Area at Ras-Laffan
CONTRACT: CT/RG27/L029/12
CLIENT
CONSULTANT
CONTRACTOR
TABLE OF CONTENTS
1. PROJECT INFORMATION ............................................................................................................
1.1. SCOPE OF WORK .....................................................................................................................
1.2. PROJECT WEIGHTAGE ..........................................................................................................
3. POGRESS WEIGHTAGE .................................................................................................................
4. OVERALL PROGRESS SUMMARY .............................................................................................
5. QA/QC STATUS ................................................................................................................................
6. HEATH AND SAFETY .....................................................................................................................
8. SUMMARY OF MATERIAL SUBMITTAL .................................................................................
9. SUMMARY OF DESIGN DRAWING SUBMITTAL .................................................................
10. MATERIAL SUBMITTAL LOG .....................................................................................................
11. DESIGN DRAWING SUBMITTAL LOG ..................................................................................
12. PROGRESS UPDATED WBS SUMMARY ..............................................................................
13. ONE MONTH LOOK-AHEAD ....................................................................................................
14. PROGRESS UPDATED PROGRAMME ...................................................................................
15. PROGRESS PHOTOS ....................................................................................................................
1. PROJECT INFORMATION
Project Title: CT/RG27/L029/12
Location: Ras Laffan
Client: Ras gas Company Limited
Contractor: Qatar Building Engineering Company W.L.L., (QBEC)
Project Start Date: 21 Oct 2012
Contract Duration: 28 Months
Completion for Construction Works: 16 Months
Completion for Operation & Maintenance: 12 Months
Extension of time: 90 days secured
1.1. SCOPE OF WORK
Site survey and study of the existing site situation including trial pits needed to verify the
physical characteristics of the site elements.
Engineering analysis and design for and shade structures and signages, including
irrigation piping network and electrical system based on the FEED design.
Development of the detailed engineering drawings and procedures based on the FEED
documents. Supply, install/construct, test and commission the work related to the Civil,
Structural, Plumbing and Electrical works.
Provision of new landscaping, which includes plants, trees, shrubs, ground cover and
climbers.
Provision of new irrigation piping, distribution network and associated accessories such
as drips, sprinklers, bubblers and valves.
Relocation and modifications to the existing planting, utilities, plumbing / mechanical and
lighting works according to the new works.
Maintenance of existing landscaping and planting during project execution and until the
Provisional Acceptance.
Operation and maintenance of new landscaping and irrigation for a period of one (1) year
i.e. during Warranty period.
All the associated demolition and reinstatement works resulting from the above works.
All the other works as indicated in the relevant FEED drawings.
Overall Wt.
5.00
2.39
0.91
1.70
5.00
0.43
0.92
3.65
17.00
5.91
0.66
0.66
0.66
0.66
0.66
0.66
0.66
0.66
0.66
11.09
0.34
0.61
1.49
1.13
1.15
1.77
1.40
2.17
1.02
62.00
22.00
16.00
17.00
7.00
5.00
6.00
100.00
Budgeted
Cost
1025000.31
489204.73
186363.66
349431.92
1024999.83
87172.24
189599.54
748228.05
3485000.97
1211165.46
134573.94
134573.94
134573.94
134573.94
134573.94
134573.94
134573.94
134573.94
134573.94
2273835.51
69607.21
125292.98
306271.72
232024.03
236664.51
361957.49
287709.80
445486.14
208821.63
12710002.80
4510001.07
3280000.62
3485000.74
1435000.37
1025000.30
1230000.35
20500004.53
2. POGRESS WEIGHTAGE
Activity Name
Overall Wt.
Planned Wt.
(Original BL)
Achieved Wt.
Variation
100.00%
5.00
5.00
5.00
5.00
0.00
1.1
Contractor Mobilisation
100.00%
2.39
2.39
2.39
2.39
0.00
1.2
100.00%
0.91
0.91
0.91
0.91
0.00
1.3
100.00%
1.70
1.70
1.70
1.70
0.00
ENGINEERING
100.00%
5.00
5.00
5.00
5.00
0.00
2.1
100.00%
0.43
0.43
0.43
0.43
0.00
2.2
100.00%
0.92
0.92
0.92
0.92
0.00
2.3
100.00%
3.65
3.65
3.65
3.65
0.00
100.00%
17.00
17.00
17.00
17.00
0.00
100.00%
5.91
5.91
5.91
5.91
0.00
100.00%
0.66
0.66
0.66
0.66
0.00
100.00%
0.66
0.66
0.66
0.66
0.00
100.00%
0.66
0.66
0.66
0.66
0.00
100.00%
0.66
0.66
0.66
0.66
0.00
100.00%
0.66
0.66
0.66
0.66
0.00
100.00%
0.66
0.66
0.66
0.66
0.00
100.00%
0.66
0.66
0.66
0.66
0.00
100.00%
0.66
0.66
0.66
0.66
0.00
100.00%
0.66
0.66
0.66
0.66
0.00
100.00%
11.09
11.09
11.09
11.09
0.00
100.00%
0.34
0.34
0.34
0.34
0.00
100.00%
0.61
0.61
0.61
0.61
0.00
100.00%
1.49
1.49
1.49
1.49
0.00
100.00%
1.13
1.13
1.13
1.13
0.00
100.00%
1.15
1.15
1.15
1.15
0.00
100.00%
1.77
1.77
1.77
1.77
0.00
100.00%
1.40
1.40
1.40
1.40
0.00
100.00%
2.17
2.17
2.17
2.17
0.00
PROCUREMENT
Physical %
100.00%
1.02
1.02
1.02
1.02
0.00
CONSTRUCTION
99.01%
62.00
62.00
62.00
61.39
-0.61
4.1
98.76%
18.00
18.00
18.00
17.78
-0.22
98.53%
4.00
4.00
4.00
3.94
-0.06
98.94%
12.00
12.00
12.00
11.87
-0.13
98.53%
4.00
4.00
4.00
3.94
-0.06
99.35%
13.00
13.00
13.00
12.92
-0.08
98.53%
4.00
4.00
4.00
3.94
-0.06
4.2
4.3
4.4
100.00%
7.00
7.00
7.00
7.00
0.00
60.407%
5.00
5.00
5.00
3.02
-1.98
6 FINAL DOCUMENTATION
45.667%
6.00
6.00
4.40
Phase 4 Works
100.00%
98.40%
2.74
-1.66
94.15%
-5.85%
94.15%
-4.25%
CONSULTANT
RsGas
CONTRACTOR
(RG27-L029) EPC OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN PROGRESS REPORT
Progress Status as on 30 June 2014
21-Oct-12
20-Jul-14
S - CURVE
618
94.15%
REMAINING DURATION
CUML. PLANNED %
INVOICED AMOUNT
VARIANCE
15,243,037.53
Activity Name
10%
20%
30%
40%
50%
100.00%
99.92%
Procurement
Construction
100.00%
99.01%
Construction
100.00%
Testing/Com
10%
45.67%
PLANNED %
100
YET TO SUBMIT0 0 19
UNDER REVIEW0 0
REVISED2
02 408
APPROVED
SUBMITTED
TOTAL NO
222
183
45
150
250
300
350
400
450
500
TOTAL NO
IFC
CODE A
CODE B
CODE D
CUM.
Design Calculation
18
18
18
YET TO
SUBMIT
0
General
26
14
12
26
12
61
61
61
20
20
20
Irrigation
23
23
23
Plumbing
20
12
13
Instrumentation
Electrical
TOTAL NO
45
31
14
45
14
229
183
14
25
222
34
Item Description
Observation Card
Security Incident
Item Description
Near Miss
B-Safe Checklist
MAN HOURS
726
74,244
7,260
748,174
0
Total PTW
Item Description
29
All
1,784
Good
0
53
3,235
This Week
136
26
155
150
SUBMITTED
62
200
250
300
42
UNDER
REVIEW
0
APPROVED
REVISED
350
YET TO
SUBMIT
0
42
5.00
5.00
0.00
2.39
2.39
0.00
100.00%
0.91
0.91
0.91
0.91
0.00
100.00%
1.70
1.70
1.70
1.70
0.00
ENGINEERING
100.00%
5.00
5.00
5.00
5.00
0.00
100.00%
0.43
0.43
0.43
0.43
0.00
100.00%
0.92
0.92
0.92
0.92
100.00%
3.65
3.65
3.65
3.65
0.00
PROCUREMENT
100.00%
17.00
17.00
17.00
17.00
0.00
100.00%
5.91
5.91
5.91
5.91
0.00
100.00%
0.66
0.66
0.66
0.66
0.00
Foundation bolts
100.00%
0.66
0.66
0.66
0.66
0.00
100.00%
0.66
0.66
0.66
0.66
0.00
100.00%
0.66
0.66
0.66
0.66
0.00
Signage structures
100.00%
0.66
0.66
0.66
0.66
0.00
Fountain sculpture
100.00%
0.66
0.66
0.66
0.66
0.00
100.00%
0.66
0.66
0.66
0.66
0.00
100.00%
0.66
0.66
0.66
0.66
0.00
100.00%
0.66
0.66
0.66
0.66
0.00
100.00%
11.09
11.09
11.09
11.09
0.00
100.00%
0.34
0.34
0.34
0.34
0.00
Foundation bolts
100.00%
0.61
0.61
0.61
0.61
0.00
100.00%
1.49
1.49
1.49
1.49
0.00
100.00%
1.13
1.13
1.13
1.13
0.00
Signage structures
100.00%
1.15
1.15
1.15
1.15
0.00
Fountain sculpture
100.00%
1.77
1.77
1.77
1.77
0.00
100.00%
1.40
1.40
1.40
1.40
0.00
100.00%
2.17
2.17
2.17
2.17
0.00
100.00%
1.02
1.02
1.02
1.02
0.00
CONSTRUCTION
99.01%
62.00
62.00
62.00
61.39
-0.61
98.76%
18.00
18.00
18.00
17.78
-0.22
-0.06
98.53%
4.00
4.00
4.00
3.94
98.94%
12.00
12.00
12.00
11.87
-0.13
98.53%
4.00
4.00
4.00
3.94
-0.06
99.35%
13.00
13.00
13.00
12.92
-0.08
-0.06
Phase 4 Works
Electrical
25
25
21
19
136
110
19
98.53%
4.00
4.00
4.00
3.94
100.00%
7.00
7.00
7.00
7.00
0.00
60.41%
5.00
5.00
5.00
3.02
-1.98
FINAL DOCUMENTATION
45.67%
6.00
6.00
4.40
100.00%
98.40%
2.74
-1.66
94.15%
-5.85%
94.15%
-4.25%
NOTE:
40.00%
0
3,235
YTD 2014
0
Year 2014
447
447
Safety Walkabouts
26
17
JSA / RA / Safety
Reviews
10
B-Safe Meetings
16
39
20.00%
0.00%
Name
Submission
Prepared By
0.00
1,784
0
121
121
121
5.00
2.39
27
Year 2014
121
5.00
2.39
26
Variation
100.00%
29
155
Achieved Wt.
100.00%
100.00%
Concern
156
Planned Wt.
(Revised BL)-RGCP472-PEP-QTR-001
REV. D)
Contractor Mobilisation
29
60.00%
YTD 2014
110
Planned Wt.
(Original BL)
80.00%
This Week
100
62
Shade Structure
21 7
29
25
29
25
50
Safety Inspections
Safety
Representation in
Meetings
Civil / Architecture
Total
Activity Summary
0
Environment Incident
27
624
624
TOTAL NO
Fountain
424
229
200
19
Overall Wt.
70.12%
50
ACTUAL %
100.00%
61 20 23 1
0 31
61 20 23 20 1
-39.59%
Final Document
-27.70%
100.00%
45
-0.99%
Physical
%
100.00%
20 23 131
61
-0.08%
73.37%
-0.42%
Testing/Com
60.41%
Final Document
Mar-14
Apr-14
May-14
Jun-14
Jul-14
Jan-14
Feb-14
Dec-13
Oct-13
Time
Nov-13
Sep-13
Jul-13
Aug-13
Jun-13
Apr-13
May-13
Mar-13
Jan-13
Feb-13
Dec-12
Nov-12
Oct-12
0%
Engineering
Procurement
20%
0.00%
50%
30%
Preliminary
25%
40%
90% 100%
0%
50%
Engineering
80%
-25%
60%
100.00%
99.58%
70%
-50%
: 94.15%
100.00%
100.00%
100.00%
% Completion
Actual Progress
70%
Preliminary
100.00%
80%
60%
121
Days of Month
100%
90%
50
REMAINING INVOICE
% Completion
TOTAL AMOUNT
42
ACTUAL PROGRESS
42
PLANNED PROGRESS
COMPLETED DURATION
42
PROJECT DURATION
150
100
20,950,917.53
20,950,917.53
ACTUAL
98.40%
638
PLANNED
MANPOWER HISTOGRAM
INVOICE STATUS
69
5,707,880.00
PROGRESS
-4.25%
121
PROJECT DURATION
CLIENT - RasGas
69
20
Manpower (Nos.)
KEY INFORMATION
Designation
Ahamed Ziyath
Reviewed By
Nabhan. S Al Qasem
Endorsed By
Bhaskar Challa
Signature
Date
Remarks
4. QA/QC STATUS
Documents Status:
Status
Total
Submitted
(Approved)
Submitted
Balance (Fountain )
23
23
Document
ITP
Procedures
Submitted
(Method of
Statements)
Balance (Fountain
works)
Remarks
IFC
IFC
IFC
Accepted
Rejected
Remark
s
Cancelled
Discipline
CA
EL
MA
CA
EL
MA
CA EL MA
CA EL
MA
13
02
04
13
02
04
01 00
00
00
00
00
724
68
90
724
65
89
26 03
01
18
01
00
Cumulative
RFI
QUALITY OBJECTIVES
Sl.
No.:
K.P.I /
QUALITY OBJECTIVES
TERGET
RESPONSIBILITY
FREQUENCY OF
REVIEW
RESULTS ACHIEVED
1)
P.M / C.M.
Quarterly
96.7%
2)
P.M / C.M.
Quarterly
99.00%
28-Jun
To
3-Jul
2014
529
INCIDENT:
Current This
Week Month
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
Days
Year to
Cumm PTD
Date
0
0
0
0
1
4
0
0
1
5
0
0
0
0
1
4
0
0
1
5
st
Period
nd
1 Quarter 2
rd
th
Quarter 3 Quarter 4 Quarter Cumulative
TRIR
0.00
0.00
0.00
0.00
0.00
LTIR
0.00
0.00
0.00
0.00
0.00
No.
CONTRACTOR
On Shore
Man Hours
Off Shore
121
On Shore
Off Shore
Total Man
Hours
6,560
6,560
6
7
8
9
Sub Total
776,824
121
6,560
6,560
776,824
770,264
121
770,264
Activity Summary
Item Description
Current Week
YTD 2013
Year 2013
Year 2012
Item Description
Current
Week
YTD
.- VE
.- VE
.- VE
.- VE
16
1811
1,811
NA
B-Safe Checklist
161
Observation Card
Item Description
All
Good
40
40
NA
NA
3275
3275
Total
Concern
NA
Current Week
YTD
Safety Inspections
453
Safety Walkabouts
JSA / RA / Safety Reviews
0
0
26
10
B-Safe Meetings
Safety Representation in Meetings
0
0
16
39
Item Description
Total % Safe
Update
Attendants
Total Monthly
Man-power
% (Percentage
Attended)
75
247
30%
Rev 1 - Jan 2013
C
C
C
C
Time
Jul-14
Jun-14
May-14
Apr-14
CUML. PLANNED %
Mar-14
Feb-14
Jan-14
Dec-13
Nov-13
Oct-13
S - CURVE
Sep-13
Aug-13
Jul-13
Jun-13
May-13
Apr-13
Mar-13
Feb-13
Actual Progress
Jan-13
80%
Dec-12
90%
Nov-12
Oct-12
% Completion
6. PROGRESS S-CURVE
CUML. ACTUAL %
100%
70%
60%
50%
40%
30%
20%
10%
0%
CODE
D
0
Cumulative Total
Remarks
Remaining
18
0
12
26
12
61
61
Shades
15
15
15
20
20
20
23
23
23
Plumbing
20
12
13
Instrumentation
Electrical
45
31
14
45
14
TOTAL
229
183 0
14
25
222
34
Regency
- New
design
Regency
- New
design
Cumulative Total
Remarks
Remaining
18
0
26
12
61
61
Shades
15
15
15
20
20
20
23
23
23
Plumbing
20
12
13
Instrumentation
Electrical
45
31
14
45
14
TOTAL
229
183 0
14
25
222
34
Regency
- New
design
Regency
- New
design
ENGINEERING, PROCUREMENT AND CONSTRUCTION OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN
PROCUREMENT LOG
LEGEND
A
Approved
Approved W Comments
MANUFACTURER
QTY REQD.
UNIT
Reviewed With No
Comments
SUBMITTAL
SUBMITTAL NO.
DESCRIPTION OF MATERIAL
SPECIFICATION
MODEL
COUNTRY OF
ORIGIN
PLAN DATE
REV
Reviwed with
Comments
Submitted
Rejected
APPROVAL
PROCUREMENT
ACTUAL
REQD DATE OF
APPROVAL
ACTUAL DATE OF
APPROVAL
STATUS
ACTUAL DATE OF
ORDER
EXPECTED DATE OF
DELIVERY
ACTUAL DATE OF
DELIVERY
11
12
13
14
15
16
17
18
19
10
RGX-S-64-1320-902
3/12/2013
3/27/2013
3/26/2013
3/28/2013
3/30/2013
4/24/1913
2/5/2013
AS REQUIRED
CIVIL / ARCHITECTURAL
RGCP-472-CA-001
READYMIX CONCRETE
Qatar
800.00
RGCP-472-CA-002
WASHED SAND
50mm thick
Qatar
Qatar National
Cement Company
668.64
RGX-S-80-134-003A
3/12/2013
5/5/2013
3/26/2013
6/5/2013
3/30/2013
5/1/2013
2/5/2013
AS REQUIRED
RGCP-472-CA-003
DUNE SAND
S-80-134A-003
Qatar
Qatar National
Cement Company
800.00
m3
S-80-134A-003
3/12/2013
3/4/2013
3/26/2013
3/11/2013
3/30/2013
5/1/2013
2/5/2013
AS REQUIRED
RGCP-472-CA-004
PAVING TILES
Qatar
Al-Sehmiah Cement
Products Factory
7395.00
m2
S-80-134A-003
3/12/2013
12/31/2012
3/26/2013
1/22/2013
3/30/2013
4/17/1913
10/5/2013
5/5/2013
3254.00
m2
S-80-134A-003
3/12/2013
12/31/2012
3/26/2013
1/22/2013
3/30/2013
4/17/1913
10/5/2013
5/5/2013
RGCP-472-CA-004
PAVING TILES
200mmX100mmX60mm Gray
Qatar
Al-Sehmiah Cement
Products Factory
RGCP-472-CA-004
PAVING TILES
200mmX100mmX60mm Red
Qatar
Al-Sehmiah Cement
Products Factory
2827.00
S-80-134A-003
3/12/2013
2/21/2013
3/26/2013
2/28/2013
3/30/2013
4/17/1913
10/5/2013
5/5/2013
RGCP-472-CA-004
PAVING TILES
200mmX100mmX60mm Yellow
Qatar
Al-Sehmiah Cement
Products Factory
168.00
m2
RG6-S-00-1317-901
3/12/2013
2/27/2013
3/26/2013
3/7/2013
3/30/2013
4/17/1913
10/5/2013
5/5/2013
34.00
tons
RGX-S-80-134-003A
3/12/2013
5/5/2013
3/26/2013
6/5/2013
3/30/2013
4/24/1913
1/5/2013
EXSTOCK
10391.00
S-80-134A-003, 2.2.16
3/12/2013
4/16/2013
3/26/2013
4/18/2013
3/30/2013
4/17/1913
2/5/2013
5/5/2013
8/27/2013
8/27/2013
RGCP-472-CA-005
CEMENT
OPC S-80-134A-003
Qatar
Qatar National
Cement Company
RGCP-472-CA-006
KERBSTONES
150mmX305mm
Qatar
Al-Sehmiah Cement
Products Factory
RGCP-472-CA-006-1
RGCP-472-CA-007
STEEL REINFORCEMENT
20mm,16mm,12mm,10mm
Qatar
Qatar Steel
91.00
tons
3/12/2013
12/31/2012
3/26/2013
1/2/2013
3/30/2013
4/22/1913
5/5/2013
5/5/2013
RGCP-472-CA-007
STEEL REINFORCEMENT
8mm
Qatar
Qatar Steel
1.00
tons
3/12/2013
12/31/2012
3/26/2013
1/2/2013
3/30/2013
4/22/1913
5/5/2013
5/5/2013
RGCP-472-CA-008
450mmx450mmX60mm
Qatar
Al-Sehmiah Cement
Products Factory
500.00
m2
S-80-134A-003 ,2.2.7
3/12/2013
5/5/2013
3/26/2013
6/5/2013
3/30/2013
4/17/1913
10/5/2013
5/5/2013
RGCP-472-CA-009
POLYTHELENE SHEET
1000 Guage
Qatar
Al-Moudi Plastic
Factory
4100.00
m2
RGX-S-64-1320-902
3/12/2013
2/21/2013
3/26/2013
2/28/2013
3/30/2013
4/21/1913
5/5/2013
5/5/2013
RGCP-472-CA-010
PROTECTION BOARD
6mm
Qatar
Sodamco-Qatar W.L.L
3311.00
m2
RGXS-64-1320-902-01
3/12/2013
2/21/2013
3/26/2013
2/28/2013
3/30/2013
4/23/1913
5/5/2013
5/5/2013
RGCP-472-CA-010A
PROTECTION BOARD
9/4/2014
RGCP-472-CA-011
5/22/2013
3/30/2013
12/5/2013
20/05/2013
RGCP-472-CA-012
AGGREGATE
5/27/2013
3/30/2013
20-5-2013
15/05/2013
RGCP-472-CA-013
5/27/2013
3/30/2013
25-5-2013
20/05/2013
17-Sep-13
RGCP-472-CA-013-1
RGCP-472-CA-014
Qatar
2CM
Sodamco-Qatar W.L.L
Qatar
6621.56
m2
RGX-S-64-1320-902-01
3/12/2013
5/21/2013
1335.07
m3
S-80-134A-003
3/12/2013
5/23/2013
no.
RG6-S-00-134A-010
3/12/2013
5/21/2013
Qatar
5CM
5/25/2013
Kiswok
29
Nos
RG6-S-00-134A-010
08-09-13
Qatar
Al-Sehmiah Cement
Products Factory
4614.13
D-80-134A-104
3/12/2013
2/24/2013
3/26/2013
3/4/2013
3/30/2013
4/17/1913
6/5/2013
5/5/2013
Qatar
Modern Building
Accessories Factory
1000.00
no.
S-80-134A-0095
3/12/2013
2/24/2013
3/26/2013
3/4/2013
3/30/2013
4/29/2013
5/5/2013
5/5/2013
26701.36
m2
S-80-134A-003
3/12/2013
2/24/2013
3/26/2013
3/4/2013
3/30/2013
4/23/1913
20-5-2013
10/5/2013
2000.00
m2
S-80-134A-003
3/12/2013
2/21/2013
3/26/2013
3/4/2013
3/30/2013
4/27/1913
10/5/2013
5/5/2013
S-80-134A-003
25-Nov-13
3/26/2013
30-Nov-13
3/30/2013
25-5-2013
15/06/2013
RGCP-472-CA-015
PLASTIC SPACERS
7CM
RGCP-472-CA-016
GEOTEXTILE MEMBRANE
1000G
RGCP-472-CA-018
MASONARY BLOCKS
200mm
RGCP-472-CA-020
20mm
RGCP-472-CA-021
S-80-134A-003
3/12/2013
5/15/2013
3/26/2013
5/22/2013
3/30/2013
25-5-2013
15/06/2013
RGCP-472-CA-022
GROUT
S-80-134A-003
05-Aug-13
5/21/2013
3/26/2013
8/19/2013
3/30/2013
25-5-2013
15/06/2013
RGCP-472-CA-023
KERBSTONE PAINT
S-80-134A-003
3/12/2013
8/17/2013
8/19/2013
25-5-2013
15/06/2013
RGCP-472-CA-024
SUBBASE
S-80-134A-003
3/12/2013
5/15/2013
5/22/2013
25-5-2013
15/06/2013
Qatar
Al-Sedriah Cement
Products Factory
Page 1 of 9
3/26/2013
3/30/2013
6/5/2013
6/5/2013
Updated on : 7/7/2014
ENGINEERING, PROCUREMENT AND CONSTRUCTION OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN
PROCUREMENT LOG
LEGEND
A
Approved
Approved W Comments
MANUFACTURER
QTY REQD.
UNIT
Reviewed With No
Comments
SUBMITTAL
SUBMITTAL NO.
DESCRIPTION OF MATERIAL
SPECIFICATION
MODEL
COUNTRY OF
ORIGIN
PLAN DATE
REV
Reviwed with
Comments
APPROVAL
ACTUAL
REQD DATE OF
APPROVAL
PROCUREMENT
ACTUAL DATE OF
APPROVAL
STATUS
RGCP-472-CA-025
24-Jul-13
25-Jul-13
RGCP-472-CA-027
ROAD MARKING
11-Jul-13
18-Jul-13
Page 2 of 9
Submitted
Rejected
ACTUAL DATE OF
ORDER
EXPECTED DATE OF
DELIVERY
ACTUAL DATE OF
DELIVERY
Updated on : 7/7/2014
ENGINEERING, PROCUREMENT AND CONSTRUCTION OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN
PROCUREMENT LOG
LEGEND
A
Approved
Approved W Comments
MANUFACTURER
QTY REQD.
UNIT
Reviewed With No
Comments
SUBMITTAL
SUBMITTAL NO.
RGCP-472-CA-028
RGCP-472-CA-029
DESCRIPTION OF MATERIAL
SPECIFICATION
MODEL
COUNTRY OF
ORIGIN
Reviwed with
Comments
APPROVAL
STATUS
28-Jul-13
24-Jul-13
25-Jul-13
REV
24-Jul-13
ACTUAL
REQD DATE OF
APPROVAL
PROCUREMENT
ACTUAL DATE OF
APPROVAL
PLAN DATE
RGCP-472-CA-030
08-Sep-13
17-Sep-13
RGCP-472-CA-031
WATERPROOF MENBRANE
20-Aug-13
26-Aug-13
RGCP-472-CA-032
14-Aug-13
8/19/2013
RGCP-472-CA-033
25-Nov-13
30-Nov-13
RGCP-472-CA-034
25-Nov-13
30-Nov-13
RGCP-472-CA-035
SODAMCO
31-Aug-13
10/23/2013
24-Oct-13
RGCP-472-CA-036
SODAMCO
31-Aug-13
10/23/2013
24-Oct-13
RGCP-472-CA-037
31-Aug-13
05-Sep-13
08-Sep-13
17-Sep-13
25-Sep-13
02-Oct-13
RGCP-472-CA-039
RGCP-472-CA-040
14-Sep-13
19-Sep-13
RGCP-472-CA-041
19-Sep-13
02-Oct-13
RGCP-472-CA-042
29-Dec-13
08-Jan-14
RGCP-472-CA-043
25-Nov-13
27-Nov-13
28-Jan-14
02-Feb-14
18-Nov-13
20-Nov-13
01-Jan-14
08-Jan-14
01-Jan-14
08-Jan-14
13-Nov-13
20-Nov-13
23-Nov-13
27-Nov-13
23-Nov-13
27-Nov-13
RGCP-472-CA-038
RGCP-472-CA-043A
RGCP-472-CA-044
RGCP-472-CA-045
RGCP-472-CA-047
RGCP-472-CA-048
RGCP-472-CA-049
RGCP-472-CA-052
RGCP-472-CA-053
22-Dec-13
12-Jan-14
RGCP-472-CA-054
22-Dec-13
12-Jan-14
RGCP-472-CA-056
Bonding Agent
09-Apr-14
17-Jun-14
29-Apr-14
13-Apr-14
09-Jun-14
RGCP-472-CA-057
RGCP-472-CA-058
ACTUAL DATE OF
ORDER
EXPECTED DATE OF
DELIVERY
ACTUAL DATE OF
DELIVERY
RGCP-472-CA-059
13-Apr-14
09-Jun-14
RGCP-472-CA-060
14-Apr-14
17-Jun-14
RGCP-472-CA-061
06-Jun-14
12-Jun-14
Page 3 of 9
Submitted
Rejected
Updated on : 7/7/2014
ENGINEERING, PROCUREMENT AND CONSTRUCTION OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN
PROCUREMENT LOG
LEGEND
A
Approved
Approved W Comments
MANUFACTURER
QTY REQD.
UNIT
Reviewed With No
Comments
SUBMITTAL
SUBMITTAL NO.
DESCRIPTION OF MATERIAL
SPECIFICATION
MODEL
COUNTRY OF
ORIGIN
PLAN DATE
RGCP-472-CA-062
REV
Reviwed with
Comments
Submitted
Rejected
APPROVAL
ACTUAL
REQD DATE OF
APPROVAL
ACTUAL DATE OF
APPROVAL
PROCUREMENT
STATUS
ACTUAL DATE OF
ORDER
EXPECTED DATE OF
DELIVERY
ACTUAL DATE OF
DELIVERY
Page 4 of 9
Updated on : 7/7/2014
ENGINEERING, PROCUREMENT AND CONSTRUCTION OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN
PROCUREMENT LOG
LEGEND
A
Approved
Approved W Comments
MANUFACTURER
QTY REQD.
UNIT
Reviewed With No
Comments
SUBMITTAL
SUBMITTAL NO.
