DECEMBER 2009
1.1 Work-scope 2
1.1.3 Transformers 3
5.0 Delivery 7
Our proposal includes for the electrical infrastructure, system design and installation for
Tween Bridge Wind Farm as detailed below.
1.1 Work-scope
Our proposal comprises of the electrical scope of works as described in the tender
documents and includes:
In addition to the above, there are some elements of the work-scope which
still require clarification therefore we have provided provisional sums for the
following items:
The scope of works associated with the 33kV/66kV transformer is not clear from the enquiry
documents. We have therefore allowed a provisional sum allowance within our offer for this
work.
Within the substation, we have allowed for a 2-panel, 33kV DNO switchboard. This board
will be equipped with an incoming isolator and a wind farm circuit breaker. In the absence
of a detailed specification and specific YEDL requirements, we have provided a provisional
sum for this item within the generator transformer provisional sum.
Our offer includes for a wind farm switchboard consisting of a DNO interface circuit breaker,
two wind farm circuit breakers and an auxiliary transformer feeder. The wind farm
switchboard will be controlled from a remote control panel located in the wind farm control
room.
In order to minimise costs, we have allowed for a circuit breaker at every turbine. In the
absence of fault level information we are unable to make an assessment of compliance with
P28. We have therefore made an allowance for a total of six sectionalising switches. This
will ensure that no more than three turbine transformers are energised simultaneously. In
the event that the P28 study indicates that additional sectionalisers are required, then these
can be supplied at additional cost.
1.1.3 Transformers
We have made no allowance for any works associated with the turbine transformers.
Our system design divides the site into two circuits of eleven turbines. SEC will supply,
install and terminate 33kV cables. Cables will be 1-core unarmoured, having aluminium
conductors, XLPE insulation, copper wire screen, PE outer sheath according to BS7870
4.10. Cable cross-sectional areas have been based on soil thermal resistivity of 1.2
oCm/W. Should the actual values on site result in a requirement to alter the cable selection
then we would reserve the option to adjust our costs accordingly. From the information
70 mm2 3 x 1c x 7,300m
Should the actual length installed, exceed these lengths we would reserve the option to
adjust our costs accordingly.
As our offer is based on Siemens’ turbines, our fibre system offer is consists of a ring
topology of 12-fibre, single-mode (9/125) cable. The cable will be supplied within a 32mm
HDPE duct.
Within the substation we have allowed for a comprehensive network of control cabling
between the various items of wind farm hardware such as 33kV switchgear, wind farm
SCADA, DNO interface, tariff metering, etc.
A 33kV/230V, 50kVA transformer will be supplied, from which all low voltage supplies will
be derived for the substation building.
We have also allowed for an LV supply from the nearest turbine to the met mast. It is
assumed that this supply will be provided at the turbine by Siemens.
We have provided costs for the earth loops around each turbine and the main earth
network cabling. The earthing design is based on a resistance earthed scheme. Should the
33kV network neutral/earth link be solid, the earthing system price may require to be
reviewed.
A site earth resistivity survey will be carried out by SEC on which the detailed design of the
earthing scheme will be based.
Earthing will be provided generally in accordance with the requirements of the enquiry
document. All main cable runs will have a copper earth conductor installed at the bottom of
the cable trench. Around each turbine tower an earth system shall be installed, consisting
of two rings of buried conductor, linked to the tower at two points. A system of earthing will
interconnect the main tower structure, tower earth bar and transformer earth bar.
Our proposal includes for the installation of a bare earth conductor to be installed within the
main 33kV cable trench throughout the site. All necessary materials for joints and
interconnections will be supplied. Our design is based on the premise that the earth
conductors linking turbines together form an integral part of the earth electrode system.
The link conductors may be supplemented by either rod or horizontal electrodes at the
turbine, and this is the item covered by our provisional sum. Test links will be installed at
both ends of each link conductor to enable the testing of an individual turbine earth system,
which will include the link conductors to adjacent turbines.
Our costs allow for the fit-out of a building 288m2 in floor area. This includes heating,
lighting (internal/external/emergency), small power, control, voice and data, fire alarm and
intruder alarm
No allowance has been made for any hardware which may be required to facilitate
compliance of the wind turbines with any aspect of Grid Code or Distribution Code
All inspections, checks and tests will be carried out as are necessary to demonstrate full
compliance with the Client’s requirements and all applicable manufacturers' specifications
and recommendations. As far as practicable, inspection, checks and tests will be carried
out as an ongoing activity during the course of the installation. It is envisaged that the
following specific tests will be carried out:-
Documentation will be provided in the form of test certificates and operating and
maintenance manuals.
Our prelim costs are based on a 22-week on-site programme. The costs will require to be
reviewed should the on-site programme exceed this period.
SEC will provide the drawings and calculations to enable the construction of the electrical
scope within the wind farm.
We have made an allowance in our offer for electrical studies to demonstrate the adequacy
of the equipment within our scope of supply. The studies for which we have made an
allowance are as follows:
Fault level
Hardware selection, taking into account equipment thermal rating
Protection discrimination
Earthing and lightning protection
P28
The scope of work within the Electrical Contractors package is limited and will have little or
no effect on Grid Code compliance. We can therefore not accept full responsibility for this
item. In view of the Turbine Contractor’s responsibilities in this area, we have made no
allowance for completion or submission of a User Data Library, although we would be
happy to provide costs for carrying out this function. Similarly, we have made no allowance
for the following studies:
For clarity, and to avoid doubt, we have specifically excluded the following items from our
tender. Where reference is made to the exclusion of supply and installation of a specific
item, then the testing and commissioning of that item is also considered to be excluded.
We would also point out that our costs include for the submission of one set of drawings for
comments. Any comments or revisions would be incorporated and the drawings issued for
construction. Should any drawing require to be re-issued as a result of late or inconsistent
comments received, additional changes may be implemented.
ITEM PRICE £
Design, Supply, installation and Testing, of all the lightning protection ground
9 systems as required for the WTGs Tween Bridge Substation and any
Met Masts Included in 7
Design, Supply, installation and Testing, of all small power and lighting
10 systems within the Tween Bridge Substation Fit out £117,126.00