Академический Документы
Профессиональный Документы
Культура Документы
2M
X
t
+2Me
X
t
+Mo
X
t
(1)
where X
t
is the active (P
t
) or reactive (Q
t
) power value for hour
t of the typical load curve; M{X
t
} the sample average; Me{X
t
} the
sample median (central number of a sample); Mo{X
t
} is the sample
mode (more repeated value of a sample).
Each customer is associated to a typical load curve, according to
the monthly electric energy consumption and the economic activ-
ity data. This association also enables to know the load factor of a
typical load curve. The maximumdemand for a group of customers
k is calculated based on the load factor and on the monthly electric
energy consumption values:
P
Max
k
=
W
k
T f
Ck
(2)
where P
Max
k
is the maximum demand for a group of customers k
(kW); W
k
the monthly electric energy consumption (kWh); T is the
monthly period (h); f
Ck
is the load factor.
Since the typical curves used are normalized according to the
maximum active demand, the load curve for a group of customers
k can be built by multiplying each ordinate by this value:
P
kUt
= P
Max
k
P
kUt
;
P
kSt
= P
Max
k
P
kSt
;
Please cite this article in press as: D.P. Bernardon, et al., Electric distribution network reconguration based on a fuzzy multi-criteria
decision making algorithm, Electr. Power Syst. Res. (2009), doi:10.1016/j.epsr.2009.04.012
ARTICLE IN PRESS
G Model
EPSR-2869; No. of Pages 8
D.P. Bernardon et al. / Electric Power Systems Research xxx (2009) xxxxxx 3
P
kDt
= P
Max
k
P
kDt
. (3)
Q
kUt
= P
Max
k
Q
kUt
Q
kSt
= P
Max
k
Q
kSt
;
Q
kDt
= P
Max
k
Q
kDt
(4)
where P
kt
and Q
kt
are the active and reactive power values, nor-
malized for ordinate t of typical curve k; U the working days; S the
saturdays; D is sundays or holidays.
The complete load curves for the distribution transformer j,
considering working days, saturdays and sundays, can be created
through the sum of the load curves of the several groups of cus-
tomers k connected to it:
P
jUt
=
k
P
kUt
; P
jSt
=
k
P
kSt
and P
jDt
=
k
P
kDt
(5)
Q
jUt
=
k
Q
kUt
; Q
jSt
=
k
Q
kSt
and Q
jDt
=
k
Q
kDt
(6)
Using these load curves, it is possible to analyse several load
levels according to the utilities requirements. Inthe network recon-
guration case studies, the maximum load prole was adopted
by properly representing the worst operation scenario considering
power losses.
Fig. 1 shows the comparison of the results obtained by applying
our proposed method and the traditional methods (use of simple
average) for modelling the power load prole. In this case, a feeder
was selected, whose two distribution transformers were measured.
Comparatively, the modelled curves are quite similar to the
measured curves (load prole and values). Although small, the
difference between the modelled loads shows that our proposed
method achieved a better result than the traditional methods,
because the values were closer of the measured.
3. Topology algorithm
A common approach for the topological representation of elec-
trical networks is the use of a matrix. In this approach, all the
connections between elements are expressed to enable that the
congurationof the representeddistributionnetwork canbe repro-
duced faithfully. However, for real distribution systems, the matrix
can be sparse, which can lead to unnecessary processing time. For
this reason, an alternative method was developed [13] to repre-
sent only the existing connections, without the use of matrices.
This method enables faster and simpler calculation of load ows
and execution of optimization algorithms.
Two sets are needed to represent information: one for the nodes
and another one for the branches. Each branch is represented by an
initial and a nal node. It is essential to set the initial node to be
the closest node from the main source providing power (i.e. the
substation).
This methodology allows the identication of dependen-
cies among the networks, loads and devices, and also checks
the conguration correctness and completeness. Therefore, two
characteristics are added to the elements to represent existing con-
nections between them:
Information about the branch within the branch set;
Information about the feeding branch of the branch being
considered.
The parameter is usedonly to identify the order of the network
branch within the branch set (we opted for a numerical order). The
Fig. 2. Representation of parameters and .
parameter receives the value of the parameter upstream of the
considered branch. Fig. 2 shows the representation of and .
The electric way of a radial system can be obtained using this
methodology, as shown in Table 1.
