Sewer Separation Projects Look Ahead June 30, to July 14, 2014

Including ongoing and projects in the construction, planning, & design phases
Submitted by :Tom Hamel
June 30-July 4
th
NO Work Chicopee Falls 4
th
of July Shutdown week
Detours & Delays:
1.Montgomery/Sheridan/North Aldenville: Phase 3A
Sheridan Street: Closed May 19 to July 11, 2014,
Montgomery Street open
Taylor Street June 12 to June 30 drainage pipe
Fitzpatrick street, Ambrose,McGertie, Columba: limited access

2.Chicopee Falls Phase C
Paving Limited access streets: Medford, Courtland, Williams, Edmond,
Kirby, Woodlawn, second reclaim of street & final grading and then binder
( base paving course)
Paving: July 11
th
- 27
th
Beauchamp Terr & Hendrick Driveway binder,
Street binder: on Medford Courtland, Woodlawn, Williams, Edmond,
Top Course paving:Frontenac, Hillcrest, Clair, and Lachine
Loaming and Seeding : Frontenac area
Week of July 1-4
th
no work in Phase C - Chicopee Falls.





3. Empire/Hearthstone/Bray/Ward
Chicopee Street : detour at intersection of Meadow and Empire June 30-
July 4
Sewer Separation Projects
1 .Montgomery/Sheridan/North Aldenville: Phase 3A
The following streets will be impacted by construction activates and
traffic will be impaired.
Installing house connections on:
Catch Basins:
Water main:
Sewer Main line:,McGertie,, Sheridan, Jennings, Cecile, Schley, Wawel,
Wymanlea.
Sewer Services: Columba,, McGertie, Sheridan
Water services:
Geoweb & Fencing Fitzpartick.
House sewer service investigations thru the area. Sheridan and Taylor
Drainage: Taylor
Misc: temp pavement every Friday,
Hydrant Use: Authorized-Hamel Street (Ludlow)-
Testing sewers throughout the area at various manholes
Columbia GAS Co. working on:
Restoration/Lawns: limited every Friday.
Final landscaping after paving in Fall 2014
Paving: August at the earliest.






2 .Chicopee Falls:
Phase C-
Paving activates:July 7-11
th
Lower Structures on Broadway, Theodore,
Thornwood, Marlborough, Smith, and Philipa.
July 14-18
th
Cleanup (loam and seed ) Chateaugay, Spoence, Richelieu, &
Quebec Beauchamp and Hendricks
July 7-11 Install backup Berm of Hendrick
Raise structures on Williams and Edmond.
This will include removal of excess material, adding gravel as needed lowering
of manholes and catch basins, grading and preparation for paving, driveways
and curbs, installing driveway aprons, berms where needed.
Reclaim,
Paving Binder:
Paving top course: Mt. Royal, Hillcrest, Lachine, Brittany- July 7-18th
Beauchamp about July 15. Hendrick on or about July 15.
Broadway on or about August 15.

Drain services :
Lawn restoration: Preliminary after paving, Final Fall 2014.


3.Willimansett and West Aldenville Sewer Project
Willimansett sewer separation project to be bid opened June 10 2014.
Notic to start intend to be given by July 7, 2014
West Aldenville sewer separation project to be bid by December 2014.







4.Empire//Bray/Hearthstone/James Street(s) Sewer & Drain projects
Grattan street: at Hearthstone detours are planned for wk of June 9 to June 20
th
..
Sewer Main: Empire, Hearthstone.
Belcher School drainage work start after July 4, 2014

Drain Main: Empire
Sewer Services: Empire

5.Nutmeg Circle : Final Clean up and punch list work.