Вы находитесь на странице: 1из 63

Building External Areas Upgrade in Administration

Area at Ras-Laffan
CONTRACT: CT/RG27/L029/12

MONTHLY PROGRESS REPORT NO: 20


FOR THE MONTH OF JUNE 2014

CLIENT

CONSULTANT

CONTRACTOR

TABLE OF CONTENTS
1. PROJECT INFORMATION ............................................................................................................
1.1. SCOPE OF WORK .....................................................................................................................
1.2. PROJECT WEIGHTAGE ..........................................................................................................
3. POGRESS WEIGHTAGE .................................................................................................................
4. OVERALL PROGRESS SUMMARY .............................................................................................
5. QA/QC STATUS ................................................................................................................................
6. HEATH AND SAFETY .....................................................................................................................
8. SUMMARY OF MATERIAL SUBMITTAL .................................................................................
9. SUMMARY OF DESIGN DRAWING SUBMITTAL .................................................................
10. MATERIAL SUBMITTAL LOG .....................................................................................................
11. DESIGN DRAWING SUBMITTAL LOG ..................................................................................
12. PROGRESS UPDATED WBS SUMMARY ..............................................................................
13. ONE MONTH LOOK-AHEAD ....................................................................................................
14. PROGRESS UPDATED PROGRAMME ...................................................................................
15. PROGRESS PHOTOS ....................................................................................................................

1. PROJECT INFORMATION
Project Title: CT/RG27/L029/12
Location: Ras Laffan
Client: Ras gas Company Limited
Contractor: Qatar Building Engineering Company W.L.L., (QBEC)
Project Start Date: 21 Oct 2012
Contract Duration: 28 Months
Completion for Construction Works: 16 Months
Completion for Operation & Maintenance: 12 Months
Extension of time: 90 days secured
1.1. SCOPE OF WORK

Site survey and study of the existing site situation including trial pits needed to verify the
physical characteristics of the site elements.
Engineering analysis and design for and shade structures and signages, including
irrigation piping network and electrical system based on the FEED design.
Development of the detailed engineering drawings and procedures based on the FEED
documents. Supply, install/construct, test and commission the work related to the Civil,
Structural, Plumbing and Electrical works.
Provision of new landscaping, which includes plants, trees, shrubs, ground cover and
climbers.
Provision of new irrigation piping, distribution network and associated accessories such
as drips, sprinklers, bubblers and valves.
Relocation and modifications to the existing planting, utilities, plumbing / mechanical and
lighting works according to the new works.
Maintenance of existing landscaping and planting during project execution and until the
Provisional Acceptance.
Operation and maintenance of new landscaping and irrigation for a period of one (1) year
i.e. during Warranty period.
All the associated demolition and reinstatement works resulting from the above works.
All the other works as indicated in the relevant FEED drawings.

1.2. PROJECT WEIGHTAGE


Activity Name
Construction Mobilisation and Finalisation of key subcontractor
& key suppliers
Contractor Mobilisation

Overall Wt.
5.00
2.39

Submission of Early Documentation & Key Deliverables

0.91

Key Subcontractors and Suppliers


ENGINEERING
Site Survey and Trial pit Excavation

1.70
5.00
0.43

Submission and Approval of Design Calculations


Submission and Approval of Detailed Engineering Drawings
PROCUREMENT
Materials Submission and Approval
Interlock pavers, kerb stones and tree guards
Foundation bolts
Main piping material
Shade structures including fabric material
Signage structures
Fountain sculpture
Electrical Poles, DBs and Field Controls
Valves and pumps
Irrigation distribution accessories
Placing of Orders and First Delivery to Project Site
Interlock pavers, kerb stones and tree guards
Foundation bolts
Main piping material
Shade structures including fabric material
Signage structures
Fountain sculpture
Electrical Poles, DBs and Field Controls
Valves and pumps
Irrigation distribution accessories
CONSTRUCTION
Phase 1 Works
Phase 2 Works
Phase 3 Works
Phase 4 Works
TESTING AND COMMINSIONING
FINAL DOCUMENTATION
Total

0.92
3.65
17.00
5.91
0.66
0.66
0.66
0.66
0.66
0.66
0.66
0.66
0.66
11.09
0.34
0.61
1.49
1.13
1.15
1.77
1.40
2.17
1.02
62.00
22.00
16.00
17.00
7.00
5.00
6.00
100.00

Budgeted
Cost
1025000.31
489204.73
186363.66
349431.92
1024999.83
87172.24
189599.54
748228.05
3485000.97
1211165.46
134573.94
134573.94
134573.94
134573.94
134573.94
134573.94
134573.94
134573.94
134573.94
2273835.51
69607.21
125292.98
306271.72
232024.03
236664.51
361957.49
287709.80
445486.14
208821.63
12710002.80
4510001.07
3280000.62
3485000.74
1435000.37
1025000.30
1230000.35
20500004.53

2. POGRESS WEIGHTAGE

Summary of progress report as of 30 June 2014


SR

Activity Name

Overall Wt.

Planned Wt.
(Original BL)

Planned Wt. (Revised


BL)-RGCP-472-PEPQTR-001 REV. D)

Achieved Wt.

Variation

Construction Mobilisation and Finalisation of key subcontractor & key


suppliers

100.00%

5.00

5.00

5.00

5.00

0.00

1.1

Contractor Mobilisation

100.00%

2.39

2.39

2.39

2.39

0.00

1.2

Submission of Early Documentation & Key Deliverables

100.00%

0.91

0.91

0.91

0.91

0.00

1.3

Key Subcontractors and Suppliers

100.00%

1.70

1.70

1.70

1.70

0.00

ENGINEERING

100.00%

5.00

5.00

5.00

5.00

0.00

2.1

Site Survey and Trial pit Excavation

100.00%

0.43

0.43

0.43

0.43

0.00

2.2

Submission and Approval of Design Calculations

100.00%

0.92

0.92

0.92

0.92

0.00

2.3

Submission and Approval of Detailed Engineering Drawings

100.00%

3.65

3.65

3.65

3.65

0.00

100.00%

17.00

17.00

17.00

17.00

0.00

100.00%

5.91

5.91

5.91

5.91

0.00

3.1.1 Interlock pavers, kerb stones and tree guards

100.00%

0.66

0.66

0.66

0.66

0.00

3.1.2 Foundation bolts

100.00%

0.66

0.66

0.66

0.66

0.00

3.1.3 Main piping material

100.00%

0.66

0.66

0.66

0.66

0.00

3.1.4 Shade structures including fabric material

100.00%

0.66

0.66

0.66

0.66

0.00

3.1.5 Signage structures

100.00%

0.66

0.66

0.66

0.66

0.00

3.1.6 Fountain sculpture

100.00%

0.66

0.66

0.66

0.66

0.00

3.1.7 Electrical Poles, DBs and Field Controls

100.00%

0.66

0.66

0.66

0.66

0.00

3.1.8 Valves and pumps

100.00%

0.66

0.66

0.66

0.66

0.00

3.1.9 Irrigation distribution accessories

100.00%

0.66

0.66

0.66

0.66

0.00

100.00%

11.09

11.09

11.09

11.09

0.00

3.2.1 Interlock pavers, kerb stones and tree guards

100.00%

0.34

0.34

0.34

0.34

0.00

3.2.2 Foundation bolts

100.00%

0.61

0.61

0.61

0.61

0.00

3.2.3 Main piping material

100.00%

1.49

1.49

1.49

1.49

0.00

3.2.4 Shade structures including fabric material

100.00%

1.13

1.13

1.13

1.13

0.00

3.2.5 Signage structures

100.00%

1.15

1.15

1.15

1.15

0.00

3.2.6 Fountain sculpture

100.00%

1.77

1.77

1.77

1.77

0.00

3.2.7 Electrical Poles, DBs and Field Controls

100.00%

1.40

1.40

1.40

1.40

0.00

3.2.8 Valves and pumps

100.00%

2.17

2.17

2.17

2.17

0.00

3.2.9 Irrigation distribution accessories

PROCUREMENT

3.1 Materials Submission and Approval

3.2 Placing of Orders and First Delivery to Project Site

Physical %

100.00%

1.02

1.02

1.02

1.02

0.00

CONSTRUCTION

99.01%

62.00

62.00

62.00

61.39

-0.61

4.1

Phase 1: Construction work

98.76%

18.00

18.00

18.00

17.78

-0.22

Phase 1:Testing & commissioning

98.53%

4.00

4.00

4.00

3.94

-0.06

Phase 2: Construction work

98.94%

12.00

12.00

12.00

11.87

-0.13

Phase 2:Testing & commissioning

98.53%

4.00

4.00

4.00

3.94

-0.06

Phase 3: Construction work

99.35%

13.00

13.00

13.00

12.92

-0.08

Phase 3:Testing & commissioning

98.53%

4.00

4.00

4.00

3.94

-0.06

4.2

4.3

4.4

100.00%

7.00

7.00

7.00

7.00

0.00

TESTING AND COMMINSIONING (PROVISIONAL ACCEPTENACE


5
CERTIFICATE)

60.407%

5.00

5.00

5.00

3.02

-1.98

6 FINAL DOCUMENTATION

45.667%

6.00

6.00

4.40

Phase 4 Works

Total (Original BL)


Total (Revised BL-RGCP-472-PEP-QTR-001 REV. D)

100.00%
98.40%

2.74

-1.66

94.15%

-5.85%

94.15%

-4.25%

3. OVERALL PROGRESS SUMMARY


CLIENT

CONSULTANT

RsGas

CONTRACTOR

Assiociated Consulting Engineers

Qatar Building Engineering Company

(RG27-L029) EPC OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN PROGRESS REPORT
Progress Status as on 30 June 2014

PROJECT START DATE

21-Oct-12

PROJECT COMPLETION DATE

20-Jul-14

S - CURVE

618

94.15%

REMAINING DURATION

CUML. PLANNED %

INVOICED AMOUNT

VARIANCE

15,243,037.53

Activity Name

10%

20%

30%

40%

50%

Planned Progress : 98.40%

100.00%
99.92%

Procurement

Construction

100.00%
99.01%

Construction

100.00%

Testing/Com

10%

45.67%

PLANNED %

MATERIAL SUBMITTAL STATUS

100

YET TO SUBMIT0 0 19
UNDER REVIEW0 0
REVISED2
02 408
APPROVED
SUBMITTED
TOTAL NO

222

183

45

150

250

300

350

400

450

500

TOTAL NO

IFC

CODE A

CODE B

CODE D

CUM.

Design Calculation

18

18

18

YET TO
SUBMIT
0

General

26

14

12

26

12

Landscape & Civil

61

61

61

Signage & Road Marking

20

20

20

Irrigation

23

23

23

Plumbing

20

12

13

Instrumentation
Electrical

TOTAL NO

45

31

14

45

14

229

183

14

25

222

34

LTI FREE SAFE WORK DAYS ACHIEVED/ MAN HOURS


Fire Incident
0

Restricted Work Case


(RWC)

Medical Treatment Case


(MTC)

First Aid Case (FAC)

Motor Vehicle Accident


(MVA)
Property Damage &
Equipment Failure

Item Description

Observation Card

Security Incident

Item Description

Near Miss

B-Safe Checklist

PTW Failure / Violation eSafety

PTW Audit onshore

PTW Violation PTW Coordinator


Report

MAN HOURS

Total Man Power This Week

726

Cum. Total Man Power

74,244

Man Hours This Week

7,260

Cum. Total Man Hours

748,174
0

Total PTW
Item Description

29
All

1,784
Good

0
53
3,235
This Week

136
26

155
150

SUBMITTED
62

200

250

300

42

UNDER
REVIEW
0

APPROVED

REVISED

350

YET TO
SUBMIT
0

42

5.00

5.00

0.00

2.39

2.39

0.00

Submission of Early Documentation & Key Deliverables

100.00%

0.91

0.91

0.91

0.91

0.00

Key Subcontractors and Suppliers

100.00%

1.70

1.70

1.70

1.70

0.00

ENGINEERING

100.00%

5.00

5.00

5.00

5.00

0.00

Site Survey and Trial pit Excavation

100.00%

0.43

0.43

0.43

0.43

0.00

Submission and Approval of Design Calculations

100.00%

0.92

0.92

0.92

0.92

Submission and Approval of Detailed Engineering Drawings

100.00%

3.65

3.65

3.65

3.65

0.00

PROCUREMENT

100.00%

17.00

17.00

17.00

17.00

0.00

Materials Submission and Approval

100.00%

5.91

5.91

5.91

5.91

0.00

Interlock pavers, kerb stones and tree guards

100.00%

0.66

0.66

0.66

0.66

0.00

Foundation bolts

100.00%

0.66

0.66

0.66

0.66

0.00

Main piping material

100.00%

0.66

0.66

0.66

0.66

0.00

Shade structures including fabric material

100.00%

0.66

0.66

0.66

0.66

0.00

Signage structures

100.00%

0.66

0.66

0.66

0.66

0.00

Fountain sculpture

100.00%

0.66

0.66

0.66

0.66

0.00

Electrical Poles, DBs and Field Controls

100.00%

0.66

0.66

0.66

0.66

0.00

Valves and pumps

100.00%

0.66

0.66

0.66

0.66

0.00

Irrigation distribution accessories

100.00%

0.66

0.66

0.66

0.66

0.00

Placing of Orders and First Delivery to Project Site

100.00%

11.09

11.09

11.09

11.09

0.00

Interlock pavers, kerb stones and tree guards

100.00%

0.34

0.34

0.34

0.34

0.00

Foundation bolts

100.00%

0.61

0.61

0.61

0.61

0.00

Main piping material

100.00%

1.49

1.49

1.49

1.49

0.00

Shade structures including fabric material

100.00%

1.13

1.13

1.13

1.13

0.00

Signage structures

100.00%

1.15

1.15

1.15

1.15

0.00

Fountain sculpture

100.00%

1.77

1.77

1.77

1.77

0.00

Electrical Poles, DBs and Field Controls

100.00%

1.40

1.40

1.40

1.40

0.00

Valves and pumps

100.00%

2.17

2.17

2.17

2.17

0.00

Irrigation distribution accessories

100.00%

1.02

1.02

1.02

1.02

0.00

CONSTRUCTION

99.01%

62.00

62.00

62.00

61.39

-0.61

Phase 1: Construction work

98.76%

18.00

18.00

18.00

17.78

-0.22
-0.06

98.53%

4.00

4.00

4.00

3.94

Phase 2: Construction work

98.94%

12.00

12.00

12.00

11.87

-0.13

Phase 2:Testing & commissioning

98.53%

4.00

4.00

4.00

3.94

-0.06

Phase 3: Construction work

99.35%

13.00

13.00

13.00

12.92

-0.08
-0.06

Phase 4 Works

Electrical

25

25

21

19

136

110

19

98.53%

4.00

4.00

4.00

3.94

100.00%

7.00

7.00

7.00

7.00

0.00

TESTING AND COMMINSIONING (PROVISIONAL ACCEPTENACE


CERTIFICATE)

60.41%

5.00

5.00

5.00

3.02

-1.98

FINAL DOCUMENTATION

45.67%

6.00

6.00

4.40

Phase 3:Testing & commissioning

100.00%

Total (Original BL)

98.40%

Total (Revised BL-RGCP-472-PEP-QTR-001 REV. D)

2.74

-1.66

94.15%

-5.85%

94.15%

-4.25%

NOTE:

40.00%

0
3,235
YTD 2014

0
Year 2014

447

447

Safety Walkabouts

26

17

JSA / RA / Safety
Reviews

10

B-Safe Meetings

16
39

20.00%

0.00%

Name

Submission
Prepared By

0.00

Phase 1:Testing & commissioning

1,784
0

121

121

121
5.00
2.39

27

Year 2014

121
5.00
2.39

26

Variation

100.00%

29

155

Achieved Wt.

100.00%

100.00%

Concern

156

Planned Wt.
(Revised BL)-RGCP472-PEP-QTR-001
REV. D)

Contractor Mobilisation

29

60.00%

YTD 2014

110

Planned Wt.
(Original BL)

Construction Mobilisation and Finalisation of key subcontractor


& key suppliers

Irrigation & Plantation

80.00%

This Week

100

62

Shade Structure

21 7
29
25
29
25

50

ONE WEEK LOOKAHEAD

Safety Inspections

Safety
Representation in
Meetings

Civil / Architecture

Total

Activity Summary
0

Environment Incident

27
624
624

TOTAL NO

Fountain

HEALTH AND SAFETY

Lost Time Injury (LTI)

424

229

200

19

Overall Wt.

70.12%

50

ACTUAL %

100.00%

61 20 23 1
0 31
61 20 23 20 1

-39.59%

Final Document
-27.70%

100.00%

45

-0.99%

Physical
%

100.00%

20 23 131

61

-0.08%

73.37%

DESIGN DRAWING SUBMITTAL STATUS


YET TO SUBMIT012
0 07114 34
CUM. 18 26
CODE D012
0 0121
0 25
CODE B0 014 14
CODE A0 0
IFC 18 14
TOTAL NO 18 26

-0.42%

Testing/Com

60.41%

Final Document

Mar-14
Apr-14
May-14
Jun-14
Jul-14

Jan-14

Feb-14

Dec-13

Oct-13

Time

Nov-13

Sep-13

Jul-13

Aug-13

Jun-13

Apr-13

May-13

Mar-13

Jan-13

Feb-13

Dec-12

Nov-12

Oct-12

0%

Engineering

Procurement

20%

0.00%

50%

30%

Preliminary

25%

40%

90% 100%

0%

50%

Engineering

80%

-25%

60%

100.00%
99.58%

70%

-50%

: 94.15%

100.00%
100.00%

100.00%

% Completion

Actual Progress

70%

Preliminary

100.00%

80%

60%

121

Days of Month

Summary of progress report as of 30 June 2014

100%
90%

50

REMAINING INVOICE

SCHEDULE VARIANCE (SV)

PROGRESS BAR CHART - BREAKDOWN PROGRESS

% Completion

TOTAL AMOUNT

42

ACTUAL PROGRESS

42

PLANNED PROGRESS

COMPLETED DURATION

42

PROJECT DURATION

150

100

20,950,917.53

20,950,917.53

ACTUAL

CONTRACT AMOUNT in QAR

98.40%

638

PLANNED

MANPOWER HISTOGRAM

INVOICE STATUS

69

CONSULTANT - Assiociated Consulting Engineers


CONTRACTOR - Qatar Building Engineering Company

5,707,880.00

PROGRESS

-4.25%

121

PROJECT DURATION

CLIENT - RasGas

69

20

Manpower (Nos.)

KEY INFORMATION

Designation

Ahamed Ziyath

QBEC: Planning Engineer

Reviewed By

Nabhan. S Al Qasem

QBEC: Project Manager

Endorsed By

Bhaskar Challa

RG: Project Specialist

Signature

Date

Remarks

4. QA/QC STATUS
Documents Status:
Status

Total
Submitted

(Approved)

P.Q.P. (Main contractor QBEC)

Sub-Contractor P.Q.P. (Total 5)

Submitted

Balance (Fountain )

23

23

Document

ITP
Procedures

Submitted

(Method of
Statements)

Balance (Fountain
works)

Remarks
IFC
IFC
IFC

Inspection Status: (CA Civil, EL Electrical, MA Mechanical)


Total RFI
Inspected

Accepted

Rejected

Remark
s

Cancelled

Discipline

CA

EL

MA

CA

EL

MA

CA EL MA

CA EL

MA

This week RFI

13

02

04

13

02

04

01 00

00

00

00

00

724

68

90

724

65

89

26 03

01

18

01

00

Cumulative
RFI

QUALITY OBJECTIVES
Sl.
No.:

K.P.I /
QUALITY OBJECTIVES

TERGET

RESPONSIBILITY

FREQUENCY OF
REVIEW

RESULTS ACHIEVED

1)

% of RFI approval against submitted

More than 95%

P.M / C.M.

Quarterly

96.7%

2)

% of Material approval against


inspected

More than 95%

P.M / C.M.

Quarterly

99.00%

5. HEATH AND SAFET

QBEC Weekly Safety Report Week 75


Cut-off Period From

28-Jun

To

PTW Failure / Violations

3-Jul

2014
529

LTI free safe work days achieved


Item Description

INCIDENT:

Lost Time Injury (LTI)


Restricted Work Case (RWC)
Medical Treatment Case (MTC)
First Aid Case (FAC)
Motor Vehicle Accident (MVA)
Property Damage & Equipment
Fire Incident
Environment Incident
Security Incident
Near Miss

Date & Time - 19/03/2013 15:10 hours

Current This
Week Month
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Days

Year to
Cumm PTD
Date
0
0
0
0
1
4
0
0
1
5

0
0
0
0
1
4
0
0
1
5

PTW Failure / Violation eSafety

PTW Violation PTW Coordinator

st

Period

nd

1 Quarter 2

rd
th
Quarter 3 Quarter 4 Quarter Cumulative

TRIR

0.00

0.00

0.00

0.00

0.00

LTIR

0.00

0.00

0.00

0.00

0.00

No Body Get Hurt- Zero Incident Target

Man Power & Man Hours


Man Power

No.

CONTRACTOR

Qatar Building Engineering Co.

On Shore

Man Hours

Off Shore

121

On Shore

Off Shore

Total Man
Hours

Cum. Man Hours Total Cumulative


YTD
Man-hours

6,560

6,560

6
7

8
9

Sub Total

776,824

121

6,560

6,560

776,824

Total Man Power

770,264

Total Cum. Man Hrs To Date

121

770,264

Activity Summary
Item Description

Current Week

YTD 2013

Year 2013

Year 2012

Item Description

Current
Week

YTD

.- VE

.- VE

.- VE

.- VE

16

1811

1,811

NA

B-Safe Checklist

161

Observation Card
Item Description

All

Good

PTW Audit Onshore

40

40

PTW Audit Offshore

NA

NA

3275

3275

Total

Concern
NA

Current Week

YTD

Safety Inspections

453

Safety Walkabouts
JSA / RA / Safety Reviews

0
0

26
10

B-Safe Meetings
Safety Representation in Meetings

0
0

16
39

Item Description

Safety SHE Monthly Focus


Training

Safety Campaign HEAT


STRESS PREVENTION"

Total % Safe

Update
Attendants

Total Monthly
Man-power

% (Percentage
Attended)

75

247

30%
Rev 1 - Jan 2013

Project Safety Highlights / Achievements

Daily Toolbox talk being conducted on daily


basis

Weekly mass safety tool box talk conducted


this morning (03-07-2014)

C
C
C
C

Time
Jul-14

Jun-14

May-14

Apr-14

CUML. PLANNED %

Mar-14

Feb-14

Jan-14

Dec-13

Nov-13

Oct-13

S - CURVE

Sep-13

Aug-13

Jul-13

Jun-13

May-13

Apr-13

Mar-13

Feb-13

Actual Progress

Jan-13

80%

Dec-12

90%

Nov-12

Oct-12

% Completion

6. PROGRESS S-CURVE
CUML. ACTUAL %

100%

Planned Progress : 98.40%


: 94.15%

70%

60%

50%

40%

30%

20%

10%

0%

7. SUMMARY OF MATERIAL SUBMITTAL


Drawing Title
Total IFC CODE CODE
A
B
Design
18
18 0
0
Calculations
General
26
14 0
0

CODE
D
0

Cumulative Total
Remarks
Remaining
18
0

12

26

12

Landscape & Civil 61

61

61

Shades

15

15

15

Signage & Road


Marking
Irrigation

20

20

20

23

23

23

Plumbing

20

12

13

Instrumentation

Electrical

45

31

14

45

14

TOTAL

229

183 0

14

25

222

34

8. SUMMARY OF DESIGN DRAWING SUBMITTAL


Drawing Title
Total IFC CODE CODE CODE
A
B
D
Design
18
18 0
0
0
Calculations
General
26
14 0
0
12

Regency
- New
design
Regency
- New
design

Cumulative Total
Remarks
Remaining
18
0
26

12

Landscape & Civil 61

61

61

Shades

15

15

15

Signage & Road


Marking
Irrigation

20

20

20

23

23

23

Plumbing

20

12

13

Instrumentation

Electrical

45

31

14

45

14

TOTAL

229

183 0

14

25

222

34

Regency
- New
design
Regency
- New
design

9. MATERIAL SUBMITTAL LOG

ENGINEERING, PROCUREMENT AND CONSTRUCTION OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN

PROCUREMENT LOG
LEGEND
A

Approved

Approved W Comments

MANUFACTURER

QTY REQD.

UNIT

RASGAS SPEC REF.

Reviewed With No
Comments

SUBMITTAL
SUBMITTAL NO.

DESCRIPTION OF MATERIAL

SPECIFICATION

MODEL

COUNTRY OF
ORIGIN

PLAN DATE

REV

Reviwed with
Comments

Submitted

Rejected

APPROVAL

PROCUREMENT

ACTUAL

REQD DATE OF
APPROVAL

ACTUAL DATE OF
APPROVAL

STATUS

PLANNED DATE FOR


ORDER

ACTUAL DATE OF
ORDER

DATE REQD. AT SITE

EXPECTED DATE OF
DELIVERY

ACTUAL DATE OF
DELIVERY

11

12

13

14

15

16

17

18

19

10

RGX-S-64-1320-902

3/12/2013

3/27/2013

3/26/2013

3/28/2013

3/30/2013

4/24/1913

2/5/2013

AS REQUIRED

CIVIL / ARCHITECTURAL
RGCP-472-CA-001

READYMIX CONCRETE

48N , 28N (Blinding)

Qatar

ReadyMix Qatar W.L.L

800.00

RGCP-472-CA-002

WASHED SAND

50mm thick

Qatar

Qatar National
Cement Company

668.64

RGX-S-80-134-003A

3/12/2013

5/5/2013

3/26/2013

6/5/2013

3/30/2013

5/1/2013

2/5/2013

AS REQUIRED

RGCP-472-CA-003

DUNE SAND

S-80-134A-003

Qatar

Qatar National
Cement Company

800.00

m3

S-80-134A-003

3/12/2013

3/4/2013

3/26/2013

3/11/2013

3/30/2013

5/1/2013

2/5/2013

AS REQUIRED

RGCP-472-CA-004

PAVING TILES

80mm, 60mm Gray / 60mm Red,


Yellow

Qatar

Al-Sehmiah Cement
Products Factory

7395.00

m2

S-80-134A-003

3/12/2013

12/31/2012

3/26/2013

1/22/2013

3/30/2013

4/17/1913

10/5/2013

5/5/2013

3254.00

m2

S-80-134A-003

3/12/2013

12/31/2012

3/26/2013

1/22/2013

3/30/2013

4/17/1913

10/5/2013

5/5/2013

RGCP-472-CA-004

PAVING TILES

200mmX100mmX60mm Gray

Qatar

Al-Sehmiah Cement
Products Factory

RGCP-472-CA-004

PAVING TILES

200mmX100mmX60mm Red

Qatar

Al-Sehmiah Cement
Products Factory

2827.00

S-80-134A-003

3/12/2013

2/21/2013

3/26/2013

2/28/2013

3/30/2013

4/17/1913

10/5/2013

5/5/2013

RGCP-472-CA-004

PAVING TILES

200mmX100mmX60mm Yellow

Qatar

Al-Sehmiah Cement
Products Factory

168.00

m2

RG6-S-00-1317-901

3/12/2013

2/27/2013

3/26/2013

3/7/2013

3/30/2013

4/17/1913

10/5/2013

5/5/2013

34.00

tons

RGX-S-80-134-003A

3/12/2013

5/5/2013

3/26/2013

6/5/2013

3/30/2013

4/24/1913

1/5/2013

EXSTOCK

10391.00

S-80-134A-003, 2.2.16

3/12/2013

4/16/2013

3/26/2013

4/18/2013

3/30/2013

4/17/1913

2/5/2013

5/5/2013

8/27/2013

8/27/2013

RGCP-472-CA-005

CEMENT

OPC S-80-134A-003

Qatar

Qatar National
Cement Company

RGCP-472-CA-006

KERBSTONES

150mmX305mm

Qatar

Al-Sehmiah Cement
Products Factory

RGCP-472-CA-006-1

PRECAST CONCRETE FLUSH KERB

RGCP-472-CA-007

STEEL REINFORCEMENT

20mm,16mm,12mm,10mm

Qatar

Qatar Steel

91.00

tons

ASTM-A615 Grade 460

3/12/2013

12/31/2012

3/26/2013

1/2/2013

3/30/2013

4/22/1913

5/5/2013

5/5/2013

RGCP-472-CA-007

STEEL REINFORCEMENT

8mm

Qatar

Qatar Steel

1.00

tons

ASTM-A615 Grade 460

3/12/2013

12/31/2012

3/26/2013

1/2/2013

3/30/2013

4/22/1913

5/5/2013

5/5/2013

RGCP-472-CA-008

CONCRETE FLAG STONES

450mmx450mmX60mm

Qatar

Al-Sehmiah Cement
Products Factory

500.00

m2

S-80-134A-003 ,2.2.7

3/12/2013

5/5/2013

3/26/2013

6/5/2013

3/30/2013

4/17/1913

10/5/2013

5/5/2013

RGCP-472-CA-009

POLYTHELENE SHEET

1000 Guage

Qatar

Al-Moudi Plastic
Factory

4100.00

m2

RGX-S-64-1320-902

3/12/2013

2/21/2013

3/26/2013

2/28/2013

3/30/2013

4/21/1913

5/5/2013

5/5/2013

RGCP-472-CA-010

PROTECTION BOARD

6mm

Qatar

Sodamco-Qatar W.L.L

3311.00

m2

RGXS-64-1320-902-01

3/12/2013

2/21/2013

3/26/2013

2/28/2013

3/30/2013

4/23/1913

5/5/2013

5/5/2013

RGCP-472-CA-010A

PROTECTION BOARD

9/4/2014

RGCP-472-CA-011

WATERPROOF BITUMEN PAINT (Master Seal)

5/22/2013

3/30/2013

12/5/2013

20/05/2013

RGCP-472-CA-012

AGGREGATE

5/27/2013

3/30/2013

20-5-2013

15/05/2013

RGCP-472-CA-013

DRAIN CHANNEL WITH GRATING 300MM

5/27/2013

3/30/2013

25-5-2013

20/05/2013

17-Sep-13

RGCP-472-CA-013-1

CHANNEL GRATING &FRAMES

RGCP-472-CA-014

EDGERS FOR PLANTS & SHRUBS

Qatar
2CM

Sodamco-Qatar W.L.L

Qatar

6621.56

m2

RGX-S-64-1320-902-01

3/12/2013

5/21/2013

1335.07

m3

S-80-134A-003

3/12/2013

5/23/2013

no.

RG6-S-00-134A-010

3/12/2013

5/21/2013

Qatar

5CM

5/25/2013

Kiswok

29

Nos

RG6-S-00-134A-010

08-09-13

Qatar

Al-Sehmiah Cement
Products Factory

4614.13

D-80-134A-104

3/12/2013

2/24/2013

3/26/2013

3/4/2013

3/30/2013

4/17/1913

6/5/2013

5/5/2013

Qatar

Modern Building
Accessories Factory

1000.00

no.

S-80-134A-0095

3/12/2013

2/24/2013

3/26/2013

3/4/2013

3/30/2013

4/29/2013

5/5/2013

5/5/2013

26701.36

m2

S-80-134A-003

3/12/2013

2/24/2013

3/26/2013

3/4/2013

3/30/2013

4/23/1913

20-5-2013

10/5/2013

2000.00

m2

S-80-134A-003

3/12/2013

2/21/2013

3/26/2013

3/4/2013

3/30/2013

4/27/1913

10/5/2013

5/5/2013

S-80-134A-003

25-Nov-13

3/26/2013

30-Nov-13

3/30/2013

25-5-2013

15/06/2013

RGCP-472-CA-015

PLASTIC SPACERS

7CM

RGCP-472-CA-016

GEOTEXTILE MEMBRANE

1000G

RGCP-472-CA-018

MASONARY BLOCKS

200mm

RGCP-472-CA-020

ADHESIVE FOR GRANITE7MOSAIC TILES IN


WATERFEATURE

20mm

RGCP-472-CA-021

EXPANSION JOINT FILLER

S-80-134A-003

3/12/2013

5/15/2013

3/26/2013

5/22/2013

3/30/2013

25-5-2013

15/06/2013

RGCP-472-CA-022

GROUT

S-80-134A-003

05-Aug-13

5/21/2013

3/26/2013

8/19/2013

3/30/2013

25-5-2013

15/06/2013

RGCP-472-CA-023

KERBSTONE PAINT

S-80-134A-003

3/12/2013

8/17/2013

8/19/2013

25-5-2013

15/06/2013

RGCP-472-CA-024

SUBBASE

S-80-134A-003

3/12/2013

5/15/2013

5/22/2013

25-5-2013

15/06/2013

Qatar

Al-Sedriah Cement
Products Factory

Page 1 of 9

3/26/2013

3/30/2013

6/5/2013

6/5/2013

Updated on : 7/7/2014

ENGINEERING, PROCUREMENT AND CONSTRUCTION OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN

PROCUREMENT LOG
LEGEND
A

Approved

Approved W Comments

MANUFACTURER

QTY REQD.

UNIT

RASGAS SPEC REF.

Reviewed With No
Comments

SUBMITTAL
SUBMITTAL NO.

DESCRIPTION OF MATERIAL

SPECIFICATION

MODEL

COUNTRY OF
ORIGIN

PLAN DATE

REV

Reviwed with
Comments

APPROVAL

ACTUAL

REQD DATE OF
APPROVAL

PROCUREMENT

ACTUAL DATE OF
APPROVAL

STATUS

RGCP-472-CA-025

STRUCTTURAL CONCRETE REPAIR MORTARRENDROC- LAXtra

24-Jul-13

25-Jul-13

RGCP-472-CA-027

ROAD MARKING

11-Jul-13

18-Jul-13

Page 2 of 9

Submitted

Rejected

PLANNED DATE FOR


ORDER

ACTUAL DATE OF
ORDER

DATE REQD. AT SITE

EXPECTED DATE OF
DELIVERY

ACTUAL DATE OF
DELIVERY

Updated on : 7/7/2014

ENGINEERING, PROCUREMENT AND CONSTRUCTION OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN

PROCUREMENT LOG
LEGEND
A

Approved

Approved W Comments

MANUFACTURER

QTY REQD.

UNIT

RASGAS SPEC REF.

Reviewed With No
Comments

SUBMITTAL
SUBMITTAL NO.

RGCP-472-CA-028
RGCP-472-CA-029

DESCRIPTION OF MATERIAL

SPECIFICATION

MODEL

COUNTRY OF
ORIGIN

NITOSEAL MS60 SEALANT FOR EXPANSION


JOINTS
STRUCTTURAL CONCRETE REPAIR MORTARRENDROC- LAXtra

Reviwed with
Comments

APPROVAL

STATUS

28-Jul-13

24-Jul-13

25-Jul-13

REV

24-Jul-13

ACTUAL

REQD DATE OF
APPROVAL

PROCUREMENT

ACTUAL DATE OF
APPROVAL

PLAN DATE

RGCP-472-CA-030

PVC WATER STOP

08-Sep-13

17-Sep-13

RGCP-472-CA-031

WATERPROOF MENBRANE

20-Aug-13

26-Aug-13

RGCP-472-CA-032

NITOSEAL MS600 SEALANT FOR EXPANSION


JOINTS

14-Aug-13

8/19/2013

RGCP-472-CA-033

WATERPROOFING FOR WATERFEATURE

25-Nov-13

30-Nov-13

RGCP-472-CA-034

GROUT FOR GRANITE7MOSAIC TILES IN


WATERFEATURE

25-Nov-13

30-Nov-13

RGCP-472-CA-035

ADHESIVE FO REXTERNAL GRANITE CLADDING

SODAMCO

31-Aug-13

10/23/2013

24-Oct-13

RGCP-472-CA-036

GROUT FOR EXTERNAL GRANITE CLADDING

SODAMCO

31-Aug-13

10/23/2013

24-Oct-13

RGCP-472-CA-037

CONCRETE CURING COMPOUND

31-Aug-13

05-Sep-13

08-Sep-13

17-Sep-13

25-Sep-13

02-Oct-13

RGCP-472-CA-039

VERY HIGH STRENGTH SHRINKAGE


COMPENSATED GROUT FOR USE UDER BASE
PLATES OF LAMP POSTS
ANCHOR BOLTS SIGNAGE (GULF STEEL)

RGCP-472-CA-040

GRANITE (BLCK GALAXY)

14-Sep-13

19-Sep-13

RGCP-472-CA-041

GRANITE (LIGHT & DARK GREY)

19-Sep-13

02-Oct-13

RGCP-472-CA-042

Drop Sculpture (Acrylic sheet)

29-Dec-13

08-Jan-14

RGCP-472-CA-043

PLASTIC EDGING FOR PLANTING AREA

25-Nov-13

27-Nov-13

28-Jan-14

02-Feb-14

18-Nov-13

20-Nov-13

01-Jan-14

08-Jan-14

01-Jan-14

08-Jan-14

13-Nov-13

20-Nov-13

23-Nov-13

27-Nov-13

23-Nov-13

27-Nov-13

RGCP-472-CA-038

RGCP-472-CA-043A
RGCP-472-CA-044
RGCP-472-CA-045
RGCP-472-CA-047
RGCP-472-CA-048
RGCP-472-CA-049
RGCP-472-CA-052

PLASTIC EDGING FOR PLANTING AREA


(Alternative)
FOSROC THIOFLEX 600 SEALANT FOR
EXPANSION JOINTS
PAINT SYSTEM FOR CONCRETE ZONE ID
SIGNAGE
GRANITE (CHINA BLACK G654) FOR ROADWAY
AT ENTRANCE PLAZA
PAINT SYSTEM FOR CONCRETE ABOVE
GROUND
SOLVENT BASED BITUMINOUS PRIMER FOR
DERMABIT WATER PROOFING
MOSAIC TILES FOR WATER FEATURESPECTRUM KK11379 OPT 4 FOR FOUNTAIN

RGCP-472-CA-053

GRANITE (BLACK GALAXY) FOR FOR FOUNTAIN

22-Dec-13

12-Jan-14

RGCP-472-CA-054

DROP SCULPTURE (STAINLESS STEEL 316L) FOR


FOUNTAIN

22-Dec-13

12-Jan-14

RGCP-472-CA-056

Bonding Agent

09-Apr-14

17-Jun-14

29-Apr-14

13-Apr-14

09-Jun-14

RGCP-472-CA-057
RGCP-472-CA-058

Fostoc Nitocote CM 210 for balancing


tank in zone 2
Epoxy coating for Pump room and
Enclosure flooring

PLANNED DATE FOR


ORDER

ACTUAL DATE OF
ORDER

DATE REQD. AT SITE

EXPECTED DATE OF
DELIVERY

ACTUAL DATE OF
DELIVERY

RGCP-472-CA-059

Paint for Pump room Internal Walls

13-Apr-14

09-Jun-14

RGCP-472-CA-060

GRC PANEL COVERS

14-Apr-14

17-Jun-14

RGCP-472-CA-061

Material Submittal-G.I Ladder ,Checkered Plate


& Brackets, G.I Bollards &Handrail

06-Jun-14

12-Jun-14

Page 3 of 9

Submitted

Rejected

Updated on : 7/7/2014

ENGINEERING, PROCUREMENT AND CONSTRUCTION OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN

PROCUREMENT LOG
LEGEND
A

Approved

Approved W Comments

MANUFACTURER

QTY REQD.

UNIT

RASGAS SPEC REF.

Reviewed With No
Comments

SUBMITTAL
SUBMITTAL NO.

DESCRIPTION OF MATERIAL

SPECIFICATION

MODEL

COUNTRY OF
ORIGIN

PLAN DATE

RGCP-472-CA-062

REV

Reviwed with
Comments

Submitted

Rejected

APPROVAL

ACTUAL

REQD DATE OF
APPROVAL

ACTUAL DATE OF
APPROVAL

PROCUREMENT

STATUS

PLANNED DATE FOR


ORDER

ACTUAL DATE OF
ORDER

DATE REQD. AT SITE

EXPECTED DATE OF
DELIVERY

ACTUAL DATE OF
DELIVERY

CEMENT BASED WATERPROOFING FOR PUMP


ROOM

Page 4 of 9

Updated on : 7/7/2014

ENGINEERING, PROCUREMENT AND CONSTRUCTION OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN

PROCUREMENT LOG
LEGEND
A

Approved

Approved W Comments

MANUFACTURER

QTY REQD.

UNIT

RASGAS SPEC REF.

Reviewed With No
Comments

SUBMITTAL
SUBMITTAL NO.