Sections 4 and 5 describe, respectively, the algorithms for load
ow calculation and for network reconguration. Both algorithms
consider the previously presented representation.
4. Algorithm of load ow
A version of the classical backward/forward sweep algorithmto
calculate the load ow in radial distribution networks is provided
in [14]. The solution is found only iteratively, because the loads are
modelled as constant power and because the current absorbed by
the loads depends onthe voltage (anunknownvalue). The resulting
procedure is described as follows:
1st Stage: Let the voltage at all points of the feeder be equal to the
voltage measured at the substation bar. This data can be automat-
ically gathered by the remote measurement systems installed at
the substations. Do not consider voltage drops in the branches at
this stage.
2nd Stage: Compute the active and reactive components of the
primary currents absorbed and/or injected in the system by the
electrical elements.
3rd Stage: Obtain the current in all network branches. This stage
includes two steps: (a) search the node set to dene the current
values of each branch, and (b) accumulate the currents from the
nal sections upstream to the substation.
4th Stage: Compute the voltage drops in the branches.
5th Stage: Obtain the accumulated voltage drops in all the pri-
mary network sections fromthe substation bar, thus obtaining the
voltage values at any other point.
6th Stage: Compute the difference between the new voltage val-
ues for all nodes and the previous values. If it is small enough,
the solution for the load ow calculation was found and the sys-
tem is considered convergent. Otherwise, the previous steps are
repeated, starting fromthe second stage, using the computed volt-
ages to obtain the current values. The iteration stops when the
difference found is lower than a threshold. In this paper, a thresh-
Table 1
Network in Fig. 2.
Initial node Final node Characteristic Characteristic
0 1 1
1 2 2 1
2 3 3 2
3 4 4 3
4 5 5 4
3 6 6 3
6 7 7 6
1 8 8 1
8 9 9 8
Please cite this article in press as: D.P. Bernardon, et al., Electric distribution network reconguration based on a fuzzy multi-criteria
decision making algorithm, Electr. Power Syst. Res. (2009), doi:10.1016/j.epsr.2009.04.012
ARTICLE IN PRESS
G Model
EPSR-2869; No. of Pages 8
4 D.P. Bernardon et al. / Electric Power Systems Research xxx (2009) xxxxxx
old of 1% was chosen, because it promotes accurate values for the
status variables without requiring too much time to process.
In the end of the process, the active and reactive powers and the
technical losses in the primary conductors are dened for all feeder
branches.
5. Distribution network reconguration
An optimization problem is derived from the switching proce-
dures to change the network topology. This problem is known as
the network reconguration problem. The main goal is to nd an
optimal operation strategy.
An efcient solution for this problem requires the selection of
the most appropriated operation topology among all the available
congurations. Thecost of inspectingall thepossiblecongurations
is prohibitive for current distribution systems, as the number of
possible congurations grows exponentially given the number of
switches and their layout in the system. Such exponential growth
is known as a combinatorial explosion [15].
Therefore, a heuristic algorithm for the solution of the dis-
tribution network reconguration problem is proposed, using an
efcient fuzzy multi-criteria decision making method. It removes
the less promising congurations, aiming at reducing the search
space of the optimization problem. The goal is to reduce power
losses, enhance the voltage prole for customers, and increase the
reliability levels.
The optimization criteria and the constraints according to the
inherent characteristics of the problem are dened, to the regula-
tion policies, and to public awareness.
5.1. Objective functions and constraints
Several aspects are considered in the denition of the objective
function of the network reconguration problem. The minimiza-
tion of power losses is one of the most commonly considered ones,
together with the maximization of the reliability indexes, used by
several researchers as another aspect to be addressed [16].
The current limit on the electrical elements (conductors, trans-
formers, protection and switching devices) is a typical constraint
included in the network reconguration problem. Another impor-
tant and frequent constraint is the voltage limit, closely related to
power quality [17].
Considering the previous comments, the objective functions and
constraints are dened as follows:
Objective functions:
i
3
I
i
2
r
i
. (7)
j
(
0n
Protjn
C
Protjn
). (8)
Constraints:
Radial network;
I
i
I
i max
. (9)
Protjn
the length of branches protected by the protective device
j at feeder n; C
Protjn
is the number of customers downstream the
protective device j at feeder n.
