site conditions.
B. Piping to be cleaned shall be isolated from all equipment, machined surfaces, and non- ferrous components to avoid damage.
C. Piping shall be dismantled in suitable sections to ensure sufficient flow of fluids in each section.
D. Each section shall be degreased. Degreasing shall be performed by use of heavy duty alkaline or detergent solutions maintained at 175 to 195F for a duration sufficient to remove oils or greases in the piping. After degreasing the piping shall be thoroughly flushed with potable water to remove all traces of degreasing solution.
E. Acid cleaning or pickling shall be carried out by use of 10% solution of hot (not exceeding 150F) inhibited hydrochloric acid. The piping shall be flushed with acid solution repeatedly until cleanliness is achieved. Pickling shall continue until all loose rust, mill scale, or other foreign materials are not visible in the piping. The strength of the acid shall be monitored to maintain the required concentration and the solution shall be replaced if ferric content exceeds 0.6% by weight.
021.5 3115-BWK-PRQ-021.5 F. The piping shall be thoroughly rinsed and flushed with potable water as rapidly as possible after the acid cleaning to remove all traces of acid and iron salts to prevent rust. The rinsing/flushing shall continue for 10 minutes after the pH of the effluent water equals the pH of the in going water.
G. Passivation of piping surfaces shall be performed after the pickling and flushing. This will be done by circulating a 3% phosphoric acid solution at 160 to 175F for an adequate duration.
H. The piping shall be thoroughly rinsed after passivation with potable water. After rinsing the piping shall be drained of water and air dried with hot, dry, filtered air at 150 to 170F.
I. Piping that will not be immediately flushed with oil and put into service shall be internally coated or flushed with a preservative oil per Solar ES 9- 248, and capped with metal blind flanges or threaded plugs.