DESCRIPTION OF MATERIAL

SPECIFICATION

MODEL

COUNTRY OF
ORIGIN

Reviwed with
Comments

Submitted

Rejected

APPROVAL

PROCUREMENT

PLAN DATE

REV

ACTUAL

REQD DATE OF
APPROVAL

ACTUAL DATE OF
APPROVAL

STATUS

PLANNED DATE FOR


ORDER

ACTUAL DATE OF
ORDER

DATE REQD. AT SITE

EXPECTED DATE OF
DELIVERY

ACTUAL DATE OF
DELIVERY

SHADE STRUCTURE FABRICATION


RGCP-472-CT-001

Tensile Roof Shade - Hot Dip Galvanized


Steel

S-80-134A-003

Qatar

Qatar Steel

361.00

m2

RG6-D-00-1330-002

4/6/2013

2/26/2013

4/18/2013

3/4/2013

4/22/2013

5/1/2013

6/2/2013

5/30/2013

RGCP-472-CT-002

Shade Structure Painting System

S-80-134A-003

Qatar

Juton Paints

104.00

m2

RG6-D-00-1330-004

4/6/2013

2/26/2013

4/18/2013

3/4/2013

4/22/2013

5/1/2013

6/2/2013

5/30/2013

RGCP-472-CT-003

PVC Fabric for Shades

S-80-134A-003

France

Ferrari

S-80-134A-003

4/6/2013

5/5/2013

4/18/2013

6/5/2013

4/22/2013

6/2/2013

5/30/2013

RGCP-472-CT-003D

FABRIC SHADE COLOR

S-80-134A-003

France

Ferrari

9/10/2013

10/23/2013

RGCP-472-CT-004

Hot Dip Galvanizing Process for Signage


Pipe

S-80-134A-003

Qatar

RGCP-472-CT-005

GI Pipe for Signage

S-80-134A-003

Qatar

RGCP-472-CT-006

STAINLESS STEEL TUBE 100X50X2MM

S-80-134A-003

Qatar

RGCP-472-CT-007

Rectangular Hollow Section Support for


Signage

Qatar

SIGNAGE WORK

S-80-134A-003

RGCP-472-CT-008

3M Sticker for Signage

Reflective Traffic Sign

RGCP-472-CT-009

Aluminum Extruded Profile for Signage

4.3 support Syste,

RGCP-472-CT-010

Aluminum Sheet 3mm Thick for signage

RGCP-472-CT-011

SS SHEET 2MM THICK

RGCP-472-CT-012
RGCP-472-CT-013

Gulf Building
Material
Gulf Building
Material

146.00

Nos

RG6-D-00-1330-002

06-Mar-13

04-Mar-13

20-Mar-13

11-Mar-13

25-Mar-13

01-May-13

05-May-13

02-May-13

280.00

Lm

S-80-134-A003

06-Mar-13

19-Mar-13

20-Mar-13

27-Mar-13

25-Mar-13

08-Apr-13

05-May-13

02-May-13

Hidayath

378.00

Lm

S-80-134-A003

06-Mar-13

19-Mar-13

20-Mar-13

27-Mar-13

25-Mar-13

08-Apr-13

05-May-13

02-May-13

Gulf Building
Material

1040.00

Lm

S-80-134-A003

06-Mar-13

19-Mar-13

20-Mar-13

02-Apr-13

25-Mar-13

08-Apr-13

05-May-13

02-May-13

S-80-134-A003

06-Mar-13

19-Mar-13

20-Mar-13

24-Mar-13

25-Mar-13

08-Apr-13

05-May-13

02-May-13

UAE

3M

378.00

Qatar

Al-Jaber

320.00

no.

S-80-134-A003

06-Mar-13

19-Mar-13

20-Mar-13

24-Mar-13

25-Mar-13

08-Apr-13

05-May-13

02-May-13

S-80-134A-003

Qatar

Alubond

520.00

m2

S-80-134-A003

06-Mar-13

19-Mar-13

20-Mar-13

24-Mar-13

25-Mar-13

08-Apr-13

05-May-13

02-May-13

S-80-134A-003

Qatar

Hidayath

45.00

m2

S-80-134-A003

06-Mar-13

20-Mar-13

20-Mar-13

27-Mar-13

25-Mar-13

08-Apr-13

05-May-13

02-May-13

Paint System for Signage

07-Oct-13

PVC Fabric for Shades

27-May-14

6061& 6065

By Email

IRRIGATION & PLANTATION


RGCP-472-PI-002

HDPE Pipes and Fittings

RGCP-472-PI-002

HDPE Pipes and Fittings

RGCP-472-PI-002

HDPE Pipes and Fittings

RGCP-472-PI-002

HDPE Pipes and Fittings

RGCP-472-PI-002

HDPE Pipes and Fittings

RGCP-472-PI-002

HDPE Pipes and Fittings

RGCP-472-PI-002

HDPE Pipes and Fittings

RGCP-472-PI-002

HDPE Pipes and Fittings

RGCP-472-PI-002

HDPE Pipes and Fittings

RGCP-472-PI-002-1

HDPE Pipes and Fittings

RGCP-472-PI-003

Sleeves

RGCP-472-PI-003-1

Sleeves

4" * 90o Elbow Compression


3" * 90o Elbow Compression
3 * 2 Reducer Socket Compression

Qatar

Hepworth

10.00

no.

S-80-134A-002

13-Apr-13

13-Mar-13

25-Apr-13

18-Apr-13

29-Apr-13

17-May-13

15/05/2013

Qatar

Hepworth

4.00

no.

S-80-134A-002

13-Apr-13

13-Mar-13

25-Apr-13

18-Apr-13

29-Apr-13

17-May-13

15/05/2013

Qatar

Hepworth

2.00

no.

S-80-134A-002

13-Apr-13

13-Mar-13

25-Apr-13

18-Apr-13

29-Apr-13

17-May-13

15/05/2013

Qatar

Hepworth

4.00

no.

S-80-134A-002

13-Apr-13

13-Mar-13

25-Apr-13

18-Apr-13

29-Apr-13

17-May-13

15/05/2013

Qatar

Hepworth

11.00

no.

S-80-134A-002

13-Apr-13

13-Mar-13

25-Apr-13

18-Apr-13

29-Apr-13

17-May-13

15/05/2013

Qatar

Hepworth

3.00

no.

S-80-134A-002

13-Apr-13

13-Mar-13

25-Apr-13

18-Apr-13

29-Apr-13

17-May-13

15/05/2013

Qatar

Hepworth

2.00

no.

S-80-134A-002

13-Apr-13

13-Mar-13

25-Apr-13

18-Apr-13

29-Apr-13

17-May-13

15/05/2013

3" End Caop - Compression

Qatar

Hepworth

1.00

no.

S-80-134A-002

13-Apr-13

13-Mar-13

25-Apr-13

18-Apr-13

29-Apr-13

17-May-13

15/05/2013

2" End Caop - Compression

Qatar

Hepworth

9.00

no.

S-80-134A-002

13-Apr-13

13-Mar-13

25-Apr-13

18-Apr-13

29-Apr-13

17-May-13

15/05/2013

21-May-13

30-May-13

01-May-13

08-May-13

29-Apr-13

21-May-13

20/05/2013

21-May-13

30-May-13

18-Mar-13

26-Mar-13

17-Mar-13

06-Jun-13

15-May-13

18-03-13

26-Mar-13

17-Mar-13

06-Jun-13

15-May-13

3" Equal TEE - Compression


4 * 4 * 2 Reducer TEE Compression
4 * 4 * 3 Reducer TEE Compression
3 * 3 * 2 Reducer TEE Compression

U.P.V.C Sleeve 6AND 1.5 "

RGCP-472-PI-AG-001

Remote Control Solenoid Valve

Rain Bird

RGCP-472-PI-AG-002

Dripline

Rain Bird

Qatar

EFB-CP-R Brass
Valves

qatar pipe line

USA

Rainbird

U.S.A

RAIN BIRD

300.00

81.00

no.

S-80-134A-002

D-80-134A-70
D-80-134A-70

Page 5 of 9

13-Apr-13

26-Feb-13

12-Mar-13

17-Apr-13

Updated on : 7/7/2014

ENGINEERING, PROCUREMENT AND CONSTRUCTION OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN

PROCUREMENT LOG
LEGEND
A

Approved

Approved W Comments

MANUFACTURER

QTY REQD.

UNIT

RASGAS SPEC REF.

Reviewed With No
Comments

SUBMITTAL
SUBMITTAL NO.

DESCRIPTION OF MATERIAL

SPECIFICATION

MODEL

COUNTRY OF
ORIGIN

Reviwed with
Comments

Submitted

Rejected

APPROVAL

PROCUREMENT

PLAN DATE

REV

ACTUAL

REQD DATE OF
APPROVAL

ACTUAL DATE OF
APPROVAL

STATUS

PLANNED DATE FOR


ORDER

ACTUAL DATE OF
ORDER

DATE REQD. AT SITE

EXPECTED DATE OF
DELIVERY

26-Feb-13

18-Mar-13

12-Mar-13

26-Mar-13

17-Mar-13

17-Apr-13

04-Jun-13

01-Jun-13

18-03-13

26-Mar-13

17-Mar-13

18-Mar-13

31-Mar-13

29-Apr-13

18-03-13

31-Mar-13

29-Apr-13

04-Jun-13
04-Jun-13

01-Jun-13

RGCP-472-PI-AG-003

Gate Valve

PEGLER

1065 Forged
Glass

USA

Pegler

RGCP-472-PI-AG-004

Quick Coupling Valve

Rain Bird

44LRC

U.S.A

Rainbird

RGCP-472-PI-AG-005

ROTOR SPRINKLERS

Rain Bird

5500 Series

USA

Rainbird

RGCP-472-PI-AG-006

Bubblers

Rain Bird

1400 Series

U.S.A

Rainbird

D-80-134A-70

RGCP-472-PI-AG-007

Irrigation Controller

Rain Bird

ESP-LXME
Controller

U.S.A

Rainbird

D-80-134A-70

13-Apr-13

18-Mar-13

25-Apr-13

26-Mar-13

29-Apr-13

RGCP-472-PI-AG-008

Valve Boxes Jumbo Rectangular Series

Rain Bird

VB-JMB

U.S.A

Rainbird

25.00

no.

D-80-134A-70

13-Apr-13

18-Mar-13

25-Apr-13

26-Mar-13

29-Apr-13

17-Apr-13

04-Jun-13

01-Jun-13

UNI Spray
Series

U.S.A

Rainbird

200.00

no.

D-80-134A-70

13-Apr-13

18-Mar-13

25-Apr-13

26-Mar-13

29-Apr-13

17-Apr-13

04-Jun-13

01-Jun-13

13-03-13

18-Apr-13

25.00

no.

D-80-134A-70
D-80-134A-70

180.00

no.

D-80-134A-70

13-Apr-13

25-Apr-13

15-Jun-13
17-Apr-13

04-Jun-13

01-Jun-13

RGCP-472-PI-AG-009

Sprayer Pop-Up sprinkler

Rain Bird

RGCP-472-PI-AG-010

XFD on Surface Driline

Rain Bird

U.S.A

Rainbird

RGCP-472-PI-AG-011

Agriculture Soil Mix

S-80-134A-003

Qatar

Municipality

12396.17

m3

D-80-134A-70

13-Apr-13

28-Feb-13

25-Apr-13

07-Mar-13

29-Apr-13

17-Apr-13

04-Jun-13

01-Jun-13

RGCP-472-PI-AG-012

Irrigation Control Cable Paige

Rain Bird

U.S.A

Rainbird

5000.00

D-80-134A-70

13-Apr-13

27-Feb-13

25-Apr-13

04-Mar-13

29-Apr-13

17-Apr-13

04-Jun-13

01-Jun-13

RGCP-472-PI-AG-013

Compost

S-80-134A-003

KSA

AL Safi Fertilizer
Factory

6000.00

bag

D-80-134A-70

12-Mar-13

28-Feb-13

26-Mar-13

07-Mar-13

30-Mar-13

17-Apr-13

08-May-13

04-May-13

RGCP-472-PI-AG-014

Peat Moss

S-80-134A-003

Germany

SAB Syker

500.00

bag

D-80-134A-70

12-Mar-13

26-Mar-13

26-Mar-13

28-Mar-13

30-Mar-13

17-Apr-13

08-May-13

04-May-13

RGCP-472-PI-AG-018

PLANT LIST

S-80-134A-003

KSA & Qatar

A.G

D-80-134A-71

12-Mar-13

13-Mar-13

26-Mar-13

24-Mar-13

30-Mar-13

17-Apr-13

08-Apr-13

04-May-13

RGCP-472-PI-AG-019

IRRIGATION & PLUMBING WARNING


TAPE

22-May-13

30-May-13

RGCP-472-PI-AG-020

MULCH

24-Sep-13

26-Sep-13

SAB Turba
Peat 340

200MM

D-80-134A-74

AS LISTED

Uniplast
Qatar

ACTUAL DATE OF
DELIVERY

04-Jun-13

ELECTRICAL
RGCP-472-EL-001

BOLLARD LIGHT (70 WATTS)

1000 mm hight - corrosion


resistant die-cast aluminum IP65 ,
UV-stabilized diffuser with integral
junction box - 15 amp single pole
and neutral cut-out/MCB

RGCP-472-EL-002

POLE LIGHT 6M

6 meters hight hot dip galvanized


steel octagonal type pole with
removable door of IP55 - ready for
mounting HPSV flood light fittings

RGCP-472-EL-003

HPSV FLOOD LIGHT (100 WATTS)

Die-cast aluminium housing with


heat resistant glass of IP65 and
corrosion resistant material

D-80-134A-284 section 10.3

27-Mar-13

03-Apr-13

10-Apr-13

07-Apr-13

15-Apr-13

RGCP-472-EL-004

LIGHTING POLE CUTOUT BOX

15 amp single pole and neutral cutout/MCB of IP55

D-80-134A-284 section 10.12

30-Jul-13

28-Apr-13

10-Apr-13

01-Aug-13

15-Apr-13

RGCP-472-EL-005

WALL MOUNTED WALKWAY LIGHT (36 WATTS)

Decorative ressed square shape


light of IP65, cool white light lamp
and die-cast aluminium sheet
reflector

RGCP-472-EL-006

single linear 36 watts lamp and


CEILING / WALL MOUNTED LIGHTS (1 X 36 WATTS)

Qatar

Q-Light

12.00

no.

D-80-134A-284 section 10.3

27-Mar-13

03-Mar-13

10-Apr-13

07-Mar-13

15-Apr-13

20-Apr-13

04-Jun-13

5/05/2013

Qatar

Q-Light

14.00

no.

D-80-134A-284 section 10.2

27-Mar-13

03-Mar-13

10-Apr-13

10-Mar-13

15-Apr-13

20-Apr-13

04-Jun-13

20/05/2013

20-Apr-13

04-Jun-13

5/05/2013

04-Jun-13

20/05/2013

Qatar

Q-Light

8.00

no.

D-80-134A-284 section 10.3

27-Mar-13

19-Feb-13

10-Apr-13

26-Feb-13

15-Apr-13

20-Apr-13

04-Jun-13

5/05/2013

Qatar

Q-Light

9.00

no.

D-80-134A-284 section 10.3

27-Mar-13

19-Feb-13

10-Apr-13

26-Feb-13

15-Apr-13

20-Apr-13

04-Jun-13

5/05/2013

Qatar

Q-Light

8.00

no.

D-80-134A-284 section 10.3

27-Mar-13

19-Feb-13

10-Apr-13

26-Feb-13

15-Apr-13

20-Apr-13

04-Jun-13

5/05/2013

Rectangular flurocent type with


polycarbonate cover of IP65

RGCP-472-EL-007

CEILING MOUNTED LIGHTS (2X 36 WATTS)

Rectangular flurocent type with


double linear 36 watts lamp and
polycarbonate cover of IP65

Page 6 of 9

Updated on : 7/7/2014

ENGINEERING, PROCUREMENT AND CONSTRUCTION OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN

PROCUREMENT LOG
LEGEND
A

Approved

Approved W Comments

MANUFACTURER

QTY REQD.

UNIT

RASGAS SPEC REF.

Reviewed With No
Comments

SUBMITTAL
SUBMITTAL NO.

DESCRIPTION OF MATERIAL

SPECIFICATION

MODEL

COUNTRY OF
ORIGIN

Reviwed with
Comments

Submitted

Rejected

APPROVAL

PLAN DATE

REV

ACTUAL

D-80-134A-283

27-Mar-13

18-Aug-13

REQD DATE OF
APPROVAL

PROCUREMENT

ACTUAL DATE OF
APPROVAL

STATUS

26-Aug-13

PLANNED DATE FOR


ORDER

ACTUAL DATE OF
ORDER

DATE REQD. AT SITE

EXPECTED DATE OF
DELIVERY

RGCP-472-EL-010

FEEDER PILLAR

Stainless steel encloure of IP55


with a protective canopy fitted
with a photocell and timer

RGCP-472-EL-011

CABLE LUGS

Nickel plated brass weather proof


cable gland of IP55 High
conductivity non-insulated tinned
copper

Qatar

FANCY

325.00

no.

D-80-134A-284 section 10.5

27-Mar-13

07-Mar-13

10-Apr-13

12-Mar-13

15-Apr-13

04-Jun-13

15/05/2013

RGCP-472-EL-011

CABLE GLAND

Nickel plated brass weather proof


cable gland of IP55 High
conductivity non-insulated tinned
copper

Qatar

FANCY

55.00

no.

D-80-134A-284 section 10.5

27-Mar-13

07-Mar-13

10-Apr-13

12-Mar-13

15-Apr-13

04-Jun-13

15/05/2013

RGCP-472-EL-012

PVC PIPES, JUNCTION BOXES AND ACCESSORIES

Thick-walled havey duty type , UV


stabilized material

Qatar

Al-Amer Group

300.00

no.

27-Mar-13

10-Mar-13

10-Apr-13

14-Mar-13

15-Apr-13

04-Jun-13

15/05/2013

RGCP-472-EL-013

GI PIPES AND ACCESSORIES

Hot dip galvanized steel of IP55

Qatar

FANCY

200.00

no.

27-Mar-13

04-Mar-13

10-Apr-13

11-Mar-13

15-Apr-13

04-Jun-13

20/05/2013

RGCP-472-EL-013-1

GI PIPES AND ACCESSORIES

25-Aug-13

26-Aug-13

27-Mar-13

18-Mar-13

18-Mar-13

15-Apr-13

04-Jun-13

20/05/2013

19-May-13

22-May-13

26-Aug-13

C
04-Jun-13

20/05/2013

04-Jun-13

15/05/2013

RGCP-472-EL-014

XLPE/SWA/PVC CABLES - PVC/ECC CABLES

RGCP-472-EL-014-1

ELECTRICAL CABLES

RGCP-472-EL-014-2

ELECTRICAL CABLES (Ducab)

RGCP-472-EL-015
RGCP-472-EL-017

Armoured cables of hight


conductivity copper

HR PVC FLEXIBLE CABLES

Copper 3 core flexible cables

CABLES WARNING TAPE

Yellow Danger marker PVC


strip/tape

Qatar

Qatar
Qatar

Al-Amer Group

1000.00

D-80-134A-284 section 10.9 ,


10.11
D-80-134A-284 section 10.9 ,
10.11

D-80-134A-284 section 10.4

25-Aug-13

10-Apr-13

Al-Amer Group

D-80-134A-284 section 10.4

27-Mar-13

13-Mar-13

10-Apr-13

18-Mar-13

15-Apr-13

UNIPLAST

Refrence to D-80-134A-284
section 10.6

27-Mar-13

20-Feb-13

10-Apr-13

26-Feb-13

15-Apr-13

300.00

Page 7 of 9

22-Apr-13

ACTUAL DATE OF
DELIVERY

Updated on : 7/7/2014

ENGINEERING, PROCUREMENT AND CONSTRUCTION OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN

PROCUREMENT LOG
LEGEND
A

Approved

Approved W Comments

MANUFACTURER

QTY REQD.

UNIT

RASGAS SPEC REF.

Reviewed With No
Comments

SUBMITTAL
SUBMITTAL NO.

DESCRIPTION OF MATERIAL

SPECIFICATION

MODEL

COUNTRY OF
ORIGIN

Refrence to D-80-134A-284
section 10.6
Refrence to D-80-134A-284
section 10.6

Reviwed with
Comments

APPROVAL

PROCUREMENT

PLAN DATE

REV

ACTUAL

REQD DATE OF
APPROVAL

ACTUAL DATE OF
APPROVAL

STATUS

PLANNED DATE FOR


ORDER

27-Mar-13

18-Mar-13

10-Apr-13

20-Mar-13

27-Mar-13

15-May-13

22-May-13

RGCP-472-EL-018

CABLE TRAY /TRUNKING

RGCP-472-EL-019

WIRING ACCESSORIES

RGCP-472-EL-020

PRECAST CABLE TILE PROTECTION AND CABLE ROUTE MARKERS

31-Aug-13

05-Sep-13

RGCP-472-EL-021

LABELS FOR WIRING

27-Aug-13

05-Sep-13

RGCP-472-EL-022

EARTHING MATERIALS

31-Aug-13

05-Sep-13

RGCP-472-EL-023

POLYURATHANE FOAM CAULKING

04-Sep-13

11-Sep-13

RGCP-472-EL-024

HEAT SHHRINK SLEEVES FOR CABLES

04-Sep-13

24-Oct-13

RGCP-472-EL-025

PRE CAST CABLE ROUTE MRKERS

12-Nov-13

11-Dec-13

RGCP-472-EL-026

SURFACE MOUNTED ELECTRICAL JUNCTION BOX FOR LIGHTING CABLES

13-Nov-13

20-Nov-13

RGCP-472-EL-027

UPVC Sleeves & Accessories for Electrical

13-Jan-14

20-Jan-14

RGCP-472-EL-028

Material Submittal-Electrical Cables

08-Jun-14

12-Jun-14

MEP MATERIAL FOR WATER FEATURE

05-Oct-13

SHEZNON

Submitted

Rejected

23-Oct-13

ACTUAL DATE OF
ORDER

DATE REQD. AT SITE

EXPECTED DATE OF
DELIVERY

15-Apr-13

04-Jun-13

20/05/2013

15-Apr-13

04-Jun-13

20/05/2013

ACTUAL DATE OF
DELIVERY

FOUNTAIN
RGCP-472-PI-016

1. Fountain Nozzle
2. Jet Nozzle
3. Sculpture Water Pump
4. Cascade Water Pump
5. Jet Nozzle and Filters
6. Scupture sand filter
7. Cascade water sand filter
8. Drain Pump/Submersible Pump
9. Valve and fittings
10. Main Drain
11. Inlet for water cascade
12. Overflow filter
13. Suction / Vacuum Filter
14. Water level regulator
15. Underwater lights for nozzle
16. Underwater light for fountain base

Page 8 of 9

Updated on : 7/7/2014

ENGINEERING, PROCUREMENT AND CONSTRUCTION OF BUILDING EXTERNAL AREAS UPGRADE IN ADMIN AREA AT RAS LAFFAN

PROCUREMENT LOG
LEGEND
A

Approved

Approved W Comments

MANUFACTURER

QTY REQD.

UNIT

RASGAS SPEC REF.

Reviewed With No
Comments

SUBMITTAL
SUBMITTAL NO.

DESCRIPTION OF MATERIAL

SPECIFICATION

MODEL

COUNTRY OF
ORIGIN

PLAN DATE

REV

Reviwed with
Comments

Submitted

Rejected

APPROVAL

ACTUAL

REQD DATE OF
APPROVAL

PROCUREMENT

ACTUAL DATE OF
APPROVAL

STATUS

PLANNED DATE FOR


ORDER

ACTUAL DATE OF
ORDER

DATE REQD. AT SITE

EXPECTED DATE OF
DELIVERY

ACTUAL DATE OF
DELIVERY

17. Transformer for Lights


18. Underwater LED lights
19. Power supply for lighting
21. Connector for lights
22, Under water junction box
23. Chemical Dosing Pot
RGCP-472-PI-017

PRESSURE REDUCING VALVE

12-Nov-13

03-Dec-13

RGCP-472-PI-018

Gate Valve

12-Nov-13

03-Dec-13

RGCP-472-PI-019

ELECTRIC JUNCTION BOX FOR TOP OF WATER


FEATURE WALL FOR LIGHTING

13-Nov-13

20-Nov-13

RGCP-472-PI-020

CAST IRON Y STRAINER FOR WATER FEATURE


ECON TYPE STAINER

18-Nov-13

03-Dec-13

RGCP-472-PI-021

PRESURE REDUCING VALVE FOR WATER


FEATURE

25-Nov-13

03-Dec-13

RGCP-472-PI-022

Fresh Air Centrifugal in Line Duct Fans for


Pump Room

18-Jun-14

RGCP-472-PI-023

MOTORIZED VALVES

RGCP-472-PI-024

PLC

RGCP-472-PI-025

PUMP ROOM LIGHTS

RGCP-472-PI-026

PUMP ROOM EARTHING

Page 9 of 9

Updated on : 7/7/2014

10. DESIGN DRAWING SUBMITTAL LOG

EPC of Building External Areas Upgrade in Admin Area at Raslaffan -RGCP-472


DESIGN DRAWING SUBMITTAL LOG
LEGEND
Approved/IFC

Sl.
No.

Drawing Title

Drawing Number

No of
Sheets

QBEC Transmittal
Reference

Approved with
Comments

Reviewed W No
Comments

Issue for Review

Plan
Submission
date

Rev

Submit Date

Reviewed with
Comments

Submitted

Issue for Approval

Issued for Construction

As-Built
Zone

Reply Date

Approval
Status

Rev

Submit Date Reply Date

Approval
Status

Rev

Submit Date Reply Date

Approval
Status

Rev

Submit Date

Reply Date

Approval
Status

DESIGN CALCULATIONS
1

Design calculation for balancing tank

C-80-134A-006

RGCP-472-T-QTR-642

16-Jan-13

17-Jan-13

23-Jan-13

17-Aug-13

21-Aug-13

05-Sep-13

30-Sep-13

IFC

Design calculation for Signage

C-80-134A-007

RGCP-472-T-QTR-641

21-Jan-13

24-Feb-13

27-Feb-13

08-Jul-13

25-Jul-13

05-Sep-13

30-Sep-13

IFC

All Zones

Uncovered carpark lighting calculation

C-80-134A-008

RGCP-472-T-QTR-166

21-Jan-13

22-Jan-13

23-Jan-13

10-Feb-13

14-Feb-13

26-Feb-13

27-Feb-13

IFC

1,14

Bus Plaza, Entrance Plaza, Covered Parking & Lighting Calculations

C-80-134A-009

RGCP-472-T-QTR-292

03-Feb-13

5-Feb-13

31-Mar-13

1-Apr-13

IFC

19

LV Cable Sizing Calculation

C-80-134A-010

RGCP-472-T-QTR-520

13-May-13

15-May-13

19-Jun-13

23-Jun-13

IFC

Water Feature Plumbing works Calculation

C-80-134A-011

RGCP-472-T-QTR-750

10-Mar-13

20-Mar-13

Pump Room Calculation Heat Loading

C-80-134A-011A

RGCP-472-T-QTR-860

Design Calculation for walkway Shade (Type 1)

C-80-134A-012

RGCP-472-T-QTR-741

03-Apr-13

10-Apr-13

Design Calculation for walkway Shade (Type 2)

C-80-134A-013

RGCP-472-T-QTR-742

03-Apr-13

11

Design Calculation for Warehouse Plaza Shade XK-32 and XK-03

C-80-134A-015

RGCP-472-T-QTR-698

12

Pump Room Lighting Calculation

C-80-134A-016

RGCP-472-T-QTR-634

13

Design Calculation for Flag pole

C-80-134A-017

14

Design Calculation for Carpark Shade

15

01-Oct-13

03-Oct-13

12-Nov-13

04-Dec-13

IFC

16-Dec-13

24-Dec-13

24-Apr-14

19-May-14

07-Oct-13

10-Oct-13

22-Oct-13

27-Oct-13

IFC

10-Apr-13

07-Oct-13

08-Oct-13

22-Oct-13

27-Oct-13

IFC

7,12,15

03-Apr-13

09-Apr-13

12-Sep-13

18-Sep-13

24-Sep-13

25-Sep-13

IFC

11

28-Apr-13

01-May-13

11-Aug-13

28-Aug-13

31-Aug-13

05-Sep-13

IFC

11

RGCP-472-T-QTR-640

11-May-13

14-May-13

18-Jul-13

04-Aug-13

12-Sep-13

23-Sep-13

IFC

C-80-134A-018

RGCP-472-T-QTR-697

14-May-13

16-May-13

16-Sep-13

18-Sep-13

24-Sep-13

25-Sep-13

IFC

Design Calculation for Mosque Plaza

C-80-134A-019

RGCP-472-T-QTR-695

05-Sep-13

09-Sep-13

16-Sep-13

18-Sep-13

24-Sep-13

26-Sep-13

IFC

16

Design Calculation for bus plaza near Admin

C-80-134A-020

RGCP-472-T-QTR-696

24-Aug-13

27-Aug-13

05-Sep-13

18-Sep-13

24-Sep-13

25-Sep-13

IFC

17

Adequacy Check for Power Source

C-80-134A-021

RGCP-472-T-QTR-556

29-Jun-13

30-Jun-13

08-Jul-13

10-Jul-13

16-Jul-13

29-Jul-13

IFC

18

LV Cable Schedule

C-80-134A-022

RGCP-472-T-QTR-764

05-Sep-13

05-Sep-13

29-Sep-13

29-Sep-13

13-Nov-13

01-Dec-13

IFC

19

Structural Calculation for Water Feature

C-80-134A-028

RGCP-472-T-QTR-639

11-Jul-13

29-Jul-13

11-Aug-13

19-Aug-13

05-Sep-13

23-Sep-13

IFC

20

Design Calculation for Bus Plaza Shade near XK-26

C-80-134A-029

RGCP-472-T-QTR-718

18/Aug/13

22/Aug/13

24-Sep-13

26-Sep-13

05-Oct-13

06-Oct-13

IFC

21

Structural Calculations for 0.50m and 1.00m Retaining Walls

C-80-134A-030

RGCP-472-T-QTR-827

06-Jan-14

12-Jan-14

22

Structural Calculations for Special Foundation Cases for shade

C-80-134A-031

RGCP-472-T-QTR-840

22-Feb-14

23-Feb-14

23

Structural Calculation for Enclosure Calculation

C-80-134A-032

RGCP-472-T-QTR-854

18-Mar-14

20-Mar-14

24

Structural Calculation for water Tank Top Slab

C-80-134A-033

RGCP-472-T-QTR-850

11-Mar-14

11-Mar-14

25

Structural Calculations for Drop Sculpture Structure

C-80-134A-034

RGCP-472-T-QTR-895

13-May-14

29-May-14

26

Structural Calculation for shades foundation Modification at axes B-1


and B-3 (Bus plaza near XK-26)

C-80-134A-035

RGCP-472-T-QTR-879

24-Apr-14

24-Apr-14

27

Structural Calculation for V-Ditch Slabs

C-80-134A-036

RGCP-472-T-QTR-884

24-Apr-14

24-Apr-14

21-Feb-13

24-Feb-13

IFC

All Zones

GENERAL
1

General Notes

D-80-134A-101

1 of 1

RGCP-472-T-QTR-085

20-Jan-13

03-Feb-13

10-Feb-13

Demolition And Reinstatement works layout

D-80-134A-105

1 of 4

RGCP-472-T-QTR-265

17-Jan-13

23-Jan-13

31-Jan-13

21-Feb-13

3-Mar-13

24-Mar-13

26-Mar-13

IFC

All Zones

Demolition And Reinstatement works layout

D-80-134A-105

2 of 4

RGCP-472-T-QTR-265

17-Jan-13

23-Jan-13

31-Jan-13

21-Feb-13

3-Mar-13

24-Mar-13

26-Mar-13

IFC

All Zones

Demolition And Reinstatement works layout

D-80-134A-105

3 of 4

RGCP-472-T-QTR-265

17-Jan-13

23-Jan-13

31-Jan-13

21-Feb-13

3-Mar-13

24-Mar-13

26-Mar-13

IFC

All Zones

Demolition And Reinstatement works layout

D-80-134A-105

4 of 4

RGCP-472-T-QTR-265

17-Jan-13

23-Jan-13

31-Jan-13

21-Feb-13

3-Mar-13

24-Mar-13

26-Mar-13

IFC

All Zones

Work Sequence Layout

D-80-134A-107

1 of 4

RGCP-472-T-QTR-333

17-Jan-13

23-Jan-13

30-Jan-13

21-Apr-13

22-Apr-13

IFC

All Zones

Work Sequence Layout

D-80-134A-107

2 of 4

RGCP-472-T-QTR-333

17-Jan-13

23-Jan-13

30-Jan-13

21-Apr-13

22-Apr-13

IFC

All Zones

Work Sequence Layout

D-80-134A-107

3 of 4

RGCP-472-T-QTR-333

17-Jan-13

23-Jan-13

30-Jan-13

21-Apr-13

22-Apr-13

IFC

All Zones

Work Sequence Layout

D-80-134A-107

4 of 4

RGCP-472-T-QTR-333

17-Jan-13

23-Jan-13

30-Jan-13

21-Apr-13

22-Apr-13

IFC

All Zones

D-80-134A-068X

1 of 5

RGCP-472-T-QTR-822

05-Mar-13

12-Mar-13

3-Apr-13

9-Apr-13

29-Dec-13

2-Jan-14

IFC

2,3,4,6,7,8,9,11

D-80-134A-068X

2 of 5

RGCP-472-T-QTR-822

05-Mar-13

12-Mar-13

3-Apr-13

9-Apr-13

29-Dec-13

2-Jan-14

IFC

2,3,4,6,7,8,9,11

D-80-134A-068X

3 of 5

RGCP-472-T-QTR-822

05-Mar-13

12-Mar-13

3-Apr-13

9-Apr-13

29-Dec-13

2-Jan-14

IFC

2,3,4,6,7,8,9,11

D-80-134A-068X

4 of 5

RGCP-472-T-QTR-822

05-Mar-13

12-Mar-13

3-Apr-13

9-Apr-13

29-Dec-13

2-Jan-14

IFC

2,3,4,6,7,8,9,11

D-80-134A-068X

5 of 5

RGCP-472-T-QTR-822

05-Mar-13

12-Mar-13

3-Apr-13

9-Apr-13

29-Dec-13

2-Jan-14

IFC

2,3,4,6,7,8,9,11

10
11
12
13
14

Planting & Irrigation Works Demolition & Reinstatement of Planting


Work
Planting & Irrigation Works Demolition & Reinstatement of Planting
Work
Planting & Irrigation Works Demolition & Reinstatement of Planting
Work
Planting & Irrigation Works Demolition & Reinstatement of Planting
Work
Planting & Irrigation Works Demolition & Reinstatement of Planting
Work

15

General Layout for Civil Works

D-80-134A-103

1 of 15

RGCP-472-T-QTR-819

17-Jan-13

23-Jan-13

30-Jan-13

26-Nov-13

5-Dec-13

28-Dec-13

2-Jan-14

All Zones

16

General Layout for Civil Works

D-80-134A-103

2 of 15

RGCP-472-T-QTR-819

17-Jan-13

23-Jan-13

30-Jan-13

26-Nov-13

5-Dec-13

28-Dec-13

2-Jan-14

All Zones

17

General Layout for Civil Works

D-80-134A-103

3 of 15

RGCP-472-T-QTR-819

17-Jan-13

23-Jan-13

30-Jan-13

26-Nov-13

5-Dec-13

28-Dec-13

2-Jan-14

All Zones

18

General Layout for Civil Works

D-80-134A-103

4 of 15

RGCP-472-T-QTR-819

17-Jan-13

23-Jan-13

30-Jan-13

26-Nov-13

5-Dec-13

28-Dec-13

2-Jan-14

All Zones

19

General Layout for Civil Works

D-80-134A-103

5 of 15

RGCP-472-T-QTR-819

17-Jan-13

23-Jan-13

30-Jan-13

26-Nov-13

5-Dec-13

28-Dec-13

2-Jan-14

All Zones

20

General Layout for Civil Works

D-80-134A-103

6 of 15

RGCP-472-T-QTR-819

17-Jan-13

23-Jan-13

30-Jan-13

26-Nov-13

5-Dec-13

28-Dec-13

2-Jan-14

All Zones

MDR_Master Document Register

1 of 6

Updated on : 7/7/2014

EPC of Building External Areas Upgrade in Admin Area at Raslaffan -RGCP-472


DESIGN DRAWING SUBMITTAL LOG
LEGEND
Approved/IFC

Sl.
No.

Drawing Title

Drawing Number

No of
Sheets

QBEC Transmittal
Reference

Approved with
Comments

Reviewed W No
Comments

Issue for Review

Plan
Submission
date

Rev

Submit Date

Reviewed with
Comments

Submitted

Issue for Approval

Issued for Construction

As-Built
Zone

Reply Date

Approval
Status

Rev

Submit Date Reply Date

Approval
Status

Rev

Submit Date Reply Date

Approval
Status

Rev

Submit Date

Reply Date

Approval
Status

21

General Layout for Civil Works

D-80-134A-103

7 of 15

RGCP-472-T-QTR-819

17-Jan-13

23-Jan-13

30-Jan-13

26-Nov-13

5-Dec-13

28-Dec-13

2-Jan-14

All Zones

22

General Layout for Civil Works

D-80-134A-103

8 of 15

RGCP-472-T-QTR-819

17-Jan-13

23-Jan-13

30-Jan-13

26-Nov-13

5-Dec-13

28-Dec-13

2-Jan-14

All Zones

23

General Layout for Civil Works

D-80-134A-103

9 of 15

RGCP-472-T-QTR-819

17-Jan-13

23-Jan-13

30-Jan-13

26-Nov-13

5-Dec-13

28-Dec-13

2-Jan-14

All Zones

24

General Layout for Civil Works

D-80-134A-103

10 of 15

RGCP-472-T-QTR-819

17-Jan-13

23-Jan-13

30-Jan-13

26-Nov-13

5-Dec-13

28-Dec-13

2-Jan-14

All Zones

25

General Layout for Civil Works

D-80-134A-103

11 of 15

RGCP-472-T-QTR-819

17-Jan-13

23-Jan-13

30-Jan-13

26-Nov-13

5-Dec-13

28-Dec-13

2-Jan-14

All Zones

26

General Layout for Civil Works

D-80-134A-103

12 of 15

RGCP-472-T-QTR-819

17-Jan-13

23-Jan-13

30-Jan-13

26-Nov-13

5-Dec-13

28-Dec-13

2-Jan-14

All Zones

26

General Layout for Civil Works

D-80-134A-103

13 of 15

RGCP-472-T-QTR-819

17-Jan-13

23-Jan-13

30-Jan-13

26-Nov-13

5-Dec-13

28-Dec-13

2-Jan-14

All Zones

26

General Layout for Civil Works

D-80-134A-103

14 of 15

RGCP-472-T-QTR-819

17-Jan-13

23-Jan-13

30-Jan-13

26-Nov-13

5-Dec-13

28-Dec-13

2-Jan-14

All Zones

27

General Layout for Civil Works

D-80-134A-103

15 of 15

RGCP-472-T-QTR-819

17-Jan-13

23-Jan-13

30-Jan-13

26-Nov-13

5-Dec-13

28-Dec-13

2-Jan-13

All Zones

28

Under Ground Maintenance Complex(XK-10) Area Plot Plan

RG-2044

1 of 1

12-Nov-13

05-Dec-13

29

Walkway Shade Structure Layout &Details

D-80-134AX-56

1 TO 35

RGCP-472-T-QTR-832

28-Jan-14

All Zones
0

28-Jan-14

02-Feb-14

All Zones

LANDSCAPING AND CIVIL


1

General Landscape Layout

D-80-134A-102

1 of 3

RGCP-472-T-QTR-820

27-Feb-13

6-Mar-13

18-Apr-13

15-Apr-13

28-Dec-13

01-Dec-14

IFC

All Zones

General Landscape Layout

D-80-134A-102

2 of 3

RGCP-472-T-QTR-820

27-Feb-13

6-Mar-13

18-Apr-13

15-Apr-13

28-Dec-13

01-Dec-14

IFC

All Zones

General Landscape Layout

D-80-134A-102

3 of 3

RGCP-472-T-QTR-820

18-Apr-13

15-Apr-13

28-Dec-13

01-Dec-14

IFC

All Zones

General Layout for Walkways/ Pavement

D-80-134A-096

1 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

General Layout for Walkways/ Pavement

D-80-134A-096

2 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

General Layout for Walkways/ Pavement

D-80-134A-096

3 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

General Layout for Walkways/ Pavement

D-80-134A-096

4 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

General Layout for Walkways/ Pavement

D-80-134A-096

5 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

General Layout for Walkways/ Pavement

D-80-134A-096

6 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

10

General Layout for Walkways/ Pavement

D-80-134A-096

7 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

11

General Layout for Walkways/ Pavement

D-80-134A-096

8 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

12

General Layout for Walkways/ Pavement

D-80-134A-096

9 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

13

General Layout for Walkways/ Pavement

D-80-134A-096

10 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

14

General Layout for Walkways/ Pavement

D-80-134A-096

11 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

15

General Layout for Walkways/ Pavement

D-80-134A-096

12 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

16

General Layout for Walkways/ Pavement

D-80-134A-096

13 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

17

General Layout for Walkways/ Pavement

D-80-134A-096

14 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

18

General Layout for Walkways/ Pavement

D-80-134A-096

15 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

19

General Layout for Walkways/ Pavement

D-80-134A-096

16 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

20

General Layout for Walkways/ Pavement

D-80-134A-096

17 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

21

General Layout for Walkways/ Pavement

D-80-134A-096

18 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

22

General Layout for Walkways/ Pavement

D-80-134A-096

19 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

23

General Layout for Walkways/ Pavement

D-80-134A-096

20 of 20

RGCP-472-T-QTR-319

17-Jan-13

03-Feb-13

10-Feb-13

26-Mar-13

28-Mar-13

9-Apr-13

15-Apr-13

IFC

All Zones

24

General Layout For Planting

D-80-134A-068

1 of 7

RGCP-472-T-QTR-821

11-Apr-13

27-Feb-13

6-Mar-13

18-Apr-13

21-Apr-13

29-Dec-13

2-Jan-14

IFC

All Zones

25

General Layout For Planting

D-80-134A-068

2 of 7

RGCP-472-T-QTR-821

11-Apr-13

27-Feb-13

6-Mar-13

18-Apr-13

21-Apr-13

29-Dec-13

2-Jan-14

IFC

All Zones

26

General Layout For Planting

D-80-134A-068

3 of 7

RGCP-472-T-QTR-821

11-Apr-13

27-Feb-13

6-Mar-13

18-Apr-13

21-Apr-13

29-Dec-13

2-Jan-14

IFC

All Zones

27

General Layout For Planting

D-80-134A-068

4 of 7

RGCP-472-T-QTR-821

11-Apr-13

27-Feb-13

6-Mar-13

18-Apr-13

21-Apr-13

29-Dec-13

2-Jan-14

IFC

All Zones

28

General Layout For Planting

D-80-134A-068

5 of 7

RGCP-472-T-QTR-821

11-Apr-13

27-Feb-13

6-Mar-13

18-Apr-13

21-Apr-13

29-Dec-13

2-Jan-14

IFC

All Zones

29

General Layout For Planting

D-80-134A-068

6 of 7

RGCP-472-T-QTR-821

11-Apr-13

27-Feb-13

6-Mar-13

18-Apr-13

21-Apr-13

29-Dec-13

2-Jan-14

IFC

All Zones

30

General Layout For Planting

D-80-134A-068

7 of 7

RGCP-472-T-QTR-821

11-Apr-13

27-Feb-13

6-Mar-13

18-Apr-13

21-Apr-13

29-Dec-13

2-Jan-14

IFC

All Zones

31

Typical Planting Details

D-80-134A-069

1 of 4

RGCP-472-T-QTR-326

11-Apr-13

27-Feb-13

6-Mar-13

26-Mar-13

28-Mar-13

21-Apr-13

28-Apr-13

IFC

All Zones

32

Typical Planting Details

D-80-134A-069

2 of 4

RGCP-472-T-QTR-824

11-Apr-13

27-Feb-13

6-Mar-13

26-Mar-13

28-Mar-13

2-Jan-14

7-Jan-14

IFC

All Zones

33

Typical Planting Details

D-80-134A-069

3 of 4

RGCP-472-T-QTR-326

11-Apr-13

27-Feb-13

6-Mar-13

26-Mar-13

28-Mar-13

21-Apr-13

28-Apr-13

IFC

All Zones

34

Typical Planting Details

D-80-134A-069

4 of 4

RGCP-472-T-QTR-326

11-Apr-13

27-Feb-13

6-Mar-13

26-Mar-13

28-Mar-13

21-Apr-13

28-Apr-13

IFC

All Zones

35

Entrance Plaza - Detailed Plan

D-80-134A-108

1 of 1

RGCP-472-T-QTR-454

21-Jan-13

21-Feb-13

28-Feb-13

13-May-13

16-May-13

25-May-13

28-May-13

IFC

36

Entrance Plaza - Detail Section and Details

D-80-134A-109

1 of 2

RGCP-472-T-QTR-679

21/Jan/13

21-Feb-13

28-Feb-13

18-Jul-13

21-Jul-13

18-Sep-13

03-Oct-13

IFC

MDR_Master Document Register

2 of 6

Updated on : 7/7/2014

EPC of Building External Areas Upgrade in Admin Area at Raslaffan -RGCP-472


DESIGN DRAWING SUBMITTAL LOG
LEGEND
Approved/IFC

Sl.
No.