The load ow method presented in Section 4 computes the
power losses in the distribution network. Traditional reliability
equations [18] are used to compute the number of interrupted cus-
tomers per year. Note that this objective function is closely related
to SAIFI (SystemAverage Interruption Frequency Index). Violations
of limits related to current and voltage on the electrical elements
are prohibited.
5.2. The proposed method for selecting congurations
Heuristic search procedures in the denition of the proposed
methodology is considered, based on the branch-exchange strategy
[19]. Using this strategy, a radial conguration is assumed at rst
and several switching procedures are applied, aiming at producing
newandpromisingcongurations, always maintainingthenetwork
radial topology. These applied procedures correspond to open one
switch and to close another one.
The generated congurations are then classied accord-
ing to the dened objective functions, while still considering
the chosen constraints. Note that infeasible solutions are
removed.
The key idea is to analyse the tie (normally opened) switches
between feeders. For each tie-switch, the best conguration is con-
sideredregardingthetwofeeders involved. Inthis moment, isolated
analyses for each tie-switch are conducted based on the initial con-
guration.
The algorithm for selecting the candidate congurations is
dened as follows:
1st Stage: Change the network conguration, closing an NO
(normally opened) tie-switch and opening an NC (normally
closed) switch of any of the two feeders involved. However,
it should be the rst switch upstream from the tie-switch
(Fig. 3).
2nd Stage: Perform the load ow calculation for this new congu-
ration and check if both objective functions are improved without
violating the constraints. If they are improved, proceed to the 3rd
stage. Otherwise, go to the 4th stage.
3rd Stage: Change the network conguration, closing the actual
NO tie-switch and opening the rst NC switch upstream from
the NO tie-switch, but in the same direction (feeder) that the
switch was opened in the previous iteration (Fig. 4). Go to the 5th
stage.
4th Stage: Re-establish the initial conguration and change the
network topology, closing the NO tie-switch and opening the NC
switch of the other feeder upstream from the tie-switch (Fig. 5).
Go to the 5th stage.
5th Stage: The 3rd stage is performed when both objective func-
tions are improved for the considered conguration without
violating the dened constraints. The process is completed and
conguration of the previous iteration is assumed as nal if infea-
sibility is found or one of the objective functions does not improve
a given conguration.
The process must be repeated when another tie-switch is anal-
ysed, beginning from the initial conguration.
Please cite this article in press as: D.P. Bernardon, et al., Electric distribution network reconguration based on a fuzzy multi-criteria
decision making algorithm, Electr. Power Syst. Res. (2009), doi:10.1016/j.epsr.2009.04.012
ARTICLE IN PRESS
G Model
EPSR-2869; No. of Pages 8
D.P. Bernardon et al. / Electric Power Systems Research xxx (2009) xxxxxx 5
Fig. 3. Distribution network: (a) initial conguration and (b) switching status
changed.
5.3. The multi-criteria decision making algorithm
This section presents the algorithm for determining the dis-
tribution network conguration, based on multi-criteria analysis.
The main goal is to dene a sequence of switch manipulations
according to the results obtained from the application of the
method described in the previous section. Multi-criteria analy-
sis guides the switch manipulation, aiming at reaching the best
conguration resulting from the application of our proposed
methodology.
The algorithm is applied to the tie-switches according the best
results, without returning back to the initial conguration when
analysing the next tie-switch. The mainchallenge is to dene which
Fig. 4. Switching status changed.
Fig. 5. Switching status changed on the opposite direction.
tie-switches hold the best results according to the two objective
functions. For example, one conguration has the most promising
values for power losses, whereas the other one is better evaluated
for the reliability function. A decision making algorithm is the key
for deciding which conguration is the best.
The BellmanZadeh method [9] is used as the decision making
technique for our approach because of its efciency in handling
quantitative and qualitative criteria for the problemresolution. The
objective functions are replaced by other functions in the form of
fuzzy sets.
Eqs. (11) and (12) describe two membership functions: one for
objective functions to be maximized and another one for objective
functions to be minimized, respectively:
A
j
(x) =
F
j
(x)
max
x Dx
F
j
(x)
, (11)
A
j
(x) =
min
x Dx
F
j
(x)
F
j
(x)
, (12)
The maximumintersection between the membership functions
is the best congurationi.e. the best solution, as shown in the
following equation.
max
x Dx
D
(x) = max
x Dx
min
j=1,...,n
A
j
(x). (13)
Fig. 6 illustrates this approach.