DESCRIPTION OF MATERIAL
SPECIFICATION
MODEL
COUNTRY OF
ORIGIN
Reviwed with
Comments
Submitted
Rejected
APPROVAL
PROCUREMENT
PLAN DATE
REV
ACTUAL
REQD DATE OF
APPROVAL
ACTUAL DATE OF
APPROVAL
STATUS
ACTUAL DATE OF
ORDER
EXPECTED DATE OF
DELIVERY
ACTUAL DATE OF
DELIVERY
S-80-134A-003
Qatar
Qatar Steel
361.00
m2
RG6-D-00-1330-002
4/6/2013
2/26/2013
4/18/2013
3/4/2013
4/22/2013
5/1/2013
6/2/2013
5/30/2013
RGCP-472-CT-002
S-80-134A-003
Qatar
Juton Paints
104.00
m2
RG6-D-00-1330-004
4/6/2013
2/26/2013
4/18/2013
3/4/2013
4/22/2013
5/1/2013
6/2/2013
5/30/2013
RGCP-472-CT-003
S-80-134A-003
France
Ferrari
S-80-134A-003
4/6/2013
5/5/2013
4/18/2013
6/5/2013
4/22/2013
6/2/2013
5/30/2013
RGCP-472-CT-003D
S-80-134A-003
France
Ferrari
9/10/2013
10/23/2013
RGCP-472-CT-004
S-80-134A-003
Qatar
RGCP-472-CT-005
S-80-134A-003
Qatar
RGCP-472-CT-006
S-80-134A-003
Qatar
RGCP-472-CT-007
Qatar
SIGNAGE WORK
S-80-134A-003
RGCP-472-CT-008
RGCP-472-CT-009
RGCP-472-CT-010
RGCP-472-CT-011
RGCP-472-CT-012
RGCP-472-CT-013
Gulf Building
Material
Gulf Building
Material
146.00
Nos
RG6-D-00-1330-002
06-Mar-13
04-Mar-13
20-Mar-13
11-Mar-13
25-Mar-13
01-May-13
05-May-13
02-May-13
280.00
Lm
S-80-134-A003
06-Mar-13
19-Mar-13
20-Mar-13
27-Mar-13
25-Mar-13
08-Apr-13
05-May-13
02-May-13
Hidayath
378.00
Lm
S-80-134-A003
06-Mar-13
19-Mar-13
20-Mar-13
27-Mar-13
25-Mar-13
08-Apr-13
05-May-13
02-May-13
Gulf Building
Material
1040.00
Lm
S-80-134-A003
06-Mar-13
19-Mar-13
20-Mar-13
02-Apr-13
25-Mar-13
08-Apr-13
05-May-13
02-May-13
S-80-134-A003
06-Mar-13
19-Mar-13
20-Mar-13
24-Mar-13
25-Mar-13
08-Apr-13
05-May-13
02-May-13
UAE
3M
378.00
Qatar
Al-Jaber
320.00
no.
S-80-134-A003
06-Mar-13
19-Mar-13
20-Mar-13
24-Mar-13
25-Mar-13
08-Apr-13
05-May-13
02-May-13
S-80-134A-003
Qatar
Alubond
520.00
m2
S-80-134-A003
06-Mar-13
19-Mar-13
20-Mar-13
24-Mar-13
25-Mar-13
08-Apr-13
05-May-13
02-May-13
S-80-134A-003
Qatar
Hidayath
45.00
m2
S-80-134-A003
06-Mar-13
20-Mar-13
20-Mar-13
27-Mar-13
25-Mar-13
08-Apr-13
05-May-13
02-May-13
07-Oct-13
27-May-14
6061& 6065
By Email
RGCP-472-PI-002
RGCP-472-PI-002
RGCP-472-PI-002
RGCP-472-PI-002
RGCP-472-PI-002
RGCP-472-PI-002
RGCP-472-PI-002
RGCP-472-PI-002
RGCP-472-PI-002-1
RGCP-472-PI-003
Sleeves
RGCP-472-PI-003-1
Sleeves
Qatar
Hepworth
10.00
no.
S-80-134A-002
13-Apr-13
13-Mar-13
25-Apr-13
18-Apr-13
29-Apr-13
17-May-13
15/05/2013
Qatar
Hepworth
4.00
no.
S-80-134A-002
13-Apr-13
13-Mar-13
25-Apr-13
18-Apr-13
29-Apr-13
17-May-13
15/05/2013
Qatar
Hepworth
2.00
no.
S-80-134A-002
13-Apr-13
13-Mar-13
25-Apr-13
18-Apr-13
29-Apr-13
17-May-13
15/05/2013
Qatar
Hepworth
4.00
no.
S-80-134A-002
13-Apr-13
13-Mar-13
25-Apr-13
18-Apr-13
29-Apr-13
17-May-13
15/05/2013
Qatar
Hepworth
11.00
no.
S-80-134A-002
13-Apr-13
13-Mar-13
25-Apr-13
18-Apr-13
29-Apr-13
17-May-13
15/05/2013
Qatar
Hepworth
3.00
no.
S-80-134A-002
13-Apr-13
13-Mar-13
25-Apr-13
18-Apr-13
29-Apr-13
17-May-13
15/05/2013
Qatar
Hepworth
2.00
no.
S-80-134A-002
13-Apr-13
13-Mar-13
25-Apr-13
18-Apr-13
29-Apr-13
17-May-13
15/05/2013
Qatar
Hepworth
1.00
no.
S-80-134A-002
13-Apr-13
13-Mar-13
25-Apr-13
18-Apr-13
29-Apr-13
17-May-13
15/05/2013
Qatar
Hepworth
9.00
no.
S-80-134A-002
13-Apr-13
13-Mar-13
25-Apr-13
18-Apr-13
29-Apr-13
17-May-13
15/05/2013
21-May-13
30-May-13
01-May-13
08-May-13
29-Apr-13
21-May-13
20/05/2013
21-May-13
30-May-13
18-Mar-13
26-Mar-13
17-Mar-13
06-Jun-13
15-May-13
18-03-13
26-Mar-13
17-Mar-13
06-Jun-13
15-May-13
RGCP-472-PI-AG-001
Rain Bird
RGCP-472-PI-AG-002
Dripline
Rain Bird
Qatar
EFB-CP-R Brass
Valves
USA
Rainbird
U.S.A
RAIN BIRD
300.00
81.00
no.
S-80-134A-002
D-80-134A-70
D-80-134A-70
Page 5 of 9
13-Apr-13
26-Feb-13
12-Mar-13
17-Apr-13
Updated on : 7/7/2014
ENGINEERING, PROCUREMENT AND CONSTRUCTION OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN
PROCUREMENT LOG
LEGEND
A
Approved
Approved W Comments
MANUFACTURER
QTY REQD.
UNIT
Reviewed With No
Comments
SUBMITTAL
SUBMITTAL NO.
DESCRIPTION OF MATERIAL
SPECIFICATION
MODEL
COUNTRY OF
ORIGIN
Reviwed with
Comments
Submitted
Rejected
APPROVAL
PROCUREMENT
PLAN DATE
REV
ACTUAL
REQD DATE OF
APPROVAL
ACTUAL DATE OF
APPROVAL
STATUS
ACTUAL DATE OF
ORDER
EXPECTED DATE OF
DELIVERY
26-Feb-13
18-Mar-13
12-Mar-13
26-Mar-13
17-Mar-13
17-Apr-13
04-Jun-13
01-Jun-13
18-03-13
26-Mar-13
17-Mar-13
18-Mar-13
31-Mar-13
29-Apr-13
18-03-13
31-Mar-13
29-Apr-13
04-Jun-13
04-Jun-13
01-Jun-13
RGCP-472-PI-AG-003
Gate Valve
PEGLER
1065 Forged
Glass
USA
Pegler
RGCP-472-PI-AG-004
Rain Bird
44LRC
U.S.A
Rainbird
RGCP-472-PI-AG-005
ROTOR SPRINKLERS
Rain Bird
5500 Series
USA
Rainbird
RGCP-472-PI-AG-006
Bubblers
Rain Bird
1400 Series
U.S.A
Rainbird
D-80-134A-70
RGCP-472-PI-AG-007
Irrigation Controller
Rain Bird
ESP-LXME
Controller
U.S.A
Rainbird
D-80-134A-70
13-Apr-13
18-Mar-13
25-Apr-13
26-Mar-13
29-Apr-13
RGCP-472-PI-AG-008
Rain Bird
VB-JMB
U.S.A
Rainbird
25.00
no.
D-80-134A-70
13-Apr-13
18-Mar-13
25-Apr-13
26-Mar-13
29-Apr-13
17-Apr-13
04-Jun-13
01-Jun-13
UNI Spray
Series
U.S.A
Rainbird
200.00
no.
D-80-134A-70
13-Apr-13
18-Mar-13
25-Apr-13
26-Mar-13
29-Apr-13
17-Apr-13
04-Jun-13
01-Jun-13
13-03-13
18-Apr-13
25.00
no.
D-80-134A-70
D-80-134A-70
180.00
no.
D-80-134A-70
13-Apr-13
25-Apr-13
15-Jun-13
17-Apr-13
04-Jun-13
01-Jun-13
RGCP-472-PI-AG-009
Rain Bird
RGCP-472-PI-AG-010
Rain Bird
U.S.A
Rainbird
RGCP-472-PI-AG-011
S-80-134A-003
Qatar
Municipality
12396.17
m3
D-80-134A-70
13-Apr-13
28-Feb-13
25-Apr-13
07-Mar-13
29-Apr-13
17-Apr-13
04-Jun-13
01-Jun-13
RGCP-472-PI-AG-012
Rain Bird
U.S.A
Rainbird
5000.00
D-80-134A-70
13-Apr-13
27-Feb-13
25-Apr-13
04-Mar-13
29-Apr-13
17-Apr-13
04-Jun-13
01-Jun-13
RGCP-472-PI-AG-013
Compost
S-80-134A-003
KSA
AL Safi Fertilizer
Factory
6000.00
bag
D-80-134A-70
12-Mar-13
28-Feb-13
26-Mar-13
07-Mar-13
30-Mar-13
17-Apr-13
08-May-13
04-May-13
RGCP-472-PI-AG-014
Peat Moss
S-80-134A-003
Germany
SAB Syker
500.00
bag
D-80-134A-70
12-Mar-13
26-Mar-13
26-Mar-13
28-Mar-13
30-Mar-13
17-Apr-13
08-May-13
04-May-13
RGCP-472-PI-AG-018
PLANT LIST
S-80-134A-003
A.G
D-80-134A-71
12-Mar-13
13-Mar-13
26-Mar-13
24-Mar-13
30-Mar-13
17-Apr-13
08-Apr-13
04-May-13
RGCP-472-PI-AG-019
22-May-13
30-May-13
RGCP-472-PI-AG-020
MULCH
24-Sep-13
26-Sep-13
SAB Turba
Peat 340
200MM
D-80-134A-74
AS LISTED
Uniplast
Qatar
ACTUAL DATE OF
DELIVERY
04-Jun-13
ELECTRICAL
RGCP-472-EL-001
RGCP-472-EL-002
POLE LIGHT 6M
RGCP-472-EL-003
27-Mar-13
03-Apr-13
10-Apr-13
07-Apr-13
15-Apr-13
RGCP-472-EL-004
30-Jul-13
28-Apr-13
10-Apr-13
01-Aug-13
15-Apr-13
RGCP-472-EL-005
RGCP-472-EL-006
Qatar
Q-Light
12.00
no.
27-Mar-13
03-Mar-13
10-Apr-13
07-Mar-13
15-Apr-13
20-Apr-13
04-Jun-13
5/05/2013
Qatar
Q-Light
14.00
no.
27-Mar-13
03-Mar-13
10-Apr-13
10-Mar-13
15-Apr-13
20-Apr-13
04-Jun-13
20/05/2013
20-Apr-13
04-Jun-13
5/05/2013
04-Jun-13
20/05/2013
Qatar
Q-Light
8.00
no.
27-Mar-13
19-Feb-13
10-Apr-13
26-Feb-13
15-Apr-13
20-Apr-13
04-Jun-13
5/05/2013
Qatar
Q-Light
9.00
no.
27-Mar-13
19-Feb-13
10-Apr-13
26-Feb-13
15-Apr-13
20-Apr-13
04-Jun-13
5/05/2013
Qatar
Q-Light
8.00
no.
27-Mar-13
19-Feb-13
10-Apr-13
26-Feb-13
15-Apr-13
20-Apr-13
04-Jun-13
5/05/2013
RGCP-472-EL-007
Page 6 of 9
Updated on : 7/7/2014
ENGINEERING, PROCUREMENT AND CONSTRUCTION OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN
PROCUREMENT LOG
LEGEND
A
Approved
Approved W Comments
MANUFACTURER
QTY REQD.
UNIT
Reviewed With No
Comments
SUBMITTAL
SUBMITTAL NO.
DESCRIPTION OF MATERIAL
SPECIFICATION
MODEL
COUNTRY OF
ORIGIN
Reviwed with
Comments
Submitted
Rejected
APPROVAL
PLAN DATE
REV
ACTUAL
D-80-134A-283
27-Mar-13
18-Aug-13
REQD DATE OF
APPROVAL
PROCUREMENT
ACTUAL DATE OF
APPROVAL
STATUS
26-Aug-13
ACTUAL DATE OF
ORDER
EXPECTED DATE OF
DELIVERY
RGCP-472-EL-010
FEEDER PILLAR
RGCP-472-EL-011
CABLE LUGS
Qatar
FANCY
325.00
no.
27-Mar-13
07-Mar-13
10-Apr-13
12-Mar-13
15-Apr-13
04-Jun-13
15/05/2013
RGCP-472-EL-011
CABLE GLAND
Qatar
FANCY
55.00
no.
27-Mar-13
07-Mar-13
10-Apr-13
12-Mar-13
15-Apr-13
04-Jun-13
15/05/2013
RGCP-472-EL-012
Qatar
Al-Amer Group
300.00
no.
27-Mar-13
10-Mar-13
10-Apr-13
14-Mar-13
15-Apr-13
04-Jun-13
15/05/2013
RGCP-472-EL-013
Qatar
FANCY
200.00
no.
27-Mar-13
04-Mar-13
10-Apr-13
11-Mar-13
15-Apr-13
04-Jun-13
20/05/2013
RGCP-472-EL-013-1
25-Aug-13
26-Aug-13
27-Mar-13
18-Mar-13
18-Mar-13
15-Apr-13
04-Jun-13
20/05/2013
19-May-13
22-May-13
26-Aug-13
C
04-Jun-13
20/05/2013
04-Jun-13
15/05/2013
RGCP-472-EL-014
RGCP-472-EL-014-1
ELECTRICAL CABLES
RGCP-472-EL-014-2
RGCP-472-EL-015
RGCP-472-EL-017
Qatar
Qatar
Qatar
Al-Amer Group
1000.00
25-Aug-13
10-Apr-13
Al-Amer Group
27-Mar-13
13-Mar-13
10-Apr-13
18-Mar-13
15-Apr-13
UNIPLAST
Refrence to D-80-134A-284
section 10.6
27-Mar-13
20-Feb-13
10-Apr-13
26-Feb-13
15-Apr-13
300.00
Page 7 of 9
22-Apr-13
ACTUAL DATE OF
DELIVERY
Updated on : 7/7/2014
ENGINEERING, PROCUREMENT AND CONSTRUCTION OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN
PROCUREMENT LOG
LEGEND
A
Approved
Approved W Comments
MANUFACTURER
QTY REQD.
UNIT
Reviewed With No
Comments
SUBMITTAL
SUBMITTAL NO.
DESCRIPTION OF MATERIAL
SPECIFICATION
MODEL
COUNTRY OF
ORIGIN
Refrence to D-80-134A-284
section 10.6
Refrence to D-80-134A-284
section 10.6
Reviwed with
Comments
APPROVAL
PROCUREMENT
PLAN DATE
REV
ACTUAL
REQD DATE OF
APPROVAL
ACTUAL DATE OF
APPROVAL
STATUS
27-Mar-13
18-Mar-13
10-Apr-13
20-Mar-13
27-Mar-13
15-May-13
22-May-13
RGCP-472-EL-018
RGCP-472-EL-019
WIRING ACCESSORIES
RGCP-472-EL-020
31-Aug-13
05-Sep-13
RGCP-472-EL-021
27-Aug-13
05-Sep-13
RGCP-472-EL-022
EARTHING MATERIALS
31-Aug-13
05-Sep-13
RGCP-472-EL-023
04-Sep-13
11-Sep-13
RGCP-472-EL-024
04-Sep-13
24-Oct-13
RGCP-472-EL-025
12-Nov-13
11-Dec-13
RGCP-472-EL-026
13-Nov-13
20-Nov-13
RGCP-472-EL-027
13-Jan-14
20-Jan-14
RGCP-472-EL-028
08-Jun-14
12-Jun-14
05-Oct-13
SHEZNON
Submitted
Rejected
23-Oct-13
ACTUAL DATE OF
ORDER
EXPECTED DATE OF
DELIVERY
15-Apr-13
04-Jun-13
20/05/2013
15-Apr-13
04-Jun-13
20/05/2013
ACTUAL DATE OF
DELIVERY
FOUNTAIN
RGCP-472-PI-016
1. Fountain Nozzle
2. Jet Nozzle
3. Sculpture Water Pump
4. Cascade Water Pump
5. Jet Nozzle and Filters
6. Scupture sand filter
7. Cascade water sand filter
8. Drain Pump/Submersible Pump
9. Valve and fittings
10. Main Drain
11. Inlet for water cascade
12. Overflow filter
13. Suction / Vacuum Filter
14. Water level regulator
15. Underwater lights for nozzle
16. Underwater light for fountain base
Page 8 of 9
Updated on : 7/7/2014
ENGINEERING, PROCUREMENT AND CONSTRUCTION OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN
PROCUREMENT LOG
LEGEND
A
Approved
Approved W Comments
MANUFACTURER
QTY REQD.
UNIT
Reviewed With No
Comments
SUBMITTAL
SUBMITTAL NO.
DESCRIPTION OF MATERIAL
SPECIFICATION
MODEL
COUNTRY OF
ORIGIN
PLAN DATE
REV
Reviwed with
Comments
Submitted
Rejected
APPROVAL
ACTUAL
REQD DATE OF
APPROVAL
PROCUREMENT
ACTUAL DATE OF
APPROVAL
STATUS
ACTUAL DATE OF
ORDER
EXPECTED DATE OF
DELIVERY
ACTUAL DATE OF
DELIVERY
12-Nov-13
03-Dec-13
RGCP-472-PI-018
Gate Valve
12-Nov-13
03-Dec-13
RGCP-472-PI-019
13-Nov-13
20-Nov-13
RGCP-472-PI-020
18-Nov-13
03-Dec-13
RGCP-472-PI-021
25-Nov-13
03-Dec-13
RGCP-472-PI-022
18-Jun-14
RGCP-472-PI-023
MOTORIZED VALVES
RGCP-472-PI-024
PLC
RGCP-472-PI-025
RGCP-472-PI-026
Page 9 of 9
Updated on : 7/7/2014
Sl.
No.
Drawing Title
Drawing Number
No of
Sheets
QBEC Transmittal
Reference
Approved with
Comments
Reviewed W No
Comments
Plan
Submission
date
Rev
Submit Date
Reviewed with
Comments
Submitted
As-Built
Zone
Reply Date
Approval
Status
Rev
Approval
Status
Rev
Approval
Status
Rev
Submit Date
Reply Date
Approval
Status
DESIGN CALCULATIONS
1
C-80-134A-006
RGCP-472-T-QTR-642
16-Jan-13
17-Jan-13
23-Jan-13
17-Aug-13
21-Aug-13
05-Sep-13
30-Sep-13
IFC
C-80-134A-007
RGCP-472-T-QTR-641
21-Jan-13
24-Feb-13
27-Feb-13
08-Jul-13
25-Jul-13
05-Sep-13
30-Sep-13
IFC
All Zones
C-80-134A-008
RGCP-472-T-QTR-166
21-Jan-13
22-Jan-13
23-Jan-13
10-Feb-13
14-Feb-13
26-Feb-13
27-Feb-13
IFC
1,14
C-80-134A-009
RGCP-472-T-QTR-292
03-Feb-13
5-Feb-13
31-Mar-13
1-Apr-13
IFC
19
C-80-134A-010
RGCP-472-T-QTR-520
13-May-13
15-May-13
19-Jun-13
23-Jun-13
IFC
C-80-134A-011
RGCP-472-T-QTR-750
10-Mar-13
20-Mar-13
C-80-134A-011A
RGCP-472-T-QTR-860
C-80-134A-012
RGCP-472-T-QTR-741
03-Apr-13
10-Apr-13
C-80-134A-013
RGCP-472-T-QTR-742
03-Apr-13
11
C-80-134A-015
RGCP-472-T-QTR-698
12
C-80-134A-016
RGCP-472-T-QTR-634
13
C-80-134A-017
14
15
01-Oct-13
03-Oct-13
12-Nov-13
04-Dec-13
IFC
16-Dec-13
24-Dec-13
24-Apr-14
19-May-14
07-Oct-13
10-Oct-13
22-Oct-13
27-Oct-13
IFC
10-Apr-13
07-Oct-13
08-Oct-13
22-Oct-13
27-Oct-13
IFC
7,12,15
03-Apr-13
09-Apr-13
12-Sep-13
18-Sep-13
24-Sep-13
25-Sep-13
IFC
11
28-Apr-13
01-May-13
11-Aug-13
28-Aug-13
31-Aug-13
05-Sep-13
IFC
11
RGCP-472-T-QTR-640
11-May-13
14-May-13
18-Jul-13
04-Aug-13
12-Sep-13
23-Sep-13
IFC
C-80-134A-018
RGCP-472-T-QTR-697
14-May-13
16-May-13
16-Sep-13
18-Sep-13
24-Sep-13
25-Sep-13
IFC
C-80-134A-019
RGCP-472-T-QTR-695
05-Sep-13
09-Sep-13
16-Sep-13
18-Sep-13
24-Sep-13
26-Sep-13
IFC
16
C-80-134A-020
RGCP-472-T-QTR-696
24-Aug-13
27-Aug-13
05-Sep-13
18-Sep-13
24-Sep-13
25-Sep-13
IFC
17
C-80-134A-021
RGCP-472-T-QTR-556
29-Jun-13
30-Jun-13
08-Jul-13
10-Jul-13
16-Jul-13
29-Jul-13
IFC
18
LV Cable Schedule
C-80-134A-022
RGCP-472-T-QTR-764
05-Sep-13
05-Sep-13
29-Sep-13
29-Sep-13
13-Nov-13
01-Dec-13
IFC
19
C-80-134A-028
RGCP-472-T-QTR-639
11-Jul-13
29-Jul-13
11-Aug-13
19-Aug-13
05-Sep-13
23-Sep-13
IFC
20
C-80-134A-029
RGCP-472-T-QTR-718
18/Aug/13
22/Aug/13
24-Sep-13
26-Sep-13
05-Oct-13
06-Oct-13
IFC
21
C-80-134A-030
RGCP-472-T-QTR-827
06-Jan-14
12-Jan-14
22
C-80-134A-031
RGCP-472-T-QTR-840
22-Feb-14
23-Feb-14
23
C-80-134A-032
RGCP-472-T-QTR-854
18-Mar-14
20-Mar-14
24
C-80-134A-033
RGCP-472-T-QTR-850
11-Mar-14
11-Mar-14
25
C-80-134A-034
RGCP-472-T-QTR-895
13-May-14
29-May-14
26
C-80-134A-035
RGCP-472-T-QTR-879
24-Apr-14
24-Apr-14
27
C-80-134A-036
RGCP-472-T-QTR-884
24-Apr-14
24-Apr-14
21-Feb-13
24-Feb-13
IFC
All Zones
GENERAL
1
General Notes
D-80-134A-101
1 of 1
RGCP-472-T-QTR-085
20-Jan-13
03-Feb-13
10-Feb-13
D-80-134A-105
1 of 4
RGCP-472-T-QTR-265
17-Jan-13
23-Jan-13
31-Jan-13
21-Feb-13
3-Mar-13
24-Mar-13
26-Mar-13
IFC
All Zones
D-80-134A-105
2 of 4
RGCP-472-T-QTR-265
17-Jan-13
23-Jan-13
31-Jan-13
21-Feb-13
3-Mar-13
24-Mar-13
26-Mar-13
IFC
All Zones
D-80-134A-105
3 of 4
RGCP-472-T-QTR-265
17-Jan-13
23-Jan-13
31-Jan-13
21-Feb-13
3-Mar-13
24-Mar-13
26-Mar-13
IFC
All Zones
D-80-134A-105
4 of 4
RGCP-472-T-QTR-265
17-Jan-13
23-Jan-13
31-Jan-13
21-Feb-13
3-Mar-13
24-Mar-13
26-Mar-13
IFC
All Zones
D-80-134A-107
1 of 4
RGCP-472-T-QTR-333
17-Jan-13
23-Jan-13
30-Jan-13
21-Apr-13
22-Apr-13
IFC
All Zones
D-80-134A-107
2 of 4
RGCP-472-T-QTR-333
17-Jan-13
23-Jan-13
30-Jan-13
21-Apr-13
22-Apr-13
IFC
All Zones
D-80-134A-107
3 of 4
RGCP-472-T-QTR-333
17-Jan-13
23-Jan-13
30-Jan-13
21-Apr-13
22-Apr-13
IFC
All Zones
D-80-134A-107
4 of 4
RGCP-472-T-QTR-333
17-Jan-13
23-Jan-13
30-Jan-13
21-Apr-13
22-Apr-13
IFC
All Zones
D-80-134A-068X
1 of 5
RGCP-472-T-QTR-822
05-Mar-13
12-Mar-13
3-Apr-13
9-Apr-13
29-Dec-13
2-Jan-14
IFC
2,3,4,6,7,8,9,11
D-80-134A-068X
2 of 5
RGCP-472-T-QTR-822
05-Mar-13
12-Mar-13
3-Apr-13
9-Apr-13
29-Dec-13
2-Jan-14
IFC
2,3,4,6,7,8,9,11
D-80-134A-068X
3 of 5
RGCP-472-T-QTR-822
05-Mar-13
12-Mar-13
3-Apr-13
9-Apr-13
29-Dec-13
2-Jan-14
IFC
2,3,4,6,7,8,9,11
D-80-134A-068X
4 of 5
RGCP-472-T-QTR-822
05-Mar-13
12-Mar-13
3-Apr-13
9-Apr-13
29-Dec-13
2-Jan-14
IFC
2,3,4,6,7,8,9,11
D-80-134A-068X
5 of 5
RGCP-472-T-QTR-822
05-Mar-13
12-Mar-13
3-Apr-13
9-Apr-13
29-Dec-13
2-Jan-14
IFC
2,3,4,6,7,8,9,11
10
11
12
13
14
15
D-80-134A-103
1 of 15
RGCP-472-T-QTR-819
17-Jan-13
23-Jan-13
30-Jan-13
26-Nov-13
5-Dec-13
28-Dec-13
2-Jan-14
All Zones
16
D-80-134A-103
2 of 15
RGCP-472-T-QTR-819
17-Jan-13
23-Jan-13
30-Jan-13
26-Nov-13
5-Dec-13
28-Dec-13
2-Jan-14
All Zones
17
D-80-134A-103
3 of 15
RGCP-472-T-QTR-819
17-Jan-13
23-Jan-13
30-Jan-13
26-Nov-13
5-Dec-13
28-Dec-13
2-Jan-14
All Zones
18
D-80-134A-103
4 of 15
RGCP-472-T-QTR-819
17-Jan-13
23-Jan-13
30-Jan-13
26-Nov-13
5-Dec-13
28-Dec-13
2-Jan-14
All Zones
19
D-80-134A-103
5 of 15
RGCP-472-T-QTR-819
17-Jan-13
23-Jan-13
30-Jan-13
26-Nov-13
5-Dec-13
28-Dec-13
2-Jan-14
All Zones
20
D-80-134A-103
6 of 15
RGCP-472-T-QTR-819
17-Jan-13
23-Jan-13
30-Jan-13
26-Nov-13
5-Dec-13
28-Dec-13
2-Jan-14
All Zones
1 of 6
Updated on : 7/7/2014
Sl.
No.