Drawing Title

Drawing Number

No of
Sheets

QBEC Transmittal
Reference

Approved with
Comments

Reviewed W No
Comments

Issue for Review

Plan
Submission
date

Rev

Submit Date

Reviewed with
Comments

Submitted

Issue for Approval

Issued for Construction

As-Built
Zone

Reply Date

Approval
Status

Rev

Submit Date Reply Date

Approval
Status

Rev

Submit Date Reply Date

Approval
Status

Rev

Submit Date

Reply Date

Approval
Status

37

Entrance Plaza - Detail Section and Details

D-80-134A-109

2 of 2

RGCP-472-T-QTR-679

21/Jan/13

21-Feb-13

28-Feb-13

18-Jul-13

21-Jul-13

18-Sep-13

03-Oct-13

IFC

38

Water Feature Details

D-80-134A-110

1 of 1

RGCP-472-T-QTR-754

27-Jan-13

21-Feb-13

27-Feb-13

18-Sep-13

23-Sep-13

28-Oct-13

29-Oct-13

IFC

39

Civil Work Fountain Plan Details

D-80-134A-192

1 of 2

RGCP-472-T-QTR-686

27-Jan-13

21-Feb-13

27-Feb-13

11-Sep-13

15-Sep-13

24-Sep-13

02-Oct-13

IFC

40

Civil Work Fountain Plan Details

D-80-134A-192

2 of 2

RGCP-472-T-QTR-686

27-Jan-13

21-Feb-13

27-Feb-13

11-Sep-13

15-Sep-13

24-Sep-13

02-Oct-13

IFC

41

Bus Plaza in Front of Admin (Typ. Of 2 noc.)-plan section and details

D-80-134A-194

1 of 1

RGCP-472-T-QTR-270

24-Jan-13

11-Feb-13

21-Feb-13

5-Mar-13

12-Mar-13

26-Mar-13

28-Mar-13

IFC

42

Bus plaza near XK-26-Plan, Section and Details

D-80-134A-195

1 of 1

RGCP-472-T-QTR-271

21-Jan-13

11-Feb-13

19-Feb-13

5-Mar-13

12-Mar-13

26-Mar-13

9-Apr-13

IFC

All Zones

43

Mosque Plaza Detail -Plan ,Section and Details

D-80-134A-197

1 of 1

RGCP-472-T-QTR-504

28-Jan-13

12-May-13

14-May-13

25-May-13

28-May-13

10-Jun-13

11-Jun-13

IFC

44

Open Parking Area 1 at Admin - Detail-Plan

D-80-134A-090

1 of 1

RGCP-472-T-QTR-432

24-Jan-13

17-Feb-13

21-Feb-13

13-Mar-13

20-Mar-13

19-May-13

3-Apr-13

IFC

45

Open Parking Area 1 at Admin - Sections

D-80-134A-091

1 of 1

RGCP-472-T-QTR-433

24-Jan-13

17-Feb-13

13-Mar-13

20-Mar-13

19-May-13

22/5/2013

BY EMAIL

46

Parking Area 2 at XK-10-Detail Plan and Sections

D-80-134A-093

1 of 1

RGCP-472-T-QTR-434

24-Jan-13

17-Feb-13

24-Feb-13

13-Mar-13

20-Mar-13

19-May-13

14-Apr-13

IFC

47

Parking Area 3 at XK-10-Detail Plan and Sections

D-80-134A-095

1 of 1

RGCP-472-T-QTR-321

24-Jan-13

17-Feb-13

24-Feb-13

13-Mar-13

20-Mar-13

9-Apr-13

11-Apr-13

IFC

19

48

Civil Work Structural details Sheet 1 to 2

D-80-134A-097

1 of 2

RGCP-472-T-QTR-623

22-Jul-13

22-Jul-13

24-Jul-13

24-Aug-13

26-Aug-13

29-Aug-13

08-Sep-13

IFC

49

Civil Work Structural details Sheet 2 to 2

D-80-134A-097

2 of 2

RGCP-472-T-QTR-623

22-Jul-13

22-Jul-13

24-Jul-13

24-Aug-13

26-Aug-13

29-Aug-13

08-Sep-13

IFC

50

Courtyard Detail-Plan, Section

D-80-134A-098

1 of 1

RGCP-472-T-QTR-267

24-Jan-13

11-Feb-13

18-Feb-13

5-Mar-13

12-Mar-13

26-Mar-13

28-Mar-13

IFC

51

XK-03Plaza Detail -Plan ,Section and Details

D-80-134A-099

1 of 1

RGCP-472-T-QTR-268

24-Jan-13

11-Feb-13

18-Feb-13

5-Mar-13

12-Mar-13

26-Mar-13

28-Mar-13

IFC

17

52

XK-32 Ware House Plaza Detail - Plan, Section and Details

D-80-134A-111A

1 of 1

RGCP-472-T-QTR-269

24-Jan-13

11-Feb-13

18-Feb-13

5-Mar-13

12-Mar-13

26-03-13

28-Mar-13

IFC

11

53

General Civil Works Details

D-80-134A-104

1 of 3

RGCP-472-T-QTR-524

15-Jan-13

03/Feb/13

28-Feb-13

13-May-13

20-May-13

23-Jun-13

14-Aug-13

IFC

All Zones

54

General Civil Works Details

D-80-134A-104

2 of 3

RGCP-472-T-QTR-524

15-Jan-13

03/Feb/13

28-Feb-13

13-May-13

20-May-13

23-Jun-13

14-Aug-13

IFC

All Zones

55

General Civil Works Details

D-80-134A-104

3 of 3

RGCP-472-T-QTR-524

15-Jan-13

03/Feb/13

28/Feb/13

13-May-13

20-May-13

23-Jun-13

14-Aug-13

IFC

All Zones

56

Reinstatement works details

D-80-134A-106

1 of 1

RGCP-472-T-QTR-609

24-Jan-13

09-Apr-13

11-Apr-13

18-Apr-13

21-Apr-13

27-Aug-13

03-Sep-13

IFC

All Zones

57

Foundation for signage

D-80-134A-081

1 of 3

RGCP-472-T-QTR-569

19/Jan/13

03/Feb/13

10/Feb/13

4-Jul-13

11-Jul-13

27-Jul-13

01-Aug-13

IFC

All Zones

58

Foundation for signage

D-80-134A-081

2 of 3

RGCP-472-T-QTR-569

19/Jan/13

03/Feb/13

10/Feb/13

4-Jul-13

11-Jul-13

27-Jul-13

01-Aug-13

IFC

All Zones

59

Foundation for signage

D-80-134A-081

3 of 3

RGCP-472-T-QTR-569

19/Jan/13

03/Feb/13

10/Feb/13

4-Jul-13

11-Jul-13

27-Jul-13

01-Aug-13

IFC

All Zones

60

Water Tank General Arrangement

D-80-134A-121

1 of 1

RGCP-472-T-QTR-519

16-Jun-13

16-Jun-13

18-Jun-13

29-Jul-13

IFC

61

Civil Works water tank structural detail

D-80-134A-122

1 of 1

RGCP-472-T-QTR-849

23-Jan-13

30-Jan-13

26-Aug-13

06-Oct-13

11-Mar-14

11-Mar-14

62

Civil works Entrance Plaza Tile Layout

D-80-134AX-055

1 of 3

RGCP-472-T-QTR-753

8-Oct-13

10-Oct-13

28/Oct/13

29-Oct-13

IFC

63

Civil works Entrance Plaza Tile Layout

D-80-134AX-055

2 of 3

RGCP-472-T-QTR-753

8-Oct-13

10-Oct-13

28/Oct/13

29-Oct-13

IFC

64

Civil works Entrance Plaza Tile Layout

D-80-134AX-055

3 of 3

RGCP-472-T-QTR-753

8-Oct-13

10-Oct-13

28/Oct/13

29-Oct-13

IFC

65

Civil Works Fountain Structural Detail sheet 1of 6

D-80-134A-470A

1 o f6

RGCP-472-T-QTR-917

13-May-14

26-May-14

19-Jun-14

23-Jun-14

66

Civil Works Fountain Structural Detail sheet 2 of 6

D-80-134A-470A

2 of 6

RGCP-472-T-QTR-917

13-May-14

26-May-14

19-Jun-14

23-Jun-14

67

Civil Works Fountain Structural Detail sheet 3of 6

D-80-134A-470A

3 of 6

RGCP-472-T-QTR-917

13-May-14

26-May-14

19-Jun-14

23-Jun-14

68

Civil Works Fountain Structural Detail sheet 4 to 6

D-80-134A-470A

4 of 6

RGCP-472-T-QTR-917

13-May-14

26-May-14

19-Jun-14

23-Jun-14

69

Civil Works Fountain Structural Detail sheet 5 to 6

D-80-134A-470A

5 of 6

RGCP-472-T-QTR-917

13-May-14

26-May-14

19-Jun-14

23-Jun-14

69

Civil Works Fountain Structural Detail sheet 6 to 6

D-80-134A-470A

6 of 6

RGCP-472-T-QTR-917

19-Jun-14

23-Jun-14

69

Bus Plaza Shade Structure near XK-26 modification of foundation in


Grid B-1 and B-3

D-80-134AX-60

RGCP-472-T-QTR-880

22-Apr-14

24-Apr-14

69

Civil Works-V-Ditch Cover Slab Details

D-80-134AX-61

RGCP-472-T-QTR-901

24-Apr-14

22-May-14

28-May-14

06-Jun-14

SHADES
1

Bus Plaza Shade Structure -Plan, Elevation and Details

D-80-134A-102A

1 of 3

RGCP-472-T-QTR-689

21-Aug-13

21-Aug-13

27-Aug-13

05-Sep-13

08-Sep-13

24-Sep-13

25-Sep-13

IFC

All Zones

Bus Plaza Shade Structure -Plan, Elevation and Details

D-80-134A-102A

2 of 3

RGCP-472-T-QTR-689

21-Aug-13

21-Aug-13

27-Aug-13

05-Sep-13

08-Sep-13

24-Sep-13

25-Sep-13

IFC

All Zones

Bus Plaza Shade Structure -Plan, Elevation and Details

D-80-134A-102A

3 of 3

RGCP-472-T-QTR-689

21-Aug-13

21-Aug-13

27-Aug-13

05-Sep-13

08-Sep-13

24-Sep-13

25-Sep-13

IFC

All Zones

Bus Plaza Shade Structure Near XK-26 -Plan, Elevation and Details

D-80-134A-103A

1 of 3

RGCP-472-T-QTR-719

18-Aug-13

18-Aug-13

22-Aug-13

24-Sep-13

26-Sep-13

5-Oct-13

6-Oct-13

IFC

All Zones

Bus Plaza Shade Structure Near XK-26 -Plan, Elevation and Details

D-80-134A-103A

2 of 3

RGCP-472-T-QTR-719

18-Aug-13

18-Aug-13

22-Aug-13

24-Sep-13

26-Sep-13

5-Oct-13

6-Oct-13

IFC

All Zones

Bus Plaza Shade Structure Near XK-26 -Plan, Elevation and Details

D-80-134A-103A

3 of 3

RGCP-472-T-QTR-719

18-Aug-13

18-Aug-13

22-Aug-13

24-Sep-13

26-Sep-13

5-Oct-13

6-Oct-13

IFC

All Zones

Mosque Plaza Shade Structure - Plan, Elevation and Details

D-80-134A-104A

1 of 2

RGCP-472-T-QTR-690

5-Sep-13

5-Sep-13

9-Sep-13

16-Sep-13

19-Sep-13

24-Sep-13

25-Sep-13

IFC

All Zones

Mosque Plaza Shade Structure - Plan, Elevation and Details

D-80-134A-104A

2 of 2

RGCP-472-T-QTR-690

5-Sep-13

5-Sep-13

9-Sep-13

16-Sep-13

19-Sep-13

24-Sep-13

25-Sep-13

IFC

All Zones

XK-03Plaza Shade Structure -Plan , Elevation and Details

D-80-134A-105A

1 of 2

RGCP-472-T-QTR-691

03-Apr-13

9-Apr-13

12-Sep-13

15-Sep-13

24-Sep-13

25-Sep-13

IFC

All Zones

10

XK-03Plaza Shade Structure -Plan , Elevation and Details

D-80-134A-105A

2 of 2

RGCP-472-T-QTR-691

03-Apr-13

9-Apr-13

12-Sep-13

15-Sep-13

24-Sep-13

25-Sep-13

IFC

All Zones

11

XK-32 Warehouse Plaza Shade Structure -Plan ,Elevation and Details

D-80-134A-106A

1 of 2

RGCP-472-T-QTR-692

03-Apr-13

9-Apr-13

29-Aug-13

11-Sep-13

24-Sep-13

25-Sep-13

IFC

All Zones

MDR_Master Document Register

3 of 6

Updated on : 7/7/2014

EPC of Building External Areas Upgrade in Admin Area at Raslaffan -RGCP-472


DESIGN DRAWING SUBMITTAL LOG
LEGEND
Approved/IFC

Sl.
No.

12
13
14

Drawing Title

XK-32 Warehouse Plaza Shade Structure -Plan ,Elevation and Details


Walkway shade structure (Type 1) typical plan, elevation section and
details
Walkway shade structure (Type 2) typical plan, elevation section and
details

Drawing Number

No of
Sheets

QBEC Transmittal
Reference

Plan
Submission
date

Approved with
Comments

Reviewed W No
Comments

Issue for Review

Reviewed with
Comments

Submitted

Issue for Approval

Issued for Construction

As-Built
Zone

Rev

Submit Date

Reply Date

Approval
Status

Rev

Submit Date Reply Date

Approval
Status

Rev

Submit Date Reply Date

Approval
Status

Rev

Submit Date

Reply Date

Approval
Status

D-80-134A-106A

2 of 2

RGCP-472-T-QTR-692

03-Apr-13

9-Apr-13

29-Aug-13

11-Sep-13

24-Sep-13

25-Sep-13

IFC

All Zones

D-80-134A-107A

1 of 3

RGCP-472-T-QTR-743

03-Apr-13

9-Apr-13

07-Oct-13

10-Oct-13

22-Oct-13

27-Oct-13

IFC

All Zones

D-80-134A-107A

2 of 3

RGCP-472-T-QTR-743

03-Apr-13

9-Apr-13

07-Oct-13

10-Oct-13

22-Oct-13

27-Oct-13

IFC

All Zones

07-Oct-13

10-Oct-13

22-Oct-13

27-Oct-13

IFC

15

Walkway shade stuctures typical plan, elevation section and details

D-80-134A-107A

3 of 3

RGCP-472-T-QTR-743

03-Apr-13

9-Apr-13

16

Parking Area 2 at XK-10 - Shade Structure -Plan , Elevation and Details

D-80-134A-108A

1 of 2

RGCP-472-T-QTR-693

16-May-13

21-May-13

05-Sep-13

16-Sep-13

24-Sep-13

25-Sep-13

IFC

All Zones

17

Parking Area 2 at XK-10 - Shade Structure -Plan , Elevation and Details

D-80-134A-108A

2 of 2

RGCP-472-T-QTR-693

16-May-13

21-May-13

05-Sep-13

16-Sep-13

24-Sep-13

25-Sep-13

IFC

All Zones

SIGNAGE AND ROAD MARKING


1

General Layout for signage location 1

D-80-134A-075

1 of 9

RGCP-472-T-QTR-479

31-Mar-13

4-Apr-13

7-May-13

12-May-13

2-Jun-13

11-Jun-13

IFC

All Zones

General Layout for signage location 2

D-80-134A-075

2 of 9

RGCP-472-T-QTR-479

31-Mar-13

4-Apr-13

7-May-13

12-May-13

2-Jun-13

11-Jun-13

IFC

All Zones

General Layout for signage location 3

D-80-134A-075

3 of 9

RGCP-472-T-QTR-479

31-Mar-13

4-Apr-13

7-May-13

12-May-13

2-Jun-13

11-Jun-13

IFC

All Zones

General Layout for signage location 4

D-80-134A-075

4 of 9

RGCP-472-T-QTR-479

31-Mar-13

4-Apr-13

7-May-13

12-May-13

2-Jun-13

11-Jun-13

IFC

All Zones

General Layout for signage location 5

D-80-134A-075

5 of 9

RGCP-472-T-QTR-479

31-Mar-13

4-Apr-13

7-May-13

12-May-13

2-Jun-13

11-Jun-13

IFC

All Zones

General Layout for signage location 6

D-80-134A-075

6 of 9

RGCP-472-T-QTR-479

31-Mar-13

4-Apr-13

7-May-13

12-May-13

2-Jun-13

11-Jun-13

IFC

All Zones

General Layout for signage location 7

D-80-134A-075

7 of 9

RGCP-472-T-QTR-479

31-Mar-13

4-Apr-13

7-May-13

12-May-13

2-Jun-13

11-Jun-13

IFC

All Zones

General Layout for signage location 8

D-80-134A-075

8 of 9

RGCP-472-T-QTR-479

31-Mar-13

4-Apr-13

7-May-13

12-May-13

2-Jun-13

11-Jun-13

IFC

All Zones

General Layout for signage location 9

D-80-134A-075

9 of 9

RGCP-472-T-QTR-479

31-Mar-13

4-Apr-13

7-May-13

12-May-13

2-Jun-13

11-Jun-13

IFC

All Zones

10

General Layout for Traffic Signage

D-80-134A-076

1 of 2

RGCP-472-T-QTR-782

21-Apr-13

22-Apr-13

3-Jun-13

10-Jun-13

23-Nov-13

26-Nov-13

IFC

All Zones

11

General Layout for Traffic Signage

D-80-134A-076

2 of 2

RGCP-472-T-QTR-782

21-Apr-13

22-Apr-13

3-Jun-13

10-Jun-13

23-Nov-13

26-Nov-13

IFC

All Zones

12

Typical Signage Detail - Plan, Elevation and Details

D-80-134A-077

1 of 3

RGCP-472-T-QTR-480

31-Mar-13

9-Apr-13

7-May-13

12-May-13

2-Jun-13

10-Jun-13

IFC

All Zones

13

Typical Signage Detail - Plan, Elevation and Details

D-80-134A-077

2 of 3

RGCP-472-T-QTR-480

31-Mar-13

9-Apr-13

7-May-13

12-May-13

2-Jun-13

10-Jun-13

IFC

All Zones

14

Typical Signage Detail - Plan, Elevation and Details

D-80-134A-077

3 of 3

RGCP-472-T-QTR-480

31-Mar-13

9-Apr-13

7-May-13

12-May-13

2-Jun-13

10-Jun-13

IFC

All Zones

15

Schedule of Signs

D-80-134A-078

1 of 1

RGCP-472-T-QTR-482

31-Mar-13

9-Apr-13

7-May-13

15-May-13

2-Jun-13

10-Jun-13

IFC

All Zones

16

Traffic Signage Details

D-80-134A-079

1 of 3

RGCP-472-T-QTR-484

31-Mar-13

9-Apr-13

7-May-13

12-May-13

3-Jun-13

10-Jun-13

IFC

All Zones

17

Traffic Signage Details

D-80-134A-079

2 of 3

RGCP-472-T-QTR-484

31-Mar-13

9-Apr-13

7-May-13

12-May-13

3-Jun-13

10-Jun-13

IFC

All Zones

18

Traffic Signage Details

D-80-134A-079

3 of 3

RGCP-472-T-QTR-484

31-Mar-13

9-Apr-13

7-May-13

12-May-13

3-Jun-13

10-Jun-13

IFC

All Zones

19

Traffic Signage Details

D-80-134A-079

4 of 4

RGCP-472-T-QTR-783

31-Mar-13

9-Apr-13

3-Jun-13

10-Jun-13

24-Nov-13

26-Nov-13

IFC

All Zones

20

Road Marking Details

D-80-134A-140

1 of 3

RGCP-472-T-QTR-513

03-Jun-13

4-Jun-13

10-Jun-13

11-Jun-13

16-Jun-13

16-Jun-13

IFC

All Zones

21

Road Marking Details

D-80-134A-140

2 of 3

RGCP-472-T-QTR-513

03-Jun-13

4-Jun-13

10-Jun-13

11-Jun-13

16-Jun-13

16-Jun-13

IFC

22

Road Marking Details

D-80-134A-140

3 of 3

RGCP-472-T-QTR-513

03-Jun-13

4-Jun-13

10-Jun-13

11-Jun-13

16-Jun-13

16-Jun-13

IFC

IRRIGATION
1

Irrigation Main line (Primary and Secondary) layout

D-80-134A-002A

1 of 5

RGCP-472-T-QTR-435

31-Mar-13

18-Apr-13

28-Apr-13

12-May-13

19-May-13

5-Jun-13

IFC

All Zones

Irrigation Main line (Primary and Secondary) layout

D-80-134A-003A

2 of 5

RGCP-472-T-QTR-435

31-Mar-13

18-Apr-13

28-Apr-13

12-May-13

19-May-13

5-Jun-13

IFC

All Zones

Irrigation Main line (Primary and Secondary) layout

D-80-134A-004A

3 of 5

RGCP-472-T-QTR-435

31-Mar-13

18-Apr-13

28-Apr-13

12-May-13

19-May-13

5-Jun-13

IFC

All Zones

Irrigation Main line (Primary and Secondary) layout

D-80-134A-005A

4 of 5

RGCP-472-T-QTR-435

31-Mar-13

18-Apr-13

28-Apr-13

12-May-13

19-May-13

5-Jun-13

IFC

All Zones

Irrigation Main line (Primary and Secondary) layout

D-80-134A-006A

5 of 5

RGCP-472-T-QTR-435

31-Mar-13

18-Apr-13

28-Apr-13

12-May-13

19-May-13

5-Jun-13

IFC

All Zones

Irrigation Layout lateral Lines

D-80-134A-007A

1 of 5

RGCP-472-T-QTR-436

31-Mar-13

18-Apr-13

28-Apr-13

6-May-13

19-May-13

23-May-13

IFC

All Zones

Irrigation Layout lateral Lines

D-80-134A-008A

2 of 5

RGCP-472-T-QTR-436

31-Mar-13

18-Apr-13

28-Apr-13

6-May-13

19-May-13

23-May-13

IFC

All Zones

Irrigation Layout lateral Lines

D-80-134A-009A

3 of 5

RGCP-472-T-QTR-436

31-Mar-13

18-Apr-13

28-Apr-13

6-May-13

19-May-13

23-May-13

IFC

All Zones

Irrigation Layout lateral Lines

D-80-134A-010A

4 of 5

RGCP-472-T-QTR-436

31-Mar-13

18-Apr-13

28-Apr-13

6-May-13

19-May-13

23-May-13

IFC

All Zones

10

Irrigation Layout lateral Lines

D-80-134A-011A

5 of 5

RGCP-472-T-QTR-436

31-Mar-13

18-Apr-13

28-Apr-13

6-May-13

19-May-13

23-May-13

IFC

All Zones

11

Solenoid Valve Schedule

D-80-134A-012A

1 of 1

RGCP-472-T-QTR-445

31-Mar-13

18-Apr-13

28-Apr-13

6-May-13

21-May-13

23-May-13

IFC

All Zones

12

Piping & Instrumentation Diagram - irrigation & Landscape

D-80-134A-013A

1 of 1

RGCP-472-T-QTR-700

31-Mar-13

2-Apr-13

17-Aug-13

3-Sep-13

24-Sep-13

2-Oct-13

IFC

All Zones

13

Irrigation Typical Details

D-80-134A-022

1 of 3

RGCP-472-T-QTR-446

31-Mar-13

18-Apr-13

28-Apr-13

7-May-13

21-May-13

23-May-13

IFC

All Zones

14

Irrigation Typical Details

D-80-134A-022

2 of 3

RGCP-472-T-QTR-446

31-Mar-13

18-Apr-13

28-Apr-13

7-May-13

21-May-13

23-May-13

IFC

All Zones

15

Irrigation Typical Details

D-80-134A-022

3 of 3

RGCP-472-T-QTR-446

31-Mar-13

18-Apr-13

28-Apr-13

7-May-13

21-May-13

23-May-13

IFC

All Zones

16

General Irrigation Control Wiring Layout

D-80-134A-024A

1 of 5

RGCP-472-T-QTR-481

12-May-13

16-May-13

2-Jun-13

30-Jun-13

IFC

All Zones

17

General Irrigation Control Wiring Layout

D-80-134A-025A

2 of 5

RGCP-472-T-QTR-481

12-May-13

16-May-13

2-Jun-13

30-Jun-13

IFC

All Zones

18

General Irrigation Control Wiring Layout

D-80-134A-026A

3 of 5

RGCP-472-T-QTR-481

12-May-13

16-May-13

2-Jun-13

30-Jun-13

IFC

All Zones

MDR_Master Document Register

4 of 6

Updated on : 7/7/2014

EPC of Building External Areas Upgrade in Admin Area at Raslaffan -RGCP-472


DESIGN DRAWING SUBMITTAL LOG
LEGEND
Approved/IFC

Sl.
No.

Drawing Title

Drawing Number

No of
Sheets

QBEC Transmittal
Reference

Plan
Submission
date

Approved with
Comments

Reviewed W No
Comments

Issue for Review

Reviewed with
Comments

Submitted

Issue for Approval

Issued for Construction

As-Built
Zone

Rev

Submit Date

Reply Date

Approval
Status

Rev

Submit Date Reply Date

Approval
Status

Rev

Submit Date Reply Date

Approval
Status

Rev

Submit Date

Reply Date

Approval
Status

19

General Irrigation Control Wiring Layout

D-80-134A-027A

4 of 5

RGCP-472-T-QTR-481

12-May-13

16-May-13

2-Jun-13

30-Jun-13

IFC

All Zones

20

General Irrigation Control Wiring Layout

D-80-134A-028A

5 of 5

RGCP-472-T-QTR-481

12-May-13

16-May-13

2-Jun-13

30-Jun-13

IFC

All Zones

21

Controller Schematic

D-80-134A-031A

1 of 1

RGCP-472-T-QTR-799

03-Jun-13

11-Jun-13

27-Oct-13

28-Oct-13

16-Dec-13

24-Dec-13

IFC

All Zones

22

Hydraulic Calculation Steady Condition

C-80-134A-221

1 of 1

RGCP-472-T-QTR-716

28-Apr-13

7-May-13

02-Jun-13

10-Jun-13

5-Oct-13

20-Oct-13

IFC

All Zones

23

General Irrigation Tie in Point list

S-80-134A-011

1 of 1

RGCP-472-T-QTR-717

02-Jun-13

4-Jun-13

11-Jul-13

21-Aug-13

5-Oct-13

27-Oct-13

IFC

All Zones

PLUMBING
1

Water Feature Process Flow Diagram

D-80-134A-468

1 of 2

RGCP-472-T-QTR-859

10-Mar-13

20-Mar-13

16-Dec-13

24-Dec-13

24-Mar-13

02-Apr-13

REGENCY TO SUBMIT

Water Feature Process Flow Diagram

D-80-134A-468

2 of 2

RGCP-472-T-QTR-859

10-Mar-13

20-Mar-13

16-Dec-13

24-Dec-13

24-Mar-13

02-Apr-13

REGENCY TO SUBMIT

Water Feature - cause and effect diagram

D-80-134A-469

1 of 1

RGCP-472-T-QTR-417

16-May-13

29-May-13

ACE TO SUBMIT

Water Feature -Plumbing Schematic


Diagram/Piping System (drainage supply)

D-80-134A-470

1 of 1

RGCP-472-T-QTR-858

10-Mar-13

20-Mar-13

16-Dec-13

26-Dec-13

IFC

Water Feature logic, startup, shutdown procedure

S-80-134A-400

1 of 1

RGCP-472-T-QTR-804

14-May-13

21-May-13

16-Dec-13

24-Dec-13

REGENCY TO SUBMIT

Water Feature logic, startup, shutdown procedure

S-80-134A-401

1 of 1

RGCP-472-T-QTR-805

16-May-13

21-May-13

16-Dec-13

24-Dec-13

REGENCY TO SUBMIT

Water Feature logic, startup, shutdown procedure

S-80-134A-402

1 of 1

RGCP-472-T-QTR-775

16-May-13

22-May-13

18-Nov-13

11-Dec-13

ACE TO SUBMIT

Water Feature -Plumbing layout (water supply)

D-80-134A-471A

1 of 3

RGCP-472-T-QTR-877

10-Mar-13

20-Mar-13

24-Mar-14

30-Mar-14

22-Mar-14

19-May-14

IFC

Water Feature -Plumbing layout (water supply)

D-80-134A-471A

2 of 3

RGCP-472-T-QTR-877

10-Mar-13

20-Mar-13

24-Mar-14

30-Mar-14

22-Mar-14

19-May-14

IFC

10

Water Feature -Plumbing layout (water supply)

D-80-134A-471A

3 of 3

RGCP-472-T-QTR-877

10-Mar-13

20-Mar-13

24-Mar-14

30-Mar-14

22-Mar-14

19-May-14

IFC

11

Water Feature Plumbing Layout work Plan

D-80-134A-472A

1 of 2

RGCP-472-T-QTR-878

10-Mar-13

18-Apr-13

24-Mar-14

30-Mar-14

22-Mar-14

19-May-14

IFC

12

Water Feature Plumbing Layout work Plan

D-80-134A-472A

2 of 2

RGCP-472-T-QTR-878

10-Mar-13

18-Apr-13

24-Mar-14

30-Mar-14

22-Mar-14

19-May-14

IFC

13

Water Feature - corrdination with underground utilities (layout,


sections)

D-80-134A-473

RGCP-472-T-QTR-488

10-Mar-13

20-Mar-13

25-May-13

30-May-13

3-Jun-13

4-Jun-13

IFC

14

Water Feature Plumbing Works Section/Details

D-80-134A-474

RGCP-472-T-QTR-518

19/Jun/13

07/Aug/13

15

Water Feature - pump room (layout, section)

D-80-134A-475

RGCP-472-T-QTR-902

10-Mar-13

20-Mar-13

16

Water Feature - pump room layout(Pipe sleeves)

D-80-134A-475A

RGCP-472-T-QTR-918

17

Water Feature - pump room (layout, section)

D-80-134A-476

RGCP-472-T-QTR-800

18

Water Feature - pump room Elevation(Pipe sleeves)

D-80-134A-476A

RGCP-472-T-QTR-919

19

Water Feature - process description

S-80-134A-404

RGCP-472-T-QTR-806

10-Mar-13

20-Mar-13

20

Water Feature - balancing tank data sheet

S-80-134A-405

RGCP-472-T-QTR-810

10-Mar-13

24-Mar-13

24

Water Feature Sculpture Details

D-80-134AX-058

RGCP-472-T-QTR-846

11-Mar-14

13-Mar-14

25

Enclosure Structure Plan,Sections&Details

D-80-134AX-057

RGCP-472-T-QTR-881

18-Mar-14

20-Mar-14

26

Water Feature Plumbing Works Layout Plan(Water Supply)

D-80-134A-470C

RGCP-472-T-QTR-903

28-May-14

11-Jun-14

10-Mar-13

20-Mar-13

24-Mar-14

31-Mar-14

IFC

ACE TO SUBMIT

REGENCY TO SUBMIT

2
2

16-Dec-13

24-Dec-13

28-May-14

17-Jun-14

REGENCY TO SUBMIT

16-Dec-13

26-Dec-13

19-Jun-14

25-Jun-14

REGENCY TO SUBMIT

07-Jul-13

7-Jul-13

16-Dec-13

16-Dec-13

26-Dec-13

19-Jun-14

25-Jun-14

REGENCY TO SUBMIT

16-Dec-13

02-Jan-13

WITH RASGAS

ACE TO SUBMIT

WITH RASGAS

18-Jun-13

26-Jun-13

16-Dec-13

26-Dec-13

01-Apr-14

02-Apr-14

24-Apr-14

09-Jun-14

By Email

INSTRUMENT
1

Water Feature P&I Diagram

D-80-134A-655

1 of 1

RGCP-472-T-QTR-219

10-Mar-13

20-Mar-13

All Zones

ELECTRICAL
1

LPP- XK-011 Panel Schedule

D-80-134A-274

1 to 3

RGCP-472-T-QTR-0725

19-Feb-13

20-Mar-13

07-Oct-13

10-Oct-13

IFC

LPP- XK-021 Panel Schedule

D-80-134A-274

1 to 3

RGCP-472-T-QTR-0725

19-Feb-13

20-Mar-13

07-Oct-13

10-Oct-13

IFC

LPP- XK-101 Panel Schedule

D-80-134A-274

1 to 3

RGCP-472-T-QTR-0725

07-Oct-13

10-Oct-13

IFC

Electrical Works -Single Line Diagram

D-80-134A-275

1 of 1

RGCP-472-T-QTR-0726

27-Jan-13

05-May-13

12-May-13

07-Oct-13

20-Oct-13

IFC

All Zones

General Notes for Electrical Works

D-80-134A-280

1 of 1

RGCP-472-T-QTR-587

27/Jan/13

19-Feb-13

24-Feb-13

11-Aug-13

23-Sep-13

IFC

All Zones

Electrical Load List

D-80-134A-286

1 of 1

RGCP-472-T-QTR-581

05-May-13

08-May-13

11-Aug-13

23-Sep-13

IFC

Standard Electrical Installation Drawing

D-80-134A-287

1 of 4

RGCP-472-T-QTR-0541

27-Jan-13

23-Apr-13

24-Apr-13

5-Nov-13

6-Nov-13

IFC

All Zones

Standard Electrical Installation Drawing

D-80-134A-287

2 of 4

RGCP-472-T-QTR-0541

27-Jan-13

23-Apr-13

24-Apr-13

5-Nov-13

6-Nov-13

IFC

All Zones

Standard Electrical Installation Drawing

D-80-134A-287

3 of 4

RGCP-472-T-QTR-0541

27-Jan-13

23-Apr-13

24-Apr-13

5-Nov-13

6-Nov-13

IFC

All Zones

10

Standard Electrical Installation Drawing

D-80-134A-287

4 of 4

RGCP-472-T-QTR-0541

27-Jan-13

23-Apr-13

24-Apr-13

5-Nov-13

6-Nov-13

IFC

All Zones

11

Lighting Wiring Diagram XK-011 Zone 1

D-80-134A-288

1 of 3

RGCP-472-T-QTR-724

27-Jan-13

06-May-13

12-May-13

16-Jun-13

24-Jun-13

07-Oct-13

10-Oct-13

IFC

All Zones

12

Lighting Wiring DiagramXK21 - Zone 4

D-80-134A-288

2 of 3

RGCP-472-T-QTR-724

27-Jan-13

06-May-13

12-May-13

16-Jun-13

24-Jun-13

07-Oct-13

10-Oct-13

IFC

All Zones

13

Lighting Wiring Diagram XK101 Zone 19

D-80-134A-288

3 of 3

RGCP-472-T-QTR-724

27-Jan-13

06-May-13

12-May-13

16-Jun-13

24-Jun-13

07-Oct-13

10-Oct-13

IFC

All Zones

14

Electrical Works - General Layout for Lighting (Zone 1 & Zone 10)

D-80-134A-289

1 of 1

RGCP-472-T-QTR-766

21-Apr-13

23-Apr-13

25-May-13

29-May-13

13-Nov-13

17-Nov-13

IFC

All Zones

15

Electrical Cable Route Layout XK-01 / XK-02

D-80-134A-290

1 of 1

RGCP-472-T-QTR-0721

19-Feb-13

24-Feb-13

9-Jun-13

11-Jun-13

27-Nov-13

27-Nov-13

IFC

All Zones

MDR_Master Document Register

27-Jan-13

5 of 6

9-Jun-13

13-May-13

12-Jun-13

15-May-13

Updated on : 7/7/2014

EPC of Building External Areas Upgrade in Admin Area at Raslaffan -RGCP-472


DESIGN DRAWING SUBMITTAL LOG
LEGEND
Approved/IFC

Sl.
No.