Tables 2 and 3 showthe results of a hypothetical example of the
applicationof the BelmanZadehalgorithmfor selecting congura-
tion of distribution networks with ve tie-switches (Fig. 7) whose
membership functions are calculated from the Eq. (11).
This analysis denes the best sequence of tie-switches. Consid-
ering the data in Table 2, for example, the best sequence is TS-5,
TS-4, TS-2, TS-1, and TS-3. Additional analysis can be conducted for
each switch in this sequence. The initial conguration is considered
Fig. 6. Intersection between the membership functions.
Please cite this article in press as: D.P. Bernardon, et al., Electric distribution network reconguration based on a fuzzy multi-criteria
decision making algorithm, Electr. Power Syst. Res. (2009), doi:10.1016/j.epsr.2009.04.012
ARTICLE IN PRESS
G Model
EPSR-2869; No. of Pages 8
6 D.P. Bernardon et al. / Electric Power Systems Research xxx (2009) xxxxxx
Fig. 7. Example network with ve tie-switches.
Table 2
Analysis of results for each tie-switch.
Tie-switch Power losses reduction Number of interrupted
customers per year reduction
TS-1 P
1
=25kW
1
=200
TS-2 P
2
=30kW
2
=300
TS-3 P
3
=20kW
3
=180
TS-4 P
4
=40kW
4
=250
TS-5 P5 =35kW 5 =300
max F
j
(x) 40kW 300
only for the rst one. At the end of this process, the set containing
the switches that yield the best results is obtained.
6. Experimental analysis
The proposed algorithm is tested in one medium size distri-
bution network, presented by Schmidt [20], which includes 96
branches and 28 switches. The best solution for this network was
previously obtained by the exhaustive search considering only the
minimization of power losses, as shown in Table 4.
Case studies are considered including existing networks to ver-
ify the efciency of approach. Fig. 8 presents this network, which
includes 2 substations, 5 feeders, 922 branches, 99 switches, and 15
tie-switches.
Tables 5 and 6 present the results obtained by the application
of our approach to the actual system. Table 7 shows the obtained
results for the proposed method compared to the initial congura-
tion, considering the actual system.
Analysing Table 7, the proposed methodology obtained a reduc-
tion on the power losses of 22.7%, and on the number of interrupted
Fig. 8. Actual distribution network considered.
customers per year of 12.5%, when compared to the initial congu-
ration.
Assuming that there are no guarantees about the optimality of
the solution found, the proposed algorithmwas applied to the nal
solutionfound, describedinTable 6. Giventhat the process does not
yield any improvements, we have been optimistic about the qual-
ity of the solution obtained. The computational time required was
less than 4min to the large system, which seems to be appropriate
for an actual network. In spite of the increasing computation time
comparing to other methods, the values are reasonable with regard
to the complexity of the studied systems.
Table 3
Membership functions values and fuzzy solutions.
Tie-switch Power losses reduction Number of interrupted customers per year reduction Intersection of pertinence functions
TS-1
P
1
(x) = 0.63
1
(x) = 0.67 min
P
1
,
1
= 0.63
TS-2
P
2
(x) = 0.75
2
(x) = 1.00 min
P
2
,
2
= 0.75
TS-3
P
3
(x) = 0.50
3
(x) = 0.60 min
P
3
,
3
= 0.50
TS-4
P
4
(x) = 1.00
4
(x) = 0.83 min
P
4
,
4
= 0.83
TS-5
P
5
(x) = 0.88
5
(x) = 1.00 min
P
5
,
5
= 0.88
Please cite this article in press as: D.P. Bernardon, et al., Electric distribution network reconguration based on a fuzzy multi-criteria
decision making algorithm, Electr. Power Syst. Res. (2009), doi:10.1016/j.epsr.2009.04.012
ARTICLE IN PRESS
G Model
EPSR-2869; No. of Pages 8
D.P. Bernardon et al. / Electric Power Systems Research xxx (2009) xxxxxx 7
Table 4
Results for the reconguration problem.
Parameter Schmidt Method A Schmidt Method B Proposed Method
Initial solution loss (kW) 1447.93 1447.93 1447.93
Optimal solution loss (kW) 1251.55 1251.55 1251.55
Obtained loss (kW) 1320.10 1253.24 1251.55
Difference (%) 5.5 0.1 0.0
Processing time (2.66GHz) (s) 0.16 0.18 18.4
Table 5
Results for each tie-switch analysis.