Drawing Title
Drawing Number
No of
Sheets
QBEC Transmittal
Reference
Approved with
Comments
Reviewed W No
Comments
Plan
Submission
date
Rev
Submit Date
Reviewed with
Comments
Submitted
As-Built
Zone
Reply Date
Approval
Status
Rev
Approval
Status
Rev
Approval
Status
Rev
Submit Date
Reply Date
Approval
Status
21
D-80-134A-103
7 of 15
RGCP-472-T-QTR-819
17-Jan-13
23-Jan-13
30-Jan-13
26-Nov-13
5-Dec-13
28-Dec-13
2-Jan-14
All Zones
22
D-80-134A-103
8 of 15
RGCP-472-T-QTR-819
17-Jan-13
23-Jan-13
30-Jan-13
26-Nov-13
5-Dec-13
28-Dec-13
2-Jan-14
All Zones
23
D-80-134A-103
9 of 15
RGCP-472-T-QTR-819
17-Jan-13
23-Jan-13
30-Jan-13
26-Nov-13
5-Dec-13
28-Dec-13
2-Jan-14
All Zones
24
D-80-134A-103
10 of 15
RGCP-472-T-QTR-819
17-Jan-13
23-Jan-13
30-Jan-13
26-Nov-13
5-Dec-13
28-Dec-13
2-Jan-14
All Zones
25
D-80-134A-103
11 of 15
RGCP-472-T-QTR-819
17-Jan-13
23-Jan-13
30-Jan-13
26-Nov-13
5-Dec-13
28-Dec-13
2-Jan-14
All Zones
26
D-80-134A-103
12 of 15
RGCP-472-T-QTR-819
17-Jan-13
23-Jan-13
30-Jan-13
26-Nov-13
5-Dec-13
28-Dec-13
2-Jan-14
All Zones
26
D-80-134A-103
13 of 15
RGCP-472-T-QTR-819
17-Jan-13
23-Jan-13
30-Jan-13
26-Nov-13
5-Dec-13
28-Dec-13
2-Jan-14
All Zones
26
D-80-134A-103
14 of 15
RGCP-472-T-QTR-819
17-Jan-13
23-Jan-13
30-Jan-13
26-Nov-13
5-Dec-13
28-Dec-13
2-Jan-14
All Zones
27
D-80-134A-103
15 of 15
RGCP-472-T-QTR-819
17-Jan-13
23-Jan-13
30-Jan-13
26-Nov-13
5-Dec-13
28-Dec-13
2-Jan-13
All Zones
28
RG-2044
1 of 1
12-Nov-13
05-Dec-13
29
D-80-134AX-56
1 TO 35
RGCP-472-T-QTR-832
28-Jan-14
All Zones
0
28-Jan-14
02-Feb-14
All Zones
D-80-134A-102
1 of 3
RGCP-472-T-QTR-820
27-Feb-13
6-Mar-13
18-Apr-13
15-Apr-13
28-Dec-13
01-Dec-14
IFC
All Zones
D-80-134A-102
2 of 3
RGCP-472-T-QTR-820
27-Feb-13
6-Mar-13
18-Apr-13
15-Apr-13
28-Dec-13
01-Dec-14
IFC
All Zones
D-80-134A-102
3 of 3
RGCP-472-T-QTR-820
18-Apr-13
15-Apr-13
28-Dec-13
01-Dec-14
IFC
All Zones
D-80-134A-096
1 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
D-80-134A-096
2 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
D-80-134A-096
3 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
D-80-134A-096
4 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
D-80-134A-096
5 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
D-80-134A-096
6 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
10
D-80-134A-096
7 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
11
D-80-134A-096
8 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
12
D-80-134A-096
9 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
13
D-80-134A-096
10 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
14
D-80-134A-096
11 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
15
D-80-134A-096
12 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
16
D-80-134A-096
13 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
17
D-80-134A-096
14 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
18
D-80-134A-096
15 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
19
D-80-134A-096
16 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
20
D-80-134A-096
17 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
21
D-80-134A-096
18 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
22
D-80-134A-096
19 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
23
D-80-134A-096
20 of 20
RGCP-472-T-QTR-319
17-Jan-13
03-Feb-13
10-Feb-13
26-Mar-13
28-Mar-13
9-Apr-13
15-Apr-13
IFC
All Zones
24
D-80-134A-068
1 of 7
RGCP-472-T-QTR-821
11-Apr-13
27-Feb-13
6-Mar-13
18-Apr-13
21-Apr-13
29-Dec-13
2-Jan-14
IFC
All Zones
25
D-80-134A-068
2 of 7
RGCP-472-T-QTR-821
11-Apr-13
27-Feb-13
6-Mar-13
18-Apr-13
21-Apr-13
29-Dec-13
2-Jan-14
IFC
All Zones
26
D-80-134A-068
3 of 7
RGCP-472-T-QTR-821
11-Apr-13
27-Feb-13
6-Mar-13
18-Apr-13
21-Apr-13
29-Dec-13
2-Jan-14
IFC
All Zones
27
D-80-134A-068
4 of 7
RGCP-472-T-QTR-821
11-Apr-13
27-Feb-13
6-Mar-13
18-Apr-13
21-Apr-13
29-Dec-13
2-Jan-14
IFC
All Zones
28
D-80-134A-068
5 of 7
RGCP-472-T-QTR-821
11-Apr-13
27-Feb-13
6-Mar-13
18-Apr-13
21-Apr-13
29-Dec-13
2-Jan-14
IFC
All Zones
29
D-80-134A-068
6 of 7
RGCP-472-T-QTR-821
11-Apr-13
27-Feb-13
6-Mar-13
18-Apr-13
21-Apr-13
29-Dec-13
2-Jan-14
IFC
All Zones
30
D-80-134A-068
7 of 7
RGCP-472-T-QTR-821
11-Apr-13
27-Feb-13
6-Mar-13
18-Apr-13
21-Apr-13
29-Dec-13
2-Jan-14
IFC
All Zones
31
D-80-134A-069
1 of 4
RGCP-472-T-QTR-326
11-Apr-13
27-Feb-13
6-Mar-13
26-Mar-13
28-Mar-13
21-Apr-13
28-Apr-13
IFC
All Zones
32
D-80-134A-069
2 of 4
RGCP-472-T-QTR-824
11-Apr-13
27-Feb-13
6-Mar-13
26-Mar-13
28-Mar-13
2-Jan-14
7-Jan-14
IFC
All Zones
33
D-80-134A-069
3 of 4
RGCP-472-T-QTR-326
11-Apr-13
27-Feb-13
6-Mar-13
26-Mar-13
28-Mar-13
21-Apr-13
28-Apr-13
IFC
All Zones
34
D-80-134A-069
4 of 4
RGCP-472-T-QTR-326
11-Apr-13
27-Feb-13
6-Mar-13
26-Mar-13
28-Mar-13
21-Apr-13
28-Apr-13
IFC
All Zones
35
D-80-134A-108
1 of 1
RGCP-472-T-QTR-454
21-Jan-13
21-Feb-13
28-Feb-13
13-May-13
16-May-13
25-May-13
28-May-13
IFC
36
D-80-134A-109
1 of 2
RGCP-472-T-QTR-679
21/Jan/13
21-Feb-13
28-Feb-13
18-Jul-13
21-Jul-13
18-Sep-13
03-Oct-13
IFC
2 of 6
Updated on : 7/7/2014
Sl.
No.
Drawing Title
Drawing Number
No of
Sheets
QBEC Transmittal
Reference
Approved with
Comments
Reviewed W No
Comments
Plan
Submission
date
Rev
Submit Date
Reviewed with
Comments
Submitted
As-Built
Zone
Reply Date
Approval
Status
Rev
Approval
Status
Rev
Approval
Status
Rev
Submit Date
Reply Date
Approval
Status
37
D-80-134A-109
2 of 2
RGCP-472-T-QTR-679
21/Jan/13
21-Feb-13
28-Feb-13
18-Jul-13
21-Jul-13
18-Sep-13
03-Oct-13
IFC
38
D-80-134A-110
1 of 1
RGCP-472-T-QTR-754
27-Jan-13
21-Feb-13
27-Feb-13
18-Sep-13
23-Sep-13
28-Oct-13
29-Oct-13
IFC
39
D-80-134A-192
1 of 2
RGCP-472-T-QTR-686
27-Jan-13
21-Feb-13
27-Feb-13
11-Sep-13
15-Sep-13
24-Sep-13
02-Oct-13
IFC
40
D-80-134A-192
2 of 2
RGCP-472-T-QTR-686
27-Jan-13
21-Feb-13
27-Feb-13
11-Sep-13
15-Sep-13
24-Sep-13
02-Oct-13
IFC
41
D-80-134A-194
1 of 1
RGCP-472-T-QTR-270
24-Jan-13
11-Feb-13
21-Feb-13
5-Mar-13
12-Mar-13
26-Mar-13
28-Mar-13
IFC
42
D-80-134A-195
1 of 1
RGCP-472-T-QTR-271
21-Jan-13
11-Feb-13
19-Feb-13
5-Mar-13
12-Mar-13
26-Mar-13
9-Apr-13
IFC
All Zones
43
D-80-134A-197
1 of 1
RGCP-472-T-QTR-504
28-Jan-13
12-May-13
14-May-13
25-May-13
28-May-13
10-Jun-13
11-Jun-13
IFC
44
D-80-134A-090
1 of 1
RGCP-472-T-QTR-432
24-Jan-13
17-Feb-13
21-Feb-13
13-Mar-13
20-Mar-13
19-May-13
3-Apr-13
IFC
45
D-80-134A-091
1 of 1
RGCP-472-T-QTR-433
24-Jan-13
17-Feb-13
13-Mar-13
20-Mar-13
19-May-13
22/5/2013
BY EMAIL
46
D-80-134A-093
1 of 1
RGCP-472-T-QTR-434
24-Jan-13
17-Feb-13
24-Feb-13
13-Mar-13
20-Mar-13
19-May-13
14-Apr-13
IFC
47
D-80-134A-095
1 of 1
RGCP-472-T-QTR-321
24-Jan-13
17-Feb-13
24-Feb-13
13-Mar-13
20-Mar-13
9-Apr-13
11-Apr-13
IFC
19
48
D-80-134A-097
1 of 2
RGCP-472-T-QTR-623
22-Jul-13
22-Jul-13
24-Jul-13
24-Aug-13
26-Aug-13
29-Aug-13
08-Sep-13
IFC
49
D-80-134A-097
2 of 2
RGCP-472-T-QTR-623
22-Jul-13
22-Jul-13
24-Jul-13
24-Aug-13
26-Aug-13
29-Aug-13
08-Sep-13
IFC
50
D-80-134A-098
1 of 1
RGCP-472-T-QTR-267
24-Jan-13
11-Feb-13
18-Feb-13
5-Mar-13
12-Mar-13
26-Mar-13
28-Mar-13
IFC
51
D-80-134A-099
1 of 1
RGCP-472-T-QTR-268
24-Jan-13
11-Feb-13
18-Feb-13
5-Mar-13
12-Mar-13
26-Mar-13
28-Mar-13
IFC
17
52
D-80-134A-111A
1 of 1
RGCP-472-T-QTR-269
24-Jan-13
11-Feb-13
18-Feb-13
5-Mar-13
12-Mar-13
26-03-13
28-Mar-13
IFC
11
53
D-80-134A-104
1 of 3
RGCP-472-T-QTR-524
15-Jan-13
03/Feb/13
28-Feb-13
13-May-13
20-May-13
23-Jun-13
14-Aug-13
IFC
All Zones
54
D-80-134A-104
2 of 3
RGCP-472-T-QTR-524
15-Jan-13
03/Feb/13
28-Feb-13
13-May-13
20-May-13
23-Jun-13
14-Aug-13
IFC
All Zones
55
D-80-134A-104
3 of 3
RGCP-472-T-QTR-524
15-Jan-13
03/Feb/13
28/Feb/13
13-May-13
20-May-13
23-Jun-13
14-Aug-13
IFC
All Zones
56
D-80-134A-106
1 of 1
RGCP-472-T-QTR-609
24-Jan-13
09-Apr-13
11-Apr-13
18-Apr-13
21-Apr-13
27-Aug-13
03-Sep-13
IFC
All Zones
57
D-80-134A-081
1 of 3
RGCP-472-T-QTR-569
19/Jan/13
03/Feb/13
10/Feb/13
4-Jul-13
11-Jul-13
27-Jul-13
01-Aug-13
IFC
All Zones
58
D-80-134A-081
2 of 3
RGCP-472-T-QTR-569
19/Jan/13
03/Feb/13
10/Feb/13
4-Jul-13
11-Jul-13
27-Jul-13
01-Aug-13
IFC
All Zones
59
D-80-134A-081
3 of 3
RGCP-472-T-QTR-569
19/Jan/13
03/Feb/13
10/Feb/13
4-Jul-13
11-Jul-13
27-Jul-13
01-Aug-13
IFC
All Zones
60
D-80-134A-121
1 of 1
RGCP-472-T-QTR-519
16-Jun-13
16-Jun-13
18-Jun-13
29-Jul-13
IFC
61
D-80-134A-122
1 of 1
RGCP-472-T-QTR-849
23-Jan-13
30-Jan-13
26-Aug-13
06-Oct-13
11-Mar-14
11-Mar-14
62
D-80-134AX-055
1 of 3
RGCP-472-T-QTR-753
8-Oct-13
10-Oct-13
28/Oct/13
29-Oct-13
IFC
63
D-80-134AX-055
2 of 3
RGCP-472-T-QTR-753
8-Oct-13
10-Oct-13
28/Oct/13
29-Oct-13
IFC
64
D-80-134AX-055
3 of 3
RGCP-472-T-QTR-753
8-Oct-13
10-Oct-13
28/Oct/13
29-Oct-13
IFC
65
D-80-134A-470A
1 o f6
RGCP-472-T-QTR-917
13-May-14
26-May-14
19-Jun-14
23-Jun-14
66
D-80-134A-470A
2 of 6
RGCP-472-T-QTR-917
13-May-14
26-May-14
19-Jun-14
23-Jun-14
67
D-80-134A-470A
3 of 6
RGCP-472-T-QTR-917
13-May-14
26-May-14
19-Jun-14
23-Jun-14
68
D-80-134A-470A
4 of 6
RGCP-472-T-QTR-917
13-May-14
26-May-14
19-Jun-14
23-Jun-14
69
D-80-134A-470A
5 of 6
RGCP-472-T-QTR-917
13-May-14
26-May-14
19-Jun-14
23-Jun-14
69
D-80-134A-470A
6 of 6
RGCP-472-T-QTR-917
19-Jun-14
23-Jun-14
69
D-80-134AX-60
RGCP-472-T-QTR-880
22-Apr-14
24-Apr-14
69
D-80-134AX-61
RGCP-472-T-QTR-901
24-Apr-14
22-May-14
28-May-14
06-Jun-14
SHADES
1
D-80-134A-102A
1 of 3
RGCP-472-T-QTR-689
21-Aug-13
21-Aug-13
27-Aug-13
05-Sep-13
08-Sep-13
24-Sep-13
25-Sep-13
IFC
All Zones
D-80-134A-102A
2 of 3
RGCP-472-T-QTR-689
21-Aug-13
21-Aug-13
27-Aug-13
05-Sep-13
08-Sep-13
24-Sep-13
25-Sep-13
IFC
All Zones
D-80-134A-102A
3 of 3
RGCP-472-T-QTR-689
21-Aug-13
21-Aug-13
27-Aug-13
05-Sep-13
08-Sep-13
24-Sep-13
25-Sep-13
IFC
All Zones
Bus Plaza Shade Structure Near XK-26 -Plan, Elevation and Details
D-80-134A-103A
1 of 3
RGCP-472-T-QTR-719
18-Aug-13
18-Aug-13
22-Aug-13
24-Sep-13
26-Sep-13
5-Oct-13
6-Oct-13
IFC
All Zones
Bus Plaza Shade Structure Near XK-26 -Plan, Elevation and Details
D-80-134A-103A
2 of 3
RGCP-472-T-QTR-719
18-Aug-13
18-Aug-13
22-Aug-13
24-Sep-13
26-Sep-13
5-Oct-13
6-Oct-13
IFC
All Zones
Bus Plaza Shade Structure Near XK-26 -Plan, Elevation and Details
D-80-134A-103A
3 of 3
RGCP-472-T-QTR-719
18-Aug-13
18-Aug-13
22-Aug-13
24-Sep-13
26-Sep-13
5-Oct-13
6-Oct-13
IFC
All Zones
D-80-134A-104A
1 of 2
RGCP-472-T-QTR-690
5-Sep-13
5-Sep-13
9-Sep-13
16-Sep-13
19-Sep-13
24-Sep-13
25-Sep-13
IFC
All Zones
D-80-134A-104A
2 of 2
RGCP-472-T-QTR-690
5-Sep-13
5-Sep-13
9-Sep-13
16-Sep-13
19-Sep-13
24-Sep-13
25-Sep-13
IFC
All Zones
D-80-134A-105A
1 of 2
RGCP-472-T-QTR-691
03-Apr-13
9-Apr-13
12-Sep-13
15-Sep-13
24-Sep-13
25-Sep-13
IFC
All Zones
10
D-80-134A-105A
2 of 2
RGCP-472-T-QTR-691
03-Apr-13
9-Apr-13
12-Sep-13
15-Sep-13
24-Sep-13
25-Sep-13
IFC
All Zones
11
D-80-134A-106A
1 of 2
RGCP-472-T-QTR-692
03-Apr-13
9-Apr-13
29-Aug-13
11-Sep-13
24-Sep-13
25-Sep-13
IFC
All Zones
3 of 6
Updated on : 7/7/2014
Sl.
No.
12
13
14
Drawing Title
Drawing Number
No of
Sheets
QBEC Transmittal
Reference
Plan
Submission
date
Approved with
Comments
Reviewed W No
Comments
Reviewed with
Comments
Submitted
As-Built
Zone
Rev
Submit Date
Reply Date
Approval
Status
Rev
Approval
Status
Rev
Approval
Status
Rev
Submit Date
Reply Date
Approval
Status
D-80-134A-106A
2 of 2
RGCP-472-T-QTR-692
03-Apr-13
9-Apr-13
29-Aug-13
11-Sep-13
24-Sep-13
25-Sep-13
IFC
All Zones
D-80-134A-107A
1 of 3
RGCP-472-T-QTR-743
03-Apr-13
9-Apr-13
07-Oct-13
10-Oct-13
22-Oct-13
27-Oct-13
IFC
All Zones
D-80-134A-107A
2 of 3
RGCP-472-T-QTR-743
03-Apr-13
9-Apr-13
07-Oct-13
10-Oct-13
22-Oct-13
27-Oct-13
IFC
All Zones
07-Oct-13
10-Oct-13
22-Oct-13
27-Oct-13
IFC
15
D-80-134A-107A
3 of 3
RGCP-472-T-QTR-743
03-Apr-13
9-Apr-13
16
D-80-134A-108A
1 of 2
RGCP-472-T-QTR-693
16-May-13
21-May-13
05-Sep-13
16-Sep-13
24-Sep-13
25-Sep-13
IFC
All Zones
17
D-80-134A-108A
2 of 2
RGCP-472-T-QTR-693
16-May-13
21-May-13
05-Sep-13
16-Sep-13
24-Sep-13
25-Sep-13
IFC
All Zones
D-80-134A-075
1 of 9
RGCP-472-T-QTR-479
31-Mar-13
4-Apr-13
7-May-13
12-May-13
2-Jun-13
11-Jun-13
IFC
All Zones
D-80-134A-075
2 of 9
RGCP-472-T-QTR-479
31-Mar-13
4-Apr-13
7-May-13
12-May-13
2-Jun-13
11-Jun-13
IFC
All Zones
D-80-134A-075
3 of 9
RGCP-472-T-QTR-479
31-Mar-13
4-Apr-13
7-May-13
12-May-13
2-Jun-13
11-Jun-13
IFC
All Zones
D-80-134A-075
4 of 9
RGCP-472-T-QTR-479
31-Mar-13
4-Apr-13
7-May-13
12-May-13
2-Jun-13
11-Jun-13
IFC
All Zones
D-80-134A-075
5 of 9
RGCP-472-T-QTR-479
31-Mar-13
4-Apr-13
7-May-13
12-May-13
2-Jun-13
11-Jun-13
IFC
All Zones
D-80-134A-075
6 of 9
RGCP-472-T-QTR-479
31-Mar-13
4-Apr-13
7-May-13
12-May-13
2-Jun-13
11-Jun-13
IFC
All Zones
D-80-134A-075
7 of 9
RGCP-472-T-QTR-479
31-Mar-13
4-Apr-13
7-May-13
12-May-13
2-Jun-13
11-Jun-13
IFC
All Zones
D-80-134A-075
8 of 9
RGCP-472-T-QTR-479
31-Mar-13
4-Apr-13
7-May-13
12-May-13
2-Jun-13
11-Jun-13
IFC
All Zones
D-80-134A-075
9 of 9
RGCP-472-T-QTR-479
31-Mar-13
4-Apr-13
7-May-13
12-May-13
2-Jun-13
11-Jun-13
IFC
All Zones
10
D-80-134A-076
1 of 2
RGCP-472-T-QTR-782
21-Apr-13
22-Apr-13
3-Jun-13
10-Jun-13
23-Nov-13
26-Nov-13
IFC
All Zones
11
D-80-134A-076
2 of 2
RGCP-472-T-QTR-782
21-Apr-13
22-Apr-13
3-Jun-13
10-Jun-13
23-Nov-13
26-Nov-13
IFC
All Zones
12
D-80-134A-077
1 of 3
RGCP-472-T-QTR-480
31-Mar-13
9-Apr-13
7-May-13
12-May-13
2-Jun-13
10-Jun-13
IFC
All Zones
13
D-80-134A-077
2 of 3
RGCP-472-T-QTR-480
31-Mar-13
9-Apr-13
7-May-13
12-May-13
2-Jun-13
10-Jun-13
IFC
All Zones
14
D-80-134A-077
3 of 3
RGCP-472-T-QTR-480
31-Mar-13
9-Apr-13
7-May-13
12-May-13
2-Jun-13
10-Jun-13
IFC
All Zones
15
Schedule of Signs
D-80-134A-078
1 of 1
RGCP-472-T-QTR-482
31-Mar-13
9-Apr-13
7-May-13
15-May-13
2-Jun-13
10-Jun-13
IFC
All Zones
16
D-80-134A-079
1 of 3
RGCP-472-T-QTR-484
31-Mar-13
9-Apr-13
7-May-13
12-May-13
3-Jun-13
10-Jun-13
IFC
All Zones
17
D-80-134A-079
2 of 3
RGCP-472-T-QTR-484
31-Mar-13
9-Apr-13
7-May-13
12-May-13
3-Jun-13
10-Jun-13
IFC
All Zones
18
D-80-134A-079
3 of 3
RGCP-472-T-QTR-484
31-Mar-13
9-Apr-13
7-May-13
12-May-13
3-Jun-13
10-Jun-13
IFC
All Zones
19
D-80-134A-079
4 of 4
RGCP-472-T-QTR-783
31-Mar-13
9-Apr-13
3-Jun-13
10-Jun-13
24-Nov-13
26-Nov-13
IFC
All Zones
20
D-80-134A-140
1 of 3
RGCP-472-T-QTR-513
03-Jun-13
4-Jun-13
10-Jun-13
11-Jun-13
16-Jun-13
16-Jun-13
IFC
All Zones
21
D-80-134A-140
2 of 3
RGCP-472-T-QTR-513
03-Jun-13
4-Jun-13
10-Jun-13
11-Jun-13
16-Jun-13
16-Jun-13
IFC
22
D-80-134A-140
3 of 3
RGCP-472-T-QTR-513
03-Jun-13
4-Jun-13
10-Jun-13
11-Jun-13
16-Jun-13
16-Jun-13
IFC
IRRIGATION
1
D-80-134A-002A
1 of 5
RGCP-472-T-QTR-435
31-Mar-13
18-Apr-13
28-Apr-13
12-May-13
19-May-13
5-Jun-13
IFC
All Zones
D-80-134A-003A
2 of 5
RGCP-472-T-QTR-435
31-Mar-13
18-Apr-13
28-Apr-13
12-May-13
19-May-13
5-Jun-13
IFC
All Zones
D-80-134A-004A
3 of 5
RGCP-472-T-QTR-435
31-Mar-13
18-Apr-13
28-Apr-13
12-May-13
19-May-13
5-Jun-13
IFC
All Zones
D-80-134A-005A
4 of 5
RGCP-472-T-QTR-435
31-Mar-13
18-Apr-13
28-Apr-13
12-May-13
19-May-13
5-Jun-13
IFC
All Zones
D-80-134A-006A
5 of 5
RGCP-472-T-QTR-435
31-Mar-13
18-Apr-13
28-Apr-13
12-May-13
19-May-13
5-Jun-13
IFC
All Zones
D-80-134A-007A
1 of 5
RGCP-472-T-QTR-436
31-Mar-13
18-Apr-13
28-Apr-13
6-May-13
19-May-13
23-May-13
IFC
All Zones
D-80-134A-008A
2 of 5
RGCP-472-T-QTR-436
31-Mar-13
18-Apr-13
28-Apr-13
6-May-13
19-May-13
23-May-13
IFC
All Zones
D-80-134A-009A
3 of 5
RGCP-472-T-QTR-436
31-Mar-13
18-Apr-13
28-Apr-13
6-May-13
19-May-13
23-May-13
IFC
All Zones
D-80-134A-010A
4 of 5
RGCP-472-T-QTR-436
31-Mar-13
18-Apr-13
28-Apr-13
6-May-13
19-May-13
23-May-13
IFC
All Zones
10
D-80-134A-011A
5 of 5
RGCP-472-T-QTR-436
31-Mar-13
18-Apr-13
28-Apr-13
6-May-13
19-May-13
23-May-13
IFC
All Zones
11
D-80-134A-012A
1 of 1
RGCP-472-T-QTR-445
31-Mar-13
18-Apr-13
28-Apr-13
6-May-13
21-May-13
23-May-13
IFC
All Zones
12
D-80-134A-013A
1 of 1
RGCP-472-T-QTR-700
31-Mar-13
2-Apr-13
17-Aug-13
3-Sep-13
24-Sep-13
2-Oct-13
IFC
All Zones
13
D-80-134A-022
1 of 3
RGCP-472-T-QTR-446
31-Mar-13
18-Apr-13
28-Apr-13
7-May-13
21-May-13
23-May-13
IFC
All Zones
14
D-80-134A-022
2 of 3
RGCP-472-T-QTR-446
31-Mar-13
18-Apr-13
28-Apr-13
7-May-13
21-May-13
23-May-13
IFC
All Zones
15
D-80-134A-022
3 of 3
RGCP-472-T-QTR-446
31-Mar-13
18-Apr-13
28-Apr-13
7-May-13
21-May-13
23-May-13
IFC
All Zones
16
D-80-134A-024A
1 of 5
RGCP-472-T-QTR-481
12-May-13
16-May-13
2-Jun-13
30-Jun-13
IFC
All Zones
17
D-80-134A-025A
2 of 5
RGCP-472-T-QTR-481
12-May-13
16-May-13
2-Jun-13
30-Jun-13
IFC
All Zones
18
D-80-134A-026A
3 of 5
RGCP-472-T-QTR-481
12-May-13
16-May-13
2-Jun-13
30-Jun-13
IFC
All Zones
4 of 6
Updated on : 7/7/2014
Sl.
No.
Drawing Title
Drawing Number
No of
Sheets
QBEC Transmittal
Reference
Plan
Submission
date
Approved with
Comments
Reviewed W No
Comments
Reviewed with
Comments
Submitted
As-Built
Zone
Rev
Submit Date
Reply Date
Approval
Status
Rev
Approval
Status
Rev
Approval
Status
Rev
Submit Date
Reply Date
Approval
Status
19
D-80-134A-027A
4 of 5
RGCP-472-T-QTR-481
12-May-13
16-May-13
2-Jun-13
30-Jun-13
IFC
All Zones
20
D-80-134A-028A
5 of 5
RGCP-472-T-QTR-481
12-May-13
16-May-13
2-Jun-13
30-Jun-13
IFC
All Zones
21
Controller Schematic
D-80-134A-031A
1 of 1
RGCP-472-T-QTR-799
03-Jun-13
11-Jun-13
27-Oct-13
28-Oct-13
16-Dec-13
24-Dec-13
IFC
All Zones
22
C-80-134A-221
1 of 1
RGCP-472-T-QTR-716
28-Apr-13
7-May-13
02-Jun-13
10-Jun-13
5-Oct-13
20-Oct-13
IFC
All Zones
23
S-80-134A-011
1 of 1
RGCP-472-T-QTR-717
02-Jun-13
4-Jun-13
11-Jul-13
21-Aug-13
5-Oct-13
27-Oct-13
IFC
All Zones
PLUMBING
1
D-80-134A-468
1 of 2
RGCP-472-T-QTR-859
10-Mar-13
20-Mar-13
16-Dec-13
24-Dec-13
24-Mar-13
02-Apr-13
REGENCY TO SUBMIT
D-80-134A-468
2 of 2
RGCP-472-T-QTR-859
10-Mar-13
20-Mar-13
16-Dec-13
24-Dec-13
24-Mar-13
02-Apr-13
REGENCY TO SUBMIT
D-80-134A-469
1 of 1
RGCP-472-T-QTR-417
16-May-13
29-May-13
ACE TO SUBMIT
D-80-134A-470
1 of 1
RGCP-472-T-QTR-858
10-Mar-13
20-Mar-13
16-Dec-13
26-Dec-13
IFC
S-80-134A-400
1 of 1
RGCP-472-T-QTR-804
14-May-13
21-May-13
16-Dec-13
24-Dec-13
REGENCY TO SUBMIT
S-80-134A-401
1 of 1
RGCP-472-T-QTR-805
16-May-13
21-May-13
16-Dec-13
24-Dec-13
REGENCY TO SUBMIT
S-80-134A-402
1 of 1
RGCP-472-T-QTR-775
16-May-13
22-May-13
18-Nov-13
11-Dec-13
ACE TO SUBMIT
D-80-134A-471A
1 of 3
RGCP-472-T-QTR-877
10-Mar-13
20-Mar-13
24-Mar-14
30-Mar-14
22-Mar-14
19-May-14
IFC
D-80-134A-471A
2 of 3
RGCP-472-T-QTR-877
10-Mar-13
20-Mar-13
24-Mar-14
30-Mar-14
22-Mar-14
19-May-14
IFC
10
D-80-134A-471A
3 of 3
RGCP-472-T-QTR-877
10-Mar-13
20-Mar-13
24-Mar-14
30-Mar-14
22-Mar-14
19-May-14
IFC
11
D-80-134A-472A
1 of 2
RGCP-472-T-QTR-878
10-Mar-13
18-Apr-13
24-Mar-14
30-Mar-14
22-Mar-14
19-May-14
IFC
12
D-80-134A-472A
2 of 2
RGCP-472-T-QTR-878
10-Mar-13
18-Apr-13
24-Mar-14
30-Mar-14
22-Mar-14
19-May-14
IFC
13
D-80-134A-473
RGCP-472-T-QTR-488
10-Mar-13
20-Mar-13
25-May-13
30-May-13
3-Jun-13
4-Jun-13
IFC
14
D-80-134A-474
RGCP-472-T-QTR-518
19/Jun/13
07/Aug/13
15
D-80-134A-475
RGCP-472-T-QTR-902
10-Mar-13
20-Mar-13
16
D-80-134A-475A
RGCP-472-T-QTR-918
17
D-80-134A-476
RGCP-472-T-QTR-800
18
D-80-134A-476A
RGCP-472-T-QTR-919
19
S-80-134A-404
RGCP-472-T-QTR-806
10-Mar-13
20-Mar-13
20
S-80-134A-405
RGCP-472-T-QTR-810
10-Mar-13
24-Mar-13
24
D-80-134AX-058
RGCP-472-T-QTR-846
11-Mar-14
13-Mar-14
25
D-80-134AX-057
RGCP-472-T-QTR-881
18-Mar-14
20-Mar-14
26
D-80-134A-470C
RGCP-472-T-QTR-903
28-May-14
11-Jun-14
10-Mar-13
20-Mar-13
24-Mar-14
31-Mar-14
IFC
ACE TO SUBMIT
REGENCY TO SUBMIT
2
2
16-Dec-13
24-Dec-13
28-May-14
17-Jun-14
REGENCY TO SUBMIT
16-Dec-13
26-Dec-13
19-Jun-14
25-Jun-14
REGENCY TO SUBMIT
07-Jul-13
7-Jul-13
16-Dec-13
16-Dec-13
26-Dec-13
19-Jun-14
25-Jun-14
REGENCY TO SUBMIT
16-Dec-13
02-Jan-13
WITH RASGAS
ACE TO SUBMIT
WITH RASGAS
18-Jun-13
26-Jun-13
16-Dec-13
26-Dec-13
01-Apr-14
02-Apr-14
24-Apr-14
09-Jun-14
By Email
INSTRUMENT
1
D-80-134A-655
1 of 1
RGCP-472-T-QTR-219
10-Mar-13
20-Mar-13
All Zones
ELECTRICAL
1
D-80-134A-274
1 to 3
RGCP-472-T-QTR-0725
19-Feb-13
20-Mar-13
07-Oct-13
10-Oct-13
IFC
D-80-134A-274
1 to 3
RGCP-472-T-QTR-0725
19-Feb-13
20-Mar-13
07-Oct-13
10-Oct-13
IFC
D-80-134A-274
1 to 3
RGCP-472-T-QTR-0725
07-Oct-13
10-Oct-13
IFC
D-80-134A-275
1 of 1
RGCP-472-T-QTR-0726
27-Jan-13
05-May-13
12-May-13
07-Oct-13
20-Oct-13
IFC
All Zones
D-80-134A-280
1 of 1
RGCP-472-T-QTR-587
27/Jan/13
19-Feb-13
24-Feb-13
11-Aug-13
23-Sep-13
IFC
All Zones
D-80-134A-286
1 of 1
RGCP-472-T-QTR-581
05-May-13
08-May-13
11-Aug-13
23-Sep-13
IFC
D-80-134A-287
1 of 4
RGCP-472-T-QTR-0541
27-Jan-13
23-Apr-13
24-Apr-13
5-Nov-13
6-Nov-13
IFC
All Zones
D-80-134A-287
2 of 4
RGCP-472-T-QTR-0541
27-Jan-13
23-Apr-13
24-Apr-13
5-Nov-13
6-Nov-13
IFC
All Zones
D-80-134A-287
3 of 4
RGCP-472-T-QTR-0541
27-Jan-13
23-Apr-13
24-Apr-13
5-Nov-13
6-Nov-13
IFC
All Zones
10
D-80-134A-287
4 of 4
RGCP-472-T-QTR-0541
27-Jan-13
23-Apr-13
24-Apr-13
5-Nov-13
6-Nov-13
IFC
All Zones
11
D-80-134A-288
1 of 3
RGCP-472-T-QTR-724
27-Jan-13
06-May-13
12-May-13
16-Jun-13
24-Jun-13
07-Oct-13
10-Oct-13
IFC
All Zones
12
D-80-134A-288
2 of 3
RGCP-472-T-QTR-724
27-Jan-13
06-May-13
12-May-13
16-Jun-13
24-Jun-13
07-Oct-13
10-Oct-13
IFC
All Zones
13
D-80-134A-288
3 of 3
RGCP-472-T-QTR-724
27-Jan-13
06-May-13
12-May-13
16-Jun-13
24-Jun-13
07-Oct-13
10-Oct-13
IFC
All Zones
14
Electrical Works - General Layout for Lighting (Zone 1 & Zone 10)
D-80-134A-289
1 of 1
RGCP-472-T-QTR-766
21-Apr-13
23-Apr-13
25-May-13
29-May-13
13-Nov-13
17-Nov-13
IFC
All Zones
15
D-80-134A-290
1 of 1
RGCP-472-T-QTR-0721
19-Feb-13
24-Feb-13
9-Jun-13
11-Jun-13
27-Nov-13
27-Nov-13
IFC
All Zones
27-Jan-13
5 of 6
9-Jun-13
13-May-13
12-Jun-13
15-May-13
Updated on : 7/7/2014
Sl.
