0 оценок0% нашли этот документ полезным (0 голосов)
32 просмотров66 страниц
Analysis included the transformer high side fuse, the transformer damage curve, and the transformer low side breaker protection. Proper coordination was achieved for fault currents less than 10,000 amps. The results are discussed in more detail below.
Исходное описание:
Оригинальное название
2013-11-07 Generator Step Up Protection Coordination_eng
Analysis included the transformer high side fuse, the transformer damage curve, and the transformer low side breaker protection. Proper coordination was achieved for fault currents less than 10,000 amps. The results are discussed in more detail below.
Analysis included the transformer high side fuse, the transformer damage curve, and the transformer low side breaker protection. Proper coordination was achieved for fault currents less than 10,000 amps. The results are discussed in more detail below.
Prepared by Senergy Michael K. Ketch, P.E. Checked by Senergy J effrey H. Fenn, P.E. 11/ 07/ 13 Revision B Salkhit Generator Protection November 07, 2013
1.0 Coordination
SGC/Senergy was contracted by Leighton, LLC to complete a coordination analysis of the generator step up transformer protection. This analysis includes the transformer high side fuse, the transformer damage curve, and the transformer low side breaker protection. This does not include the generator breaker protection since the setting configuration and coordination with the kiosk transformer low voltage circuit breaker protection is the responsibility of GE. From the study, it was found that proper coordination was achieved for fault currents less than 10,000 amps. The results are discussed in more detail below.
2.0 CLIENT PROVIDED DATA / ASSUMPTIONS
Data was provided to SGC/Senergy to create a system short circuit model in the Aspen software to complete a coordination study for Salkhit Wind Farm. The same model was used to complete the generator step-up transformer protection coordination. For the assumptions to develop the original model, please reference the protection study report titled 2013-11-04 Salkhit Wind Farm Protection Study. In addition to this data, the transformer low side breaker protection was provided to determine if proper coordination between the high side transformer fuse and the low side breaker protection was achieved. The data provided includes the transformer low side breaker manual (See Appendix A) and the settings from the breaker control. The settings provided from the breaker control are as follows:
Long Time Trip: I r = 2,000 Amps = 100.0% I n
Curve Type = I 2 t Time Delay = C2 Cooling Time = Instantaneous
Short Time Trip: Inverse Time Trip = 4.0 x I r = 8,000 amps Inverse Time Delay = C2 and 0.19 seconds at 6 x I r or 12,000 amps Fixed Time Trip = 3.0 x I r = 6,000 amps Fixed Time Delay = 0.4 seconds
Instantaneous Trip: Instantaneous Trip = 5 x I r = 10,000 amps
These three components make up the protection curve for the transformer low side breaker and are all included on the graph in Figure 1. In this figure, curve A is the transformer damage curve, curve 1 is the fixed time portion of the short time trip curve, curve 2 is the inverse time curve for the short time trip curve, curve 3 is the long time Salkhit Generator Protection November 07, 2013
curve and the instantaneous curve combined, and curve 4 is transformer high side fuse curve.
3.0 COORDINATION ANALYSIS
The coordination curves are shown in Figure 1 on the next page. Note that curves 1, 2, and 3 are the curves representing the transformer low side breaker protection. Curve 2 represents the short term inverse curve and is well above all other protection and will never trip the breaker. The long term inverse curve (curve 3) is below the high side fuse curve and properly coordinates with the fuse. This curve intersects the short term definite time curve (curve 1) at 6,000 amps. Since the definite time curve operates faster than the time portion of curve 3, this element takes over from 6,000 amps until 10,000 amps. This portion of the protection also properly coordinates with the high side fuse. At 10,000 amps, the definite time curve intersects the instantaneous portion of curve 3, and since the instantaneous curve operates faster than curve 1, it takes over from 10,000 amps on. The instantaneous curve properly coordinates with the high side fuse until the acceptable time margin for proper coordination of 0.3 seconds is reached at approximately 12,000 amps. At this point, the high side fuse may be impacted even though the instantaneous element picks up first. Thus, proper coordination is achieved between the transformer low side breaker and the transformer high side fuse for all fault currents below 12,000 amps. For fault currents greater than 12,000 amps, it is possible that the transformer high side fuses and low side breaker may both operate.
Based on the GE generator breaker instantaneous setting of 8,000 amps as shown on GEs setting drawing in Appendix B, it is possible that the transformer and generator breakers will both trip instantaneously for all fault currents greater than 10,000 amps.
