Activity ID Activity Name Original

Duration
Total Float Start Finish
2014/06 Mid Barrel 2014/06 Mid Barrel 1900
89.00 40.00 13-J un-14 08:30 PM A 16-J un-14 06:00 PM
Unit Shutdown & S Unit Shutdown & Startup
89.00 40.00 13-J un-14 08:30 PM A 16-J un-14 06:00 PM
Unit Shutdown Unit Shutdown 89.00 40.00 13-J un-14 08:30 PM A 16-J un-14 06:00 PM
1900.UNIT.S/D.1000 Remove Feed From Unit 2.00 13-J un-14 08:30 PM A 13-J un-14 10:30 PM A
1900.UNIT.S/D.190 Drain Feed Pump Line 4.00 13-J un-14 09:30 PM A 14-J un-14 12:00 AM A
1900.UNIT.S/D.200 Blind Feed Pump Line 4.00 14-J un-14 06:00 AM A 14-J un-14 08:00 AM A
1900.UNIT.S/D.1095 Take the Stabilizer Reboiler Heater RW 0030out of ser 1.00 14-J un-14 07:00 AM A 14-J un-14 08:00 AM A
1900.UNIT.S/D.1010 Hot hydrogen strip the reaction section for 12 hours 12.00 13-J un-14 09:30 PM A 14-J un-14 10:00 AM A
1900.UNIT.S/D.1032 Shutdown Release Gas Amine Contactor / Start Shut D 0.00 14-J un-14 11:00 AM A
1900.UNIT.S/D.1080 Reduce Reboiler Heater outlet 18.00 13-J un-14 09:30 PM A 14-J un-14 04:00 PM A
1900.UNIT.S/D.1030 Take the Feed Heater RW 0029 214.09 out of service 1.00 14-J un-14 01:00 PM A 14-J un-14 08:00 PM A
1900.UNIT.S/D.1100 Shut down Off Gas Compressors 1.00 13-J un-14 09:00 PM A 14-J un-14 08:00 PM A
1900.UNIT.S/D.1020 Cool Down Reactor Beds To 120 F 28.00 14-J un-14 10:00 AM A 14-J un-14 09:00 PM A
1900.UNIT.S/D.1090 Discontinue Stabilizer bottoms circulation 1.00 14-J un-14 10:00 PM A 14-J un-14 10:30 PM A
1900.UNIT.S/D.1110 Depressure the Stabilizer section to fuel 1.00 14-J un-14 11:00 PM A 15-J un-14 12:00 AM A
1900.UNIT.S/D.1035 When reactor skin temperatures approach 250 F, redu 3.00 14-J un-14 08:20 PM A 15-J un-14 12:00 AM A
1900.UNIT.S/D.1115 DePressure Unit Fuel Gas Header 3.00 14-J un-14 10:00 PM A 15-J un-14 01:00 AM A
1900.UNIT.S/D.1040 Shut down Feed/Recycle Compressors when reactor 1.00 15-J un-14 01:00 AM A 15-J un-14 02:00 AM A
1900.UNIT.S/D.1120 Pressure Stabilizer section with 40 psig N2 2.00 14-J un-14 12:00 AM A 15-J un-14 02:00 AM A
1900.UNIT.S/D.1150 Depressure the Stabilizer Section 3.00 14-J un-14 11:00 PM A 15-J un-14 02:00 AM A
1900.UNIT.S/D.210 Chemical Clean Feed Pump Line 12.00 14-J un-14 01:00 AM A 15-J un-14 06:00 AM A
1900.UNIT.S/D.1042 Depressure The Reaction Section 4.00 15-J un-14 02:00 AM A 15-J un-14 06:00 AM A
1900.UNIT.S/D.1044 Pressure Up The Reaction Section To 20-40 PSIG N2 2.00 15-J un-14 06:00 AM A 15-J un-14 08:00 AM A
1900.UNIT.S/D.1050 Drain the reaction section low points 6.00 15-J un-14 08:00 AM A 15-J un-14 11:00 AM A
1900.UNIT.S/D.1130 Drain Reboiler coils, Stabilizer feed lines, Stabilizer and 6.00 15-J un-14 07:00 AM A 15-J un-14 11:00 AM A
1900.UNIT.S/D.280 Blind Recycle Gas SystemBy Maintainence 6.00 15-J un-14 11:00 AM A 15-J un-14 05:00 PM A
1900.UNIT.S/D.1060 Perform two pressure dumps 6.00 15-J un-14 11:00 AM A 15-J un-14 06:00 PM A
1900.UNIT.S/D.1075 Turn Over Reaction System To Maintainence / TAR Co 0.00 15-J un-14 06:00 PM A
1900.UNIT.S/D.1160 Blind Stabilizer Section For Chemical Cleaning 6.00 -3.00 15-J un-14 02:00 PM A 15-J un-14 09:00 PM
1900.UNIT.S/D.180 Chemical Clean Stabilizer Section 6.00 -3.00 15-J un-14 09:00 PM 16-J un-14 03:00 AM
1900.UNIT.S/D.320 Blind Stabilizer System 6.00 -3.00 15-J un-14 02:00 PM A 16-J un-14 06:00 AM
1900.UNIT.S/D.330 Turn Over Stabilizer System To Maintainence / TAR Co 0.00 -3.00 16-J un-14 06:00 AM*
1900.UNIT.S/D.290 Steam Out Recycle Gas System 24.00 21.00 15-J un-14 06:00 PM 16-J un-14 06:00 PM
1900.UNIT.S/D.300 Turn Over Recycle Gas System to Capital 0.00 21.00 16-J un-14 06:00 PM*
Thr Fri Sat Sun Mon Tue Wed Thr
J un 09 J un 16
2014
16-J un-14 06:00 PM, 2014/06 Mid Barrel 1900
16-J un-14 06:00 PM, Unit Shutdown & Startup
16-J un-14 06:00 PM, Unit Shutdown
Remove Feed From Unit
Drain Feed Pump Line
Blind Feed Pump Line
Take the Stabilizer Reboiler Heater RW 0030out of service
Hot hydrogen strip the reaction section for 12 hours
Shutdown Release Gas Amine Contactor / Start Shut Down Of #1 DEA
Reduce Reboiler Heater outlet
Take the Feed Heater RW 0029 214.09 out of service
Shut down Off Gas Compressors
Cool Down Reactor Beds To 120 F
Discontinue Stabilizer bottoms circulation
Depressure the Stabilizer section to fuel
When reactor skin temperatures approach 250 F, reduce pressure to 250 PSIG
DePressure Unit Fuel Gas Header
Shut down Feed/Recycle Compressors when reactor beds are at 120 F or less
Pressure Stabilizer section with 40 psig N2
Depressure the Stabilizer Section
Chemical Clean Feed Pump Line
Depressure The Reaction Section
Pressure Up The Reaction Section To 20-40 PSIG N2
Drain the reaction section low points
Drain Reboiler coils, Stabilizer feed lines, Stabilizer and product lines
Blind Recycle Gas System By Maintainence
Perform two pressure dumps
Turn Over Reaction System To Maintainence / TAR Condition
Blind Stabilizer Section For Chemical Cleaning
Chemical Clean Stabilizer Section
Blind Stabilizer System
Turn Over Stabilizer System To Maintainence / TAR Condition
Steam Out Recycle Gas System
Turn Over Recycle Gas System to Capital
2014/06 Mid Barrel 1900 Mid Barrel Shutdown Schedule 15-J un-14 03:28 PM
Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Page 1 of 1 TASK filter: (Untitled Filter)_1.
(c) Primavera Systems, Inc.