No.
Drawing Title
Drawing Number
No of
Sheets
QBEC Transmittal
Reference
Approved with
Comments
Reviewed W No
Comments
Plan
Submission
date
Rev
Submit Date
Reviewed with
Comments
Submitted
As-Built
Zone
Reply Date
Approval
Status
Rev
Approval
Status
Rev
Approval
Status
Rev
Submit Date
Reply Date
Approval
Status
16
D-80-134A-291
1 of 1
RGCP-472-T-QTR-0503
27-Jan-13
19-Feb-13
24-Feb-13
25-May-13
29-May-13
9-Jun-13
11-Jun-13
IFC
All Zones
17
D-80-134A-292
1 of 1
RGCP-472-T-QTR-0722
27-Jan-13
19-Feb-13
24-Feb-13
9-Jun-13
11-Jun-13
07-Oct-13
10-Oct-13
IFC
All Zones
18
D-80-134A-293
1 of 1
RGCP-472-T-QTR-0723
03-Apr-13
4-Apr-13
25-May-13
29-May-13
07-Oct-13
22-Oct-13
IFC
All Zones
19
D-80-134A-294
1 of 1
RGCP-472-T-QTR-0720
03-Apr-13
4-Apr-13
5-May-13
12-May-13
07-Oct-13
10-Oct-13
IFC
All Zones
20
D-80-134A-295
1 of 1
RGCP-472-T-QTR-767
03-Apr-13
4-Apr-13
5-May-13
12-May-13
13-Nov-13
1-Dec-13
IFC
All Zones
21
D-80-134A-296
1 of 1
RGCP-472-T-QTR-769
03-Apr-13
4-Apr-13
5-May-13
12-May-13
13-Nov-13
17-Nov-13
IFC
All Zones
22
D-80-134A-297
1 of 1
RGCP-472-T-QTR-768
03-Apr-13
4-Apr-13
5-May-13
12-May-13
13-Nov-13
17-Nov-13
IFC
All Zones
23
D-80-134A-298
1 of 1
RGCP-472-T-QTR-0494
12-May-13
15-May-13
25-May-13
29-May-13
9-Jun-13
11-Jun-13
IFC
All Zones
24
D-80-134A-299
1 of 1
RGCP-472-T-QTR-0495
12-May-13
15-May-13
25-May-13
29-May-13
9-Jun-13
11-Jun-13
IFC
All Zones
25
D-80-134A-200A
1 of 1
RGCP-472-T-QTR-0496
12-May-13
15-May-13
25-May-13
28-May-13
9-Jun-13
11-Jun-13
IFC
All Zones
26
D-80-134A-201A
1 of 1
RGCP-472-T-QTR-0497
12-May-13
15-May-13
25-May-13
29-May-13
9-Jun-13
11-Jun-13
IFC
All Zones
27
D-80-134A-202A
1 of 1
RGCP-472-T-QTR-542
05-May-13
12-May-13
14-May-13
16-May-13
9-Jul-13
11-Jul-13
IFC
All Zones
28
D-80-134A-202B
1 of 2
RGCP-472-T-QTR-882
05-May-13
12-May-13
16-Dec-13
23-Dec-13
22-Apr-14
22-May-14
All Zones
29
D-80-134A-202B
2 of 2
RGCP-472-T-QTR-882
16-Dec-13
23-Dec-13
22-Apr-14
22-May-14
30
D-80-134A-202C
1 of 1
RGCP-472-T-QTR-862
01-Oct-13
27-Oct-13
28-Oct-13
29-Mar-14
31-Mar-14
31
D-80-134A-202E
1 of 1
RGCP-472-T-QTR-861
29-Mar-14
31-Mar-14
32
D-80-134A-202D
32
33
34
35
02-Oct-13
RGCP-472-T-QTR-915
17-Jun-14
25-Jun-14
IFC
D-80-134B-225
1 of 1
RGCP-472-T-QTR-559
27-May-13
29-May-13
18-Jul-13
31-Jul-13
IFC
D-80-134A-253
1 of 1
RGCP-472-T-QTR-594
27-May-13
29-May-13
17-Aug-13
19-Aug-13
IFC
RGX-D-61-1382004
1 of 1
RGCP-472-T-QTR-582
27-May-13
29-May-13
11-Aug-13
21-Aug-13
IFC
S-80-134A-225
1 of 1
RGCP-472-T-QTR-765
08-Jul-13
11-Jul-11
13-Nov-13
17-Nov-13
IFC
06-Jun-14
10-Jun-14
D-80-134A-470B
30-Sep-13
3-Oct-13
RGCP-472-T-QTR-905
35
D-61-1316-001
1 of 1
RGCP-472-T-QTR-677
14A
13-Jul-13
31-Jul-13
14B
18-Sep-13
03-Oct-13
14C
10-Feb-14
16-Feb-14
36
D-61-1316-001
1 of 1
RGCP-472-T-QTR-677
9A
13-Jul-13
31-Jul-13
9B
18-Sep-13
03-Oct-13
9C
10-Feb-14
16-Feb-14
37
D-61-1316-001
1 of 1
RGCP-472-T-QTR-677
14A
13-Jul-13
31-Jul-13
14B
18-Sep-13
03-Oct-13
14C
10-Feb-14
16-Feb-14
38
D-61-1316-001
1 of 1
RGCP-472-T-QTR-677
12A
13-Jul-13
31-Jul-13
12B
18-Sep-13
03-Oct-13
12C
10-Feb-14
16-Feb-14
39
D-61-1316-001
1 of 1
RGCP-472-T-QTR-677
17A
13-Jul-13
31-Jul-13
17B
18-Sep-13
03-Oct-13
17C
10-Feb-14
16-Feb-14
40
D-61-1316-001
1 of 1
RGCP-472-T-QTR-677
13A
13-Jul-13
31-Jul-13
13B
18-Sep-13
03-Oct-13
13C
10-Feb-14
16-Feb-14
41
D-61-1316-001
1 of 1
RGCP-472-T-QTR-677
11A
13-Jul-13
31-Jul-13
11B
18-Sep-13
03-Oct-13
11C
10-Feb-14
16-Feb-14
42
D-61-1316-001
1 of 1
RGCP-472-T-QTR-677
12A
13-Jul-13
31-Jul-13
1B
18-Sep-13
03-Oct-13
1C
10-Feb-14
16-Feb-14
43
D-61-1316-001
1 of 1
RGCP-472-T-QTR-677
14A
13-Jul-13
31-Jul-13
14B
18-Sep-13
03-Oct-13
14C
10-Feb-14
16-Feb-14
44
D-61-1316-001
1 of 1
RGCP-472-T-QTR-677
8A
13-Jul-13
31-Jul-13
8B
18-Sep-13
03-Oct-13
8C
10-Feb-14
16-Feb-14
45
D-61-1316-001
1 of 1
RGCP-472-T-QTR-677
10A
13-Jul-13
31-Jul-13
10B
18-Sep-13
03-Oct-13
10C
10-Feb-14
16-Feb-14
6 of 6
Updated on : 7/7/2014
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
654 21-Oct-12 A
26-Jul-14
-7
94.15%
98.4%
QR20,950,917.53
644 21-Oct-12 A
26-Jul-14
-7
100%
100%
QR1,047,545.97
GENERAL MILESTONES
644 21-Oct-12 A
26-Jul-14
-7
0%
0%
QR0.00
KEY MILESTONES
CONTRACTOR MOBILISATION and FINALIZATION OF KEY SUB-CONTR
543 04-Jan-13 A
30-Jun-14
19
0%
0%
QR0.00
ENGINEERING
Site Survey and Trial pit Excavation
Submission and Approval of Design Calculations
Car Parks
Structural Shades and Covered Car Parks
Piping Hydraulic Calculations
Concrete Foundations
Electrical Lighting and Cable Sizing
Cable Submission
PROCUREMENT
Materials Submission and Approval
Interlock pavers, kerb stones and tree guards
Foundation bolts
Main piping material
Shade structures including fabric material
Signage structures
Fountain sculpture
Electrical Poles, DBs and Field Controls
Valves and pumps
Irrigation distribution accessories
CONSTRUCTION
Phase 1 Works
Construction
Zone 1
Open car park paving - Kerb and interlock paving works
Irrigation piping main laying
Kerb, plant edgers and interlock paving works
Area lighting and control cable laying
Shade structures erection
Remaining
75 21-Oct-12 A
03-Jan-13 A
100%
100%
QR1,047,545.97
540 23-Oct-12 A
12-Jun-14 A
100%
100%
QR1,047,545.47
120 23-Oct-12 A
05-Feb-13 A
100%
100%
QR89,089.66
100%
100%
QR193,769.92
47
48
49
49
49
49
482
08-Nov-12 A
03-Dec-12 A
01-Nov-12 A
19-Nov-12 A
12-Nov-12 A
31-Dec-12 A
20-Dec-12 A
26-Dec-12 A
21-Jan-13 A
20-Dec-12 A
07-Jan-13 A
31-Dec-12 A
18-Feb-13 A
12-Jun-14 A
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
QR34,680.65
QR31,236.71
QR31,963.14
QR31,963.14
QR31,963.14
QR31,963.14
QR764,685.89
56
65
53
75
471
91
423
26-Dec-12 A
06-Jan-13 A
21-Jan-13 A
31-Dec-12 A
31-Dec-12 A
20-Dec-12 A
04-Feb-13 A
20-Feb-13 A
11-Mar-13 A
14-Mar-13 A
17-Mar-13 A
12-Jun-14 A
21-Mar-13 A
12-Jun-14 A
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
QR209,689.55
QR82,813.59
QR138,022.65
QR165,627.18
QR110,418.12
QR58,114.80
QR3,561,656.18
345 04-Feb-13 A
28-Feb-14 A
100%
100%
QR1,237,805.96
36
36
36
35
36
330
36
50
61
432
18-Feb-13 A
05-Mar-13 A
04-Feb-13 A
14-Mar-13 A
13-Feb-13 A
20-Feb-13 A
06-Mar-13 A
04-Feb-13 A
21-Mar-13 A
12-Mar-13 A
26-Mar-13 A
10-Apr-13 A
12-Mar-13 A
18-Apr-13 A
20-Mar-13 A
27-Feb-14 A
10-Apr-13 A
28-Feb-14 A
22-May-13 A
12-Jun-14 A
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
QR137,534.00
QR137,534.00
QR137,534.00
QR137,534.00
QR137,534.00
QR137,533.99
QR137,533.99
QR137,533.99
QR137,533.99
QR2,323,850.22
15
27
66
381
384
414
62
96
45
565
26-Mar-13 A
10-Apr-13 A
12-Mar-13 A
18-Apr-13 A
20-Mar-13 A
28-Mar-13 A
10-Apr-13 A
27-Mar-13 A
22-May-13 A
20-Feb-13 A
08-Apr-13 A
04-May-13 A
09-May-13 A
03-Apr-14 A
27-Feb-14 A
12-Jun-14 A
04-Jun-13 A
03-Apr-14 A
01-Jul-13 A
08-Jul-14
22
100%
100%
100%
100%
100%
100%
100%
100%
100%
99.01%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
QR71,138.27
QR128,048.89
QR313,008.40
QR237,127.57
QR241,870.12
QR369,919.02
QR294,038.19
QR455,284.94
QR213,414.82
QR12,989,568.83
564 20-Feb-13 A
30-Jun-14
23
98.72%
100%
QR4,609,201.93
564
200
109
83
88
58
64
30-Jun-14
23-Jan-14 A
27-May-13 A
29-Jul-13 A
31-Dec-13 A
20-Jun-13 A
08-Jul-13 A
23
98.76%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
QR3,771,165.17
QR979,862.42
QR287,597.98
QR61,396.20
QR206,433.64
QR85,420.80
QR66,735.00
20-Feb-13 A
20-Feb-13 A
20-Feb-13 A
18-May-13 A
11-Mar-13 A
30-Apr-13 A
13-May-13 A
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
2013
N
J Jul A
2014
S
A M
J Jul A
Page 1 of 4
S Oct N
Activity Name
Original Start
Duration
Phase 2 Works
Construction
Zone 5
Concrete foundations signage
Kerb, plant edgers works
Irrigation piping main laying & zone valve's installation
Signage structures erection
Irrigation lateral piping & distribution accessories
Zone 6
Concrete foundations for shades and signage
Kerb, plant edgers and interlock paving works
Irrigation piping main laying & zone valve's installation
Remaining
Finish
33
30
27
36
40
543
69
156
89
58
104
54
135
22
36
40
514
43
89
58
173
285
27
27
40
493
43
83
58
209
77
27
120
40
326
119
74
207
27
114
128
13
544
27-May-13 A
04-Jun-13 A
05-Jun-13 A
14-Jul-13 A
13-May-13 A
11-Mar-13 A
11-Mar-13 A
05-Jun-13 A
11-Mar-13 A
27-May-13 A
19-Jan-14 A
22-May-14 A
01-Jan-14 A
18-Jan-14 A
24-Sep-13 A
19-May-13 A
28-Mar-13 A
01-Oct-13 A
28-Mar-13 A
22-Jun-13 A
01-Feb-14 A
19-Jun-13 A
23-Oct-13 A
24-Oct-13 A
09-Jun-13 A
16-Apr-13 A
23-Oct-13 A
16-Apr-13 A
29-May-13 A
31-Dec-13 A
05-Jan-14 A
11-Nov-13 A
10-Nov-13 A
04-Jul-13 A
05-May-13 A
11-Nov-13 A
05-May-13 A
15-Jul-13 A
11-Nov-13 A
16-Nov-13 A
17-Aug-13 A
11-Dec-13 A
11-Mar-13 A
24-Jun-13 A
01-Jul-13 A
19-Jan-14 A
23-Jan-14 A
17-Jun-13 A
30-Jun-14
11-Jan-14 A
18-Jan-14 A
10-Apr-14 A
06-Feb-14 A
10-Apr-14 A
30-Jun-14
24-Apr-14 A
30-Apr-14 A
31-Mar-14 A
26-Apr-14 A
30-Jun-14
18-Jan-14 A
31-Dec-13 A
15-Aug-13 A
30-Jun-14
10-Apr-14 A
18-Jan-14 A
18-Jan-14 A
03-Apr-14 A
30-Jun-14
18-Jan-14 A
31-Dec-13 A
31-Dec-13 A
30-Jun-14
10-Apr-14 A
13-Feb-14 A
24-Jan-14 A
17-Apr-14 A
03-Apr-14 A
24-Jan-14 A
06-Mar-14 A
03-Apr-14 A
18-Jan-14 A
24-Jan-14 A
03-Apr-14 A
30-Jun-14
08-Jul-14
544
205
122
179
144
199
23
352
208
122
41
11-Mar-13 A
21-Jul-13 A
21-Jul-13 A
29-Jul-13 A
07-Sep-13 A
25-Jul-13 A
12-Dec-13 A
21-Aug-13 A
21-Aug-13 A
02-Feb-14 A
10-Dec-13 A
08-Jul-14
03-Apr-14 A
13-Nov-13 A
25-Jan-14 A
31-Dec-13 A
03-Apr-14 A
31-Dec-13 A
30-Jun-14
03-Apr-14 A
22-May-14 A
22-Jan-14 A
Total
Float
23
22
23
23
23
22
-8
22
22
23
Actual %
Complete
Planned %
Complete
100%
100%
100%
100%
100%
97.66%
100%
100%
100%
100%
100%
75%
100%
100%
100%
100%
97.98%
100%
100%
100%
80%
100%
100%
100%
100%
98.07%
100%
100%
100%
80%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
98.53%
98.84%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
QR29,363.40
QR53,388.00
QR24,024.60
QR112,114.80
QR53,388.00
QR855,987.67
QR86,310.61
QR125,461.80
QR206,433.64
QR85,420.80
QR29,363.40
QR80,082.02
QR53,388.00
QR24,024.60
QR112,114.80
QR53,388.00
QR660,231.64
QR114,784.20
QR206,433.64
QR85,420.80
QR66,735.00
QR29,363.40
QR24,024.60
QR80,082.00
QR53,388.00
QR692,264.44
QR114,784.20
QR206,433.64
QR85,420.80
QR66,735.00
QR29,363.40
QR24,024.60
QR112,114.80
QR53,388.00
QR582,819.00
QR224,229.60
QR179,739.60
QR21,355.20
QR24,024.60
QR80,082.00
QR53,388.00
QR838,036.76
QR3,352,146.70
98.94%
100%
100%
100%
100%
100%
100%
98.24%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
QR2,514,109.94
QR276,898.83
QR89,723.97
QR66,016.95
QR67,736.27
QR14,332.63
QR39,089.01
QR259,724.61
QR61,673.73
QR74,703.39
QR29,968.24
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
2013
N
J Jul A
2014
S
A M
J Jul A
Page 2 of 4
S Oct N
Activity Name
Original Start
Duration
Phase 3 Works
Remaining
109
76
35
331
184
142
23
172
85
177
256
116
150
38
34
131
270
101
69
19
73
10
151
135
340
112
159
37
112
116
209
28
206
92
58
33
67
201
96
45
63
18
58
528
89
54
84
43
99
33
275
36
9
361
27-Mar-14 A
01-Feb-14 A
01-Feb-14 A
09-Sep-13 A
09-Sep-13 A
01-Feb-14 A
24-Dec-13 A
01-Feb-14 A
01-Feb-14 A
21-Dec-13 A
10-Sep-13 A
29-Sep-13 A
10-Sep-13 A
24-Dec-13 A
27-Mar-14 A
07-Dec-13 A
22-Oct-13 A
22-Oct-13 A
01-Feb-14 A
19-Dec-13 A
27-Mar-14 A
29-Mar-14 A
14-Dec-13 A
19-Dec-13 A
10-Sep-13 A
29-Sep-13 A
10-Sep-13 A
14-Dec-13 A
02-Mar-14 A
20-Mar-14 A
24-Oct-13 A
08-Dec-13 A
26-Oct-13 A
26-Oct-13 A
26-Nov-13 A
27-Mar-14 A
17-Dec-13 A
21-Oct-13 A
21-Oct-13 A
01-Feb-14 A
19-Dec-13 A
27-Mar-14 A
21-Dec-13 A
11-Mar-13 A
11-Mar-13 A
28-Mar-13 A
28-Mar-13 A
30-Apr-13 A
27-Mar-14 A
15-Jun-13 A
06-Jun-13 A
22-May-13 A
08-Dec-13 A
17-Aug-13 A
Finish
30-Jun-14
10-Apr-14 A
10-Apr-14 A
30-Jun-14
31-Mar-14 A
22-May-14 A
31-Dec-13 A
30-Jun-14
10-Apr-14 A
12-Jun-14 A
10-Apr-14 A
13-Feb-14 A
10-Apr-14 A
06-Jan-14 A
10-Apr-14 A
29-Jan-14 A
30-Jun-14
06-Mar-14 A
05-Apr-14 A
23-Jan-14 A
30-Jun-14
17-Apr-14 A
31-Mar-14 A
17-Apr-14 A
08-Jul-14
06-Feb-14 A
20-Feb-14 A
06-Feb-14 A
08-Jul-14
10-Apr-14 A
31-Mar-14 A
13-Feb-14 A
10-Apr-14 A
06-Feb-14 A
01-Jan-14 A
10-Apr-14 A
06-Feb-14 A
10-Apr-14 A
26-Feb-14 A
02-Mar-14 A
12-Feb-14 A
10-Apr-14 A
09-Feb-14 A
30-Jun-14
27-May-13 A
15-May-13 A
31-Dec-13 A
06-Jun-13 A
30-Jun-14
14-Jul-13 A
06-Feb-14 A
23-Dec-13 A
30-Jun-14
30-Jun-14
Total
Float
Actual %
Complete
Planned %
Complete
-8
81.58%
100%
100%
98.25%
100%
100%
100%
81.58%
100%
100%
100%
100%
100%
100%
100%
100%
98.23%
100%
100%
100%
81.58%
100%
100%
100%
97.72%
100%
100%
100%
80%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
98.31%
100%
100%
100%
100%
80%
100%
100%
100%
98.53%
99.16%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
QR24,756.37
QR13,898.31
QR54,724.57
QR260,158.93
QR61,673.73
QR74,703.39
QR29,968.24
QR24,756.37
QR14,332.63
QR54,724.57
QR260,167.93
QR61,673.73
QR74,703.39
QR54,733.61
QR14,332.63
QR54,724.57
QR257,552.99
QR34,311.44
QR73,400.42
QR29,968.24
QR24,756.37
QR14,332.63
QR26,059.32
QR54,724.57
QR285,349.63
QR35,614.41
QR92,076.31
QR29,968.24
QR32,574.15
QR14,332.63
QR26,059.32
QR54,724.57
QR267,976.71
QR142,891.95
QR56,027.56
QR14,332.63
QR54,724.57
QR260,167.93
QR35,614.41
QR74,703.39
QR80,792.93
QR14,332.63
QR54,724.57
QR386,112.38
QR100,762.75
QR35,614.41
QR92,076.31
QR29,968.24
QR32,574.15
QR14,332.63
QR26,059.32
QR54,724.57
QR838,036.76
QR3,561,655.92
23
23
-8
-8
22
22
-8
-8
-9
23
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
2013
N
J Jul A
2014
S
A M
J Jul A
Page 3 of 4
S Oct N
Activity Name
Original Start
Duration
Construction
Zone 12
Concrete foundations for shades and signage
Kerb, plant edgers and interlock paving works
Irrigation piping main laying & zone valve's installation
Shade structures erection
Signage structures erection
Irrigation lateral piping & distribution accessories
Road Kerb and Furnishing Works
Zone 13
Concrete foundations for signage
Kerbs and interlock paving works
Irrigation piping main laying & zone valve's installation
Signage structures erection
Irrigation lateral piping & distribution accessories
Road Kerb and Furnishing Works
Zone 14
Open car park paving - Kerb and interlock paving works
Concrete foundations for signage
Kerb, plant edgers and interlock paving works
Irrigation piping main laying & zone valve's installation
Signage structures erection
Irrigation lateral piping & distribution accessories
Road Kerb and Furnishing Works
Zone 15
Concrete foundations for shades and signage
Kerb, plant edgers and interlock paving works
Irrigation piping main laying & zone valve's installation
Shade structures erection
Signage structures erection
Irrigation lateral piping & distribution accessories
Road Kerb and Furnishing Works
Zone 16
Concrete foundations for signage
Kerb, plant edgers works
Irrigation piping main laying & zone valve's installation
Signage structures erection
Irrigation lateral piping & distribution accessories
Road Kerb and Furnishing Works
Phase 3 - Testing and Commissioning
Phase 4 Works
Remaining
Total
Float
Actual %
Complete
Planned %
Complete
30-Jun-14
30-Jun-14
06-Feb-14 A
17-Apr-14 A
14-Jan-14 A
30-Jun-14
10-Apr-14 A
18-Feb-14 A
31-Dec-13 A
03-Apr-14 A
31-Dec-13 A
04-Jan-14 A
31-Dec-13 A
03-Apr-14 A
04-Jan-14 A
31-Dec-13 A
03-Apr-14 A
31-Dec-13 A
30-Dec-13 A
31-Dec-13 A
31-Dec-13 A
03-Apr-14 A
18-Jan-14 A
31-Dec-13 A
30-Jun-14
06-Mar-14 A
14-Apr-14 A
12-Jan-14 A
30-Jun-14
17-Apr-14 A
30-Apr-14 A
24-Apr-14 A
10-Apr-14 A
31-Dec-13 A
31-Dec-13 A
31-Dec-13 A
10-Apr-14 A
31-Dec-13 A
31-Dec-13 A
30-Jun-14
21-Jun-14 A
23
23
99.35%
98.63%
100%
100%
100%
81.58%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
98.28%
100%
100%
100%
80%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
98.53%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
QR2,723,619.16
QR529,814.28
QR94,881.77
QR119,121.64
QR47,787.17
QR39,476.36
QR22,162.17
QR87,263.53
QR119,121.64
QR458,479.80
QR119,814.21
QR103,192.58
QR47,787.17
QR22,162.17
QR62,331.09
QR103,192.58
QR615,000.09
QR153,750.02
QR92,804.07
QR119,121.64
QR47,787.17
QR22,854.74
QR73,412.17
QR105,270.28
QR605,054.60
QR156,963.30
QR119,121.64
QR47,787.17
QR51,942.58
QR22,854.74
QR87,263.53
QR119,121.64
QR515,270.39
QR128,817.59
QR119,121.64
QR43,631.77
QR22,854.74
QR81,723.01
QR119,121.64
QR838,036.76
QR1,466,564.28
83 10-Apr-14 A
30-Jun-14
21
60.41%
100%
QR1,047,545.95
109 19-Apr-14 A
26-Jul-14
-7
45.67%
73.37%
QR1,257,055.13
361
330
88
216
32
134
30
70
159
236
147
146
136
39
21
204
254
148
130
164
95
38
28
153
361
215
15
138
137
46
139
183
246
212
204
184
38
20
184
13
263
17-Aug-13 A
10-Sep-13 A
26-Oct-13 A
10-Sep-13 A
18-Dec-13 A
05-Mar-14 A
20-Mar-14 A
19-Dec-13 A
10-Sep-13 A
10-Sep-13 A
12-Sep-13 A
10-Sep-13 A
12-Sep-13 A
06-Mar-14 A
17-Dec-13 A
14-Sep-13 A
24-Aug-13 A
24-Aug-13 A
01-Sep-13 A
24-Aug-13 A
17-Nov-13 A
06-Mar-14 A
25-Dec-13 A
01-Sep-13 A
17-Aug-13 A
17-Aug-13 A
06-Mar-14 A
31-Aug-13 A
06-Mar-14 A
06-Mar-14 A
22-Dec-13 A
10-Sep-13 A
31-Aug-13 A
31-Aug-13 A
17-Sep-13 A
16-Sep-13 A
06-Mar-14 A
22-Dec-13 A
14-Sep-13 A
05-Dec-13 A
25-Sep-13 A
Finish
23
23
23
-8
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
2013
N
J Jul A
2014
S
A M
J Jul A
Page 4 of 4
S Oct N
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
Calendar
2013
ND J F
241 08-Dec-13 A
26-Jul-14
-7
67.02%
88.17%
QR3,716,773.03
27 30-Jun-14
26-Jul-14
-7
0%
0%
QR0.00
26 30-Jun-14
J J AS
2015
2014
N D J FMA
J J AS
N D J FM
26-Jul-14
-7
0%
0%
QR0.00
30-Jun-14
19
0%
0%
QR0.00
Provisional Proje
26-Jul-14
-7
0%
0%
QR0.00
Final Project C
KEY MILESTONES
1 30-Jun-14
30-Jun-14
19
0%
0%
QR0.00
30-Jun-14
19
0%
0%
QR0.00
Completion of Ph
30-Jun-14
20
0%
0%
QR0.00
Completion of Ph
30-Jun-14
20
0%
0%
QR0.00
Completion of Ph
243 08-Dec-13 A
30-Jun-14
22
90.94%
97.59%
QR1,412,171.95
231 17-Dec-13 A
CONSTRUCTION
Phase 1 Works
Construction
Zone 2
Fountain sculpture and finishing
Fix fountain finishes
Zone 3
Shade structures erection
Fix fabric shades
Zone 4
Shade structures erection
Fix fabric shades
Phase 1 - Testing and Commissioning
Testing and Commissioning for mechanical works
Phase 2 Works
Construction
Zone 6
Shade structures erection
23
88.28%
96.6%
QR503,429.13
30-Jun-14
30-Jun-14
30-Jun-14
30-Jun-14
23
22
22
22
50%
50%
50%
50%
81.7%
66.22%
66.22%
66.22%
QR93,429.01
QR40,041.01
QR40,041.01
QR40,041.01
30 05-Jun-14 A
30 05-Jun-14 A
30 05-Jun-14 A
30-Jun-14
30-Jun-14
30-Jun-14
23
23
23
50%
50%
50%
93.3%
93.3%
93.3%
QR26,694.00
QR26,694.00
QR26,694.00
30 05-Jun-14 A
30 05-Jun-14 A
30 05-Jun-14 A
30-Jun-14
30-Jun-14
30-Jun-14
22
22
22
50%
50%
50%
93.3%
93.3%
93.3%
QR26,694.00
QR26,694.00
QR26,694.00
6 17-Dec-13 A
6 17-Dec-13 A
30-Jun-14
30-Jun-14
-8
-8
97%
97%
100%
100%
QR410,000.12
QR410,000.12
243 08-Dec-13 A
30-Jun-14
22
91.58%
98.76%
QR463,421.75
12-Jun-14 A
12-Jun-14 A
12-Jun-14 A
12-Jun-14 A
30-Jun-14
30-Jun-14
30-Jun-14
30-Jun-14
22
-8
-8
-8
50%
50%
50%
50%
89.21%
94.6%
94.6%
94.6%
QR53,421.63
QR9,120.77
QR9,120.77
QR9,120.77
21 12-Jun-14 A
21 12-Jun-14 A
21 12-Jun-14 A
30-Jun-14
30-Jun-14
30-Jun-14
23
23
23
50%
50%
50%
94.6%
94.6%
94.6%
QR9,120.77
QR9,120.77
QR9,120.77
5 12-Jun-14 A
5 12-Jun-14 A
5 12-Jun-14 A
30-Jun-14
30-Jun-14
30-Jun-14
-8
-8
-8
50%
50%
50%
100%
100%
100%
QR9,120.77
QR9,120.77
QR9,120.77
30 12-Jun-14 A
30 12-Jun-14 A
30 12-Jun-14 A
30-Jun-14
30-Jun-14
30-Jun-14
-9
-9
-9
50%
50%
50%
63.33%
63.33%
63.33%
QR13,029.66
QR13,029.66
QR13,029.66
15 12-Jun-14 A
15 12-Jun-14 A
15 12-Jun-14 A
30-Jun-14
30-Jun-14
30-Jun-14
-8
-8
-8
50%
50%
50%
100%
100%
100%
QR13,029.66
QR13,029.66
QR13,029.66
9 08-Dec-13 A
9 08-Dec-13 A
30-Jun-14
30-Jun-14
-8
-8
97%
97%
100%
100%
QR410,000.12
QR410,000.12
234 10-Dec-13 A
30-Jun-14
23
93.27%
97.49%
QR445,321.07
12-Jun-14 A
12-Jun-14 A
12-Jun-14 A
12-Jun-14 A
30-Jun-14
30-Jun-14
30-Jun-14
30-Jun-14
23
23
23
23
50%
50%
50%
50%
68.37%
94.6%
94.6%
94.6%
QR35,320.95
QR14,543.92
QR14,543.92
QR14,543.92
10 25-Jun-14 A
10 25-Jun-14 A
10 25-Jun-14 A
30-Jun-14
30-Jun-14
30-Jun-14
23
23
23
50%
50%
50%
50%
50%
50%
QR20,777.03
QR20,777.03
QR20,777.03
31
21
21
21
Phase 3 Works
Construction
Zone 12
Shade structures erection
25
21
21
21
30-Jun-14
05-Jun-14 A
12-Jun-14 A
12-Jun-14 A
12-Jun-14 A
38
30
30
30
Remaining
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Page 1 of 2
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
Calendar
