Вы находитесь на странице: 1из 4

Refer to Note 1 of the General Notes for S.

Aramco
Inspection responsibility, afterwhich pre-arranged
witnessing shall be agreed upon.
MATERIAL RECEIVING
Random witnessing by S. Aramco at each calibration
cycle.
2.3
Positive Material Identification of Low
Alloy, Stainless Steel, Nickel & Copper
Based Materials (If Required)
SAIC-L-2010
SAIC-L-2010
SATR-L-2012
SATR-L-2013
H1 W2
W2
SAIC-W-2079
Production Weld Hardness Testing
Procedure
H1
SAIC-W-2080
SAIC-L-2004
See Remarks
2.2
Welding Equipment Calibration
Verification
1.8 Non-Destructive Testing Procedures
1.9
1.5
SAIC-W-2081
SAIC-W-2082
SATR-W-2009
SATR-W-2011
WELDING OF API TANKS
DOCUMENT REVIEW
2.0
Receiving Inspection and Verification of
Welding Consumables-(Properties, Type,
approve source, storage, etc.)
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Welder & Welding Operator
Certifications (and Issuance of J CC)
SAIC-W-2035
QUALITY
PROCEDURE
1.0
SAIC-W-2075
ITEM
NO.
PROJ ECT TITLE:
1.2
1.1
Review of Procedure for Control of
Welding Consumables
Positive Material Identification Procedure
(Alloy Verification)
1.6
1.4 Weld J oint Identification System
1.7
1.3
APPROVED DATE
25-May-05
See SATIP No: W-014-01
SATIP No.
SATIP-W-017-01
QUALITY
RECORD
RH1
RH1
Welding Procedure
Specifications/Welding Procedure
Qualification Record (WPS/WPQR)
Method Statement & WPS for Weld
Repair
SAIC-W-2076
Post Weld Heat Treatment (PWHT)
Procedure
SAIC-W-2078
SAIC-W-2077
Welding of Overlays & Clad Materials
(If Required)
R1
RH1 RH1
RH1 RH1
RH1 RH1
RH1
DISCIPLINE:
REMARKS
INSPECTION RESPONSIBILITY
ASSIGNMENTS
MECHANICAL
PROJECT PHASE &
ACTIVITY CODE
TASK / ACTIVITY
CNTRCTR
RH1
CONTRACTOR/SUBCONTRACTOR
RH1
WBS/BI/J O/NO.
SAUDI
ARAMCO
3.0 INSTALLATION
SAIC-W-2082
Refer to the respective SATIP for NDE (SATIP-NDE-UT-
01, LPT-01, MPT-01, RT-01)
RH1 SATR-W-2004
RH1
RH1 R1
S. Aramco shall verify and inspect the first batch of
delivered consumables, then random inspection
thereafter.
SAIC-W-2081 H1 W2 2.1
3.1
SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)
Page 1 of 4
WELDING OF API TANKS
SAUDI ARAMCO TYPICAL INSPECTION PLAN
QUALITY
PROCEDURE
ITEM
NO.
PROJ ECT TITLE:
APPROVED DATE
25-May-05
SATIP No.
SATIP-W-017-01
QUALITY
RECORD
DISCIPLINE:
REMARKS
INSPECTION RESPONSIBILITY
ASSIGNMENTS
MECHANICAL
PROJECT PHASE &
ACTIVITY CODE
TASK / ACTIVITY
CNTRCTR
CONTRACTOR/SUBCONTRACTOR WBS/BI/J O/NO.
SAUDI
ARAMCO
SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)
SAIC-W-2089
SATR-W-2005
R1 S. Aramco reviews on weekly basis.
Refer to Note 1 of the General Notes for S.Aramco
Inspection responsibility, afterwhich pre-arranged
witnessing shall be agreed upon.
H1 W1/R1 3.11
Post Weld Heat Treatment Inspection (If
Required)
SAIC-W-2089
H1 W1 SAIC-W-2087
SAIC-W-2088
SAIC-W-2088
SATR-W-2007
3.9 Post-Welding Visual Inspection
3.15 Selection of Weld J oints for NDE (Tanks) H1
"W2"--Refer to Note 1 of the General Notes for
S.Aramco Inspection responsibility, then random
inspection thereafter.
3.8 In-Process Weld Inspection SAIC-W-2086
S. Aramco's responsibilities varies as follows:
a) "S" - Generally is a surveillance activity for Saudi
Aramco, except in welding of stainless steel tanks and
tanks in low temp service.
b) "W2" - S. Aramco inspects and verifies Heat Input at
random or on routine basis for low temp service and for
stainless steel welding.
SAIC-W-2086
SATR-W-2007
W1
S/W2
(See
remarks)
H1 W2 3.7 Pre-Welding Inspection SAIC-W-2085
SAIC-W-2085
SATR-W-2006
SAIC-W-2084
SAIC-W-2084
SATR-W-2006
H1
3.5
Control of Welding Consumables-
Storage, Handling, Issuance &
Conditioning
SAIC-W-2083
See SATIP No: W-016-01
3.4 Welding of piping appurtenances See SATIP-W-011-01
H1 S
W1/H1