Drawing Title

Drawing Number

No of
Sheets

QBEC Transmittal
Reference

Approved with
Comments

Reviewed W No
Comments

Issue for Review

Plan
Submission
date

Rev

Submit Date

Reviewed with
Comments

Submitted

Issue for Approval

Issued for Construction

As-Built
Zone

Reply Date

Approval
Status

Rev

Submit Date Reply Date

Approval
Status

Rev

Submit Date Reply Date

Approval
Status

Rev

Submit Date

Reply Date

Approval
Status

16

Electrical Cable Route Layout ( Zone 11,Zone12 & Zone 15)

D-80-134A-291

1 of 1

RGCP-472-T-QTR-0503

27-Jan-13

19-Feb-13

24-Feb-13

25-May-13

29-May-13

9-Jun-13

11-Jun-13

IFC

All Zones

17

Electrical Cable Route Layout Admin & Maint.Annex XK-10

D-80-134A-292

1 of 1

RGCP-472-T-QTR-0722

27-Jan-13

19-Feb-13

24-Feb-13

9-Jun-13

11-Jun-13

07-Oct-13

10-Oct-13

IFC

All Zones

18

Electrical Works - General Layout for Lighting (Zone 2)

D-80-134A-293

1 of 1

RGCP-472-T-QTR-0723

03-Apr-13

4-Apr-13

25-May-13

29-May-13

07-Oct-13

22-Oct-13

IFC

All Zones

19

Electrical Works - General Layout for Lighting (Zone 19)

D-80-134A-294

1 of 1

RGCP-472-T-QTR-0720

03-Apr-13

4-Apr-13

5-May-13

12-May-13

07-Oct-13

10-Oct-13

IFC

All Zones

20

Electrical Works - General Layout for Lighting (Zone 4)

D-80-134A-295

1 of 1

RGCP-472-T-QTR-767

03-Apr-13

4-Apr-13

5-May-13

12-May-13

13-Nov-13

1-Dec-13

IFC

All Zones

21

Electrical Works - General Layout for Lighting (Zone 12)

D-80-134A-296

1 of 1

RGCP-472-T-QTR-769

03-Apr-13

4-Apr-13

5-May-13

12-May-13

13-Nov-13

17-Nov-13

IFC

All Zones

22

Electrical Works - General Layout for Lighting (Zone 15)

D-80-134A-297

1 of 1

RGCP-472-T-QTR-768

03-Apr-13

4-Apr-13

5-May-13

12-May-13

13-Nov-13

17-Nov-13

IFC

All Zones

23

Earthing Works - General Earthing Layout (Zone 1 - Zone 10)

D-80-134A-298

1 of 1

RGCP-472-T-QTR-0494

12-May-13

15-May-13

25-May-13

29-May-13

9-Jun-13

11-Jun-13

IFC

All Zones

24

Earthing Works - General Earthing Layout (Zone 2)

D-80-134A-299

1 of 1

RGCP-472-T-QTR-0495

12-May-13

15-May-13

25-May-13

29-May-13

9-Jun-13

11-Jun-13

IFC

All Zones

25

Earthing Works - General Earthing Layout (Zone 19)

D-80-134A-200A

1 of 1

RGCP-472-T-QTR-0496

12-May-13

15-May-13

25-May-13

28-May-13

9-Jun-13

11-Jun-13

IFC

All Zones

26

Earthing Works - General Earthing Layout (Zone 4 & 11)

D-80-134A-201A

1 of 1

RGCP-472-T-QTR-0497

12-May-13

15-May-13

25-May-13

29-May-13

9-Jun-13

11-Jun-13

IFC

All Zones

27

Pump Room Layout - Lighting and small power

D-80-134A-202A

1 of 1

RGCP-472-T-QTR-542

05-May-13

12-May-13

14-May-13

16-May-13

9-Jul-13

11-Jul-13

IFC

All Zones

28

Pump Room Cable Route Layout

D-80-134A-202B

1 of 2

RGCP-472-T-QTR-882

05-May-13

12-May-13

16-Dec-13

23-Dec-13

22-Apr-14

22-May-14

All Zones

29

Pump Room Cable Route Layout

D-80-134A-202B

2 of 2

RGCP-472-T-QTR-882

16-Dec-13

23-Dec-13

22-Apr-14

22-May-14

30

Water Feature Electrical Lighting Layout

D-80-134A-202C

1 of 1

RGCP-472-T-QTR-862

01-Oct-13

27-Oct-13

28-Oct-13

29-Mar-14

31-Mar-14

31

Earthing Layout and Details

D-80-134A-202E

1 of 1

RGCP-472-T-QTR-861

29-Mar-14

31-Mar-14

32

Pump Room Air Conditioning & Ventilation Pipe Layout

D-80-134A-202D

32
33
34
35

Mosque XK2 Electrical Single Line Diagram & Distribution Board


Schedule
Main Building XK-1 Single Line Diagram PP-XK01-61A PP-61B & PPXK01-62E
Rasgas Offices Project Maintenance Complex Relocation Single Line
Diagram
Electrical Tie-In Schedule
Water Feature Electrical Lighting Layout

02-Oct-13

RGCP-472-T-QTR-915

17-Jun-14

25-Jun-14

IFC

D-80-134B-225

1 of 1

RGCP-472-T-QTR-559

27-May-13

29-May-13

18-Jul-13

31-Jul-13

IFC

D-80-134A-253

1 of 1

RGCP-472-T-QTR-594

27-May-13

29-May-13

17-Aug-13

19-Aug-13

IFC

RGX-D-61-1382004

1 of 1

RGCP-472-T-QTR-582

27-May-13

29-May-13

11-Aug-13

21-Aug-13

IFC

S-80-134A-225

1 of 1

RGCP-472-T-QTR-765

08-Jul-13

11-Jul-11

13-Nov-13

17-Nov-13

IFC

06-Jun-14

10-Jun-14

D-80-134A-470B

30-Sep-13

3-Oct-13

RGCP-472-T-QTR-905

35

Underground Facilities Administration & Maintenance Area

D-61-1316-001

1 of 1

RGCP-472-T-QTR-677

14A

13-Jul-13

31-Jul-13

14B

18-Sep-13

03-Oct-13

14C

10-Feb-14

16-Feb-14

36

Underground Facilities Administration & Maintenance Area

D-61-1316-001

1 of 1

RGCP-472-T-QTR-677

9A

13-Jul-13

31-Jul-13

9B

18-Sep-13

03-Oct-13

9C

10-Feb-14

16-Feb-14

37

Underground Facilities Administration & Maintenance Area

D-61-1316-001

1 of 1

RGCP-472-T-QTR-677

14A

13-Jul-13

31-Jul-13

14B

18-Sep-13

03-Oct-13

14C

10-Feb-14

16-Feb-14

38

Underground Facilities Administration & Maintenance Area

D-61-1316-001

1 of 1

RGCP-472-T-QTR-677

12A

13-Jul-13

31-Jul-13

12B

18-Sep-13

03-Oct-13

12C

10-Feb-14

16-Feb-14

39

Underground Facilities Administration & Maintenance Area

D-61-1316-001

1 of 1

RGCP-472-T-QTR-677

17A

13-Jul-13

31-Jul-13

17B

18-Sep-13

03-Oct-13

17C

10-Feb-14

16-Feb-14

40

Underground Facilities Administration & Maintenance Area

D-61-1316-001

1 of 1

RGCP-472-T-QTR-677

13A

13-Jul-13

31-Jul-13

13B

18-Sep-13

03-Oct-13

13C

10-Feb-14

16-Feb-14

41

Underground Facilities Administration & Maintenance Area

D-61-1316-001

1 of 1

RGCP-472-T-QTR-677

11A

13-Jul-13

31-Jul-13

11B

18-Sep-13

03-Oct-13

11C

10-Feb-14

16-Feb-14

42

Underground Facilities Administration & Maintenance Area

D-61-1316-001

1 of 1

RGCP-472-T-QTR-677

12A

13-Jul-13

31-Jul-13

1B

18-Sep-13

03-Oct-13

1C

10-Feb-14

16-Feb-14

43

Underground Facilities Administration & Maintenance Area

D-61-1316-001

1 of 1

RGCP-472-T-QTR-677

14A

13-Jul-13

31-Jul-13

14B

18-Sep-13

03-Oct-13

14C

10-Feb-14

16-Feb-14

44

Underground Facilities Administration & Maintenance Area

D-61-1316-001

1 of 1

RGCP-472-T-QTR-677

8A

13-Jul-13

31-Jul-13

8B

18-Sep-13

03-Oct-13

8C

10-Feb-14

16-Feb-14

45

Underground Facilities Administration & Maintenance Area

D-61-1316-001

1 of 1

RGCP-472-T-QTR-677

10A

13-Jul-13

31-Jul-13

10B

18-Sep-13

03-Oct-13

10C

10-Feb-14

16-Feb-14

MDR_Master Document Register

6 of 6

Updated on : 7/7/2014

11. PROGRESS UPDATED WBS SUMMARY

Activity Name

Original Start
Duration

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


O

654 21-Oct-12 A

26-Jul-14

-7

94.15%

98.4%

QR20,950,917.53

644 21-Oct-12 A

26-Jul-14

-7

100%

100%

QR1,047,545.97

GENERAL MILESTONES

644 21-Oct-12 A

26-Jul-14

-7

0%

0%

QR0.00

KEY MILESTONES
CONTRACTOR MOBILISATION and FINALIZATION OF KEY SUB-CONTR

543 04-Jan-13 A

30-Jun-14

19

0%

0%

QR0.00

EPC of Building External Areas Upgrade in Admin Are


GENERAL REQUIREMENTS

ENGINEERING
Site Survey and Trial pit Excavation
Submission and Approval of Design Calculations
Car Parks
Structural Shades and Covered Car Parks
Piping Hydraulic Calculations
Concrete Foundations
Electrical Lighting and Cable Sizing
Cable Submission

Submission and Approval of Detailed Engineering Drawings


Civil and Structural Works
Planting and Irrigation Distribution Work
Shade Structure Works
Signage Works
Electrical Works
Mechanical Works

PROCUREMENT
Materials Submission and Approval
Interlock pavers, kerb stones and tree guards
Foundation bolts
Main piping material
Shade structures including fabric material
Signage structures
Fountain sculpture
Electrical Poles, DBs and Field Controls
Valves and pumps
Irrigation distribution accessories

Placing of Orders and First Delivery to Project Site


Interlock pavers, kerb stones and tree guards
Foundation bolts
Main piping material
Shade structures including fabric material
Signage structures
Fountain sculpture
Electrical Poles, DBs and Field Controls
Valves and pumps
Irrigation distribution accessories

CONSTRUCTION
Phase 1 Works
Construction
Zone 1
Open car park paving - Kerb and interlock paving works
Irrigation piping main laying
Kerb, plant edgers and interlock paving works
Area lighting and control cable laying
Shade structures erection

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

75 21-Oct-12 A

03-Jan-13 A

100%

100%

QR1,047,545.97

540 23-Oct-12 A

12-Jun-14 A

100%

100%

QR1,047,545.47

120 23-Oct-12 A

05-Feb-13 A

100%

100%

QR89,089.66

109 01-Nov-12 A 18-Feb-13 A

100%

100%

QR193,769.92

47
48
49
49
49
49
482

08-Nov-12 A
03-Dec-12 A
01-Nov-12 A
19-Nov-12 A
12-Nov-12 A
31-Dec-12 A
20-Dec-12 A

26-Dec-12 A
21-Jan-13 A
20-Dec-12 A
07-Jan-13 A
31-Dec-12 A
18-Feb-13 A
12-Jun-14 A

100%
100%
100%
100%
100%
100%
100%

100%
100%
100%
100%
100%
100%
100%

QR34,680.65
QR31,236.71
QR31,963.14
QR31,963.14
QR31,963.14
QR31,963.14
QR764,685.89

56
65
53
75
471
91
423

26-Dec-12 A
06-Jan-13 A
21-Jan-13 A
31-Dec-12 A
31-Dec-12 A
20-Dec-12 A
04-Feb-13 A

20-Feb-13 A
11-Mar-13 A
14-Mar-13 A
17-Mar-13 A
12-Jun-14 A
21-Mar-13 A
12-Jun-14 A

100%
100%
100%
100%
100%
100%
100%

100%
100%
100%
100%
100%
100%
100%

QR209,689.55
QR82,813.59
QR138,022.65
QR165,627.18
QR110,418.12
QR58,114.80
QR3,561,656.18

345 04-Feb-13 A

28-Feb-14 A

100%

100%

QR1,237,805.96

36
36
36
35
36
330
36
50
61
432

18-Feb-13 A
05-Mar-13 A
04-Feb-13 A
14-Mar-13 A
13-Feb-13 A
20-Feb-13 A
06-Mar-13 A
04-Feb-13 A
21-Mar-13 A
12-Mar-13 A

26-Mar-13 A
10-Apr-13 A
12-Mar-13 A
18-Apr-13 A
20-Mar-13 A
27-Feb-14 A
10-Apr-13 A
28-Feb-14 A
22-May-13 A
12-Jun-14 A

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

QR137,534.00
QR137,534.00
QR137,534.00
QR137,534.00
QR137,534.00
QR137,533.99
QR137,533.99
QR137,533.99
QR137,533.99
QR2,323,850.22

15
27
66
381
384
414
62
96
45
565

26-Mar-13 A
10-Apr-13 A
12-Mar-13 A
18-Apr-13 A
20-Mar-13 A
28-Mar-13 A
10-Apr-13 A
27-Mar-13 A
22-May-13 A
20-Feb-13 A

08-Apr-13 A
04-May-13 A
09-May-13 A
03-Apr-14 A
27-Feb-14 A
12-Jun-14 A
04-Jun-13 A
03-Apr-14 A
01-Jul-13 A
08-Jul-14

22

100%
100%
100%
100%
100%
100%
100%
100%
100%
99.01%

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

QR71,138.27
QR128,048.89
QR313,008.40
QR237,127.57
QR241,870.12
QR369,919.02
QR294,038.19
QR455,284.94
QR213,414.82
QR12,989,568.83

564 20-Feb-13 A

30-Jun-14

23

98.72%

100%

QR4,609,201.93

564
200
109
83
88
58
64

30-Jun-14
23-Jan-14 A
27-May-13 A
29-Jul-13 A
31-Dec-13 A
20-Jun-13 A
08-Jul-13 A

23

98.76%
100%
100%
100%
100%
100%
100%

100%
100%
100%
100%
100%
100%
100%

QR3,771,165.17
QR979,862.42
QR287,597.98
QR61,396.20
QR206,433.64
QR85,420.80
QR66,735.00

20-Feb-13 A
20-Feb-13 A
20-Feb-13 A
18-May-13 A
11-Mar-13 A
30-Apr-13 A
13-May-13 A

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

2013
N

J Jul A

2014
S

A M

J Jul A

Page 1 of 4

S Oct N

Activity Name

Original Start
Duration

Signage structures erection


Electrical Poles, DBs and Field Controls
Zone valves's installation
Irrigation lateral piping & distribution accessories
Hardscape and finishing works
Zone 2
Concrete foundations for water tanks
Irrigation piping main laying
Kerb, plant edgers and granite paving works
Area lighting and control cable laying
Signage structures erection
Fountain sculpture and finishing
Electrical Poles, DBs and Field Controls
Valves and pumps installation
Irrigation lateral piping & distribution accessories
Hardscape and finishing works
Zone 3
Irrigation piping main laying
Kerb, plant edgers and interlock paving works
Area lighting and control cable laying
Shade structures erection
Signage structures erection
Zone valves's installation
Irrigation lateral piping & distribution accessories
Hardscape and finishing works
Zone 4
Irrigation piping main laying
Kerb, plant edgers and interlock paving works
Area lighting and control cable laying
Shade structures erection
Signage structures erection
Zone valves and water tie-in installation
Irrigation lateral piping & distribution accessories
Hardscape and finishing works
Zone 8
Irrigation piping main laying
Kerb, plant edgers and interlock paving works
Signage structures erection
Zone valves's installation
Irrigation lateral piping & distribution accessories
Hardscape and finishing works
Phase 1 - Testing and Commissioning

Phase 2 Works
Construction
Zone 5
Concrete foundations signage
Kerb, plant edgers works
Irrigation piping main laying & zone valve's installation
Signage structures erection
Irrigation lateral piping & distribution accessories
Zone 6
Concrete foundations for shades and signage
Kerb, plant edgers and interlock paving works
Irrigation piping main laying & zone valve's installation

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

Finish

33
30
27
36
40
543
69
156
89
58
104
54
135
22
36
40
514
43
89
58
173
285
27
27
40
493
43
83
58
209
77
27
120
40
326
119
74
207
27
114
128
13
544

27-May-13 A
04-Jun-13 A
05-Jun-13 A
14-Jul-13 A
13-May-13 A
11-Mar-13 A
11-Mar-13 A
05-Jun-13 A
11-Mar-13 A
27-May-13 A
19-Jan-14 A
22-May-14 A
01-Jan-14 A
18-Jan-14 A
24-Sep-13 A
19-May-13 A
28-Mar-13 A
01-Oct-13 A
28-Mar-13 A
22-Jun-13 A
01-Feb-14 A
19-Jun-13 A
23-Oct-13 A
24-Oct-13 A
09-Jun-13 A
16-Apr-13 A
23-Oct-13 A
16-Apr-13 A
29-May-13 A
31-Dec-13 A
05-Jan-14 A
11-Nov-13 A
10-Nov-13 A
04-Jul-13 A
05-May-13 A
11-Nov-13 A
05-May-13 A
15-Jul-13 A
11-Nov-13 A
16-Nov-13 A
17-Aug-13 A
11-Dec-13 A
11-Mar-13 A

24-Jun-13 A
01-Jul-13 A
19-Jan-14 A
23-Jan-14 A
17-Jun-13 A
30-Jun-14
11-Jan-14 A
18-Jan-14 A
10-Apr-14 A
06-Feb-14 A
10-Apr-14 A
30-Jun-14
24-Apr-14 A
30-Apr-14 A
31-Mar-14 A
26-Apr-14 A
30-Jun-14
18-Jan-14 A
31-Dec-13 A
15-Aug-13 A
30-Jun-14
10-Apr-14 A
18-Jan-14 A
18-Jan-14 A
03-Apr-14 A
30-Jun-14
18-Jan-14 A
31-Dec-13 A
31-Dec-13 A
30-Jun-14
10-Apr-14 A
13-Feb-14 A
24-Jan-14 A
17-Apr-14 A
03-Apr-14 A
24-Jan-14 A
06-Mar-14 A
03-Apr-14 A
18-Jan-14 A
24-Jan-14 A
03-Apr-14 A
30-Jun-14
08-Jul-14

544
205
122
179
144
199
23
352
208
122
41

11-Mar-13 A
21-Jul-13 A
21-Jul-13 A
29-Jul-13 A
07-Sep-13 A
25-Jul-13 A
12-Dec-13 A
21-Aug-13 A
21-Aug-13 A
02-Feb-14 A
10-Dec-13 A

08-Jul-14
03-Apr-14 A
13-Nov-13 A
25-Jan-14 A
31-Dec-13 A
03-Apr-14 A
31-Dec-13 A
30-Jun-14
03-Apr-14 A
22-May-14 A
22-Jan-14 A

Total
Float

23

22

23

23

23

22

-8
22
22

23

Actual %
Complete

Planned %
Complete

COI-01 Total Cost

100%
100%
100%
100%
100%
97.66%
100%
100%
100%
100%
100%
75%
100%
100%
100%
100%
97.98%
100%
100%
100%
80%
100%
100%
100%
100%
98.07%
100%
100%
100%
80%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
98.53%
98.84%

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

QR29,363.40
QR53,388.00
QR24,024.60
QR112,114.80
QR53,388.00
QR855,987.67
QR86,310.61
QR125,461.80
QR206,433.64
QR85,420.80
QR29,363.40
QR80,082.02
QR53,388.00
QR24,024.60
QR112,114.80
QR53,388.00
QR660,231.64
QR114,784.20
QR206,433.64
QR85,420.80
QR66,735.00
QR29,363.40
QR24,024.60
QR80,082.00
QR53,388.00
QR692,264.44
QR114,784.20
QR206,433.64
QR85,420.80
QR66,735.00
QR29,363.40
QR24,024.60
QR112,114.80
QR53,388.00
QR582,819.00
QR224,229.60
QR179,739.60
QR21,355.20
QR24,024.60
QR80,082.00
QR53,388.00
QR838,036.76
QR3,352,146.70

98.94%
100%
100%
100%
100%
100%
100%
98.24%
100%
100%
100%

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

QR2,514,109.94
QR276,898.83
QR89,723.97
QR66,016.95
QR67,736.27
QR14,332.63
QR39,089.01
QR259,724.61
QR61,673.73
QR74,703.39
QR29,968.24

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

2013
N

J Jul A

2014
S

A M

J Jul A

Page 2 of 4

S Oct N

Activity Name

Original Start
Duration

Shade structures erection


Signage structures erection
Irrigation lateral piping & distribution accessories
Zone 7
Concrete foundations for shades and signage
Kerb, plant edgers and interlock paving works
Irrigation piping main laying & zone valve's installation
Shade structures erection
Signage structures erection
Irrigation lateral piping & distribution accessories
Zone 9
Concrete foundations for signage
Kerb for plant edgers
Irrigation piping main laying & zone valve's installation
Signage structures erection
Irrigation lateral piping & distribution accessories
Zone 10
Concrete foundations for shades and signage
Kerb, plant edgers and interlock paving works
Irrigation piping main laying & zone valve's installation
Shade structures erection
Signage structures erection
Electrical lighting and DBs installation
Irrigation lateral piping & distribution accessories
Zone 11
Concrete foundations for shades and signage
Kerb, plant edgers and interlock paving works
Irrigation piping main laying & zone valve's installation
Shade structures erection
Signage structures erection
Electrical lighting and DBs installation
Irrigation lateral piping & distribution accessories
Zone 17
Concrete foundations for signage
Irrigation piping main laying and water tie-in installation
Signage structures erection
Irrigation lateral piping & distribution accessories
Zone 18
Concrete foundations for signage
Kerbs and interlock paving works
Irrigation piping main laying & zone valve's installation
Signage structures erection
Irrigation lateral piping & distribution accessories
Zone 19
Open car park paving - Kerb and interlock paving works
Concrete foundations for shades and signage
Kerb, plant edgers and interlock paving works
Irrigation piping main laying & zone valve's installation
Shade structures erection
Signage structures erection
Electrical lighting and DBs installation
Irrigation lateral piping & distribution accessories
Phase 2 - Testing and Commissioning

Phase 3 Works

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

109
76
35
331
184
142
23
172
85
177
256
116
150
38
34
131
270
101
69
19
73
10
151
135
340
112
159
37
112
116
209
28
206
92
58
33
67
201
96
45
63
18
58
528
89
54
84
43
99
33
275
36
9
361

27-Mar-14 A
01-Feb-14 A
01-Feb-14 A
09-Sep-13 A
09-Sep-13 A
01-Feb-14 A
24-Dec-13 A
01-Feb-14 A
01-Feb-14 A
21-Dec-13 A
10-Sep-13 A
29-Sep-13 A
10-Sep-13 A
24-Dec-13 A
27-Mar-14 A
07-Dec-13 A
22-Oct-13 A
22-Oct-13 A
01-Feb-14 A
19-Dec-13 A
27-Mar-14 A
29-Mar-14 A
14-Dec-13 A
19-Dec-13 A
10-Sep-13 A
29-Sep-13 A
10-Sep-13 A
14-Dec-13 A
02-Mar-14 A
20-Mar-14 A
24-Oct-13 A
08-Dec-13 A
26-Oct-13 A
26-Oct-13 A
26-Nov-13 A
27-Mar-14 A
17-Dec-13 A
21-Oct-13 A
21-Oct-13 A
01-Feb-14 A
19-Dec-13 A
27-Mar-14 A
21-Dec-13 A
11-Mar-13 A
11-Mar-13 A
28-Mar-13 A
28-Mar-13 A
30-Apr-13 A
27-Mar-14 A
15-Jun-13 A
06-Jun-13 A
22-May-13 A
08-Dec-13 A
17-Aug-13 A

Finish
30-Jun-14
10-Apr-14 A
10-Apr-14 A
30-Jun-14
31-Mar-14 A
22-May-14 A
31-Dec-13 A
30-Jun-14
10-Apr-14 A
12-Jun-14 A
10-Apr-14 A
13-Feb-14 A
10-Apr-14 A
06-Jan-14 A
10-Apr-14 A
29-Jan-14 A
30-Jun-14
06-Mar-14 A
05-Apr-14 A
23-Jan-14 A
30-Jun-14
17-Apr-14 A
31-Mar-14 A
17-Apr-14 A
08-Jul-14
06-Feb-14 A
20-Feb-14 A
06-Feb-14 A
08-Jul-14
10-Apr-14 A
31-Mar-14 A
13-Feb-14 A
10-Apr-14 A
06-Feb-14 A
01-Jan-14 A
10-Apr-14 A
06-Feb-14 A
10-Apr-14 A
26-Feb-14 A
02-Mar-14 A
12-Feb-14 A
10-Apr-14 A
09-Feb-14 A
30-Jun-14
27-May-13 A
15-May-13 A
31-Dec-13 A
06-Jun-13 A
30-Jun-14
14-Jul-13 A
06-Feb-14 A
23-Dec-13 A
30-Jun-14
30-Jun-14

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost

-8

81.58%
100%
100%
98.25%
100%
100%
100%
81.58%
100%
100%
100%
100%
100%
100%
100%
100%
98.23%
100%
100%
100%
81.58%
100%
100%
100%
97.72%
100%
100%
100%
80%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
98.31%
100%
100%
100%
100%
80%
100%
100%
100%
98.53%
99.16%

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

QR24,756.37
QR13,898.31
QR54,724.57
QR260,158.93
QR61,673.73
QR74,703.39
QR29,968.24
QR24,756.37
QR14,332.63
QR54,724.57
QR260,167.93
QR61,673.73
QR74,703.39
QR54,733.61
QR14,332.63
QR54,724.57
QR257,552.99
QR34,311.44
QR73,400.42
QR29,968.24
QR24,756.37
QR14,332.63
QR26,059.32
QR54,724.57
QR285,349.63
QR35,614.41
QR92,076.31
QR29,968.24
QR32,574.15
QR14,332.63
QR26,059.32
QR54,724.57
QR267,976.71
QR142,891.95
QR56,027.56
QR14,332.63
QR54,724.57
QR260,167.93
QR35,614.41
QR74,703.39
QR80,792.93
QR14,332.63
QR54,724.57
QR386,112.38
QR100,762.75
QR35,614.41
QR92,076.31
QR29,968.24
QR32,574.15
QR14,332.63
QR26,059.32
QR54,724.57
QR838,036.76
QR3,561,655.92

23

23

-8

-8

22

22

-8

-8

-9
23

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

2013
N

J Jul A

2014
S

A M

J Jul A

Page 3 of 4

S Oct N

Activity Name

Original Start
Duration

Construction
Zone 12
Concrete foundations for shades and signage
Kerb, plant edgers and interlock paving works
Irrigation piping main laying & zone valve's installation
Shade structures erection
Signage structures erection
Irrigation lateral piping & distribution accessories
Road Kerb and Furnishing Works
Zone 13
Concrete foundations for signage
Kerbs and interlock paving works
Irrigation piping main laying & zone valve's installation
Signage structures erection
Irrigation lateral piping & distribution accessories
Road Kerb and Furnishing Works
Zone 14
Open car park paving - Kerb and interlock paving works
Concrete foundations for signage
Kerb, plant edgers and interlock paving works
Irrigation piping main laying & zone valve's installation
Signage structures erection
Irrigation lateral piping & distribution accessories
Road Kerb and Furnishing Works
Zone 15
Concrete foundations for shades and signage
Kerb, plant edgers and interlock paving works
Irrigation piping main laying & zone valve's installation
Shade structures erection
Signage structures erection
Irrigation lateral piping & distribution accessories
Road Kerb and Furnishing Works
Zone 16
Concrete foundations for signage
Kerb, plant edgers works
Irrigation piping main laying & zone valve's installation
Signage structures erection
Irrigation lateral piping & distribution accessories
Road Kerb and Furnishing Works
Phase 3 - Testing and Commissioning

Phase 4 Works

TESTING & COMMISSIONING (PROVISIONAL ACCEPTE


FINAL DOCUMENTATION and FINAL ACCEPTANCE CER

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost

30-Jun-14
30-Jun-14
06-Feb-14 A
17-Apr-14 A
14-Jan-14 A
30-Jun-14
10-Apr-14 A
18-Feb-14 A
31-Dec-13 A
03-Apr-14 A
31-Dec-13 A
04-Jan-14 A
31-Dec-13 A
03-Apr-14 A
04-Jan-14 A
31-Dec-13 A
03-Apr-14 A
31-Dec-13 A
30-Dec-13 A
31-Dec-13 A
31-Dec-13 A
03-Apr-14 A
18-Jan-14 A
31-Dec-13 A
30-Jun-14
06-Mar-14 A
14-Apr-14 A
12-Jan-14 A
30-Jun-14
17-Apr-14 A
30-Apr-14 A
24-Apr-14 A
10-Apr-14 A
31-Dec-13 A
31-Dec-13 A
31-Dec-13 A
10-Apr-14 A
31-Dec-13 A
31-Dec-13 A
30-Jun-14
21-Jun-14 A

23
23

99.35%
98.63%
100%
100%
100%
81.58%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
98.28%
100%
100%
100%
80%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
98.53%
100%

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%

QR2,723,619.16
QR529,814.28
QR94,881.77
QR119,121.64
QR47,787.17
QR39,476.36
QR22,162.17
QR87,263.53
QR119,121.64
QR458,479.80
QR119,814.21
QR103,192.58
QR47,787.17
QR22,162.17
QR62,331.09
QR103,192.58
QR615,000.09
QR153,750.02
QR92,804.07
QR119,121.64
QR47,787.17
QR22,854.74
QR73,412.17
QR105,270.28
QR605,054.60
QR156,963.30
QR119,121.64
QR47,787.17
QR51,942.58
QR22,854.74
QR87,263.53
QR119,121.64
QR515,270.39
QR128,817.59
QR119,121.64
QR43,631.77
QR22,854.74
QR81,723.01
QR119,121.64
QR838,036.76
QR1,466,564.28

83 10-Apr-14 A

30-Jun-14

21

60.41%

100%

QR1,047,545.95

109 19-Apr-14 A

26-Jul-14

-7

45.67%

73.37%

QR1,257,055.13

361
330
88
216
32
134
30
70
159
236
147
146
136
39
21
204
254
148
130
164
95
38
28
153
361
215
15
138
137
46
139
183
246
212
204
184
38
20
184
13
263

17-Aug-13 A
10-Sep-13 A
26-Oct-13 A
10-Sep-13 A
18-Dec-13 A
05-Mar-14 A
20-Mar-14 A
19-Dec-13 A
10-Sep-13 A
10-Sep-13 A
12-Sep-13 A
10-Sep-13 A
12-Sep-13 A
06-Mar-14 A
17-Dec-13 A
14-Sep-13 A
24-Aug-13 A
24-Aug-13 A
01-Sep-13 A
24-Aug-13 A
17-Nov-13 A
06-Mar-14 A
25-Dec-13 A
01-Sep-13 A
17-Aug-13 A
17-Aug-13 A
06-Mar-14 A
31-Aug-13 A
06-Mar-14 A
06-Mar-14 A
22-Dec-13 A
10-Sep-13 A
31-Aug-13 A
31-Aug-13 A
17-Sep-13 A
16-Sep-13 A
06-Mar-14 A
22-Dec-13 A
14-Sep-13 A
05-Dec-13 A
25-Sep-13 A

Finish

23

23

23

-8

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

2013
N

J Jul A

2014
S

A M

J Jul A

Page 4 of 4

S Oct N

12. ONE MONTH LOOK-AHEAD

Activity Name

Original Start
Duration

EPC of Building External Areas Upgrade in Admin Are


GENERAL REQUIREMENTS
GENERAL MILESTONES

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost

Calendar

2013
ND J F

241 08-Dec-13 A

26-Jul-14

-7

67.02%

88.17%

QR3,716,773.03

27 30-Jun-14

26-Jul-14

-7

0%

0%

QR0.00

7- Day Workweek - default

26 30-Jun-14

J J AS

2015

2014
N D J FMA

J J AS

N D J FM

26-Jul-14

-7

0%

0%

QR0.00

7- Day Workweek - default

Provisional Project Completion

30-Jun-14

19

0%

0%

QR0.00

7- Day Workweek - default

Provisional Proje

Final Project Completion

26-Jul-14

-7

0%

0%

QR0.00

7- Day Workweek - default

Final Project C

KEY MILESTONES

1 30-Jun-14

30-Jun-14

19

0%

0%

QR0.00

7- Day Workweek - default

Completion of Phase 2 Works

30-Jun-14

19

0%

0%

QR0.00

7- Day Workweek - default

Completion of Ph

Completion of Phase 3 Works

30-Jun-14

20

0%

0%

QR0.00

7- Day Workweek - default

Completion of Ph

Completion of Phase 4 Works

30-Jun-14

20

0%

0%

QR0.00

7- Day Workweek - default

Completion of Ph

243 08-Dec-13 A

30-Jun-14

22

90.94%

97.59%

QR1,412,171.95

6-Day Work Week + Holidasys

231 17-Dec-13 A

CONSTRUCTION
Phase 1 Works
Construction
Zone 2
Fountain sculpture and finishing
Fix fountain finishes
Zone 3
Shade structures erection
Fix fabric shades
Zone 4
Shade structures erection
Fix fabric shades
Phase 1 - Testing and Commissioning
Testing and Commissioning for mechanical works

Phase 2 Works
Construction
Zone 6
Shade structures erection

23

88.28%

96.6%

QR503,429.13

6-Day Work Week + Holidasys

30-Jun-14
30-Jun-14
30-Jun-14
30-Jun-14

23
22
22
22

50%
50%
50%
50%

81.7%
66.22%
66.22%
66.22%

QR93,429.01
QR40,041.01
QR40,041.01
QR40,041.01

6-Day Work Week + Holidasys


6-Day Work Week + Holidasys
6-Day Work Week + Holidasys
6-Day Work Week + Holidasys

Fix fountain finish

30 05-Jun-14 A
30 05-Jun-14 A
30 05-Jun-14 A

30-Jun-14
30-Jun-14
30-Jun-14

23
23
23

50%
50%
50%

93.3%
93.3%
93.3%

QR26,694.00
QR26,694.00
QR26,694.00

6-Day Work Week + Holidasys


6-Day Work Week + Holidasys
6-Day Work Week + Holidasys

Fix fabric shades

30 05-Jun-14 A
30 05-Jun-14 A
30 05-Jun-14 A

30-Jun-14
30-Jun-14
30-Jun-14

22
22
22

50%
50%
50%

93.3%
93.3%
93.3%

QR26,694.00
QR26,694.00
QR26,694.00

6-Day Work Week + Holidasys


6-Day Work Week + Holidasys
6-Day Work Week + Holidasys

Fix fabric shades

6 17-Dec-13 A
6 17-Dec-13 A

30-Jun-14
30-Jun-14

-8
-8

97%
97%

100%
100%

QR410,000.12
QR410,000.12

6-Day Work Week + Holidasys


6-Day Work Week + Holidasys

Testing and Com

243 08-Dec-13 A

30-Jun-14

22

91.58%

98.76%

QR463,421.75

6-Day Work Week + Holidasys

12-Jun-14 A
12-Jun-14 A
12-Jun-14 A
12-Jun-14 A

30-Jun-14
30-Jun-14
30-Jun-14
30-Jun-14

22
-8
-8
-8

50%
50%
50%
50%

89.21%
94.6%
94.6%
94.6%

QR53,421.63
QR9,120.77
QR9,120.77
QR9,120.77

6-Day Work Week + Holidasys


6-Day Work Week + Holidasys
6-Day Work Week + Holidasys
6-Day Work Week + Holidasys

Fix fabric shades

21 12-Jun-14 A
21 12-Jun-14 A
21 12-Jun-14 A

30-Jun-14
30-Jun-14
30-Jun-14

23
23
23

50%
50%
50%

94.6%
94.6%
94.6%

QR9,120.77
QR9,120.77
QR9,120.77

6-Day Work Week + Holidasys


6-Day Work Week + Holidasys
6-Day Work Week + Holidasys

Fix fabric shades

5 12-Jun-14 A
5 12-Jun-14 A
5 12-Jun-14 A

30-Jun-14
30-Jun-14
30-Jun-14

-8
-8
-8

50%
50%
50%

100%
100%
100%

QR9,120.77
QR9,120.77
QR9,120.77

6-Day Work Week + Holidasys


6-Day Work Week + Holidasys
6-Day Work Week + Holidasys

Fix fabric shades

30 12-Jun-14 A
30 12-Jun-14 A
30 12-Jun-14 A

30-Jun-14
30-Jun-14
30-Jun-14

-9
-9
-9

50%
50%
50%

63.33%
63.33%
63.33%

QR13,029.66
QR13,029.66
QR13,029.66

6-Day Work Week + Holidasys


6-Day Work Week + Holidasys
6-Day Work Week + Holidasys

Fix fabric shades

15 12-Jun-14 A
15 12-Jun-14 A
15 12-Jun-14 A

30-Jun-14
30-Jun-14
30-Jun-14

-8
-8
-8

50%
50%
50%

100%
100%
100%

QR13,029.66
QR13,029.66
QR13,029.66

6-Day Work Week + Holidasys


6-Day Work Week + Holidasys
6-Day Work Week + Holidasys

Fix fabric shades

9 08-Dec-13 A
9 08-Dec-13 A

30-Jun-14
30-Jun-14

-8
-8

97%
97%

100%
100%

QR410,000.12
QR410,000.12

6-Day Work Week + Holidasys


6-Day Work Week + Holidasys

Testing and Com

234 10-Dec-13 A

30-Jun-14

23

93.27%

97.49%

QR445,321.07

6-Day Work Week + Holidasys

12-Jun-14 A
12-Jun-14 A
12-Jun-14 A
12-Jun-14 A

30-Jun-14
30-Jun-14
30-Jun-14
30-Jun-14

23
23
23
23

50%
50%
50%
50%

68.37%
94.6%
94.6%
94.6%

QR35,320.95
QR14,543.92
QR14,543.92
QR14,543.92

6-Day Work Week + Holidasys


6-Day Work Week + Holidasys
6-Day Work Week + Holidasys
6-Day Work Week + Holidasys

Fix fabric shades

10 25-Jun-14 A
10 25-Jun-14 A
10 25-Jun-14 A

30-Jun-14
30-Jun-14
30-Jun-14

23
23
23

50%
50%
50%

50%
50%
50%

QR20,777.03
QR20,777.03
QR20,777.03

6-Day Work Week + Holidasys


6-Day Work Week + Holidasys
6-Day Work Week + Holidasys

Fix fabric shades

31
21
21
21

Fix fabric shades


Zone 7
Shade structures erection
Fix fabric shades
Zone 10
Shade structures erection
Fix fabric shades
Zone 11
Shade structures erection
Fix fabric shades
Zone 19
Shade structures erection
Fix fabric shades
Phase 2 - Testing and Commissioning
Testing and Commissioning for mechanical works

Phase 3 Works
Construction
Zone 12
Shade structures erection

25
21
21
21

Fix fabric shades


Zone 15
Shade structures erection
Fix fabric shades

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

30-Jun-14

05-Jun-14 A
12-Jun-14 A
12-Jun-14 A
12-Jun-14 A

38
30
30
30

Remaining

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Page 1 of 2

Activity Name

Original Start
Duration

Phase 3 - Testing and Commissioning


Testing and Commissioning for mechanical works

TESTING & COMMISSIONING (PROVISIONAL ACCEPTE


Prepare punch list Category "A"

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost

Calendar

2013
ND J F

8 10-Dec-13 A
8 10-Dec-13 A

30-Jun-14
30-Jun-14

-8
-8

97%
97%

100%
100%

QR410,000.12
QR410,000.12

6-Day Work Week + Holidasys


6-Day Work Week + Holidasys

83 10-Apr-14 A

30-Jun-14

21

60.41%

100%

QR1,047,545.95

6-Day Work Week + Holidasys

J J AS

2015

2014
N D J FMA

J J AS

N D J FM

Testing and Com

6 10-Apr-14 A

30-Jun-14

-9

88%

100%

QR125,045.68

6-Day Work Week + Holidasys

Prepare punch li

Clear punch list Category "A"

14 01-May-14 A

30-Jun-14

21

65%

100%

QR239,166.74

6-Day Work Week + Holidasys

Clear punch list C

Pre-commissioning for irrigation, utilities and electrical system

10 19-Apr-14 A

30-Jun-14

21

65%

100%

QR170,833.38

6-Day Work Week + Holidasys

Pre-commissioni

6 18-May-14 A

30-Jun-14

21

50%

100%

QR102,500.03

6-Day Work Week + Holidasys

Prepare punch li

Clear punch list Category "B"

14 17-May-14 A

30-Jun-14

21

50%

100%

QR239,166.74

6-Day Work Week + Holidasys

Clear punch list C

Final testing & commissioning for irrigation, utilities and electrical system

10 14-Jun-14 A

30-Jun-14

21

50%

100%

QR170,833.38

6-Day Work Week + Holidasys

Final testing & co

109 19-Apr-14 A

26-Jul-14

-7

45.67%

67.74%

QR1,257,055.13

Prepare punch list Category "B"