2013
ND J F
8 10-Dec-13 A
8 10-Dec-13 A
30-Jun-14
30-Jun-14
-8
-8
97%
97%
100%
100%
QR410,000.12
QR410,000.12
83 10-Apr-14 A
30-Jun-14
21
60.41%
100%
QR1,047,545.95
J J AS
2015
2014
N D J FMA
J J AS
N D J FM
6 10-Apr-14 A
30-Jun-14
-9
88%
100%
QR125,045.68
Prepare punch li
14 01-May-14 A
30-Jun-14
21
65%
100%
QR239,166.74
10 19-Apr-14 A
30-Jun-14
21
65%
100%
QR170,833.38
Pre-commissioni
6 18-May-14 A
30-Jun-14
21
50%
100%
QR102,500.03
Prepare punch li
14 17-May-14 A
30-Jun-14
21
50%
100%
QR239,166.74
Final testing & commissioning for irrigation, utilities and electrical system
10 14-Jun-14 A
30-Jun-14
21
50%
100%
QR170,833.38
109 19-Apr-14 A
26-Jul-14
-7
45.67%
67.74%
QR1,257,055.13
83 19-Apr-14 A
30-Jun-14
-8
42.59%
67.35%
QR367,460.78
45 19-Apr-14 A
30-Jun-14
-9
50%
100%
QR231,298.38
10 26-Jun-14 A
30-Jun-14
-6
30%
11.88%
QR136,162.40
Company review
34 07-Jun-14 A
06-Jul-14
-9
38%
60.34%
QR226,937.33
30 07-Jun-14 A
30-Jun-14
-9
50%
88.44%
QR136,162.40
11 26-Jun-14 A
06-Jul-14
-5
20%
18.18%
QR90,774.93
Company Revie
25 07-Jun-14 A
10-Jul-14
-8
50%
100%
QR118,007.41
25 07-Jun-14 A
10-Jul-14
-8
50%
100%
QR118,007.41
25 07-Jun-14 A
15-Jul-14
-8
50%
100%
QR113,468.67
25 07-Jun-14 A
15-Jul-14
-8
50%
100%
QR113,468.67
25 07-Jun-14 A
21-Jul-14
-8
50%
100%
QR113,468.67
25 07-Jun-14 A
21-Jul-14
-8
50%
100%
QR113,468.67
69 07-Jun-14 A
26-Jul-14
-8
50%
38.45%
QR317,712.27
69 07-Jun-14 A
26-Jul-14
-8
50%
38.45%
QR317,712.27
Redline Mark-ups
Project Dossier
Prepare & Submit project dossier
Material Take-off
Prepare & Submit material take-off & spare parts
O&M Manual
Prepare & submit O&M Manual
Remaining
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Page 2 of 2
Activity Name
Original Start
Duration
Finish
Planned %
Complete
26-Jul-14
-7
94.15%
98.4%
QR20,950,917.53
644 21-Oct-12 A
26-Jul-14
-7
100%
100%
QR1,047,545.97
644 21-Oct-12 A
26-Jul-14
-7
0%
0%
QR0.00
100%
100%
QR0.00
19
0%
100%
QR0.00
26-Jul-14
-7
0%
0%
QR0.00
30-Jun-14
19
0%
0%
QR0.00
0 21-Oct-12 A
30-Jun-14
Actual %
Complete
654 21-Oct-12 A
KEY MILESTONES
Total
Float
543 04-Jan-13 A
2013
N
J Jul A
2014
S
A M
J Jul A
S Oct N
Completion of Mobilisation
04-Jan-13 A
100%
100%
QR0.00
21-Mar-13 A
100%
100%
QR0.00
Completion of Procurement
01-Jul-13 A
100%
100%
QR0.00
19-Dec-13 A
100%
100%
QR0.00
30-Jun-14
19
0%
100%
QR0.00
Completion of Pha
30-Jun-14
20
0%
100%
QR0.00
Completion of Pha
30-Jun-14
20
Completion of Pha
0%
100%
QR0.00
75 21-Oct-12 A
03-Jan-13 A
100%
100%
QR1,047,545.97
60
39
19
3
21-Oct-12 A
21-Oct-12 A
21-Oct-12 A
21-Oct-12 A
20-Dec-12 A
28-Nov-12 A
08-Nov-12 A
23-Oct-12 A
100%
100%
100%
100%
100%
100%
100%
100%
QR499,965.17
QR321,366.64
QR41,821.06
QR16,584.31
10 23-Oct-12 A
06-Nov-12 A
100%
100%
QR19,412.88
3 06-Nov-12 A 08-Nov-12 A
100%
100%
QR5,823.87
19 21-Oct-12 A
3 21-Oct-12 A
08-Nov-12 A
23-Oct-12 A
100%
100%
100%
100%
QR31,060.62
QR5,823.87
10 23-Oct-12 A
06-Nov-12 A
100%
100%
QR19,412.88
3 06-Nov-12 A 08-Nov-12 A
100%
100%
QR5,823.87
19 21-Oct-12 A
3 21-Oct-12 A
08-Nov-12 A
23-Oct-12 A
100%
100%
100%
100%
QR31,060.62
QR5,823.87
10 23-Oct-12 A
06-Nov-12 A
100%
100%
QR19,412.88
3 06-Nov-12 A 08-Nov-12 A
100%
100%
QR5,823.87
20 23-Oct-12 A
3 23-Oct-12 A
12-Nov-12 A
25-Oct-12 A
100%
100%
100%
100%
QR31,060.62
QR5,823.87
10 28-Oct-12 A
08-Nov-12 A
100%
100%
QR19,412.88
3 08-Nov-12 A 12-Nov-12 A
100%
100%
QR5,823.87
20 23-Oct-12 A
3 23-Oct-12 A
12-Nov-12 A
25-Oct-12 A
100%
100%
100%
100%
QR31,060.62
QR5,823.87
10 28-Oct-12 A
08-Nov-12 A
100%
100%
QR19,412.88
3 08-Nov-12 A 12-Nov-12 A
Completion of Mobilisation
Completion of Engineering Works
Completion of Procurement
Completion of Phase 1 Works
100%
100%
QR5,823.87
20 23-Oct-12 A
3 23-Oct-12 A
12-Nov-12 A
25-Oct-12 A
100%
100%
100%
100%
QR31,060.62
QR5,823.87
10 28-Oct-12 A
08-Nov-12 A
100%
100%
QR19,412.88
3 08-Nov-12 A 12-Nov-12 A
100%
100%
QR5,823.87
QA/QC Engineer
20 23-Oct-12 A
3 23-Oct-12 A
12-Nov-12 A
25-Oct-12 A
100%
100%
100%
100%
QR31,060.62
QR5,823.87
10 28-Oct-12 A
08-Nov-12 A
100%
100%
QR19,412.88
3 08-Nov-12 A 12-Nov-12 A
100%
100%
QR5,823.87
20 08-Nov-12 A 28-Nov-12 A
3 08-Nov-12 A 12-Nov-12 A
100%
100%
100%
100%
QR31,060.62
QR5,823.87
10 12-Nov-12 A 26-Nov-12 A
100%
100%
QR19,412.88
Remaining
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Page 1 of 25
Activity Name
Original Start
Duration
Finish
3 26-Nov-12 A 28-Nov-12 A
Electrical Engineer
Total
Float
Actual %
Complete
Planned %
Complete
100%
100%
QR5,823.87
20 25-Oct-12 A
3 25-Oct-12 A
14-Nov-12 A
29-Oct-12 A
100%
100%
100%
100%
QR31,060.62
QR5,823.87
10 29-Oct-12 A
12-Nov-12 A
100%
100%
QR19,412.88
3 12-Nov-12 A 14-Nov-12 A
100%
100%
QR5,823.87
20 25-Oct-12 A
3 25-Oct-12 A
14-Nov-12 A
29-Oct-12 A
100%
100%
100%
100%
QR31,060.62
QR5,823.87
10 29-Oct-12 A
12-Nov-12 A
100%
100%
QR19,412.88
3 12-Nov-12 A 14-Nov-12 A
100%
100%
QR5,823.87
2013
N
J Jul A
2014
S
31-Oct-12 A
100%
100%
QR11,647.73
12 29-Oct-12 A
08-Nov-12 A
100%
100%
QR23,295.46
18 05-Nov-12 A 20-Nov-12 A
100%
100%
QR34,943.19
18 12-Nov-12 A 27-Nov-12 A
100%
100%
QR34,943.19
14 27-Nov-12 A 10-Dec-12 A
100%
100%
QR27,178.04
14 03-Dec-12 A
16-Dec-12 A
100%
100%
QR27,178.04
4 16-Dec-12 A
19-Dec-12 A
100%
100%
QR7,765.15
1 19-Dec-12 A
20-Dec-12 A
100%
100%
QR1,941.29
66 21-Oct-12 A
10 21-Oct-12 A
25-Dec-12 A
29-Oct-12 A
100%
100%
100%
100%
QR190,462.86
QR23,512.08
10 21-Oct-12 A
29-Oct-12 A
100%
100%
QR19,412.88
44 12-Nov-12 A 25-Dec-12 A
24 12-Nov-12 A 06-Dec-12 A
12 12-Nov-12 A 22-Nov-12 A
100%
100%
100%
100%
100%
100%
QR73,768.95
QR42,708.34
QR23,295.46
10 22-Nov-12 A 06-Dec-12 A
100%
100%
QR19,412.88
20 06-Dec-12 A
6 06-Dec-12 A
25-Dec-12 A
11-Dec-12 A
100%
100%
100%
100%
QR31,060.61
QR11,647.73
10 11-Dec-12 A
25-Dec-12 A
100%
100%
QR19,412.88
44 12-Nov-12 A 25-Dec-12 A
24 12-Nov-12 A 06-Dec-12 A
12 12-Nov-12 A 22-Nov-12 A
100%
100%
100%
100%
100%
100%
QR73,768.95
QR42,708.34
QR23,295.46
10 22-Nov-12 A 06-Dec-12 A
100%
100%
QR19,412.88
20 06-Dec-12 A
6 06-Dec-12 A
25-Dec-12 A
11-Dec-12 A
100%
100%
100%
100%
QR31,060.61
QR11,647.73
10 11-Dec-12 A
25-Dec-12 A
100%
100%
QR19,412.88
64 08-Nov-12 A 03-Jan-13 A
60 08-Nov-12 A 31-Dec-12 A
18 08-Nov-12 A 25-Nov-12 A
100%
100%
100%
100%
100%
100%
QR357,117.94
QR182,401.98
QR42,629.21
21 18-Nov-12 A 06-Dec-12 A
100%
100%
QR40,767.06
30 26-Nov-12 A 23-Dec-12 A
100%
100%
QR58,238.65
21 13-Dec-12 A
31-Dec-12 A
100%
100%
QR40,767.06
57 15-Nov-12 A 03-Jan-13 A
18 15-Nov-12 A 01-Dec-12 A
100%
100%
100%
100%
QR174,715.96
QR34,943.19
21 24-Nov-12 A 12-Dec-12 A
100%
100%
QR40,767.06
30 03-Dec-12 A
29-Dec-12 A
100%
100%
QR58,238.65
21 17-Dec-12 A
03-Jan-13 A
100%
100%
QR40,767.06
540 23-Oct-12 A
12-Jun-14 A
100%
100%
QR1,047,545.47
120 23-Oct-12 A
05-Feb-13 A
100%
100%
QR89,089.66
Key Suppliers
ENGINEERING
Site Survey and Trial pit Excavation
Remaining
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
J Jul A
S Oct N
6 25-Oct-12 A
Final Submission
A M
QR178,598.53
QR9,706.44
100%
100%
Final Submission
100%
100%
20-Dec-12 A
25-Oct-12 A
Levelling, Grading & Setting -Out for Site Offices & Lay Down Areas
60 21-Oct-12 A
5 21-Oct-12 A
Page 2 of 25
Activity Name
Original Start
Duration
Actual %
Complete
Planned %
Complete
05-Feb-13 A
100%
100%
QR89,089.66
100%
100%
QR193,769.92
47 08-Nov-12 A 26-Dec-12 A
25 08-Nov-12 A 03-Dec-12 A
12 08-Nov-12 A 19-Nov-12 A
100%
100%
100%
100%
100%
100%
QR34,680.65
QR20,151.95
QR12,887.60
10 20-Nov-12 A 03-Dec-12 A
100%
100%
QR7,264.35
22 03-Dec-12 A
10 03-Dec-12 A
26-Dec-12 A
12-Dec-12 A
100%
100%
100%
100%
QR14,528.70
QR7,264.35
10 12-Dec-12 A
26-Dec-12 A
100%
100%
QR7,264.35
48 03-Dec-12 A
24 03-Dec-12 A
12 03-Dec-12 A
21-Jan-13 A
27-Dec-12 A
13-Dec-12 A
100%
100%
100%
100%
100%
100%
QR31,236.71
QR15,981.57
QR8,717.22
10 16-Dec-12 A
27-Dec-12 A
100%
100%
QR7,264.35
24 27-Dec-12 A
11 27-Dec-12 A
21-Jan-13 A
07-Jan-13 A
100%
100%
100%
100%
QR15,255.14
QR7,990.79
10 07-Jan-13 A
21-Jan-13 A
100%
100%
QR7,264.35
49 01-Nov-12 A 20-Dec-12 A
25 01-Nov-12 A 26-Nov-12 A
12 01-Nov-12 A 12-Nov-12 A
100%
100%
100%
100%
100%
100%
QR31,963.14
QR15,981.57
QR8,717.22
10 12-Nov-12 A 26-Nov-12 A
100%
100%
QR7,264.35
24 26-Nov-12 A 20-Dec-12 A
12 26-Nov-12 A 06-Dec-12 A
100%
100%
100%
100%
QR15,981.57
QR8,717.22
10 06-Dec-12 A
120 23-Oct-12 A
Final Submission
Final Submission
Final Submission
Finish
Total
Float
2013
N
J Jul A
10 02-Dec-12 A
13-Dec-12 A
100%
100%
QR7,264.35
25 13-Dec-12 A
12 13-Dec-12 A
07-Jan-13 A
24-Dec-12 A
100%
100%
100%
100%
QR15,981.57
QR8,717.22
10 25-Dec-12 A
07-Jan-13 A
100%
100%
QR7,264.35
49 12-Nov-12 A 31-Dec-12 A
24 12-Nov-12 A 06-Dec-12 A
12 12-Nov-12 A 22-Nov-12 A
100%
100%
100%
100%
100%
100%
QR31,963.14
QR15,981.57
QR8,717.22
10 22-Nov-12 A 06-Dec-12 A
100%
100%
QR7,264.35
25 06-Dec-12 A
12 06-Dec-12 A
31-Dec-12 A
17-Dec-12 A
100%
100%
100%
100%
QR15,981.57
QR8,717.22
10 17-Dec-12 A
31-Dec-12 A
100%
100%
QR7,264.35
49 31-Dec-12 A
24 31-Dec-12 A
12 31-Dec-12 A
18-Feb-13 A
24-Jan-13 A
10-Jan-13 A
100%
100%
100%
100%
100%
100%
QR31,963.14
QR15,981.57
QR8,717.22
10 10-Jan-13 A
24-Jan-13 A
100%
100%
QR7,264.35
25 24-Jan-13 A
12 24-Jan-13 A
18-Feb-13 A
04-Feb-13 A
100%
100%
100%
100%
QR15,981.57
QR8,717.22
10 04-Feb-13 A
18-Feb-13 A
100%
100%
QR7,264.35
482 20-Dec-12 A
12-Jun-14 A
100%
100%
QR764,685.89
56
43
24
12
26-Dec-12 A
07-Jan-13 A
07-Jan-13 A
07-Jan-13 A
20-Feb-13 A
20-Feb-13 A
31-Jan-13 A
17-Jan-13 A
100%
100%
100%
100%
100%
100%
100%
100%
QR209,689.55
QR44,062.37
QR32,439.41
QR25,175.06
10 20-Jan-13 A
31-Jan-13 A
100%
100%
QR7,264.35
Remaining
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
S Oct N
J Jul A
A M
QR7,264.35
QR31,963.14
QR15,981.57
QR8,717.22
100%
100%
100%
Final Submission
100%
Cable Submission
First Submission
100%
100%
100%
Final Submission
100%
20-Dec-12 A
Final Submission
49 19-Nov-12 A 07-Jan-13 A
24 19-Nov-12 A 13-Dec-12 A
12 19-Nov-12 A 29-Nov-12 A
Concrete Foundations
First Submission
2014
Page 3 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
2013
N
J Jul A
2014
S
19 31-Jan-13 A
6 31-Jan-13 A
20-Feb-13 A
06-Feb-13 A
100%
100%
100%
100%
10 06-Feb-13 A
20-Feb-13 A
100%
100%
QR7,264.35
44
24
12
10
06-Jan-13 A
06-Jan-13 A
06-Jan-13 A
16-Jan-13 A
18-Feb-13 A
30-Jan-13 A
16-Jan-13 A
30-Jan-13 A
100%
100%
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
QR7,264.35
Prepare & resubmit Design for Civil/Structural Works of Paved Pedestrian Plaz
20 30-Jan-13 A
6 30-Jan-13 A
18-Feb-13 A
04-Feb-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 05-Feb-13 A
18-Feb-13 A
100%
100%
QR7,264.35
Prepare & submit Design for Civil/Structural Works of Walkways & road crossin
44 26-Dec-12 A
25 26-Dec-12 A
12 26-Dec-12 A
07-Feb-13 A
20-Jan-13 A
06-Jan-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 06-Jan-13 A
20-Jan-13 A
100%
100%
QR7,264.35
Prepare & resubmit Design for Civil/Structural Works of Walkways & road cross
19 20-Jan-13 A
6 20-Jan-13 A
07-Feb-13 A
24-Jan-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 27-Jan-13 A
07-Feb-13 A
100%
100%
QR7,264.35
Prepare & submit Design for Civil/Structural Works of Gravel Beds & Boulders
44 26-Dec-12 A
25 26-Dec-12 A
12 26-Dec-12 A
07-Feb-13 A
20-Jan-13 A
06-Jan-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 06-Jan-13 A
20-Jan-13 A
100%
100%
QR7,264.35
Prepare & resubmit Design for Civil/Structural Works of Gravel Beds & Boulder
19 20-Jan-13 A
6 20-Jan-13 A
07-Feb-13 A
24-Jan-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 27-Jan-13 A
07-Feb-13 A
100%
100%
QR7,264.35
Prepare & submit Design for Civil/Structural Works of Site Grading & Drainage
44 26-Dec-12 A
25 26-Dec-12 A
12 26-Dec-12 A
07-Feb-13 A
20-Jan-13 A
06-Jan-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 06-Jan-13 A
20-Jan-13 A
100%
100%
QR7,264.35
Prepare & resubmit Design for Civil/Structural Works of Site Grading & Drainag
19 20-Jan-13 A
6 20-Jan-13 A
07-Feb-13 A
24-Jan-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 27-Jan-13 A
07-Feb-13 A
100%
100%
QR7,264.35
44 26-Dec-12 A
25 26-Dec-12 A
12 26-Dec-12 A
07-Feb-13 A
20-Jan-13 A
06-Jan-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 06-Jan-13 A
20-Jan-13 A
100%
100%
QR7,264.35
19 20-Jan-13 A
6 20-Jan-13 A
07-Feb-13 A
24-Jan-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 27-Jan-13 A
07-Feb-13 A
100%
100%
QR7,264.35
44 26-Dec-12 A
25 26-Dec-12 A
12 26-Dec-12 A
07-Feb-13 A
20-Jan-13 A
06-Jan-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 06-Jan-13 A
20-Jan-13 A
100%
100%
QR7,264.35
19 20-Jan-13 A
6 20-Jan-13 A
07-Feb-13 A
24-Jan-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 27-Jan-13 A
07-Feb-13 A
100%
100%
QR7,264.35
65
44
24
12
06-Jan-13 A
06-Jan-13 A
06-Jan-13 A
06-Jan-13 A
11-Mar-13 A
18-Feb-13 A
30-Jan-13 A
16-Jan-13 A
100%
100%
100%
100%
100%
100%
100%
100%
QR82,813.59
QR27,604.53
QR15,981.57
QR8,717.22
10 16-Jan-13 A
30-Jan-13 A
100%
100%
QR7,264.35
20 30-Jan-13 A
18-Feb-13 A
100%
100%
QR11,622.96
Car Parking
Submission for Company Comments
Edgers
Submission for Company Comments
Remaining
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
A M
J Jul A
S Oct N
Prepare & submit Design for Civil/Structural Works of Paved Pedestrian Plaza
Company review and comments
Prepare & resubmit Design for Civil/Structural Works of Paved Pedestrian Plaza
Company review and Approval
Prepare & submit Design for Civil/Structural Works of Walkways & road crossings
Company review and comments
Prepare & resubmit Design for Civil/Structural Works of Walkways & road crossings
Company review and Approval
Prepare & submit Design for Civil/Structural Works of Gravel Beds & Boulders
Company review and comments
Prepare & resubmit Design for Civil/Structural Works of Gravel Beds & Boulders
Company review and Approval
Prepare & submit Design for Civil/Structural Works of Site Grading & Drainage
Company review and comments
Prepare & resubmit Design for Civil/Structural Works of Site Grading & Drainage
Company review and Approval
Page 4 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
6 30-Jan-13 A
04-Feb-13 A
100%
100%
10 05-Feb-13 A
18-Feb-13 A
100%
100%
QR7,264.35
44 16-Jan-13 A
25 16-Jan-13 A
12 16-Jan-13 A
28-Feb-13 A
10-Feb-13 A
27-Jan-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 27-Jan-13 A
10-Feb-13 A
100%
100%
QR7,264.35
19 10-Feb-13 A
6 10-Feb-13 A
28-Feb-13 A
14-Feb-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 17-Feb-13 A
28-Feb-13 A
100%
100%
QR7,264.35
44 27-Jan-13 A
24 27-Jan-13 A
12 27-Jan-13 A
11-Mar-13 A
20-Feb-13 A
06-Feb-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 06-Feb-13 A
20-Feb-13 A
100%
100%
QR7,264.35
20 20-Feb-13 A
6 20-Feb-13 A
11-Mar-13 A
25-Feb-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 26-Feb-13 A
11-Mar-13 A
100%
100%
QR7,264.35
53
44
24
12
21-Jan-13 A
21-Jan-13 A
21-Jan-13 A
21-Jan-13 A
14-Mar-13 A
05-Mar-13 A
14-Feb-13 A
31-Jan-13 A
100%
100%
100%
100%
100%
100%
100%
100%
QR138,022.65
QR27,604.53
QR15,981.57
QR8,717.22
10 31-Jan-13 A
14-Feb-13 A
100%
100%
QR7,264.35
20 14-Feb-13 A
6 14-Feb-13 A
05-Mar-13 A
19-Feb-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 19-Feb-13 A
05-Mar-13 A
100%
100%
QR7,264.35
44 21-Jan-13 A
24 21-Jan-13 A
12 21-Jan-13 A
05-Mar-13 A
14-Feb-13 A
31-Jan-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 31-Jan-13 A
14-Feb-13 A
100%
100%
QR7,264.35
20 14-Feb-13 A
6 14-Feb-13 A
05-Mar-13 A
19-Feb-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 19-Feb-13 A
05-Mar-13 A
100%
100%
QR7,264.35
43 31-Jan-13 A
25 31-Jan-13 A
12 31-Jan-13 A
14-Mar-13 A
25-Feb-13 A
11-Feb-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 11-Feb-13 A
25-Feb-13 A
100%
100%
QR7,264.35
18 25-Feb-13 A
6 25-Feb-13 A
14-Mar-13 A
02-Mar-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 03-Mar-13 A
14-Mar-13 A
100%
100%
QR7,264.35
43 31-Jan-13 A
25 31-Jan-13 A
12 31-Jan-13 A
14-Mar-13 A
25-Feb-13 A
11-Feb-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 11-Feb-13 A
25-Feb-13 A
100%
100%
QR7,264.35
18 25-Feb-13 A
6 25-Feb-13 A
14-Mar-13 A
02-Mar-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 03-Mar-13 A
14-Mar-13 A
100%
100%
QR7,264.35
43 31-Jan-13 A
25 31-Jan-13 A
12 31-Jan-13 A
14-Mar-13 A
25-Feb-13 A
11-Feb-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 11-Feb-13 A
25-Feb-13 A
100%
100%
QR7,264.35
18 25-Feb-13 A
14-Mar-13 A
100%
100%
QR11,622.96
Mosque Plaza
Submission for Company Comments
Bus Plaza
Submission for Company Comments
Walkways (2-Types)
Submission for Company Comments
Parking Areas
Submission for Company Comments
Remaining
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
2013
N
J Jul A
2014
S
A M
J Jul A
S Oct N
Page 5 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
6 25-Feb-13 A
02-Mar-13 A
100%
100%
10 03-Mar-13 A
14-Mar-13 A
100%
100%
QR7,264.35
75
43
24
12
31-Dec-12 A
31-Dec-12 A
31-Dec-12 A
31-Dec-12 A
17-Mar-13 A
13-Feb-13 A
24-Jan-13 A
10-Jan-13 A
100%
100%
100%
100%
100%
100%
100%
100%
QR165,627.18
QR27,604.53
QR15,981.57
QR8,717.22
10 10-Jan-13 A
24-Jan-13 A
100%
100%
QR7,264.35
19 24-Jan-13 A
6 24-Jan-13 A
13-Feb-13 A
30-Jan-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 30-Jan-13 A
13-Feb-13 A
100%
100%
QR7,264.35
43 31-Dec-12 A
24 31-Dec-12 A
12 31-Dec-12 A
13-Feb-13 A
24-Jan-13 A
10-Jan-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 10-Jan-13 A
24-Jan-13 A
100%
100%
QR7,264.35
19 24-Jan-13 A
6 24-Jan-13 A
13-Feb-13 A
30-Jan-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 30-Jan-13 A
13-Feb-13 A
100%
100%
QR7,264.35
44 10-Jan-13 A
25 10-Jan-13 A
12 10-Jan-13 A
24-Feb-13 A
04-Feb-13 A
21-Jan-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 21-Jan-13 A
04-Feb-13 A
100%
100%
QR7,264.35
19 04-Feb-13 A
6 04-Feb-13 A
24-Feb-13 A
10-Feb-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 10-Feb-13 A
24-Feb-13 A
100%
100%
QR7,264.35
44 10-Jan-13 A
25 10-Jan-13 A
12 10-Jan-13 A
24-Feb-13 A
04-Feb-13 A
21-Jan-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 21-Jan-13 A
04-Feb-13 A
100%
100%
QR7,264.35
19 04-Feb-13 A
6 04-Feb-13 A
24-Feb-13 A
10-Feb-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 10-Feb-13 A
24-Feb-13 A
100%
100%
QR7,264.35
43 21-Jan-13 A
24 21-Jan-13 A
12 21-Jan-13 A
06-Mar-13 A
14-Feb-13 A
31-Jan-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 31-Jan-13 A
14-Feb-13 A
100%
100%
QR7,264.35
19 14-Feb-13 A
6 14-Feb-13 A
06-Mar-13 A
20-Feb-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 20-Feb-13 A
06-Mar-13 A
100%
100%
QR7,264.35
44 31-Jan-13 A
25 31-Jan-13 A
12 31-Jan-13 A
17-Mar-13 A
25-Feb-13 A
11-Feb-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 11-Feb-13 A
25-Feb-13 A
100%
100%
QR7,264.35
19 25-Feb-13 A
6 25-Feb-13 A
17-Mar-13 A
03-Mar-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 03-Mar-13 A
17-Mar-13 A
100%
100%
QR7,264.35
31-Dec-12 A
31-Dec-12 A
31-Dec-12 A
31-Dec-12 A
12-Jun-14 A
13-Feb-13 A
24-Jan-13 A
10-Jan-13 A
100%
100%
100%
100%
100%
100%
100%
100%
QR110,418.12
QR27,604.53
QR15,981.57
QR8,717.22
10 10-Jan-13 A
24-Jan-13 A
100%
100%
QR7,264.35
Secondary Entrance ID
Submission for Company Comments
Pedestrian Directions
Submission for Company Comments
Electrical Works
Lighting in the Car Parking Areas
Submission for Company Comments
Prepare & submit Design for lighting in the car parking areas
Company review and comments
Remaining
471
43
24
12
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
2013
N
J Jul A
2014
S
A M
J Jul A
S Oct N
Prepare & submit Design for lighting in the car parking areas
Company review and comments
Page 6 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
2013
N
J Jul A
2014
S
A M
J Jul A
S Oct N
Prepare & resubmit Design for lighting in the car parking areas
19 24-Jan-13 A
6 24-Jan-13 A
13-Feb-13 A
30-Jan-13 A
100%
100%
100%
100%
10 30-Jan-13 A
13-Feb-13 A
100%
100%
QR7,264.35
44 10-Jan-13 A
25 10-Jan-13 A
12 10-Jan-13 A
24-Feb-13 A
04-Feb-13 A
21-Jan-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 21-Jan-13 A
04-Feb-13 A
100%
100%
QR7,264.35
19 04-Feb-13 A
6 04-Feb-13 A
24-Feb-13 A
10-Feb-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 10-Feb-13 A
24-Feb-13 A
100%
100%
QR7,264.35