Saudi Aramco inspection responsibility varies from H1
to W1:
a) " W1" -for build-up thickness not exceeding 1/3
of the metal thickness or 10mm whicever is
less.
b) " H1" - for build-up thickness exceeding the above
and requiring CSD's approval.
See SATIP N0: W-016-01 or other SATIP-W series as
required
Welding of Strip Linings
(If Required)
Buttering or Weld Build-Up of J oints
Welding of Special Corrosion-Resistant
Materials
(If Required)
SAIC-W-2083
SATR-W-2010
3.3
3.2
3.6
Page 2 of 4
WELDING OF API TANKS
SAUDI ARAMCO TYPICAL INSPECTION PLAN
QUALITY
PROCEDURE
ITEM
NO.
PROJ ECT TITLE:
APPROVED DATE
25-May-05
SATIP No.
SATIP-W-017-01
QUALITY
RECORD
DISCIPLINE:
REMARKS
INSPECTION RESPONSIBILITY
ASSIGNMENTS
MECHANICAL
PROJECT PHASE &
ACTIVITY CODE
TASK / ACTIVITY
CNTRCTR
CONTRACTOR/SUBCONTRACTOR WBS/BI/J O/NO.
SAUDI
ARAMCO
SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)
W1 & R1
Refer to Note 1 of the General Notes for S.Aramco
Inspection responsibility, afterwhich pre-arranged
witnessing shall be agreed upon.
3.12 Weld Repair Verification and Inspection SAIC-W-2091
S. Aramco reviews on weekly basis. 3.15
Weekly Reporting of the following:
a) Production Weld and Welder
b) Welder Repair Rate
c) Welder repair Assessment & Tracer
Welds
SAIC-W-2090
SAIC-W-2090
SATR-W-2013
SATR-W-2018
SATR-W-2019
H1
3
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
representative is not present.
4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
3.13
3.12
SAIC-W-2092
SATR-W-2012
SAIC-L-2010
SAIC-W-2092
Positive Material Identification (PMI) of
Deposited Weld for alloyed materials
within the scope of SAES-A-206.
SAIC-L-2010
SATR-L-2012
SATR-L-2013
Refer to Note 1 of the General Notes for S.Aramco
Inspection responsibility, afterwhich pre-arranged
witnessing shall be agreed upon.
Refer to Note 1 of the General Notes for S.Aramco
Inspection responsibility, afterwhich pre-arranged
witnessing shall be agreed upon.
W1 & R1 H1
W1/R1 H1
Verification of Hardness Testing
Application and Results (If Required)
4.0
4.1
3.14
Verification of Non-Destructive
Examination Method Application and
Evaluation of Results
See Remarks W1/RH1 W1/R1
R1
SAIC-W-2091
SATR-W-2012
H1
Refer to Note 1 of the General Notes for S.Aramco
Inspection responsibility, afterwhich pre-arranged or
random Review shall be agreed upon.
* Use the applicable SATIPS:
a) SATIP-D-100-01
b) SATIP-NDE-LPT-01
c) SATIP-NDE-MPT-01
d) SATIP-NDE-RT-01
e) SATIP-NDE-UT-01
**Refer to Note 1 of the General Notes for S.Aramco
Inspection responsibility, afterwhich pre-arranged or
random Witnessing shall be agreed upon.
PRE-COMMISSIONING
H1 R1
GENERAL NOTES
1
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
levels of Saudi Aramco participation based upon the Contractors performance.
Final Welding Inspection & Document
Verification (Welding Summary Report/
Record & Weld Map)
SATR-W-2008
(or equiv)
Page 3 of 4
WELDING OF API TANKS
SAUDI ARAMCO TYPICAL INSPECTION PLAN
QUALITY
PROCEDURE
ITEM
NO.
PROJ ECT TITLE:
APPROVED DATE
25-May-05
SATIP No.
SATIP-W-017-01
QUALITY
RECORD
DISCIPLINE:
REMARKS
INSPECTION RESPONSIBILITY
ASSIGNMENTS
MECHANICAL
PROJECT PHASE &
ACTIVITY CODE
TASK / ACTIVITY
CNTRCTR
CONTRACTOR/SUBCONTRACTOR WBS/BI/J O/NO.
SAUDI
ARAMCO
SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)
5
R1
H1 100% Hold Point for QC Inspection or Test R2 Sample Review of Documents
100% Review of Documents
If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
W1 100% Witness Inspection/Test H2 Sample Hold Point for QC Inspection or Test
W2 Sample Witness Inspection/Test
100% Review and Approval of Documents RH1
RH2 Sample Review and Approval of Documents
S Surveillance
Page 4 of 4

Вам также может понравиться