Recommendations include as a table in the following format:

Recommendation Likely resource implications Priority Target date


Observation #1

a. The tools are to be
removed from the
workshop by the
supervisor in charge.

b. Review and
application of The Safe
System of Work for
Tool Storage and Use
is called for.


A 1 week would be enough to
serve this purpose. No cost



45 minutes to One hour of
reassessment and application.
No cost


High (1 week)




Low (2 Months)

Observation #2

Constant reminders
from the supervisor to
the workers about the
dangers of an electrical
generator.

Regular inspections
preventing accidents
involving the electric
generator.


Prevent access to the
electric generator by
posting a guard or
building a fence.


No cost, only the supervisors
time.





No cost.






Guards salary
1 day




Ongoing




2 months

Observation #3

The Fire extinguisher
should be sent to
maintenance.


Replacement of fire
extinguishers and
adaptation of a better
storage area is
recommended.


Immediate


1 month

Observation #4



Ongoing

Observation #5
Proper Training and
regular fire drills for all
the employees on site.


Reminders about the
allocated cooking area
will be given to all
employees.

Risk assessment for all
activities, further action
will be enforced
afterwards.
Observation #6
First Aid Kits will be
supplied and all
employees will be
given familiarization as
to where the kits are.

The first aid kits will be
properly labelled as
such.

2 weeks




1 month

Observation #7
All First Aid kits will be
resupplied regularly.



2 weeks




1 month

Observation #8
Additional First Aid kits
should be supplied to
the site.

Positive finding.
Continuously ensure
the PPE remains in
good condition.


1 week



1 month

Observation #9
Positive finding. Keep
proper maintenance of
the pump and filter so
that it continues to
produce clean water.
Be noted that this water
is to be used for
showering only and not
drinking.

2 months


Observation #10
Installation of a drip
tray is recommended to
avoid leaking into the
ground.


N/A

Observation #11
Completion and writing
up of the Material
Safety Data Sheets,
putting it up in the area
for any handlers to
read as well as in case
of spillage and other
emergencies.


N/A

Observation #12
Allocate a more proper
place for the storage of
these items and
unused materials.


2 months

Observation #13
Inform the Area
supervisor to move the
hazard to a safer
position.


2 months

Observation #14

The portable generator
will be stored in an
appropriate area and
away from temperate
areas. All work in the
immediate area will be
halted and cleared of
personnel. Personnel
would be briefed on
how to perform
maintenance of the
said generator.


1 month

Observation #15
Best practices show
that according to the
international standards
to best reduce it to
about 20 km/hr. A new

1 week

sign could be
implemented with the
new number as well as
the proper unit term.

Observation #16
Install dual language
signs for the
convenience of visitors
and contractors.


Immediate

Observation #19
To be noted to the
supervisor for possible
remedial reminder and
training.

Note the supervisor for
constant reminders and
training.

Include this as a part of
the inspection and
rounds to be done for
the on-site supervisor.

1 week

Observation #20
There should be a
good toolbox talk or a
notice to r0065mind
and tell the people
involved to remember
not to leave the keys in
the ignition of any
vehicles or machinery
as best practically
possible. .


Immediate



Immediate







Ongoing



1 month



2 months



3 months