Prepare & submit Design for underwater lights in the water fountain
43 21-Jan-13 A
24 21-Jan-13 A
12 21-Jan-13 A
06-Mar-13 A
14-Feb-13 A
31-Jan-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 31-Jan-13 A
14-Feb-13 A
100%
100%
QR7,264.35
Prepare & resubmit Design for underwater lights in the water fountain
19 14-Feb-13 A
6 14-Feb-13 A
06-Mar-13 A
20-Feb-13 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 20-Feb-13 A
06-Mar-13 A
100%
100%
QR7,264.35
440 31-Jan-13 A
25 31-Jan-13 A
12 31-Jan-13 A
12-Jun-14 A
25-Feb-13 A
11-Feb-13 A
100%
100%
100%
100%
100%
100%
QR27,604.53
QR15,981.57
QR8,717.22
10 11-Feb-13 A
25-Feb-13 A
100%
100%
QR7,264.35
28 20-Mar-14 A
6 20-Mar-14 A
12-Jun-14 A
25-Mar-14 A
100%
100%
100%
100%
QR11,622.96
QR4,358.61
10 03-Apr-14 A
12-Jun-14 A
100%
100%
QR7,264.35
91
46
25
12
20-Dec-12 A
20-Dec-12 A
20-Dec-12 A
20-Dec-12 A
21-Mar-13 A
04-Feb-13 A
14-Jan-13 A
31-Dec-12 A
100%
100%
100%
100%
100%
100%
100%
100%
QR58,114.80
QR29,057.40
QR15,981.57
QR8,717.22
10 31-Dec-12 A
14-Jan-13 A
100%
100%
QR7,264.35
21 14-Jan-13 A
8 14-Jan-13 A
04-Feb-13 A
21-Jan-13 A
100%
100%
100%
100%
QR13,075.83
QR5,811.48
10 21-Jan-13 A
04-Feb-13 A
100%
100%
QR7,264.35
45 04-Feb-13 A
24 04-Feb-13 A
12 04-Feb-13 A
21-Mar-13 A
28-Feb-13 A
14-Feb-13 A
100%
100%
100%
100%
100%
100%
QR29,057.40
QR15,981.57
QR8,717.22
10 14-Feb-13 A
28-Feb-13 A
100%
100%
QR7,264.35
21 28-Feb-13 A
8 28-Feb-13 A
21-Mar-13 A
07-Mar-13 A
100%
100%
100%
100%
QR13,075.83
QR5,811.48
Mechanical Works
Service Water Network
Submission for Company Comments
Prepare & resubmit Design for lighting in the car parking areas
Company review and Approval
Prepare & submit Design for underwater lights in the water fountain
Company review and comments
Prepare & resubmit Design for underwater lights in the water fountain
Company review and Approval
10 07-Mar-13 A
21-Mar-13 A
100%
100%
QR7,264.35
423 04-Feb-13 A
12-Jun-14 A
100%
100%
QR3,561,656.18
345 04-Feb-13 A
28-Feb-14 A
100%
100%
QR1,237,805.96
36 18-Feb-13 A
19 18-Feb-13 A
6 18-Feb-13 A
26-Mar-13 A
10-Mar-13 A
24-Feb-13 A
100%
100%
100%
100%
100%
100%
QR137,534.00
QR77,207.75
QR30,802.94
10 24-Feb-13 A
10-Mar-13 A
100%
100%
QR46,404.81
16 10-Mar-13 A
3 10-Mar-13 A
26-Mar-13 A
12-Mar-13 A
100%
100%
100%
100%
QR60,326.25
QR13,921.44
10 12-Mar-13 A
26-Mar-13 A
100%
100%
QR46,404.81
36 05-Mar-13 A
19 05-Mar-13 A
10-Apr-13 A
25-Mar-13 A
100%
100%
100%
100%
QR137,534.00
QR77,207.75
PROCUREMENT
Materials Submission and Approval
Interlock pavers, kerb stones and tree guards
First Submission
Final Submission
Foundation bolts
First Submission
Remaining
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Page 7 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
2013
N
J Jul A
2014
S
A M
J Jul A
S Oct N
6 05-Mar-13 A
11-Mar-13 A
100%
100%
QR30,802.94
10 11-Mar-13 A
25-Mar-13 A
100%
100%
QR46,404.81
16 25-Mar-13 A
3 25-Mar-13 A
10-Apr-13 A
27-Mar-13 A
100%
100%
100%
100%
QR60,326.25
QR13,921.44
10 27-Mar-13 A
10-Apr-13 A
100%
100%
QR46,404.81
36 04-Feb-13 A
19 04-Feb-13 A
6 04-Feb-13 A
12-Mar-13 A
24-Feb-13 A
10-Feb-13 A
100%
100%
100%
100%
100%
100%
QR137,534.00
QR77,207.75
QR30,802.94
10 10-Feb-13 A
24-Feb-13 A
100%
100%
QR46,404.81
16 24-Feb-13 A
3 24-Feb-13 A
12-Mar-13 A
26-Feb-13 A
100%
100%
100%
100%
QR60,326.25
QR13,921.44
10 26-Feb-13 A
12-Mar-13 A
100%
100%
QR46,404.81
Prepare & submit materials for shade structures & fabric materials
35 14-Mar-13 A
19 14-Mar-13 A
6 14-Mar-13 A
18-Apr-13 A
03-Apr-13 A
20-Mar-13 A
100%
100%
100%
100%
100%
100%
QR137,534.00
QR77,207.75
QR30,802.94
10 20-Mar-13 A
03-Apr-13 A
100%
100%
QR46,404.81
Prepare & submit materials for shade structures & fabric materials
16 03-Apr-13 A
3 03-Apr-13 A
18-Apr-13 A
06-Apr-13 A
100%
100%
100%
100%
QR60,326.25
QR13,921.44
Prepare & submit materials for shade structures & fabric materials
10 07-Apr-13 A
18-Apr-13 A
100%
100%
QR46,404.81
36 13-Feb-13 A
20 13-Feb-13 A
6 13-Feb-13 A
20-Mar-13 A
04-Mar-13 A
18-Feb-13 A
100%
100%
100%
100%
100%
100%
QR137,534.00
QR77,207.75
QR30,802.94
10 18-Feb-13 A
04-Mar-13 A
100%
100%
QR46,404.81
16 04-Mar-13 A
3 04-Mar-13 A
20-Mar-13 A
06-Mar-13 A
100%
100%
100%
100%
QR60,326.25
QR13,921.44
10 07-Mar-13 A
20-Mar-13 A
100%
100%
QR46,404.81
330 20-Feb-13 A
20 20-Feb-13 A
6 20-Feb-13 A
27-Feb-14 A
11-Mar-13 A
25-Feb-13 A
100%
100%
100%
100%
100%
100%
QR137,533.99
QR77,207.74
QR30,802.93
10 26-Feb-13 A
11-Mar-13 A
100%
100%
QR46,404.81
16 31-Dec-13 A
3 31-Dec-13 A
27-Feb-14 A
27-Feb-14 A
100%
100%
100%
100%
QR60,326.25
QR13,921.44
10 02-Jan-14 A
27-Feb-14 A
100%
100%
QR46,404.81
36 06-Mar-13 A
20 06-Mar-13 A
6 06-Mar-13 A
10-Apr-13 A
25-Mar-13 A
11-Mar-13 A
100%
100%
100%
100%
100%
100%
QR137,533.99
QR77,207.74
QR30,802.93
10 11-Mar-13 A
25-Mar-13 A
100%
100%
QR46,404.81
16 25-Mar-13 A
3 25-Mar-13 A
10-Apr-13 A
27-Mar-13 A
100%
100%
100%
100%
QR60,326.25
QR13,921.44
10 28-Mar-13 A
10-Apr-13 A
100%
100%
QR46,404.81
50 04-Feb-13 A
19 04-Feb-13 A
6 04-Feb-13 A
28-Feb-14 A
24-Feb-13 A
10-Feb-13 A
100%
100%
100%
100%
100%
100%
QR137,533.99
QR77,207.74
QR30,802.93
10 10-Feb-13 A
24-Feb-13 A
100%
100%
QR46,404.81
31 24-Feb-13 A
20 24-Feb-13 A
28-Feb-14 A
28-Feb-14 A
100%
100%
100%
100%
QR60,326.25
QR13,921.44
10 13-Mar-13 A
28-Feb-14 A
100%
100%
QR46,404.81
61 21-Mar-13 A
19 21-Mar-13 A
6 21-Mar-13 A
22-May-13 A
10-Apr-13 A
27-Mar-13 A
100%
100%
100%
100%
100%
100%
QR137,533.99
QR77,207.74
QR30,802.93
Final Submission
Final Submission
Signage structures
First Submission
Final Submission
Fountain sculpture
First Submission
Prepare & submit materials for fountain sculpture
Company Review & approval
Final Submission
Final Submission
Final Submission
Remaining
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Prepare & submit materials for shade structures & fabric materials
Page 8 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
10 27-Mar-13 A
10-Apr-13 A
100%
100%
QR46,404.81
42 10-Apr-13 A
24 10-Apr-13 A
22-May-13 A
01-May-13 A
100%
100%
100%
100%
QR60,326.25
QR13,921.44
15 01-May-13 A 22-May-13 A
100%
100%
QR46,404.81
Final Submission
432 12-Mar-13 A
12-Jun-14 A
100%
100%
QR2,323,850.22
15 26-Mar-13 A
4 26-Mar-13 A
08-Apr-13 A
30-Mar-13 A
100%
100%
100%
100%
QR71,138.27
QR20,092.98
10 30-Mar-13 A
08-Apr-13 A
100%
100%
QR46,404.81
1 08-Apr-13 A
08-Apr-13 A
100%
100%
QR4,640.48
27 10-Apr-13 A
5 10-Apr-13 A
04-May-13 A
15-Apr-13 A
100%
100%
100%
100%
QR128,048.89
QR25,958.31
21 15-Apr-13 A
04-May-13 A
100%
100%
QR97,450.10
1 04-May-13 A 04-May-13 A
100%
100%
QR4,640.48
66 12-Mar-13 A
5 12-Mar-13 A
09-May-13 A
17-Mar-13 A
100%
100%
100%
100%
QR313,008.40
QR29,939.08
60 17-Mar-13 A
08-May-13 A
100%
100%
QR278,428.84
1 08-May-13 A 09-May-13 A
100%
100%
QR4,640.48
381 18-Apr-13 A
4 18-Apr-13 A
03-Apr-14 A
22-Apr-13 A
100%
100%
100%
100%
QR237,127.57
QR18,561.92
45 22-Apr-13 A
03-Apr-14 A
100%
100%
QR213,925.17
1 27-Mar-14 A
03-Apr-14 A
100%
100%
QR4,640.48
384 20-Mar-13 A
5 20-Mar-13 A
27-Feb-14 A
25-Mar-13 A
100%
100%
100%
100%
QR241,870.12
QR28,408.01
45 25-Mar-13 A
27-Feb-14 A
100%
100%
QR208,821.63
1 26-Feb-14 A
27-Feb-14 A
100%
100%
QR4,640.48
414 28-Mar-13 A
5 28-Mar-13 A
12-Jun-14 A
02-Apr-13 A
100%
100%
100%
100%
QR369,919.02
QR31,163.93
72 02-Apr-13 A
03-Apr-14 A
100%
100%
QR334,114.61
1 03-Apr-14 A
12-Jun-14 A
100%
100%
QR4,640.48
62 10-Apr-13 A
5 10-Apr-13 A
04-Jun-13 A
15-Apr-13 A
100%
100%
100%
100%
QR294,038.19
QR29,530.79
56 15-Apr-13 A
03-Jun-13 A
100%
100%
QR259,866.92
1 03-Jun-13 A
04-Jun-13 A
100%
100%
QR4,640.48
96 27-Mar-13 A
5 27-Mar-13 A
03-Apr-14 A
01-Apr-13 A
100%
100%
100%
100%
QR455,284.94
QR33,001.20
90 01-Apr-13 A
31-Mar-14 A
100%
100%
QR417,643.26
1 18-Jun-13 A
03-Apr-14 A
100%
100%
QR4,640.48
45 22-May-13 A 01-Jul-13 A
4 22-May-13 A 26-May-13 A
100%
100%
100%
100%
QR213,414.82
QR23,155.11
40 26-May-13 A 30-Jun-13 A
100%
100%
QR185,619.23
Signage structures
Placing of Orders for sinage structures
Manufacturing & shipment
Delivery arrive on site
Fountain sculpture
Placing of Orders for fountain sculpture
Manufacturing & shipment
Delivery arrive on site
Electrical Poles, DBs and Field Controls
1 30-Jun-13 A
100%
100%
QR4,640.48
CONSTRUCTION
565 20-Feb-13 A
08-Jul-14
22
99.01%
100%
QR12,989,568.83
564 20-Feb-13 A
30-Jun-14
23
98.72%
100%
QR4,609,201.93
564
200
109
21
20-Feb-13 A
20-Feb-13 A
20-Feb-13 A
20-Feb-13 A
30-Jun-14
23-Jan-14 A
27-May-13 A
11-Mar-13 A
23
98.76%
100%
100%
100%
100%
100%
100%
100%
QR3,771,165.17
QR979,862.42
QR287,597.98
QR99,850.14
6 11-Mar-13 A
16-Mar-13 A
100%
100%
QR5,338.80
25 03-Mar-13 A
25-Mar-13 A
100%
100%
QR22,245.00
Phase 1 Works
Construction
Zone 1
Open car park paving - Kerb and interlock paving works
Earthworks excavation
Disposal of waste materials
Subgrade formation
Remaining
01-Jul-13 A
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
2013
N
J Jul A
2014
S
A M
J Jul A
S Oct N
Earthworks excavation
Disposal of waste materials
Subgrade formation
Page 9 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
2013
N
2014
J Jul A
45 13-Mar-13 A
22-Apr-13 A
100%
100%
QR40,041.01
45 08-Apr-13 A
18-May-13 A
100%
100%
QR40,041.01
45 14-Apr-13 A
23-May-13 A
100%
100%
QR40,041.01
Paving works
45 17-Apr-13 A
27-May-13 A
100%
100%
QR40,041.01
Paving works
83 18-May-13 A 29-Jul-13 A
21 18-May-13 A 05-Jun-13 A
100%
100%
100%
100%
QR61,396.20
QR18,685.80
21 01-Jul-13 A
18-Jul-13 A
100%
100%
QR18,685.80
21 06-Jul-13 A
24-Jul-13 A
100%
100%
QR18,685.80
6 24-Jul-13 A
29-Jul-13 A
100%
100%
QR5,338.80
88 11-Mar-13 A
21 11-Mar-13 A
31-Dec-13 A
28-Mar-13 A
100%
100%
100%
100%
QR206,433.64
QR18,685.80
Pre-testing of irrigation
Kerb, plant edgers and interlock paving works
Earthworks excavation
Disposal of waste materials
6 28-Mar-13 A
03-Apr-13 A
100%
100%
QR5,338.80
Subgrade formation
25 21-Mar-13 A
11-Apr-13 A
100%
100%
QR22,245.00
40 26-Mar-13 A
30-Apr-13 A
100%
100%
QR40,041.01
40 08-Apr-13 A
13-May-13 A
100%
100%
QR40,041.01
45 14-Apr-13 A
23-May-13 A
100%
100%
QR40,041.01
Paving works
45 17-Apr-13 A
31-Dec-13 A
100%
100%
QR40,041.01
58 30-Apr-13 A
30 30-Apr-13 A
20-Jun-13 A
27-May-13 A
100%
100%
100%
100%
QR85,420.80
QR26,694.00
30 09-May-13 A 04-Jun-13 A
100%
100%
QR26,694.00
30 20-May-13 A 15-Jun-13 A
100%
100%
QR26,694.00
6 15-Jun-13 A
A M
J Jul A
Pre-testing of irrigation
Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for kerbstones
Fix kerbs and supports
Aggregate subbase and fill compaction
Paving works
Excavation for area lightings
Install cables below the ground
Backfilling and compaction
20-Jun-13 A
100%
100%
QR5,338.80
64 13-May-13 A 08-Jul-13 A
15 13-May-13 A 27-May-13 A
100%
100%
100%
100%
QR66,735.00
QR13,347.00
30 02-Jun-13 A
27-Jun-13 A
100%
100%
QR26,694.00
30 12-Jun-13 A
08-Jul-13 A
100%
100%
QR26,694.00
33 27-May-13 A 24-Jun-13 A
15 27-May-13 A 09-Jun-13 A
100%
100%
100%
100%
QR29,363.40
QR13,347.00
Fix signage
18 09-Jun-13 A
24-Jun-13 A
100%
100%
QR16,016.40
30 04-Jun-13 A
30 04-Jun-13 A
01-Jul-13 A
01-Jul-13 A
100%
100%
100%
100%
QR53,388.00
QR26,694.00
30 04-Jun-13 A
01-Jul-13 A
100%
100%
QR26,694.00
27 05-Jun-13 A
21 05-Jun-13 A
19-Jan-14 A
31-Dec-13 A
100%
100%
100%
100%
QR24,024.60
QR18,685.80
6 24-Jun-13 A
19-Jan-14 A
100%
100%
QR5,338.80
36 14-Jul-13 A
30 14-Jul-13 A
23-Jan-14 A
12-Aug-13 A
100%
100%
100%
100%
QR112,114.80
QR26,694.00
30 14-Jul-13 A
12-Aug-13 A
100%
100%
QR26,694.00
30 14-Jul-13 A
12-Aug-13 A
100%
100%
QR26,694.00
30 14-Jul-13 A
12-Aug-13 A
100%
100%
QR26,694.00
23-Jan-14 A
100%
100%
QR5,338.80
Hardscaping works
40 13-May-13 A 17-Jun-13 A
30 13-May-13 A 09-Jun-13 A
100%
100%
100%
100%
QR53,388.00
QR26,694.00
Hardscaping works
Finishing Works
30 22-May-13 A 17-Jun-13 A
100%
100%
QR26,694.00
Finishing Works
97.66%
100%
100%
100%
100%
100%
QR855,987.67
QR86,310.61
QR18,685.80
Pre-testing of irrigation
6 12-Aug-13 A
Zone 2
Concrete foundations for water tanks
Earthworks excavation
Disposal of waste materials
Subgrade formation
Remaining
543 11-Mar-13 A
69 11-Mar-13 A
21 11-Mar-13 A
30-Jun-14
11-Jan-14 A
28-Mar-13 A
23
6 28-Mar-13 A
03-Apr-13 A
100%
100%
QR5,338.80
25 21-Mar-13 A
31-Dec-13 A
100%
100%
QR22,245.00
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
S Oct N
Pre-testing of irrigation
Earthworks excavation
Disposal of waste materials
Subgrade formation
Page 10 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
2013
N
2014
J Jul A
A M
J Jul A
S Oct N
45 01-Apr-13 A
11-Jan-14 A
100%
100%
QR40,041.01
156 05-Jun-13 A
130 05-Jun-13 A
18-Jan-14 A
01-Oct-13 A
100%
100%
100%
100%
QR125,461.80
QR84,531.00
122 20-Jun-13 A
10-Oct-13 A
100%
100%
QR17,796.00
120 27-Jun-13 A
19-Oct-13 A
100%
100%
QR17,796.00
10 19-Oct-13 A
18-Jan-14 A
100%
100%
QR5,338.80
89 11-Mar-13 A
21 11-Mar-13 A
10-Apr-14 A
28-Mar-13 A
100%
100%
100%
100%
QR206,433.64
QR18,685.80
6 03-Apr-13 A
08-Apr-13 A
100%
100%
QR5,338.80
Subgrade formation
25 21-Mar-13 A
11-Apr-13 A
100%
100%
QR22,245.00
45 01-Apr-13 A
13-Mar-14 A
100%
100%
QR40,041.01
45 09-Apr-13 A
22-Mar-14 A
100%
100%
QR40,041.01
45 15-Apr-13 A
27-Mar-14 A
100%
100%
QR40,041.01
Paving works
45 18-Apr-13 A
10-Apr-14 A
100%
100%
QR40,041.01
58 27-May-13 A 06-Feb-14 A
30 27-May-13 A 22-Jun-13 A
100%
100%
100%
100%
QR85,420.80
QR26,694.00
30 04-Jun-13 A
01-Jul-13 A
100%
100%
QR26,694.00
30 15-Jun-13 A
11-Jul-13 A
100%
100%
QR26,694.00
6 11-Jul-13 A
06-Feb-14 A
100%
100%
QR5,338.80
104 19-Jan-14 A
15 19-Jan-14 A
10-Apr-14 A
31-Jan-14 A
100%
100%
100%
100%
QR29,363.40
QR13,347.00
19 03-Apr-14 A
10-Apr-14 A
100%
100%
QR16,016.40
75%
100%
100%
100%
QR80,082.02
QR40,041.01
Pre-testing of irrigation
Kerb, plant edgers and granite paving works
Earthworks excavation
Disposal of waste materials
54 22-May-14 A 30-Jun-14
30 22-May-14 A 12-Jun-14 A
22
30 12-Jun-14 A
22
Paving works
Excavation for area lightings
Install cables below the ground
Backfilling and compaction
Pre-testing of area lighting
Fix signage structure concrete foundatio
Fix signage
50%
100%
QR40,041.01
135 01-Jan-14 A
30 01-Jan-14 A
24-Apr-14 A
27-Jan-14 A
100%
100%
100%
100%
QR53,388.00
QR26,694.00
30 03-Apr-14 A
24-Apr-14 A
100%
100%
QR26,694.00
22 18-Jan-14 A
21 18-Jan-14 A
30-Apr-14 A
06-Feb-14 A
100%
100%
100%
100%
QR24,024.60
QR18,685.80
6 01-Feb-14 A
30-Apr-14 A
100%
100%
QR5,338.80
36 24-Sep-13 A
30 24-Sep-13 A
31-Mar-14 A
24-Oct-13 A
100%
100%
100%
100%
QR112,114.80
QR26,694.00
30 24-Sep-13 A
24-Oct-13 A
100%
100%
QR26,694.00
30 24-Sep-13 A
24-Oct-13 A
100%
100%
QR26,694.00
30 24-Sep-13 A
31-Mar-14 A
100%
100%
QR26,694.00
6 24-Oct-13 A
31-Mar-14 A
100%
100%
QR5,338.80
Pre-testing of irrigation
Hardscaping works
40 19-May-13 A 26-Apr-14 A
30 19-May-13 A 17-Apr-14 A
100%
100%
100%
100%
QR53,388.00
QR26,694.00
Hardscaping works
Finishing Works
30 27-May-13 A 26-Apr-14 A
100%
100%
QR26,694.00
Finishing Works
97.98%
100%
100%
100%
100%
100%
QR660,231.64
QR114,784.20
QR72,073.80
Pre-testing of irrigation
Hardscape and finishing works
Zone 3
Irrigation piping main laying
30-Jun-14
514 28-Mar-13 A
43 01-Oct-13 A
21 01-Oct-13 A
30-Jun-14
18-Jan-14 A
23-Oct-13 A
21 10-Oct-13 A
02-Nov-13 A
100%
100%
QR18,685.80
21 19-Oct-13 A
06-Nov-13 A
100%
100%
QR18,685.80
6 06-Nov-13 A 18-Jan-14 A
Pre-testing of irrigation
Kerb, plant edgers and interlock paving works
Earthworks excavation
Disposal of waste materials
Remaining
23
100%
100%
QR5,338.80
89 28-Mar-13 A
21 28-Mar-13 A
31-Dec-13 A
16-Apr-13 A
100%
100%
100%
100%
QR206,433.64
QR18,685.80
6 16-Apr-13 A
22-Apr-13 A
100%
100%
QR5,338.80
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Pre-testing of irrigation
Earthworks excavation
Disposal of waste materials
Page 11 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
2013
N
2014
J Jul A
A M
J Jul A
S Oct N
Subgrade formation
25 08-Apr-13 A
30-Apr-13 A
100%
100%
QR22,245.00
45 18-Apr-13 A
28-May-13 A
100%
100%
QR40,041.01
45 28-Apr-13 A
06-Jun-13 A
100%
100%
QR40,041.01
45 02-May-13 A 11-Jun-13 A
100%
100%
QR40,041.01
Paving works
45 06-May-13 A 31-Dec-13 A
100%
100%
QR40,041.01
58 22-Jun-13 A
30 22-Jun-13 A
15-Aug-13 A
18-Jul-13 A
100%
100%
100%
100%
QR85,420.80
QR26,694.00
30 01-Jul-13 A
27-Jul-13 A
100%
100%
QR26,694.00
30 11-Jul-13 A
06-Aug-13 A
100%
100%
QR26,694.00
6 06-Aug-13 A
15-Aug-13 A
100%
100%
QR5,338.80
173 01-Feb-14 A
15 01-Feb-14 A
30-Jun-14
06-Feb-14 A
80%
100%
100%
100%
QR66,735.00
QR13,347.00
30 17-Apr-14 A
24-Apr-14 A
100%
100%
QR26,694.00
30 05-Jun-14 A
30-Jun-14
50%
100%
QR26,694.00
23
23
Subgrade formation
Concrete foundation for kerbstones
Fix kerbs and supports
Aggregate subbase and fill compaction
Paving works
Excavation for area lightings
Install cables below the ground
Backfilling and compaction
Pre-testing of area lighting
285 19-Jun-13 A
15 19-Jun-13 A
10-Apr-14 A
02-Jul-13 A
100%
100%
100%
100%
QR29,363.40
QR13,347.00
18 18-Jan-14 A
10-Apr-14 A
100%
100%
QR16,016.40
Fix signage
27 23-Oct-13 A
21 23-Oct-13 A
18-Jan-14 A
11-Nov-13 A
100%
100%
100%
100%
QR24,024.60
QR18,685.80
6 11-Nov-13 A 18-Jan-14 A
100%
100%
QR5,338.80
Fix valves
27 24-Oct-13 A
21 24-Oct-13 A
18-Jan-14 A
12-Nov-13 A
100%
100%
100%
100%
QR80,082.00
QR18,685.80
21 24-Oct-13 A
12-Nov-13 A
100%
100%
QR18,685.80
21 24-Oct-13 A
12-Nov-13 A
100%
100%
QR18,685.80
21 24-Oct-13 A
12-Nov-13 A
100%
100%
QR18,685.80
6 12-Nov-13 A 18-Jan-14 A
100%
100%
QR5,338.80
Pre-testing of irrigation
Hardscape and finishing works
Pre-testing of irrigation
Hardscaping works
40 09-Jun-13 A
30 09-Jun-13 A
03-Apr-14 A
04-Jul-13 A
100%
100%
100%
100%
QR53,388.00
QR26,694.00
Finishing Works
30 17-Jun-13 A
03-Apr-14 A
100%
100%
QR26,694.00
493 16-Apr-13 A
43 23-Oct-13 A
21 23-Oct-13 A
30-Jun-14
18-Jan-14 A
11-Nov-13 A
98.07%
100%
100%
100%
100%
100%
QR692,264.44
QR114,784.20
QR72,073.80
Zone 4
Irrigation piping main laying
Excavation for network line pipes
23
21 02-Nov-13 A 19-Nov-13 A
100%
100%
QR18,685.80
21 06-Nov-13 A 25-Nov-13 A
100%
100%
QR18,685.80
6 25-Nov-13 A 18-Jan-14 A
100%
100%
QR5,338.80
31-Dec-13 A
05-May-13 A
100%
100%
100%
100%
QR206,433.64
QR18,685.80
6 05-May-13 A 09-May-13 A
100%
100%
QR5,338.80
Pre-testing of irrigation
Kerb, plant edgers and interlock paving works
Earthworks excavation
Disposal of waste materials
83 16-Apr-13 A
21 16-Apr-13 A
Hardscaping works
Finishing Works
Subgrade formation
25 27-Apr-13 A
19-May-13 A
100%
100%
QR22,245.00
25 07-May-13 A 29-May-13 A
100%
100%
QR40,041.01
45 11-May-13 A 19-Jun-13 A
100%
100%
QR40,041.01
45 16-May-13 A 24-Jun-13 A
100%
100%
QR40,041.01
Paving works
45 20-May-13 A 31-Dec-13 A
100%
100%
QR40,041.01
58 29-May-13 A 31-Dec-13 A
30 29-May-13 A 24-Jun-13 A
100%
100%
100%
100%
QR85,420.80
QR26,694.00
30 06-Jun-13 A
03-Jul-13 A
100%
100%
QR26,694.00
30 17-Jun-13 A
14-Jul-13 A
100%
100%
QR26,694.00
6 14-Jul-13 A
31-Dec-13 A
100%
100%
QR5,338.80
209 31-Dec-13 A
80%
100%
QR66,735.00
Remaining
30-Jun-14
22
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Subgrade formation
Concrete foundation for kerbstones
Paving works
Excavation for area lightings
Install cables below the ground
Backfilling and compaction
Pre-testing of area lighting
Page 12 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
100%
100%
QR13,347.00
100%
100%
QR26,694.00
50%
100%
QR26,694.00
2013
N
2014
J Jul A
A M
J Jul A
S Oct N
15 31-Dec-13 A
13-Jan-14 A
30 13-Jan-14 A
17-Apr-14 A
30 05-Jun-14 A
30-Jun-14
77 05-Jan-14 A
15 13-Jan-14 A
10-Apr-14 A
26-Jan-14 A
100%
100%
100%
100%
QR29,363.40
QR13,347.00
Fix signage
18 05-Jan-14 A
10-Apr-14 A
100%
100%
QR16,016.40
Fix signage
27 11-Nov-13 A 13-Feb-14 A
21 11-Nov-13 A 30-Nov-13 A
100%
100%
100%
100%
QR24,024.60
QR18,685.80
6 30-Nov-13 A 13-Feb-14 A
100%
100%
QR5,338.80
100%
100%
100%
100%
QR112,114.80
QR26,694.00
30 10-Nov-13 A 07-Dec-13 A
100%
100%
QR26,694.00
30 10-Nov-13 A 07-Dec-13 A
100%
100%
QR26,694.00
30 10-Nov-13 A 07-Dec-13 A
22
Fix valves
Install drip lines for shrubs & ground covers
100%
100%
QR26,694.00
24-Jan-14 A
100%
100%
QR5,338.80
Pre-testing of irrigation
Hardscaping works
40 04-Jul-13 A
30 04-Jul-13 A
17-Apr-14 A
06-Feb-14 A
100%
100%
100%
100%
QR53,388.00
QR26,694.00
Hardscaping works
Finishing Works
30 14-Jul-13 A
17-Apr-14 A
100%
100%
QR26,694.00
100%
100%
100%
100%
100%
100%