FINAL DOCUMENTATION and FINAL ACCEPTANCE CER


As-built Drawings

83 19-Apr-14 A

30-Jun-14

-8

42.59%

67.35%

QR367,460.78

Prepare & submit As-built Drawings

45 19-Apr-14 A

30-Jun-14

-9

50%

100%

QR231,298.38

6-Day Work Week + Holidasys

Prepare & subm

Company review & approval of As-built drawings

10 26-Jun-14 A

30-Jun-14

-6

30%

11.88%

QR136,162.40

5-Day Work Week + Holidays

Company review

34 07-Jun-14 A

06-Jul-14

-9

38%

60.34%

QR226,937.33

Prepare & Submit Redline Mark-ups

30 07-Jun-14 A

30-Jun-14

-9

50%

88.44%

QR136,162.40

6-Day Work Week + Holidasys

Prepare & Subm

Company Review & approval of Redline Mark-ups

11 26-Jun-14 A

06-Jul-14

-5

20%

18.18%

QR90,774.93

5-Day Work Week + Holidays

Company Revie

25 07-Jun-14 A

10-Jul-14

-8

50%

100%

QR118,007.41

6-Day Work Week + Holidasys

25 07-Jun-14 A

10-Jul-14

-8

50%

100%

QR118,007.41

6-Day Work Week + Holidasys

25 07-Jun-14 A

15-Jul-14

-8

50%

100%

QR113,468.67

6-Day Work Week + Holidasys

25 07-Jun-14 A

15-Jul-14

-8

50%

100%

QR113,468.67

6-Day Work Week + Holidasys

25 07-Jun-14 A

21-Jul-14

-8

50%

100%

QR113,468.67

6-Day Work Week + Holidasys

25 07-Jun-14 A

21-Jul-14

-8

50%

100%

QR113,468.67

6-Day Work Week + Holidasys

69 07-Jun-14 A

26-Jul-14

-8

50%

38.45%

QR317,712.27

6-Day Work Week + Holidasys

69 07-Jun-14 A

26-Jul-14

-8

50%

38.45%

QR317,712.27

6-Day Work Week + Holidasys

Redline Mark-ups

Project Dossier
Prepare & Submit project dossier

Material Take-off
Prepare & Submit material take-off & spare parts

O&M Manual
Prepare & submit O&M Manual

Completion of all outstanding snag or punch list items


Completion of all outstanding snag/punch list

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Prepare & Subm


Prepare & Subm
Prepare & subm
Completion of

Page 2 of 2

13. PROGRESS UPDATED PROGRAMME

Activity Name

Original Start
Duration

EPC of Building External Areas Upgrade in Admin Are


GENERAL REQUIREMENTS
GENERAL MILESTONES

Finish

Planned %
Complete

COI-01 Total Cost


O

26-Jul-14

-7

94.15%

98.4%

QR20,950,917.53

644 21-Oct-12 A

26-Jul-14

-7

100%

100%

QR1,047,545.97

644 21-Oct-12 A

26-Jul-14

-7

0%

0%

QR0.00

100%

100%

QR0.00

19

0%

100%

QR0.00

26-Jul-14

-7

0%

0%

QR0.00

30-Jun-14

19

0%

0%

QR0.00

0 21-Oct-12 A

Provisional Project Completion

30-Jun-14

Final Project Completion

Actual %
Complete

654 21-Oct-12 A

Contractual Project Start

KEY MILESTONES

Total
Float

543 04-Jan-13 A

2013
N

J Jul A

2014
S

A M

J Jul A

S Oct N

Contractual Project Start


Provisional Project
Final Project Co

Completion of Mobilisation

04-Jan-13 A

100%

100%

QR0.00

Completion of Engineering Works

21-Mar-13 A

100%

100%

QR0.00

Completion of Procurement

01-Jul-13 A

100%

100%

QR0.00

Completion of Phase 1 Works

19-Dec-13 A

100%

100%

QR0.00

Completion of Phase 2 Works

30-Jun-14

19

0%

100%

QR0.00

Completion of Pha

Completion of Phase 3 Works

30-Jun-14

20

0%

100%

QR0.00

Completion of Pha

30-Jun-14

20

Completion of Pha

Completion of Phase 4 Works

0%

100%

QR0.00

75 21-Oct-12 A

03-Jan-13 A

100%

100%

QR1,047,545.97

Prepare and Submit CV of Project Manager

60
39
19
3

21-Oct-12 A
21-Oct-12 A
21-Oct-12 A
21-Oct-12 A

20-Dec-12 A
28-Nov-12 A
08-Nov-12 A
23-Oct-12 A

100%
100%
100%
100%

100%
100%
100%
100%

QR499,965.17
QR321,366.64
QR41,821.06
QR16,584.31

Company Review and Approval

10 23-Oct-12 A

06-Nov-12 A

100%

100%

QR19,412.88

3 06-Nov-12 A 08-Nov-12 A

100%

100%

QR5,823.87

CONTRACTOR MOBILISATION and FINALIZATION OF KEY SUB-CONTR


Contractor Mobilisation
Key Personnels
Project Manager

Project Manager Mobilisation to Site


Construction Manager
Prepare and Submit CV of Construction Manager

19 21-Oct-12 A
3 21-Oct-12 A

08-Nov-12 A
23-Oct-12 A

100%
100%

100%
100%

QR31,060.62
QR5,823.87

Company Review and Approval

10 23-Oct-12 A

06-Nov-12 A

100%

100%

QR19,412.88

3 06-Nov-12 A 08-Nov-12 A

100%

100%

QR5,823.87

Construction Manager Mobilisation to Site


Engineering Coordinator
Prepare and Submit CV of Engineering Coordinator

19 21-Oct-12 A
3 21-Oct-12 A

08-Nov-12 A
23-Oct-12 A

100%
100%

100%
100%

QR31,060.62
QR5,823.87

Company Review and Approval

10 23-Oct-12 A

06-Nov-12 A

100%

100%

QR19,412.88

3 06-Nov-12 A 08-Nov-12 A

100%

100%

QR5,823.87

Engineering Coordinator Mobilisation to Site


Civil Engineer / Landscape Architect
Prepare and Submit CV of Civil Engr / Landscape Arch

20 23-Oct-12 A
3 23-Oct-12 A

12-Nov-12 A
25-Oct-12 A

100%
100%

100%
100%

QR31,060.62
QR5,823.87

Company Review and Approval

10 28-Oct-12 A

08-Nov-12 A

100%

100%

QR19,412.88

3 08-Nov-12 A 12-Nov-12 A

100%

100%

QR5,823.87

Civil Engr / Landscape Arch Mobilisation to Site


Mechanical / Plumbing Engineer
Prepare and Submit CV of Mechanical/Plumbing Engineer

20 23-Oct-12 A
3 23-Oct-12 A

12-Nov-12 A
25-Oct-12 A

100%
100%

100%
100%

QR31,060.62
QR5,823.87

Company Review and Approval

10 28-Oct-12 A

08-Nov-12 A

100%

100%

QR19,412.88

3 08-Nov-12 A 12-Nov-12 A

Mechanical/Plumbing Engineer Mobilisation to Site

Completion of Mobilisation
Completion of Engineering Works
Completion of Procurement
Completion of Phase 1 Works

Prepare and Submit CV of Project Manager


Company Review and Approval
Project Manager Mobilisation to Site
Prepare and Submit CV of Construction Manager
Company Review and Approval
Construction Manager Mobilisation to Site
Prepare and Submit CV of Engineering Coordinator
Company Review and Approval
Engineering Coordinator Mobilisation to Site
Prepare and Submit CV of Civil Engr / Landscape Arch
Company Review and Approval
Civil Engr / Landscape Arch Mobilisation to Site
Prepare and Submit CV of Mechanical/Plumbing Engineer
Company Review and Approval

100%

100%

QR5,823.87

Prepare and Submit CV of QA/QC Engineer

20 23-Oct-12 A
3 23-Oct-12 A

12-Nov-12 A
25-Oct-12 A

100%
100%

100%
100%

QR31,060.62
QR5,823.87

Company Review and Approval

10 28-Oct-12 A

08-Nov-12 A

100%

100%

QR19,412.88

3 08-Nov-12 A 12-Nov-12 A

100%

100%

QR5,823.87

QA/QC Engineer Mobilisation to Site


Prepare and Submit CV of Safety Officer

QA/QC Engineer

QA/QC Engineer Mobilisation to Site


Safety Officer
Prepare and Submit CV of Safety Officer

20 23-Oct-12 A
3 23-Oct-12 A

12-Nov-12 A
25-Oct-12 A

100%
100%

100%
100%

QR31,060.62
QR5,823.87

Company Review and Approval

10 28-Oct-12 A

08-Nov-12 A

100%

100%

QR19,412.88

3 08-Nov-12 A 12-Nov-12 A

100%

100%

QR5,823.87

Prepare and Submit CV of Project Manager

20 08-Nov-12 A 28-Nov-12 A
3 08-Nov-12 A 12-Nov-12 A

100%
100%

100%
100%

QR31,060.62
QR5,823.87

Company Review and Approval

10 12-Nov-12 A 26-Nov-12 A

100%

100%

QR19,412.88

Safety Officer Mobilisation to Site


Planning Engineer

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Mechanical/Plumbing Engineer Mobilisation to Site


Prepare and Submit CV of QA/QC Engineer
Company Review and Approval

Company Review and Approval


Safety Officer Mobilisation to Site
Prepare and Submit CV of Project Manager
Company Review and Approval

Page 1 of 25

Activity Name

Original Start
Duration

Project Manager Mobilisation to Site

Finish

3 26-Nov-12 A 28-Nov-12 A

Electrical Engineer

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost

100%

100%

QR5,823.87

Prepare and Submit CV of Electrical Engineer

20 25-Oct-12 A
3 25-Oct-12 A

14-Nov-12 A
29-Oct-12 A

100%
100%

100%
100%

QR31,060.62
QR5,823.87

Company Review and Approval

10 29-Oct-12 A

12-Nov-12 A

100%

100%

QR19,412.88

3 12-Nov-12 A 14-Nov-12 A

100%

100%

QR5,823.87

Electrical Engineer Mobilisation to Site


Document Controller
Prepare and Submit CV of Document Controller

20 25-Oct-12 A
3 25-Oct-12 A

14-Nov-12 A
29-Oct-12 A

100%
100%

100%
100%

QR31,060.62
QR5,823.87

Company Review and Approval

10 29-Oct-12 A

12-Nov-12 A

100%

100%

QR19,412.88

3 12-Nov-12 A 14-Nov-12 A

100%

100%

QR5,823.87

Document Controller Mobilisation to Site


Site Office & Laydown Areas

2013
N

J Jul A

2014
S

31-Oct-12 A

100%

100%

QR11,647.73

Construction of Foundation for Site Offices

12 29-Oct-12 A

08-Nov-12 A

100%

100%

QR23,295.46

Installation of Prefabricated Portable Units for Site Offices

18 05-Nov-12 A 20-Nov-12 A

100%

100%

QR34,943.19

M.E.P.D Connections & Installations for Site Offices

18 12-Nov-12 A 27-Nov-12 A

100%

100%

QR34,943.19

Furniture Installation for Site Offices

14 27-Nov-12 A 10-Dec-12 A

100%

100%

QR27,178.04

Computer & Internet Installation for Site Offices

14 03-Dec-12 A

16-Dec-12 A

100%

100%

QR27,178.04

Testing & Commissioning for Site Offices

4 16-Dec-12 A

19-Dec-12 A

100%

100%

QR7,765.15

Testing & Commissioning for Site Offices

Start Function for Site Offices

1 19-Dec-12 A

20-Dec-12 A

100%

100%

QR1,941.29

Start Function for Site Offices

Prepare and submit Performance Bond

66 21-Oct-12 A
10 21-Oct-12 A

25-Dec-12 A
29-Oct-12 A

100%
100%

100%
100%

QR190,462.86
QR23,512.08

Prepare and submit Insurance Certificate

10 21-Oct-12 A

29-Oct-12 A

100%

100%

QR19,412.88

Project Quality Plan


First Submission
Prepare and submit Project Quality Plan

44 12-Nov-12 A 25-Dec-12 A
24 12-Nov-12 A 06-Dec-12 A
12 12-Nov-12 A 22-Nov-12 A

100%
100%
100%

100%
100%
100%

QR73,768.95
QR42,708.34
QR23,295.46

Company Review and Approval

10 22-Nov-12 A 06-Dec-12 A

100%

100%

QR19,412.88

Prepare and submit Project Quality Plan

20 06-Dec-12 A
6 06-Dec-12 A

25-Dec-12 A
11-Dec-12 A

100%
100%

100%
100%

QR31,060.61
QR11,647.73

Company Review and Approval

10 11-Dec-12 A

25-Dec-12 A

100%

100%

QR19,412.88

Prepare and submit HSE Plan

44 12-Nov-12 A 25-Dec-12 A
24 12-Nov-12 A 06-Dec-12 A
12 12-Nov-12 A 22-Nov-12 A

100%
100%
100%

100%
100%
100%

QR73,768.95
QR42,708.34
QR23,295.46

Company Review and Approval

10 22-Nov-12 A 06-Dec-12 A

100%

100%

QR19,412.88

Company Review and Approval

Prepare and submit HSE Plan

20 06-Dec-12 A
6 06-Dec-12 A

25-Dec-12 A
11-Dec-12 A

100%
100%

100%
100%

QR31,060.61
QR11,647.73

Prepare and submit HSE Plan

Company Review and Approval

10 11-Dec-12 A

25-Dec-12 A

100%

100%

QR19,412.88

Sourcing and evaluation of key subcontractors

64 08-Nov-12 A 03-Jan-13 A
60 08-Nov-12 A 31-Dec-12 A
18 08-Nov-12 A 25-Nov-12 A

100%
100%
100%

100%
100%
100%

QR357,117.94
QR182,401.98
QR42,629.21

Prepare and submit prequalification

21 18-Nov-12 A 06-Dec-12 A

100%

100%

QR40,767.06

Company review & approval

30 26-Nov-12 A 23-Dec-12 A

100%

100%

QR58,238.65

Finalization and award subcontract

21 13-Dec-12 A

31-Dec-12 A

100%

100%

QR40,767.06

Sourcing and evaluation of key suppliers

57 15-Nov-12 A 03-Jan-13 A
18 15-Nov-12 A 01-Dec-12 A

100%
100%

100%
100%

QR174,715.96
QR34,943.19

Prepare and submit prequalification

21 24-Nov-12 A 12-Dec-12 A

100%

100%

QR40,767.06

Company review & approval

30 03-Dec-12 A

29-Dec-12 A

100%

100%

QR58,238.65

Finalization with suppliers

21 17-Dec-12 A

03-Jan-13 A

100%

100%

QR40,767.06

540 23-Oct-12 A

12-Jun-14 A

100%

100%

QR1,047,545.47

120 23-Oct-12 A

05-Feb-13 A

100%

100%

QR89,089.66

Key Subcontractors and Suppliers


Key Subcontractors

Key Suppliers

ENGINEERING
Site Survey and Trial pit Excavation

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

J Jul A

S Oct N

Document Controller Mobilisation to Site

6 25-Oct-12 A

Final Submission

A M

Company Review and Approval

QR178,598.53
QR9,706.44

Health & Safety Environment (HSE) Plan


First Submission

Prepare and Submit CV of Document Controller

100%
100%

Final Submission

Electrical Engineer Mobilisation to Site

100%
100%

Submission of Early Documentation & Key Deliverables

Company Review and Approval

20-Dec-12 A
25-Oct-12 A

Levelling, Grading & Setting -Out for Site Offices & Lay Down Areas

Prepare and Submit CV of Electrical Engineer

60 21-Oct-12 A
5 21-Oct-12 A

Company to give location of Site Office & Lay Down Areas

Project Manager Mobilisation to Site

Company to give location of Site Office & Lay Down Areas


Levelling, Grading & Setting -Out for Site Offices & Lay Down Areas
Construction of Foundation for Site Offices
Installation of Prefabricated Portable Units for Site Offices
M.E.P.D Connections & Installations for Site Offices
Furniture Installation for Site Offices
Computer & Internet Installation for Site Offices

Prepare and submit Performance Bond


Prepare and submit Insurance Certificate

Prepare and submit Project Quality Plan


Company Review and Approval
Prepare and submit Project Quality Plan
Company Review and Approval

Prepare and submit HSE Plan

Company Review and Approval

Sourcing and evaluation of key subcontractors


Prepare and submit prequalification
Company review & approval
Finalization and award subcontract
Sourcing and evaluation of key suppliers
Prepare and submit prequalification
Company review & approval
Finalization with suppliers

Page 2 of 25

Activity Name

Original Start
Duration

Actual %
Complete

Planned %
Complete

COI-01 Total Cost

05-Feb-13 A

100%

100%

QR89,089.66

109 01-Nov-12 A 18-Feb-13 A

100%

100%

QR193,769.92

Prepare and submit design calculations for Car Park

47 08-Nov-12 A 26-Dec-12 A
25 08-Nov-12 A 03-Dec-12 A
12 08-Nov-12 A 19-Nov-12 A

100%
100%
100%

100%
100%
100%

QR34,680.65
QR20,151.95
QR12,887.60

Company review & approval

10 20-Nov-12 A 03-Dec-12 A

100%

100%

QR7,264.35

Prepare and submit design calculations for Car Park

22 03-Dec-12 A
10 03-Dec-12 A

26-Dec-12 A
12-Dec-12 A

100%
100%

100%
100%

QR14,528.70
QR7,264.35

Company review & approval

10 12-Dec-12 A

26-Dec-12 A

100%

100%

QR7,264.35

Prepare and submit structural shades & covered car parks

48 03-Dec-12 A
24 03-Dec-12 A
12 03-Dec-12 A

21-Jan-13 A
27-Dec-12 A
13-Dec-12 A

100%
100%
100%

100%
100%
100%

QR31,236.71
QR15,981.57
QR8,717.22

Company review & approval

10 16-Dec-12 A

27-Dec-12 A

100%

100%

QR7,264.35

Prepare and submit structural shades & covered car parks

24 27-Dec-12 A
11 27-Dec-12 A

21-Jan-13 A
07-Jan-13 A

100%
100%

100%
100%

QR15,255.14
QR7,990.79

Company review & approval

10 07-Jan-13 A

21-Jan-13 A

100%

100%

QR7,264.35

Company review & approval

Prepare and submit piping hydraulic calculations

49 01-Nov-12 A 20-Dec-12 A
25 01-Nov-12 A 26-Nov-12 A
12 01-Nov-12 A 12-Nov-12 A

100%
100%
100%

100%
100%
100%

QR31,963.14
QR15,981.57
QR8,717.22

Prepare and submit piping hydraulic calculations

Company review & approval

10 12-Nov-12 A 26-Nov-12 A

100%

100%

QR7,264.35

Prepare and submit piping hydraulic calculations

24 26-Nov-12 A 20-Dec-12 A
12 26-Nov-12 A 06-Dec-12 A

100%
100%

100%
100%

QR15,981.57
QR8,717.22

Company review & approval

10 06-Dec-12 A

Site Survey and Trial Pit Excavation

120 23-Oct-12 A

Submission and Approval of Design Calculations


Car Parks
First Submission

Final Submission

Structural Shades and Covered Car Parks


First Submission

Final Submission

Piping Hydraulic Calculations


First Submission

Final Submission

Finish

Total
Float

2013
N

J Jul A

10 02-Dec-12 A

13-Dec-12 A

100%

100%

QR7,264.35

Prepare and submit concrete foundations

25 13-Dec-12 A
12 13-Dec-12 A

07-Jan-13 A
24-Dec-12 A

100%
100%

100%
100%

QR15,981.57
QR8,717.22

Company review & approval

10 25-Dec-12 A

07-Jan-13 A

100%

100%

QR7,264.35

Prepare and submit electrical lighting & cable sizing

49 12-Nov-12 A 31-Dec-12 A
24 12-Nov-12 A 06-Dec-12 A
12 12-Nov-12 A 22-Nov-12 A

100%
100%
100%

100%
100%
100%

QR31,963.14
QR15,981.57
QR8,717.22

Company review & approval

10 22-Nov-12 A 06-Dec-12 A

100%

100%

QR7,264.35

Prepare and submit electrical lighting & cable sizing

25 06-Dec-12 A
12 06-Dec-12 A

31-Dec-12 A
17-Dec-12 A

100%
100%

100%
100%

QR15,981.57
QR8,717.22

Company review & approval

10 17-Dec-12 A

31-Dec-12 A

100%

100%

QR7,264.35

Company review & approval

Prepare and submit cables

49 31-Dec-12 A
24 31-Dec-12 A
12 31-Dec-12 A

18-Feb-13 A
24-Jan-13 A
10-Jan-13 A

100%
100%
100%

100%
100%
100%

QR31,963.14
QR15,981.57
QR8,717.22

Prepare and submit cables

Company review & approval

10 10-Jan-13 A

24-Jan-13 A

100%

100%

QR7,264.35

Company review & approval

25 24-Jan-13 A
12 24-Jan-13 A

18-Feb-13 A
04-Feb-13 A

100%
100%

100%
100%

QR15,981.57
QR8,717.22

Prepare and submit cables

10 04-Feb-13 A

18-Feb-13 A

100%

100%

QR7,264.35

482 20-Dec-12 A

12-Jun-14 A

100%

100%

QR764,685.89

Prepare & submit Design for Civil/Structural Works of Etrance Plaza

56
43
24
12

26-Dec-12 A
07-Jan-13 A
07-Jan-13 A
07-Jan-13 A

20-Feb-13 A
20-Feb-13 A
31-Jan-13 A
17-Jan-13 A

100%
100%
100%
100%

100%
100%
100%
100%

QR209,689.55
QR44,062.37
QR32,439.41
QR25,175.06

Company review and comments

10 20-Jan-13 A

31-Jan-13 A

100%

100%

QR7,264.35

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

S Oct N

Prepare and submit piping hydraulic calculations

Company review & approval

Civil and Structural Works


Entrance Plaza
Submission for Company Comments

J Jul A

Company review & approval

Prepare and submit concrete foundations

Company review & approval

A M

Prepare and submit structural shades & covered car parks

QR7,264.35

Submission and Approval of Detailed Engineering Drawings

Company review & approval

QR31,963.14
QR15,981.57
QR8,717.22

Prepare and submit cables

Prepare and submit structural shades & covered car parks

100%
100%
100%

Final Submission

Company review & approval

100%

Cable Submission
First Submission

Prepare and submit design calculations for Car Park

100%
100%
100%

Final Submission

Company review & approval

100%

Electrical Lighting and Cable Sizing


First Submission

Prepare and submit design calculations for Car Park

20-Dec-12 A

Final Submission

Site Survey and Trial Pit Excavation

49 19-Nov-12 A 07-Jan-13 A
24 19-Nov-12 A 13-Dec-12 A
12 19-Nov-12 A 29-Nov-12 A

Concrete Foundations
First Submission

2014

Company review & approval

Prepare and submit concrete foundations


Company review & approval
Prepare and submit concrete foundations
Company review & approval

Prepare and submit electrical lighting & cable sizing


Company review & approval
Prepare and submit electrical lighting & cable sizing

Company review & approval

Prepare & submit Design for Civil/Structural Works of Etrance Plaza


Company review and comments

Page 3 of 25

Activity Name

Original Start
Duration

Submission for Company Approval

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


QR11,622.96
QR4,358.61

2013
N

J Jul A

2014
S

Prepare & resubmit Design for Civil/Structural Works of Etrance Plaza

19 31-Jan-13 A
6 31-Jan-13 A

20-Feb-13 A
06-Feb-13 A

100%
100%

100%
100%

Company review and Approval

10 06-Feb-13 A

20-Feb-13 A

100%

100%

QR7,264.35

44
24
12
10

06-Jan-13 A
06-Jan-13 A
06-Jan-13 A
16-Jan-13 A

18-Feb-13 A
30-Jan-13 A
16-Jan-13 A
30-Jan-13 A

100%
100%
100%
100%

100%
100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22
QR7,264.35

Prepare & resubmit Design for Civil/Structural Works of Paved Pedestrian Plaz

20 30-Jan-13 A
6 30-Jan-13 A

18-Feb-13 A
04-Feb-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 05-Feb-13 A

18-Feb-13 A

100%

100%

QR7,264.35

Prepare & submit Design for Civil/Structural Works of Walkways & road crossin

44 26-Dec-12 A
25 26-Dec-12 A
12 26-Dec-12 A

07-Feb-13 A
20-Jan-13 A
06-Jan-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 06-Jan-13 A

20-Jan-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for Civil/Structural Works of Walkways & road cross

19 20-Jan-13 A
6 20-Jan-13 A

07-Feb-13 A
24-Jan-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 27-Jan-13 A

07-Feb-13 A

100%

100%

QR7,264.35

Prepare & submit Design for Civil/Structural Works of Gravel Beds & Boulders

44 26-Dec-12 A
25 26-Dec-12 A
12 26-Dec-12 A

07-Feb-13 A
20-Jan-13 A
06-Jan-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 06-Jan-13 A

20-Jan-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for Civil/Structural Works of Gravel Beds & Boulder

19 20-Jan-13 A
6 20-Jan-13 A

07-Feb-13 A
24-Jan-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 27-Jan-13 A

07-Feb-13 A

100%

100%

QR7,264.35

Prepare & submit Design for Civil/Structural Works of Site Grading & Drainage

44 26-Dec-12 A
25 26-Dec-12 A
12 26-Dec-12 A

07-Feb-13 A
20-Jan-13 A
06-Jan-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 06-Jan-13 A

20-Jan-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for Civil/Structural Works of Site Grading & Drainag

19 20-Jan-13 A
6 20-Jan-13 A

07-Feb-13 A
24-Jan-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 27-Jan-13 A

07-Feb-13 A

100%

100%

QR7,264.35

Prepare & submit Design for Civil/Structural Works of Car Parking

44 26-Dec-12 A
25 26-Dec-12 A
12 26-Dec-12 A

07-Feb-13 A
20-Jan-13 A
06-Jan-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 06-Jan-13 A

20-Jan-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for Civil/Structural Works of Car Parking

19 20-Jan-13 A
6 20-Jan-13 A

07-Feb-13 A
24-Jan-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 27-Jan-13 A

07-Feb-13 A

100%

100%

QR7,264.35

Prepare & submit Design for Civil/Structural Works of Edgers

44 26-Dec-12 A
25 26-Dec-12 A
12 26-Dec-12 A

07-Feb-13 A
20-Jan-13 A
06-Jan-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 06-Jan-13 A

20-Jan-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for Civil/Structural Works of Edgers

19 20-Jan-13 A
6 20-Jan-13 A

07-Feb-13 A
24-Jan-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 27-Jan-13 A

07-Feb-13 A

100%

100%

QR7,264.35

Company review and Approval

Prepare & submit Design for Plantings

65
44
24
12

06-Jan-13 A
06-Jan-13 A
06-Jan-13 A
06-Jan-13 A

11-Mar-13 A
18-Feb-13 A
30-Jan-13 A
16-Jan-13 A

100%
100%
100%
100%

100%
100%
100%
100%

QR82,813.59
QR27,604.53
QR15,981.57
QR8,717.22

Prepare & submit Design for Plantings

Company review and comments

10 16-Jan-13 A

30-Jan-13 A

100%

100%

QR7,264.35

20 30-Jan-13 A

18-Feb-13 A

100%

100%

QR11,622.96

Paved Pedestrian Plaza


Submission for Company Comments
Prepare & submit Design for Civil/Structural Works of Paved Pedestrian Plaza
Company review and comments
Submission for Company Approval

Walkways and Road Crossings


Submission for Company Comments

Submission for Company Approval

Gravel Beds and Boulders


Submission for Company Comments

Submission for Company Approval

Site Grading and Drainage


Submission for Company Comments

Submission for Company Approval

Car Parking
Submission for Company Comments

Submission for Company Approval

Edgers
Submission for Company Comments

Submission for Company Approval

Planting and Irrigation Distribution Work


Planting
Submission for Company Comments

Submission for Company Approval

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

A M

J Jul A

S Oct N

Prepare & resubmit Design for Civil/Structural Works of Etrance Plaza


Company review and Approval

Prepare & submit Design for Civil/Structural Works of Paved Pedestrian Plaza
Company review and comments
Prepare & resubmit Design for Civil/Structural Works of Paved Pedestrian Plaza
Company review and Approval

Prepare & submit Design for Civil/Structural Works of Walkways & road crossings
Company review and comments
Prepare & resubmit Design for Civil/Structural Works of Walkways & road crossings
Company review and Approval

Prepare & submit Design for Civil/Structural Works of Gravel Beds & Boulders
Company review and comments
Prepare & resubmit Design for Civil/Structural Works of Gravel Beds & Boulders
Company review and Approval

Prepare & submit Design for Civil/Structural Works of Site Grading & Drainage
Company review and comments
Prepare & resubmit Design for Civil/Structural Works of Site Grading & Drainage
Company review and Approval

Prepare & submit Design for Civil/Structural Works of Car Parking


Company review and comments
Prepare & resubmit Design for Civil/Structural Works of Car Parking
Company review and Approval

Prepare & submit Design for Civil/Structural Works of Edgers


Company review and comments
Prepare & resubmit Design for Civil/Structural Works of Edgers

Company review and comments

Page 4 of 25

Activity Name

Original Start
Duration

Prepare & resubmit Design for Plantings

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


QR4,358.61

6 30-Jan-13 A

04-Feb-13 A

100%

100%

10 05-Feb-13 A

18-Feb-13 A

100%

100%

QR7,264.35

Prepare & submit Design for Planting soils

44 16-Jan-13 A
25 16-Jan-13 A
12 16-Jan-13 A

28-Feb-13 A
10-Feb-13 A
27-Jan-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 27-Jan-13 A

10-Feb-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for Planting soils

19 10-Feb-13 A
6 10-Feb-13 A

28-Feb-13 A
14-Feb-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 17-Feb-13 A

28-Feb-13 A

100%

100%

QR7,264.35

Prepare & submit Design for Land Irrigation Distribution System

44 27-Jan-13 A
24 27-Jan-13 A
12 27-Jan-13 A

11-Mar-13 A
20-Feb-13 A
06-Feb-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 06-Feb-13 A

20-Feb-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for Land Irrigation Distribution System

20 20-Feb-13 A
6 20-Feb-13 A

11-Mar-13 A
25-Feb-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 26-Feb-13 A

11-Mar-13 A

100%

100%

QR7,264.35

Prepare & submit Design for structure of warehouse plaza

53
44
24
12

21-Jan-13 A
21-Jan-13 A
21-Jan-13 A
21-Jan-13 A

14-Mar-13 A
05-Mar-13 A
14-Feb-13 A
31-Jan-13 A

100%
100%
100%
100%

100%
100%
100%
100%

QR138,022.65
QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 31-Jan-13 A

14-Feb-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for structure of warehouse plaza

20 14-Feb-13 A
6 14-Feb-13 A

05-Mar-13 A
19-Feb-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 19-Feb-13 A

05-Mar-13 A

100%

100%

QR7,264.35

Prepare & submit Design for structure of Mosque Plaza

44 21-Jan-13 A
24 21-Jan-13 A
12 21-Jan-13 A

05-Mar-13 A
14-Feb-13 A
31-Jan-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 31-Jan-13 A

14-Feb-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for structure of Mosque Plaza

20 14-Feb-13 A
6 14-Feb-13 A

05-Mar-13 A
19-Feb-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 19-Feb-13 A

05-Mar-13 A

100%

100%

QR7,264.35

Prepare & submit Design for structure of Bus Plaza

43 31-Jan-13 A
25 31-Jan-13 A
12 31-Jan-13 A

14-Mar-13 A
25-Feb-13 A
11-Feb-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 11-Feb-13 A

25-Feb-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for structure of Bus Plaza

18 25-Feb-13 A
6 25-Feb-13 A

14-Mar-13 A
02-Mar-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 03-Mar-13 A

14-Mar-13 A

100%

100%

QR7,264.35

Prepare & submit Design for structure of walkways (2-Types)

43 31-Jan-13 A
25 31-Jan-13 A
12 31-Jan-13 A

14-Mar-13 A
25-Feb-13 A
11-Feb-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 11-Feb-13 A

25-Feb-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for structure of walkways (2-Types)

18 25-Feb-13 A
6 25-Feb-13 A

14-Mar-13 A
02-Mar-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 03-Mar-13 A

14-Mar-13 A

100%

100%

QR7,264.35

Prepare & submit Design for structure of parking areas

43 31-Jan-13 A
25 31-Jan-13 A
12 31-Jan-13 A

14-Mar-13 A
25-Feb-13 A
11-Feb-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 11-Feb-13 A

25-Feb-13 A

100%

100%

QR7,264.35

18 25-Feb-13 A

14-Mar-13 A

100%

100%

QR11,622.96

Company review and Approval


Planting Soil
Submission for Company Comments

Submission for Company Approval

Land Irrigation Distribution System


Submission for Company Comments

Submission for Company Approval

Shade Structure Works


Warehouse Plaza
Submission for Company Comments

Submission for Company Approval

Mosque Plaza
Submission for Company Comments

Submission for Company Approval

Bus Plaza
Submission for Company Comments

Submission for Company Approval

Walkways (2-Types)
Submission for Company Comments

Submission for Company Approval

Parking Areas
Submission for Company Comments

Submission for Company Approval

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

2013
N

J Jul A

2014
S

A M

J Jul A

S Oct N

Prepare & resubmit Design for Plantings


Company review and Approval

Prepare & submit Design for Planting soils


Company review and comments
Prepare & resubmit Design for Planting soils
Company review and Approval

Prepare & submit Design for Land Irrigation Distribution System


Company review and comments
Prepare & resubmit Design for Land Irrigation Distribution System
Company review and Approval

Prepare & submit Design for structure of warehouse plaza


Company review and comments
Prepare & resubmit Design for structure of warehouse plaza
Company review and Approval

Prepare & submit Design for structure of Mosque Plaza


Company review and comments
Prepare & resubmit Design for structure of Mosque Plaza
Company review and Approval

Prepare & submit Design for structure of Bus Plaza


Company review and comments
Prepare & resubmit Design for structure of Bus Plaza
Company review and Approval

Prepare & submit Design for structure of walkways (2-Types)


Company review and comments
Prepare & resubmit Design for structure of walkways (2-Types)
Company review and Approval

Prepare & submit Design for structure of parking areas


Company review and comments

Page 5 of 25

Activity Name

Original Start
Duration

Prepare & resubmit Design for structure of parking areas

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


QR4,358.61

6 25-Feb-13 A

02-Mar-13 A

100%

100%

10 03-Mar-13 A

14-Mar-13 A

100%

100%

QR7,264.35

Prepare & submit Design for primary entrance ID

75
43
24
12

31-Dec-12 A
31-Dec-12 A
31-Dec-12 A
31-Dec-12 A

17-Mar-13 A
13-Feb-13 A
24-Jan-13 A
10-Jan-13 A

100%
100%
100%
100%

100%
100%
100%
100%

QR165,627.18
QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 10-Jan-13 A

24-Jan-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for primary entrance ID

19 24-Jan-13 A
6 24-Jan-13 A

13-Feb-13 A
30-Jan-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 30-Jan-13 A

13-Feb-13 A

100%

100%

QR7,264.35

Prepare & submit Design for secondary entrance ID

43 31-Dec-12 A
24 31-Dec-12 A
12 31-Dec-12 A

13-Feb-13 A
24-Jan-13 A
10-Jan-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 10-Jan-13 A

24-Jan-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for secondary entrance ID

19 24-Jan-13 A
6 24-Jan-13 A

13-Feb-13 A
30-Jan-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 30-Jan-13 A

13-Feb-13 A

100%

100%

QR7,264.35

Prepare & submit Design for primary vehicular directions

44 10-Jan-13 A
25 10-Jan-13 A
12 10-Jan-13 A

24-Feb-13 A
04-Feb-13 A
21-Jan-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 21-Jan-13 A

04-Feb-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for primary vehicular directions

19 04-Feb-13 A
6 04-Feb-13 A

24-Feb-13 A
10-Feb-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 10-Feb-13 A

24-Feb-13 A

100%

100%

QR7,264.35

Prepare & submit Design for secondary vehicular directions

44 10-Jan-13 A
25 10-Jan-13 A
12 10-Jan-13 A

24-Feb-13 A
04-Feb-13 A
21-Jan-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 21-Jan-13 A

04-Feb-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for secondary vehicular directions

19 04-Feb-13 A
6 04-Feb-13 A

24-Feb-13 A
10-Feb-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 10-Feb-13 A

24-Feb-13 A

100%

100%

QR7,264.35

Prepare & submit Design for pedestrian directions

43 21-Jan-13 A
24 21-Jan-13 A
12 21-Jan-13 A

06-Mar-13 A
14-Feb-13 A
31-Jan-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 31-Jan-13 A

14-Feb-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for pedestrian directions

19 14-Feb-13 A
6 14-Feb-13 A

06-Mar-13 A
20-Feb-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 20-Feb-13 A

06-Mar-13 A

100%

100%

QR7,264.35

Prepare & submit Design for free standing building

44 31-Jan-13 A
25 31-Jan-13 A
12 31-Jan-13 A

17-Mar-13 A
25-Feb-13 A
11-Feb-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 11-Feb-13 A

25-Feb-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for free standing building

19 25-Feb-13 A
6 25-Feb-13 A

17-Mar-13 A
03-Mar-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 03-Mar-13 A

17-Mar-13 A

100%

100%

QR7,264.35

31-Dec-12 A
31-Dec-12 A
31-Dec-12 A
31-Dec-12 A

12-Jun-14 A
13-Feb-13 A
24-Jan-13 A
10-Jan-13 A

100%
100%
100%
100%

100%
100%
100%
100%

QR110,418.12
QR27,604.53
QR15,981.57
QR8,717.22

10 10-Jan-13 A

24-Jan-13 A

100%

100%

QR7,264.35

Company review and Approval


Signage Works
Primary Entrance ID
Submission for Company Comments

Submission for Company Approval

Secondary Entrance ID
Submission for Company Comments

Submission for Company Approval

Primary Vehicular Directions


Submission for Company Comments

Submission for Company Approval

Secondary Vehicular Directions


Submission for Company Comments

Submission for Company Approval

Pedestrian Directions
Submission for Company Comments

Submission for Company Approval

Free Standing Building ID


Submission for Company Comments

Submission for Company Approval

Electrical Works
Lighting in the Car Parking Areas
Submission for Company Comments
Prepare & submit Design for lighting in the car parking areas
Company review and comments

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

471
43
24
12

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

2013
N

J Jul A

2014
S

A M

J Jul A

S Oct N

Prepare & resubmit Design for structure of parking areas


Company review and Approval

Prepare & submit Design for primary entrance ID


Company review and comments
Prepare & resubmit Design for primary entrance ID
Company review and Approval

Prepare & submit Design for secondary entrance ID


Company review and comments
Prepare & resubmit Design for secondary entrance ID
Company review and Approval

Prepare & submit Design for primary vehicular directions


Company review and comments
Prepare & resubmit Design for primary vehicular directions
Company review and Approval

Prepare & submit Design for secondary vehicular directions


Company review and comments
Prepare & resubmit Design for secondary vehicular directions
Company review and Approval

Prepare & submit Design for pedestrian directions


Company review and comments
Prepare & resubmit Design for pedestrian directions
Company review and Approval

Prepare & submit Design for free standing building


Company review and comments
Prepare & resubmit Design for free standing building
Company review and Approval

Prepare & submit Design for lighting in the car parking areas
Company review and comments

Page 6 of 25

Activity Name

Original Start
Duration

Submission for Company Approval

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


QR11,622.96
QR4,358.61

2013
N

J Jul A

2014
S

A M

J Jul A

S Oct N

Prepare & resubmit Design for lighting in the car parking areas

19 24-Jan-13 A
6 24-Jan-13 A

13-Feb-13 A
30-Jan-13 A

100%
100%

100%
100%

Company review and Approval

10 30-Jan-13 A

13-Feb-13 A

100%

100%

QR7,264.35

Prepare & submit Design for low level bollard

44 10-Jan-13 A
25 10-Jan-13 A
12 10-Jan-13 A

24-Feb-13 A
04-Feb-13 A
21-Jan-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 21-Jan-13 A

04-Feb-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for low level bollard

19 04-Feb-13 A
6 04-Feb-13 A

24-Feb-13 A
10-Feb-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 10-Feb-13 A

24-Feb-13 A

100%

100%

QR7,264.35

Prepare & submit Design for underwater lights in the water fountain

43 21-Jan-13 A
24 21-Jan-13 A
12 21-Jan-13 A

06-Mar-13 A
14-Feb-13 A
31-Jan-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

Company review and comments

10 31-Jan-13 A

14-Feb-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for underwater lights in the water fountain

19 14-Feb-13 A
6 14-Feb-13 A

06-Mar-13 A
20-Feb-13 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Company review and Approval

10 20-Feb-13 A

06-Mar-13 A

100%

100%

QR7,264.35

440 31-Jan-13 A
25 31-Jan-13 A
12 31-Jan-13 A

12-Jun-14 A
25-Feb-13 A
11-Feb-13 A

100%
100%
100%

100%
100%
100%

QR27,604.53
QR15,981.57
QR8,717.22

10 11-Feb-13 A

25-Feb-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for lighting for fountain sculpture