From this analysis, the transformer low side breaker properly coordinates with the transformer high side fuse for most available fault current. For bolted faults exceeding 10,000 amps, more than one device may operate, but will still provide adequate equipment protection. However, short of using a fuse type with different characteristics, the transformer low side breaker coordination cannot be improved on.
Salkhit Generator Protection November 07, 2013
Figure 1: Generator Step Up Transformer Coordination
10 2 3 4 5 7 100 2 3 4 5 7 1000 2 3 4 5 7 10000 2 3 4 5 7 10 2 3 4 5 7 100 2 3 4 5 7 1000 2 3 4 5 7 10000 2 3 4 5 7 CURRENT (A) S E C O N D S 2 3 4 5 7 10 20 30 40 50 70 100 200 300 400 500 700 1000 2 3 4 5 7 10 20 30 40 50 70 100 200 300 400 500 700 1000 .01 .02 .03 .04 .05 .07 .1 .2 .3 .4 .5 .7 1 .01 .02 .03 .04 .05 .07 .1 .2 .3 .4 .5 .7 1 TIME-CURRENT CURVES By For No. Comment Date I=17206.1A 1 1. YSA2 Definite Instant. Relay 8 Group1-2 0.69kV - 7 Group1-1 34.5kV 1 T 1.75MVA-1 CTR=1 Inst.=6000A Ib=17206.1A T= 0.40s 2 2. Phase relay YSA2 Short SHORT TIME TD=1 8 Group1-2 0.69kV - 7 Group1-1 34.5kV 1 T 1.75MVA-1 CTR=1 Pickup=8000.A No inst. TP@ 5.0=1.1043s Ib=17206.1A T= 2.33s 3 3. Phase relay YSA2 Long Long Time TD=1 8 Group1-2 0.69kV - 7 Group1-1 34.5kV 1 T 1.75MVA-1 CTR=1 Pickup=2000.A Inst=10000A TP@ 5.0=9.s Ib=17206.1A T= 0.00s 4 4. Fuse XRNT-40.5 XRNT-40.5 7 Group1-1 34.5kV - 8 Group1-2 0.69kV 1 T 1.75MVA-1 Current div=1.00 Time mult=1.00 Ic= 384.0A T(M. Melt)= 0.07s A A. Transf. damage curve. 1.75 MVA. Category 2 Linked to curve no. 1. Z= 6.3 percent. FAULT DESCRIPTION: Bus Fault on: 8 Group1-2 0.69 kV LL Type=B-C Salkhit Generator Protection November 07, 2013
Appendix A
Generator Step-Up Transformer
Low Voltage Breaker Manual
Salkhit Generator Protection November 07, 2013
Appendix B
GE Low Voltage Breaker
Settings Drawing
previous REV DESCRIPTION 0 3 1 CHECKED BY REVISED BY 2 GE Energy DRAWN ISSUED SEE PLM 11-MAY-2010 B.Shaw 3 GENERAL ELECTRIC COMPANY WIND ENERGY TECHNOLOGY 4 Power Distribution Cabinet Main Breaker and Synch Contactor 5 6 COMPONENT Downtower Assembly COMP NO. 7 COMP-DRW. NO. COMP-PART NO. 108W2243 107W5379P002 8 TYPE REV B 9 of = + Sh PDC 5 next 7 4 B PDC - Added note to indicate 100A FB3 fuses are used for 1.6 MW SEE PLM SEE PLM C COPYRIGHT 2010 GENERAL ELECTRIC COMPANY PROPRIETARY INFORMATION-THIS DOCUMENT CONTAINS PROPRIETARY INFORMATION OF GENERAL ELECTRIC COMPANY AND MAY NOT BE USED OR DISCLOSED TO OTHERS, EXCEPT WITH THE WRITTEN PERMISSION OF GENERAL ELECTRIC COMPANY. Documentation L1A L2A L3A Stator Voltage Feedback to AEAA (Other Devices - See One Lines) L2 T3 T1 L3 T2 L1 Q1 2000A Motor Operated L1 T1 K1 /7.6 L2 T2 L3 T3 PDC_AUX L1 T1 L2 T2 L3 T3 Q6 0.63-1A (1A) I>> I>> I>> L1B 3.9 L2B 3.9 L3B 3.9 C O N V L 1 A / 5 .0 C O N V L 2 A / 5 .0 C O N V L 3 A / 5 .0 A E A A P 1 - L 1 / = M C C / 1 8 .1 A E A A P 2 - L 2 / = M C C / 1 8 .2 A E A A P 4 - L 3 / = M C C / 1 8 .3 L1D =CFC/5.0 L2D =CFC/5.0 L3D =CFC/5.0 A E A A P 3 - L 2 / = M C C / 1 8 .3