QR582,819.00
QR224,229.60
QR181,519.20
21 16-Nov-13 A 03-Dec-13 A
100%
100%
QR18,685.80
21 19-Nov-13 A 31-Dec-13 A
100%
100%
QR18,685.80
24-Jan-14 A
100%
100%
QR5,338.80
Pre-testing of irrigation
74 05-May-13 A 06-Mar-14 A
21 05-May-13 A 23-May-13 A
100%
100%
100%
100%
QR179,739.60
QR45,379.80
6 23-May-13 A 28-May-13 A
100%
100%
QR5,338.80
Subgrade formation
25 15-May-13 A 06-Jun-13 A
100%
100%
QR22,245.00
30 26-May-13 A 20-Jun-13 A
100%
100%
QR26,694.00
30 03-Jun-13 A
30-Jun-13 A
100%
100%
QR26,694.00
30 09-Jun-13 A
31-Dec-13 A
100%
100%
QR26,694.00
30 12-Jun-13 A
06-Mar-14 A
100%
100%
QR26,694.00
03-Apr-14 A
25-Jul-13 A
100%
100%
100%
100%
QR21,355.20
QR10,677.60
03-Apr-14 A
100%
100%
QR10,677.60
27 11-Nov-13 A 18-Jan-14 A
21 11-Nov-13 A 30-Nov-13 A
100%
100%
100%
100%
QR24,024.60
QR18,685.80
6 30-Nov-13 A 18-Jan-14 A
100%
100%
QR5,338.80
100%
100%
100%
100%
QR80,082.00
QR18,685.80
21 16-Nov-13 A 03-Dec-13 A
100%
100%
QR18,685.80
21 16-Nov-13 A 03-Dec-13 A
100%
100%
QR18,685.80
21 16-Nov-13 A 18-Jan-14 A
100%
100%
QR18,685.80
Pre-testing of irrigation
6 18-Jan-14 A
Zone 8
Irrigation piping main laying
Excavation for network line pipes
Pre-testing of irrigation
6 18-Jan-14 A
Paving works
Signage structures erection
Fix signage structure concrete foundations
Fix signage
12 12-Jan-14 A
Pre-testing of irrigation
Hardscape and finishing works
Hardscaping works
Finishing Works
Phase 1 - Testing and Commissioning
Testing and Commissioning for electrical works
207 15-Jul-13 A
12 15-Jul-13 A
Remaining
Milestone
Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for kerbstones
Fix kerbs and supports
Aggregate subbase and fill compaction
Paving works
Fix signage structure concrete foundations
Fix signage
Fix foundations for zone valves
Fix valves
6 18-Jan-14 A
24-Jan-14 A
100%
100%
QR5,338.80
Pre-testing of irrigation
128 17-Aug-13 A
118 17-Aug-13 A
03-Apr-14 A
06-Feb-14 A
100%
100%
100%
100%
QR53,388.00
QR26,694.00
Hardscaping works
99 12-Sep-13 A
03-Apr-14 A
100%
100%
QR26,694.00
13 11-Dec-13 A
6 11-Dec-13 A
30-Jun-14
17-Apr-14 A
98.53%
100%
100%
100%
QR838,036.76
QR428,036.64
-8
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Finishing Works
Finishing Works
Testing and Commissioning f
Page 13 of 25
Activity Name
Original Start
Duration
Total
Float
Actual %
Complete
Planned %
Complete
30-Jun-14
-8
97%
100%
QR410,000.12
544 11-Mar-13 A
08-Jul-14
22
98.84%
100%
QR3,352,146.70
544
205
122
115
11-Mar-13 A
21-Jul-13 A
21-Jul-13 A
21-Jul-13 A
08-Jul-14
03-Apr-14 A
13-Nov-13 A
07-Nov-13 A
22
98.94%
100%
100%
100%
100%
100%
100%
100%
QR2,514,109.94
QR276,898.83
QR89,723.97
QR63,230.33
80 25-Aug-13 A
07-Nov-13 A
100%
100%
QR2,605.93
Subgrade formation
25 21-Oct-13 A
11-Nov-13 A
100%
100%
QR10,858.05
Subgrade formation
20 27-Oct-13 A
13-Nov-13 A
100%
100%
QR13,029.66
179 29-Jul-13 A
87 29-Jul-13 A
25-Jan-14 A
21-Oct-13 A
100%
100%
100%
100%
QR66,016.95
QR9,120.77
86 30-Jul-13 A
21-Oct-13 A
100%
100%
QR2,605.93
Subgrade formation
110 09-Sep-13 A
19-Dec-13 A
100%
100%
QR10,858.05
100 23-Sep-13 A
24-Dec-13 A
100%
100%
QR10,858.05
25 10-Dec-13 A
31-Dec-13 A
100%
100%
QR10,858.05
25 16-Dec-13 A
31-Dec-13 A
100%
100%
QR10,858.05
Paving works
25 21-Dec-13 A
25-Jan-14 A
100%
100%
QR10,858.05
144 07-Sep-13 A
87 07-Sep-13 A
31-Dec-13 A
26-Nov-13 A
100%
100%
100%
100%
QR67,736.27
QR46,888.80
115 17-Sep-13 A
31-Dec-13 A
100%
100%
QR9,120.77
117 21-Sep-13 A
31-Dec-13 A
100%
100%
QR9,120.77
23 26-Dec-13 A
31-Dec-13 A
100%
100%
QR2,605.93
Pre-testing of irrigation
03-Apr-14 A
31-Oct-13 A
100%
100%
100%
100%
QR14,332.63
QR6,514.83
19 09-Jan-14 A
03-Apr-14 A
100%
100%
QR7,817.80
23 12-Dec-13 A
21 12-Dec-13 A
31-Dec-13 A
31-Dec-13 A
100%
100%
100%
100%
QR39,089.01
QR9,120.77
21 12-Dec-13 A
31-Dec-13 A
100%
100%
QR9,120.77
21 12-Dec-13 A
31-Dec-13 A
100%
100%
QR9,120.77
21 12-Dec-13 A
31-Dec-13 A
100%
100%
QR9,120.77
6 29-Dec-13 A
31-Dec-13 A
100%
100%
QR2,605.93
Pre-testing of irrigation
Earthworks excavation
352 21-Aug-13 A
208 21-Aug-13 A
131 21-Aug-13 A
30-Jun-14
03-Apr-14 A
19-Dec-13 A
98.24%
100%
100%
100%
100%
100%
QR259,724.61
QR61,673.73
QR35,180.09
Phase 2 Works
Construction
Zone 5
Concrete foundations signage
Earthworks excavation
Pre-testing of irrigation
Signage structures erection
Fix signage structure concrete foundations
Fix signage
Irrigation lateral piping & distribution accessories
Pre-testing of irrigation
Zone 6
Concrete foundations for shades and signage
6 17-Dec-13 A
199 25-Jul-13 A
103 25-Jul-13 A
Finish
23
2013
N
J Jul A
2014
S
A M
J Jul A
S Oct N
Earthworks excavation
Disposal of waste materials
Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for kerbstones
Paving works
Excavation for network line pipes
Earthworks excavation
110 10-Sep-13 A
31-Dec-13 A
100%
100%
QR2,605.93
Subgrade formation
25 01-Feb-14 A
20-Mar-14 A
100%
100%
QR10,858.05
25 03-Feb-14 A
03-Apr-14 A
100%
100%
QR13,029.66
122 02-Feb-14 A
21 02-Feb-14 A
22-May-14 A
24-Apr-14 A
100%
100%
100%
100%
QR74,703.39
QR9,120.77
21 13-Feb-14 A
24-Apr-14 A
100%
100%
QR2,605.93
Subgrade formation
21 09-Apr-14 A
30-Apr-14 A
100%
100%
QR10,858.05
Subgrade formation
21 26-Apr-14 A
01-May-14 A
100%
100%
QR13,029.66
21 27-Apr-14 A
01-May-14 A
100%
100%
QR13,029.66
21 01-May-14 A 08-May-14 A
100%
100%
QR13,029.66
Paving works
21 01-May-14 A 22-May-14 A
100%
100%
QR13,029.66
Paving works
41 10-Dec-13 A
15 10-Dec-13 A
22-Jan-14 A
31-Dec-13 A
100%
100%
100%
100%
QR29,968.24
QR9,120.77
15 17-Dec-13 A
31-Dec-13 A
100%
100%
QR9,120.77
15 17-Dec-13 A
09-Jan-14 A
100%
100%
QR9,120.77
Remaining
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Page 14 of 25
Activity Name
Original Start
Duration
Pre-testing of irrigation
Finish
Total
Float
Actual %
Complete
Planned %
Complete
100%
100%
QR2,605.93
81.58%
100%
100%
100%
QR24,756.37
QR6,514.83
100%
100%
QR9,120.77
50%
100%
QR9,120.77
QR13,898.31
QR6,080.51
6 18-Jan-14 A
22-Jan-14 A
109 27-Mar-14 A
15 27-Mar-14 A
30-Jun-14
31-Mar-14 A
21 31-Mar-14 A
12-Jun-14 A
21 12-Jun-14 A
30-Jun-14
76 01-Feb-14 A
14 01-Feb-14 A
10-Apr-14 A
06-Feb-14 A
100%
100%
100%
100%
-8
-8
2013
N
J Jul A
2014
S
A M
J Jul A
S Oct N
Pre-testing of irrigation
9 31-Mar-14 A
10-Apr-14 A
100%
100%
QR7,817.80
35 01-Feb-14 A
20 01-Feb-14 A
10-Apr-14 A
10-Apr-14 A
100%
100%
100%
100%
QR54,724.57
QR13,029.66
20 13-Feb-14 A
10-Apr-14 A
100%
100%
QR13,029.66
20 13-Feb-14 A
10-Apr-14 A
100%
100%
QR13,029.66
20 13-Feb-14 A
10-Apr-14 A
100%
100%
QR13,029.66
Pre-testing of irrigation
2 15-Feb-14 A
10-Apr-14 A
331 09-Sep-13 A
184 09-Sep-13 A
110 09-Sep-13 A
30-Jun-14
31-Mar-14 A
17-Dec-13 A
88 29-Sep-13 A
Subgrade formation
Concrete foundation for shades and signage
Fix signage
100%
100%
QR2,605.93
98.25%
100%
100%
100%
100%
100%
QR260,158.93
QR61,673.73
QR35,180.09
17-Dec-13 A
100%
100%
QR2,605.93
25 01-Feb-14 A
06-Feb-14 A
100%
100%
QR10,858.05
Subgrade formation
30 17-Dec-13 A
31-Mar-14 A
100%
100%
QR13,029.66
142 01-Feb-14 A
21 01-Feb-14 A
22-May-14 A
31-Mar-14 A
100%
100%
100%
100%
QR74,703.39
QR9,120.77
Earthworks excavation
21 20-Feb-14 A
31-Mar-14 A
100%
100%
QR2,605.93
Subgrade formation
21 20-Mar-14 A
31-Mar-14 A
100%
100%
QR10,858.05
21 17-Apr-14 A
08-May-14 A
100%
100%
QR13,029.66
21 08-May-14 A 15-May-14 A
100%
100%
QR13,029.66
21 13-May-14 A 15-May-14 A
100%
100%
QR13,029.66
Paving works
21 16-May-14 A 22-May-14 A
100%
100%
QR13,029.66
Paving works
23 24-Dec-13 A
21 24-Dec-13 A
31-Dec-13 A
31-Dec-13 A
100%
100%
100%
100%
QR29,968.24
QR9,120.77
21 25-Dec-13 A
31-Dec-13 A
100%
100%
QR9,120.77
21 26-Dec-13 A
31-Dec-13 A
100%
100%
QR9,120.77
6 26-Dec-13 A
31-Dec-13 A
100%
100%
QR2,605.93
Pre-testing of irrigation
172 01-Feb-14 A
15 01-Feb-14 A
30-Jun-14
06-Feb-14 A
81.58%
100%
100%
100%
QR24,756.37
QR6,514.83
100%
100%
QR9,120.77
50%
100%
QR9,120.77
Zone 7
Concrete foundations for shades and signage
Earthworks excavation
Pre-testing of irrigation
Shade structures erection
Fix shade structure concrete foundations
23
23
Pre-testing of irrigation
Earthworks excavation
21 22-May-14 A 12-Jun-14 A
21 12-Jun-14 A
30-Jun-14
85 01-Feb-14 A
15 01-Feb-14 A
10-Apr-14 A
31-Mar-14 A
100%
100%
100%
100%
QR14,332.63
QR6,514.83
Fix signage
18 31-Mar-14 A
10-Apr-14 A
100%
100%
QR7,817.80
177 21-Dec-13 A
20 21-Dec-13 A
12-Jun-14 A
31-Dec-13 A
100%
100%
100%
100%
QR54,724.57
QR13,029.66
20 21-Dec-13 A
31-Dec-13 A
100%
100%
QR13,029.66
20 21-Dec-13 A
05-Jun-14 A
100%
100%
QR13,029.66
20 21-Dec-13 A
05-Jun-14 A
100%
100%
QR13,029.66
6 19-Apr-14 A
12-Jun-14 A
100%
100%
QR2,605.93
Pre-testing of irrigatio
256 10-Sep-13 A
116 29-Sep-13 A
106 29-Sep-13 A
10-Apr-14 A
13-Feb-14 A
31-Dec-13 A
100%
100%
100%
100%
100%
100%
QR260,167.93
QR61,673.73
QR35,180.09
Pre-testing of irrigation
Zone 9
Concrete foundations for signage
Earthworks excavation
Remaining
23
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Earthworks excavation
Page 15 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
2013
N
J Jul A
2014
S
A M
J Jul A
S Oct N
84 21-Oct-13 A
31-Dec-13 A
100%
100%
QR2,605.93
Subgrade formation
79 04-Nov-13 A 31-Dec-13 A
100%
100%
QR10,858.05
30 14-Dec-13 A
13-Feb-14 A
100%
100%
QR13,029.66
Earthworks excavation
150 10-Sep-13 A
110 10-Sep-13 A
10-Apr-14 A
19-Dec-13 A
100%
100%
100%
100%
QR74,703.39
QR9,120.77
100 19-Sep-13 A
19-Dec-13 A
100%
100%
QR2,605.93
Subgrade formation
25 03-Dec-13 A
26-Dec-13 A
100%
100%
QR10,858.05
Subgrade formation
30 14-Dec-13 A
31-Dec-13 A
100%
100%
QR13,029.66
30 24-Dec-13 A
27-Mar-14 A
100%
100%
QR13,029.66
30 29-Dec-13 A
02-Apr-14 A
100%
100%
QR13,029.66
Paving works
30 25-Dec-13 A
10-Apr-14 A
100%
100%
QR13,029.66
38 24-Dec-13 A
21 24-Dec-13 A
06-Jan-14 A
31-Dec-13 A
100%
100%
100%
100%
QR54,733.61
QR33,886.14
21 25-Dec-13 A
31-Dec-13 A
100%
100%
QR9,120.77
21 26-Dec-13 A
06-Jan-14 A
100%
100%
QR9,120.77
Pre-testing of irrigation
6 28-Dec-13 A
06-Jan-14 A
100%
100%
QR2,605.93
34 27-Mar-14 A
15 27-Mar-14 A
10-Apr-14 A
31-Mar-14 A
100%
100%
100%
100%
QR14,332.63
QR6,514.83
Fix signage
18 29-Mar-14 A
10-Apr-14 A
100%
100%
QR7,817.80
131 07-Dec-13 A
30 07-Dec-13 A
29-Jan-14 A
19-Jan-14 A
100%
100%
100%
100%
QR54,724.57
QR13,029.66
30 14-Dec-13 A
19-Jan-14 A
100%
100%
QR13,029.66
30 14-Dec-13 A
19-Jan-14 A
100%
100%
QR13,029.66
30 14-Dec-13 A
19-Jan-14 A
100%
100%
QR13,029.66
2 28-Jan-14 A
29-Jan-14 A
100%
100%
QR2,605.93
270 22-Oct-13 A
101 22-Oct-13 A
72 22-Oct-13 A
30-Jun-14
06-Mar-14 A
25-Dec-13 A
98.23%
100%
100%
100%
100%
100%
QR257,552.99
QR34,311.44
QR7,817.80
72 23-Oct-13 A
25-Dec-13 A
100%
100%
QR2,605.93
Subgrade formation
25 12-Dec-13 A
01-Feb-14 A
100%
100%
QR10,858.05
30 24-Dec-13 A
06-Mar-14 A
100%
100%
QR13,029.66
Earthworks excavation
69 01-Feb-14 A
21 01-Feb-14 A
05-Apr-14 A
18-Feb-14 A
100%
100%
100%
100%
QR73,400.42
QR7,817.80
Earthworks excavation
21 01-Feb-14 A
06-Feb-14 A
100%
100%
QR2,605.93
Subgrade formation
21 01-Feb-14 A
06-Feb-14 A
100%
100%
QR10,858.05
21 01-Mar-14 A
20-Mar-14 A
100%
100%
QR13,029.66
21 13-Mar-14 A
25-Mar-14 A
100%
100%
QR13,029.66
21 13-Feb-14 A
31-Mar-14 A
100%
100%
QR13,029.66
Paving works
21 13-Feb-14 A
05-Apr-14 A
100%
100%
QR13,029.66
Paving works
19 19-Dec-13 A
10 19-Dec-13 A
23-Jan-14 A
28-Dec-13 A
100%
100%
100%
100%
QR29,968.24
QR9,120.77
10 28-Dec-13 A
31-Dec-13 A
100%
100%
QR9,120.77
10 28-Dec-13 A
23-Jan-14 A
100%
100%
QR9,120.77
6 29-Dec-13 A
23-Jan-14 A
100%
100%
QR2,605.93
Pre-testing of irrigation
73 27-Mar-14 A
10 27-Mar-14 A
30-Jun-14
31-Mar-14 A
81.58%
100%
100%
100%
QR24,756.37
QR6,514.83
10 22-May-14 A 12-Jun-14 A
100%
100%
QR9,120.77
50%
100%
QR9,120.77
100%
100%
QR14,332.63
Pre-testing of irrigation
Zone 10
Concrete foundations for shades and signage
Earthworks excavation
Pre-testing of irrigation
Shade structures erection
5 12-Jun-14 A
10 29-Mar-14 A
Remaining
30-Jun-14
17-Apr-14 A
-8
-8
-8
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Pre-testing of irrigation
Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for shades an
Subgrade formation
Page 16 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
10 29-Mar-14 A
31-Mar-14 A
100%
100%
2013
N
J Jul A
2014
S
A M
J Jul A
S Oct N
10 29-Mar-14 A
17-Apr-14 A
100%
100%
QR7,817.80
151 14-Dec-13 A
30 14-Dec-13 A
31-Mar-14 A
31-Dec-13 A
100%
100%
100%
100%
QR26,059.32
QR13,029.66
30 27-Mar-14 A
31-Mar-14 A
100%
100%
QR13,029.66
135 19-Dec-13 A
20 19-Dec-13 A
17-Apr-14 A
31-Dec-13 A
100%
100%
100%
100%
QR54,724.57
QR13,029.66
20 19-Dec-13 A
31-Dec-13 A
100%
100%
QR13,029.66
20 19-Dec-13 A
31-Dec-13 A
100%
100%
QR13,029.66
20 19-Dec-13 A
17-Apr-14 A
100%
100%
QR13,029.66
6 12-Apr-14 A
16-Apr-14 A
100%
100%
QR2,605.93
340 10-Sep-13 A
112 29-Sep-13 A
83 29-Sep-13 A
08-Jul-14
06-Feb-14 A
14-Dec-13 A
97.72%
100%
100%
100%
100%
100%
QR285,349.63
QR35,614.41
QR9,120.77
82 30-Sep-13 A
14-Dec-13 A
100%
100%
QR2,605.93
Subgrade formation
25 03-Dec-13 A
25-Dec-13 A
100%
100%
QR10,858.05
30 14-Dec-13 A
06-Feb-14 A
100%
100%
QR13,029.66
Earthworks excavation
159 10-Sep-13 A
110 10-Sep-13 A
20-Feb-14 A
21-Dec-13 A
100%
100%
100%
100%
QR92,076.31
QR9,120.77
109 11-Sep-13 A
21-Dec-13 A
100%
100%
QR2,605.93
Subgrade formation
25 08-Dec-13 A
31-Dec-13 A
100%
100%
QR10,858.05
Subgrade formation
40 19-Dec-13 A
31-Dec-13 A
100%
100%
QR17,372.89
40 28-Dec-13 A
06-Feb-14 A
100%
100%
QR17,372.89
40 28-Dec-13 A
06-Feb-14 A
100%
100%
QR17,372.89
Paving works
40 26-Dec-13 A
20-Feb-14 A
100%
100%
QR17,372.89
37 14-Dec-13 A
21 14-Dec-13 A
06-Feb-14 A
31-Dec-13 A
100%
100%
100%
100%
QR29,968.24
QR9,120.77
21 24-Dec-13 A
31-Dec-13 A
100%
100%
QR9,120.77
21 29-Dec-13 A
31-Dec-13 A
100%
100%
QR9,120.77
6 26-Dec-13 A
06-Feb-14 A
100%
100%
QR2,605.93
112 02-Mar-14 A
15 02-Mar-14 A
08-Jul-14
27-Mar-14 A
80%
100%
100%
100%
QR32,574.15
QR6,514.83
100%
100%
QR13,029.66
50%
100%
QR13,029.66
Pre-testing of irrigation
Zone 11
Concrete foundations for shades and signage
Earthworks excavation
Pre-testing of irrigation
Shade structures erection
Fix shade structure concrete foundations
Fix shade structural elements
30 31-May-14 A 08-Jul-14 A
30 12-Jun-14 A
30-Jun-14
22
22
-9
Fix signage
Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for shades and si
Earthworks excavation
Disposal of waste materials
Paving works
Excavation for network line pipes
Pre-testing of irrigation
Fix shade structure concrete fou
Fix shade structur
Fix fabric shades
116 20-Mar-14 A
10 20-Mar-14 A
10-Apr-14 A
27-Mar-14 A
100%
100%
100%
100%
QR14,332.63
QR6,514.83
18 29-Mar-14 A
10-Apr-14 A
100%
100%
QR7,817.80
209 24-Oct-13 A
111 24-Oct-13 A
31-Mar-14 A
31-Dec-13 A
100%
100%
100%
100%
QR26,059.32
QR13,029.66
30 27-Mar-14 A
31-Mar-14 A
100%
100%
QR13,029.66
28 08-Dec-13 A
25 08-Dec-13 A
13-Feb-14 A
30-Dec-13 A
100%
100%
100%
100%
QR54,724.57
QR13,029.66
25 08-Dec-13 A
30-Dec-13 A
100%
100%
QR13,029.66
25 08-Dec-13 A
30-Dec-13 A
100%
100%
QR13,029.66
25 08-Dec-13 A
30-Dec-13 A
100%
100%
QR13,029.66
3 28-Dec-13 A
13-Feb-14 A
100%
100%
QR2,605.93
206 26-Oct-13 A
92 26-Oct-13 A
72 26-Oct-13 A
10-Apr-14 A
06-Feb-14 A
29-Dec-13 A
100%
100%
100%
100%
100%
100%
QR267,976.71
QR142,891.95
QR116,398.31
Pre-testing of irrigation
Zone 17
Concrete foundations for signage
Earthworks excavation
Remaining
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Pre-testing of irrigation
Earthworks excavation
Page 17 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
2013
N
J Jul A
2014
S
A M
J Jul A
S Oct N
72 26-Oct-13 A
29-Dec-13 A
100%
100%
QR2,605.93
Subgrade formation
75 30-Oct-13 A
31-Dec-13 A
100%
100%
QR10,858.05
30 19-Dec-13 A
06-Feb-14 A
100%
100%
QR13,029.66
58 26-Nov-13 A 01-Jan-14 A
21 26-Nov-13 A 14-Dec-13 A
100%
100%
100%
100%
QR56,027.56
QR35,180.09
21 04-Dec-13 A
24-Dec-13 A
100%
100%
QR9,120.77
21 26-Dec-13 A
31-Dec-13 A
100%
100%
QR9,120.77
6 28-Dec-13 A
01-Jan-14 A
100%
100%
QR2,605.93
Pre-testing of irrigation
33 27-Mar-14 A
33 27-Mar-14 A
10-Apr-14 A
31-Mar-14 A
100%
100%
100%
100%
QR14,332.63
QR6,514.83
Fix signage
18 29-Mar-14 A
10-Apr-14 A
100%
100%
QR7,817.80
67 17-Dec-13 A
30 17-Dec-13 A
06-Feb-14 A
31-Dec-13 A
100%
100%
100%
100%
QR54,724.57
QR13,029.66
30 17-Dec-13 A
31-Dec-13 A
100%
100%
QR13,029.66
30 17-Dec-13 A
31-Dec-13 A
100%
100%
QR13,029.66
30 31-Dec-13 A
26-Jan-14 A
100%
100%
QR13,029.66
6 01-Feb-14 A
06-Feb-14 A
100%
100%
QR2,605.93
201 21-Oct-13 A
96 21-Oct-13 A
66 21-Oct-13 A
10-Apr-14 A
26-Feb-14 A
17-Dec-13 A
100%
100%
100%
100%
100%
100%
QR260,167.93
QR35,614.41
QR9,120.77
46 07-Nov-13 A 17-Dec-13 A
100%
100%
QR2,605.93
Subgrade formation
25 07-Dec-13 A
29-Dec-13 A
100%
100%
QR10,858.05
30 17-Dec-13 A
26-Feb-14 A
100%
100%
QR13,029.66
Earthworks excavation
45 01-Feb-14 A
21 01-Feb-14 A
02-Mar-14 A
06-Feb-14 A
100%
100%
100%
100%
QR74,703.39
QR9,120.77
21 01-Feb-14 A
06-Feb-14 A
100%
100%
QR2,605.93
Subgrade formation
25 01-Feb-14 A
06-Feb-14 A
100%
100%
QR10,858.05
Subgrade formation
30 01-Feb-14 A
06-Feb-14 A
100%
100%
QR13,029.66
30 01-Feb-14 A
06-Feb-14 A
100%
100%
QR13,029.66
30 01-Feb-14 A
06-Feb-14 A
100%
100%
QR13,029.66
Paving works
30 13-Feb-14 A
02-Mar-14 A
100%
100%
QR13,029.66
63 19-Dec-13 A
21 19-Dec-13 A
12-Feb-14 A
19-Jan-14 A
100%
100%
100%
100%
QR80,792.93
QR59,945.46
21 19-Jan-14 A
24-Jan-14 A
100%
100%
QR9,120.77
21 23-Jan-14 A
06-Feb-14 A
100%
100%
QR9,120.77
Pre-testing of irrigation
Signage structures erection
Pre-testing of irrigation
Zone 18
Concrete foundations for signage
Earthworks excavation
Pre-testing of irrigation
Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for shades and
Earthworks excavation
Disposal of waste materials
Paving works
Excavation for network line pipes
Install HDPE network line pipes & zone v
Backfilling and compaction
6 08-Feb-14 A
12-Feb-14 A
100%
100%
QR2,605.93
18 27-Mar-14 A
15 27-Mar-14 A
10-Apr-14 A
31-Mar-14 A
100%
100%
100%
100%
QR14,332.63
QR6,514.83
Fix signage
18 31-Mar-14 A
10-Apr-14 A
100%
100%
QR7,817.80
58 21-Dec-13 A
30 21-Dec-13 A
09-Feb-14 A
06-Feb-14 A
100%
100%
100%
100%
QR54,724.57
QR13,029.66
30 21-Dec-13 A
06-Feb-14 A
100%
100%
QR13,029.66
30 21-Dec-13 A
06-Feb-14 A
100%
100%
QR13,029.66
30 21-Dec-13 A
06-Feb-14 A
100%
100%
QR13,029.66
2 08-Feb-14 A
09-Feb-14 A
100%
100%
QR2,605.93
528 11-Mar-13 A
89 11-Mar-13 A
21 11-Mar-13 A
30-Jun-14
27-May-13 A
28-Mar-13 A
98.31%
100%
100%
100%
100%
100%
QR386,112.38
QR100,762.75
QR9,120.77
6 28-Mar-13 A
03-Apr-13 A
100%
100%
QR2,605.93
Pre-testing of irrigation
Zone 19
Open car park paving - Kerb and interlock paving works
Earthworks excavation
Disposal of waste materials
Remaining
-8
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Pre-testing of irrigation
Fix signage structure concrete f
Fix signage
Pre-testing of irrigation
Earthworks excavation
Disposal of waste materials
Page 18 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
2013
N
2014
J Jul A
Subgrade formation
25 21-Mar-13 A
11-Apr-13 A
100%
100%
QR10,858.05
45 01-Apr-13 A
09-May-13 A
100%
100%
QR19,544.50
45 09-Apr-13 A
19-May-13 A
100%
100%
QR19,544.50
45 15-Apr-13 A
23-May-13 A
100%
100%
QR19,544.50
Paving works
45 18-Apr-13 A
27-May-13 A
100%
100%
QR19,544.50
Paving works
54 28-Mar-13 A
21 28-Mar-13 A
15-May-13 A
16-Apr-13 A
100%
100%
100%
100%
QR35,614.41
QR9,120.77
6 16-Apr-13 A
22-Apr-13 A
100%
100%
QR2,605.93
Subgrade formation
25 08-Apr-13 A
30-Apr-13 A
100%
100%
QR10,858.05
30 18-Apr-13 A
15-May-13 A
100%
100%
QR13,029.66
84 28-Mar-13 A
21 28-Mar-13 A
31-Dec-13 A
16-Apr-13 A
100%
100%
100%
100%
QR92,076.31
QR9,120.77
6 22-Apr-13 A
27-Apr-13 A
100%
100%
QR2,605.93
Subgrade formation
25 08-Apr-13 A
30-Apr-13 A
100%
100%
QR10,858.05
40 18-Apr-13 A
23-May-13 A
100%
100%
QR17,372.89
40 28-Apr-13 A
02-Jun-13 A
100%
100%
QR17,372.89
40 02-May-13 A 06-Jun-13 A
100%
100%
QR17,372.89
Paving works
40 06-May-13 A 31-Dec-13 A
100%
100%
QR17,372.89
43 30-Apr-13 A
21 30-Apr-13 A
06-Jun-13 A
19-May-13 A
100%
100%
100%
100%
QR29,968.24
QR9,120.77
21 09-May-13 A 27-May-13 A
100%
100%
QR9,120.77
21 14-May-13 A 02-Jun-13 A
100%
100%
QR9,120.77
100%
100%
QR2,605.93
Pre-testing of irrigation
80%
100%
100%
100%
QR32,574.15
QR6,514.83
100%
100%
QR13,029.66
50%
100%
QR13,029.66
Pre-testing of irrigation