28 20-Mar-14 A
6 20-Mar-14 A

12-Jun-14 A
25-Mar-14 A

100%
100%

100%
100%

QR11,622.96
QR4,358.61

Prepare & resubmit Design for l

Company review and Approval

10 03-Apr-14 A

12-Jun-14 A

100%

100%

QR7,264.35

Company review and

Prepare & submit Design for service water network

91
46
25
12

20-Dec-12 A
20-Dec-12 A
20-Dec-12 A
20-Dec-12 A

21-Mar-13 A
04-Feb-13 A
14-Jan-13 A
31-Dec-12 A

100%
100%
100%
100%

100%
100%
100%
100%

QR58,114.80
QR29,057.40
QR15,981.57
QR8,717.22

Company review and comments

10 31-Dec-12 A

14-Jan-13 A

100%

100%

QR7,264.35

Prepare & resubmit Design for service water network

21 14-Jan-13 A
8 14-Jan-13 A

04-Feb-13 A
21-Jan-13 A

100%
100%

100%
100%

QR13,075.83
QR5,811.48

Company review and Approval

10 21-Jan-13 A

04-Feb-13 A

100%

100%

QR7,264.35

Prepare & submit Design for irrigation water network

45 04-Feb-13 A
24 04-Feb-13 A
12 04-Feb-13 A

21-Mar-13 A
28-Feb-13 A
14-Feb-13 A

100%
100%
100%

100%
100%
100%

QR29,057.40
QR15,981.57
QR8,717.22

Company review and comments

10 14-Feb-13 A

28-Feb-13 A

100%

100%

QR7,264.35

21 28-Feb-13 A
8 28-Feb-13 A

21-Mar-13 A
07-Mar-13 A

100%
100%

100%
100%

QR13,075.83
QR5,811.48

Low Level bollard


Submission for Company Comments

Submission for Company Approval

Underwater Lights in the Water Fountain


Submission for Company Comments

Submission for Company Approval

Lighting for Fountain Sculpture


Submission for Company Comments
Prepare & submit Design for lighting for fountain sculpture
Company review and comments
Submission for Company Approval

Mechanical Works
Service Water Network
Submission for Company Comments

Submission for Company Approval

Irrigation Water Network


Submission for Company Comments

Submission for Company Approval


Prepare & resubmit Design for irrigation water network
Company review and Approval

Prepare & resubmit Design for lighting in the car parking areas
Company review and Approval

Prepare & submit Design for low level bollard


Company review and comments
Prepare & resubmit Design for low level bollard
Company review and Approval

Prepare & submit Design for underwater lights in the water fountain
Company review and comments
Prepare & resubmit Design for underwater lights in the water fountain
Company review and Approval

Prepare & submit Design for lighting for fountain sculpture


Company review and comments

Prepare & submit Design for service water network


Company review and comments
Prepare & resubmit Design for service water network
Company review and Approval

Prepare & submit Design for irrigation water network


Company review and comments
Prepare & resubmit Design for irrigation water network

10 07-Mar-13 A

21-Mar-13 A

100%

100%

QR7,264.35

423 04-Feb-13 A

12-Jun-14 A

100%

100%

QR3,561,656.18

345 04-Feb-13 A

28-Feb-14 A

100%

100%

QR1,237,805.96

Prepare & submit materials for interlocks/kerbs/tree gurads

36 18-Feb-13 A
19 18-Feb-13 A
6 18-Feb-13 A

26-Mar-13 A
10-Mar-13 A
24-Feb-13 A

100%
100%
100%

100%
100%
100%

QR137,534.00
QR77,207.75
QR30,802.94

Company Review & approval

10 24-Feb-13 A

10-Mar-13 A

100%

100%

QR46,404.81

Company Review & approval

Prepare & submit materials for interlocks/kerbs/tree gurads

16 10-Mar-13 A
3 10-Mar-13 A

26-Mar-13 A
12-Mar-13 A

100%
100%

100%
100%

QR60,326.25
QR13,921.44

Prepare & submit materials for interlocks/kerbs/tree gurads

Company Review & approval

10 12-Mar-13 A

26-Mar-13 A

100%

100%

QR46,404.81

36 05-Mar-13 A
19 05-Mar-13 A

10-Apr-13 A
25-Mar-13 A

100%
100%

100%
100%

QR137,534.00
QR77,207.75

PROCUREMENT
Materials Submission and Approval
Interlock pavers, kerb stones and tree guards
First Submission

Final Submission

Foundation bolts
First Submission

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Company review and Approval

Prepare & submit materials for interlocks/kerbs/tree gurads

Company Review & approval

Page 7 of 25

Activity Name

Original Start
Duration

Prepare & submit materials for foundation bolts

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


O

2013
N

J Jul A

2014
S

A M

J Jul A

S Oct N

6 05-Mar-13 A

11-Mar-13 A

100%

100%

QR30,802.94

10 11-Mar-13 A

25-Mar-13 A

100%

100%

QR46,404.81

Company Review & approval

Prepare & submit materials for foundation bolts

16 25-Mar-13 A
3 25-Mar-13 A

10-Apr-13 A
27-Mar-13 A

100%
100%

100%
100%

QR60,326.25
QR13,921.44

Prepare & submit materials for foundation bolts

Company Review & approval

10 27-Mar-13 A

10-Apr-13 A

100%

100%

QR46,404.81

Prepare & submit materials for main piping materials

36 04-Feb-13 A
19 04-Feb-13 A
6 04-Feb-13 A

12-Mar-13 A
24-Feb-13 A
10-Feb-13 A

100%
100%
100%

100%
100%
100%

QR137,534.00
QR77,207.75
QR30,802.94

Company Review & approval

10 10-Feb-13 A

24-Feb-13 A

100%

100%

QR46,404.81

Company Review & approval

Prepare & submit materials for main piping materials

16 24-Feb-13 A
3 24-Feb-13 A

12-Mar-13 A
26-Feb-13 A

100%
100%

100%
100%

QR60,326.25
QR13,921.44

Prepare & submit materials for main piping materials

Company Review & approval

10 26-Feb-13 A

12-Mar-13 A

100%

100%

QR46,404.81

Prepare & submit materials for shade structures & fabric materials

35 14-Mar-13 A
19 14-Mar-13 A
6 14-Mar-13 A

18-Apr-13 A
03-Apr-13 A
20-Mar-13 A

100%
100%
100%

100%
100%
100%

QR137,534.00
QR77,207.75
QR30,802.94

Company Review & approval

10 20-Mar-13 A

03-Apr-13 A

100%

100%

QR46,404.81

Company Review & approval

Prepare & submit materials for shade structures & fabric materials

16 03-Apr-13 A
3 03-Apr-13 A

18-Apr-13 A
06-Apr-13 A

100%
100%

100%
100%

QR60,326.25
QR13,921.44

Prepare & submit materials for shade structures & fabric materials

Company Review & approval

10 07-Apr-13 A

18-Apr-13 A

100%

100%

QR46,404.81

Prepare & submit materials for signage structures

36 13-Feb-13 A
20 13-Feb-13 A
6 13-Feb-13 A

20-Mar-13 A
04-Mar-13 A
18-Feb-13 A

100%
100%
100%

100%
100%
100%

QR137,534.00
QR77,207.75
QR30,802.94

Company Review & approval

10 18-Feb-13 A

04-Mar-13 A

100%

100%

QR46,404.81

Company Review & approval

Prepare & submit materials for signage structures

16 04-Mar-13 A
3 04-Mar-13 A

20-Mar-13 A
06-Mar-13 A

100%
100%

100%
100%

QR60,326.25
QR13,921.44

Prepare & submit materials for signage structures

Company Review & approval

10 07-Mar-13 A

20-Mar-13 A

100%

100%

QR46,404.81

330 20-Feb-13 A
20 20-Feb-13 A
6 20-Feb-13 A

27-Feb-14 A
11-Mar-13 A
25-Feb-13 A

100%
100%
100%

100%
100%
100%

QR137,533.99
QR77,207.74
QR30,802.93

10 26-Feb-13 A

11-Mar-13 A

100%

100%

QR46,404.81

Prepare & submit materials for fountain sculpture

16 31-Dec-13 A
3 31-Dec-13 A

27-Feb-14 A
27-Feb-14 A

100%
100%

100%
100%

QR60,326.25
QR13,921.44

Prepare & submit materials for foun

Company Review & approval

10 02-Jan-14 A

27-Feb-14 A

100%

100%

QR46,404.81

Company Review & approval

Prepare & submit materials for electrical poles/DBs & Controls

36 06-Mar-13 A
20 06-Mar-13 A
6 06-Mar-13 A

10-Apr-13 A
25-Mar-13 A
11-Mar-13 A

100%
100%
100%

100%
100%
100%

QR137,533.99
QR77,207.74
QR30,802.93

Company Review & approval

10 11-Mar-13 A

25-Mar-13 A

100%

100%

QR46,404.81

Company Review & approval

Prepare & submit materials for electrical poles/DBs & Controls

16 25-Mar-13 A
3 25-Mar-13 A

10-Apr-13 A
27-Mar-13 A

100%
100%

100%
100%

QR60,326.25
QR13,921.44

Prepare & submit materials for electrical poles/DBs & Controls

Company Review & approval

10 28-Mar-13 A

10-Apr-13 A

100%

100%

QR46,404.81

Company Review & approval

Prepare & submit materials for valves & pumps

50 04-Feb-13 A
19 04-Feb-13 A
6 04-Feb-13 A

28-Feb-14 A
24-Feb-13 A
10-Feb-13 A

100%
100%
100%

100%
100%
100%

QR137,533.99
QR77,207.74
QR30,802.93

Prepare & submit materials for valves & pumps

Company Review & approval

10 10-Feb-13 A

24-Feb-13 A

100%

100%

QR46,404.81

Prepare & submit materials for valves & pumps

31 24-Feb-13 A
20 24-Feb-13 A

28-Feb-14 A
28-Feb-14 A

100%
100%

100%
100%

QR60,326.25
QR13,921.44

Prepare & submit materials for valv

Company Review & approval

10 13-Mar-13 A

28-Feb-14 A

100%

100%

QR46,404.81

Company Review & approval

61 21-Mar-13 A
19 21-Mar-13 A
6 21-Mar-13 A

22-May-13 A
10-Apr-13 A
27-Mar-13 A

100%
100%
100%

100%
100%
100%

QR137,533.99
QR77,207.74
QR30,802.93

Company Review & approval


Final Submission

Main piping material


First Submission

Final Submission

Shade structures including fabric material


First Submission

Final Submission

Signage structures
First Submission

Final Submission

Fountain sculpture
First Submission
Prepare & submit materials for fountain sculpture
Company Review & approval
Final Submission

Electrical Poles, DBs and Field Controls


First Submission

Final Submission

Valves and pumps


First Submission

Final Submission

Irrigation distribution accessories


First Submission
Prepare & submit materials for irrigation distribution accessories

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Prepare & submit materials for foundation bolts

Company Review & approval

Prepare & submit materials for main piping materials

Company Review & approval

Prepare & submit materials for shade structures & fabric materials

Company Review & approval

Prepare & submit materials for signage structures

Company Review & approval

Prepare & submit materials for fountain sculpture


Company Review & approval

Prepare & submit materials for electrical poles/DBs & Controls

Company Review & approval

Prepare & submit materials for irrigation distribution accessories

Page 8 of 25

Activity Name

Original Start
Duration

Company Review & approval

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


O

10 27-Mar-13 A

10-Apr-13 A

100%

100%

QR46,404.81

Prepare & submit materials for irrigation distribution accessories

42 10-Apr-13 A
24 10-Apr-13 A

22-May-13 A
01-May-13 A

100%
100%

100%
100%

QR60,326.25
QR13,921.44

Company Review & approval

15 01-May-13 A 22-May-13 A

100%

100%

QR46,404.81

Final Submission

Placing of Orders and First Delivery to Project Site

432 12-Mar-13 A

12-Jun-14 A

100%

100%

QR2,323,850.22

Placing of Orders for interlocks/kerbs/tree guards

15 26-Mar-13 A
4 26-Mar-13 A

08-Apr-13 A
30-Mar-13 A

100%
100%

100%
100%

QR71,138.27
QR20,092.98

Manufacturing & shipment

10 30-Mar-13 A

08-Apr-13 A

100%

100%

QR46,404.81

1 08-Apr-13 A

08-Apr-13 A

100%

100%

QR4,640.48

Placing of Orders for foundation bolts

27 10-Apr-13 A
5 10-Apr-13 A

04-May-13 A
15-Apr-13 A

100%
100%

100%
100%

QR128,048.89
QR25,958.31

Manufacturing & shipment

21 15-Apr-13 A

04-May-13 A

100%

100%

QR97,450.10

1 04-May-13 A 04-May-13 A

100%

100%

QR4,640.48

Interlock pavers, kerb stones and tree guards

Delivery arrive on site


Foundation bolts

Delivery arrive on site


Main piping material
Placing of Orders for main piping materials

66 12-Mar-13 A
5 12-Mar-13 A

09-May-13 A
17-Mar-13 A

100%
100%

100%
100%

QR313,008.40
QR29,939.08

Manufacturing & shipment

60 17-Mar-13 A

08-May-13 A

100%

100%

QR278,428.84

1 08-May-13 A 09-May-13 A

100%

100%

QR4,640.48

Delivery arrive on site


Shade structures including fabric material
Placing of Orders for shade structures & fabric materials
Manufacturing & shipment
First Delivery arrive on site

381 18-Apr-13 A
4 18-Apr-13 A

03-Apr-14 A
22-Apr-13 A

100%
100%

100%
100%

QR237,127.57
QR18,561.92

45 22-Apr-13 A

03-Apr-14 A

100%

100%

QR213,925.17

1 27-Mar-14 A

03-Apr-14 A

100%

100%

QR4,640.48

384 20-Mar-13 A
5 20-Mar-13 A

27-Feb-14 A
25-Mar-13 A

100%
100%

100%
100%

QR241,870.12
QR28,408.01

45 25-Mar-13 A

27-Feb-14 A

100%

100%

QR208,821.63

1 26-Feb-14 A

27-Feb-14 A

100%

100%

QR4,640.48

414 28-Mar-13 A
5 28-Mar-13 A

12-Jun-14 A
02-Apr-13 A

100%
100%

100%
100%

QR369,919.02
QR31,163.93

72 02-Apr-13 A

03-Apr-14 A

100%

100%

QR334,114.61

1 03-Apr-14 A

12-Jun-14 A

100%

100%

QR4,640.48

Placing of Orders for poles/DBs & Controls

62 10-Apr-13 A
5 10-Apr-13 A

04-Jun-13 A
15-Apr-13 A

100%
100%

100%
100%

QR294,038.19
QR29,530.79

Manufacturing & shipment

56 15-Apr-13 A

03-Jun-13 A

100%

100%

QR259,866.92

1 03-Jun-13 A

04-Jun-13 A

100%

100%

QR4,640.48

Placing of Orders for valves & pumps

96 27-Mar-13 A
5 27-Mar-13 A

03-Apr-14 A
01-Apr-13 A

100%
100%

100%
100%

QR455,284.94
QR33,001.20

Manufacturing & shipment

90 01-Apr-13 A

31-Mar-14 A

100%

100%

QR417,643.26

1 18-Jun-13 A

03-Apr-14 A

100%

100%

QR4,640.48

Placing of Orders for irrigation & distribution accessories

45 22-May-13 A 01-Jul-13 A
4 22-May-13 A 26-May-13 A

100%
100%

100%
100%

QR213,414.82
QR23,155.11

Manufacturing & shipment

40 26-May-13 A 30-Jun-13 A

100%

100%

QR185,619.23

Signage structures
Placing of Orders for sinage structures
Manufacturing & shipment
Delivery arrive on site
Fountain sculpture
Placing of Orders for fountain sculpture
Manufacturing & shipment
Delivery arrive on site
Electrical Poles, DBs and Field Controls

Delivery arrive on site


Valves and pumps

Delivery arrive on site


Irrigation distribution accessories

Delivery arrive on site

1 30-Jun-13 A

100%

100%

QR4,640.48

CONSTRUCTION

565 20-Feb-13 A

08-Jul-14

22

99.01%

100%

QR12,989,568.83

564 20-Feb-13 A

30-Jun-14

23

98.72%

100%

QR4,609,201.93

564
200
109
21

20-Feb-13 A
20-Feb-13 A
20-Feb-13 A
20-Feb-13 A

30-Jun-14
23-Jan-14 A
27-May-13 A
11-Mar-13 A

23

98.76%
100%
100%
100%

100%
100%
100%
100%

QR3,771,165.17
QR979,862.42
QR287,597.98
QR99,850.14

6 11-Mar-13 A

16-Mar-13 A

100%

100%

QR5,338.80

25 03-Mar-13 A

25-Mar-13 A

100%

100%

QR22,245.00

Phase 1 Works
Construction
Zone 1
Open car park paving - Kerb and interlock paving works
Earthworks excavation
Disposal of waste materials
Subgrade formation

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

01-Jul-13 A

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

2013
N

J Jul A

2014
S

A M

J Jul A

S Oct N

Company Review & approval


Prepare & submit materials for irrigation distribution accessories
Company Review & approval

Placing of Orders for interlocks/kerbs/tree guards


Manufacturing & shipment
Delivery arrive on site
Placing of Orders for foundation bolts
Manufacturing & shipment
Delivery arrive on site
Placing of Orders for main piping materials
Manufacturing & shipment
Delivery arrive on site
Placing of Orders for shade structures & fabric materials
Manufacturing & shipment
First Delivery arrive on site
Placing of Orders for sinage structures
Manufacturing & shipment
Delivery arrive on site
Placing of Orders for fountain sculpture
Manufacturing & shipment
Delivery arrive on site
Placing of Orders for poles/DBs & Controls
Manufacturing & shipment
Delivery arrive on site
Placing of Orders for valves & pumps
Manufacturing & shipment
Delivery arrive on site
Placing of Orders for irrigation & distribution accessories
Manufacturing & shipment
Delivery arrive on site

Earthworks excavation
Disposal of waste materials
Subgrade formation

Page 9 of 25

Activity Name

Original Start
Duration

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


O

2013
N

2014

J Jul A

Concrete foundation for kerbstones

45 13-Mar-13 A

22-Apr-13 A

100%

100%

QR40,041.01

Fix kerbs and supports

45 08-Apr-13 A

18-May-13 A

100%

100%

QR40,041.01

Fix kerbs and supports

Aggregate subbase and fill compaction

45 14-Apr-13 A

23-May-13 A

100%

100%

QR40,041.01

Aggregate subbase and fill compaction

Paving works

45 17-Apr-13 A

27-May-13 A

100%

100%

QR40,041.01

Paving works

Excavation for network line pipes

83 18-May-13 A 29-Jul-13 A
21 18-May-13 A 05-Jun-13 A

100%
100%

100%
100%

QR61,396.20
QR18,685.80

Install HDPE network line pipes

21 01-Jul-13 A

18-Jul-13 A

100%

100%

QR18,685.80

Install HDPE network line pipes

Backfilling and compaction

21 06-Jul-13 A

24-Jul-13 A

100%

100%

QR18,685.80

Backfilling and compaction

6 24-Jul-13 A

29-Jul-13 A

100%

100%

QR5,338.80

88 11-Mar-13 A
21 11-Mar-13 A

31-Dec-13 A
28-Mar-13 A

100%
100%

100%
100%

QR206,433.64
QR18,685.80

Irrigation piping main laying

Pre-testing of irrigation
Kerb, plant edgers and interlock paving works
Earthworks excavation
Disposal of waste materials

6 28-Mar-13 A

03-Apr-13 A

100%

100%

QR5,338.80

Subgrade formation

25 21-Mar-13 A

11-Apr-13 A

100%

100%

QR22,245.00

Concrete foundation for kerbstones

40 26-Mar-13 A

30-Apr-13 A

100%

100%

QR40,041.01

Fix kerbs and supports

40 08-Apr-13 A

13-May-13 A

100%

100%

QR40,041.01

Aggregate subbase and fill compaction

45 14-Apr-13 A

23-May-13 A

100%

100%

QR40,041.01

Paving works

45 17-Apr-13 A

31-Dec-13 A

100%

100%

QR40,041.01

Excavation for area lightings

58 30-Apr-13 A
30 30-Apr-13 A

20-Jun-13 A
27-May-13 A

100%
100%

100%
100%

QR85,420.80
QR26,694.00

Install cables below the ground

30 09-May-13 A 04-Jun-13 A

100%

100%

QR26,694.00

Backfilling and compaction

30 20-May-13 A 15-Jun-13 A

100%

100%

QR26,694.00

Area lighting and control cable laying

Pre-testing of area lighting

6 15-Jun-13 A

A M

J Jul A

Excavation for network line pipes

Pre-testing of irrigation
Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for kerbstones
Fix kerbs and supports
Aggregate subbase and fill compaction
Paving works
Excavation for area lightings
Install cables below the ground
Backfilling and compaction

20-Jun-13 A

100%

100%

QR5,338.80

Fix shade structure concrete foundations

64 13-May-13 A 08-Jul-13 A
15 13-May-13 A 27-May-13 A

100%
100%

100%
100%

QR66,735.00
QR13,347.00

Fix shade structural elements

30 02-Jun-13 A

27-Jun-13 A

100%

100%

QR26,694.00

Fix fabric shades

30 12-Jun-13 A

08-Jul-13 A

100%

100%

QR26,694.00

Fix signage structure concrete foundations

33 27-May-13 A 24-Jun-13 A
15 27-May-13 A 09-Jun-13 A

100%
100%

100%
100%

QR29,363.40
QR13,347.00

Fix signage

18 09-Jun-13 A

24-Jun-13 A

100%

100%

QR16,016.40

Fix foundations for light poles, DBs & field Controls

30 04-Jun-13 A
30 04-Jun-13 A

01-Jul-13 A
01-Jul-13 A

100%
100%

100%
100%

QR53,388.00
QR26,694.00

Fix foundations for light poles, DBs & field Controls

Fix light poles, DBs & field control

30 04-Jun-13 A

01-Jul-13 A

100%

100%

QR26,694.00

Fix light poles, DBs & field control

27 05-Jun-13 A
21 05-Jun-13 A

19-Jan-14 A
31-Dec-13 A

100%
100%

100%
100%

QR24,024.60
QR18,685.80

6 24-Jun-13 A

19-Jan-14 A

100%

100%

QR5,338.80

Shade structures erection

Signage structures erection

Electrical Poles, DBs and Field Controls

Zone valves's installation


Fix foundations for zone valves
Fix valves
Irrigation lateral piping & distribution accessories

Pre-testing of area lighting


Fix shade structure concrete foundations
Fix shade structural elements
Fix fabric shades
Fix signage structure concrete foundations
Fix signage

Fix foundations for zone valves


Fix valves

Install drip lines for shrubs & ground covers

36 14-Jul-13 A
30 14-Jul-13 A

23-Jan-14 A
12-Aug-13 A

100%
100%

100%
100%

QR112,114.80
QR26,694.00

Install sprinklers for lawn

30 14-Jul-13 A

12-Aug-13 A

100%

100%

QR26,694.00

Install sprinklers for lawn

Install bublers for palm & trees

30 14-Jul-13 A

12-Aug-13 A

100%

100%

QR26,694.00

Install bublers for palm & trees

Install automation & time controls

30 14-Jul-13 A

12-Aug-13 A

100%

100%

QR26,694.00

Install automation & time controls

23-Jan-14 A

100%

100%

QR5,338.80

Hardscaping works

40 13-May-13 A 17-Jun-13 A
30 13-May-13 A 09-Jun-13 A

100%
100%

100%
100%

QR53,388.00
QR26,694.00

Hardscaping works

Finishing Works

30 22-May-13 A 17-Jun-13 A

100%

100%

QR26,694.00

Finishing Works

97.66%
100%
100%

100%
100%
100%

QR855,987.67
QR86,310.61
QR18,685.80

Pre-testing of irrigation

6 12-Aug-13 A

Hardscape and finishing works

Zone 2
Concrete foundations for water tanks
Earthworks excavation
Disposal of waste materials
Subgrade formation

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

543 11-Mar-13 A
69 11-Mar-13 A
21 11-Mar-13 A

30-Jun-14
11-Jan-14 A
28-Mar-13 A

23

6 28-Mar-13 A

03-Apr-13 A

100%

100%

QR5,338.80

25 21-Mar-13 A

31-Dec-13 A

100%

100%

QR22,245.00

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

S Oct N

Concrete foundation for kerbstones

Install drip lines for shrubs & ground covers

Pre-testing of irrigation

Earthworks excavation
Disposal of waste materials
Subgrade formation

Page 10 of 25

Activity Name

Original Start
Duration

Concrete foundation for plaza shades and water tanks

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


O

2013
N

2014

J Jul A

A M

J Jul A

S Oct N

45 01-Apr-13 A

11-Jan-14 A

100%

100%

QR40,041.01

Excavation for network line pipes

156 05-Jun-13 A
130 05-Jun-13 A

18-Jan-14 A
01-Oct-13 A

100%
100%

100%
100%

QR125,461.80
QR84,531.00

Excavation for network line pipes

Install HDPE network line pipes

122 20-Jun-13 A

10-Oct-13 A

100%

100%

QR17,796.00

Install HDPE network line pipes

Backfilling and compaction

120 27-Jun-13 A

19-Oct-13 A

100%

100%

QR17,796.00

10 19-Oct-13 A

18-Jan-14 A

100%

100%

QR5,338.80

89 11-Mar-13 A
21 11-Mar-13 A

10-Apr-14 A
28-Mar-13 A

100%
100%

100%
100%

QR206,433.64
QR18,685.80

6 03-Apr-13 A

08-Apr-13 A

100%

100%

QR5,338.80

Subgrade formation

25 21-Mar-13 A

11-Apr-13 A

100%

100%

QR22,245.00

Concrete foundation for kerbstones

45 01-Apr-13 A

13-Mar-14 A

100%

100%

QR40,041.01

Fix kerbs and supports

45 09-Apr-13 A

22-Mar-14 A

100%

100%

QR40,041.01

Fix kerbs and supports

Aggregate subbase and fill compaction

45 15-Apr-13 A

27-Mar-14 A

100%

100%

QR40,041.01

Aggregate subbase and fill com

Paving works

45 18-Apr-13 A

10-Apr-14 A

100%

100%

QR40,041.01

Excavation for area lightings

58 27-May-13 A 06-Feb-14 A
30 27-May-13 A 22-Jun-13 A

100%
100%

100%
100%

QR85,420.80
QR26,694.00

Install cables below the ground

30 04-Jun-13 A

01-Jul-13 A

100%

100%

QR26,694.00

Backfilling and compaction

30 15-Jun-13 A

11-Jul-13 A

100%

100%

QR26,694.00

Pre-testing of area lighting

6 11-Jul-13 A

06-Feb-14 A

100%

100%

QR5,338.80

104 19-Jan-14 A
15 19-Jan-14 A

10-Apr-14 A
31-Jan-14 A

100%
100%

100%
100%

QR29,363.40
QR13,347.00

19 03-Apr-14 A

10-Apr-14 A

100%

100%

QR16,016.40

75%
100%

100%
100%

QR80,082.02
QR40,041.01

Fix fountain sculpture

Irrigation piping main laying

Pre-testing of irrigation
Kerb, plant edgers and granite paving works
Earthworks excavation
Disposal of waste materials

Area lighting and control cable laying

Signage structures erection


Fix signage structure concrete foundations
Fix signage
Fountain sculpture and finishing
Fix fountain sculpture
Fix fountain finishes

54 22-May-14 A 30-Jun-14
30 22-May-14 A 12-Jun-14 A

22

30 12-Jun-14 A

22

Backfilling and compaction


Pre-testing of irrigation
Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for kerbstone

Paving works
Excavation for area lightings
Install cables below the ground
Backfilling and compaction
Pre-testing of area lighting
Fix signage structure concrete foundatio
Fix signage

50%

100%

QR40,041.01

Fix fountain finishe

135 01-Jan-14 A
30 01-Jan-14 A

24-Apr-14 A
27-Jan-14 A

100%
100%

100%
100%

QR53,388.00
QR26,694.00

Fix foundations for light poles, DBs & fie

30 03-Apr-14 A

24-Apr-14 A

100%

100%

QR26,694.00

22 18-Jan-14 A
21 18-Jan-14 A

30-Apr-14 A
06-Feb-14 A

100%
100%

100%
100%

QR24,024.60
QR18,685.80

6 01-Feb-14 A

30-Apr-14 A

100%

100%

QR5,338.80

Install drip lines for shrubs & ground covers

36 24-Sep-13 A
30 24-Sep-13 A

31-Mar-14 A
24-Oct-13 A

100%
100%

100%
100%

QR112,114.80
QR26,694.00

Install sprinklers for lawn

30 24-Sep-13 A

24-Oct-13 A

100%

100%

QR26,694.00

Install sprinklers for lawn

Install bublers for palm & trees

30 24-Sep-13 A

24-Oct-13 A

100%

100%

QR26,694.00

Install bublers for palm & trees

Install automation & time controls

30 24-Sep-13 A

31-Mar-14 A

100%

100%

QR26,694.00

6 24-Oct-13 A

31-Mar-14 A

100%

100%

QR5,338.80

Pre-testing of irrigation

Hardscaping works

40 19-May-13 A 26-Apr-14 A
30 19-May-13 A 17-Apr-14 A

100%
100%

100%
100%

QR53,388.00
QR26,694.00

Hardscaping works

Finishing Works

30 27-May-13 A 26-Apr-14 A

100%

100%

QR26,694.00

Finishing Works

97.98%
100%
100%

100%
100%
100%

QR660,231.64
QR114,784.20
QR72,073.80

Excavation for network line pipes

Electrical Poles, DBs and Field Controls


Fix foundations for light poles, DBs & field Controls
Fix light poles, DBs & field control
Valves and pumps installation
Fix foundations for valves
Fix valves
Irrigation lateral piping & distribution accessories

Pre-testing of irrigation
Hardscape and finishing works

Zone 3
Irrigation piping main laying

30-Jun-14

Concrete foundation for plaza shades and

Fix foundations for valves


Fix valves
Install drip lines for shrubs & ground covers

Install automation & time contro

514 28-Mar-13 A
43 01-Oct-13 A
21 01-Oct-13 A

30-Jun-14
18-Jan-14 A
23-Oct-13 A

Install HDPE network line pipes

21 10-Oct-13 A

02-Nov-13 A

100%

100%

QR18,685.80

Install HDPE network line pipes

Backfilling and compaction

21 19-Oct-13 A

06-Nov-13 A

100%

100%

QR18,685.80

Backfilling and compaction

6 06-Nov-13 A 18-Jan-14 A

Excavation for network line pipes

Pre-testing of irrigation
Kerb, plant edgers and interlock paving works
Earthworks excavation
Disposal of waste materials

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

23

Fix light poles, DBs & field co

100%

100%

QR5,338.80

89 28-Mar-13 A
21 28-Mar-13 A

31-Dec-13 A
16-Apr-13 A

100%
100%

100%
100%

QR206,433.64
QR18,685.80

6 16-Apr-13 A

22-Apr-13 A

100%

100%

QR5,338.80

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Pre-testing of irrigation
Earthworks excavation
Disposal of waste materials

Page 11 of 25

Activity Name

Original Start
Duration

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


O

2013
N

2014

J Jul A

A M

J Jul A

S Oct N

Subgrade formation

25 08-Apr-13 A

30-Apr-13 A

100%

100%

QR22,245.00

Concrete foundation for kerbstones

45 18-Apr-13 A

28-May-13 A

100%

100%

QR40,041.01

Fix kerbs and supports

45 28-Apr-13 A

06-Jun-13 A

100%

100%

QR40,041.01

Aggregate subbase and fill compaction

45 02-May-13 A 11-Jun-13 A

100%

100%

QR40,041.01

Paving works

45 06-May-13 A 31-Dec-13 A

100%

100%

QR40,041.01

Excavation for area lightings

58 22-Jun-13 A
30 22-Jun-13 A

15-Aug-13 A
18-Jul-13 A

100%
100%

100%
100%

QR85,420.80
QR26,694.00

Install cables below the ground

30 01-Jul-13 A

27-Jul-13 A

100%

100%

QR26,694.00

Backfilling and compaction

30 11-Jul-13 A

06-Aug-13 A

100%

100%

QR26,694.00

6 06-Aug-13 A

15-Aug-13 A

100%

100%

QR5,338.80

173 01-Feb-14 A
15 01-Feb-14 A

30-Jun-14
06-Feb-14 A

80%
100%

100%
100%

QR66,735.00
QR13,347.00

Fix shade structure concrete foundatio

Fix shade structural elements

30 17-Apr-14 A

24-Apr-14 A

100%

100%

QR26,694.00

Fix shade structural elemen

Fix fabric shades

30 05-Jun-14 A

30-Jun-14

50%

100%

QR26,694.00

Area lighting and control cable laying

Pre-testing of area lighting


Shade structures erection
Fix shade structure concrete foundations

Signage structures erection


Fix signage structure concrete foundations
Fix signage
Zone valves's installation
Fix foundations for zone valves
Fix valves
Irrigation lateral piping & distribution accessories

23

23

Subgrade formation
Concrete foundation for kerbstones
Fix kerbs and supports
Aggregate subbase and fill compaction
Paving works
Excavation for area lightings
Install cables below the ground
Backfilling and compaction
Pre-testing of area lighting

Fix fabric shades

285 19-Jun-13 A
15 19-Jun-13 A

10-Apr-14 A
02-Jul-13 A

100%
100%

100%
100%

QR29,363.40
QR13,347.00

18 18-Jan-14 A

10-Apr-14 A

100%

100%

QR16,016.40

Fix signage

27 23-Oct-13 A
21 23-Oct-13 A

18-Jan-14 A
11-Nov-13 A

100%
100%

100%
100%

QR24,024.60
QR18,685.80

Fix foundations for zone valves

6 11-Nov-13 A 18-Jan-14 A

100%

100%

QR5,338.80

Fix signage structure concrete foundations

Fix valves

Install drip lines for shrubs & ground covers

27 24-Oct-13 A
21 24-Oct-13 A

18-Jan-14 A
12-Nov-13 A

100%
100%

100%
100%

QR80,082.00
QR18,685.80

Install drip lines for shrubs & ground covers

Install sprinklers for lawn

21 24-Oct-13 A

12-Nov-13 A

100%

100%

QR18,685.80

Install sprinklers for lawn

Install bublers for palm & trees

21 24-Oct-13 A

12-Nov-13 A

100%

100%

QR18,685.80

Install bublers for palm & trees

Install automation & time controls

21 24-Oct-13 A

12-Nov-13 A

100%

100%

QR18,685.80

Install automation & time controls

6 12-Nov-13 A 18-Jan-14 A

100%

100%

QR5,338.80

Pre-testing of irrigation
Hardscape and finishing works

Pre-testing of irrigation

Hardscaping works

40 09-Jun-13 A
30 09-Jun-13 A

03-Apr-14 A
04-Jul-13 A

100%
100%

100%
100%

QR53,388.00
QR26,694.00

Finishing Works

30 17-Jun-13 A

03-Apr-14 A

100%

100%

QR26,694.00

493 16-Apr-13 A
43 23-Oct-13 A
21 23-Oct-13 A

30-Jun-14
18-Jan-14 A
11-Nov-13 A

98.07%
100%
100%

100%
100%
100%

QR692,264.44
QR114,784.20
QR72,073.80

Excavation for network line pipes


Install HDPE network line pipes

Zone 4
Irrigation piping main laying
Excavation for network line pipes

23

Install HDPE network line pipes

21 02-Nov-13 A 19-Nov-13 A

100%

100%

QR18,685.80

Backfilling and compaction

21 06-Nov-13 A 25-Nov-13 A

100%

100%

QR18,685.80

6 25-Nov-13 A 18-Jan-14 A

100%

100%

QR5,338.80

31-Dec-13 A
05-May-13 A

100%
100%

100%
100%

QR206,433.64
QR18,685.80

6 05-May-13 A 09-May-13 A

100%

100%

QR5,338.80

Pre-testing of irrigation
Kerb, plant edgers and interlock paving works
Earthworks excavation
Disposal of waste materials

83 16-Apr-13 A
21 16-Apr-13 A

Hardscaping works
Finishing Works

Backfilling and compaction


Pre-testing of irrigation
Earthworks excavation
Disposal of waste materials

Subgrade formation

25 27-Apr-13 A

19-May-13 A

100%

100%

QR22,245.00

Concrete foundation for kerbstones

25 07-May-13 A 29-May-13 A

100%

100%

QR40,041.01

Fix kerbs and supports

45 11-May-13 A 19-Jun-13 A

100%

100%

QR40,041.01

Fix kerbs and supports

Aggregate subbase and fill compaction

45 16-May-13 A 24-Jun-13 A

100%

100%

QR40,041.01

Aggregate subbase and fill compaction

Paving works

45 20-May-13 A 31-Dec-13 A

100%

100%

QR40,041.01

Excavation for area lightings

58 29-May-13 A 31-Dec-13 A
30 29-May-13 A 24-Jun-13 A

100%
100%

100%
100%

QR85,420.80
QR26,694.00

Install cables below the ground

30 06-Jun-13 A

03-Jul-13 A

100%

100%

QR26,694.00

Backfilling and compaction

30 17-Jun-13 A

14-Jul-13 A

100%

100%

QR26,694.00

Pre-testing of area lighting

6 14-Jul-13 A

31-Dec-13 A

100%

100%

QR5,338.80

Shade structures erection

209 31-Dec-13 A

80%

100%

QR66,735.00

Area lighting and control cable laying

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

30-Jun-14

22

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Subgrade formation
Concrete foundation for kerbstones

Paving works
Excavation for area lightings
Install cables below the ground
Backfilling and compaction
Pre-testing of area lighting

Page 12 of 25

Activity Name

Original Start
Duration

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost

100%

100%

QR13,347.00

100%

100%

QR26,694.00

50%

100%

QR26,694.00

2013
N

2014

J Jul A

A M

J Jul A

S Oct N

Fix shade structure concrete foundations

15 31-Dec-13 A

13-Jan-14 A

Fix shade structural elements

30 13-Jan-14 A

17-Apr-14 A

Fix fabric shades

30 05-Jun-14 A

30-Jun-14

Fix signage structure concrete foundations

77 05-Jan-14 A
15 13-Jan-14 A

10-Apr-14 A
26-Jan-14 A

100%
100%

100%
100%

QR29,363.40
QR13,347.00

Fix signage

18 05-Jan-14 A

10-Apr-14 A

100%

100%

QR16,016.40

Fix signage

27 11-Nov-13 A 13-Feb-14 A
21 11-Nov-13 A 30-Nov-13 A

100%
100%

100%
100%

QR24,024.60
QR18,685.80

Fix foundations for zone valves and water tie-in

6 30-Nov-13 A 13-Feb-14 A

100%

100%

QR5,338.80

120 10-Nov-13 A 24-Jan-14 A


30 10-Nov-13 A 07-Dec-13 A

100%
100%

100%
100%

QR112,114.80
QR26,694.00

Install sprinklers for lawn

30 10-Nov-13 A 07-Dec-13 A

100%

100%

QR26,694.00

Install sprinklers for lawn

Install bublers for palm & trees

30 10-Nov-13 A 07-Dec-13 A

100%

100%

QR26,694.00

Install bublers for palm & trees

Install automation & time controls

30 10-Nov-13 A 07-Dec-13 A

Install automation & time controls

Signage structures erection

Zone valves and water tie-in installation


Fix foundations for zone valves and water tie-in
Fix valves
Irrigation lateral piping & distribution accessories
Install drip lines for shrubs & ground covers

22

Fix shade structure concrete foundations


Fix shade structural elements
Fix fabric shades
Fix signage structure concrete foundatio