Individual analysis
(tie-switch)
Power losses
reduction (kW)
Number of interrupted
customers per year reduction
Fuzzy index Sequence
TS-1 0.1 5,185.6 0.002 5
TS-2 0.0 0.0 0.000 6
TS-3 2.3 13,350.3 0.055 4
TS-4 0.0 0.0 0.000 7
TS-5 0.0 0.0 0.000 8
TS-6 0.0 0.0 0.000 9
TS-7 30.2 10,985.0 0.714 2
TS-8 42.2 14,656.8 0.953 0
TS-9 27.6 10,985.0 0.654 3
TS-10 35.7 15,387.7 0.846 1
TS-11 0.0 0.0 0.000 10
TS-12 0.0 0.0 0.000 11
TS-13 0.0 0.0 0.000 12
TS-14 0.0 0.0 0.000 13
TS-15 0.0 0.0 0.000 14
Table 6
Results for the sequence dened in Table 5.
Reconguration
sequence (tie-switch)
Power losses
reduction (kW)
Number of interrupted
customers per year reduction
TS-8 42.2 14,656.8
TS-10 0.0 0.0
TS-7 0.0 0.0
TS-9 6.5 517.7
TS-3 2.0 13,350.3
TS-1 0.0 0.0
TS-2 24.8 2,538.7
TS-4 0.0 0.0
TS-5 0.0 0.0
TS-6 0.0 0.0
TS-11 1.0 923.8
TS-12 0.0 0.0
TS-13 0.4 62.4
TS-14 0.0 0.0
TS-15 0.0 0.0
Total 76.9 32,049.7
Reduction 22.7% 12.5%
Table 7
Results for the network reconguration of Fig. 8.
Conguration Power losses Number of interrupted
customers per year
Initial 338.89kW 255,930.4
Proposed 261.99kW 223,880.7
Reduction 22.7% 12.5%
7. Conclusions and recommendations
The main contribution of this work is a newfuzzy multi-criteria
decision making algorithm for the network reconguration prob-
lem. The algorithm focuses on both power losses reduction and on
the improvement of reliability. Furthermore, the alternative meth-
ods for modelling power load proles and electric topology were
presented. The exibility of the proposed methodology provides
a wide audience for the developed tool support, resulting in a
useful, reliable and easy-to-use tool for utilities. Case studies were
conducted with real data fromutilities to evaluate the performance
of the developed software application, which provided promising
results.
References
[1] E.M. Carreno, R. Romero, A.P. Feltrin, An efcient codication to solve distribu-
tion network for loss reduction problem, IEEE Transactions on Power Systems
23 (4) (2008) 15421551.
[2] M.E. Baran, F.F. Wu, Network reconguration in distribution systems for loss
reduction and load balancing, IEEE Transactions on Power Delivery 4 (2) (1989)
14011407.
[3] Y.Y. Hong, S.Y. Ho, Determination of network conguration considering multi-
objective in distribution systems using genetic algorithms, IEEE Transactions
on Power Systems 20 (2) (2005) 10621069.
[4] K. Nara, Y. Mishima, T. Satoh, Network reconguration for loss minimization
and load balancing, IEEE Power Engineering Society General Meeting 4 (2003).
[5] C.T. Su, C.S. Lee, Network reconguration of distribution systems using
improved mixed-integer hybrid differential evolution, IEEE Transactions on
Power Delivery 18 (3) (2003) 10221027.
[6] D. Das, A fuzzy multiobjective approach for network reconguration of distri-
bution systems, IEEE Transactions on Power Delivery 21 (1) (2006) 202209.
[7] N. Kagan, C.C.B. Oliveira, Fuzzy decision model for the reconguration of distri-
bution networks using genetic algorithms, in: Proceedings of the 13th Power
Systems Computation Conference, Trondheim, 1999.
[8] V. Venkatech, R. Ranjan, H.B. Gooi, Optimal recongurationof radial distribution
systems to maximize loadability, IEEE Transactions on Power Systems 19 (1)
(2004) 260266.
[9] R. Bellman, L.A. Zadeh, Decision making in a fuzzy environment, Management
Science 17 (4) (1970) 141164.
