Sub: Safety Precautions at work-site in proximity to running track.
Several incidents have occurred wherein contractors lorry while working very close to the Railway line have infringed the moving dimensions resulting into train accidents. Some accidents also took place due to infringement left at work-site after closure of the work such as repair in tunnels, Complete Track Renewals etc. Instructions have been issued vide Railway Boards letter No. 98/CE- II/PRA/63/CRS Dated 19.11.98 (Annexure-I), 98/CE/CT/15 Dated 13.08.98 (Annexure-II), 99/CE-II/PRA/32 Dated 20.04.2000 (Annexure-III), 2000/CE-II/PRA/12 Dated 16.05.2002 (Annexure-IV) and CE/SERs Circular No.214 (Annexure-V) to take adequate precautions so as to ensure that the Road vehicles do not come very close to the Railway line and all works are executed under proper safety cover.
Following instructions are issued in this regard:-
1. All permissible or sanctioned infringements should be consolidated for each Division, Section wise. The consolidated list should be in possession of DRM, ADRM, Sr.DSO or DSO, Construction officers in-charge of the Division and relevant extract with each Divisional and other officers. These should be checked once a year at Assistant officers level and it should be ensured that there is no aggravation of any permitted infringement. 2. All works planned for execution close to the running lines and fixed structures, on bridges, inside tunnels, cutting, constricted area etc. should be carried out only after preparation of detailed plans for the same and getting clearance from Engineering Department of open line and approval of competent authority to ensure that the execution of the work will not in any way infringe the prescribed schedule of dimension or aggravate existing permissible infringement. 3. Special Training and Counselling should be imparted to all Field staff engaged in maintenance of railway assets regarding the Safety at work site and all of them should be in possession of a Compendium prepared in the same format as Engineering Standing order No.16 (Annexure-VI) issued by the Railway Board in August,1999. 4. Similar training should be organised for railways Associates and Contractors working in close proximity of the running track as directed by the Railway Board in their letter No.99/CE-II/PRA/32 of 20.04.2000. 5. All the works inside a tunnel, deep cutting, on bridges, constricted area etc. should be carried out in accordance to the provision on Chapter VIII of IRPWM (Annexure-VII) and Para 1009 of Bridge Manual 1998 (Annexure-VIII) and preferably under block protection. 6. Work should not be allowed to progress without prior approval of the Engineer-in-charge in case of movement of vehicle close to track is involved. Area of work and the area where track are allowed to ply, should be demarcated on the Plan and get the same acknowledged by the Contractor. 7. Machines and vehicles should ply 6m clear of the track. In case movement at less than 6m up to maximum 3.5m clear of the track is inescapable, it should be permitted in presence of Railway Representative, not below the rank of works Mistry/P.Way Mistry authorised by the Engineer-in- charge who will be posted with hand signal flag to ensure that lorries do not infringe the Standard Dimensions at any time and to protect the track in case of any emergency. 8. The area of work should be demarcated by providing loarricades and Sign Boards, which will enable the work-men posted at site and also the lorry drives to have clear guide lines of the movement on vehicles. 9. Movements of lorries near the track should be prohibited during night. In case it is unavoidable, adequate protective measures including lighting must be ensured. 10. In one block section, lorries should be permitted to work at not more than two locations at a time. 11. Where tunings of lorries are found necessary in course of work, locations for reversing for the purpose of turning should be nominated and should be selected in such a way that there is no dangers to the running train. At such locations, a Railway official not below the rank of Works Mistry/P-Way Mistry should be available wih Hand Signal Flaf to ensure that the lorries do not infringe the Standard Dimension for the running lines. Sufficiently strong stoppers or rail barricades should be installed at such locations wherever required to ensure that even by carelessness or oversight the lorries do not infringe the fixed dimensions. Wherever lorries have to take turn, the reversing should be done in such a way the driver invariably faces the running lines at all time. 12. Driver of the train must be served with caution order to lookout for any obstruction at the place of work and be prepared to apply brakes if any danger is apprehended. 13. Arrangement should be made to protect the track in case of emergency at work site. 14. Engineering Supervisors and Contractors representative should ensure the clearance of total infringements before they leave the work site.
Wherever there is a likelihood of Contractors road vehicle plying on the railway land next to running line or yard, certain clauses attached herewith, as (Annexure-IX) should be incorporated in the Special Conditions of Contract.
Encl:
1. Annexure-I: Railway Boards letter No.98/CE-II/PRA/63/CRS Dated 19.11.98. 2. Annexure-II: Railway Boards letter No.98/CE/CT/15 Dated 13.08.98 3. Annexure-III: Railway Boards letter No.99/CE-II/PRA/32 Dated 20.04.2000 4. Annexure-IV: Railway Boards letter No.2000/CE-II/PRA/12 Dated 16.05.2002 5. Annexure-V : Chief Engineer/S.E.Railways Circular No.214. 6. Annexure-VI: Rly. Boards Engineering Standing Order No.16 7. Annexure-VII: Chapter VIII of IRPWM 8. Annexure-VIII: Para 1009 of Bridge Manual 1998. 9. Annexure-IX: Special Conditions of Contract.