Fix valves
Install drip lines for shrubs & ground covers

100%

100%

QR26,694.00

24-Jan-14 A

100%

100%

QR5,338.80

Pre-testing of irrigation

Hardscaping works

40 04-Jul-13 A
30 04-Jul-13 A

17-Apr-14 A
06-Feb-14 A

100%
100%

100%
100%

QR53,388.00
QR26,694.00

Hardscaping works

Finishing Works

30 14-Jul-13 A

17-Apr-14 A

100%

100%

QR26,694.00

326 05-May-13 A 03-Apr-14 A


119 11-Nov-13 A 24-Jan-14 A
15 11-Nov-13 A 24-Nov-13 A

100%
100%
100%

100%
100%
100%

QR582,819.00
QR224,229.60
QR181,519.20

Excavation for network line pipes

Install HDPE network line pipes

21 16-Nov-13 A 03-Dec-13 A

100%

100%

QR18,685.80

Install HDPE network line pipes

Backfilling and compaction

21 19-Nov-13 A 31-Dec-13 A

100%

100%

QR18,685.80

Backfilling and compaction

24-Jan-14 A

100%

100%

QR5,338.80

Pre-testing of irrigation

74 05-May-13 A 06-Mar-14 A
21 05-May-13 A 23-May-13 A

100%
100%

100%
100%

QR179,739.60
QR45,379.80

6 23-May-13 A 28-May-13 A

100%

100%

QR5,338.80

Subgrade formation

25 15-May-13 A 06-Jun-13 A

100%

100%

QR22,245.00

Concrete foundation for kerbstones

30 26-May-13 A 20-Jun-13 A

100%

100%

QR26,694.00

Fix kerbs and supports

30 03-Jun-13 A

30-Jun-13 A

100%

100%

QR26,694.00

Aggregate subbase and fill compaction

30 09-Jun-13 A

31-Dec-13 A

100%

100%

QR26,694.00

30 12-Jun-13 A

06-Mar-14 A

100%

100%

QR26,694.00

03-Apr-14 A
25-Jul-13 A

100%
100%

100%
100%

QR21,355.20
QR10,677.60

03-Apr-14 A

100%

100%

QR10,677.60

27 11-Nov-13 A 18-Jan-14 A
21 11-Nov-13 A 30-Nov-13 A

100%
100%

100%
100%

QR24,024.60
QR18,685.80

6 30-Nov-13 A 18-Jan-14 A

100%

100%

QR5,338.80

114 16-Nov-13 A 24-Jan-14 A


21 16-Nov-13 A 03-Dec-13 A

100%
100%

100%
100%

QR80,082.00
QR18,685.80

Install drip lines for shrubs & ground covers

Install sprinklers for lawn

21 16-Nov-13 A 03-Dec-13 A

100%

100%

QR18,685.80

Install sprinklers for lawn

Install bublers for palm & trees

21 16-Nov-13 A 03-Dec-13 A

100%

100%

QR18,685.80

Install bublers for palm & trees

Install automation & time controls

21 16-Nov-13 A 18-Jan-14 A

100%

100%

QR18,685.80

Pre-testing of irrigation

6 18-Jan-14 A

Hardscape and finishing works

Zone 8
Irrigation piping main laying
Excavation for network line pipes

Pre-testing of irrigation

6 18-Jan-14 A

Kerb, plant edgers and interlock paving works


Earthworks excavation
Disposal of waste materials

Paving works
Signage structures erection
Fix signage structure concrete foundations
Fix signage

12 12-Jan-14 A

Zone valves's installation


Fix foundations for zone valves
Fix valves
Irrigation lateral piping & distribution accessories
Install drip lines for shrubs & ground covers

Pre-testing of irrigation
Hardscape and finishing works
Hardscaping works
Finishing Works
Phase 1 - Testing and Commissioning
Testing and Commissioning for electrical works

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

207 15-Jul-13 A
12 15-Jul-13 A

Remaining

Milestone

Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for kerbstones
Fix kerbs and supports
Aggregate subbase and fill compaction
Paving works
Fix signage structure concrete foundations
Fix signage
Fix foundations for zone valves
Fix valves

Install automation & time controls

6 18-Jan-14 A

24-Jan-14 A

100%

100%

QR5,338.80

Pre-testing of irrigation

128 17-Aug-13 A
118 17-Aug-13 A

03-Apr-14 A
06-Feb-14 A

100%
100%

100%
100%

QR53,388.00
QR26,694.00

Hardscaping works

99 12-Sep-13 A

03-Apr-14 A

100%

100%

QR26,694.00

13 11-Dec-13 A
6 11-Dec-13 A

30-Jun-14
17-Apr-14 A

98.53%
100%

100%
100%

QR838,036.76
QR428,036.64

-8

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work

Finishing Works

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Finishing Works
Testing and Commissioning f

Page 13 of 25

Activity Name

Original Start
Duration

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost

30-Jun-14

-8

97%

100%

QR410,000.12

544 11-Mar-13 A

08-Jul-14

22

98.84%

100%

QR3,352,146.70

544
205
122
115

11-Mar-13 A
21-Jul-13 A
21-Jul-13 A
21-Jul-13 A

08-Jul-14
03-Apr-14 A
13-Nov-13 A
07-Nov-13 A

22

98.94%
100%
100%
100%

100%
100%
100%
100%

QR2,514,109.94
QR276,898.83
QR89,723.97
QR63,230.33

Disposal of waste materials

80 25-Aug-13 A

07-Nov-13 A

100%

100%

QR2,605.93

Subgrade formation

25 21-Oct-13 A

11-Nov-13 A

100%

100%

QR10,858.05

Subgrade formation

Concrete foundation for shades and signage

20 27-Oct-13 A

13-Nov-13 A

100%

100%

QR13,029.66

Concrete foundation for shades and signage

179 29-Jul-13 A
87 29-Jul-13 A

25-Jan-14 A
21-Oct-13 A

100%
100%

100%
100%

QR66,016.95
QR9,120.77

86 30-Jul-13 A

21-Oct-13 A

100%

100%

QR2,605.93

Subgrade formation

110 09-Sep-13 A

19-Dec-13 A

100%

100%

QR10,858.05

Concrete foundation for kerbstones

100 23-Sep-13 A

24-Dec-13 A

100%

100%

QR10,858.05

Fix kerbs and supports

25 10-Dec-13 A

31-Dec-13 A

100%

100%

QR10,858.05

Fix kerbs and supports

Aggregate subbase and fill compaction

25 16-Dec-13 A

31-Dec-13 A

100%

100%

QR10,858.05

Aggregate subbase and fill compaction

Paving works

25 21-Dec-13 A

25-Jan-14 A

100%

100%

QR10,858.05

Excavation for network line pipes

144 07-Sep-13 A
87 07-Sep-13 A

31-Dec-13 A
26-Nov-13 A

100%
100%

100%
100%

QR67,736.27
QR46,888.80

Install HDPE network line pipes & zone valves's installation

115 17-Sep-13 A

31-Dec-13 A

100%

100%

QR9,120.77

Install HDPE network line pipes & zone valv

Backfilling and compaction

117 21-Sep-13 A

31-Dec-13 A

100%

100%

QR9,120.77

Backfilling and compaction

23 26-Dec-13 A

31-Dec-13 A

100%

100%

QR2,605.93

Pre-testing of irrigation

03-Apr-14 A
31-Oct-13 A

100%
100%

100%
100%

QR14,332.63
QR6,514.83

19 09-Jan-14 A

03-Apr-14 A

100%

100%

QR7,817.80

Install drip lines for shrubs & ground covers

23 12-Dec-13 A
21 12-Dec-13 A

31-Dec-13 A
31-Dec-13 A

100%
100%

100%
100%

QR39,089.01
QR9,120.77

Install sprinklers for lawn

21 12-Dec-13 A

31-Dec-13 A

100%

100%

QR9,120.77

Install sprinklers for lawn

Install bublers for palm & trees

21 12-Dec-13 A

31-Dec-13 A

100%

100%

QR9,120.77

Install bublers for palm & trees

Install automation & time controls

21 12-Dec-13 A

31-Dec-13 A

100%

100%

QR9,120.77

Install automation & time controls

6 29-Dec-13 A

31-Dec-13 A

100%

100%

QR2,605.93

Pre-testing of irrigation

Earthworks excavation

352 21-Aug-13 A
208 21-Aug-13 A
131 21-Aug-13 A

30-Jun-14
03-Apr-14 A
19-Dec-13 A

98.24%
100%
100%

100%
100%
100%

QR259,724.61
QR61,673.73
QR35,180.09

Disposal of waste materials

Testing and Commissioning for mechanical works

Phase 2 Works
Construction
Zone 5
Concrete foundations signage
Earthworks excavation

Kerb, plant edgers works


Earthworks excavation
Disposal of waste materials

Irrigation piping main laying & zone valve's installation

Pre-testing of irrigation
Signage structures erection
Fix signage structure concrete foundations
Fix signage
Irrigation lateral piping & distribution accessories

Pre-testing of irrigation
Zone 6
Concrete foundations for shades and signage

6 17-Dec-13 A

199 25-Jul-13 A
103 25-Jul-13 A

Finish

23

2013
N

J Jul A

2014
S

A M

J Jul A

S Oct N

Testing and Comm

Earthworks excavation
Disposal of waste materials

Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for kerbstones

Paving works
Excavation for network line pipes

Fix signage structure concrete foundations


Fix signage
Install drip lines for shrubs & ground covers

Earthworks excavation

110 10-Sep-13 A

31-Dec-13 A

100%

100%

QR2,605.93

Subgrade formation

25 01-Feb-14 A

20-Mar-14 A

100%

100%

QR10,858.05

Concrete foundation for shades and signage

25 03-Feb-14 A

03-Apr-14 A

100%

100%

QR13,029.66

122 02-Feb-14 A
21 02-Feb-14 A

22-May-14 A
24-Apr-14 A

100%
100%

100%
100%

QR74,703.39
QR9,120.77

Disposal of waste materials

21 13-Feb-14 A

24-Apr-14 A

100%

100%

QR2,605.93

Subgrade formation

21 09-Apr-14 A

30-Apr-14 A

100%

100%

QR10,858.05

Subgrade formation

Concrete foundation for kerbstones

21 26-Apr-14 A

01-May-14 A

100%

100%

QR13,029.66

Concrete foundation for ke

Fix kerbs and supports

21 27-Apr-14 A

01-May-14 A

100%

100%

QR13,029.66

Fix kerbs and supports

Aggregate subbase and fill compaction

21 01-May-14 A 08-May-14 A

100%

100%

QR13,029.66

Paving works

21 01-May-14 A 22-May-14 A

100%

100%

QR13,029.66

Paving works

Excavation for network line pipes

41 10-Dec-13 A
15 10-Dec-13 A

22-Jan-14 A
31-Dec-13 A

100%
100%

100%
100%

QR29,968.24
QR9,120.77

Excavation for network line pipes

Install HDPE network line pipes & zone valves's installation

15 17-Dec-13 A

31-Dec-13 A

100%

100%

QR9,120.77

Backfilling and compaction

15 17-Dec-13 A

09-Jan-14 A

100%

100%

QR9,120.77

Kerb, plant edgers and interlock paving works


Earthworks excavation

Irrigation piping main laying & zone valve's installation

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Disposal of waste materials


Subgrade formation
Concrete foundation for shade
Earthworks excavation
Disposal of waste materials

Aggregate subbase and fi

Install HDPE network line pipes & zone valv


Backfilling and compaction

Page 14 of 25

Activity Name

Original Start
Duration

Pre-testing of irrigation

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost

100%

100%

QR2,605.93

81.58%
100%

100%
100%

QR24,756.37
QR6,514.83

Fix shade structure concrete fo

100%

100%

QR9,120.77

Fix shade structural e

50%

100%

QR9,120.77

Fix fabric shades

QR13,898.31
QR6,080.51

6 18-Jan-14 A

22-Jan-14 A

109 27-Mar-14 A
15 27-Mar-14 A

30-Jun-14
31-Mar-14 A

Fix shade structural elements

21 31-Mar-14 A

12-Jun-14 A

Fix fabric shades

21 12-Jun-14 A

30-Jun-14

76 01-Feb-14 A
14 01-Feb-14 A

10-Apr-14 A
06-Feb-14 A

100%
100%

100%
100%

Shade structures erection


Fix shade structure concrete foundations

Signage structures erection


Fix signage structure concrete foundations
Fix signage

-8

-8

2013
N

J Jul A

2014
S

A M

J Jul A

S Oct N

Pre-testing of irrigation

Fix signage structure concrete foundat

9 31-Mar-14 A

10-Apr-14 A

100%

100%

QR7,817.80

Install drip lines for shrubs & ground covers

35 01-Feb-14 A
20 01-Feb-14 A

10-Apr-14 A
10-Apr-14 A

100%
100%

100%
100%

QR54,724.57
QR13,029.66

Install drip lines for shrubs & g

Install sprinklers for lawn

20 13-Feb-14 A

10-Apr-14 A

100%

100%

QR13,029.66

Install sprinklers for lawn

Install bublers for palm & trees

20 13-Feb-14 A

10-Apr-14 A

100%

100%

QR13,029.66

Install bublers for palm & trees

Install automation & time controls

20 13-Feb-14 A

10-Apr-14 A

100%

100%

QR13,029.66

Install automation & time contr

Irrigation lateral piping & distribution accessories

Pre-testing of irrigation

2 15-Feb-14 A

10-Apr-14 A

331 09-Sep-13 A
184 09-Sep-13 A
110 09-Sep-13 A

30-Jun-14
31-Mar-14 A
17-Dec-13 A

Disposal of waste materials

88 29-Sep-13 A

Subgrade formation
Concrete foundation for shades and signage

Fix signage

100%

100%

QR2,605.93

98.25%
100%
100%

100%
100%
100%

QR260,158.93
QR61,673.73
QR35,180.09

17-Dec-13 A

100%

100%

QR2,605.93

Disposal of waste materials

25 01-Feb-14 A

06-Feb-14 A

100%

100%

QR10,858.05

Subgrade formation

30 17-Dec-13 A

31-Mar-14 A

100%

100%

QR13,029.66

Concrete foundation for shades

142 01-Feb-14 A
21 01-Feb-14 A

22-May-14 A
31-Mar-14 A

100%
100%

100%
100%

QR74,703.39
QR9,120.77

Earthworks excavation

Disposal of waste materials

21 20-Feb-14 A

31-Mar-14 A

100%

100%

QR2,605.93

Subgrade formation

21 20-Mar-14 A

31-Mar-14 A

100%

100%

QR10,858.05

Concrete foundation for kerbstones

21 17-Apr-14 A

08-May-14 A

100%

100%

QR13,029.66

Fix kerbs and supports

21 08-May-14 A 15-May-14 A

100%

100%

QR13,029.66

Fix kerbs and supports

Aggregate subbase and fill compaction

21 13-May-14 A 15-May-14 A

100%

100%

QR13,029.66

Aggregate subbase and f

Paving works

21 16-May-14 A 22-May-14 A

100%

100%

QR13,029.66

Paving works

Excavation for network line pipes

23 24-Dec-13 A
21 24-Dec-13 A

31-Dec-13 A
31-Dec-13 A

100%
100%

100%
100%

QR29,968.24
QR9,120.77

Excavation for network line pipes

Install HDPE network line pipes & zone valves's installation

21 25-Dec-13 A

31-Dec-13 A

100%

100%

QR9,120.77

Install HDPE network line pipes & zone valv

Backfilling and compaction

21 26-Dec-13 A

31-Dec-13 A

100%

100%

QR9,120.77

Backfilling and compaction

6 26-Dec-13 A

31-Dec-13 A

100%

100%

QR2,605.93

Pre-testing of irrigation

172 01-Feb-14 A
15 01-Feb-14 A

30-Jun-14
06-Feb-14 A

81.58%
100%

100%
100%

QR24,756.37
QR6,514.83

Fix shade structure concrete foundatio

100%

100%

QR9,120.77

Fix shade structural e

50%

100%

QR9,120.77

Fix fabric shades

Zone 7
Concrete foundations for shades and signage
Earthworks excavation

Kerb, plant edgers and interlock paving works


Earthworks excavation

Irrigation piping main laying & zone valve's installation

Pre-testing of irrigation
Shade structures erection
Fix shade structure concrete foundations

23

23

Pre-testing of irrigation

Earthworks excavation

Disposal of waste materials


Subgrade formation
Concrete foundation for ke

Fix shade structural elements

21 22-May-14 A 12-Jun-14 A

Fix fabric shades

21 12-Jun-14 A

30-Jun-14

Fix signage structure concrete foundations

85 01-Feb-14 A
15 01-Feb-14 A

10-Apr-14 A
31-Mar-14 A

100%
100%

100%
100%

QR14,332.63
QR6,514.83

Fix signage

18 31-Mar-14 A

10-Apr-14 A

100%

100%

QR7,817.80

177 21-Dec-13 A
20 21-Dec-13 A

12-Jun-14 A
31-Dec-13 A

100%
100%

100%
100%

QR54,724.57
QR13,029.66

Install drip lines for shrubs & ground covers

Install sprinklers for lawn

20 21-Dec-13 A

31-Dec-13 A

100%

100%

QR13,029.66

Install sprinklers for lawn

Install bublers for palm & trees

20 21-Dec-13 A

05-Jun-14 A

100%

100%

QR13,029.66

Install bublers for palm

Install automation & time controls

20 21-Dec-13 A

05-Jun-14 A

100%

100%

QR13,029.66

Install automation & tim

6 19-Apr-14 A

12-Jun-14 A

100%

100%

QR2,605.93

Pre-testing of irrigatio

256 10-Sep-13 A
116 29-Sep-13 A
106 29-Sep-13 A

10-Apr-14 A
13-Feb-14 A
31-Dec-13 A

100%
100%
100%

100%
100%
100%

QR260,167.93
QR61,673.73
QR35,180.09

Signage structures erection

Irrigation lateral piping & distribution accessories


Install drip lines for shrubs & ground covers

Pre-testing of irrigation
Zone 9
Concrete foundations for signage
Earthworks excavation

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

23

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Fix signage structure concrete f


Fix signage

Earthworks excavation

Page 15 of 25

Activity Name

Original Start
Duration

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


O

2013
N

J Jul A

2014
S

A M

J Jul A

S Oct N

Disposal of waste materials

84 21-Oct-13 A

31-Dec-13 A

100%

100%

QR2,605.93

Subgrade formation

79 04-Nov-13 A 31-Dec-13 A

100%

100%

QR10,858.05

Concrete foundation for shades and signage

30 14-Dec-13 A

13-Feb-14 A

100%

100%

QR13,029.66

Earthworks excavation

150 10-Sep-13 A
110 10-Sep-13 A

10-Apr-14 A
19-Dec-13 A

100%
100%

100%
100%

QR74,703.39
QR9,120.77

Disposal of waste materials

100 19-Sep-13 A

19-Dec-13 A

100%

100%

QR2,605.93

Subgrade formation

25 03-Dec-13 A

26-Dec-13 A

100%

100%

QR10,858.05

Subgrade formation

Concrete foundation for kerbstones

30 14-Dec-13 A

31-Dec-13 A

100%

100%

QR13,029.66

Concrete foundation for kerbstones

Fix kerbs and supports

30 24-Dec-13 A

27-Mar-14 A

100%

100%

QR13,029.66

Aggregate subbase and fill compaction

30 29-Dec-13 A

02-Apr-14 A

100%

100%

QR13,029.66

Paving works

30 25-Dec-13 A

10-Apr-14 A

100%

100%

QR13,029.66

Excavation for network line pipes

38 24-Dec-13 A
21 24-Dec-13 A

06-Jan-14 A
31-Dec-13 A

100%
100%

100%
100%

QR54,733.61
QR33,886.14

Install HDPE network line pipes & zone valves's installation

21 25-Dec-13 A

31-Dec-13 A

100%

100%

QR9,120.77

Backfilling and compaction

21 26-Dec-13 A

06-Jan-14 A

100%

100%

QR9,120.77

Backfilling and compaction


Pre-testing of irrigation

Kerb for plant edgers

Irrigation piping main laying & zone valve's installation

Pre-testing of irrigation

Disposal of waste materials


Subgrade formation
Concrete foundation for shades and s
Earthworks excavation
Disposal of waste materials

Fix kerbs and supports


Aggregate subbase and fill com
Paving works
Excavation for network line pipes
Install HDPE network line pipes & zone valv

6 28-Dec-13 A

06-Jan-14 A

100%

100%

QR2,605.93

Fix signage structure concrete foundations

34 27-Mar-14 A
15 27-Mar-14 A

10-Apr-14 A
31-Mar-14 A

100%
100%

100%
100%

QR14,332.63
QR6,514.83

Fix signage

18 29-Mar-14 A

10-Apr-14 A

100%

100%

QR7,817.80

131 07-Dec-13 A
30 07-Dec-13 A

29-Jan-14 A
19-Jan-14 A

100%
100%

100%
100%

QR54,724.57
QR13,029.66

Install drip lines for shrubs & ground cove

Install sprinklers for lawn

30 14-Dec-13 A

19-Jan-14 A

100%

100%

QR13,029.66

Install sprinklers for lawn

Install bublers for palm & trees

30 14-Dec-13 A

19-Jan-14 A

100%

100%

QR13,029.66

Install bublers for palm & trees

Install automation & time controls

30 14-Dec-13 A

19-Jan-14 A

100%

100%

QR13,029.66

Install automation & time controls

2 28-Jan-14 A

29-Jan-14 A

100%

100%

QR2,605.93

270 22-Oct-13 A
101 22-Oct-13 A
72 22-Oct-13 A

30-Jun-14
06-Mar-14 A
25-Dec-13 A

98.23%
100%
100%

100%
100%
100%

QR257,552.99
QR34,311.44
QR7,817.80

Disposal of waste materials

72 23-Oct-13 A

25-Dec-13 A

100%

100%

QR2,605.93

Subgrade formation

25 12-Dec-13 A

01-Feb-14 A

100%

100%

QR10,858.05

Concrete foundation for shades and signage

30 24-Dec-13 A

06-Mar-14 A

100%

100%

QR13,029.66

Earthworks excavation

69 01-Feb-14 A
21 01-Feb-14 A

05-Apr-14 A
18-Feb-14 A

100%
100%

100%
100%

QR73,400.42
QR7,817.80

Earthworks excavation

Disposal of waste materials

21 01-Feb-14 A

06-Feb-14 A

100%

100%

QR2,605.93

Disposal of waste materials

Subgrade formation

21 01-Feb-14 A

06-Feb-14 A

100%

100%

QR10,858.05

Concrete foundation for kerbstones

21 01-Mar-14 A

20-Mar-14 A

100%

100%

QR13,029.66

Concrete foundation for kerbston

Fix kerbs and supports

21 13-Mar-14 A

25-Mar-14 A

100%

100%

QR13,029.66

Fix kerbs and supports

Aggregate subbase and fill compaction

21 13-Feb-14 A

31-Mar-14 A

100%

100%

QR13,029.66

Aggregate subbase and fill com

Paving works

21 13-Feb-14 A

05-Apr-14 A

100%

100%

QR13,029.66

Paving works

Excavation for network line pipes

19 19-Dec-13 A
10 19-Dec-13 A

23-Jan-14 A
28-Dec-13 A

100%
100%

100%
100%

QR29,968.24
QR9,120.77

Install HDPE network line pipes & zone valves's installation

10 28-Dec-13 A

31-Dec-13 A

100%

100%

QR9,120.77

Backfilling and compaction

10 28-Dec-13 A

23-Jan-14 A

100%

100%

QR9,120.77

Backfilling and compaction

6 29-Dec-13 A

23-Jan-14 A

100%

100%

QR2,605.93

Pre-testing of irrigation

Fix shade structure concrete foundations

73 27-Mar-14 A
10 27-Mar-14 A

30-Jun-14
31-Mar-14 A

81.58%
100%

100%
100%

QR24,756.37
QR6,514.83

Fix shade structure concrete fo

Fix shade structural elements

10 22-May-14 A 12-Jun-14 A

100%

100%

QR9,120.77

Fix shade structural e

50%

100%

QR9,120.77

Fix fabric shades

100%

100%

QR14,332.63

Signage structures erection

Irrigation lateral piping & distribution accessories


Install drip lines for shrubs & ground covers

Pre-testing of irrigation
Zone 10
Concrete foundations for shades and signage
Earthworks excavation

Kerb, plant edgers and interlock paving works

Irrigation piping main laying & zone valve's installation

Pre-testing of irrigation
Shade structures erection

Fix fabric shades

5 12-Jun-14 A

Signage structures erection

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

10 29-Mar-14 A
Remaining

30-Jun-14
17-Apr-14 A

-8

-8

-8

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Fix signage structure concrete f


Fix signage

Pre-testing of irrigation

Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for shades an

Subgrade formation

Excavation for network line pipes


Install HDPE network line pipes & zone valv

Page 16 of 25

Activity Name

Original Start
Duration

Fix signage structure concrete foundations


Fix signage

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


QR6,514.83

10 29-Mar-14 A

31-Mar-14 A

100%

100%

2013
N

J Jul A

2014
S

A M

J Jul A

S Oct N

Fix signage structure concrete f

10 29-Mar-14 A

17-Apr-14 A

100%

100%

QR7,817.80

151 14-Dec-13 A
30 14-Dec-13 A

31-Mar-14 A
31-Dec-13 A

100%
100%

100%
100%

QR26,059.32
QR13,029.66

Fix foundations for light poles, DBs & field C

30 27-Mar-14 A

31-Mar-14 A

100%

100%

QR13,029.66

Fix light poles, DBs & field contr

135 19-Dec-13 A
20 19-Dec-13 A

17-Apr-14 A
31-Dec-13 A

100%
100%

100%
100%

QR54,724.57
QR13,029.66

Install drip lines for shrubs & ground covers

Install sprinklers for lawn

20 19-Dec-13 A

31-Dec-13 A

100%

100%

QR13,029.66

Install sprinklers for lawn

Install bublers for palm & trees

20 19-Dec-13 A

31-Dec-13 A

100%

100%

QR13,029.66

Install bublers for palm & trees

Install automation & time controls

20 19-Dec-13 A

17-Apr-14 A

100%

100%

QR13,029.66

6 12-Apr-14 A

16-Apr-14 A

100%

100%

QR2,605.93

340 10-Sep-13 A
112 29-Sep-13 A
83 29-Sep-13 A

08-Jul-14
06-Feb-14 A
14-Dec-13 A

97.72%
100%
100%

100%
100%
100%

QR285,349.63
QR35,614.41
QR9,120.77

Disposal of waste materials

82 30-Sep-13 A

14-Dec-13 A

100%

100%

QR2,605.93

Subgrade formation

25 03-Dec-13 A

25-Dec-13 A

100%

100%

QR10,858.05

Concrete foundation for shades and signage

30 14-Dec-13 A

06-Feb-14 A

100%

100%

QR13,029.66

Earthworks excavation

159 10-Sep-13 A
110 10-Sep-13 A

20-Feb-14 A
21-Dec-13 A

100%
100%

100%
100%

QR92,076.31
QR9,120.77

Disposal of waste materials

109 11-Sep-13 A

21-Dec-13 A

100%

100%

QR2,605.93

Subgrade formation

25 08-Dec-13 A

31-Dec-13 A

100%

100%

QR10,858.05

Subgrade formation

Concrete foundation for kerbstones

40 19-Dec-13 A

31-Dec-13 A

100%

100%

QR17,372.89

Concrete foundation for kerbstones

Fix kerbs and supports

40 28-Dec-13 A

06-Feb-14 A

100%

100%

QR17,372.89

Fix kerbs and supports

Aggregate subbase and fill compaction

40 28-Dec-13 A

06-Feb-14 A

100%

100%

QR17,372.89

Aggregate subbase and fill compaction

Paving works

40 26-Dec-13 A

20-Feb-14 A

100%

100%

QR17,372.89

Excavation for network line pipes

37 14-Dec-13 A
21 14-Dec-13 A

06-Feb-14 A
31-Dec-13 A

100%
100%

100%
100%

QR29,968.24
QR9,120.77

Install HDPE network line pipes & zone valves's installation

21 24-Dec-13 A

31-Dec-13 A

100%

100%

QR9,120.77

Install HDPE network line pipes & zone valv

Backfilling and compaction

21 29-Dec-13 A

31-Dec-13 A

100%

100%

QR9,120.77

Backfilling and compaction

6 26-Dec-13 A

06-Feb-14 A

100%

100%

QR2,605.93

112 02-Mar-14 A
15 02-Mar-14 A

08-Jul-14
27-Mar-14 A

80%
100%

100%
100%

QR32,574.15
QR6,514.83

100%

100%

QR13,029.66

50%

100%

QR13,029.66

Electrical lighting and DBs installation


Fix foundations for light poles, DBs & field Controls
Fix light poles, DBs & field control
Irrigation lateral piping & distribution accessories
Install drip lines for shrubs & ground covers

Pre-testing of irrigation
Zone 11
Concrete foundations for shades and signage
Earthworks excavation

Kerb, plant edgers and interlock paving works

Irrigation piping main laying & zone valve's installation

Pre-testing of irrigation
Shade structures erection
Fix shade structure concrete foundations
Fix shade structural elements

30 31-May-14 A 08-Jul-14 A

Fix fabric shades

30 12-Jun-14 A

Signage structures erection

30-Jun-14

22

22

-9

Fix signage

Install automation & time con


Pre-testing of irrigation

Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for shades and si
Earthworks excavation
Disposal of waste materials

Paving works
Excavation for network line pipes

Pre-testing of irrigation
Fix shade structure concrete fou
Fix shade structur
Fix fabric shades

116 20-Mar-14 A
10 20-Mar-14 A

10-Apr-14 A
27-Mar-14 A

100%
100%

100%
100%

QR14,332.63
QR6,514.83

18 29-Mar-14 A

10-Apr-14 A

100%

100%

QR7,817.80

209 24-Oct-13 A
111 24-Oct-13 A

31-Mar-14 A
31-Dec-13 A

100%
100%

100%
100%

QR26,059.32
QR13,029.66

Fix foundations for light poles, DBs & field C

30 27-Mar-14 A

31-Mar-14 A

100%

100%

QR13,029.66

Fix light poles, DBs & field contr

Install drip lines for shrubs & ground covers

28 08-Dec-13 A
25 08-Dec-13 A

13-Feb-14 A
30-Dec-13 A

100%
100%

100%
100%

QR54,724.57
QR13,029.66

Install drip lines for shrubs & ground covers

Install sprinklers for lawn

25 08-Dec-13 A

30-Dec-13 A

100%

100%

QR13,029.66

Install sprinklers for lawn

Install bublers for palm & trees

25 08-Dec-13 A

30-Dec-13 A

100%

100%

QR13,029.66

Install bublers for palm & trees

Install automation & time controls

25 08-Dec-13 A

30-Dec-13 A

100%

100%

QR13,029.66

Install automation & time controls

3 28-Dec-13 A

13-Feb-14 A

100%

100%

QR2,605.93

206 26-Oct-13 A
92 26-Oct-13 A
72 26-Oct-13 A

10-Apr-14 A
06-Feb-14 A
29-Dec-13 A

100%
100%
100%

100%
100%
100%

QR267,976.71
QR142,891.95
QR116,398.31

Fix signage structure concrete foundations


Fix signage
Electrical lighting and DBs installation
Fix foundations for light poles, DBs & field Controls
Fix light poles, DBs & field control
Irrigation lateral piping & distribution accessories

Pre-testing of irrigation
Zone 17
Concrete foundations for signage
Earthworks excavation

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Fix signage structure concrete f


Fix signage

Pre-testing of irrigation

Earthworks excavation

Page 17 of 25

Activity Name

Original Start
Duration

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


O

2013
N

J Jul A

2014
S

A M

J Jul A

S Oct N

Disposal of waste materials

72 26-Oct-13 A

29-Dec-13 A

100%

100%

QR2,605.93

Subgrade formation

75 30-Oct-13 A

31-Dec-13 A

100%

100%

QR10,858.05

Concrete foundation for shades and signage

30 19-Dec-13 A

06-Feb-14 A

100%

100%

QR13,029.66

Excavation for network line pipes

58 26-Nov-13 A 01-Jan-14 A
21 26-Nov-13 A 14-Dec-13 A

100%
100%

100%
100%

QR56,027.56
QR35,180.09

Install HDPE network line pipes & water tie-in

21 04-Dec-13 A

24-Dec-13 A

100%

100%

QR9,120.77

Backfilling and compaction

21 26-Dec-13 A

31-Dec-13 A

100%

100%

QR9,120.77

Backfilling and compaction

6 28-Dec-13 A

01-Jan-14 A

100%

100%

QR2,605.93

Pre-testing of irrigation

Fix signage structure concrete foundations

33 27-Mar-14 A
33 27-Mar-14 A

10-Apr-14 A
31-Mar-14 A

100%
100%

100%
100%

QR14,332.63
QR6,514.83

Fix signage

18 29-Mar-14 A

10-Apr-14 A

100%

100%

QR7,817.80

Install drip lines for shrubs & ground covers

67 17-Dec-13 A
30 17-Dec-13 A

06-Feb-14 A
31-Dec-13 A

100%
100%

100%
100%

QR54,724.57
QR13,029.66

Install drip lines for shrubs & ground covers

Install sprinklers for lawn

30 17-Dec-13 A

31-Dec-13 A

100%

100%

QR13,029.66

Install sprinklers for lawn

Install bublers for palm & trees

30 17-Dec-13 A

31-Dec-13 A

100%

100%

QR13,029.66

Install bublers for palm & trees

Install automation & time controls

30 31-Dec-13 A

26-Jan-14 A

100%

100%

QR13,029.66

6 01-Feb-14 A

06-Feb-14 A

100%

100%

QR2,605.93

201 21-Oct-13 A
96 21-Oct-13 A
66 21-Oct-13 A

10-Apr-14 A
26-Feb-14 A
17-Dec-13 A

100%
100%
100%

100%
100%
100%

QR260,167.93
QR35,614.41
QR9,120.77

Disposal of waste materials

46 07-Nov-13 A 17-Dec-13 A

100%

100%

QR2,605.93

Subgrade formation

25 07-Dec-13 A

29-Dec-13 A

100%

100%

QR10,858.05

Concrete foundation for shades and signage

30 17-Dec-13 A

26-Feb-14 A

100%

100%

QR13,029.66

Earthworks excavation

45 01-Feb-14 A
21 01-Feb-14 A

02-Mar-14 A
06-Feb-14 A

100%
100%

100%
100%

QR74,703.39
QR9,120.77

Disposal of waste materials

21 01-Feb-14 A

06-Feb-14 A

100%

100%

QR2,605.93

Subgrade formation

25 01-Feb-14 A

06-Feb-14 A

100%

100%

QR10,858.05

Subgrade formation

Concrete foundation for kerbstones

30 01-Feb-14 A

06-Feb-14 A

100%

100%

QR13,029.66

Concrete foundation for kerbstones

Fix kerbs and supports

30 01-Feb-14 A

06-Feb-14 A

100%

100%

QR13,029.66

Fix kerbs and supports

Aggregate subbase and fill compaction

30 01-Feb-14 A

06-Feb-14 A

100%

100%

QR13,029.66

Aggregate subbase and fill compaction

Paving works

30 13-Feb-14 A

02-Mar-14 A

100%

100%

QR13,029.66

Excavation for network line pipes

63 19-Dec-13 A
21 19-Dec-13 A

12-Feb-14 A
19-Jan-14 A

100%
100%

100%
100%

QR80,792.93
QR59,945.46

Install HDPE network line pipes & zone valves's installation

21 19-Jan-14 A

24-Jan-14 A

100%

100%

QR9,120.77

Backfilling and compaction

21 23-Jan-14 A

06-Feb-14 A

100%

100%

QR9,120.77

Irrigation piping main laying and water tie-in installation

Pre-testing of irrigation
Signage structures erection

Irrigation lateral piping & distribution accessories

Pre-testing of irrigation
Zone 18
Concrete foundations for signage
Earthworks excavation

Kerbs and interlock paving works

Irrigation piping main laying & zone valve's installation

Pre-testing of irrigation

Disposal of waste materials


Subgrade formation
Concrete foundation for shades and si
Excavation for network line pipes
Install HDPE network line pipes & water tie-in

Fix signage structure concrete f


Fix signage

Install automation & time controls


Pre-testing of irrigation

Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for shades and
Earthworks excavation
Disposal of waste materials

Paving works
Excavation for network line pipes
Install HDPE network line pipes & zone v
Backfilling and compaction

6 08-Feb-14 A

12-Feb-14 A

100%

100%

QR2,605.93

Fix signage structure concrete foundations

18 27-Mar-14 A
15 27-Mar-14 A

10-Apr-14 A
31-Mar-14 A

100%
100%

100%
100%

QR14,332.63
QR6,514.83

Fix signage

18 31-Mar-14 A

10-Apr-14 A

100%

100%

QR7,817.80

Install drip lines for shrubs & ground covers

58 21-Dec-13 A
30 21-Dec-13 A

09-Feb-14 A
06-Feb-14 A

100%
100%

100%
100%

QR54,724.57
QR13,029.66

Install drip lines for shrubs & ground co

Install sprinklers for lawn

30 21-Dec-13 A

06-Feb-14 A

100%

100%

QR13,029.66

Install sprinklers for lawn

Install bublers for palm & trees

30 21-Dec-13 A

06-Feb-14 A

100%

100%

QR13,029.66

Install bublers for palm & trees

Install automation & time controls

30 21-Dec-13 A

06-Feb-14 A

100%

100%

QR13,029.66

Install automation & time controls

2 08-Feb-14 A

09-Feb-14 A

100%

100%

QR2,605.93

528 11-Mar-13 A
89 11-Mar-13 A
21 11-Mar-13 A

30-Jun-14
27-May-13 A
28-Mar-13 A

98.31%
100%
100%

100%
100%
100%

QR386,112.38
QR100,762.75
QR9,120.77

6 28-Mar-13 A

03-Apr-13 A

100%

100%

QR2,605.93

Signage structures erection

Irrigation lateral piping & distribution accessories

Pre-testing of irrigation
Zone 19
Open car park paving - Kerb and interlock paving works
Earthworks excavation
Disposal of waste materials

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

-8

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Pre-testing of irrigation
Fix signage structure concrete f
Fix signage

Pre-testing of irrigation

Earthworks excavation
Disposal of waste materials

Page 18 of 25

Activity Name

Original Start
Duration

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


O

2013
N

2014

J Jul A

Subgrade formation

25 21-Mar-13 A

11-Apr-13 A

100%

100%

QR10,858.05

Concrete foundation for kerbstones

45 01-Apr-13 A

09-May-13 A

100%

100%

QR19,544.50

Fix kerbs and supports

45 09-Apr-13 A

19-May-13 A

100%

100%

QR19,544.50

Fix kerbs and supports

Aggregate subbase and fill compaction

45 15-Apr-13 A

23-May-13 A

100%

100%

QR19,544.50

Aggregate subbase and fill compaction

Paving works

45 18-Apr-13 A

27-May-13 A

100%

100%

QR19,544.50

Paving works

54 28-Mar-13 A
21 28-Mar-13 A

15-May-13 A
16-Apr-13 A

100%
100%

100%
100%

QR35,614.41
QR9,120.77

6 16-Apr-13 A

22-Apr-13 A

100%

100%

QR2,605.93

Subgrade formation

25 08-Apr-13 A

30-Apr-13 A

100%

100%

QR10,858.05

Concrete foundation for shades and signage

30 18-Apr-13 A

15-May-13 A

100%

100%

QR13,029.66

84 28-Mar-13 A
21 28-Mar-13 A

31-Dec-13 A
16-Apr-13 A

100%
100%

100%
100%

QR92,076.31
QR9,120.77

6 22-Apr-13 A

27-Apr-13 A

100%

100%

QR2,605.93

Subgrade formation

25 08-Apr-13 A

30-Apr-13 A

100%

100%

QR10,858.05

Concrete foundation for kerbstones

40 18-Apr-13 A

23-May-13 A

100%

100%

QR17,372.89

Fix kerbs and supports

40 28-Apr-13 A

02-Jun-13 A

100%

100%

QR17,372.89

Fix kerbs and supports

Aggregate subbase and fill compaction

40 02-May-13 A 06-Jun-13 A

100%

100%

QR17,372.89

Aggregate subbase and fill compaction

Paving works

40 06-May-13 A 31-Dec-13 A

100%

100%

QR17,372.89

Excavation for network line pipes

43 30-Apr-13 A
21 30-Apr-13 A

06-Jun-13 A
19-May-13 A

100%
100%

100%
100%

QR29,968.24
QR9,120.77

Install HDPE network line pipes & zone valves's installation

21 09-May-13 A 27-May-13 A

100%

100%

QR9,120.77

Backfilling and compaction

21 14-May-13 A 02-Jun-13 A

100%

100%

QR9,120.77

Backfilling and compaction

100%

100%

QR2,605.93

Pre-testing of irrigation

80%
100%

100%
100%

QR32,574.15
QR6,514.83

100%

100%

QR13,029.66

50%

100%

QR13,029.66

Concrete foundations for shades and signage


Earthworks excavation
Disposal of waste materials

Kerb, plant edgers and interlock paving works


Earthworks excavation
Disposal of waste materials

Irrigation piping main laying & zone valve's installation

Pre-testing of irrigation

A M

J Jul A

S Oct N

Subgrade formation
Concrete foundation for kerbstones

Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for shades and signage
Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for kerbstones

Paving works
Excavation for network line pipes
Install HDPE network line pipes & zone valves's installation