[10] P.Y. Ekel, L.D.B. Terra, M.F.D. Junges, Methods of multicriteria decision making
in fuzzy environment and their applications to power system problems, in:
Proceedings of the 13th Power Systems Computation Conference, vol. 2, 1999,
pp. 755761.
[11] V.A. Popov, P. Ekel, S. Ansuj, Node load modelling and distribution systemstate
estimation using the heuristic approach, in: Proceedings of the International
Symposium on Electrical Power Engineering, Stockholm Power Tech, 1995, pp.
294299.
[12] D.P. Bernardon, L. Comassetto, F.D. Veiga, L.N. Canha, Studies of parallelism in
distribution networks served by different-source substations, Electric Power
Systems Research 78 (3) (2008) 450457.
[13] L. Comassetto, D.P. Bernardon, L.N. Canha, A.R. Abaide, Software for automatic
coordination of protection devices in distribution system, IEEE Transactions on
Power Delivery 23 (4) (2008) 22412246.
[14] D.P. Bernardon, L. Comassetto, L.N. Canha, A.R. Abiade, New methods for dis-
tribution network reconguration frommulticriteria decision-making, in: IEEE
International Conference on Power Engineering, Energy and Electrical Drives,
2007, pp. 225230.
Please cite this article in press as: D.P. Bernardon, et al., Electric distribution network reconguration based on a fuzzy multi-criteria
decision making algorithm, Electr. Power Syst. Res. (2009), doi:10.1016/j.epsr.2009.04.012
ARTICLE IN PRESS
G Model
EPSR-2869; No. of Pages 8
8 D.P. Bernardon et al. / Electric Power Systems Research xxx (2009) xxxxxx
[15] J.T. Boardman, C.C. Meckiff, A branch and bound formulation to an electric-
ity distribution planning problem, IEEE Transaction on Power Apparatus and
Systems 104 (8) (1985) 21122118.
[16] V.A. Popov, A.R. Abaide, L.N. Canha, D.P. Bernardon, et al., Algorithm of relia-
bility optimization for operational planning of distribution systems, IEEE/PES
TransmissionandDistributionConference andExpositionLatinAmerica (2004)
523528.
[17] S. Civanlar, J.J. Grainger, H. Yin, S.S.H. Lee, Distribution feeder reconguration
for loss reduction, IEEE Transactions on Power Delivery 3 (3) (1988) 12171223.
[18] L. Tsai, Network reconguration to enhance reliability of electrical distribution
systems, Electric Power System Research (27) (1993) 135140.
[19] R. Cherkaoui, A. Bart, A.J. Germond, Optimal conguration of electrical distri-
bution networks using heuristic methods, in: Proceedings of the 11th Power
Systems Computation Conference, Zurich, vol. 1, 1993, pp. 147154.
[20] H.P. Schmidt, N. Ida, N. Kagan, J.C. Guaraldo, Fast reconguration of distribution
systems considering loss minimization, IEEE Transactions on Power Systems
20 (3) (2005) 13111319.
Daniel Pinheiro Bernardon was born in Santa Maria, Brazil on the 15th of September
1977. He received his Dr. Eng. degree fromFederal University of Santa Maria, in 2007,
and has been a professor of Electrical Engineering at Federal University of Pampa,
since 2008. His research interests include distribution systemanalysis, planning and
operation, besides working for 8 years in Operation of Electric Systems.
Vincius Jacques Garcia was born in Santo ngelo, Brazil on the 1st of April 1976. He
received his Dr. Eng. degree fromState University of Campinas in 2005 and has been
a professor of Computer and Electrical Engineering at Federal University of Pampa
since 2006. His research interests include distribution system analysis, planning,
operation and combinatorial optimization.
Adriana Scheffer Quintela Ferreira was born in Volta Redonda, Brazil on the 24th of
June 1975. She received her Dr. Eng. degree from University of Campinas, in 2006,
and has been a professor of Electrical Engineering at Federal University of Pampa,
since 2008. Her research interests include transmission system analysis, planning
and operation.
Luciane Neves Canha was born in Santa Maria, Brazil on the 16th of March 1971. She
received her Dr. Eng. degree from Federal University of Santa Maria, in 2004, and
has been a professor of Electrical Engineering at Federal University of Santa Maria,
since 1997. Her research interests include distribution systemanalysis, planning and
operation, distributed generation and renewable energy.