Вы находитесь на странице: 1из 2

Table of Content for Project Report

Project : IDEO Wutthakat (S11)


Date: 09/08/14

ITEM DISCUSSION INFO. NOTE

1. Project Introduction ANANDA
1.1. General information
1.1.1. Concept Idea, layout , customer group, room type,
no. of room, Area


1.1.2. Designer &
contractor
Main contractor, MEP contractor,
structural designer, architectural
designer, interior designer, landscape
designer


1.1.3. Cost & Budget Construction cost, design fee, special
consultant fee


1.1.4. Precast concrete No. of precast member
1.2. Project development Conventional to Precast concrete, why &
how?


1.3. Site Environment Nearby location, canal, temple,
infrastructure, Road


1.4. Construction schedule Start, finish, master plan
2. Structural Design BE1TECH Design report
2.1. Structural system
2.1.1. Gravity system Foundation, column, wall, slab
2.1.2. Lateral system Shear wall Lift core, stair core etc.
2.1.3. Structural response 1
st
, 2
nd
, 3
rd
Mode
2.1.4. Loading criteria Seismic, Wind, Live load, Superimposed,
Partition


3. Architectural Design PLAN/ANANDA Design report
3.1. Design consideration
3.2. Room type Type 1, 2, 3
3.3. Parking Layout
4. Material HELIX/GEL
4.1. Concrete Strength, age, slump, slab, wall, post-
tension slab, transfer floor, foundation


4.2. Reinforcement Steel reinforcement, strength
4.3. Grouting
4.4. Mechanical splice
4.5. Cement padding
4.6. Post-install system
4.7. Sealant
4.8. Water proofing
5. Precast Production GEL
5.1. About GEL GEL company
5.2. Plant layout Stock yard, construction, curing etc.
5.3. Production line
5.4. Production capacity
5.5. Quality control
5.6. Product tolerance
5.7. Mock up
5.8. Transportation
6. Erection HELIX
6.1. Planning Erection planning, team set-up, floor
sequence


6.2. Quality control Pre-erection/post-erection
6.3. Erection tolerance
6.4. Erection time Wall, slab, shear wall, faade
6.5. Machine & equipment Which machine, How
6.6. Labour Team member
6.7. Yarding & storage
6.8. Site traffic
7. Precast Connection HELIX
7.1. Type
7.2. Installation method
7.3. Installation time
8. MEP System MINERVA
8.1. Electrical
8.2. Sanitary
8.3. Mechanical
8.4. Ventilation & Aircondition
8.5. OTTV RTTV
9. Safety HELIX
9.1. Safety plan & protocol
9.2. Equipment Crane, Rigging
9.3. Fall protection
10. Drafting MINERVA/HELIX/
GEL

10.1. Shop drawing
10.2. Production drawing
10.3. Erection drawing
11. Project evaluation MINERVA/ANANDA
11.1. Conventional VS Precast Cost, time, quality
11.2. Structural point of view
11.3. Architectural point of view
12. Problem & solution Problem and solution in construction MINERVA
12.1. Structural
12.2. Architectural
12.3. MEP
13. Observation and
Recommendation
How can we improve the product?
Design, Construction, Cost, Time
THANIT

13.1. Topic 1
13.2. Topic 2
13.3. Topic 3

Вам также может понравиться