6 02-Jun-13 A

06-Jun-13 A

Fix shade structure concrete foundations

99 27-Mar-14 A
15 27-Mar-14 A

30-Jun-14
31-Mar-14 A

Fix shade structural elements

15 10-Apr-14 A

17-Apr-14 A

Fix fabric shades

15 12-Jun-14 A

30-Jun-14

Fix signage structure concrete foundations

33 15-Jun-13 A
15 15-Jun-13 A

14-Jul-13 A
27-Jun-13 A

100%
100%

100%
100%

QR14,332.63
QR6,514.83

Fix signage

18 27-Jun-13 A

14-Jul-13 A

100%

100%

QR7,817.80

275 06-Jun-13 A
30 06-Jun-13 A

06-Feb-14 A
03-Jul-13 A

100%
100%

100%
100%

QR26,059.32
QR13,029.66

30 18-Jan-14 A

06-Feb-14 A

100%

100%

QR13,029.66

Install drip lines for shrubs & ground covers

36 22-May-13 A 23-Dec-13 A
30 22-May-13 A 17-Dec-13 A

100%
100%

100%
100%

QR54,724.57
QR13,029.66

Install drip lines for shrubs & ground covers

Install sprinklers for lawn

30 22-May-13 A 17-Dec-13 A

100%

100%

QR13,029.66

Install sprinklers for lawn

Install bublers for palm & trees

30 22-May-13 A 17-Dec-13 A

100%

100%

QR13,029.66

Install bublers for palm & trees

Install automation & time controls

30 22-May-13 A 17-Dec-13 A

100%

100%

QR13,029.66

Install automation & time controls

100%

100%

QR2,605.93

98.53%
100%

100%
100%

QR838,036.76
QR428,036.64

Testing and Commissioning f


Testing and Comm

Shade structures erection

Signage structures erection

Electrical lighting and DBs installation


Fix foundations for light poles, DBs & field Controls
Fix light poles, DBs & field control
Irrigation lateral piping & distribution accessories

Pre-testing of irrigation
Phase 2 - Testing and Commissioning
Testing and Commissioning for electrical works
Testing and Commissioning for mechanical works

6 17-Jun-13 A

23-Dec-13 A

9 08-Dec-13 A
9 08-Dec-13 A

30-Jun-14
17-Apr-14 A

-8

-8

-9

9 08-Dec-13 A

30-Jun-14

-8

97%

100%

QR410,000.12

361 17-Aug-13 A

30-Jun-14

23

99.16%

100%

QR3,561,655.92

361
330
88
72

17-Aug-13 A
10-Sep-13 A
26-Oct-13 A
26-Oct-13 A

30-Jun-14
30-Jun-14
06-Feb-14 A
29-Dec-13 A

23
23

99.35%
98.63%
100%
100%

100%
100%
100%
100%

QR2,723,619.16
QR529,814.28
QR94,881.77
QR56,097.98

Disposal of waste materials

69 28-Oct-13 A

01-Feb-14 A

100%

100%

QR4,155.41

Subgrade formation

72 30-Oct-13 A

03-Feb-14 A

100%

100%

QR17,314.19

Phase 3 Works
Construction
Zone 12
Concrete foundations for shades and signage
Earthworks excavation

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Fix shade structure concrete fo


Fix shade structural elements
Fix fabric shades
Fix signage structure concrete foundations
Fix signage
Fix foundations for light poles, DBs & field Controls
Fix light poles, DBs & field control

Pre-testing of irrigation

Earthworks excavation
Disposal of waste materials
Subgrade formation

Page 19 of 25

Activity Name

Original Start
Duration

Concrete foundation for shades and signage

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


O

2013
N

J Jul A

2014
S

A M

J Jul A

S Oct N

25 21-Dec-13 A

06-Feb-14 A

100%

100%

QR17,314.19

216 10-Sep-13 A
112 10-Sep-13 A

17-Apr-14 A
22-Dec-13 A

100%
100%

100%
100%

QR119,121.64
QR14,543.92

Disposal of waste materials

90 30-Sep-13 A

22-Dec-13 A

100%

100%

QR4,155.41

Subgrade formation

80 22-Oct-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Subgrade formation

Concrete foundation for kerbstones

30 16-Dec-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Concrete foundation for kerbstones

Fix kerbs and supports

30 13-Feb-14 A

27-Mar-14 A

100%

100%

QR20,777.03

Aggregate subbase and fill compaction

30 20-Feb-14 A

10-Apr-14 A

100%

100%

QR20,777.03

Paving works

30 24-Feb-14 A

17-Apr-14 A

100%

100%

QR20,777.03

Excavation for network line pipes

32 18-Dec-13 A
21 18-Dec-13 A

14-Jan-14 A
31-Dec-13 A

100%
100%

100%
100%

QR47,787.17
QR14,543.92

Install HDPE network line pipes & zone valves's installation

21 19-Dec-13 A

08-Jan-14 A

100%

100%

QR14,543.92

Backfilling and compaction

21 19-Dec-13 A

14-Jan-14 A

100%

100%

QR14,543.92

6 21-Dec-13 A

14-Jan-14 A

100%

100%

QR4,155.41

134 05-Mar-14 A
15 05-Mar-14 A

30-Jun-14
13-Mar-14 A

81.58%
100%

100%
100%

QR39,476.36
QR10,388.52

Fix shade structure concrete foun

Fix shade structural elements

21 10-Apr-14 A

12-Jun-14 A

100%

100%

QR14,543.92

Fix shade structural e

Fix fabric shades

21 12-Jun-14 A

30-Jun-14

50%

100%

QR14,543.92

Fix fabric shades

Fix signage structure concrete foundations

30 20-Mar-14 A
14 20-Mar-14 A

10-Apr-14 A
27-Mar-14 A

100%
100%

100%
100%

QR22,162.17
QR9,695.95

Fix signage

18 31-Mar-14 A

10-Apr-14 A

100%

100%

QR12,466.22

Install drip lines for shrubs & ground covers

70 19-Dec-13 A
30 19-Dec-13 A

18-Feb-14 A
13-Feb-14 A

100%
100%

100%
100%

QR87,263.53
QR20,777.03

Install drip lines for shrubs & ground c

Install sprinklers for lawn

30 19-Dec-13 A

13-Feb-14 A

100%

100%

QR20,777.03

Install sprinklers for lawn

Install bublers for palm & trees

30 19-Dec-13 A

13-Feb-14 A

100%

100%

QR20,777.03

Install bublers for palm & trees

Install automation & time controls

30 19-Dec-13 A

13-Feb-14 A

100%

100%

QR20,777.03

Install automation & time controls

6 13-Feb-14 A

18-Feb-14 A

100%

100%

QR4,155.41

Earthworks excavation

159 10-Sep-13 A
159 10-Sep-13 A

31-Dec-13 A
31-Dec-13 A

100%
100%

100%
100%

QR119,121.64
QR14,543.92

Disposal of waste materials

150 18-Sep-13 A

31-Dec-13 A

100%

100%

QR4,155.41

Subgrade formation

25 22-Dec-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Subgrade formation

Concrete foundation for kerbstones

30 22-Dec-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Concrete foundation for kerbstones

Fix kerbs and supports

30 25-Dec-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Fix kerbs and supports

Aggregate subbase and fill compaction

30 26-Dec-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Aggregate subbase and fill compaction


Furnishing works

Kerb, plant edgers and interlock paving works


Earthworks excavation

Irrigation piping main laying & zone valve's installation

Pre-testing of irrigation
Shade structures erection
Fix shade structure concrete foundations

Signage structures erection

Irrigation lateral piping & distribution accessories

Pre-testing of irrigation
Road Kerb and Furnishing Works

Furnishing works

23

23

Concrete foundation for shades and si


Earthworks excavation
Disposal of waste materials

Fix kerbs and supports


Aggregate subbase and fill co
Paving works
Excavation for network line pipes
Install HDPE network line pipes & zone val
Backfilling and compaction
Pre-testing of irrigation

Fix signage structure concrete f


Fix signage

Pre-testing of irrigation
Earthworks excavation
Disposal of waste materials

30 28-Dec-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Earthworks excavation

236 10-Sep-13 A
147 12-Sep-13 A
123 12-Sep-13 A

03-Apr-14 A
31-Dec-13 A
31-Dec-13 A

100%
100%
100%

100%
100%
100%

QR458,479.80
QR119,814.21
QR81,030.42

Disposal of waste materials

104 29-Sep-13 A

31-Dec-13 A

100%

100%

QR4,155.41

Subgrade formation

117 28-Sep-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Subgrade formation

Concrete foundation for shades and signage

116 09-Oct-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Concrete foundation for shades and signag

146 10-Sep-13 A
112 10-Sep-13 A

04-Jan-14 A
22-Dec-13 A

100%
100%

100%
100%

QR103,192.58
QR12,466.22

Disposal of waste materials

90 30-Sep-13 A

22-Dec-13 A

100%

100%

QR4,155.41

Subgrade formation

80 22-Oct-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Subgrade formation

Concrete foundation for kerbstones

30 16-Dec-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Concrete foundation for kerbstones

Fix kerbs and supports

30 25-Dec-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Fix kerbs and supports

Aggregate subbase and fill compaction

30 25-Dec-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Aggregate subbase and fill compaction

Paving works

30 25-Dec-13 A

04-Jan-14 A

100%

100%

QR17,314.19

Paving works

Zone 13
Concrete foundations for signage

Kerbs and interlock paving works


Earthworks excavation

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Earthworks excavation
Disposal of waste materials

Earthworks excavation
Disposal of waste materials

Page 20 of 25

Activity Name

Original Start
Duration

Irrigation piping main laying & zone valve's installation

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


O

2013
N

J Jul A

2014
S

A M

J Jul A

S Oct N

Excavation for network line pipes

136 12-Sep-13 A
120 12-Sep-13 A

31-Dec-13 A
31-Dec-13 A

100%
100%

100%
100%

QR47,787.17
QR14,543.92

Excavation for network line pipes

Install HDPE network line pipes & zone valves's installation

116 24-Sep-13 A

31-Dec-13 A

100%

100%

QR14,543.92

Install HDPE network line pipes & zone valv

21 26-Dec-13 A

31-Dec-13 A

100%

100%

QR14,543.92

Backfilling and compaction

6 25-Dec-13 A

31-Dec-13 A

100%

100%

QR4,155.41

Fix signage structure concrete foundations

39 06-Mar-14 A
10 06-Mar-14 A

03-Apr-14 A
13-Mar-14 A

100%
100%

100%
100%

QR22,162.17
QR9,695.95

Fix signage

10 27-Mar-14 A

03-Apr-14 A

100%

100%

QR12,466.22

Install drip lines for shrubs & ground covers

21 17-Dec-13 A
21 17-Dec-13 A

04-Jan-14 A
31-Dec-13 A

100%
100%

100%
100%

QR62,331.09
QR14,543.92

Install drip lines for shrubs & ground covers

Install sprinklers for lawn

21 17-Dec-13 A

31-Dec-13 A

100%

100%

QR14,543.92

Install sprinklers for lawn

Install bublers for palm & trees

21 17-Dec-13 A

31-Dec-13 A

100%

100%

QR14,543.92

Install bublers for palm & trees

Install automation & time controls

21 17-Dec-13 A

31-Dec-13 A

100%

100%

QR14,543.92

Install automation & time controls

Backfilling and compaction


Pre-testing of irrigation
Signage structures erection

Irrigation lateral piping & distribution accessories

Pre-testing of irrigation

Pre-testing of irrigation
Fix signage structure concrete fou
Fix signage

6 23-Dec-13 A

04-Jan-14 A

100%

100%

QR4,155.41

Pre-testing of irrigation

Earthworks excavation

204 14-Sep-13 A
157 14-Sep-13 A

31-Dec-13 A
31-Dec-13 A

100%
100%

100%
100%

QR103,192.58
QR12,466.22

Earthworks excavation

Disposal of waste materials

155 16-Sep-13 A

31-Dec-13 A

100%

100%

QR4,155.41

Subgrade formation

156 25-Sep-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Subgrade formation

Concrete foundation for kerbstones

156 06-Oct-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Concrete foundation for kerbstones

Fix kerbs and supports

156 14-Oct-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Fix kerbs and supports

Aggregate subbase and fill compaction

156 23-Oct-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Aggregate subbase and fill compaction

Furnishing works

156 29-Oct-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Furnishing works

Earthworks excavation

254 24-Aug-13 A
148 24-Aug-13 A
115 24-Aug-13 A

03-Apr-14 A
31-Dec-13 A
07-Dec-13 A

100%
100%
100%

100%
100%
100%

QR615,000.09
QR153,750.02
QR49,172.30

Earthworks excavation

Disposal of waste materials

111 27-Aug-13 A

07-Dec-13 A

100%

100%

QR4,155.41

Subgrade formation

121 28-Aug-13 A

17-Dec-13 A

100%

100%

QR17,314.19

Concrete foundation for kerbstones

125 29-Aug-13 A

23-Dec-13 A

100%

100%

QR20,777.03

Concrete foundation for kerbstones

Fix kerbs and supports

124 31-Aug-13 A

23-Dec-13 A

100%

100%

QR20,777.03

Fix kerbs and supports

Aggregate subbase and fill compaction

125 08-Sep-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Aggregate subbase and fill compaction

Paving works

125 14-Sep-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Paving works

130 01-Sep-13 A
64 01-Sep-13 A

30-Dec-13 A
31-Oct-13 A

100%
100%

100%
100%

QR92,804.07
QR54,020.28

Disposal of waste materials

63 02-Sep-13 A

31-Oct-13 A

100%

100%

QR4,155.41

Subgrade formation

63 02-Sep-13 A

31-Oct-13 A

100%

100%

QR17,314.19

107 23-Sep-13 A

30-Dec-13 A

100%

100%

QR17,314.19

164 24-Aug-13 A
140 24-Aug-13 A

31-Dec-13 A
30-Dec-13 A

100%
100%

100%
100%

QR119,121.64
QR14,543.92

Disposal of waste materials

90 07-Oct-13 A

30-Dec-13 A

100%

100%

QR4,155.41

Subgrade formation

80 30-Oct-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Subgrade formation

Concrete foundation for kerbstones

30 01-Dec-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Concrete foundation for kerbstones

Fix kerbs and supports

30 02-Dec-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Fix kerbs and supports

Aggregate subbase and fill compaction

30 07-Dec-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Aggregate subbase and fill compaction

Paving works

30 11-Dec-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Paving works

Excavation for network line pipes

95 17-Nov-13 A 31-Dec-13 A
77 17-Nov-13 A 31-Dec-13 A

100%
100%

100%
100%

QR47,787.17
QR14,543.92

Excavation for network line pipes

Install HDPE network line pipes & zone valves's installation

71 01-Dec-13 A

31-Dec-13 A

100%

100%

QR14,543.92

Install HDPE network line pipes & zone valv

Backfilling and compaction

73 05-Dec-13 A

31-Dec-13 A

100%

100%

QR14,543.92

Backfilling and compaction

6 19-Dec-13 A

31-Dec-13 A

100%

100%

QR4,155.41

Road Kerb and Furnishing Works

Zone 14
Open car park paving - Kerb and interlock paving works

Concrete foundations for signage


Earthworks excavation

Concrete foundation for shades and signage


Kerb, plant edgers and interlock paving works
Earthworks excavation

Irrigation piping main laying & zone valve's installation

Pre-testing of irrigation

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Disposal of waste materials

Disposal of waste materials


Subgrade formation

Earthworks excavation
Disposal of waste materials
Subgrade formation
Concrete foundation for shades and signag
Earthworks excavation
Disposal of waste materials

Pre-testing of irrigation

Page 21 of 25

Activity Name

Original Start
Duration

Signage structures erection

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


O

2013
N

J Jul A

2014
S

A M

J Jul A

S Oct N

Fix signage structure concrete foundations

38 06-Mar-14 A
10 06-Mar-14 A

03-Apr-14 A
13-Mar-14 A

100%
100%

100%
100%

QR22,854.74
QR10,388.52

Fix signage

10 31-Mar-14 A

03-Apr-14 A

100%

100%

QR12,466.22

Install drip lines for shrubs & ground covers

28 25-Dec-13 A
25 25-Dec-13 A

18-Jan-14 A
31-Dec-13 A

100%
100%

100%
100%

QR73,412.17
QR17,314.19

Install drip lines for shrubs & ground covers

Install sprinklers for lawn

25 25-Dec-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Install sprinklers for lawn

Install bublers for palm & trees

25 25-Dec-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Install bublers for palm & trees

Install automation & time controls

25 25-Dec-13 A

13-Jan-14 A

100%

100%

QR17,314.19

6 13-Jan-14 A

18-Jan-14 A

100%

100%

QR4,155.41

Earthworks excavation

153 01-Sep-13 A
129 01-Sep-13 A

31-Dec-13 A
29-Dec-13 A

100%
100%

100%
100%

QR105,270.28
QR14,543.92

Disposal of waste materials

128 02-Sep-13 A

29-Dec-13 A

100%

100%

QR4,155.41

Subgrade formation

25 16-Dec-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Subgrade formation

Concrete foundation for kerbstones

25 25-Dec-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Concrete foundation for kerbstones

Fix kerbs and supports

25 26-Dec-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Fix kerbs and supports

Aggregate subbase and fill compaction

25 25-Dec-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Aggregate subbase and fill compaction

Furnishing works

25 26-Dec-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Furnishing works

361 17-Aug-13 A
215 17-Aug-13 A
132 17-Aug-13 A

30-Jun-14
06-Mar-14 A
14-Dec-13 A

98.28%
100%
100%

100%
100%
100%

QR605,054.60
QR156,963.30
QR114,716.67

Earthworks excavation

Disposal of waste materials

10 01-Feb-14 A

06-Feb-14 A

100%

100%

QR4,155.41

Disposal of waste materials

Subgrade formation

25 01-Feb-14 A

27-Feb-14 A

100%

100%

QR17,314.19

Subgrade formation

Concrete foundation for shades and signage

30 01-Feb-14 A

06-Mar-14 A

100%

100%

QR20,777.03

Earthworks excavation

15 06-Mar-14 A
10 06-Mar-14 A

14-Apr-14 A
13-Mar-14 A

100%
100%

100%
100%

QR119,121.64
QR14,543.92

Disposal of waste materials

10 06-Mar-14 A

13-Mar-14 A

100%

100%

QR4,155.41

Subgrade formation

10 10-Mar-14 A

17-Mar-14 A

100%

100%

QR17,314.19

Subgrade formation

Concrete foundation for kerbstones

10 10-Mar-14 A

20-Mar-14 A

100%

100%

QR20,777.03

Concrete foundation for kerbston

Fix kerbs and supports

10 09-Mar-14 A

24-Mar-14 A

100%

100%

QR20,777.03

Fix kerbs and supports

Aggregate subbase and fill compaction

10 06-Mar-14 A

10-Apr-14 A

100%

100%

QR20,777.03

Aggregate subbase and fill co


Paving works

Irrigation lateral piping & distribution accessories

Pre-testing of irrigation
Road Kerb and Furnishing Works

Zone 15
Concrete foundations for shades and signage
Earthworks excavation

Kerb, plant edgers and interlock paving works

Paving works

23

Fix signage structure concrete fou


Fix signage

Install automation & time controls


Pre-testing of irrigation
Earthworks excavation
Disposal of waste materials

Concrete foundation for shades an


Earthworks excavation
Disposal of waste materials

10 06-Mar-14 A

14-Apr-14 A

100%

100%

QR20,777.03

Excavation for network line pipes

138 31-Aug-13 A
121 31-Aug-13 A

12-Jan-14 A
19-Dec-13 A

100%
100%

100%
100%

QR47,787.17
QR14,543.92

Excavation for network line pipes

Install HDPE network line pipes & zone valves's installation

116 09-Sep-13 A

24-Dec-13 A

100%

100%

QR14,543.92

Install HDPE network line pipes & zone valve

85 12-Oct-13 A

31-Dec-13 A

100%

100%

QR14,543.92

Backfilling and compaction

100%

100%

QR4,155.41

Pre-testing of irrigation

80%
100%

100%
100%

QR51,942.58
QR10,388.52

Fix shade structure concrete foun

100%

100%

QR20,777.03

Fix shade structura

50%

100%

QR20,777.03

Fix fabric shades

Irrigation piping main laying & zone valve's installation

Backfilling and compaction


Pre-testing of irrigation

6 25-Dec-13 A

12-Jan-14 A

137 06-Mar-14 A
15 06-Mar-14 A

30-Jun-14
13-Mar-14 A

Fix shade structural elements

10 10-Apr-14 A

25-Jun-14 A

Fix fabric shades

10 25-Jun-14 A

30-Jun-14

46 06-Mar-14 A
15 06-Mar-14 A

17-Apr-14 A
13-Mar-14 A

100%
100%

100%
100%

QR22,854.74
QR10,388.52

Shade structures erection


Fix shade structure concrete foundations

Signage structures erection


Fix signage structure concrete foundations
Fix signage

23

23

Fix signage structure concrete fou

18 31-Mar-14 A

17-Apr-14 A

100%

100%

QR12,466.22

139 22-Dec-13 A
30 22-Dec-13 A

30-Apr-14 A
31-Dec-13 A

100%
100%

100%
100%

QR87,263.53
QR20,777.03

Install sprinklers for lawn

30 22-Dec-13 A

30-Apr-14 A

100%

100%

QR20,777.03

Install sprinklers for lawn

Install bublers for palm & trees

30 22-Dec-13 A

30-Apr-14 A

100%

100%

QR20,777.03

Install bublers for palm & tr

Install automation & time controls

30 22-Dec-13 A

30-Apr-14 A

100%

100%

QR20,777.03

Install automation & time co

6 17-Apr-14 A

30-Apr-14 A

100%

100%

QR4,155.41

Irrigation lateral piping & distribution accessories


Install drip lines for shrubs & ground covers

Pre-testing of irrigation

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Fix signage
Install drip lines for shrubs & ground covers

Pre-testing of irrigation

Page 22 of 25

Activity Name

Original Start
Duration

Road Kerb and Furnishing Works

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


QR119,121.64
QR14,543.92

2013
N

J Jul A

2014
S

A M

J Jul A

S Oct N

Earthworks excavation

183 10-Sep-13 A
164 10-Sep-13 A

24-Apr-14 A
31-Dec-13 A

100%
100%

100%
100%

Disposal of waste materials

163 11-Sep-13 A

31-Dec-13 A

100%

100%

QR4,155.41

Subgrade formation

163 15-Sep-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Subgrade formation

Concrete foundation for kerbstones

163 17-Sep-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Concrete foundation for kerbstones

Fix kerbs and supports

163 22-Sep-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Fix kerbs and supports

Aggregate subbase and fill compaction

163 24-Sep-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Aggregate subbase and fill compaction

Furnishing works

163 28-Sep-13 A

24-Apr-14 A

100%

100%

QR20,777.03

Earthworks excavation

246 31-Aug-13 A
212 31-Aug-13 A
197 31-Aug-13 A

10-Apr-14 A
31-Dec-13 A
31-Dec-13 A

100%
100%
100%

100%
100%
100%

QR515,270.39
QR128,817.59
QR86,570.96

Disposal of waste materials

196 01-Sep-13 A

31-Dec-13 A

100%

100%

QR4,155.41

Subgrade formation

197 09-Sep-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Subgrade formation

Concrete foundation for shades and signage

196 15-Sep-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Concrete foundation for shades and signag

Earthworks excavation

204 17-Sep-13 A
180 17-Sep-13 A

31-Dec-13 A
31-Dec-13 A

100%
100%

100%
100%

QR119,121.64
QR14,543.92

Disposal of waste materials

180 17-Sep-13 A

31-Dec-13 A

100%

100%

QR4,155.41

Subgrade formation

180 25-Sep-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Subgrade formation

Concrete foundation for kerbstones

180 26-Sep-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Concrete foundation for kerbstones

Fix kerbs and supports

180 28-Sep-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Fix kerbs and supports

Aggregate subbase and fill compaction

180 05-Oct-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Aggregate subbase and fill compaction

Paving works

180 08-Oct-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Paving works

Excavation for network line pipes

184 16-Sep-13 A
172 16-Sep-13 A

31-Dec-13 A
31-Dec-13 A

100%
100%

100%
100%

QR43,631.77
QR10,388.52

Excavation for network line pipes

Install HDPE network line pipes & zone valves's installation

162 30-Sep-13 A

31-Dec-13 A

100%

100%

QR14,543.92

Install HDPE network line pipes & zone valv

Backfilling and compaction

162 06-Oct-13 A

31-Dec-13 A

100%

100%

QR14,543.92

Backfilling and compaction

6 07-Dec-13 A

31-Dec-13 A

100%

100%

QR4,155.41

Fix signage structure concrete foundations

38 06-Mar-14 A
10 06-Mar-14 A

10-Apr-14 A
13-Mar-14 A

100%
100%

100%
100%

QR22,854.74
QR10,388.52

Fix signage

10 31-Mar-14 A

10-Apr-14 A

100%

100%

QR12,466.22

Install drip lines for shrubs & ground covers

20 22-Dec-13 A
20 22-Dec-13 A

31-Dec-13 A
31-Dec-13 A

100%
100%

100%
100%

QR81,723.01
QR19,391.90

Install drip lines for shrubs & ground covers

Install sprinklers for lawn

20 22-Dec-13 A

31-Dec-13 A

100%

100%

QR19,391.90

Install sprinklers for lawn

Install bublers for palm & trees

20 22-Dec-13 A

31-Dec-13 A

100%

100%

QR19,391.90

Install bublers for palm & trees

Install automation & time controls

20 22-Dec-13 A

31-Dec-13 A

100%

100%

QR19,391.90

Install automation & time controls

Zone 16
Concrete foundations for signage

Kerb, plant edgers works

Irrigation piping main laying & zone valve's installation

Pre-testing of irrigation
Signage structures erection

Irrigation lateral piping & distribution accessories

Pre-testing of irrigation

Earthworks excavation
Disposal of waste materials

Furnishing works

Earthworks excavation
Disposal of waste materials

Earthworks excavation
Disposal of waste materials

Pre-testing of irrigation
Fix signage structure concrete fou
Fix signage

6 25-Dec-13 A

31-Dec-13 A

100%

100%

QR4,155.41

Pre-testing of irrigation

Earthworks excavation

184 14-Sep-13 A
140 14-Sep-13 A

31-Dec-13 A
31-Dec-13 A

100%
100%

100%
100%

QR119,121.64
QR14,543.92

Earthworks excavation

Disposal of waste materials

136 17-Sep-13 A

31-Dec-13 A

100%

100%

QR4,155.41

Subgrade formation

136 18-Sep-13 A

31-Dec-13 A

100%

100%

QR17,314.19

Subgrade formation

Concrete foundation for kerbstones

136 22-Sep-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Concrete foundation for kerbstones

Fix kerbs and supports

136 28-Sep-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Fix kerbs and supports

Aggregate subbase and fill compaction

136 29-Sep-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Aggregate subbase and fill compaction

Furnishing works

167 29-Sep-13 A

31-Dec-13 A

100%

100%

QR20,777.03

Furnishing works

13 05-Dec-13 A
9 05-Dec-13 A

30-Jun-14
10-Apr-14 A

-8

98.53%
100%

100%
100%

QR838,036.76
QR428,036.64

Testing and Commissioning fo

30-Jun-14

-8

Testing and Comm

Road Kerb and Furnishing Works

Phase 3 - Testing and Commissioning


Testing and Commissioning for electrical works
Testing and Commissioning for mechanical works

Phase 4 Works
Palm trees and shade trees

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

97%

100%

QR410,000.12

263 25-Sep-13 A

8 10-Dec-13 A

21-Jun-14 A

100%

100%

QR1,466,564.28

217 25-Sep-13 A

21-Jun-14 A

100%

100%

QR459,559.80

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Disposal of waste materials

Page 23 of 25

Activity Name

Original Start
Duration

Planting of palm trees & shade trees in Zone 01

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


O

2013
N

J Jul A

2014
S

A M

J Jul A

S Oct N

110 25-Sep-13 A

06-Mar-14 A

100%

100%

QR25,271.62

Planting of palm trees & shade trees in Zone 02

18 20-Mar-14 A

05-Jun-14 A

100%

100%

QR25,271.46

Planting of palm trees & shade trees in Zone 03

110 30-Sep-13 A

06-Mar-14 A

100%

100%

QR25,271.46

Planting of palm trees & shade tree

Planting of palm trees & shade trees in Zone 04

110 30-Sep-13 A

06-Mar-14 A

100%

100%

QR25,271.46

Planting of palm trees & shade tree

Planting of palm trees & shade trees in Zone 05

110 30-Sep-13 A

06-Mar-14 A

100%

100%

QR25,271.46

Planting of palm trees & shade tree

Planting of palm trees & shade trees in Zone 06

110 30-Sep-13 A

14-Jun-14 A

100%

100%

QR25,271.46

Planting of palm trees & shade trees in Zone 07

110 30-Sep-13 A

14-Jun-14 A

100%

100%

QR25,271.46

Planting of palm trees & shade trees in Zone 08

110 30-Sep-13 A

06-Mar-14 A

100%

100%

QR25,271.46

Planting of palm trees & shade trees in Zone 09

110 30-Sep-13 A

22-May-14 A

100%

100%

QR25,271.46

Planting of palm trees & shade trees in Zone 10

18 04-Mar-14 A

10-Apr-14 A

100%

100%

QR25,271.46

Planting of palm trees & shade

Planting of palm trees & shade trees in Zone 11

110 30-Sep-13 A

06-Mar-14 A

100%

100%

QR25,271.46

Planting of palm trees & shade tree

Planting of palm trees & shade trees in Zone 12

110 30-Sep-13 A

21-Jun-14 A

100%

100%

QR21,151.84

Planting of palm tree

Planting of palm trees & shade trees in Zone 13

110 30-Sep-13 A

13-Mar-14 A

100%

100%

QR21,151.84

Planting of palm trees & shade tre

Planting of palm trees & shade trees in Zone 14

110 30-Sep-13 A

06-Mar-14 A

100%

100%

QR21,151.84

Planting of palm trees & shade tree

Planting of palm trees & shade trees in Zone 15

110 30-Sep-13 A

21-Jun-14 A

100%

100%

QR21,151.84

Planting of palm tree

Planting of palm trees & shade trees in Zone 16

110 30-Sep-13 A

13-Mar-14 A

100%

100%

QR21,151.84

Planting of palm trees & shade tre

Planting of palm trees & shade trees in Zone 17

110 30-Sep-13 A

06-Mar-14 A

100%

100%

QR25,271.46

Planting of palm trees & shade tree

Planting of palm trees & shade trees in Zone 18

18 23-Mar-14 A

12-Jun-14 A

100%

100%

QR25,271.46

Planting of palm trees

Planting of palm trees & shade trees in Zone 19

110 30-Sep-13 A

06-Mar-14 A

100%

100%

QR25,271.46

Planting of palm trees & shade tree

258 30-Sep-13 A
110 30-Sep-13 A

21-Jun-14 A
31-Dec-13 A

100%
100%

100%
100%

QR459,559.64
QR25,271.46

18 01-May-14 A 05-Jun-14 A

100%

100%

QR25,271.46

Shrubs and hedges


Planting of shrubs and hedges in Zone 01
Planting of shrubs and hedges in Zone 02

Planting of palm trees & shade tree


Planting of palm trees

Planting of palm tree


Planting of palm tree
Planting of palm trees & shade tree
Planting of palm trees &

Planting of shrubs and hedges in Zone 01


Planting of shrubs and

Planting of shrubs and hedges in Zone 03

110 30-Sep-13 A

31-Dec-13 A

100%

100%

QR25,271.46

Planting of shrubs and hedges in Zone 03

Planting of shrubs and hedges in Zone 04

110 30-Sep-13 A

31-Dec-13 A

100%

100%

QR25,271.46

Planting of shrubs and hedges in Zone 04

Planting of shrubs and hedges in Zone 05

110 30-Sep-13 A

20-Feb-14 A

100%

100%

QR25,271.46

Planting of shrubs and hedges in Zone 06

110 30-Sep-13 A

21-Jun-14 A

100%

100%

QR25,271.46

Planting of shrubs and hedges in Zone 07

110 30-Sep-13 A

21-Jun-14 A

100%

100%

QR25,271.46

Planting of shrubs and hedges in Zone 08

110 30-Sep-13 A

20-Feb-14 A

100%

100%

QR25,271.46

Planting of shrubs and hedges in Zon

Planting of shrubs and hedges in Zone 09

110 30-Sep-13 A

17-Apr-14 A

100%

100%

QR25,271.46

Planting of shrubs and hedge

Planting of shrubs and hedges in Zone 10

18 09-Mar-14 A

24-Apr-14 A

100%

100%

QR25,271.46

Planting of shrubs and hedg

Planting of shrubs and hedges in Zone 11

110 30-Sep-13 A

20-Feb-14 A

100%

100%

QR25,271.46

Planting of shrubs and hedges in Zon

Planting of shrubs and hedges in Zone 12

110 30-Sep-13 A

30-Apr-14 A

100%

100%

QR21,151.84

Planting of shrubs and hed

Planting of shrubs and hedges in Zone 13

110 30-Sep-13 A

13-Mar-14 A

100%

100%

QR21,151.84

Planting of shrubs and hedges in

Planting of shrubs and hedges in Zone 14

110 30-Sep-13 A

20-Feb-14 A

100%

100%

QR21,151.84

Planting of shrubs and hedges in Zon

Planting of shrubs and hedges in Zone 15

110 30-Sep-13 A

30-Apr-14 A

100%

100%

QR21,151.84

Planting of shrubs and hedges in Zone 16

110 30-Sep-13 A

31-Dec-13 A

100%

100%

QR21,151.84

Planting of shrubs and hedges in Zone 17

110 30-Sep-13 A

20-Feb-14 A

100%

100%

QR25,271.46

Planting of shrubs and hedges in Zone 18

18 09-Mar-14 A

29-May-14 A

100%

100%

QR25,271.46

Planting of shrubs and hedges in Zone 19

110 30-Sep-13 A

20-Feb-14 A

100%

100%

QR25,271.46

Ground cover works in Zone 01

242 30-Sep-13 A
110 30-Sep-13 A

14-Jun-14 A
20-Feb-14 A

100%
100%

100%
100%

QR459,559.64
QR25,271.46

Ground cover works in Zone 02

18 30-Sep-13 A

14-Jun-14 A

100%

100%

QR25,271.46

Ground cover works in Zone 03

110 30-Sep-13 A

20-Feb-14 A

100%

100%

QR25,271.46

Ground cover works in Zone 03

Ground cover works in Zone 04

110 09-Jan-14 A

20-Feb-14 A

100%

100%

QR25,271.46

Ground cover works in Zone 04

Ground cover works in Zone 05

110 09-Jan-14 A

23-Feb-14 A

100%

100%

QR25,271.46

Ground cover works in Zone 05

Ground cover works in Zone 06

18 27-Mar-14 A

12-Jun-14 A

100%

100%

QR25,271.46

Ground cover works in Zone 07

18 17-Apr-14 A

12-Jun-14 A

100%

100%

QR25,271.46

Ground cover works in Zone 08

18 15-Jan-14 A

20-Feb-14 A

100%

100%

QR25,271.46

Ground cover works

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Planting of shrubs and hedges in Zon


Planting of shrubs a
Planting of shrubs a

Planting of shrubs and hed


Planting of shrubs and hedges in Zone 16
Planting of shrubs and hedges in Zon
Planting of shrubs and
Planting of shrubs and hedges in Zon
Ground cover works in Zone 01
Ground cover works

Ground cover works


Ground cover works
Ground cover works in Zone 08

Page 24 of 25

Activity Name

Original Start
Duration

Finish

Total
Float

Actual %
Complete

Planned %
Complete

COI-01 Total Cost


O

2013
N

J Jul A

2014
S

A M

J Jul A

S Oct N

Ground cover works in Zone 09

18 16-Mar-14 A

10-Apr-14 A

100%

100%

QR25,271.46

Ground cover works in Zone 10

18 16-Mar-14 A

24-Apr-14 A

100%

100%

QR25,271.46

Ground cover works in Zone 11

18 13-Feb-14 A

20-Feb-14 A

100%

100%

QR25,271.46

Ground cover works in Zone 12

18 27-Mar-14 A

24-Apr-14 A

100%

100%

QR21,151.84

Ground cover works in Zone 13

18 13-Feb-14 A

23-Mar-14 A

100%

100%

QR21,151.84

Ground cover works in Zone 14

18 13-Feb-14 A

16-Mar-14 A

100%

100%

QR21,151.84

Ground cover works in Zone 15

18 16-Mar-14 A

24-Apr-14 A

100%

100%

QR21,151.84

Ground cover works in Zon

Ground cover works in Zone 16

18 13-Feb-14 A

24-Apr-14 A

100%

100%

QR21,151.84

Ground cover works in Zon

Ground cover works in Zone 17

18 13-Feb-14 A

20-Feb-14 A

100%

100%

QR25,271.46

Ground cover works in Zone 18

18 16-Mar-14 A

29-May-14 A

100%

100%

QR25,271.46

Ground cover works in Zone 19

18 13-Feb-14 A

20-Feb-14 A

100%

100%

QR25,271.46

Area cleaning & refurbishment works in Phase 01

71 02-Mar-14 A
21 02-Mar-14 A

21-Jun-14 A
31-May-14 A

100%
100%

100%
100%

QR87,885.20
QR28,837.33

Area cleaning & refurbishment works in Phase 02

21 02-Mar-14 A

21-Jun-14 A

100%

100%

QR28,837.33

Area cleaning & refu

Area cleaning & refurbishment works in Phase 03

23 08-Apr-14 A

21-Jun-14 A

Area cleaning & refu

83 10-Apr-14 A

30-Jun-14

6 10-Apr-14 A

Area cleaning and refurbishment works

TESTING & COMMISSIONING (PROVISIONAL ACCEPTE


Prepare punch list Category "A"

100%

100%

QR30,210.54

21

60.41%

100%

QR1,047,545.95

Ground cover works in Zone


Ground cover works in Zon
Ground cover works in Zone 11
Ground cover works in Zon
Ground cover works in Zone 13
Ground cover works in Zone 14

Ground cover works in Zone 17


Ground cover works in
Ground cover works in Zone 19
Area cleaning & refurb

30-Jun-14

-9

88%

100%

QR125,045.68

Prepare punch list

Clear punch list Category "A"

14 01-May-14 A 30-Jun-14

21

65%

100%

QR239,166.74

Clear punch list Ca

Pre-commissioning for irrigation, utilities and electrical system

10 19-Apr-14 A

30-Jun-14

21

65%

100%

QR170,833.38

Pre-commissioning

Prepare punch list Category "B"

6 18-May-14 A 30-Jun-14

21

50%

100%

QR102,500.03

Prepare punch list

Clear punch list Category "B"

14 17-May-14 A 30-Jun-14

21

50%

100%

QR239,166.74

Clear punch list Ca

Final testing & commissioning for irrigation, utilities and electrical system

10 14-Jun-14 A

30-Jun-14

21

50%

100%

QR170,833.38

Final testing & com

109 19-Apr-14 A

26-Jul-14

-7

45.67%

73.37%

QR1,257,055.13

FINAL DOCUMENTATION and FINAL ACCEPTANCE CER


As-built Drawings

83 19-Apr-14 A

30-Jun-14

-8

42.59%

100%

QR367,460.78

Prepare & submit As-built Drawings

45 19-Apr-14 A

30-Jun-14

-9

50%

100%

QR231,298.38

Prepare & submit A

Company review & approval of As-built drawings

10 26-Jun-14 A

30-Jun-14

-6

30%

100%

QR136,162.40

Company review &

34 07-Jun-14 A

06-Jul-14

-9

38%

100%

QR226,937.33

Prepare & Submit Redline Mark-ups

30 07-Jun-14 A

30-Jun-14

-9

50%

100%

QR136,162.40

Prepare & Submit

Company Review & approval of Redline Mark-ups

11 26-Jun-14 A

06-Jul-14

-5

20%

100%

QR90,774.93

Company Review

25 07-Jun-14 A

10-Jul-14

-8

50%

59.2%

QR118,007.41

25 07-Jun-14 A

10-Jul-14

-8

50%

59.2%

QR118,007.41

25 07-Jun-14 A

15-Jul-14

-8

50%

35.2%

QR113,468.67

25 07-Jun-14 A

15-Jul-14

-8

50%

35.2%

QR113,468.67

25 07-Jun-14 A

21-Jul-14

-8

50%

7.2%

QR113,468.67

25 07-Jun-14 A

21-Jul-14

-8

50%

7.2%

QR113,468.67

69 07-Jun-14 A

26-Jul-14

-8

50%

66.09%

QR317,712.27

69 07-Jun-14 A

26-Jul-14

-8

50%

66.09%

QR317,712.27

Redline Mark-ups

Project Dossier
Prepare & Submit project dossier

Material Take-off
Prepare & Submit material take-off & spare parts

O&M Manual
Prepare & submit O&M Manual

Completion of all outstanding snag or punch list items


Completion of all outstanding snag/punch list

Project start: 21-Oct-12


Project end: 26-Jul-14
Data date: 30-Jun-14

Remaining

RGCP472PEPQAR001-RVD

Actual
Critical Remaining Work
Milestone

EPC of Building External Areas Upgrade in


Admin Area at Ras Laffan

Prepare & Submi


Prepare & Subm
Prepare & subm
Completion of a

Page 25 of 25

14. PROGRESS PHOTOS

Progress photos for June 2014

Вам также может понравиться