A M
J Jul A
S Oct N
Subgrade formation
Concrete foundation for kerbstones
Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for shades and signage
Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for kerbstones
Paving works
Excavation for network line pipes
Install HDPE network line pipes & zone valves's installation
6 02-Jun-13 A
06-Jun-13 A
99 27-Mar-14 A
15 27-Mar-14 A
30-Jun-14
31-Mar-14 A
15 10-Apr-14 A
17-Apr-14 A
15 12-Jun-14 A
30-Jun-14
33 15-Jun-13 A
15 15-Jun-13 A
14-Jul-13 A
27-Jun-13 A
100%
100%
100%
100%
QR14,332.63
QR6,514.83
Fix signage
18 27-Jun-13 A
14-Jul-13 A
100%
100%
QR7,817.80
275 06-Jun-13 A
30 06-Jun-13 A
06-Feb-14 A
03-Jul-13 A
100%
100%
100%
100%
QR26,059.32
QR13,029.66
30 18-Jan-14 A
06-Feb-14 A
100%
100%
QR13,029.66
36 22-May-13 A 23-Dec-13 A
30 22-May-13 A 17-Dec-13 A
100%
100%
100%
100%
QR54,724.57
QR13,029.66
30 22-May-13 A 17-Dec-13 A
100%
100%
QR13,029.66
30 22-May-13 A 17-Dec-13 A
100%
100%
QR13,029.66
30 22-May-13 A 17-Dec-13 A
100%
100%
QR13,029.66
100%
100%
QR2,605.93
98.53%
100%
100%
100%
QR838,036.76
QR428,036.64
Pre-testing of irrigation
Phase 2 - Testing and Commissioning
Testing and Commissioning for electrical works
Testing and Commissioning for mechanical works
6 17-Jun-13 A
23-Dec-13 A
9 08-Dec-13 A
9 08-Dec-13 A
30-Jun-14
17-Apr-14 A
-8
-8
-9
9 08-Dec-13 A
30-Jun-14
-8
97%
100%
QR410,000.12
361 17-Aug-13 A
30-Jun-14
23
99.16%
100%
QR3,561,655.92
361
330
88
72
17-Aug-13 A
10-Sep-13 A
26-Oct-13 A
26-Oct-13 A
30-Jun-14
30-Jun-14
06-Feb-14 A
29-Dec-13 A
23
23
99.35%
98.63%
100%
100%
100%
100%
100%
100%
QR2,723,619.16
QR529,814.28
QR94,881.77
QR56,097.98
69 28-Oct-13 A
01-Feb-14 A
100%
100%
QR4,155.41
Subgrade formation
72 30-Oct-13 A
03-Feb-14 A
100%
100%
QR17,314.19
Phase 3 Works
Construction
Zone 12
Concrete foundations for shades and signage
Earthworks excavation
Remaining
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Pre-testing of irrigation
Earthworks excavation
Disposal of waste materials
Subgrade formation
Page 19 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
2013
N
J Jul A
2014
S
A M
J Jul A
S Oct N
25 21-Dec-13 A
06-Feb-14 A
100%
100%
QR17,314.19
216 10-Sep-13 A
112 10-Sep-13 A
17-Apr-14 A
22-Dec-13 A
100%
100%
100%
100%
QR119,121.64
QR14,543.92
90 30-Sep-13 A
22-Dec-13 A
100%
100%
QR4,155.41
Subgrade formation
80 22-Oct-13 A
31-Dec-13 A
100%
100%
QR17,314.19
Subgrade formation
30 16-Dec-13 A
31-Dec-13 A
100%
100%
QR20,777.03
30 13-Feb-14 A
27-Mar-14 A
100%
100%
QR20,777.03
30 20-Feb-14 A
10-Apr-14 A
100%
100%
QR20,777.03
Paving works
30 24-Feb-14 A
17-Apr-14 A
100%
100%
QR20,777.03
32 18-Dec-13 A
21 18-Dec-13 A
14-Jan-14 A
31-Dec-13 A
100%
100%
100%
100%
QR47,787.17
QR14,543.92
21 19-Dec-13 A
08-Jan-14 A
100%
100%
QR14,543.92
21 19-Dec-13 A
14-Jan-14 A
100%
100%
QR14,543.92
6 21-Dec-13 A
14-Jan-14 A
100%
100%
QR4,155.41
134 05-Mar-14 A
15 05-Mar-14 A
30-Jun-14
13-Mar-14 A
81.58%
100%
100%
100%
QR39,476.36
QR10,388.52
21 10-Apr-14 A
12-Jun-14 A
100%
100%
QR14,543.92
21 12-Jun-14 A
30-Jun-14
50%
100%
QR14,543.92
30 20-Mar-14 A
14 20-Mar-14 A
10-Apr-14 A
27-Mar-14 A
100%
100%
100%
100%
QR22,162.17
QR9,695.95
Fix signage
18 31-Mar-14 A
10-Apr-14 A
100%
100%
QR12,466.22
70 19-Dec-13 A
30 19-Dec-13 A
18-Feb-14 A
13-Feb-14 A
100%
100%
100%
100%
QR87,263.53
QR20,777.03
30 19-Dec-13 A
13-Feb-14 A
100%
100%
QR20,777.03
30 19-Dec-13 A
13-Feb-14 A
100%
100%
QR20,777.03
30 19-Dec-13 A
13-Feb-14 A
100%
100%
QR20,777.03
6 13-Feb-14 A
18-Feb-14 A
100%
100%
QR4,155.41
Earthworks excavation
159 10-Sep-13 A
159 10-Sep-13 A
31-Dec-13 A
31-Dec-13 A
100%
100%
100%
100%
QR119,121.64
QR14,543.92
150 18-Sep-13 A
31-Dec-13 A
100%
100%
QR4,155.41
Subgrade formation
25 22-Dec-13 A
31-Dec-13 A
100%
100%
QR17,314.19
Subgrade formation
30 22-Dec-13 A
31-Dec-13 A
100%
100%
QR20,777.03
30 25-Dec-13 A
31-Dec-13 A
100%
100%
QR20,777.03
30 26-Dec-13 A
31-Dec-13 A
100%
100%
QR20,777.03
Pre-testing of irrigation
Shade structures erection
Fix shade structure concrete foundations
Pre-testing of irrigation
Road Kerb and Furnishing Works
Furnishing works
23
23
Pre-testing of irrigation
Earthworks excavation
Disposal of waste materials
30 28-Dec-13 A
31-Dec-13 A
100%
100%
QR20,777.03
Earthworks excavation
236 10-Sep-13 A
147 12-Sep-13 A
123 12-Sep-13 A
03-Apr-14 A
31-Dec-13 A
31-Dec-13 A
100%
100%
100%
100%
100%
100%
QR458,479.80
QR119,814.21
QR81,030.42
104 29-Sep-13 A
31-Dec-13 A
100%
100%
QR4,155.41
Subgrade formation
117 28-Sep-13 A
31-Dec-13 A
100%
100%
QR17,314.19
Subgrade formation
116 09-Oct-13 A
31-Dec-13 A
100%
100%
QR17,314.19
146 10-Sep-13 A
112 10-Sep-13 A
04-Jan-14 A
22-Dec-13 A
100%
100%
100%
100%
QR103,192.58
QR12,466.22
90 30-Sep-13 A
22-Dec-13 A
100%
100%
QR4,155.41
Subgrade formation
80 22-Oct-13 A
31-Dec-13 A
100%
100%
QR17,314.19
Subgrade formation
30 16-Dec-13 A
31-Dec-13 A
100%
100%
QR17,314.19
30 25-Dec-13 A
31-Dec-13 A
100%
100%
QR17,314.19
30 25-Dec-13 A
31-Dec-13 A
100%
100%
QR17,314.19
Paving works
30 25-Dec-13 A
04-Jan-14 A
100%
100%
QR17,314.19
Paving works
Zone 13
Concrete foundations for signage
Remaining
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Earthworks excavation
Disposal of waste materials
Earthworks excavation
Disposal of waste materials
Page 20 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
2013
N
J Jul A
2014
S
A M
J Jul A
S Oct N
136 12-Sep-13 A
120 12-Sep-13 A
31-Dec-13 A
31-Dec-13 A
100%
100%
100%
100%
QR47,787.17
QR14,543.92
116 24-Sep-13 A
31-Dec-13 A
100%
100%
QR14,543.92
21 26-Dec-13 A
31-Dec-13 A
100%
100%
QR14,543.92
6 25-Dec-13 A
31-Dec-13 A
100%
100%
QR4,155.41
39 06-Mar-14 A
10 06-Mar-14 A
03-Apr-14 A
13-Mar-14 A
100%
100%
100%
100%
QR22,162.17
QR9,695.95
Fix signage
10 27-Mar-14 A
03-Apr-14 A
100%
100%
QR12,466.22
21 17-Dec-13 A
21 17-Dec-13 A
04-Jan-14 A
31-Dec-13 A
100%
100%
100%
100%
QR62,331.09
QR14,543.92
21 17-Dec-13 A
31-Dec-13 A
100%
100%
QR14,543.92
21 17-Dec-13 A
31-Dec-13 A
100%
100%
QR14,543.92
21 17-Dec-13 A
31-Dec-13 A
100%
100%
QR14,543.92
Pre-testing of irrigation
Pre-testing of irrigation
Fix signage structure concrete fou
Fix signage
6 23-Dec-13 A
04-Jan-14 A
100%
100%
QR4,155.41
Pre-testing of irrigation
Earthworks excavation
204 14-Sep-13 A
157 14-Sep-13 A
31-Dec-13 A
31-Dec-13 A
100%
100%
100%
100%
QR103,192.58
QR12,466.22
Earthworks excavation
155 16-Sep-13 A
31-Dec-13 A
100%
100%
QR4,155.41
Subgrade formation
156 25-Sep-13 A
31-Dec-13 A
100%
100%
QR17,314.19
Subgrade formation
156 06-Oct-13 A
31-Dec-13 A
100%
100%
QR17,314.19
156 14-Oct-13 A
31-Dec-13 A
100%
100%
QR17,314.19
156 23-Oct-13 A
31-Dec-13 A
100%
100%
QR17,314.19
Furnishing works
156 29-Oct-13 A
31-Dec-13 A
100%
100%
QR17,314.19
Furnishing works
Earthworks excavation
254 24-Aug-13 A
148 24-Aug-13 A
115 24-Aug-13 A
03-Apr-14 A
31-Dec-13 A
07-Dec-13 A
100%
100%
100%
100%
100%
100%
QR615,000.09
QR153,750.02
QR49,172.30
Earthworks excavation
111 27-Aug-13 A
07-Dec-13 A
100%
100%
QR4,155.41
Subgrade formation
121 28-Aug-13 A
17-Dec-13 A
100%
100%
QR17,314.19
125 29-Aug-13 A
23-Dec-13 A
100%
100%
QR20,777.03
124 31-Aug-13 A
23-Dec-13 A
100%
100%
QR20,777.03
125 08-Sep-13 A
31-Dec-13 A
100%
100%
QR20,777.03
Paving works
125 14-Sep-13 A
31-Dec-13 A
100%
100%
QR20,777.03
Paving works
130 01-Sep-13 A
64 01-Sep-13 A
30-Dec-13 A
31-Oct-13 A
100%
100%
100%
100%
QR92,804.07
QR54,020.28
63 02-Sep-13 A
31-Oct-13 A
100%
100%
QR4,155.41
Subgrade formation
63 02-Sep-13 A
31-Oct-13 A
100%
100%
QR17,314.19
107 23-Sep-13 A
30-Dec-13 A
100%
100%
QR17,314.19
164 24-Aug-13 A
140 24-Aug-13 A
31-Dec-13 A
30-Dec-13 A
100%
100%
100%
100%
QR119,121.64
QR14,543.92
90 07-Oct-13 A
30-Dec-13 A
100%
100%
QR4,155.41
Subgrade formation
80 30-Oct-13 A
31-Dec-13 A
100%
100%
QR17,314.19
Subgrade formation
30 01-Dec-13 A
31-Dec-13 A
100%
100%
QR20,777.03
30 02-Dec-13 A
31-Dec-13 A
100%
100%
QR20,777.03
30 07-Dec-13 A
31-Dec-13 A
100%
100%
QR20,777.03
Paving works
30 11-Dec-13 A
31-Dec-13 A
100%
100%
QR20,777.03
Paving works
95 17-Nov-13 A 31-Dec-13 A
77 17-Nov-13 A 31-Dec-13 A
100%
100%
100%
100%
QR47,787.17
QR14,543.92
71 01-Dec-13 A
31-Dec-13 A
100%
100%
QR14,543.92
73 05-Dec-13 A
31-Dec-13 A
100%
100%
QR14,543.92
6 19-Dec-13 A
31-Dec-13 A
100%
100%
QR4,155.41
Zone 14
Open car park paving - Kerb and interlock paving works
Pre-testing of irrigation
Remaining
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for shades and signag
Earthworks excavation
Disposal of waste materials
Pre-testing of irrigation
Page 21 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
2013
N
J Jul A
2014
S
A M
J Jul A
S Oct N
38 06-Mar-14 A
10 06-Mar-14 A
03-Apr-14 A
13-Mar-14 A
100%
100%
100%
100%
QR22,854.74
QR10,388.52
Fix signage
10 31-Mar-14 A
03-Apr-14 A
100%
100%
QR12,466.22
28 25-Dec-13 A
25 25-Dec-13 A
18-Jan-14 A
31-Dec-13 A
100%
100%
100%
100%
QR73,412.17
QR17,314.19
25 25-Dec-13 A
31-Dec-13 A
100%
100%
QR17,314.19
25 25-Dec-13 A
31-Dec-13 A
100%
100%
QR17,314.19
25 25-Dec-13 A
13-Jan-14 A
100%
100%
QR17,314.19
6 13-Jan-14 A
18-Jan-14 A
100%
100%
QR4,155.41
Earthworks excavation
153 01-Sep-13 A
129 01-Sep-13 A
31-Dec-13 A
29-Dec-13 A
100%
100%
100%
100%
QR105,270.28
QR14,543.92
128 02-Sep-13 A
29-Dec-13 A
100%
100%
QR4,155.41
Subgrade formation
25 16-Dec-13 A
31-Dec-13 A
100%
100%
QR17,314.19
Subgrade formation
25 25-Dec-13 A
31-Dec-13 A
100%
100%
QR17,314.19
25 26-Dec-13 A
31-Dec-13 A
100%
100%
QR17,314.19
25 25-Dec-13 A
31-Dec-13 A
100%
100%
QR17,314.19
Furnishing works
25 26-Dec-13 A
31-Dec-13 A
100%
100%
QR17,314.19
Furnishing works
361 17-Aug-13 A
215 17-Aug-13 A
132 17-Aug-13 A
30-Jun-14
06-Mar-14 A
14-Dec-13 A
98.28%
100%
100%
100%
100%
100%
QR605,054.60
QR156,963.30
QR114,716.67
Earthworks excavation
10 01-Feb-14 A
06-Feb-14 A
100%
100%
QR4,155.41
Subgrade formation
25 01-Feb-14 A
27-Feb-14 A
100%
100%
QR17,314.19
Subgrade formation
30 01-Feb-14 A
06-Mar-14 A
100%
100%
QR20,777.03
Earthworks excavation
15 06-Mar-14 A
10 06-Mar-14 A
14-Apr-14 A
13-Mar-14 A
100%
100%
100%
100%
QR119,121.64
QR14,543.92
10 06-Mar-14 A
13-Mar-14 A
100%
100%
QR4,155.41
Subgrade formation
10 10-Mar-14 A
17-Mar-14 A
100%
100%
QR17,314.19
Subgrade formation
10 10-Mar-14 A
20-Mar-14 A
100%
100%
QR20,777.03
10 09-Mar-14 A
24-Mar-14 A
100%
100%
QR20,777.03
10 06-Mar-14 A
10-Apr-14 A
100%
100%
QR20,777.03
Pre-testing of irrigation
Road Kerb and Furnishing Works
Zone 15
Concrete foundations for shades and signage
Earthworks excavation
Paving works
23
10 06-Mar-14 A
14-Apr-14 A
100%
100%
QR20,777.03
138 31-Aug-13 A
121 31-Aug-13 A
12-Jan-14 A
19-Dec-13 A
100%
100%
100%
100%
QR47,787.17
QR14,543.92
116 09-Sep-13 A
24-Dec-13 A
100%
100%
QR14,543.92
85 12-Oct-13 A
31-Dec-13 A
100%
100%
QR14,543.92
100%
100%
QR4,155.41
Pre-testing of irrigation
80%
100%
100%
100%
QR51,942.58
QR10,388.52
100%
100%
QR20,777.03
50%
100%
QR20,777.03
6 25-Dec-13 A
12-Jan-14 A
137 06-Mar-14 A
15 06-Mar-14 A
30-Jun-14
13-Mar-14 A
10 10-Apr-14 A
25-Jun-14 A
10 25-Jun-14 A
30-Jun-14
46 06-Mar-14 A
15 06-Mar-14 A
17-Apr-14 A
13-Mar-14 A
100%
100%
100%
100%
QR22,854.74
QR10,388.52
23
23
18 31-Mar-14 A
17-Apr-14 A
100%
100%
QR12,466.22
139 22-Dec-13 A
30 22-Dec-13 A
30-Apr-14 A
31-Dec-13 A
100%
100%
100%
100%
QR87,263.53
QR20,777.03
30 22-Dec-13 A
30-Apr-14 A
100%
100%
QR20,777.03
30 22-Dec-13 A
30-Apr-14 A
100%
100%
QR20,777.03
30 22-Dec-13 A
30-Apr-14 A
100%
100%
QR20,777.03
6 17-Apr-14 A
30-Apr-14 A
100%
100%
QR4,155.41
Pre-testing of irrigation
Remaining
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Fix signage
Install drip lines for shrubs & ground covers
Pre-testing of irrigation
Page 22 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
2013
N
J Jul A
2014
S
A M
J Jul A
S Oct N
Earthworks excavation
183 10-Sep-13 A
164 10-Sep-13 A
24-Apr-14 A
31-Dec-13 A
100%
100%
100%
100%
163 11-Sep-13 A
31-Dec-13 A
100%
100%
QR4,155.41
Subgrade formation
163 15-Sep-13 A
31-Dec-13 A
100%
100%
QR17,314.19
Subgrade formation
163 17-Sep-13 A
31-Dec-13 A
100%
100%
QR20,777.03
163 22-Sep-13 A
31-Dec-13 A
100%
100%
QR20,777.03
163 24-Sep-13 A
31-Dec-13 A
100%
100%
QR20,777.03
Furnishing works
163 28-Sep-13 A
24-Apr-14 A
100%
100%
QR20,777.03
Earthworks excavation
246 31-Aug-13 A
212 31-Aug-13 A
197 31-Aug-13 A
10-Apr-14 A
31-Dec-13 A
31-Dec-13 A
100%
100%
100%
100%
100%
100%
QR515,270.39
QR128,817.59
QR86,570.96
196 01-Sep-13 A
31-Dec-13 A
100%
100%
QR4,155.41
Subgrade formation
197 09-Sep-13 A
31-Dec-13 A
100%
100%
QR17,314.19
Subgrade formation
196 15-Sep-13 A
31-Dec-13 A
100%
100%
QR20,777.03
Earthworks excavation
204 17-Sep-13 A
180 17-Sep-13 A
31-Dec-13 A
31-Dec-13 A
100%
100%
100%
100%
QR119,121.64
QR14,543.92
180 17-Sep-13 A
31-Dec-13 A
100%
100%
QR4,155.41
Subgrade formation
180 25-Sep-13 A
31-Dec-13 A
100%
100%
QR17,314.19
Subgrade formation
180 26-Sep-13 A
31-Dec-13 A
100%
100%
QR20,777.03
180 28-Sep-13 A
31-Dec-13 A
100%
100%
QR20,777.03
180 05-Oct-13 A
31-Dec-13 A
100%
100%
QR20,777.03
Paving works
180 08-Oct-13 A
31-Dec-13 A
100%
100%
QR20,777.03
Paving works
184 16-Sep-13 A
172 16-Sep-13 A
31-Dec-13 A
31-Dec-13 A
100%
100%
100%
100%
QR43,631.77
QR10,388.52
162 30-Sep-13 A
31-Dec-13 A
100%
100%
QR14,543.92
162 06-Oct-13 A
31-Dec-13 A
100%
100%
QR14,543.92
6 07-Dec-13 A
31-Dec-13 A
100%
100%
QR4,155.41
38 06-Mar-14 A
10 06-Mar-14 A
10-Apr-14 A
13-Mar-14 A
100%
100%
100%
100%
QR22,854.74
QR10,388.52
Fix signage
10 31-Mar-14 A
10-Apr-14 A
100%
100%
QR12,466.22
20 22-Dec-13 A
20 22-Dec-13 A
31-Dec-13 A
31-Dec-13 A
100%
100%
100%
100%
QR81,723.01
QR19,391.90
20 22-Dec-13 A
31-Dec-13 A
100%
100%
QR19,391.90
20 22-Dec-13 A
31-Dec-13 A
100%
100%
QR19,391.90
20 22-Dec-13 A
31-Dec-13 A
100%
100%
QR19,391.90
Zone 16
Concrete foundations for signage
Pre-testing of irrigation
Signage structures erection
Pre-testing of irrigation
Earthworks excavation
Disposal of waste materials
Furnishing works
Earthworks excavation
Disposal of waste materials
Earthworks excavation
Disposal of waste materials
Pre-testing of irrigation
Fix signage structure concrete fou
Fix signage
6 25-Dec-13 A
31-Dec-13 A
100%
100%
QR4,155.41
Pre-testing of irrigation
Earthworks excavation
184 14-Sep-13 A
140 14-Sep-13 A
31-Dec-13 A
31-Dec-13 A
100%
100%
100%
100%
QR119,121.64
QR14,543.92
Earthworks excavation
136 17-Sep-13 A
31-Dec-13 A
100%
100%
QR4,155.41
Subgrade formation
136 18-Sep-13 A
31-Dec-13 A
100%
100%
QR17,314.19
Subgrade formation
136 22-Sep-13 A
31-Dec-13 A
100%
100%
QR20,777.03
136 28-Sep-13 A
31-Dec-13 A
100%
100%
QR20,777.03
136 29-Sep-13 A
31-Dec-13 A
100%
100%
QR20,777.03
Furnishing works
167 29-Sep-13 A
31-Dec-13 A
100%
100%
QR20,777.03
Furnishing works
13 05-Dec-13 A
9 05-Dec-13 A
30-Jun-14
10-Apr-14 A
-8
98.53%
100%
100%
100%
QR838,036.76
QR428,036.64
30-Jun-14
-8
Phase 4 Works
Palm trees and shade trees
Remaining
97%
100%
QR410,000.12
263 25-Sep-13 A
8 10-Dec-13 A
21-Jun-14 A
100%
100%
QR1,466,564.28
217 25-Sep-13 A
21-Jun-14 A
100%
100%
QR459,559.80
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Page 23 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
2013
N
J Jul A
2014
S
A M
J Jul A
S Oct N
110 25-Sep-13 A
06-Mar-14 A
100%
100%
QR25,271.62
18 20-Mar-14 A
05-Jun-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
06-Mar-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
06-Mar-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
06-Mar-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
14-Jun-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
14-Jun-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
06-Mar-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
22-May-14 A
100%
100%
QR25,271.46
18 04-Mar-14 A
10-Apr-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
06-Mar-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
21-Jun-14 A
100%
100%
QR21,151.84
110 30-Sep-13 A
13-Mar-14 A
100%
100%
QR21,151.84
110 30-Sep-13 A
06-Mar-14 A
100%
100%
QR21,151.84
110 30-Sep-13 A
21-Jun-14 A
100%
100%
QR21,151.84
110 30-Sep-13 A
13-Mar-14 A
100%
100%
QR21,151.84
110 30-Sep-13 A
06-Mar-14 A
100%
100%
QR25,271.46
18 23-Mar-14 A
12-Jun-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
06-Mar-14 A
100%
100%
QR25,271.46
258 30-Sep-13 A
110 30-Sep-13 A
21-Jun-14 A
31-Dec-13 A
100%
100%
100%
100%
QR459,559.64
QR25,271.46
18 01-May-14 A 05-Jun-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
31-Dec-13 A
100%
100%
QR25,271.46
110 30-Sep-13 A
31-Dec-13 A
100%
100%
QR25,271.46
110 30-Sep-13 A
20-Feb-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
21-Jun-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
21-Jun-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
20-Feb-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
17-Apr-14 A
100%
100%
QR25,271.46
18 09-Mar-14 A
24-Apr-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
20-Feb-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
30-Apr-14 A
100%
100%
QR21,151.84
110 30-Sep-13 A
13-Mar-14 A
100%
100%
QR21,151.84
110 30-Sep-13 A
20-Feb-14 A
100%
100%
QR21,151.84
110 30-Sep-13 A
30-Apr-14 A
100%
100%
QR21,151.84
110 30-Sep-13 A
31-Dec-13 A
100%
100%
QR21,151.84
110 30-Sep-13 A
20-Feb-14 A
100%
100%
QR25,271.46
18 09-Mar-14 A
29-May-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
20-Feb-14 A
100%
100%
QR25,271.46
242 30-Sep-13 A
110 30-Sep-13 A
14-Jun-14 A
20-Feb-14 A
100%
100%
100%
100%
QR459,559.64
QR25,271.46
18 30-Sep-13 A
14-Jun-14 A
100%
100%
QR25,271.46
110 30-Sep-13 A
20-Feb-14 A
100%
100%
QR25,271.46
110 09-Jan-14 A
20-Feb-14 A
100%
100%
QR25,271.46
110 09-Jan-14 A
23-Feb-14 A
100%
100%
QR25,271.46
18 27-Mar-14 A
12-Jun-14 A
100%
100%
QR25,271.46
18 17-Apr-14 A
12-Jun-14 A
100%
100%
QR25,271.46
18 15-Jan-14 A
20-Feb-14 A
100%
100%
QR25,271.46
Remaining
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Page 24 of 25
Activity Name
Original Start
Duration
Finish
Total
Float
Actual %
Complete
Planned %
Complete
2013
N
J Jul A
2014
S
A M
J Jul A
S Oct N
18 16-Mar-14 A
10-Apr-14 A
100%
100%
QR25,271.46
18 16-Mar-14 A
24-Apr-14 A
100%
100%
QR25,271.46
18 13-Feb-14 A
20-Feb-14 A
100%
100%
QR25,271.46
18 27-Mar-14 A
24-Apr-14 A
100%
100%
QR21,151.84
18 13-Feb-14 A
23-Mar-14 A
100%
100%
QR21,151.84
18 13-Feb-14 A
16-Mar-14 A
100%
100%
QR21,151.84
18 16-Mar-14 A
24-Apr-14 A
100%
100%
QR21,151.84
18 13-Feb-14 A
24-Apr-14 A
100%
100%
QR21,151.84
18 13-Feb-14 A
20-Feb-14 A
100%
100%
QR25,271.46
18 16-Mar-14 A
29-May-14 A
100%
100%
QR25,271.46
18 13-Feb-14 A
20-Feb-14 A
100%
100%
QR25,271.46
71 02-Mar-14 A
21 02-Mar-14 A
21-Jun-14 A
31-May-14 A
100%
100%
100%
100%
QR87,885.20
QR28,837.33
21 02-Mar-14 A
21-Jun-14 A
100%
100%
QR28,837.33
23 08-Apr-14 A
21-Jun-14 A
83 10-Apr-14 A
30-Jun-14
6 10-Apr-14 A
100%
100%
QR30,210.54
21
60.41%
100%
QR1,047,545.95
30-Jun-14
-9
88%
100%
QR125,045.68
14 01-May-14 A 30-Jun-14
21
65%
100%
QR239,166.74
10 19-Apr-14 A
30-Jun-14
21
65%
100%
QR170,833.38
Pre-commissioning
6 18-May-14 A 30-Jun-14
21
50%
100%
QR102,500.03
14 17-May-14 A 30-Jun-14
21
50%
100%
QR239,166.74
Final testing & commissioning for irrigation, utilities and electrical system
10 14-Jun-14 A
30-Jun-14
21
50%
100%
QR170,833.38
109 19-Apr-14 A
26-Jul-14
-7
45.67%
73.37%
QR1,257,055.13
83 19-Apr-14 A
30-Jun-14
-8
42.59%
100%
QR367,460.78
45 19-Apr-14 A
30-Jun-14
-9
50%
100%
QR231,298.38
10 26-Jun-14 A
30-Jun-14
-6
30%
100%
QR136,162.40
34 07-Jun-14 A
06-Jul-14
-9
38%
100%
QR226,937.33
30 07-Jun-14 A
30-Jun-14
-9
50%
100%
QR136,162.40
11 26-Jun-14 A
06-Jul-14
-5
20%
100%
QR90,774.93
Company Review
25 07-Jun-14 A
10-Jul-14
-8
50%
59.2%
QR118,007.41
25 07-Jun-14 A
10-Jul-14
-8
50%
59.2%
QR118,007.41
25 07-Jun-14 A
15-Jul-14
-8
50%
35.2%
QR113,468.67
25 07-Jun-14 A
15-Jul-14
-8
50%
35.2%
QR113,468.67
25 07-Jun-14 A
21-Jul-14
-8
50%
7.2%
QR113,468.67
25 07-Jun-14 A
21-Jul-14
-8
50%
7.2%
QR113,468.67
69 07-Jun-14 A
26-Jul-14
-8
50%
66.09%
QR317,712.27
69 07-Jun-14 A
26-Jul-14
-8
50%
66.09%
QR317,712.27
Redline Mark-ups
Project Dossier
Prepare & Submit project dossier
Material Take-off
Prepare & Submit material take-off & spare parts
O&M Manual
Prepare & submit O&M Manual
Remaining
RGCP472PEPQAR001-RVD
Actual
Critical Remaining Work
Milestone
Page 25 of 25